Advanced Individual Training A.I.T. Barracks Fort Eustis, VA. AE Senior Thesis. Natalie Bockhorst│Construction Management Chimay Anumba , PhD. PE. Presentation Outline Project Overview Analysis #1: SIPS Architectural Breadth Structural Breadth Analysis #2: Comparing Contracts - PowerPoint PPT Presentation
Citation preview
Coppin State University
AE Senior Thesis
Natalie BockhorstConstruction ManagementChimay Anumba, PhD.
PE
Advanced Individual TrainingA.I.T. Barracks Fort Eustis,
VA
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Structural Breadth Analysis #2: Comparing ContractsAnalysis #3:
Schedule AccelerationAnalysis #4: Modularization Final
RecommendationsAcknowledgements
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Advanced Individual TrainingA.I.T. Barracks Fort Eustis,
VA
Advanced Individual TrainingA.I.T. Barracks Fort Eustis,
VA
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Project Overview
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationAnalysis #4: Modularization Final
RecommendationsAcknowledgements
Project Name:Advanced Individual Training Barracks Location:Building #2301, Marshall St. Fort Eustis, VA Building Occupancy Type:Barracks Number of Stories:3Gross Building Area:91,800 S.F.
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Analysis #1 Short Interval Production Schedule: Masonry Faade
Work
Presentation Outline
Project Overview Analysis #1: SIPSProblem Identification
DurationsTypical Sequencing SIPSRecommendationArchitectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationAnalysis #4: Modularization Final
RecommendationsAcknowledgements
Problem Identification:
Unforeseen conditionsMortar time consternate concerning precast elements Limited scaffolding
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Analysis #1 Short Interval Production Schedule: Masonry Faade
Work
Presentation Outline
Project Overview Analysis #1: SIPSProblem Identification
DurationsTypical Sequencing SIPSRecommendationArchitectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationAnalysis #4: Modularization Final
RecommendationsAcknowledgements
Activity Area A (Days)Area B (Days)Area C (Days)Area D (Days) Spray Foam Insulation 1111115Install Brick Veneer 137136Brick Wash 2222Install Precast 6661Total 32223214
Activity Total Duration Unit Unit/Day Spray Foam Insulation 38 Days 36,391sqft960 SF/DayInstall Brick Veneer39 Days173,223 Bricks4500 Bricks/Day or 990 SF/DayInstall Precast 19 Days 297 precast 16 Precast/Day
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Presentation Outline
Project Overview Analysis #1: SIPS Problem Identification
DurationsTypical Sequencing SIPSRecommendationArchitectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationAnalysis #4: Modularization Final
RecommendationsAcknowledgements
Analysis #1 Short Interval Production Schedule: Masonry Faade
Work
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Presentation Outline
Project Overview Analysis #1: SIPSProblem Identification
DurationsTypical Sequencing SIPSRecommendationArchitectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationAnalysis #4: Modularization Final
RecommendationsAcknowledgements
Analysis #1 Short Interval Production Schedule: Masonry Faade
Work
July 201112345678910111213141516171819202122232425262728293031Area A South level 1 West level 1 North level 1 Area B North level 1 Area C North level 1East level 1 South level 1 Area B South level 1 Spray FoamInstall Brick VeneerInstall Precast
August 201112345678910111213141516171819202122232425262728293031Area DEast/ South level 1 West/North level 1 East/South level 2West/Northlevel 2 Spray FoamInstall Brick VeneerInstall Precast
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Presentation Outline
Project Overview Analysis #1: SIPS Problem Identification
DurationsTypical Sequencing SIPSRecommendationArchitectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationAnalysis #4: Modularization Final
RecommendationsAcknowledgements
Analysis #1 Short Interval Production Schedule: Masonry Faade
Work
It is recommended to use a SIPS for the Masonry Faade Work
Cost Reduction: 1. Labor 2. Equipment
Faade Work Schedule DurationsOriginal TargetActualSIPS120 Days194 Days59 Days
Faade Work Schedule Savings Original TargetActualSIPS38%0%70%
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Architectural Breadth
North Elevation
South Elevation
East Elevation
West Elevation
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Original Brick Veneer ElevationsNew Precast Faade
ElevationsComparisonRecommendation Analysis #2: Comparing
ContractsAnalysis #3: Schedule AccelerationAnalysis #4:
Modularization Final RecommendationsAcknowledgements
Original Brick Veneer Elevations
Original Brick Veneer Elevations
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Architectural Breadth
