١
Islamic University of Gaza - Palestine
Introduction to Principles of Production Management
WS 2012/2013
Chapter 14 – Aggregate sales and Operations Planning
Presented by
Dr. Eng. Abed Schokry
Islamic University of Gaza - Palestine
Learning Outcomes
• Explain business planning• Explain sales and operations planning • Identify different aggregate planning strategies &
options for changing demand and/or capacity in aggregate plans
• Develop aggregate plans, calculate associated costs, and evaluate the plan in terms of operations, marketing, finance, and human resources
• Describe differences between aggregate plans for service and manufacturing companies
٢
Islamic University of Gaza - Palestine
The Role of Aggregate Planning
• Integral to part of the business planning process• Supports the strategic plan• Also known as the production plan• Identifies resources required for operations for the next 6-
18 months• Details the aggregate production rate and size of work
force required
Islamic University of Gaza - Palestine
• Sales and Operations Planning
• The Aggregate Operations Plan
• Examples: Chase and Level strategies
Objectives
٣
Islamic University of Gaza - Palestine
Sales and Operations Planning Activities
• Long-range planning– Greater than one year planning horizon– Usually performed in annual increments
• Medium-range planning– Six to eighteen months – Usually with weekly, monthly or quarterly increments
• Short-range planning– One day to less than six months– Usually with weekly or daily increments
Islamic University of Gaza - Palestine
The Role of the Aggregate Plan
٤
Islamic University of Gaza - Palestine
Types of Aggregate Plans
• Level Aggregate Plans– Maintains a constant workforce– Sets capacity to accommodate average demand– Often used for make-to-stock products like
appliances– Disadvantage- builds inventory and/or uses back
orders
Islamic University of Gaza - Palestine
Types of Aggregate Plans
• Chase Aggregate Plans– Produces exactly what is needed each period– Sets labor/equipment capacity to satisfy period
demands– Disadvantage- constantly changing short term
capacity
٥
Islamic University of Gaza - Palestine
Types of Aggregate Plans con’t
• Hybrid Aggregate Plans– Uses a combination of options– Options should be limited to facilitate execution– May use a level workforce with overtime & temps– May allow inventory buildup and some backordering– May use short term sourcing
Islamic University of Gaza - Palestine
Aggregate Planning Options
• Demand-based options– Reactive: uses finished goods inventories and
backorders for fluctuations– Proactive: shifts the demand patterns to minimize
fluctuations e.g. early bird dinner prices at a restaurant
٦
Islamic University of Gaza - Palestine
Aggregate Planning Options
• Capacity-based options– Changes output capacity to meet demand– Uses overtime, under time, subcontracting, hiring, firing, and
part-timers – cost and operational implications
Islamic University of Gaza - Palestine
• Aggregate planning is the development of a long-term output and resource plan in aggregate units of measure.
• These typically define output levels over a planning horizon of 1 to 2 years, focusing on product families or total capacity requirements.
• Aggregate planning later translates into monthly or quarterly production plans, taking into account capacity limitations such as supply availability, equipment, and labor.
Aggregate planning
٧
Islamic University of Gaza - Palestine
• Level 2 planning, or disaggregation, is the process of translating aggregate plans into short-term operational plans that provide the basis for weekly and daily schedules and detailed resource requirements.
• Level 3 focuses on execution, moving work from one workstation to another, assigning people to tasks, setting priorities for jobs, scheduling equipment, and controlling processes.
Aggregate planning (cont.)
Islamic University of Gaza - Palestine
• Aggregate planning is most challenging when demand fluctuates over time.
• Managers have a variety of options in developing aggregate plans in the face of fluctuating demand:
Ø Demand managementØ Production-rate changesØ Workforce changesØ Inventory smoothingØ Facilities, equipment, and transportation
Aggregate planning (cont.)
٨
Islamic University of Gaza - Palestine
• Most service organizations do not require as many levels of intermediate planning (Level 2) as goods-producing firms.
• Level 1 and 2 planning are often combined in service businesses.
• One way to think of disaggregation in services is to go from aggregate planning (Levels 1 and 2) to front line resource (staff) capacity and scheduling decisions (Level 3). Manufacturers use and need an intermediate level of planning (Level 2), where work-in-process and subassemblies reside.
