Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Advanced Design Workshop: Bioretention Basin
…to discuss the process of designing a Bioretention Basin
Why Are We Here?
Bioretention BasinShallow stormwater basin/landscaped area that uses engineered soils, vegetation and an underdrain to treat runoff
Purpose– Reduce stormwater pollution through,
filtration, biological uptake and microbial activity, using vegetation, engineered soil mix and an underdrain
Considerations– Most applicable adjacent to roadway
shoulder and filter strip along rural sections
Bioretention Basin with Open Underdrain
Vegetative Conveyance
Filtration
Settling
Infiltration
TSS Removal = 85%Detention
Runoff Reduction = 50%
Shallow stormwater basin/landscaped area that uses engineered soils, vegetation and an underdrain to treat runoff
• Design Variations– Upturned Underdrain
Bioretention Basin
Purpose– Underdrain modified to promote
infiltration where soils allow
– Reduce stormwater pollution through filtration, biological uptake and microbial activity, using vegetation, engineered soil mix and an underdrain
Considerations– Forebay required if used with curb
and gutter sections.
Vegetative Conveyance
Filtration
Settling
Infiltration
TSS Removal = 85%Detention
Runoff Reduction = 75%
Bioretention Basin with Upturned Underdrain
Shallow stormwater basin/landscaped area that uses engineered soils, vegetation and an underdrain to treat runoff
• Design Variations– Capped Underdrain
Bioretention Basin
Purpose– Underdrain capped for maximum
infiltration
– Reduce stormwater pollution through infiltration, filtration, biological uptake and microbial activity, using vegetation, engineered soil mix.
Considerations– Native soils must have an infiltration
rate of at least 0.5 in/hr
– Forebay required if used with curb and gutter sections.
Vegetative Conveyance
Filtration
Settling
Infiltration
TSS Removal = 100%Detention
Runoff Reduction = 100%
Bioretention Basin with Capped Underdrain
Advantages– Effective in treating TSS,
fecal coliform, nitrogen, & heavy metals
– Low land requirement– Pleasing aesthetics– Can achieve runoff
reduction where soils allow
Bioretention Basin
Disadvantages– High capital cost– Medium maintenance
burden– Generally limited to 5
ac drainage area – Not intended for
discharge attenuation
Bioretention Basin
BMP RRv TSS Total Phosphorus
Total Nitrogen
Fecal Coliform
Metals
Filter Strip 25% 60 % 20 % 20 % ---------- 40 %
Grass Channel 10-25% 50 % 25 % 20 % ---------- 30 %
Enhanced Dry Swale 50% 80% 50% 50% ---------- 40%
Enhanced Dry Swale(w/ capped Underdrain
100% 100 % 100 % 100 % ---------- 100 %
Enhanced Wet Swale 0% 80 % 25 % 40 % ---------- 20 %
Infiltration Trench 100% 100 % 100 % 100 % 100 % 100 %
Sand Filter 0% 80 % 50 % 25 % 40 % 50 %
Dry Detention Basin 0% 60 % 10 % 30 % ---------- 50 %
Wet Detention Pond 0% 80 % 50 % 30 % 70 % 50 %
Stormwater Wetland – Level I 0% 80 % 40 % 30 % 70 % 50 %
Stormwater Wetland – Level II 0% 85 % 75 % 55 % 85 % 60 %
Bioslope 25-50% 85 % 60 % 25 % 60 % 75 %
OGFC 0% 50 % ---------- ---------- ---------- ----------
Bioretention with open underdrain 50 % 85 % 80 % 60 % 90% 95%
Bioretention with upturned underdrain 75 % 85 % 80 % 60 % 90% 95%
Bioretention with capped underdrain 100 % 100 % 100 % 100 % 100% 100 %
Bioretention Basin
Size to detain & treat WQV (or RRV, if applicable)
Footprint: ~ 3 to 6% of contributing area
Drainage area < 5 acres
Pretreatment to prevent clogging
Engineered soil media: fines, sand, organic matter
Max ponding depth: 12 inches (9 inches preferred)
Drain time: 24 hours
Landscaping plan, no trees
Design Considerations
Bioretention Basin Components
Forebay
Underdrain
Outlet Control Structure
Emergency Spillway
Engineered Media
Vegetation
Provides pretreatment for filtrating/infiltrating BMPs
Removes suspended solids and dissipates energy
Slows down the velocity of the inflow
Reduces large particulates and trash entering the BMPSizing:
Capacity of 0.1 inch runoff/impervious acre
Sediment Forebay
Filter Media – min 24” of permeable soil
Place on top of aggregate blanket (see Specification 169)
3-4" hardwood mulch (non-floating)
2 to 4 ft/day infiltration rate
Soil media to contain a high level of organic material to promote pollutant removal
Engineered Soil Media
Pipe: 8” diameter polyethylene (typ.) in an aggregate layer: No. 57 stone, 12” depth
Rock filter bed: 2-3”, No. 8 or 89 stone
Place engineered media min. 24” above water table
Discharge to storm drainage or stable outlet
Underdrain
No. 57
No. 8
Underdrain Installation
Underdrain System
10 ft max.
