Agenda Aug.2,2001Chaired by Nelson ChesterWelcome & Introduction Weiguo Li 10:00-10:10 CSC Management &Tooling Chunhua Jiang 10:10-10:40Coffee Break 10:40-11:10 Prototype Prod. & Quality Li Zhou 11:10-11:30 Tension and capacitance Zian Zhu 11:30-11:45Production Schedule Lingshu Wang 11:45-12:00Lunch 12:00-2:00Visit Production and Fast Site Lab 14:00 Questions and discussions 16:00 Peking Opera 18:30
CSC Production Readiness ReviewAug.2-3,2001 IHEP Beijing
Agenda(continue) Aug.3,2001Chaired by Nelson ChesterCommittee Meeting 9:30-10:30Coffee Break 10:30-11:00 Finding and Recommendations 11:00-12:00Closing Remark 12:00-12:10Lunch Party 12:10-14:00 Tour to Temple of Heaven 14:00
CSC Production Readiness ReviewAug.2-3,2001 IHEP Beijing
Production readiness Review at IHEP
Review CommitteeCommittee Members:Nelson Chester, FNAL ChairmanJohn Carson, FNALOleg Prokofoe, FNALObservers:Gena Mitselmakher, L2 Leader of CMS/EMUAndrey Korytov,UF, L3 LeaderYuri Ivanov, PNPI RussianUS Consulate at BeijingNational Science Funding Committee of ChinaMinistry of Science and Technology of ChinaAcademy of Science of China
Conclusion
CSC Production at IHEP Beijing
ME1/3ME1/2
IHEP Task:
72 ME1/2 & 72 ME1/3 CSC Assembly &Testing
For CMS Endcap Muon System
CSC Prod. Milestones at IHEP
Oct.2000-Mar.2001, Prod.Clean Lab construction
Mar.29,2001 Critical tooling arrived at IHEP
Apr.1-30,2001 Tooling set up and tuning
Apr.26,2001 ME1/2 Prototype assembly started
May.20,2001 ME1/3 Prototype started in parallel
July 13,2001 ME1/2 Prototype completed
July 26,2001 ME1/3 Prototype completed
Aug.2-3,2001 CSC Production Readiness Review
Sep.1,2001 CSC Mass Production should start
Winding Machine
CSC Production at IHEP Beijing
Wire Tension
and Pitch Machine
CSC Production at IHEP Beijing
CSC Production at IHEP Beijing
Glue Dispenser
Hand Soldering
Table
CSC Production at IHEP Beijing
Conclusion
CSC Production at IHEP Beijing
Training technicians
CSC Production at IHEP Beijing
Anode wire
fixation bar glue
table
Conclusion
CSC Production at IHEP Beijing
Capacitance Measure
set up
CSC Production at IHEP Beijing
Cathode Panel
Clamping Table
CSC Production at IHEP Beijing
Ionized Air
Clean Machine
Final Assem. table
CSC Production at IHEP Beijing
CSC Fast Site at IHEP Beijing
The first ME1/2
Prototype finished
On 13th of July
CMS/CSC Production of IHEP
Cosmic Ray Signal of 1St
ME1/2 PrototypeOn July
13th
CSC Production at IHEP Beijing
ME1/3 Prototype finished
Meter Setup
CSC Production at IHEP Beijing
Celebrate Party
Celebrate Party
CSC Production at IHEP Beijing
IHEP CSC Management
Prod.Team
Fast Site Manag.Tech. SupportProd.Manager
FNAL ManagerCustom OfficeCSC Group Leader
L2,L3 Leaders IHEP Director
Fast Site Team
Production Chart
Prod.Manager & Process Engineer
Parts Proc1pers
Hand Solder
-ing2pers
Final Ass.&Leak.Train.2pers
Panel.Prep.4pers
Wire wind & Solder 2pers
Tension&Pitch Meas.