Disaggregating Service Plans
Islamic University of Gaza - Palestine
Dealing with the Problem Complexity through Decomposition
Aggregate Planning
Master Production Scheduling
Materials Requirement Planning
Aggregate UnitDemand
End Item (SKU)Demand
Corporate Strategy
Capacity and Aggregate Production Plans
Stock Keeping Units (SKU)-level Production Plans
Manufacturingand Procurementlead times
Component Production lots and due dates
Part processplans
(Plan. Hor.: 1 year, Time Unit: 1 month)
(Plan. Hor.: a few months, Time Unit: 1 week)
(Plan. Hor.: a few months, Time Unit: 1 week)
Shop floor-level Production Control(Plan. Hor.: a day or a shift, Time Unit: real-time)
٩
Islamic University of Gaza - Palestine
Aggregate Planning Problem
Aggregate Planning
AggregateUnit Demand
AggregateUnit Availability(Current InventoryPosition)
Aggregate Production Plan
Required Production Capacity
Aggr. Unit, Production Reqs Corporate Strategy
Aggregate Production Plan:•Aggregate Production levels•Aggregate Inventory levels•Aggregate Backorder levels
Production Capacity Plan:•Workforce level(s)•Overtime level(s)•Subcontracted Quantities
Islamic University of Gaza - Palestine
Figure 14.1
١٠
Islamic University of Gaza - Palestine
Example Aggregate Planning Variables and Revenue/Cost Implications
Islamic University of Gaza - Palestine
• Meet demand (Sales Forecast)
• Use capacity efficiently• Meet inventory policy• Minimize cost
– Labor– Inventory– Plant & equipment– Subcontract
Aggregate Planning Goals
١١
Islamic University of Gaza - Palestine
Aggregate Scheduling Options - Advantages and disadvantages
Option Advantage Disadvantage SomeComments
Changinginventory levels
Changes inhuman resourcesare gradual, notabruptproductionchanges
Inventoryholding costs;Shortages mayresult in lostsales
Applies mainlyto production,not serviceoperations
Varyingworkforce sizeby hiring orlayoffs
Avoids use ofother alternatives
Hiring, layoff,and trainingcosts
Used where sizeof labor pool islarge
Islamic University of Gaza - Palestine
Option Advantage Disadvantage SomeComments
Varyingproduction ratesthrough overtimeor idle time
Matches seasonalfluctuationswithouthiring/trainingcosts
Overtimepremiums, tiredworkers, may notmeet demand
Allowsflexibility withinthe aggregateplan
Subcontracting Permitsflexibility andsmoothing of thefirm's output
Loss of qualitycontrol; reducedprofits; loss offuture business
Applies mainlyin productionsettings
Advantages and disadvantages (cont.)
١٢
Islamic University of Gaza - Palestine
Option Advantage Disadvantage SomeComments
Using part-timeworkers
Less costly andmore flexiblethan full-timeworkers
Highturnover/trainingcosts; qualitysuffers;schedulingdifficult
Good forunskilled jobs inareas with largetemporary laborpools
Influencingdemand
Tries to useexcess capacity.Discounts drawnew customers.
Uncertainty indemand. Hard tomatch demand tosupply exactly.
Createsmarketing ideas.Overbookingused in somebusinesses.
Advantages and disadvantages (cont.)
Islamic University of Gaza - Palestine
Option Advantage Disadvantage SomeComments
Back orderingduring high-demand periods
May avoidovertime. Keepscapacity constant
Customer mustbe willing towait, butgoodwill is lost.
Many companiesbacklog.
Counterseasonalproducts andservice mixing
Fully utilizesresources; allowsstable workforce.
May requireskills orequipmentoutside a firm'sareas ofexpertise.
Risky findingproducts orservices withopposite demandpatterns.
Advantages and disadvantages (cont.)