10 ft max.0.5% min. slope
100 ft max.
Underdrain Cleanout 5 ft max.
- refer to details
Underdrain System
10 ft max.
0.5% min. slope
- refer to details
Underdrain System
NOTE: DO NOT MOW!
Outlet Control Structure: Open Underdrain
Perforated Pipe
EmergencySpillway
WeirGeotextile
Outlet Control Structure
Engineered Soil Media24 to 48 in
Hardwood Mulch3 to 4 in
No. 8 or 89 Aggregate2 to 3 in
No. 57Aggregate12 in
Outlet Control Structure: Open Underdrain
Perforated Pipe
WeirGeotextile
Outlet Control Structure
Engineered Soil Media24 to 48 in
Hardwood Mulch3 to 4 in
No. 8 or 89 Aggregate2 to 3 in
No. 57Aggregate12 in
EmergencySpillway
Outlet Control Structure: Open Underdrain
Perforated Pipe
WeirGeotextile
Outlet Control Structure
Engineered Soil Media24 to 48 in
Hardwood Mulch3 to 4 in
No. 8 or 89 Aggregate2 to 3 in
No. 57Aggregate12 in
EmergencySpillway
Outlet Control Structure: Upturned Underdrain
WeirGeotextile
Outlet Control Structure
Engineered Soil Media24 to 48 in
Hardwood Mulch3 to 4 in
No. 8 or 89 Aggregate2 to 3 in
No. 57Aggregate12 in
Perforated Pipe
EmergencySpillway
Outlet Control Structure: Upturned Underdrain
WeirGeotextile
Outlet Control Structure
Engineered Soil Media24 to 48 in
Hardwood Mulch3 to 4 in
No. 8 or 89 Aggregate2 to 3 in
No. 57Aggregate12 in
Perforated Pipe
EmergencySpillway
Outlet Control Structure: Upturned Underdrain
WeirGeotextile
Outlet Control Structure
Engineered Soil Media24 to 48 in
Hardwood Mulch3 to 4 in
No. 8 or 89 Aggregate2 to 3 in
No. 57Aggregate12 in
Perforated Pipe
EmergencySpillway
Outlet Control Structure: Closed Underdrain
WeirGeotextile
Outlet Control Structure
Engineered Soil Media24 to 48 in
Hardwood Mulch3 to 4 in
No. 8 or 89 Aggregate2 to 3 in
No. 57Aggregate12 in
Perforated Pipe
EmergencySpillway
Outlet Control Structure: Closed Underdrain
WeirGeotextile
Outlet Control Structure
Engineered Soil Media24 to 48 in
Hardwood Mulch3 to 4 in
No. 8 or 89 Aggregate2 to 3 in
No. 57Aggregate12 in
Perforated Pipe
EmergencySpillway
Outlet Control Structure: Closed Underdrain
WeirGeotextile
Outlet Control Structure
Engineered Soil Media24 to 48 in
Hardwood Mulch3 to 4 in
No. 8 or 89 Aggregate2 to 3 in
No. 57Aggregate12 in
Perforated Pipe
EmergencySpillway
Mulch Layer
Dry media zone
≥ 3 inches deep
Double shredded hardwood mulch
Floating mulch clogs outlet control structure
Three zones present:
• highest elevation planted with species adapted to dry conditions
• middle level – plants able to withstand the fluctuating water levels & tolerant to dryer conditions
• lowest elevation - plants that can withstand standing & fluctuating water levels
Landscaping plan is required
List & quantity of each plant species
Spacing between plants
Vegetation
Roots enhance soil & microbial activity
