ADEBOJE

Embed Size (px)

Citation preview

  • 8/10/2019 ADEBOJE

    1/31

    CEG 307TRANSPORTATION ENGINEERING I

    Course Contents:

    Introduction to Transportation Engineering;

    Design controls and criteria;

    Elements of design;

    Fundamentals of traffic engineering;

    Airport plan and layout;

    Aircraft data related to airport classification and design;

    Design standards.

    Textbooks:

    Fundamentals of Transportation EngineeringRobert G. Hennes & Martin Ekse

    Transportation Engineering (Planning and Design)R. J. Paquette, N. Ashford & P. H.

    Wright

    FMWH Highway Manual Part IDesign

    Highway EngineeringPaul H. Wright

    Policies on Geometric Design of Rural Highways - AASHTO

    INTRODUCTION TO TRANSPORTATION ENGINEERING

    Definition of transportation

    Definition of Transportation Engineering

    Classification of transportation engineering namely Transportation Planning and Transportation

    Development

    Transportation medium includes Land, Air and Water.

    Transportation means includes Vehicles, Trains, Ships, Pipelines, Belt Conveyors and Aircrafts.

    Transportation systems provide the means of moving from one location to another.

  • 8/10/2019 ADEBOJE

    2/31

  • 8/10/2019 ADEBOJE

    3/31

    As shown in the Fig. 1 above, transportation planning is primarily a process of producing

    information that can be used by decision makers to better understand the consequences of different

    courses of action. The tasks that are part of identifying and assessing these consequences include

    the following:

    Inventory of Facilities

    Transportation engineers and planners must know what the transportation network consists

    of and the condition and performance of these facilities. In a state or urban area, much of the

    transportation investment is aimed at upgrading the physical conditionof a facility (e.g., repaving a

    road or building a new bridge) or improving its performance (e.g., building a new road to serve

    existing demand).

    Transportation agencies are expected to have a very extensive inventory of road system in

    their jurisdiction including number of lanes, type of pavement, the last time the pavement was

    replaced, the capacity of the road, accident record, etc. Transit agencies are also expected to have

    an inventory of the different assets that constitute a transit system (e.g., buses, stations, shelters, rail

    cars, etc.).

    Collect and Maintain Socioeconomic and Land Use Data

    Land use maps and other sources can be used to collect information such as the number of

    trips to schools, shopping centers, residential units, office complexes, etc which can then be used in

    transportation planning. Special surveys and census can be used to collect data on different

    socioeconomic characteristics of residents living in a community. Such socioeconomic data include

    level of income, number of members in the household, number of autos in the household, number of

    children, age of head of household, and highest level of education achieved.

    Define Goals and Objectives

    Goals are generalized statements that indicate the desired ultimate achievement of a

    transportation plan. Examples of goals statements might be, The transportation system should

    meet the mobility needs of the population or The transportation system should provide enhanced

    economic development opportunities

    Objectives are more specific statements that indicate the means by which these goals will be

    achieved. For example, the goal of meeting the mobility needs of the population could have the

  • 8/10/2019 ADEBOJE

    4/31

    following objectives associated with it: Provide transit service to major markets in the region,

    Reduce congestion on major highways, and Promote bicycle and pedestrian transportation.

    Goals and objectives define the evaluation criteria that will be used later in the planning

    process to assess the relative impacts of alternative projects and strategies. They also provide an

    important linkage to the desires and values of the public that the transportation plan is serving.

    Identify System Deficiencies or Opportunities

    Transportation planning identifies and prioritizes those elements of the transportation system

    where problems exist today or where problems will exist in the future given growth in travel.

    Additionally, transportation planning can also identify areas where significant problems do not exist

    today, but where changes to the system can provide opportunities for enhanced efficiency of

    operation.

    Develop and Analyze Alternatives

    Once the planning process has identified areas where improvements are needed,

    transportation planners define different strategies that could solve the problem. In the past, these

    strategies have focused on improvements to highways, such as adding new lanes, improving traffic

    control through signals or signing, or improving traffic flow through channelization.

    However, other modern strategies that can be used to solve the transportation problem

    include reducing the demand for transportation through flexible working hours, and application of

    advanced transportation technologies to the operation of a road system, known as intelligent

    transportation systems. Such systems might include network surveillance through video cameras,

    centralized control centers that can re-route traffic around incidents, and dynamic traffic control

    devices that provide coordinated traffic signal timings to maximize the amount of traffic that can

    flow through a set of intersections.

    Evaluate Alternatives

    Evaluation brings together all the information gathered on individual alternatives and

    provides a framework to compare the relative worth of the alternatives. In addition, evaluation

    includes methods for comparing in an analytical way the relative value of the alternatives. One of

    the most used approaches is the benefit/cost ratio, which compares the alternatives on the basis of

    discounted benefits and costs.