١٣
Islamic University of Gaza - Palestine
The Extremes
Level Strategy
Chase Strategy
Production equals sales
forecastProduction rate
is constant
Islamic University of Gaza - Palestine
• Level scheduling strategy– Produce same amount every day– Keep work force level constant – Vary non-work force capacity or demand options– Often results in lowest production costs
• Chase scheduling strategy– Vary the amount of production to match (chase) the sales forecast– This requires changing the workforce (hiring & firing)
• Mixed strategy– Combines 2 or more aggregate scheduling options
Aggregate Planning Strategies
١٤
Islamic University of Gaza - Palestine
Chase Demand Strategies
plan for matching output to customer demand
a production control plan that attempts to match capacity to the varying levels of forecast demand. Chase demand plans require flexible working practices and place varying demands on equipment requirements. Pure chase demand plans are difficult to achieve and are most commonly found in operations where output cannot be stored or where the organization is seeking to eliminate stores of finished goods.
Islamic University of Gaza - Palestine
The Trial & Error Approach to Aggregate Planning
• Forecast the demand for each period• Determine the capacity for regular time, overtime, and
subcontracting, for each period• Determine the labor costs, hiring and firing costs, and inventory
holding costs• Consider company policies which may apply to the workers,
overtime, outsourcing, or to inventory levels• Develop alternative plans, and examine their total costs
١٥
Islamic University of Gaza - Palestine
Materials Requirements Planning (MRP)
• Materials Requirements Planning (MRP) is a forward-looking, demand-based approach for planning the production of manufactured goods and ordering materials and components to minimize unnecessary inventories and reduce costs.
• The output of an MRP system is a schedule for obtaining raw materials and purchased parts, a detailed schedule for manufacturing and controlling inventories, and financial information that drives cash flow, budget, and financial needs.
Disaggregation in Manufacturing
Islamic University of Gaza - Palestine
1. Dependent demand is demand that is directly related to the demand of other Stock Keeping Units (SKUs) and can be calculated without needing to be forecasted. Demand for materials needed to produce finished goods is dependent on the number of finished goods planned.
2. Time phasing: all dependent demand requirements do not need to be ordered at the same time, but rather are time-phased as necessary.
3. Lot sizing is the process of determining the appropriate amount and timing of ordering to reduce costs.
Three Major Concepts of MRP Systems
١٦
Islamic University of Gaza - Palestine
MRP explosion is the process of using the logic of dependent demand to calculate the quantity and timing of orders for all subassemblies and components that go into and support the production of finished goods.
Lot sizing is the process of determining the appropriate amount and timing of ordering to reduce costs.
• There are three common lot sizing methods for MRP:
1. Lot-for-lot (LFL)2. Fixed order quantity (FOQ)3. Periodic order quantity (POQ)4. Economic Order Quantity (EOQ)
Each of these is illustrated in the following examples.
MRP explosion
Islamic University of Gaza - Palestine
Sales and Operations Planning Activities
• Long-range planning– Greater than one year planning horizon– Usually performed in annual increments
• Medium-range planning– Six to eighteen months – Usually with weekly, monthly or quarterly increments
