Advanced Metering Infrastructure (AMI) Update
August 19, 2020
1
Agenda
• Metering at WSSC Water
• Progress to date
• Current state: Lessons learned
• Why AMI now?
• Challenges with meter reading
• AMI project benefits
• Projected timeline
• Next steps
2
3
Progress To Date
• Initiated project in August 2018
• Performed Needs Assessment through end of 2018
• Issued RFP September 2019
• Project placed on hold due to COVID-19 in March 2020;o Solicitation was later canceled
• Conducted current state lesson learned
• Conducted opt-out peer utility survey
4
Current State: Lessons Learned
• Conducted lessons learned with subcommittees:
Pluses Opportunities
Project team management Identify additional resource needs
Project organizational structure Establish additional subcommittees
Team camaraderie and engagement Increase project communications
Project email to address customer concerns Develop decision matrix
Educating project team on AMI components
and integration needs
Streamline RFP Scope of Work
5
Why AMI Now?
“Innovation distinguishes between a leader and a follower.” Steve Jobs
• Enhance customer experience
o Access to near real-time water usage
o Quickly identify leaks and increased water consumption
o Reduce bills and save money
o Improve billing accuracy / minimize estimated bills
• Aging meter infrastructure
• Support Engineering and Construction’s Water Loss Reduction Plan
• Close data gaps:
o Metering Inaccuracies
o Meter right-sizing and replacement
o Unauthorized consumption
6
• COVID-19 operations impact
o No inside meter reads leads to increased estimated bills
o Large volume of adjustments and bill corrections strains billing team capacity
Why AMI Now? (cont.)
7
• Annual meter reader turnover
rate of 50%o 93-meter readers in last 5 years
o New meter reading staff require 4-6 weeks of on-the-job training
• Regularly fall behind in meter reading in both
counties
• Beginning May 2020, 2-year contract
for temporary personnel to enhance
meter reading services
Challenges with Meter Reading
8
Challenges with Meter Reading (cont.)• Different reading devices
for different meter sizes and manufacturers
• Costly maintenance & replacement of handhelds, antennas, laptops, receivers, and software
• Aging large meters in deep confined spaces have unreliable drive-by Automatic Meter Reading (AMR) signal
9
Challenges with Meter Reading (cont.)
• 63% of WSSC Water’s existing meter population is currently 15 years or older, with the average age being 17.03 years
• Increase number of field activities or truck rolls due to aging meters
• Increase number of testing of old meters at the meter shop
10
Less than 5 Years
6-10 Years
11-15 Years
16-20 Years
21-25 Years
26-30 Years
31-35 Years
36-40 Years
41 or more Years
0 40,000 80,000 120,000Number of Meters
Age of Meters
Challenges with Meter Reading (cont.)
11
Decreases our carbon footprint through reduction of vehicle emissions
Saves manhours by reducing the need for in-person services which saves WSSC Water time and money
Helps us strive towards world-class customer service through reduction of potentially inconvenient home visits to our customers
Average annual truck rolls from FY15-FY19 was 205,288
AMI can help reduce this, which in turn:
AMI Project Benefits
12
Customer WSSC Water
• More accurate billing
• On-property leak detection• Customer can be alerted if there is
abnormal usage
• Water usage information• Customer receives information to
better manage their water usage
• Enables monthly billing• Smaller, more frequent bills to provide
for easier budgeting
• Reduces estimated bills• Less customer dependency
• Fewer meter reading errors
• Reduces meter staff field visits
• Improved meter management
• Detection of water theft
• Distribution system leak detection
• Distribution system planning
• Water quality monitoring
Projected Timeline
13
Emails Received
60Customers
36
Majority of Concerns = Radio Frequency (RF) exposure
AMI Feedback to Date
14
Next Steps
• Present survey findingsoOpt-Out peer utility
oQuantitative customer
oWSSC Water’s Customer Feedback Community
• Virtual public hearings
• Finalize RFP for re-advertisement
15
Questions?
16