  • 8/10/2019 ADEBOJE

    5/31

    DESIGN AND LOCATION OF HIGHWAY

    Introduction

    The earliest forms of roads (highways) consisted mainly of hard tracks cleared of vegetation

    and compacted by human and animal traffic. These were later widened because of heavier trafficand gravels and broken cobblestones were poured onto the tracks to take vehicular traffic. Even

    these types of roads were found to be non-satisfactory in performance to ever increasing traffic

    volume.

    In the face of modern development therefore, the need for more resistant highway brought

    about the idea of all-weather roads. These roads not only facilitate movement but also provide more

    resistant and durable tracks for comfortable ride.

    In Nigeria today, unpaved roads (earth and gravels) are mainly in the rural areas and farm

    settlements while paved roads (flexible and rigid) are mainly in urban areas and between towns and

    cities.

    Classification of Roads

    Roads are classified into three groups in Nigeria:

    1. Trunk A roads

    These are federally maintained roads and usually link the state capitals to the central

    administration.

    2. Trunk B roads

    These are maintained by individual state governments and include all the roads linking the

    towns within the state to the state headquarters.

    3. Local roads

    These are roads under the care of the local government authorities.

    The highway types as defined in Highway Manual include the following:

    Arterial Highway a general term denoting a highway primarily for through traffic,

    usually on a continuous route.

    ExpresswayA divided arterial highway for through traffic with full or partial control

    of access.

  • 8/10/2019 ADEBOJE

    6/31

    FreewayAn expressway with full control of access and all grade crossings eliminated.

    Major Street or Major Highway An arterial highway with intersections at grade and

    direct access to abutting property, and on which geometric design and traffic control

    measures are sued to expedite the safe movement of through traffic.

    Through Street or Through HighwayEvery highway or portion thereof at the entranceto which vehicular traffic from intersecting highways is required by law to stop before

    entering or crossing the same when stop signs are erected.

    Local Street or Local Road A street or road primarily for access to residence, business

    or other abutting property.

    Divided Highway A highway with separated roadways for traffic in opposite

    directions.

    Toll Road, Bridge, or Tunnel A highway, bridge, or tunnel open to traffic only upon

    payment of a direct toll or fee.

    Cul-De-Sac StreetA local street open at one end only, and with special provisions for

    turning around.

    Dead-End StreetA local street open at one end only, without special provisions for

    turning around.

    Principles of Highway Location

    Some detailed guiding principles should be kept in mind in selecting the location for a

    highway. The following outline is not in any particular order nor complete. In addition, some of

    the elements tend to contradict one another; in practice, the location is selected which represents the

    best compromise solution.

    1. For the highway to serve its function of allowing convenient, continuous, free-flowing

    traffic operation, it should be located where it can best meet the major traffic desire lines

    and be as direct as possible.

    2.

    Keep grades and curvature to the minimum necessary to satisfy the service requirements

    of the highway.

    3. Avoid sudden changes in sight distance, especially near junctions.

    4. Avoid having a sharp horizontal curve on or adjacent to a pronounced vertical curve.

    5. In urban areas, site the highway through undeveloped or blighted areas, along the edges

    of large parklands, and in general, away from highly-developed, expensive land areas.

  • 8/10/2019 ADEBOJE

    7/31

    6. In urban areas, locate the highway as closed as possible to the principal parking

    terminals.

    7. In rural areas, locate as much as possible of the new highway on existing ones, so as to

    minimize the use of farmland and reduce total initial and maintenance costs.

    8.

    Locate along the edges of properties rather than through the middle, so as to cause theminimum interference to cultivation and avoid the need for subway construction.

    9. Avoid the destruction or removal of man-made culture.

    10. Keep the highway away from cemeteries, places of worship, hospitals, schools and

    playgrounds.

    11. The effect of the proposed highway on existing ro future utilities above, on or under the

    ground should be considered. It may be such as to warrant changes in order to avoid

    expensive relocation of these utilities.

    12.

    Never have two roads intersecting near a bend or at the top or bottom of a hill.

    13. In the case of a motorway, the need for an interchange with another road may dictate an

    alignment that will intersect the other highway at a place, at an angle and in terrain that

    will best permit the interchange to be constructed.

    14. Avoid intersections at-grade with railway lines. If possible have the highway pass over

    the railway where it goes into a cutting.

    15. Seek favourable sites for river crossing. Preferably these should be at right angles to the

    stream center line.

    16. Do not have a bridge located on or adjacent to a highway curve.

    17. Avoid the need for deep cuttings and expensive tunnel construction.

    18. Avoid locations where rock is close to the surface, as this will usually require at least

    some expensive excavation.

    19. In hilly terrain, be aware of the possibilities of landslides.

    20. To minimize drainage problems, select a location on high ground in contrast to one in a

    valley.