• Short-range planning– One day to less than six months– Usually with weekly or daily increments
١٧
Islamic University of Gaza - Palestine
The Aggregate Operations Plan
• Main purpose: Specify the optimal combination of– production rate (units completed per unit of time)– workforce level (number of workers)– inventory on hand (inventory carried from previous period)
• Product group or broad category (Aggregation)
• This planning is done over an intermediate-range planning period of 3 to18 months
Islamic University of Gaza - Palestine
Balancing Aggregate Demand and Aggregate Production Capacity
0
2000
4000
6000
8000
10000
Jan Feb Mar Apr May Jun
45005500
7000
10000
8000
6000
0
2000
4000
6000
8000
10000
Jan Feb Mar Apr May Jun
4500 4000
90008000
4000
6000
Suppose the figure to the right represents forecast demand in units
Now suppose this lower figure represents the aggregate capacity of the company to meet demand
What we want to do is balance out the production rate, workforce levels, and inventory to make these figures match up
١٨
Islamic University of Gaza - PalestineRequired Inputs to the Production Planning System
Planning for production
External capacity
Competitors’behavior
Raw material availability
Market demand
Economic conditions
Currentphysical capacity
Current workforce
Inventory levels
Activities required for production
External to firm
Internal to firm
Islamic University of Gaza - PalestineAggregate Planning Examples: Unit Demand and Cost Data
Materials $5/unitHolding costs $1/unit per mo.Marginal cost of stockout $1.25/unit per mo.Hiring and training cost $200/workerLayoff costs $250/workerLabor hours required .15 hrs/unitStraight time labor cost $8/hourBeginning inventory 250 unitsProductive hours/worker/day 7.25Paid straight hrs/day 8
Suppose we have the following unit demand and cost information:
Demand/mo Jan Feb Mar Apr May Jun
4500 5500 7000 10000 8000 6000
١٩
Islamic University of Gaza - Palestine
Jan Feb Mar Apr May JunDays/mo 22 19 21 21 22 20Hrs/worker/mo 159.5 137.75 152.25 152.25 159.5 145Units/worker 1063.33 918.33 1015 1015 1063.33 966.67$/worker $1,408 1,216 1,344 1,344 1,408 1,280
Productive hours/worker/day 7.25Paid straight hrs/day 8
Demand/mo Jan Feb Mar Apr MayJun
4500 5500 7000 10000 80006000
Given the demand and cost information below, what are the aggregate hours/worker/month, units/worker, and dollars/worker?
7.25x22
7.25x0.15=48.33 & 84.33x22=1063.3322x8hrsx$8=$140
8
Cut-and-Try Example: Determining Straight Labor Costs and Output
Islamic University of Gaza - PalestineChase Strategy /(Hiring & Firing to meet demand)
JanDays/mo 22Hrs/worker/mo 159.5Units/worker 1,063.33$/worker $1,408
JanDemand 4,500Beg. inv. 250Net req. 4,250Req. workers 3.997HiredFired 3Workforce 4Ending inventory 0
Lets assume our current workforce is 7 workers.
First, calculate net requirements for production, or 4500-250=4250 units
Then, calculate number of workers needed to produce the net requirements, or 4250/1063.33=3.997 or 4 workers
Finally, determine the number of workers to hire/fire. In this case we only need 4 workers, we have 7, so 3 can be fired.
٢٠
Islamic University of Gaza - Palestine
Jan Feb Mar Apr May JunDays/mo 22 19 21 21 22 20Hrs/worker/mo 159.5 137.75 152.25 152.25 159.5 145Units/worker 1,063 918 1,015 1,015 1,063 967$/worker $1,408 1,216 1,344 1,344 1,408 1,280
Jan Feb Mar Apr May JunDemand 4,500 5,500 7,000 10,000 8,000 6,000Beg. inv. 250Net req. 4,250 5,500 7,000 10,000 8,000 6,000Req. workers 3.997 5.989 6.897 9.852 7.524 6.207Hired 2 1 3Fired 3 2 1Workforce 4 6 7 10 8 7Ending inventory 0 0 0 0 0 0
Below are the complete calculations for the remaining months in the six month planning horizon
