12
AISC 2005 SEISMIC PROVISIONS: DESIGN DRAWING REQUIREMENTS 2008 NASCC –Nashville, TN Authors: Larry A. Kloiber, PE Lawrence A. Kloiber PE has been involved in designing, fabricating and erecting structural steel for almost 40 years, first as an AISC Engineer and then with LeJeune Steel Co. Larry is a graduate of Marquette University with a BCE and the author of numerous papers on steel design and fabrication. He is a member of the AISC Specification Committee and the AWS D1.1 Code Committee. AISC in Sept 2002 presented Larry with a Lifetime Achievement Award in “Special recognition for many years of service to the structural design, construction, and academic communities”. In 2004 he received the TR Higgins Lectureship Award for the best paper on structural steel design from the AISC for his paper “The Design of Orthogonal and Skewed Connections.” Larry S. Muir, PE Larry S. Muir, PE has been employed by Cives Steel Company for over 12 years, currently as chief engineer of Cives Steel Company and president of Cives Engineering Corporation. He is a member of the AISC Specification Committee and the AWS D1.1 Subcommittee on Design. Mr. Muir holds Bachelor’s degrees from both the Southern College of Technology and the University of Tennessee, Knoxville. He also holds a Master’s degree from the University of Tennessee. Mr. Muir has been responsible for connection design for a number of projects with seismic requirements. He has authored or co-authored numerous technical papers and is currently working on an AISC Design Guide for Vertical Bracing Connections with Dr. William A. Thornton. ABSTRACT The 2005 Seismic Provisions for Structural Steel Buildings require the structural design drawings to “show the work to be preformed” and presents a list of items required for the seismic load resisting system. The use of the list requires a knowledge of the connection requirements in the Provisions for the various seismic load resisting systems along with the requirements in Appendix Q – Quality Assurance and Appendix W – Welding Provisions. Other requirements for the seismic load resisting system connections are found in ANSI /AWS D1.8 and ANSI / AISC FEMA 358-05. This paper will review these design drawing requirements and point out where they can found in these documents. AISC 2005 SEISMIC PROVISIONS: DESIGN DRAWING REQUIREMENTS The experiences of the 1994 Northridge and the 1995 Kobe earthquake have expanded our knowledge regarding the seismic response of steel building structures. This has resulted in new, complex and unique design and fabrication requirements per the 2005 AISC Seismic Design Provisions (Provisions). The adoption of SEI/ASCE 7 (ASCE 2005) by the governing codes has expanded the range of buildings that now must be designed using these Provisions. The increased number of structures that must be designed and built with a seismic response modification factor (R-factor) greater than 3 coupled with trend for structural design firms to practice nationally

AISC 2005 SEISMIC PROVISIONS: DESIGN DRAWING REQUIREMENTS · 2019. 4. 4. · by AWS D1.8-2005, Structural Welding Code – Seismic Supplement which has subsequently been published

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

  • AISC 2005 SEISMIC PROVISIONS: DESIGN DRAWING REQUIREMENTS

    2008 NASCC –Nashville, TN

    Authors:

    Larry A. Kloiber, PE Lawrence A. Kloiber PE has been involved in designing, fabricating and erecting structural steel for almost 40 years, first as an AISC Engineer and then with LeJeune Steel Co. Larry is a graduate of Marquette University with a BCE and the author of numerous papers on steel design and fabrication. He is a member of the AISC Specification Committee and the AWS D1.1 Code Committee. AISC in Sept 2002 presented Larry with a Lifetime Achievement Award in “Special recognition for many years of service to the structural design, construction, and academic communities”. In 2004 he received the TR Higgins Lectureship Award for the best paper on structural steel design from the AISC for his paper “The Design of Orthogonal and Skewed Connections.”