    21. Avoid bogs, marshes and other low-lying lands subject to flooding.

    22. Locate the highway on soil, which will require the least pavement thickness above it.

    23. Locate the highway adjacent to sources of pavement materials.

    24. When the needs of all other factors have been satisfied, the best location is the one,

    which results in the minimum total cost of earthworks. This means that the minimum

  • 8/10/2019 ADEBOJE

    8/31

    quantities of excavation should be so balanced with the quantities of embankment as to

    require a minimum of haulage with little need for overhaul.

    25. In hilly terrain, the highway should cross ridges at their lowest points.

    26. Avoid the unnecessary and expensive destruction of wooded areas.

    27.

    Avoid placing the highway at right angles to the natural drainage channels.28. To relieve the monotony of driving on a long straight road, it is an advantage to site it so

    as to give a view of some prominent feature ahead.

    Having these guiding principles, the highway engineer will then embark on route location,

    which includes Reconnaissance Survey, Preliminary Survey and Final Survey.

    Highway Surveys and Location

    In the relocation or reconstruction of existing highways and the establishment of new ones,

    highway surveys are required for the development of project plans and the estimation of costs.

    Highway surveys usually involve measuring and computing horizontal and vertical angles, vertical

    heights (elevations), and horizontal distances. The surveys can also be used to prepare base maps

    with contour lines and longitudinal cross sections, as required.

    Highway surveying techniques have been revolutionized during the past decade due to the

    rapid development of electronic equipment and computers. These techniques can be grouped into

    three general categories:

    a. Conventional and traditional ground survey methods

    b. Digital ground survey methods

    c. Remote sensing techniques.

    The performance of good surveys requires well-trained engineers who have an

    understanding of the planning, design, and economic aspects of highway location and who are

    sensitive to the social and environmental impacts of highway development.

    The tasks involved in the highway location include:

    (i) Desk studies

    (ii) Reconnaissance survey

    (iii) Preliminary survey

    (iv) Final location survey

  • 8/10/2019 ADEBOJE

    9/31

    (i) Desk Studies

    A desk study includes the preliminary steps of evaluation of all available data procured in

    the form of maps, aerial photographs, mosaic, or charts and may require the application of a large

    variety of engineering, environmental, social, and economic knowledge. The type and amount of

    data collected during this initial phase will vary with the functional classification of the road and thenature and size of the project.

    The categories of desirable data are as follows:

    1. Engineering data

    i) Topographic and geological maps

    ii) Stream and drainage basin maps

    iii) Climatic records

    iv) Preliminary survey maps of previous projects

    v)

    Traffic surveys and capacity studies

    2. Environmental data

    i) Agricultural soil surveys indicating soil erodibility

    ii) Water quality studies

    iii) Air pollution studies

    iv) Noise and noise attenuation studies

    v)

    Fish and wildlife inventories

    vi) Historical studies

    3. Social data

    i) Demographic and land-use information

    ii) Census data, etc.

    4. Economic data

    i) Overall costs of previous projects

    ii) Unit construction cost data

    iii) Agricultural, industrial and commercial activities and trends

    iv) Property values.

  • 8/10/2019 ADEBOJE

    10/31

    When all the available data have been assembled, a detailed analysis should reveal

    information pertinent to the proposed project. For example, analysis of the available information

    may allow the engineer to determine the advisability of selecting an entirely new location or

    improving the existing one.

    After an exhaustive study of topographic maps, drainage maps, soil maps, and other data ismade in the office, a series of proposed locations may be selected for a field investigation.

    (ii) Reconnaissance Survey

    The reconnaissance survey consists of a field investigation that usually provides a means of

    verification of conditions as determined from the preliminary desk study. For example, building

    symbols on maps do not indicate the true values of property under consideration, and this

    information can usually be secured by field investigation. A study is made of the profiles and

    grades of all alternative routes and cost estimates made for grading, surfacing, structures, and right-

    of-way. A comparison of alternative routes in this fashion will aid the final selection of the most

    likely location.

    (iii) Preliminary Survey

    A preliminary survey is made to gather information about all the physical factors that affect

    the tentatively accepted route. In general, a regular survey party carries out the work. The raw data

    is normally acquired using some of the conventional surveying equipment including:

    a) Tapes, Theodolite and level

    b) Theodolite and Electromagnetic Distance Measurement

    c) Combined Theodolite and EDM system

    d) Total Station

    Field sheets or field books are required to record all observations by hand. Data loggers are

    available for automatic recording of observations when Total Station is used.

    A primary traverse or baseline is established as an open traverse consisting of tangent

    distances and deflection angles following approximately the line recommended in the

    reconnaissance report. Traditionally, conventional ground surveys are carried out by the use of

    Theodolite to measure angles in both vertical and horizontal planes, the Levelling instrument for

    measuring changes in elevations (heights), and the tape for measuring horizontal distances.

  • 8/10/2019 ADEBOJE

    11/31

    However, with developments in electronics, EDM mounted on Theodolite or total station can now

    be used more effectively for most surveying projects.