16-39
Islamic University of Gaza - Palestine
Jan Feb Mar Apr May JunDemand 4,500 5,500 7,000 10,000 8,000 6,000Beg. inv. 250Net req. 4,250 5,500 7,000 10,000 8,000 6,000Req. workers 3.997 5.989 6.897 9.852 7.524 6.207Hired 2 1 3Fired 3 2 1Workforce 4 6 7 10 8 7Ending inventory 0 0 0 0 0 0
Jan Feb Mar Apr May Jun CostsMaterial $21,250.00 $27,500.00 $35,000.00 $50,000.00 $40,000.00 $30,000.00 203,750.00Labor 5,627.59 7,282.76 9,268.97 13,241.38 10,593.10 7,944.83 53,958.62Hiring cost 400.00 200.00 600.00 1,200.00Firing cost 750.00 500.00 250.00 1,500.00
$260,408.62
Below are the complete calculations for the remaining months in the six month planning horizon with the other costs included
٢١
Islamic University of Gaza - PalestineLevel Workforce Strategy (Surplus and Shortage Allowed)
JanDemand 4,500Beg. inv. 250Net req. 4,250Workers 6Production 6,380Ending inventory 2,130Surplus 2,130Shortage
Lets take the same problem as before but this time use the Level Workforce strategy
This time we will seek to use a workforce level of 6 workers
16-41
Islamic University of Gaza - Palestine
Jan Feb Mar Apr May JunDemand 4,500 5,500 7,000 10,000 8,000 6,000Beg. inv. 250 2,130 2,140 1,230 -2,680 -1,300Net req. 4,250 3,370 4,860 8,770 10,680 7,300Workers 6 6 6 6 6 6Production 6,380 5,510 6,090 6,090 6,380 5,800Ending inventory 2,130 2,140 1,230 -2,680 -1,300 -1,500Surplus 2,130 2,140 1,230Shortage 2,680 1,300 1,500
Note, if we recalculate this sheet with 7 workers we would have a surplus
Below are the complete calculations for the remaining months in the six month planning horizon
16-42
٢٢
Islamic University of Gaza - Palestine
Jan Feb Mar Apr May Jun4,500 5,500 7,000 10,000 8,000 6,000
250 2,130 10 -910 -3,910 -1,6204,250 3,370 4,860 8,770 10,680 7,300
6 6 6 6 6 66,380 5,510 6,090 6,090 6,380 5,8002,130 2,140 1,230 -2,680 -1,300 -1,5002,130 2,140 1,230
2,680 1,300 1,500
Jan Feb Mar Apr May Jun$8,448 $7,296 $8,064 $8,064 $8,448 $7,680 $48,000.0031,900 27,550 30,450 30,450 31,900 29,000 181,250.002,130 2,140 1,230 5,500.00
3,350 1,625 1,875 6,850.00
$241,600.00
Below are the complete calculations for the remaining months in the six month planning horizon with the other costs included
Note, total costs under this strategy are less than Chase at $260.408.62
LaborMaterialStorageStockout
Islamic University of Gaza - Palestine
The IDES Sales Forecast for 2003
Unit Sales ForecastFor 2003
Quarter 1 307,200
Quarter 2 379,200
Quarter 3 360,000
Quarter 4 489,600
Total 1,536,000
٢٣
Islamic University of Gaza - Palestine
IDES Manufacturing Example
• IDES Manufacturing wants to compare the annual (year 2003) costs associated with scheduling using the following three (3) options:
• Option 1 – Maintain a constant work force during the entire year (Level).
• Option 2 – Maintain the present work force of 150 and use overtime and sub-contracting as needed (Mixed)
• Option 3 – Hire/layoff (stop) workers as needed to produce the required output (Chase).
Islamic University of Gaza - Palestine
IDES Cost Information
• Inventory Carrying Cost (per quarter) $ 0.50/unit
• Subcontracting cost $ 7/unit• Pay rate – regular time $20/hr• Pay rate – overtime $30/hr• Labor standard per unit 0.2 hrs• Cost to increase production $ 3/unit• Cost to decrease production $ 2/unit• IDES has 0 units in inventory• Each Quarter has 60 working days• At end of 2002, IDES has 150 prod. workers• IDES Policy – Maximum of 72,000 units/qtr produced using overtime
٢٤
Islamic University of Gaza - Palestine
Option 1 – Constant Workforce without overtime or subcontracting
• First, determine the number of workers required to produce the units forecast for 2003.