    Larry S. Muir, PE

    Larry S. Muir, PE has been employed by Cives Steel Company for over 12 years, currently as chief engineer of Cives Steel Company and president of Cives Engineering Corporation. He is a member of the AISC Specification Committee and the AWS D1.1 Subcommittee on Design. Mr. Muir holds Bachelor’s degrees from both the Southern College of Technology and the University of Tennessee, Knoxville. He also holds a Master’s degree from the University of Tennessee. Mr. Muir has been responsible for connection design for a number of projects with seismic requirements. He has authored or co-authored numerous technical papers and is currently working on an AISC Design Guide for Vertical Bracing Connections with Dr. William A. Thornton.

    ABSTRACT The 2005 Seismic Provisions for Structural Steel Buildings require the structural design drawings to “show the work to be preformed” and presents a list of items required for the seismic load resisting system. The use of the list requires a knowledge of the connection requirements in the Provisions for the various seismic load resisting systems along with the requirements in Appendix Q – Quality Assurance and Appendix W – Welding Provisions. Other requirements for the seismic load resisting system connections are found in ANSI /AWS D1.8 and ANSI / AISC FEMA 358-05. This paper will review these design drawing requirements and point out where they can found in these documents.

    AISC 2005 SEISMIC PROVISIONS: DESIGN DRAWING REQUIREMENTS

    The experiences of the 1994 Northridge and the 1995 Kobe earthquake have expanded our knowledge regarding the seismic response of steel building structures. This has resulted in new, complex and unique design and fabrication requirements per the 2005 AISC Seismic Design Provisions (Provisions). The adoption of SEI/ASCE 7 (ASCE 2005) by the governing codes has expanded the range of buildings that now must be designed using these Provisions. The increased number of structures that must be designed and built with a seismic response modification factor (R-factor) greater than 3 coupled with trend for structural design firms to practice nationally

  • rather than regionally means that there may be firms designing these buildings that are not be familiar with some of the special requirements of the Provisions. This paper will attempt to point out the design information that is required to ensure that fabricators and erectors can accurately bid, fabricate and erect these structures.

    There is a fundamental difference in design concept between a typical non-seismic building design (including ones with an R ≤ 3) and a design for R>3 using the Provisions. A non-seismic building under full design loads may experience some local inelastic response but typically members and connections will not experience significant yielding. If however a building designed for R>3 experiences a full design seismic event it is likely that most of the seismic load resisting system (SLRS) will experience substantial yielding possibly over several cycles. Therefore it is important that all of the requirements for materials, bracing and connection details be as specified to enable this systems to perform as designed. To ensure this happens the Provisions require the structural design drawings and specifications show the work to be preformed. Unlike non-seismic building structures where it is possible to provide member sizes and loads along with general connection requirements and have the detailer complete the design as outlined in the Code of Standard Practice Section 3.1.2 the Provisions require the design drawings show the connection configuration along with connection material and sizes.

    The Provisions provide an outline of some of the key information required on the design documents as well as detailed requirements for the various types of SLRS. The Commentary to the Provisions provides excellent background information and a rationale for the requirements along with some guidance on connection details. Appendix W of the Provision covers welding requirements, however it was intended that this would be superseded by AWS D1.8-2005, Structural Welding Code – Seismic Supplement which has subsequently been published. In addition the AISC Seismic Design Manual has general design information along with information on various pre-qualified SLRS along with sketches of connection details and a discussion of items such as demand critical welds and protected zones. Finally there is ANSI/AISC 358-05 Prequalified Connections for Special and Intermediate Moment Frames for Seismic Applications. This is available in electronic format either as a download from AISC or as a CD-ROM. This publication contains essential information for designing and detailing SLRS moment frames and the required connection details. STRUCTURAL DESIGN DRAWING AND SPECIFICATION REQUIREMENTS The Provisions Section 5.1 as mentioned above provides an outline of the key information that must be shown on the structural design drawings and requirements. These are as follows:

    1. Designation of the seismic load resisting system (SLRS) 2. Designation of the members and connections that are part of the SLRS 3. Configuration of the connections 4. Connection material specifications and sizes 5. Locations of demand critical welds 6. Lowest anticipated service temperature (LAST) of the steel structure, if the structure is not enclosed and

    maintained at a temperature of 50 °F (10 °C) or higher 7. Locations and dimensions of protected zones 8. Locations where gusset plates are to be detailed to accommodate inelastic rotation 9. Welding requirements as specified in Appendix W, Section W2.1.