Vegetation uptakes nutrients
Native species preferred
Avoid invasive species
Goal: 90% vegetative cover within 2 years
Landscaping Plan
University of Idaho
Landscaping PlanShrubs HerbaceousFothergilla Broomsedge
Chokeberry Blue Flag IrisFlorida Leucothoe
Purple Coneflower
Virginia Willow Pink Turtlehead
Possumhaw Black Eyed Susan
Winterberry Wild Blue Indigo
Dwarf Palmetto Lurid Sedge
Spicebush WoolgrassWax Myrtle Marsh Milkweed*selection is based on Georgia plant hardiness areas and planting zone within bioretention basin per the GDOT Planting Schedule Special Construction Detail
Bioretention Basin Planting Zones
Construct after site stabilization
Avoid using heavy equipment in basin area
– Maintain hydraulic conductivity– Prevent damage of underdrains
Construction Considerations
Provide safe access to BMP, outlet structure, forebay, etc. (See figure on next slide)
Provide adequate right-of-way, safely exit & enter of highway
Provide cleanouts for the underdrain system
Maintenance Considerations
Maintenance Considerations
OUTLET
FOREBAY
Determine the goals and primary function of the bioretention basin – RR or WQ
Determine if the basin will be on-line or off-line
RRv
– Calculate the Stormwater Runoff Reduction Target Volume.– Determine the storage volume of the practice and the pretreatment volume– Verify total volume provided by the practice is at least equal to the RRv– Verify that the bioretention basin will drain in the specified timeframes.
WQv
– Calculate the Target Water Quality– Determine the footprint of the bioretention basin and the pretreatment volume required
volume
Design outlet control structure and emergency overflow
Prepare a vegetation and landscaping plan
Design Steps
Example 1
Given:
– New roadway project located in Savannah, Georgia.• 1,100 feet of roadway (in length)• Two 12- foot lanes plus two 3-foot shoulders• Curb and gutter• Runoff exits the roadway through 18” RCP outlet• Soils allow for infiltration
Detention is not needed
Removal of phosphorus, metals, and other pollutants is more important than nitrogen removal
Example 1: Post-development
• Impervious area = 0.76 ac (38.5%)
Total area = 1.97 ac
1,100’ new roadway 2 x 12’ lane + 3’ shoulder
Proposed Bioretention
Area 50’ x 50’
18” RCP
1. Determine whether the bioretention area is intended to meet the Runoff Reduction target
or Water Quality target.
2. Since Soils are good - Try Runoff Reduction Volume first:
𝑅𝑅𝑣𝑣 = Volumetric runoff coefficient = 0.05 + 0.009 𝐼𝐼
𝑅𝑅𝑣𝑣 = 0.05 + 0.009 38.5 = 0.3965
𝑅𝑅𝑅𝑅𝑣𝑣 = Runoff Reduction Volume =1 𝑖𝑖𝑖𝑖 × 𝑅𝑅𝑣𝑣 × 𝐴𝐴 × 43560 𝑓𝑓𝑓𝑓2
𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎12 𝑖𝑖𝑖𝑖𝑓𝑓𝑓𝑓
𝑅𝑅𝑅𝑅𝑣𝑣 =1 × 0.3965 × 1.97 × 43560
12= 2,835 𝑓𝑓𝑓𝑓3
Example 1: Runoff Reduction (Cont’d)