    When the preliminary line has been established, the topographic features are recorded. The

    extent to the right and left of the traverse line to which the topography should be determined will

    vary but should not be less than the proposed width of right-of-way.Using the preliminary survey as a basis, a preliminary survey map is drawn. The

    preliminary map should show all tangents with their bearings and distances, all deflection angles,

    ties to property corners, etc. Certain topographic features such as streams, watercourses, lakes,

    hills, and ravines, and man-made features such as buildings, drainage structures, power lines, and

    other public facilities are shown on the map.

    (iv) Final Location Survey

    The final location survey is the detailed layout of the selected route, during which time the

    final horizontal and vertical alignments are determined and the final positions of structures and

    drainage channels are also determined. The final location survey serves the dual purpose of

    permanently establishing the centerline and collecting the information necessary for the preparation

    of plans for construction. The line to be established should follow as closely as is practical, the line

    drawn on the preliminary map, conforming to the major and minor control points and the alignment

    that was previously determined.

    The first step in the final location survey requires the establishment of the centerline, which

    is used as a survey reference line, upon which property descriptions are based for the purpose of

    purchasing right-of-way. Level work is of the utmost importance, because the grade line,

    earthwork, and drainage are designed from the level notes. Finally, cross-sections levels are taken

    at intervals ranging from 1 to 5m in the transverse direction and longitudinally at regular interval of

    25m stations and at any intermediate points with abrupt slope changes.

  • 8/10/2019 ADEBOJE

    12/31

    ELEMENTS OF GEOMETRIC DESIGN

    The essential design features of a roadway or railway are its location and its cross-section.

    In the horizontal plane, the locations of points are referenced to a coordinate system in which the

    positivey-axis is north and the positive x-axis is east. Positions along they-axis are called latitudes

    and those along thex-axis are called longitudes (departures).

    Customarily, points along the route are identified by chainages (stations), the distance in

    metres from some reference point, commonly the beginning point for the project. The location of

    points in the vertical plane (or along thez-axis) is given as the elevation above mean sea level.

    The cross section of a roadway is described by its dimensions at a right angle to the direction

    of the alignment, including widths, clearances, slopes, and so on.

    A CIRCULAR CURVES - GENERAL

    A highway route survey is initially laid out as a series of straight lines (tangents). Once the

    centerline location alignment has been confirmed, the tangents are joined by circular curves that

    allow for smooth vehicle operation at the speeds for which the highway was designed.

  • 8/10/2019 ADEBOJE

    13/31

    Figure 1Circular curve terminology

    Figure 1 illustrates how two tangents are joined by a circular curve and shows some related

    circular curve terminology. The point at which the alignment changes from straight to circular is

    known as the BC (beginning of curve). The BC is located distance T (subtangent) from the PI

    (point of tangent intersection). The length of circular curve (L) is dependent on the central angleand the value of R (radius).

    The point at which the alignment changes from circular back to tangent is known as the EC

    (end of curve). Since the curve is symmetrical about the PI, the EC is also located distance T from

    the PI. From geometry, the radius of a circle is perpendicular to the tangent at the point of

    tangency. Therefore, the radius is perpendicular to the back tangent at the BC and the forward

    tangent at the EC.

    The terms BC and EC are also referred to by some agencies as PC (point of curve or

    curvature) and PT (point of tangency), and by others as TC (tangent to curve) and CT (curve to

    tangent).

    B CIRCULAR CURVE GEOMETRY

    Most curve problems are calculated from field measurements (and the chainage of PI) and

    from design parameters (R). Given R (which is dependent on the design speed) and , all other

    curve components can be computed.

    Analysis of Figure 2 will show that the curve deflection angle (PI, BC, EC) is2

    and that

    the central angle at 0 is equal to , the tangent deflection.

    The line (0PI), joining the center of the curve to the PI, effectively bisects all related lines

    and angles. For the following derivation of equations, refer to Figure 2.

    Tangent: In triangle BC, O, PI,R

    T= tan

    2

    T = R tan2

    (1)

    Chord: In triangle BC, O, B,R

    C2/1= sin

    2

    C = 2R sin2

    (2)

  • 8/10/2019 ADEBOJE

    14/31

    Figure 2Geometry of the circle

    Mid-ordinate:R

    OB= cos

    2

    OB = Rcos2

    But OB = R M

    R - M = Rcos2

    M = R

    2cos1 (3)

    External: In triangle BC, O, PI, O to PI = R + E

    ER

    R

    = cos

    2

    E = R

    1

    2/cos

    1 (4)

    = R

    1

    2sec (alternate)

  • 8/10/2019 ADEBOJE

    15/31

    Figure 3Relationship between the degree of curve (D) and the circle

    From Figure 3,

    Arc:R

    L

    2=

    360

    ,

    3602

    RL (5)

    where is expressed in degrees and decimals of a degree.

    From Figure 3,

    D and R:R

    D

    2

    100

    360 ,

    RD

    58.5729 (6)

    Arc:R

    D

    2

    100

    360 ,

    RD

    58.5729 (7)

    where D (degree of curve) is defined as the central angle subtended by 100ft of arc.