    The User Note to this list goes on to state the following:

    User Note: These Provisions should be consistent with the Code of Standard Practice, as designated in Section A4 of the Specification. There may be specific connections and applications for which details are not specifically addressed by the Provisions. If such a condition exists, the contract documents should include appropriate requirements for those applications. These may include nondestructive testing requirements beyond those in Appendix Q, bolt hole fabrication requirements beyond those permitted by the Specification, bolting requirements other than those in the Research Council on Structural Connections (RCSC) Specification for Structural Joints Using ASTM A325 or A490 Bolts, or welding requirements other than those in Appendix W. The other items would include bracing requirements SLRS moment frames and gravity column splice details. Designation of the Seismic Load Resistant System (SLRS)

    It is imperative that the engineer define both for himself and for the fabricator the extents of the SLRS. It must be noted that this task may not be as easy as it first appears. The seismic load resisting system does not consist only of

  • the members within the bounds of the systems designated in Chapters 9 through 17 of the Provisions (SMF, IMF, OMF, SCBF, etc.), but instead also extends to members that deliver the seismic loads to the frames. This becomes especially confusing since the IBC Table 1617.6.2 is titled, “Design Coefficients and Factors for Basic Seismic-Force-Resisting Systems”, which at least would imply that the Seismic Force Resisting System is limited to those members contained within the Framing Systems listed in the table. The Provisions however define the seismic load resisting system as the “assembly of structural elements in the building that resists seismic loads, including struts, collectors, chords, diaphragms and trusses.” Modern analysis methods can further complicate the task of defining the SLRS for a particular structure. If an entire structure is modeled three-dimensionally in the computer and then subjected to a static, dynamic or pseudo-dynamic seismic loading than potentially every member in the structure will resist some of the seismic load. Does this mean that every member in the structure is part of the SLRS and must meet the requirements of the Provisions? Such a broad interpretation is rare, but not unheard of. In order to facilitate the discussion a new term Primary Seismic Load Resisting System (P-SLRS) will be introduced. The P-SLRS will consist of only those members for which the requirements of Sections 9-17 apply, whereas the SLRS consists of these members plus any other members carrying seismic loads. Designating the P-SLRS in the structural notes where the other seismic design information is given is necessary but often not sufficient. It would instead usually be shown in Item 2 where the individual elements are designated on the plans and elevations. It may be helpful to provide a short verbal description of the total system in the structural notes as a guide for the design team. It is important not to define the SLRS too generally since potentially unnecessary cost increases will be incurred. The Provisions require that “the design of connections for a member that is a part of the SLRS shall be configured such that a ductile limit state in either the connection or the member controls the design.” It should also be noted that this requirement does not limit the type of member or loading condition to which the ductile limit state must apply. A strict interpretation would be that all members or connections designated to be within the SLRS must be governed by a ductile limit state for all loading conditions. This would mean that the shear connection for a gravity beam that happens to be in a line designated as the SLRS must be governed by a ductile limit state. The strictest interpretation would also mean that all connections to a collector element must be governed by a ductile limit state whether that element transfers lateral load or not. It can often be difficult to configure connections such that a ductile limit state is achieved (Muir 2007). If fully detailed connections are to be provided to the fabricator, as the Provisions indicate, this is less of an issue. However, if connection design is to be completed by the fabricator or designated to a third party, not only must the SLRS be clearly defined, but an interpretation of the Provisions must also be agreed to. Designation of the members that are part of the SLRS This allows the entire construction team to locate the critical design elements of the building and helps provide a check to make sure nothing is overlooked or missing. The importance of this can not be overstressed. We have seen buildings where this was not done and key elements of the diaphragm and collector systems and in one case some moment frames were not properly detailed in a timely manner resulting construction delays and charges. We think the SLRS should be shown both in plan and elevation. In plan it is possible to either do a key type plan showing the elements or it can be shown my shading all of the elements on the structural plans. Either way the entire SLRS including drag struts and any diaphragm members should be shown. It is important to also show the SLRS in elevation as is typically done for vertical bracing. It is our recommendation that all member sizes be shown on the elevation rather than showing beams sizes only on the plans as is often done with bracing elevations. This will help when you add the items required in Items 3,4, 5, 7, & 8. Where the SLRS involves other materials such as shear walls these elements should be indicated where the steel connects to them. Configuration of the connections