4. Determine the Storage Volume of the practice.
• Space Available: 50 feet wide x 50 feet long = 2,500 ft2
• Forebay: Sized to contain 0.1 inches per impervious acre of contributing drainage• Impervious area: 33,000 ft2 = 0.76 acres• Forebay storage:
0.76 acres x 0.1 in = 0.076 acre-in = 275 ft3
Example 1: Storage Volume
4. Determine the Storage Volume of the practice (continued)
The actual volume provided is: 𝑉𝑉𝑃𝑃 = 𝑃𝑃𝑉𝑉 + 𝑉𝑉𝐸𝐸𝑆𝑆(𝑁𝑁𝐸𝐸𝑆𝑆) + 𝑉𝑉𝐴𝐴(𝑁𝑁𝐴𝐴) Where:
• VP = volume provided (temporary storage) • PV = ponding volume • VES = volume of engineered soils • NES = porosity of engineered soil (use 0.25) • VA = volume of aggregate • NA = porosity of aggregate (use 0.4)
Software program and/or BMP sizing calculator spreadsheet
recommended
Example 1: Storage volume (Cont’d)
4. Determine the Storage Volume of the practice - Starting points/assumptions:
Example 1: Storage Volume (Cont’d)
3
1
1
1
50’
14"
24"
12"3"
4. Determine the Storage Volume of the practice - Starting points/assumptions:
14"
24"
38.5’
42.5’
50’
36.2’
3"44’ 12"
Example 1: Storage Volume (Cont’d)
4. Determine the Storage Volume of the practice (continued)
• PV = ponding volume– Top surface = 50 ft (length) x 50 ft (width)= 2,500 ft2
– Bottom surface = 44 ft (length) x 44 ft (width) = 1,936 ft2
– VES = (2,500 ft2 + 1,936 ft2)/2 x 1 ft(depth) = 2,218 ft3
• VES = volume of engineered soils – Top surface = 42.5 ft (length) x 42.5 ft (width) = 1,806 ft2
– Bottom surface = 38.5 ft (length) x 38.5 ft (width) = 1,482 ft2
– VES = (1,806 ft2 + 1,482 ft2)/2 x 2 ft(depth) = 3,288 ft3
• NES = porosity of engineered soil (use 0.25)
Example 1: Storage Volume (Cont’d)
4. Determine the Storage Volume of the practice (continued)• VA = volume of aggregate
– Top surface = 38.5 ft (length) x 38.5 ft (width) = 1,482 ft2
– Bottom surface = 36.2 ft (length) x 36.2 ft (width) = 1,310 ft2
– VA = (1,482 ft2 + 1,310 ft2)/2 x 1.167 ft (depth) = 1,629 ft3
• NA = porosity of aggregate (use 0.4)
𝑉𝑉𝑃𝑃 = 𝑃𝑃𝑉𝑉 + 𝑉𝑉𝐸𝐸𝑆𝑆(𝑁𝑁𝐸𝐸𝑆𝑆) + 𝑉𝑉𝐴𝐴(𝑁𝑁𝐴𝐴) 𝑉𝑉𝑃𝑃 = 2,218 + 3,288(0.25) + 1,629(0.4) = 3,691 𝑓𝑓𝑓𝑓3
𝑅𝑅𝑅𝑅𝑅𝑅 = 2,835 𝑓𝑓𝑓𝑓3 < VP
Example 1: Storage Volume (Cont’d)
5. Verify that the bioretention basin will drain in the specified timeframes.
• Ponded volume should drain within 24 hours
𝑓𝑓𝑓𝑓 =𝑃𝑃𝑉𝑉(𝑑𝑑𝑓𝑓)
𝑘𝑘(ℎ𝑓𝑓 + 𝑑𝑑𝑓𝑓)𝐴𝐴𝑓𝑓Af = top surface area of filter media (1,806 ft2)PV = ponding volume (2,218 ft3)df = filter media depth (2 ft)k = hydraulic conductivity (4 ft/day)hf = average water depth (0.5 ft)tf = drain time (days)
Example 1: Drain Time
5. Verify that the bioretention basin will drain in the specified timeframes.
• Ponded volume should drain within 24 hours
𝑓𝑓𝑓𝑓 =𝑃𝑃𝑃𝑃(𝑑𝑑𝑓𝑓)
𝑘𝑘(ℎ𝑓𝑓+𝑑𝑑𝑓𝑓)𝐴𝐴𝑓𝑓= 2218 24 0.5+2 1806
= 0.24 𝑑𝑑𝑎𝑎𝑑𝑑𝑎𝑎
Example 1: Drain Time (Cont’d)