  • 8/10/2019 ADEBOJE

    16/31

    C. VERTICAL ALIGNMENT

    (a) General

    The longitudinal profile of the proposed highway is first drawn as a series of intersecting

    gradients. The straights subsequently form tangents to vertical curves, which are fitted to them.The geometric proportions encountered in most cases point to the fact that the simple

    parabola is the most convenient to use.

    The vertical alignment affects:

    a. The construction cost of the project.

    b. The operating cost of vehicles using the road.

    The vertical alignment must have good correlation with the horizontal alignment and ensure

    good sight distances over crests. Care must be taken to avoid:

    i. very short sag vertical curves

    ii. sharp drop immediately after a long up-grade

    iii. short grade between crest and sag curves

    iv. combination of two vertical curves in the same directionthey must be replaced by

    a single vertical curve.

    Grades and Grade Control

    The vertical alignment of the roadway and its effect on the safe and economical operation of

    the vehicle constitutes one of the most important features of highway and railway design. The

    vertical alignment, which consists of a series of straight lines connected by vertical parabolic or

    circular curves, is known as the grade line. When the grade line is increasing from the horizontal, it

    is known as a plus grade, and when it is decreasing from the horizontal it is known as a minus

    grade.

    Establishment of vertical alignment

    1. An ideal situation is one in which the cut is balanced against the fill without a great deal

    of borrow or an excess of cut to be wasted.

    2. All hauls should be downhill if possible, and not too long.

    3. Ideal grades should have long distances between points of intersection, with long vertical

    curves between grade tangents to provide smooth riding qualities and good visibility.

  • 8/10/2019 ADEBOJE

    17/31

    4. The grade should follow the general terrain and rise and fall in the direction of the

    existing drainage.

    5. In rock cuts and in flat, swampy areas, it is necessary to maintain higher grades.

    6. The presence of grade separations and bridge structures also control grades.

    7.

    Change of grade from plus to minus (summit curves) should be placed in cuts, andchanges from a minus grade to a plus grade (sag curves) should be placed in fills.

    8. Urban projects will usually require a more detailed study of grade controls and a fine

    adjustment of elevations than do rural projects.

    9. In urban projects, it is best to adjust the grade to meet existing conditions because of

    additional expense when doing otherwise.

    10. Grades are normally dependent on design speed and topography.

    D. VERTICAL CURVES - GENERAL

    Vertical curves are used in highway and street vertical alignment to provide a gradual

    change between two adjacent grade lines.

    Figure 4Vertical curve terminology (profile view shown).

  • 8/10/2019 ADEBOJE

    18/31

    From Figure 4,

    g1 = slope (in percent) of the lower chainage grade line,

    g2 = slope (in percent) of the higher chainage grade line,

    BVC = beginning of the vertical curve,

    EVC = end of the vertical curve,L = length of vertical curve. This is same as the projection of the curve onto a

    horizontal surface and as such corresponds to plan distance.

    A = algebraic change in slope direction i.e. A = g2g1

    There are two types of vertical curves viz: Summit or Sag vertical curve (see Figure 5). The

    parabolic curve is used almost exclusively in connecting grade tangents because (1) it has a constant

    rate of change of slope, and (2) ease of computation of vertical offsets, which permits easily,

    computed curve elevations.

    (i) The rate of change of slope of a simple parabola is constant, i.e.

    kdx

    Yd

    2

    2

    (8)

    (ii) The offset (y) from the grade (see Figure 5) is proportional to the square of

    distance from tangent point, i.e.,

    2Axy (where A = constant) (9)

    Integrating equation (8),

    Bkxdx

    dY (where B is constant) (10)

    From Figure 6, it will be noted that:

    when x = 0, %1gdx

    dY , %1gB ,

    when x = L, %2gdx

    dY ,

    Substitute %2gdx

    dY , and x = L in equation (10)

  • 8/10/2019 ADEBOJE

    19/31

    Figure 5Summit (Crest) and Sag Vertical Curves

  • 8/10/2019 ADEBOJE

    20/31

    %% 12 gkLg ,L

    ggk

    )( 12

    Equation (10) becomes:

    %)%( 112 gxLgg

    dxdY

    , (11)

    Integrating equation (11),

    Cxgx

    L

    ggY

    1

    212

    2

    )%( (12)

    x = 0 when y = 0, C = 0

    From Figure 6,x

    Yyg

    %1

    Equation (12) becomes:

    xx

    Yyx

    L

    ggY

    2

    )%( 212

    YyxLggY

    2)%(

    2

    12

    L

    Axx

    L

    ggy

    2002100

    )( 2212

    where A = algebraic difference between the two grades measured in percent.