North Elevation
South Elevation
East Elevation
West Elevation
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Original Brick Veneer ElevationsNew Precast Faade
ElevationsComparisonRecommendation Analysis #2: Comparing
ContractsAnalysis #3: Schedule AccelerationAnalysis #4:
Modularization Final RecommendationsAcknowledgements
New Precast Faade Elevations
New Precast Faade Elevations
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Architectural Breadth
North Elevation
South Elevation
North Elevation
South Elevation
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Original Brick Veneer ElevationsNew Precast Faade
ElevationsComparisonRecommendation Analysis #2: Comparing
ContractsAnalysis #3: Schedule AccelerationAnalysis #4:
Modularization Final RecommendationsAcknowledgements
New Precast Faade Elevations
Original Brick Veneer Elevations
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Architectural Breadth
East Elevation
West Elevation
East Elevation
West Elevation
New Precast Faade Elevations
Original Brick Veneer Elevations
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Original Brick Veneer ElevationsNew Precast Faade
ElevationsComparisonRecommendation Analysis #2: Comparing
ContractsAnalysis #3: Schedule AccelerationAnalysis #4:
Modularization Final RecommendationsAcknowledgements
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Architectural Breadth
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Original Brick Veneer ElevationsNew Precast Faade
ElevationsComparisonRecommendation Analysis #2: Comparing
ContractsAnalysis #3: Schedule AccelerationAnalysis #4:
Modularization Final RecommendationsAcknowledgements
It is recommended to use a Precast Concrete Faade
Faade Cost ComparisonOriginal FaadeNew FaadeUnit Masonry $65.00 Cost/SF Precast Panels $ 50.00 Cost/SFPrecast Concrete $10.00 Cost/SF Total $75.00 Cost/SF Total $ 50.00 Cost/SF
Faade Schedule ComparisonOriginal TargetActualSIPSNew Faade120 Days194 Days59 Days48 Days
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Analysis # 2: Comparing Contracts and Evaluating the Risk
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsProblem Identification Design Build
vs. Integrated Project DeliveryRisk Analysis Matrix Recommendations
Analysis #3: Schedule AccelerationAnalysis #4: Modularization Final
RecommendationsAcknowledgements
Problem Identification:
Design Build Contract Approach Industry Issue
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsProblem Identification Design Build
vs. Integrated Project DeliveryRisk Analysis Matrix Recommendations
Analysis #3: Schedule AccelerationAnalysis #4: Modularization Final
RecommendationsAcknowledgements
Analysis # 2: Comparing Contracts and Evaluating the Risk
Fundamental PrinciplesIntegrated Project DeliveryDesign Build Project DeliveryMutual respect and trust Mutual respect and trust Mutual risk and rewardCollaborative innovation and decision making Collaborative innovation and decision making Early goal definition Early involvement of all key participantsIntensified Planning Open and enhanced communication
IPDDBProsConsProsConsCollaborative teamX Target cost/value design Speed X Design choices are typically limited Early decision-making X Shared risk, reward, contingency Consolidated cost risk held with the Design Builder X Decision making process is accelerated Dynamic cost modeling X Larger team Owner staffing requirement is reduced Advanced technical coordination Reduce RFIs COs and total cost
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
When evaluating risk, risk can be defined as the likelihood
(probability) versus consequences. Setting up the acceptable level
of risk in various areas, likelihood of proposed scenarios and
acceptability of their consequences can be illustrated in the form
of a matrix
High Risk Medium Risk Low Risk
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsProblem Identification Design Build
vs. Integrated Project DeliveryRisk Analysis Matrix Recommendations
Analysis #3: Schedule AccelerationAnalysis #4: Modularization Final
RecommendationsAcknowledgements
Analysis # 2: Comparing Contracts and Evaluating the Risk
A141
C195
Risk Analysis Design BuildIntegrated Project DeliveryDescriptionOwner ArchCMSUBOwner ArchCMSUBDelays and Extras InsuranceDispute Resolution Incentive Compensation
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsProblem Identification Design Build
vs. Integrated Project DeliveryRisk Analysis Matrix Recommendations
Analysis #3: Schedule AccelerationAnalysis #4: Modularization Final
RecommendationsAcknowledgements
Analysis # 2: Comparing Contracts and Evaluating the Risk
It is not recommended to use an IPD Approach
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Analysis #3 Schedule Acceleration Techniques