5. Verify that the bioretention basin will drain in the specified timeframes.
• Bioretention basin should drain within 72 hours
𝑓𝑓𝑓𝑓 =𝑉𝑉𝑃𝑃
(𝑘𝑘𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑)𝐴𝐴𝑎𝑎VP = total volume provided (3,691 ft3)kdesign = hydraulic conductivity
=1.24 in/hr / Safety factor of 2 = 1.24 ft/dayAa = bottom surface area of aggregate (1,310 ft2)tf = drain time (days)
Example 1: Drain Time (Cont’d)
5. Verify that the bioretention basin will drain in the specified timeframes.
• Bioretention basin should drain within 72 hours
𝑓𝑓𝑓𝑓 = 𝑃𝑃𝑃𝑃(𝑘𝑘𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑)𝐴𝐴𝑎𝑎
= 3,6911.24 1,310
= 2.27 𝑑𝑑𝑎𝑎𝑑𝑑𝑎𝑎
Example 1: Drain Time (Cont’d)
Ex 2: Pre-development
Ex2: Post-development
BIO-RETENTION
BASINCULVERT
OUTLET
FOREBAY
Available BMP area: 2,675 ft2
Post: Open Space – Good: 1.20 ac Impervious: 1.15 ac
Ex2: Post-development
BIO-RETENTION
BASINCULVERT
OUTLET
FOREBAY
Pre: Open Space – Good: 2.10 ac Impervious: 0.25 ac
Determine WQv
𝑹𝑹𝒗𝒗 = 𝟎𝟎.𝟎𝟎𝟎𝟎 + 𝟎𝟎.𝟎𝟎𝟎𝟎𝟎𝟎 ∗ (% 𝑰𝑰𝑰𝑰𝑰𝑰. )
𝑅𝑅𝑣𝑣 𝑝𝑝𝑝𝑝𝑑𝑑 = 0.05 + 0.009 ∗0.252.35
∗ 100 = 𝟎𝟎.𝟏𝟏𝟏𝟏𝟏𝟏 𝑅𝑅𝑣𝑣 𝑝𝑝𝑝𝑝𝑑𝑑𝑝𝑝 = 0.05 + 0.009 ∗1.152.35
∗ 100 = 𝟎𝟎.𝟏𝟏𝟎𝟎𝟎𝟎
𝑹𝑹𝒗𝒗(𝒏𝒏𝒏𝒏𝒏𝒏) = 𝟎𝟎.𝟏𝟏𝟎𝟎𝟎𝟎 − 𝟎𝟎.𝟏𝟏𝟏𝟏𝟏𝟏 = 𝟎𝟎.𝟑𝟑𝟏𝟏𝟏𝟏
Example 2: WQv
𝑾𝑾𝑸𝑸𝒗𝒗 =𝟏𝟏.𝟐𝟐 𝒊𝒊𝒏𝒏 × 𝑹𝑹𝒗𝒗 × 𝑨𝑨 × 𝟏𝟏𝟑𝟑,𝟎𝟎𝟏𝟏𝟎𝟎 𝒇𝒇𝒏𝒏𝟐𝟐
𝒂𝒂𝒂𝒂𝒂𝒂𝒏𝒏𝟏𝟏𝟐𝟐 𝒊𝒊𝒏𝒏
𝒇𝒇𝒏𝒏
𝑾𝑾𝑸𝑸𝒗𝒗 =1.2 𝑖𝑖𝑖𝑖 × 0.344 × 2.35 × 43,560 𝑓𝑓𝑓𝑓2
𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎12 𝑖𝑖𝑖𝑖
𝑓𝑓𝑓𝑓= 𝟑𝟑,𝟎𝟎𝟐𝟐𝟏𝟏 𝒇𝒇𝒏𝒏𝟑𝟑
Size media surface area for WQv
Where, AB = surface area of bioretention basin (ft2)
WQv = water quality volume (ft3)df = filter media depth (ft) – 2.0 to 4.0 ftk = coefficient of permeability of media (ft/day) – typ. 2.0-4.0 ft/dayhf = average height of ponded water (ft) – ½ hmax, max. 1.0 fttf = design filter bed drain time (days) – 1 day max.