    The vertical offset (y) from the grade at any point (x)from the tangent point is given by

    L

    Axy

    200

    2

    (13)

  • 8/10/2019 ADEBOJE

    21/31

    Computation of the High or Low Point on a Vertical Curve

    The highest point on the vertical curve does not lie vertically below or above the point of

    intersection, except in the case where the two grades are equal. The highest point occurs when

    the gradient is zero.

    This means that equation (11) may be equated to zero, i.e.,

    %)%(

    1

    12 gxL

    gg

    dx

    dY

    = 0

    %)%(

    1

    12 gxL

    gg

    ,

    A

    Lg

    x 1

    (14)

    Thus, the highest point occurs at a point (x) given by equation (14).

    Substituting equation (14) into equation (13) to determine the vertical offset (y) at the

    highest point gives:

    A

    Lg

    A

    Lg

    L

    Ay

    200200

    2

    1

    2

    1

    A

    Lgy

    200

    2

    1 (15)

    N.B.- The above formulas apply only for the symmetrical curve, i.e., one in which the tangents

    are of equal length. The unequal tangent or unsymmetrical vertical curve is a compound

    parabolic curve. Its use generally is warranted only where a symmetrical curve cannot meetimposed alignment conditions.

  • 8/10/2019 ADEBOJE

    22/31

    E. DESIGN CONTROLS AND CRITERIA

    The geometric design of a road is the arrangement of the visible elements of a road, such as

    alignment, grades, sight distances, widths, slopes, etc. These elements are influenced by the

    following design controls and criteria:

    i)

    Functional classification of the roadway being designed.ii) Design speed.

    iii) Topography.

    iv) Cost and available funds.

    v) Human sensory capacities of drivers, bikers and pedestrians.

    vi) Size and performance characteristics of the vehicles that will use the facility.

    vii) Safety considerations.

    viii) Social and environmental concerns.

    However, the principal design criteria for highways for which there are design standards and

    procedures are:

    a) Traffic volume

    b) Design speed

    c) Vehicle Characteristics

    d) Highway Capacity.

    1. Traffic Volume

    The number of vehicles passing a particular section of the road per unit time at a specified

    time is called traffic volume. This study can be carried out separately for vehicles and pedestrians

    or combined.

    The purposes of traffic volume study can be listed as follows:

    a. It establishes the importance of any road and thus help in deciding the relative

    priority for improvement and expansion.

    b. The data are used for planning, designing and regulation phase of traffic engineering.

    c. It helps in the design of road pavements, bridges and culverts.

    d. It helps in the design of new routes and new facilities.

    e. It helps analyse traffic pattern and trend.

  • 8/10/2019 ADEBOJE

    23/31

    The general unit for reporting traffic using a particular facility is the average daily traffic

    (ADT). Numerically, the ADT is the total annual volume of traffic divided by the number of days

    in the year. The ADT is readily obtainable where continuous counts of traffic are available. ADT

    volumes are useful in economic study of the highway and also in the design of the structural

    elements of the road.Counting of traffic may be done mechanically or manually. Photo electric cells, magnetic

    detectors, radar detectors and impulse actuated recorders are some of the mechanical or automatic

    count devices.

    Traffic Projection Factor

    Normal increase in traffic volume for long term can be expected to be about 5 per cent

    compounded. Traffic projection factor gives the ultimate volume at the end of design period.

    According to the Highway Manual of the FMW&H,the Design Hourly Volume (DHV)

    should be representative of the future year chosen for design. It should be predicted on current

    traffic allowing for normal traffic growth, generated traffic or diverted traffic and development

    traffic. A period of 20 years shall be used generally as the basis for design; but this period shall be

    reduced to 10 years where stage construction is involved.

    Definitions

    a. Normal Traffic: - Normal traffic growth is the increase in traffic volume due to

    increase in number of transport vehicles.

    c. Generated Traffic: - This is the traffic created due to extra facility provided.

    d. Development Traffic: - It is the traffic which is due to improvements carried out in

    adjacent area.

    e. Current Traffic: - It is that traffic which would immediately use a new road or an

    improved one when opened to traffic.

    The formula used for analyses as developed in the United Kingdom is:

    A = 21 rP

    Where

    A = Number of vehicles per day for design

    P = Number of vehicles per day at last census

    r = Annual rate of increase in traffic and may be taken as 0.05 (i.e. 0.5%)

  • 8/10/2019 ADEBOJE

    24/31

    n = Number of years between last census and year of consideration for widening.

    2. Design Speed

    The design speed is the speed selected for the purpose of correlating those features of the

    highways such as curvature, super-elevation and visibility distances for safe operation of vehicles.The design speed is the highest continuous speed at which individual vehicles can travel

    with safety upon the highway, when weather conditions are favourable, traffic density is low, and

    the design features of the highway are the governing factors of safety.

    The design speed is therefore dependent upon:

    (ii) The terrain of the proposed route.

    (iii) Type and volume of traffic anticipated.

    (iv) Type of highway.

    (v)

    Environmental conditions.