  • The responsibility for completing connection design can vary from project to project and even more so depending on the geographic location of the structure. Engineers in the Eastern part of the U.S. are often accustomed to relegating connection design to the fabricator. Nearer the West coast connection design is often completed by the Engineer. The Provisions state that the connection configuration must be shown on the structural design drawings. This could be a pretty ambiguous statement, but when read alongside Item 4 below and the Commentary to the Provisions, it becomes difficult to satisfy the Provisions without providing fully detailed connections for the SLRS on the structural design drawings. With this in mind the connections for the prequalified SLRS moment frames and braces have a number of very specific detail requirements for items such as welds, bolts, stiffeners, gusset plates, continuity plates and doubler plates, with which some engineers may not be familiar. For example there are dimensions given for detail corner clips on continuity plates to prevent welding in the “k” zone of the column web as shown in commentary Figure C-I-7.2 below.

    When configuring a connection it is important that a force be resisted by a single type of connection in other words either entirely by bolts or by welds to ensure its performance under full load. The commentary to Provisions gives examples of this as shown below.

  • Beam to column moment connections have required dimensions and surface finish requirements for weld access holes as shown in the recommend access hole below.

  • All of this information along with the location and work points should be shown. We will give more examples when we review the specific details for the various types of SLRS. Connection material specifications and sizes The Provisions in Section 6.1 and ANSI/AISC 358-05 in the material sections of the various prequalified SLRS discuss the material requirements. The Provisions references Section A3.1a of the 2005 AISC Specification for Structural Steel Buildings (Specification) for material that can be used in SLRS. Wide flange shapes should preferably be ASTM A992 since this specification was developed specifically for SLRS members. A992 has specified maximum yield to tensile ratio to ensure ductility along with a limit on the carbon equivalent to ensure weldablity.

  • Material requirements for the connection elements must be consistent with the prequalified details in ANSI/AISC 358-05. This includes the material specification along with the size and thickness of each element along with bolts and welds. Bolt material grade, size, location, and tensioning must be shown. The Provisions Section 7.2 Bolted Joints, addresses bolting requirements. While bolts typically are designed as bearing type connections with standard holes, all bolts are required to be pretensioned and have Class A faying surfaces. In other words the connections are designed as bearing but detailed as if they were slip critical. This means painted members may have to be masked at the connections and galvanized structures will require hand-wire brushing in order to roughen the faying surfaces. There are exceptions for bolted bracing where oversize holes are permitted in one ply provided the connection is designed as slip critical and for end plate moment connections, which do not require a Class A faying surface. Section 7.3 Welded Joints, references Appendix W for welding requirements along with requirements of AWS D1.1 for weld procedure specifications. We will go into this in more detail when we review the new AWS D1.8 material. Basically the Provisions require that all welds in the SLRS be made with a filler metal that can produce welds with a minimum Charpy-V-notch toughness of 20 ft-lbs at 0 ºF either by test or manufacturer’s certification. There are additional requirements for demand critical welds as noted below. Locations of demand critical welds Welds are designated demand critical in the Provisions based on consideration of the inelastic strain demand and the consequence of failure. The location of these demand critical welds is given in Provisions and in ANSI/AISC 358-05 in the section applicable to designated SLRS. These welds shall be made with a filler metal that can produce welds with a minimum Charpy-V-notch toughness of 20 ft-lbs at -20ºF as determined by test of manufacturer’s certification and at 40 ft-lbs at 70ºF as determined by Appendix X or other approved method. The User Note in Section 7.3b lists some typical demand critical welds in SLRS. They are as follows:

    a. Welds of beam flanges to columns b. Welds of single plate shear connections to columns c. Welds of beam webs to columns d. Column splice welds including welds to base plates

