COE Renovation – Bid Package #1 CP130100 / DWP 14-251 Page 1 of 4 AES (PM) Weekly Progress Report Facilities – Architectural & Engineering Services College of Education Renovation Bid Package No. 1 – Demolition & Asbestos Abatement 921 Campus Drive University of Idaho DPW Project No: 14-251 UI Project No: CP130100 Progress Report No. 005 DATE: October 1, 2014 TIME: 1:30 pm WEATHER: sunny / breezy TEMP: 57°F UI PM: Guy Esser UI CM: Brian Woodruff CONTRACTOR: Wright Brothers Construction The following report is for internal University of Idaho / Architectural & Engineering Services use only and is meant only to monitor project progress for file reference. Field Observation Reports will be generated and filed by the Architect of Record for this project. (Miller-Hull Architects) WORK IN PROGRESS: (Refer Also to Pictures on Following Pages) Site Preparation / KIVA Demolition 1. The KIVA structure has now been demolished to just below grade. The contractor continues to separate re-bar from concrete rubble. Much of the concrete has been removed and work has started on removing some of the general interior wood and drywall waste that was deposited outside. 2. Metal continues to be separated from all materials. The contractor has gained testing and clearance to clean interior ductwork (previously designated as asbestos contaminated waste) and recycle it with the other metal. This will help Wright Brothers accommodate the LEED specifications/goals for waste diversion. 3. The newer interior carpet tile is being donated for re-use in a remodeling project in Boise. Building Demolition / Abatement Floor 1 - No progress on this floor from last week. Floor 2 - No progress on this floor from last week. Floor 3 - No progress on this floor from last week. Floor 4 - Preparation of the containment envelope is nearly complete on Floor 4. The floor is under negative pressure, and the contractor expects to start removing ceiling tiles within the next couple days. Floor 5 - All ductwork and piping has been removed. The ductwork is being cleaned and disposed / recycled as normal building waste. - The contractor expects to start wetting the asbestos fireproofing as early as tonight, with removal starting tomorrow. Cardboard “tell tales” have been installed between the layers of

AES (PM) Weekly Progress Report - University of Idahogatherco/ProgCoord/2014... · 2014. 10. 1. · COE Renovation – Bid Package #1 CP130100 / DWP 14-251 Page 1 of 4 AES (PM) Weekly

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: AES (PM) Weekly Progress Report - University of Idahogatherco/ProgCoord/2014... · 2014. 10. 1. · COE Renovation – Bid Package #1 CP130100 / DWP 14-251 Page 1 of 4 AES (PM) Weekly

COE Renovation – Bid Package #1 CP130100 / DWP 14-251 Page 1 of 4

AES (PM) Weekly Progress Report Facilities – Architectural & Engineering Services

College of Education Renovation

Bid Package No. 1 – Demolition & Asbestos Abatement

921 Campus Drive University of Idaho DPW Project No: 14-251

UI Project No: CP130100 Progress Report No. 005

DATE: October 1, 2014 TIME: 1:30 pm WEATHER: sunny / breezy TEMP: 57°F UI PM: Guy Esser UI CM: Brian Woodruff CONTRACTOR: Wright Brothers Construction

The following report is for internal University of Idaho / Architectural & Engineering Services use only and is meant only to monitor project progress for file reference. Field Observation Reports will be generated and filed by the Architect of Record for this project. (Miller-Hull Architects)

WORK IN PROGRESS: (Refer Also to Pictures on Following Pages) Site Preparation / KIVA Demolition

1. The KIVA structure has now been demolished to just below grade. The contractor continues to separate re-bar from concrete rubble. Much of the concrete has been removed and work has started on removing some of the general interior wood and drywall waste that was deposited outside.

2. Metal continues to be separated from all materials. The contractor has gained testing and clearance to clean interior ductwork (previously designated as asbestos contaminated waste) and recycle it with the other metal. This will help Wright Brothers accommodate the LEED specifications/goals for waste diversion.

3. The newer interior carpet tile is being donated for re-use in a remodeling project in Boise. Building Demolition / Abatement Floor 1

- No progress on this floor from last week. Floor 2

- No progress on this floor from last week. Floor 3

- No progress on this floor from last week. Floor 4

- Preparation of the containment envelope is nearly complete on Floor 4. The floor is under negative pressure, and the contractor expects to start removing ceiling tiles within the next couple days.

Floor 5 - All ductwork and piping has been removed. The ductwork is being cleaned and disposed /

recycled as normal building waste. - The contractor expects to start wetting the asbestos fireproofing as early as tonight, with

removal starting tomorrow. Cardboard “tell tales” have been installed between the layers of

Page 2: AES (PM) Weekly Progress Report - University of Idahogatherco/ProgCoord/2014... · 2014. 10. 1. · COE Renovation – Bid Package #1 CP130100 / DWP 14-251 Page 1 of 4 AES (PM) Weekly

COE Renovation – Bid Package #1 CP130100 / DWP 14-251 Page 2 of 4

Image 005 – A Ductwork and piping removed on Floor 5.

Image 005 – B Ductwork and piping removed on Floor 5.

plastic sheathing to provide work crews with visible indication of any water leaking through the first plastic containment layer.

Reported By: Guy Esser UI Project Manager E-Copy To: COE Renovation Core Committee Facilities / AES Administration Project File

Page 3: AES (PM) Weekly Progress Report - University of Idahogatherco/ProgCoord/2014... · 2014. 10. 1. · COE Renovation – Bid Package #1 CP130100 / DWP 14-251 Page 1 of 4 AES (PM) Weekly

COE Renovation – Bid Package #1 CP130100 / DWP 14-251 Page 3 of 4

Image 005 – C Carpet tiles staged for recycling on Floor 3.

Image 005 – D Containment plastic and cardboard “tell tales” on Floor 5.

Image 005 – E KIVA demolition progress.

Page 4: AES (PM) Weekly Progress Report - University of Idahogatherco/ProgCoord/2014... · 2014. 10. 1. · COE Renovation – Bid Package #1 CP130100 / DWP 14-251 Page 1 of 4 AES (PM) Weekly

COE Renovation – Bid Package #1 CP130100 / DWP 14-251 Page 4 of 4

Image 005 – F KIVA demolition progress.

Image 004 – G Cutting / separating rebar out of KIVA base foundations.

Image 002 – I Abatement complete in KIVA walkways.

Image 004 – H Interior demolition pile removal progress.