=3,521 𝑓𝑓𝑓𝑓3 ∗ 4.0 𝑓𝑓𝑓𝑓
3.0𝑓𝑓𝑓𝑓𝑑𝑑 ∗ 0.5 𝑓𝑓𝑓𝑓 + 4.0 𝑓𝑓𝑓𝑓 ∗ 1 𝑑𝑑𝑎𝑎𝑑𝑑= 1,043 𝑓𝑓𝑓𝑓2𝐴𝐴𝐵𝐵 =
𝑊𝑊𝑄𝑄𝑣𝑣 ∗ 𝑑𝑑𝑓𝑓𝑘𝑘 ∗ ℎ𝑓𝑓 + 𝑑𝑑𝑓𝑓 ∗ 𝑓𝑓𝑓𝑓
Req’d AB< Avail. AB = OK
Example 2: Size Media (Cont’d)
Determine CPv
• Given:– Pre-Development CNW: 65– Post-Development CNW: 79– Tc: 6 min.– P1-yr, 24-hr: 3.56 in– Valdosta, GA → SCS Type II rainfall distribution
Example 2: CPv
Determine CNW
Pre-Development Area (ac) CN
Open space – Good condition (HSG B) 2.10 61
Impervious 0.25 98
TOTAL 2.35 65
Post-Development Area (ac) CN
Open space – Good condition (HSG B) 1.20 61
Impervious 1.15 98
TOTAL 2.35 79
𝑪𝑪𝑪𝑪𝑾𝑾 =𝟐𝟐.𝟏𝟏𝟎𝟎 𝟏𝟏𝟏𝟏 + 𝟎𝟎.𝟐𝟐𝟎𝟎 𝟎𝟎𝟗𝟗
𝟐𝟐.𝟑𝟑𝟎𝟎= 𝟏𝟏𝟎𝟎 𝑪𝑪𝑪𝑪𝑾𝑾 =
𝟏𝟏.𝟐𝟐𝟎𝟎 𝟏𝟏𝟏𝟏 + 𝟏𝟏.𝟏𝟏𝟎𝟎 𝟎𝟎𝟗𝟗𝟐𝟐.𝟑𝟑𝟎𝟎
= 𝟕𝟕𝟎𝟎
Example 2: CPv (Cont’d)
𝑆𝑆 = 1000𝐶𝐶𝐶𝐶
− 10 = 100079
− 10 = 2.66 𝑖𝑖𝑖𝑖.
𝐼𝐼𝑎𝑎 = 0.2 ∗ 𝑆𝑆 = 0.2 ∗ 2.66 = 0.53 𝑖𝑖𝑖𝑖.
Determine CPv: Direct Runoff
Initial Abstraction
𝐼𝐼𝑎𝑎𝑃𝑃
=0.53 𝑖𝑖𝑖𝑖.3.56 𝑖𝑖𝑖𝑖.
= 0.15 𝑖𝑖𝑖𝑖.
𝑄𝑄 =𝑃𝑃 − 0.2𝑆𝑆 2
𝑃𝑃 + 0.8𝑆𝑆=
3.56 − 0.2 ∗ 2.66 2
3.56 + 0.8 ∗ 2.66= 1.62 𝑖𝑖𝑖𝑖.
Direct Runoff
Example 2: CPv (Cont’d)
Determine qu
– Tc: 6 min.(given)– qu = 990 csm/in
SCS Type II Distribution
Determine qo/qi
– qu = 990 csm/in– qo/qi = 0.01
qo/qi Ratio
𝑉𝑉𝑆𝑆𝑉𝑉𝑅𝑅
= 0.682 − 1.43𝑞𝑞𝑝𝑝𝑞𝑞𝑑𝑑
+ 1.64𝑞𝑞𝑝𝑝𝑞𝑞𝑑𝑑
2
− 0.804𝑞𝑞𝑝𝑝𝑞𝑞𝑑𝑑
3
= 0.682 − 1.43 0.01 + 1.64 0.01 2 − 0.804 0.01 3 = 0.67
Determine CPv: Volume Ratio
Where, 𝑃𝑃𝑑𝑑𝑃𝑃𝑅𝑅
= volume storage to release ratio 𝑞𝑞𝑜𝑜𝑞𝑞𝑑𝑑
= ratio of outflow to inflow
Example 2: CPv (Cont’d)
𝑉𝑉𝑆𝑆 =𝑉𝑉𝑑𝑑𝑉𝑉𝑅𝑅
∗ 𝑄𝑄 ∗ 𝐴𝐴 ∗ 3,630
Determine CPv
Where, VS = storage volume – CPV (ft3)𝑃𝑃𝑑𝑑𝑃𝑃𝑅𝑅
= volume storage to release ratio
Q = direct runoff (in)A = drainage area (ac)
= 0.67 ∗ 1.62 𝑖𝑖𝑖𝑖.∗ 2.35 𝑎𝑎𝑎𝑎 ∗ 3,630 = 9,259 𝑓𝑓𝑓𝑓3
Example 2: CPv (Cont’d)
Design Example
Where, AB = surface area of bioretention basin (ft2)CPv = channel protection volume (ft3)df = filter media depth (ft) – 2.0 to 4.0 ftk = coefficient of permeability of media (ft/day) – typ. 2.0-4.0 ft/dayhf = average height of ponded water (ft) – ½ hmax, max. 1.0 fttf = design filter bed drain time (days) – 1 day max.