    There are a number of other quality control / quality assurance items associated with demand critical welds that are covered in Appendices W and X along with AWS D1.8. Items such as use of backing bars and run off tabs including requirement for trimming and finishing of run off tabs are specifically addressed. Lowest anticipated service temperature (LAST) of the steel structure, if the structure is not enclosed and maintained at a temperature of 50 °F (10 °C) or higher. The majority of building applications are in temperature controlled situations where this will not be a concern. When structures are subjected to temperatures less than 50 °F such as a freezer storage building or an unheated building in a cold climate additional requirements for filler metals are necessary for demand critical welds. Locations and dimensions of protected zones The protected zone is the area immediately around the plastic hinging region. The FEMA/SAC testing has demonstrated the sensitivity of these areas to discontinuities caused by welding, penetrations, changes in section or construction caused notches. The Provisions Section 7.4 has the following requirements for the protected zone:

    (1) Within the protected zone, discontinuities created by fabrication or erection operations, such as tack welds, erection aids, air-arc gouging and thermal cutting shall be repaired as required by the engineer of record.

    (2) Welded shear studs and decking attachments that penetrate the beam flange shall not be placed on beam flanges within the protected zone. Decking arc spot welds as required to secure decking shall be permitted.

    (3) Welded, bolted, screwed or shot-in attachments for perimeter edge angles, exterior facades, partitions, duct work, piping or other construction shall not be placed within the protected zone.

    Exception: Welded shear studs and other connections shall be permitted when designated in the Prequalified Connections for Special and Intermediate Moment Frames for Seismic Applications (ANSI/AISC 358), or as

  • otherwise determined in accordance with a connection prequalification in accordance with Appendix P, or as determined in a program of qualification testing in accordance with Appendix S. The locations and dimensions of these protected zones for moment connections are found in the Provisions and in ANSI / AISC 358 in the applicable type of SLRS. The protected zone for SCBF consists of the middle quarter of the brace and an area near the end connections where buckling is likely to occur. For EBF the link represents the protected zone. The fabrication and erection work and the subsequent work by other trades have the potential to cause discontinuities in the SLRS. When located in the protected zone these discontinuities are required to be repaired by the responsible contractor to the satisfaction of the structural engineer. This highlights the need to clearly show the protected zone on the design drawings and to clearly specify the requirements for construction in this area. Locations where gusset plates are to be detailed to accommodate inelastic rotation When an R greater than 3 is assumed, significant inelastic response is expected during a seismic event. Therefore, unlike a structure designed to behave elastically, the braces in a SCBF, OCBF, or EBF are expected to buckle. It has been observed that the large deformations that occur during out-of-plane buckling of the brace can tend to tear the gusset free from the beam and/or the column. For this reason, the Provisions Section 13.3b require bracing connections to have required flexural strength equal to 1.1 Ry Mp (LRFD). This required strength need not be met in conjunction with the forces calculated to support the brace loads. Instead it should be investigated as an independent load case. Bracing typically however is designed using the exception to 13.3b that allows bracing that can meet the required tensile strength and can accommodate the required inelastic rotations associated with post-buckling rotations need not meet this provision. Tests have shown this can be accomplished where a single gusset plate is used and the brace end is separated by at least two times the thickness of the plate from a line perpendicular to the brace axis about which the plate can bend unrestrained. This typically is a line between the ends of the gusset plate weld to the beam and to the column or column connection. See the figure from the commentary below.

    Commentary to Seismic Provisions – Fig C-I-13.2 Brace-to-gusset plate requirement

    for buckling out-of-plane bracing system Welding requirements as specified in Appendix W, Section W2.1. The general welding requirements are given in AWS D1.1 and additional requirements for the SLRS are invoked in Appendix W and now in AWS D1.8. We have already talked about the basic filler metal requirements and will discuss this in more detail when reviewing Appendix W requirements. AWS D1.1 has always required a written weld procedure specification (WPS) for every structural weld. Prior to Northridge this was often overlooked. Now it is clearly required and the structural engineer or his welding consultant is required to review and approve the WPS. The contract documents should clearly show this.

