Upload
kaylin-lamison
View
216
Download
1
Tags:
Embed Size (px)
Citation preview
Alaska LNG ProjectConcept Information
Work Product In Progress
Alaska LNG Project
Overview
Kenai, Alaska
January 30, 2014
Alaska LNG ProjectConcept Information
Work Product In Progress
Alaska LNG Project - Overview
Alaska LNG PlantConceptual Layout
• BP, ConocoPhillips, ExxonMobil and TransCanada are working together to progress an Alaska LNG project:- 300+ people involved in project design work - Current work - $70M+ spent to date- Multiple third party contractors engaged – many Alaskan- Leveraging Denali, APP, related material ($700M past work)- Preliminary capital estimate - $45-65 Billion (2011 dollars)
• Key project design accomplishments to date:- Integrated Basis of Design heat/material balance complete- Confirmed ability to integrate into existing operations- Completed project design, announced concept Feb13- Finalized lead LNG plant site decision, announced Oct13
• Completed 2013 Summer Field Season: - Cultural resource assessment (>6,500 acres)- Hydrology / Lakes / Fisheries studied (37 / 17 / 20) - Traditional knowledge, subsistence, ethnographic surveys- 150 people involved
• Key project issues to address: - “Mega-project” challenges (labor, resources, equipment, etc.)- Uncertainty related to permit timing / scope- Commercial and fiscal issues with all parties, including the
State of Alaska
Results of URS ArcGIS Location SuitabilityScreening Study
- 2 -
Lead LNG Plant Site Selection- Extensive Analysis of SouthCentral coast- 20+ options analyzed; 4-5 sites feasible - Geotechnical, construction, operation issues
Lead LNG Plant SiteNikiski Industrial Area
Alaska LNG ProjectConcept Information
Work Product In Progress3
Alaska LNG Concept Summary - Upstream
PTU (62 miles east of PBU/GTP area) •Initial Production System (IPS) project in progress - 2016 SU•Preliminary AK LNG design basis for PTU:– Leverage IPS facilities, add fourteen new wells – Add new gas facilities to existing central pad / facilities – New 30” gas line from PTU to GTP in Prudhoe Bay – Peak workforce – 500-1,500 people
PBU Tie-in (adjacent to proposed GTP location)•Installation / tie-in managed by Prudhoe Bay Operator– Tie into existing CGF, deliver gas to new Gas Treatment Plant– Gas project / deliveries tied to future PBU operations
•Preliminary plan is to inject CO2 using existing injection systems as appropriate
PTU Field Layout
Process
Utilities
PowerGeneration
Diesel Storage
Livi
ng
Qua
rter
s
Mai
nten
ance
WarehouseCold Storage
Drill Rig
Point ThomsonCentral Pad
Compression
PBU Central Gas Facility Tie-in
Alaska LNG ProjectConcept Information
Work Product In Progress
Alaska LNGPipeline Elevation Design Example
Potential Pipeline Routes
Alaska LNG Concept Summary - Pipeline
Gas Pipeline and Compression Stations•800+ mile 42” x80 pipeline•3-3.5 billion cubic feet gas per day •Eight compressor stations (30kHP each)•Pipeline contents will be treated gas, impurities removed at NS GTP•Designed to manage continuous and discontinuous permafrost regions•Expansion potential with additional compression if appropriate•Refining route based on summer field information, continued design work•Five off-take points for Alaska gas delivery•Peak workforce – 3,500 - 5,000 people
Alaska LNG ProjectConcept Information
Work Product In Progress5
Alaska LNG - Concept Summary – GTP / LNG Plants
NS Gas Treatment Plant•Defined PBU integration for gas inlet, discharge•Designed to remove gas impurities•Four amine trains with compression, dehydration and chilling•Prime power generation (5 units, 54kHP)•All required utilities, infrastructure and camps•Facility will be modularized, sealifted to location•Peak workforce – 500-2,000 people
LNG Plant, Storage and Marine Facility•Three 5.8 million tons per annum (MTA) LNG trains (17-18MTA)
- Plant receives 2.2 - 2.5 billion cubic feet per day to liquefy- LNG production varies with ambient temp (4.9 - 6.3 MTA)- Small volume of stabilized condensate (~1,000 bbl/day)
•Integrated utility system with all utilities on site•Three 160,000 cubic meter LNG storage tanks•Conventional jetty with two berths (15-20 LNG Carriers)•Peak workforce – 3,500 – 5,000 people for LNG plant•Peak workforce – 1,000 – 1,500 people for marine facility•Evaluating modularization to manage risks
NS Gas Treatment Plant
LNG Plant and Storage
Alaska LNG ProjectConcept Information
Work Product In Progress
Recent Progress
6
Prudhoe Bay
•Data capture/analysis of PBU gas composition
•Evaluated field dehydration performance and
depletion planning
•Developing integrated injection system
•Evaluating integrated power grid
Point Thomson
•Comparing plot plan options for safety/operability
•Evaluated process design requirements
•Developing design basis for engineering work
Gas Treatment Plant
•Confirmed viability of 3 train design, aligns gas
treatment plan with LNG plant
•Finalized CO2 design / handling basis
•Working to modularize plant design and
evaluating sealift plans
Pipeline
•Refined route from PBU to Livengood, finalizing
preliminary route from Livengood to Cook Inlet
•Working ‘special design areas’
- Atigun Pass - Denali National Park Area
- Yukon River - Cook Inlet
-Progressing fundamental technical work on
geohazard analysis, waterway crossings,
hydraulics and design
LNG Plant and Marine
•Lead site selected
•Completed plans for metocean data gathering
•Ambient air monitoring stations / plan finalized
•Progressing work on LNG capacity and
technology
Alaska LNG ProjectConcept Information
Work Product In Progress
Recent Progress – Environmental, Regulatory and Land
Cultural ResourceSurvey Areas
Environmental, Regulatory and Land
•Safe summer field season 2013
– No incidents for >40,000 man-hours, 90,000 miles– No reportable spills or public complaints
•Peak workforce of over 130 contractor staff completed
survey work from PBU to Livengood
– Over 6,500 acres surveyed for cultural resources
– Over 75 hydrology, lakes and fisheries surveyed
– Traditional knowledge and ethnographic surveys