• Ave. Prod/day = 1,536,000 = 6,400/day240 days
• Then determine how many workers are needed.• Workers needed = 6,400/day = 160
5 units/hr X 8 hrs
Islamic University of Gaza - Palestine
Option 1 Continued:Calculate Inventory Carrying Costs
Qtr Production @ 6400/day
Sales Forecast
Inventory Change
Ending Inventory
1 384,000 307,200 +76,800 76,800
2 384,000 379,200 + 4,800 81,600
3 384,000 360,000 +24,000 105,600
4 384,000 489,600 -105,600 0
Total 1,536,000 1,536,000 264,000
٢٥
Islamic University of Gaza - Palestine
Option 1 Continued: Calculation of Annual Costs
• Inventory carrying cost:264,000 units X $0.50/unit = $ 132,000
• Cost to increase capacity:(384,000-360,000) units X $5/unit = $ 120,000
• Regular time labor cost:1,536,000 units X $4/unit = $6,144,000
• Total Annual Cost for Option 1 = $6,396,000
Islamic University of Gaza - Palestine
Option 2 – Present Workforce (150) using O/T & subcontracting
Qtr SalesForecast
In-house Production
InvChange
EndInv
UnitsReq’d
O/T OutSource
1 307,200 360,000 +52,800 52,800 0 0 0
2 379,200 360,000 -19,200 33,600 0 0 0
3 360,000 360,000 0 33,600 0 0 0
4 489,600 360,000 -33,600 0 96,000 72,000 24,000
Total 1,536,000 1,440,000 0 72,000 24,000
٢٦
Islamic University of Gaza - Palestine
Option 2 Continued: Calculation of Annual Costs
• Inventory Carrying Costs 120,000 units X $.50/unit = $ 60,000
• Regular time labor (150 workers)$4/unit X 1,440,000 units = $5,760,000
• Overtime labor$6/unit X 72,000 units = $ 432,000
• Out-sourcing$7/unit X 24,000 units = $ 168,000
• Total Annual Costs for Option 2 = $6,420,000
Islamic University of Gaza - Palestine
Option 3 – Vary Production (Workforce) to match Sales Forecast
QtrSales
ForecastBeginningCapacity
CapacityChangeNeeded
Cost ofCapacityChange
1 307,200 360,000 -52,800 $105,600
2 379,200 307,200 +72,000 216,000
3 360,000 379,200 -19,200 38,400
4 489,600 360,000 +129,600 388,800
Total 1,536,000 $748,800
٢٧
Islamic University of Gaza - Palestine
Option 3 calculation of Annual Costs (Cont.)
• Regular time labor costs1,536,000 units X $4/unit = $6,144,000
• Capacity Change Costs = $ 748,800• Total Annual Cost - Option 3 = $6,892,800
Islamic University of Gaza - Palestine
Annual Cost Comparison of the Aggregate Scheduling Strategies
Option Annual Cost
1. Level – No use of O/T or Outsourcing
$6,396,000
2. Mixed – Present work force w/ O/T & Outsourcing
$6,420,000
3. Chase – Vary Production (workforce)
$6,892,800
٢٨
Islamic University of Gaza - Palestine
The IDES Sales Forecast for 2003 revised
Unit Sales ForecastFor 2003
Quarter 1 388,000
Quarter 2 440,000
Quarter 3 400,000
Quarter 4 500,000
Total 1,728,000
Islamic University of Gaza - Palestine
IDES Cost Information - Revised
• Inventory Carrying Cost (per quarter) $ 0.75/unit
• Subcontracting cost $ 7.50/unit• Pay rate – regular time $20/hr• Pay rate – overtime $30/hr• Labor standard per unit 0.2 hrs• Cost to increase production $ 1.50/unit• Cost to decrease production $ 1/unit• IDES has 0 units in inventory• Each Quarter has 60 working days• At end of 2000, IDES has 140 prod. workers• IDES Policy – Maximum of 78,000 units/qtr produced using overtime
٢٩
Islamic University of Gaza - Palestine
Capacity Requirements Planning (CRP) is the process of determining the amount of labor and machine resources required to accomplish the tasks of production on a more detailed level, taking into account all component parts and end items in the materials plan.
• This information is provided in a work center load report.
Capacity Requirements Planning (CRP)
Islamic University of Gaza - Palestine
• Basic MRP does not consider capacity limitations (assumes infinite capacity so no rescheduling, etc.), so CRP addresses this issue.
Chapter 13 Resource Management
Capacity Requirements Planning (CRP) (cont.)
٣٠
Islamic University of Gaza - Palestine
Aggregate Planning for Services
• Most services cannot be inventoried• Demand for services is difficult to predict• Capacity is also difficult to predict• Service capacity must be provided at the appropriate
place and time• Labor is usually the most constraining resource for
services
Copyright 2011 John Wiley & Sons, Inc.
14-59
Islamic University of Gaza - Palestine
(End of Chapter 14)