  • Additional structural drawing detail requirements in the Provisions

    1. SLRS column splice requirements are given in Section 8.4a. The splices need to be located away from beam to column connections. The recommendation is typical to be 4 to 5ft above the beam but in general the splice should be in the middle third of the column. Because of the splice strength requirements in Section 8.3 it is important that the splice be fully detailed on the design drawings. Where bolted splices are used there must be plates or channels on both sides of the web.

    2. Columns that are not part of the SLRS also have additional requirements as spelled out in Section 8.4b. The minimum forces required to be developed in these splice will require a special column splice and this detail should also be shown on the design drawings.

    3. SLRS column bases must meet the requirements of Section 8.5a,b,&c and anchor rod embedment should be per ACI 318 Appendix D. Anchor rod sizes and locations, along with washer requirements, hole sizes and base plate welds must meet these design requirements and must be shown. Where special embedment is used for base fixity the design requirements must be shown. The commentary to this section gives a good discussion along with examples of how to develop these forces. While the Provisions do not cover column bases for columns that are not part of SLRS some consideration should be given to developing a limited amount of base shear either by embedment or by bearing on the anchor rods.

    4. Width / thickness ratios of SLRS members must be less than those that are resistant to local buckling in order achieve the required inelastic deformations required. While the width / thickness ratios given in the Specification Table B4.1 for compact sections are adequate to prevent buckling before the onset of strain hardening, tests have shown that they are not adequate for the required inelastic performance in several SLRS. Provisions Table I-8-1 gives the limiting ratios for seismically compact member. This often governs the selection of round or rectangular diagonal members in seismic braced frames and may control the sizing of strut members also.

    5. Lateral bracing requirements for Special Moment Frame (SMF) columns at beam connections are covered in Section 9.7. If the bracing requirement can not be met by the floor slab and the elements of the moment connection than the required bracing member and connection should be shown.

    6. SMF beams require bracing at both the top and bottom flanges per Section 9.8. While the floor slab typically will brace the top flange additional braces should be shown where required with the necessary connections.

    Appendix W –Welding Provisions and ANSI / AWS Dl.8 Structural Welding Code – Seismic Supplement These two documents list the minimum information that must be shown on the design documents. Appendix W requires the following information as a minimum:

    (1) Locations where backup bars are required to be removed (2) Locations where supplemental fillet welds are required when backing is permitted to remain (3) Locations where fillet welds are used to reinforce groove welds or to improve connection geometry (4) Locations where weld tabs are required to be removed (5) Splice locations where tapered transitions are required (6) The shape of weld access holes, if a special shape is required (7) Joints or groups of joints in which a specific assembly order, welding sequence, welding technique or other

    special precautions are required The D1.8 list includes the items above along with some of the requirements in the Provisions. D1.8 includes a requirement to show any joints that require a specific assembly order, special welding techniques (See ANSI / AISC 358-2005 for Prequalified End Plate Moment Connections) or other special precautions. There is also a requirement to show a Quality Assurance Plan for the project. The steel backing and weld tabs used with complete joint penetration (CJP) welds in fully restrained moment connections must be removed, except the top flange backing attached to the column by a continuous fillet weld at the edge below the CJP weld need not be removed. Tests have shown that by fillet welding this unfused edge of the backing the stress riser is significantly reduced. It is important that the underside of the backing be welded only to the column and not to the underside of the beam flange. The moment connection detail should show this.