    Recommended values are given in Table 1 below:-

    Table 1DESIGN SPEED

    [Highway Design Manual, 1973]

    Type of

    Highway Terrain

    Design Speed (km/hr)

    AASHTO*Minimum Desirable

    Limited Access All Terrain 96 112

    Unlimited

    Access

    Level

    Rolling

    Hilly

    96

    80

    64

    112

    96

    80

    112

    96

    80

    *Not recommended

    3. Vehicle CharacteristicsVehicle characteristic dimensions are of great importance in the design of parking facilities.

    In such cases, where the economy permits, consideration should be given to the possibility of

    making provision for one or two doors open.

    The layout of roads, especially junctions, must be related to the vehicles using them. Hence,

    vehicle sizes are essential in geometric design, especially for sharp radius turns. On the other hand,

  • 8/10/2019 ADEBOJE

    25/31

    the size, weight and features of legally permitted vehicles govern the standards to be set for lane

    width, vertical clearance, pavement thickness and bridge loadings.

    Four (4) design vehicles have been adopted to represent the main vehicle types in use (U.S.

    practice). The design vehicles are:

    P = Passenger carsSU = Single unit or buses

    WB 40 = Medium Semi-trailer combination

    WB 50 = Large Semi-trailer combination

    Typical dimensions of various design vehicles are given in Table 2 below:

    Table 2DESIGN VEHICLE

    [Highway Design Manual, FMWH]

    Design

    Vehicle Dimensions (metres)

    Type Symbol Wheel Base Overall

    Length

    Overall Width Height

    Passenger Car P 3.4

    (11)

    5.8

    (19)

    2.1

    (7)

    -

    Single Unit

    Truck (Buses)

    SU 6.1

    (20)

    9.1

    (30)

    2.6

    (8.5)

    4.1

    (13.5)Small semi-

    trailer

    combination

    WB40 12.2

    (40)

    15.2

    (50)

    2.6

    (8.5)

    4.1

    (13.5)

    Large semi-

    trailercombination

    WB50 15.2(50)

    16.8(55)

    2.6(8.5)

    4.1(13.5)

    Note: Figures in brackets are in feet.

    Weights (tons)

    AASHTO Maximum

    Single axle - 10 12

    Tandem axles - 16 20

    Max. Gross Weight - 43 69

  • 8/10/2019 ADEBOJE

    26/31

    4. Highway Capacity

    The Highway Capacity Manual defines the practical capacity (or design capacity) as the

    number of vehicles that can pass over a given section of the roadway during one hour under

    specified traffic conditions and operating at a level of service.

    The level of service depends on:(i) Probability of traffic interruptions

    (ii) Desired speed of operation

    (iii) Location and type of highway facility.

    (iv) Cost of vehicle operation.

    (v) Building, operating, and maintenance of the highway.

    As shown in Table 3(a) below, the manual recommends maximum practical capacities as follows:-

    (i) Two lane road - 900 pcu/hr

    (ii) Three lane road - 1500 pcu/hr

    (iii) Multi-lane road - 1000 pcu/hr

    * pcu = passenger car unit

    Table 3(a)DESIGN CAPACITY FOR VARIOUS TYPES OF RURAL ROADS

    (Two-Way Total) [British Standards]

    Passenger Car Unit per hour (p.c.u./hr)

    Type of Road Roads in Rural Areas Highway Capacity Manual

    Two-Lane Carriage way 900 900

    Three-Lane Carriage way 1500 1500

    Dual Two-Lane Carriage way 3300 1000 per lane in the

    direction of heavier flowDual Three-Lane Carriage way 5000

  • 8/10/2019 ADEBOJE

    27/31

    Table 3(b)DESIGN CAPACITY FOR URBAN ROADS

    [British Standards]

    Type of Road Capacity (p.c.u./hr) Remarks

    Four-lane urban motorway(with grade separation)

    3000 Capacity for one directionof flow

    Six-lane urban motorway(with grade separation)

    4500 Capacity for one directionof flow (Highest distributor)

    Two-lane all purpose road with

    unlimited access

    1500 Capacity for both direction

    of flow

    Three-lane all purpose road

    with limited access

    2200 Capacity for both

    directions

    Four-lane all purpose road with

    limited access

    2400 Capacity for both

    directions

    Two-lane all purpose road with

    capacity restrictions

    600 - 750 Two way capacity waiting

    vehicles and junctions

    F. SIGHT DISTANCE

    Under ideal conditions, geometric design standards should ensure that vehicles are mutually

    visible within eyesight distance of each other. Highway designs must ensure that the driver has

    ample distance of clear vision ahead so that he can avoid hitting unexpected obstacles and can pass

    slower vehicles safely. Recommended sight distances are given below in Tables 1 and 2 below.

    1) STOPPING SIGHT DISTANCE (Horizontal Alignment)

    Sight distance at every point on the highway should be as long as possible but never less

    than the minimum stopping sight distance.

