1 Sept 9, 2010 AEP Use of the CIM in ERCOT AEP Use of the CIM in ERCOT Jim Jacoby September 9, 2010

AEP Use of the CIM in ERCOT - EPRI

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: AEP Use of the CIM in ERCOT - EPRI

1 Sept 9, 2010

AEP Use of the CIM in ERCOTAEP Use of the CIM in ERCOT

Jim JacobySeptember 9, 2010

Page 2: AEP Use of the CIM in ERCOT - EPRI

2 Sept 9, 2010

Discussion TopicsDiscussion Topics

• AEP Texas Use of the CIM• Benefits for AEP• Future Transmission Expansion• Problems we have encountered

Page 3: AEP Use of the CIM in ERCOT - EPRI

3 Sept 9, 2010

Discussion TopicsDiscussion Topics

• AEP Texas Use of the CIM• Benefits for AEP• Future Transmission Expansion• Problems we have encountered

Page 4: AEP Use of the CIM in ERCOT - EPRI

4 Sept 9, 2010

Current Use of the CIMCurrent Use of the CIM

• External Model Updates• Ability to Quickly Merge in External Models

– Data is current and available– Approximately 4 hour process to Merge Models– Normally Merge models 4-5 times a year.

• CIM Incremental files used for some model changes to ERCOT.

Page 5: AEP Use of the CIM in ERCOT - EPRI

5 Sept 9, 2010

External Model Update ProcessExternal Model Update Process

CIMXML File

CIM Import/exportDB modeler

EMS vendor

Proprietary format

Internal EMS model

Vendor Proprietary

format

Merge application

New merged

EMS model and ICCP

models with AEP

internal model and

ERCOT external model

Page 6: AEP Use of the CIM in ERCOT - EPRI

6 Sept 9, 2010

Discussion TopicsDiscussion Topics

• AEP Texas Use of the CIM• Benefits for AEP• Future Transmission Expansion• Problems we have encountered

Page 7: AEP Use of the CIM in ERCOT - EPRI

7 Sept 9, 2010

Benefits for AEPBenefits for AEP

• Lower Manpower to Update External Models– No need to track external construction as closely.– Getting data from neighboring TO’s a challenge.– Merge process quick and can be completed and online in

a couple of days.• Data is always up to date

– TO’s model data in ERCOT systems– Data is current and available.

• Better Models and Solutions– Better Model for State Estimation and Contingency

analysis.– Real-time data for entire network.– ERCOT and AEP see the same problems.

Page 8: AEP Use of the CIM in ERCOT - EPRI

8 Sept 9, 2010

Discussion TopicsDiscussion Topics

• AEP Texas Use of the CIM• Benefits for AEP• Future Transmission Expansion• Problems we have encountered

Page 9: AEP Use of the CIM in ERCOT - EPRI

9 Sept 9, 2010

Renewables, Renewables, Renewables,RenewablesRenewables,Renewables

Page 10: AEP Use of the CIM in ERCOT - EPRI

10 Sept 9, 2010

ERCOT CREZ ProjectERCOT CREZ Project

Page 11: AEP Use of the CIM in ERCOT - EPRI

11 Sept 9, 2010

AEP Western AreaAEP Western Area

Page 12: AEP Use of the CIM in ERCOT - EPRI

12 Sept 9, 2010

AEP Western AreaAEP Western Area

Page 13: AEP Use of the CIM in ERCOT - EPRI

13 Sept 9, 2010

Discussion TopicsDiscussion Topics

• AEP Texas Use of the CIM• Benefits for AEP• Future Transmission Expansion• Problems we have encountered

Page 14: AEP Use of the CIM in ERCOT - EPRI

14 Sept 9, 2010

ProblemsProblems

• Model Exchange and Model Merge very different functions.

• ERCOT has added many CIM extensions.• We do not see a lot of RTO support across

the country.• Large Learning Curve.• Vendors License fee’s pose problems to

merging in large external models.

Page 15: AEP Use of the CIM in ERCOT - EPRI

15 Sept 9, 2010

ImprovementsImprovements

• More work needs to be done on how the industry will handle model exchange with CIM extensions.

• From an implementation standpoint, the process to move to the CIM for model exchange and incremental updates is not clear. There needs to be better ways to communicate what is involved to synchronize models to allow that to happen.