  • Where removal of the steel backing is required, the root should be back gouged to sound weld metal and a reinforcing fillet with a minimum leg of 5/16 in. While this is a minimum size weld care should be taken to make sure this reinforcement completely covers the area that was gouged. The toe of the fillet weld leg against the beam should be located on the base metal. Weld tab removal shall extend to within ⅛ in. of the base metal except at continuity plates when it can be ¼ in. Gouges and notches are not permitted and while grinding to a flush condition is not required the contour should provide a smooth transition. AWS D1.8 provides recommended details for these areas. There are a few cases where weld tab removal may impractical or unnecessary so the drawings should make it clear where weld tab removal is required. Appendix A and D 1.8 contain a number of other special requirements that should either be specifically referenced in contract documents. In addition to the filler metal requirements mentioned above, demand critical welds have the following requirements:

    • Manufacturers certificates of conformance for filler metals • Special restrictions on care and exposure of electrodes • Supplemental welder qualification for restricted access welding for bottom flange welding through access

    holes • Special weld sequence for bottom flange welding through access holes • Supplementary requirements for qualification of ultrasonic testing (UT) technicians.

    Appendix Q – Quality Assurance Plan The Quality Assurance Plan (QAP) should be prepared by the engineer of record and made a part of the contract documents. Appendix Q provides the minimum requirements for this plan listing requirements for the Contractor Documents, Quality Assurance Agency Documents, Inspection Points and Frequencies along with special requirements for weld and bolt inspections. Again each of the requirements should be listed or the appropriate sections referenced in the contract documents to make sure both the contractor and the agency responsible for quality assurance are aware of what is required. For example it is important that the fabricator and erector submit for approval a WPS for all welds and that the WPS for a demand critical weld for a bottom flange weld made through a weld access hole list the required materials, the proper technique and the required welder certification. Appendix Q has specific requirements for NDT of welds that must be shown on the contract documents. These include UT testing requirements for CJP welds and base metal over 1½ in. thick connected with CJP welds loaded in tension in the through thickness direction. There are also requirements for magnetic particle (MT) inspection of certain thermally cut surfaces such as weld access holes when the flange exceeds 1½ in. thick and areas where weld tabs have been removed except for continuity plates. Quality assurance requirements for bolting include verifying that faying surfaces meet the specification requirements and that the bolts are properly tensioned per the Research Council on Structural Connections (RCSC) specification. ANSI / AISC 358-05 - Prequalified Connections for Special and Intermediate Moment Frames for Seismic Applications SMF and IMF details that are prequalified to the requirements of the Provisions should be used. This will avoid the time and cost required for the testing required by Appendix S to qualify new designs. ANSI / AISC 358-05 provides general design requirements for prequalified systems along with special details and limits for Reduced Beam Section (RBS) and Bolted End-Plate connection designs. A good summary of this information was presented in the January 2007 issue of Modern Steel Construction. When using any prequalified system it is important to first verify that the members specified meet the section limits specified. This includes both minimum b/t and maximum depth and weight limits if any. Adding moment frames or changing member sizes late in the project to meet these requirements may cause serious cost and delay problems.

  • RBS connections have specific geometry and finish requirements for the thermally cut reduced section. The required geometry should be shown on the contract documents along with the protected area and the finish requirements either directly specified or referenced to ANSI / AISC 358-05, Section 5.7 Fabrication of Flange Cuts. End-plate connections both unstiffened and stiffened have been prequalified for SLRS, though neither are prequalified for SMFs when concrete structural slabs are in direct contact with the steel. The qualified connections requirements are given in great detail in Section 6. For example Table 6.1 Parametric Limits on Prequalification gives limits for each of the key end plate parameters. The end-plate connections should be fully detailed on design drawings and each of the dimensions checked to make sure it complies with Table 6.1. The prequalified end-plate connections have very specific weld details required for the beam flange and web connection to the end plate. The flange weld requirement is given as follows:

    “The beam flange to end-plate joint shall be made using a CJP groove weld without backing. The CJP groove weld shall be made such that the root of the weld is on the beam web side of the flange. The inside face of the flange shall have a 5/16-in. (8-mm) fillet weld. These welds shall be demand critical. Backgouging of the root is not required in the flange directly above and below the beam web for a length equal to 1.5k1. A full-depth PJP groove weld shall be permitted at this location.”