HV test1pers
Production Manager: SUN HanshengProcess Engineer: WANG LingshuFast Site Manager: ZHOU Li, HE KanglingTechnique Support: ZHU Zian, ZHENG JP Custom Formality: DENG ChunqinFrame Manufacture: WEI Chenglin
Prod. Responsibility Distribution
Production Manager: SUN Hansheng
Responsibility: 1.Manpower management 2.Distribute task 3.Shifts arrangement 4.Quality Control
Prod. Responsibility Distribution
Process Engineer: WANG Lingshu
Responsibility: 1.Traveler and documents updating and translating
2.Engineering Drawing update
3.Prod.Process arrangement
4.Parts distribution
5.Record Discrepancies
Prod. Responsibility Distribution
Technique Support: ZHU Zian, ZHENG JP
Responsibility: Critical tooling maintaness and trouble shooting,Computer Networking
CSC Web page: http://mdc.ihep.ac.cn/cms_ihep/index.htm
Custom Formality: DENG Chunqin
Frame Manufacture: WEI Chenglin
Fast Site Manager: ZHOU Li, HE Kangling
Prod. Responsibility Distribution
1 500SqMComplete New Clean Lab winding 60SqM, Tension meas.60SqM,Final 60SqM,Hand
Sodering 60SqM,Panel prep.80SqM,Storage Room80SqM,Parts procurement Room30SqM
2 Equipped with Air Conditional and Pressured Gas3 Local Tooling: Cathode Gluing Table(2),Working Table(2) Anode Wire Fixation bar Gluing Table(1&3) Hand Soldering table(4), Final Assembly Table(2) 10 sets Panel Brackets for ME1/2 and ME1/3 each
Prod.Lab readiness for Mass Production
5. 6 Critical Tooling Operation Menus in Chinese ready at needed places
6. Travelers translated into Chinese and copies at each process room
Prod. Lab Readiness for Mass Production
7. 130 SqM Fast Site test room and supporting structure ready
8. Production Computers were connected to networking
Man Power for Mass Production1. 5 new hired Technicians were trained during the ME1/2
ME1/3 Prototype production, working on panel clean,gluing,hand soldering
2. Critical Tooling used by trained engineers, like Winding Machine
3. Quality Control by Engineers and Physicists(Only part time working on CSC)
4. Will have Ph.D students join the Tension Meas. And HV training soon
5. Final Assembly by Engineers
Prod.Lab readiness for Mass Production
Prod. Lab Readiness for Mass Production
Quality Control and Tech. Ready
1. ME1/2 and ME1/3 prototype successfully assembled,Tension,Pitch, HV training,leak test meet requirements(low Leak and dark current,no trip for 58&43 Hrs at 4KV)
2. Strict work process according to Travelers
3. Key persons at each step to control quality
4. Good Lab management fits the quality requirements
Other items1. Budget Situation:Expensive test Gas Mixture requires mo
re money(CF4 imported fromUS, Complicated Chamber Packing Wooden Boxes--expensive,Shipping fee by Sea container more expensive than to US(land trans.)
2. Shipping Custom formality : Three Months effort, US Consulate Great Help. More effort needed from FNAL side for doccumentation(take as scientific Gifts)
3. Frame Manufacture: More machine budget and manpower paid from IHEP
4. Fast Site manpower and Instrumentation budget not enough
Prod.Lab readiness for Mass Production
O N D J F M A M J J A S O N D J F M A M J J A S O N D
2 4 4 3 6 6 6 6 6 6 6 6 6 6 6 3 6 6 6 6 6 6 6 6 6 6 6
Prod.Schedule
Chamber Ass.
Fast Site
Ship Unit to CERN
2001 2002 2003
Key points to keep the schedule
1.Material arrives on time
2.Documents well prep.for Custom all the time
3.More training for fast team work
Frame Manufacture-0
Receive the drawings and extrusion material from FNAL
Responsible Engineer Mr.WEI
Drawing translated to Meter System and Chinese
FeiHong company will manufacture Frames
Needed technology tools were discussed and 29 kinds
jigs should be made to keep the quality
In two months the FeiHong company could deliver the
Frame parts to IHEP when Money and Material arrive
Frame Manufacture-1
Frame Manufacture-2ME1/2 Frame Drawing Questions
368384 Tope Big End: 1.4*M5 parts missing, 2.6*Phi0.44,at Prototype, only 4, 3.6*M6, no at prototype frame, 4.6*phi5.2,only 5 at prototype, 5.no consistent drawing with Prototype
368385 Bottom Big End 6*Phi0.44,at Prototype, only 4
368387 Top Small End: 4*Phi8 ,4*M6, no exist at prototype
368382 Top HV Side: 8*M6,4*M6 at Prototype,Phi0.5+-0.3 no at Pro. 1 Full Rad Slot, 2 at Prototype
368467 Anode Side: No consistent with Prototype
368380 Top Anode Side:0.75wide*3.15Lg.Slot No consistent
Summary
• Production Lab is ready
• Technicians trained, another 7 full working persons needed
•Budget may not enough(Gas, Shipping…
• Shipping schedule should be
on time to keep Prod. speed