Size media surface area for CPv
=9,259 𝑓𝑓𝑓𝑓3 ∗ 4.0 𝑓𝑓𝑓𝑓
3.0𝑓𝑓𝑓𝑓𝑑𝑑 ∗ 0.5 𝑓𝑓𝑓𝑓 + 4.0 𝑓𝑓𝑓𝑓 ∗ 1 𝑑𝑑𝑎𝑎𝑑𝑑= 2,743 𝑓𝑓𝑓𝑓2𝐴𝐴𝐵𝐵 =
𝐶𝐶𝑃𝑃𝑃𝑃 ∗ 𝑑𝑑𝑓𝑓𝑘𝑘 ∗ ℎ𝑓𝑓 + 𝑑𝑑𝑓𝑓 ∗ 𝑓𝑓𝑓𝑓
Req’d AB> Avail. AB = RESIZE!
Example 2: Size Media (Cont’d)
Size media surface area for CPv
Where, AB = surface area of bioretention basin (ft2)CPv = channel protection volume (ft3)df = filter media depth (ft) – 2.0 to 4.0 ftk = coefficient of permeability of media (ft/day) – typ. 2.0-4.0 ft/dayhf = average height of ponded water (ft) – ½ hmax, max. 1.0 fttf = design filter bed drain time (days) – 1 day max.
=9,121 𝑓𝑓𝑓𝑓3 ∗ 𝟑𝟑.𝟎𝟎 𝒇𝒇𝒏𝒏
3.0𝑓𝑓𝑓𝑓𝑑𝑑 ∗ 0.5 𝑓𝑓𝑓𝑓 + 𝟑𝟑.𝟎𝟎 𝒇𝒇𝒏𝒏 ∗ 1 𝑑𝑑𝑎𝑎𝑑𝑑= 2,645 𝑓𝑓𝑓𝑓2𝐴𝐴𝐵𝐵 =
𝐶𝐶𝑃𝑃𝑃𝑃 ∗ 𝑑𝑑𝑓𝑓𝑘𝑘 ∗ ℎ𝑓𝑓 + 𝑑𝑑𝑓𝑓 ∗ 𝑓𝑓𝑓𝑓
Req’d AB< Avail. AB = OK
Example 2: Size Media (Cont’d)
Design Example
Design Example: Forebay
Where, VFB = Forebay Volume (ft3)Aimp = Impervious area (ac)
= 0.1 𝑖𝑖𝑖𝑖 ∗ 1.15 𝑎𝑎𝑎𝑎 ∗ 1 𝑓𝑓𝑝𝑝12 𝑑𝑑𝑑𝑑
∗ 43,560 𝑓𝑓𝑝𝑝2
1 𝑎𝑎𝑎𝑎= 417 𝑓𝑓𝑓𝑓3
𝑉𝑉𝐹𝐹𝐵𝐵 = 0.1 𝑖𝑖𝑖𝑖 ∗ 𝐴𝐴𝑑𝑑𝑖𝑖𝑝𝑝
Example 2: Forebay (Cont’d)
Major Elements• Bypass Structure• Forebay• Underdrain• Outlet Control Structure• Mulch • Vegetation Plan• Maintainable Slopes• Maintenance Access
Forebay
Underdrain
Outlet Control Structure
Bypass Structure
Example Large Established Bioretention Basin
Questions
Brad McManus, PE MS4 Program Manager
Office of Design Policy and Support
More GDOT Advanced Design Workshops can be found at https://learning.dot.ga.gov/