    When detailing this connection on the design drawings a PJP weld depth equal to the beam flange thickness should be shown over the web for the length specified above. On the flange either side of this PJP weld, a standard CJP weld detail with a reinforcing fillet should be shown. The web weld requirements are as follows:

    “The beam web to end-plate joint shall be made using either fillet welds or complete joint penetration (CJP) groove welds. When used, the fillet welds shall be sized to develop the full strength of the beam web in tension from the inside face of the flange to 6 in. (150 mm) beyond the bolt row farthest from the beam flange.”

    Where possible it is recommended that the fillet welds be shown for the web welds. Other Contract Document Requirements The Provisions in addition to all of the design the drawing requirements covered above has in Section 5, Appendix Q and Appendix W various requirements for shop drawings, erection drawings and submittals that the fabricator and erector should provide. The structural engineer should be familiar with these requirements and either specifically or by section reference require these submittals and be prepared to review and approve as required. Summary A review of the Provisions, AWS D1.8 and ANSI / AISC 358-05 shows that when a decision is made to use a R-factor greater than 3 sizing of members is just the first of many steps to meet the design drawing requirements. Often the material weight reduction gained by using a large R-factor is more than offset by the time and cost of providing all of the required details and quality assurance. Each of these documents have an extensive commentary with important background information and helpful sketches of key details. In addition there are other sources such as Lincoln Electric Company’s “FEMA 353 Welding Manual” which explains filler metal requirements and shows samples of various documents that should be submitted. References

    1. AISC (2005), Specification for Structural Steel Buildings, ANSI/AISC 360-05, March 9, American Institute of Steel Construction, Inc., Chicago, IL.

    2. AISC (2005a), AISC/ANSI 341-05, Seismic Provisions for Structural Steel Buildings, American Institute of Steel Construction, Inc., Chicago, IL.

  • 3. AISC (2005b), Prequalified Connections for Special and Intermediate Steel Moment Frames for Seismic Applications,

    4. ANSI/AISC 358-05, American Institute of Steel Construction, Inc., Chicago, IL. 5. ASCE (2005), Minimum Design Loads for Buildings and Other Structures, SEI/ASCE 7-05, American

    Society of Civil Engineers, Reston, VA. 6. AWS (2004), Structural Welding Code Steel, ANSI/AWS D1.1:2004, American Welding Society, Miami,

    FL. 7. AWS (2005), Structural Welding Code – Seismic Supplement, ANSI/AWS D1.8:2005, American Welding

    Society, Miami, FL. 8. Kochalski, Gregory and Jason Ericksen (2007), “Prequalified Seismic Moment Connections” Modern Steel

    Construction. January 2007. American Institute of Steel Construction, Inc., Chicago, IL. 9. Muir, Larry S. (2007), “Designing for Ductile Performance of Bolted Seismic Connections” Engineering

    Journal. 1st Q 2007, American Institute of Steel Construction, Inc., Chicago, IL.

    Welcome ScreenCopyrightForeword2008 NASCC CommitteeTable of Contents3D Software and Complex Hip and Valley Roof SystemsAESS and the New Canadian matrix: A Category ApproachAISC 2005 Seismic Provisions: Design Drawing RequirementsConstructability and TeamworkCool Stuff From EuropeDesign of Lateral Load Resisting Frames Using Steel Joists and Joist GirdersDesigning with DampingDetailing and Fabricating High SeismicFive Useful Stability ConceptsGreen Design: Going Beyond Material IssuesHow Much is Your Business Really Worth and What Factors Affect the Value of Your Business?Impact of Diaphragm Behavior on the Seismic Design of Low-Rise Steel BuildingsImportant Lessons They Didn't Teach Me at College (or at Least I Don't Think They Did)Large-Scale Tests of Steel Plate Shear Walls with PEC ColumnsNondestructive Examination and Special Inspection of Seismic WeldingProcedures and Processes to Manage CNC DataQuality Assurance for Structural Engineering FirmsRecent Developments From Research on Steel Plate Shear WallsThe SJI Composite Steel Joist Catalog First Edition 2007 for Use by the Design ProfessionalThe Upside of InsuranceT.R. Higgins: Buckling-Restrained Braced FramesUsing Cold-Formed Steel Members: Where Do I Begin?

    Author IndexHelpPrintSearchExit