    The safe stopping sight distance is the minimum distance required for stopping a vehicle

    traveling with or near the design speed before reaching a stationary object or vehicle on the

    highway. The safe stopping (or non-passing) sight distance can be considered as the sum of two

    components viz:

    (a) Perception - Reaction Distance

    This is the distance covered within the period the stationary vehicle/object is sighted and

    actual braking operation starts. The elements, which make up the reaction time, depend upon many

    modifying factors and individual driving abilities.

    AASHTO recommends P-R time of 2.5 seconds for Rural Roads and 1.5 seconds for Urban

    Roads. Therefore, for a rural road, the distance covered during P-R time of 2.5 seconds is d1where

  • 8/10/2019 ADEBOJE

    28/31

    d1 = vt (1)

    where v = speed in (metre/sec)

    t = perception-reaction time (seconds)

    d1 = distance covered (metres)

    If in expression (1), the speed is expressed in km/hr, then

    d1 = 5.23600

    1000

    v

    =44.1

    v metres

    ii) Braking distance

    This is the distance, d2, covered during the actual braking operation. This is estimated by

    utilizing the principle that the change in kinetic energy is equal to force multiplied by distance.

    gf

    vd

    2

    2

    2 (2)

    whered2 = braking distance (metres)

    v = driving speed (metres/sec)

    f = coefficient of friction between tyres and road surface

    g = acceleration due to gravity = 9.81m/sec2

    If the speed is expressed in V km/hr,

    f

    vd 2.254

    2

    2

    Therefore, safe stopping (non-passing) sight distance

    D = d1 + d2

    =44.1

    v +

    f

    v

    2.254

    2

    When the vehicle is on a slope q%, the braking distance is modified to

  • 8/10/2019 ADEBOJE

    29/31

    )(2.254

    2

    2qf

    vd

    Upward grades carry positive signs as against negative signs for downward grades. This means that

    upward braking distances are shorter than those for downward grades.

    Stopping (non-passing) sight distance over crests is the longest distance a driver whose eye

    is 1.143m (3.75ft) above the pavement can see the top of an object 0.15m (o.50ft) high on the road.

    See Figure 1 for approved AASHTO method of measuring stopping sight distance over crests.

    Under the condition where the difference in grade is small, ease of riding and appearance may

    demand longer curves than value allowed for sight distance.

    Table 1DESIRABLE STOPPING SIGHT DISTANCES

    *[AASHTO Recommended Sight Distances]

    DESIGN

    SPEED(km/hr)

    P-R DISTANCE BRAKING DISTANCE STOPPING SIGHTDISTANCE (metres)

    Time(sec)

    Distance(m)

    Coeff. offriction (Wet

    surface)

    Distance(on level

    ground)

    ComputedRounded

    for Design

    40

    60

    80100110

    120

    2.5

    2.5

    2.52.52.5

    2.5

    27.8

    41.7

    55.669.476.4

    83.3

    0.36

    0.33

    0.310.300.29

    0.27

    17.5

    42.9

    81.2131.1164.1

    209.8

    45.3

    84.6

    136.8200.5240.5

    293.1

    45

    85

    135200240

    290

    * Note: used mainly for horizontal sight distance

    (2) PASSING SIGHT DISTANCE

    In the design of the horizontal alignment of two/three lane carriageways, provision should

    be made for adequate passing sight distance in order that faster vehicles may overtake slower-

    moving vehicles without any fear of head-on collision.

    The safe passing sight distance is the distance required to allow safe overtaking at or near

    the design speed in the face of an on-coming vehicle.

  • 8/10/2019 ADEBOJE

    30/31

    Table 2(a): SIGHT DISTANCERURAL ROADS (British Practice)

    Carriageway

    Design Speed

    (Km/hr)

    Stopping Sight Distance Overtaking

    Sight Distance

    (crests)

    Minimum

    Stopping

    Sight Distancek value for

    crestk value for

    sags

    Dual TwoLane 120

    105 75 -- 300

    Three Lane 100 50 50 450 210Two Lane 80 20 30 360 140

    Table 2(b): SIGHT DISTANCEURBAN ROADS (British Practice)

    Design Speed(km/hr)

    Minimum OvertakingSight Distance (m)

    Minimum StoppingDistance (m)

    80 360 140

    60 270 90

    50 225 70

    30 135 30

    Table 2(c): SIGHT DISTANCES(metres)

    DesignSpeed

    (km/hr)

    STOPPING PASSING

    UK AUSTRALIA USA UK AUSTRALIA USA

    60 90 80 84 270 300 457

    80 140 120 107 360 450 549

    100 210 170 145 450 750 640

    120 300 250 183 -- -- --

    Table 2(d): Highway Manual Design (Federal Republic of Nigeria)

    Design Speed

    (km/hr)

    Passing Sight Distance

    (metres)

    48 244

    64 39680 518

    96 610

    112 701

  • 8/10/2019 ADEBOJE

    31/31