ATUL SHARMA (PMI-ACP, CSP, CSM)
Program Manager, NIIT Technologies
agilenoida.com
Case Study – Distributed Scaled Agile Development Success & Leanings
Project Context
• Product development in Travel & Transport domain
• Multi year development program with over $100 Million development budget
• Team size of 400+ (Development Team)
• Distributed teams in 3 locations (India, U.K)
• Customized Scaled Agile Development Framework
• Implementation completed in multiple countries
agilenoida.com
Teams & Roles
agilenoida.com
• Product Roadmap Planning
• Release/Stage Planning
• High Level Design
• Engage with Teams not Manage
• Product Backlog Grooming
Cross Functional Teams (CFT)
Managers, SMEs, Architects, Business Analysts, Build & Deployment Team
• Product Backlog Grooming
• Supporting Scrum Teams
• Shield from management issues
• Roles aligned to functional domain
• Scrum of Scrum
Core Team
Program Manager, Chief Scrum Master, Proxy PO, QA Manager, Configuration,
Integration
• 1 Scrum Master for two teams
• Development and Testing
• Participate in Sprint Ceremonies
• Participate in Scrum of Scrum (One rep from each team)
• Produce Increment
Scrum Teams
Lean & Scrum
agilenoida.com
Visioning & Product Roadmap
Staffing & Program
Governance
Release & Stage Planning
Product Backlog
Develop & Test
Build & Deploy
Lean Scrum
CFT & Core Team Scrum Teams
User Acceptance
agilenoida.com
KEY SUCCESS FACTORS
Communication & Transparency
Focus on verbal communication
Focus on trust/relationship building with client and teams
Transparency maintained through various communication channels
agilenoida.com
• Team – Sprint Planning, Daily Stand up – Sprint Review and Retrospective –
WebEx/Video Conference – Team Board & JIRA Board
• Core/CFT – Release/Stage Planning – Daily Scrum of Scrum, SOS Board – Story Grooming – Group Retrospective
• Management – Bimonthly Steering Committee
meeting – Monthly Senior Management meeting
Metrics
• Sprint Level – Story Burn-Down – Automated Coding standards check
report (Sonar, Klocworks, Check-style) – Unit Test Coverage and results – Functional Testing report – Build Failure & Deployment issues
report
• Release/Stage Level – Feature Burn-Down – Defect Report (Open/Close) – Cumulative Velocity Bar chart – Quality Compliance Dashboard (Unit
Tests, Sonar, Blackduck, Functional Testing)
agilenoida.com
Automation
• Code compliance – Sonar/Klocwork – Check-style – Blackduck
• Testing – Unit level (Junit) – Functional & Regression (QTP &
Selenium) – Non Functional – LoadRunner,
WebInspect
• Continuous Integration – Jenkins – Automated Build and Deployment – Daily and On Demand build
agilenoida.com
Tools & Standardization
• Reference Story Points • Definition of Ready • Definition of Done • Well defined Acceptance
Criteria • JIRA Agile, Wiki • JIRA integration with SVN for
traceability • Jenkins (CI Platform) • Junit, Sonar, Klocworks,
Checkstyle, Blackduck • QTP, Selenium, WebInspect,
Load runner
agilenoida.com
Inspect & Adapt
Sprint Retrospective
Group Retrospective
Release Retrospective
agilenoida.com
Understand and respect different point of views
Inquiry rather than advocacy
Conversation rather than argument
Set the Stage Gather Data Generate Insights
Decide what to do
Close Retrospective
More Factors …
• T&M Contract with defined quality standards
• Empowered Teams • Customer is part of development • Reword and Recognition at various
platforms • Team Celebrations at various occasions • Team Engagement rather Management • Risk Management through various
communication channels • Service Uplifting culture • Organization maturity on Agile
(Recruitment, Training, Coaching, Agile Tools etc.)
agilenoida.com
agilenoida.com
KEY LEARNING
Key Learning • Backlog readiness
– Difficulty for CFT to consistently provide sufficient volume of stories and design
– CFT size increased and focus on timely backlog readiness
• Rework – More rework than anticipated during initial stages
– Inspect and Adapt approach helped in controlling
– Definition of Ready streamlined (Changing Requirements)
• Dependency Management – Dependency across modules being developed in parallel
caused delays and rework
– Delay and unavailability of external components
– Recognized and given special focus through early detection during story grooming
– Established Dependency management team to manage dependency across teams/vendors
agilenoida.com
agilenoida.com
Thank You.