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationProblem Identification Flow ChartsLast
PlannerRecommendations Analysis #4: Modularization Final
RecommendationsAcknowledgements
Problem Identification:
Unforeseen conditions Site work moved to critical path
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationProblem Identification Flow ChartsLast
PlannerRecommendations Analysis #4: Modularization Final
RecommendationsAcknowledgements
Analysis #3 Schedule Acceleration Techniques
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
The process for creating the weekly work plans will be as
followed:
Monday Update the project schedule Tuesday Develop the future
schedule Wednesday Update the schedule if necessaryThursday
Distribute the weekly work plan for the following week to foremen,
so they can prepare for the next weeks work
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationProblem Identification Flow ChartsLast
PlannerRecommendations Analysis #4: Modularization Final
RecommendationsAcknowledgements
Analysis #3 Schedule Acceleration Techniques
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationProblem Identification Flow ChartsLast
PlannerRecommendations Analysis #4: Modularization Final
RecommendationsAcknowledgements
Analysis #3 Schedule Acceleration Techniques
It is recommended to use the Last Planner
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationAnalysis #4: ModularizationProblem Identification
Schedule Impact Areas of Modularization Financial Feasibility
RecommendationsFinal RecommendationsAcknowledgements
Analysis #4: Analyzing the Effects of Modularization
Problem Identification:
Repetitive and standardized buildingReduce schedule
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationAnalysis #4: ModularizationProblem Identification
Schedule Impact Areas of Modularization Financial Feasibility
RecommendationsFinal RecommendationsAcknowledgements
Analysis #4: Analyzing the Effects of Modularization
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Partial First Floor Plan West Wing
Typical Room Enlarged
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationAnalysis #4: ModularizationProblem Identification
Schedule Impact Areas of Modularization Financial Feasibility
RecommendationsFinal RecommendationsAcknowledgements
Analysis #4: Analyzing the Effects of Modularization
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Crane Placement and Working Radius Plan
Benefits Controlled factory environment Cost Savings Modular units
are built on a flat surface Average 50% schedule savings There is
less of a disturbance on siteStandardized design Low waste
Environmentally friendly construction process
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationAnalysis #4: ModularizationProblem Identification
Schedule Impact Areas of Modularization Financial Feasibility
RecommendationsFinal RecommendationsAcknowledgements
Analysis #4: Analyzing the Effects of Modularization
Cost ComparisonOriginal Cost:$18,618,720Modular Construction Cost:$16,756,848
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Analysis #4: Analyzing the Effects of Modularization
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationAnalysis #4: ModularizationProblem Identification
Schedule Impact Areas of Modularization Financial Feasibility
RecommendationsFinal RecommendationsAcknowledgements
It is not recommended to use Modularization
Problems Double WallsContinual Vapor Barrier Installation
Insulation Water InfiltrationRoof Logistics
Cost ComparisonOriginal Cost:$18,618,720Modular Construction Cost:$16,756,848
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Final Recommendations
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationAnalysis #4: ModularizationFinal
RecommendationsAcknowledgements
Analysis #1: SIPSSIPS is Recommended
Analysis #2: Contract Comparison IPD is not Recommended
Analysis #3 Schedule Acceleration The Last Planner is Recommended
Analysis #4 Modularization Modularization is not
Recommended
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Acknowledgements
Presentation Outline
Project Overview Analysis #1: SIPS Architectural Breadth
Analysis #2: Comparing ContractsAnalysis #3: Schedule
AccelerationAnalysis #4: ModularizationFinal
RecommendationsAcknowledgements
Friends and Family AE Faculty Advisor: Dr. Anumba Balfour Beatty
Construction Project Team U.S. Army Corps Project Team PACE
Industry Members
A.I.T. Barracks Fort Eustis, VA Natalie Bockhorst CM
Questions?
Good Afternoon and Welcome. My name is Natalie Bockhorst and I
am a 5th year Construction Management Option. I am here today to
present my senior thesis capstone project on the Advanced
Individual Training Barracks
*
First I would like to give a presentation outline..
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*