65
Addendum to Environmental Impact Assessment (EIA) For Amendment of Environmental Clearance (EC) Of Kalyani Steels Ltd For its Proposed Expansion of Iron and Steel Plant (1.4 MTPA) Located at Koppal District, Karnataka 9 th Apr, 2019

Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

Addendum to Environmental Impact Assessment (EIA)

For

Amendment of Environmental Clearance (EC)

Of

Kalyani Steels Ltd

For its Proposed Expansion of Iron and Steel Plant

(1.4 MTPA) Located at Koppal District, Karnataka

9th Apr, 2019

Page 2: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

1

Table of Contents 1 - Introduction: ................................................................................................................................................... 3

1.1 Brief introduction of Environmental Clearance details .................................................................................. 3

1.2 Nature of the project proposed ................................................................................................................................. 3

1.2.1Products with capacities include: ................................................................................................................. 3

1.2.2Production Units: ................................................................................................................................................. 3

1.3 Description of Coke Plant & DRI included in 1.4 MTPA EC ............................................................................ 4

1.4 Proposed Amendment .................................................................................................................................................. 5

1.5 Scope of the study: .......................................................................................................................................................... 5

1.5.1Technical aspects of non-recovery with heat recovery: ...................................................................... 5

1.5.2Baseline data of EIA report submitted by KSL & post project monitoring data ........................ 6

1.5.3Recent baseline status of recent EIA study appraised by Ministry for the adjoining project

of M/s Mukand Ltd ........................................................................................................................................................ 6

2 - Project Description ...................................................................................................................................... 7

2.1 Changes proposed to be made in Existing EC of 1.4 MTPA Expansion Project ..................................... 7

2.2 Basic steel plant /process flow chart (as per EC granted) with material balance ............................... 3

2.3 Change in process flow sheet for the proposed coke plant ........................................................................... 4

2.3.1Brief description of Recovery Type coke manufacturing with schematic drawings ............... 5

2.3.2Brief description of Non-Recovery Type coke manufacturing with schematic drawings ..... 7

2.4 Basic material balance for Recovery and Non-recovery coke plant for rated capacity of 0.6

MTPA .................................................................................................................................................................................... 9

2.4.1Material Balance diagram for Recovery Type 0.6 MTPA Coke Oven (As per PFR & EIA

report submitted for Existing EC): ......................................................................................................................... 9

2.4.2Material Balance diagram for Non-Recovery Type 0.6 MTPA Coke Oven (As proposed): . 10

2.5 Water balance flow chart .......................................................................................................................................... 11

2.5.1Water balance as per Existing EC: ............................................................................................................. 11

2.5.2Water balance for Proposed amendment in EC: .................................................................................. 11

2.6 Comparison between Non-Recovery and By-Product Recovery Type Coke Oven ........................... 13

2.7 Brief on demonstrated experience worldwide ................................................................................................ 14

3 - Baseline Environment ............................................................................................................................... 16

3.1 Baseline Air Environment as per the EIA appraised for earlier KSL’s Existing EC ........................... 16

3.2 Post project monitoring data .................................................................................................................................. 18

3.3 KSL’s Existing Plant’s Half Yearly Monitoring Data ....................................................................................... 18

3.4 Baseline Soil, Water and Noise as per the EIA appraised for earlier KSL’s Existing EC.................. 20

3.5 Recent baseline data from M/s Mukand Ltd (Generated for period Apr 2016 - June 2016) ........ 27

4 - Impact Assessment ..................................................................................................................................... 38

4.1 Results of impact assessment made with respect to Air Environment in the EIA as per Existing

EC ........................................................................................................................................................................................ 38

Page 3: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

2

4.2 Absolute emissions calculations for Non-recovery Coke Oven with heat recovery ......................... 42

4.3 Results of impact assessment made with respect to Air Environment considering recent

baseline data from M/s Mukand Ltd .................................................................................................................... 42

4.4 Comparison of air dispersion modeling results .............................................................................................. 47

4.5 Mitigation measures ................................................................................................................................................... 47

4.5.1By-product Recovery Coke Ovens ............................................................................................................. 47

4.5.2Heat-Recovery type Coke Ovens ................................................................................................................ 48

5 - Alternatives of Technology...................................................................................................................... 49

5.1 Alternatives in comparison to EIA for coke plant ........................................................................................... 49

5.2 Alternatives for pollution control equipment etc. .......................................................................................... 53

6 - Environmental Monitoring programme ............................................................................................. 54

6.1 Ambient Air Quality Monitoring ............................................................................................................................ 54

6.2 Water Quality Monitoring......................................................................................................................................... 54

7 - Environmental Cost benefit analysis ................................................................................................... 55

8 - Conclusion ..................................................................................................................................................... 56

Page 4: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

3

1 - INTRODUCTION:

1.1 Brief introduction of Environmental Clearance details

Kalyani Steels Ltd (KSL) is a part of over $3.0 billion Kalyani Group. KSL was established in 1973 and is

a leading manufacturer of forging and engineering quality carbon & alloy steels using the blast furnace

route.

KSL had planned expansion of their Integrated Steel Plant (ISP) for production of 1.4 MTPA carbon and

alloy steel along with stainless steel in Koppal district of Karnataka.

The Environmental Clearance (EC) for the proposed expansion was accorded by Ministry of

Environment, Forest & Climate Change (MoEFCC) vide F. No. J-11011/172/2007-IA II(I) on 19th

January 2016.

The timeline for obtaining EC was as follows:

ToR prescribed during 23rd meeting of Reconstituted Expert Appraisal Committee (EAC) held on

18th-19th September, 2014

Public Hearing conducted on 28th march 2015

Final EIA/EMP report submitted vide application dated 26th June, 2015.

EC granted vide F. No. J-11011/172/2007-IA II(I) on 19th January 2016

1.2 Nature of the project proposed

KSL had proposed the expansion of their Integrated Steel Plant (ISP) for production of 1.4 MTPA carbon

and alloy steel along with stainless steel.

Details about the nature of the project is as below:

1.2.1 Products with capacities include:

Crude Steel - 1.40 MTPA

Saleable Steel - 1.36 MTPA

o Long Products - 1.26 MTPA (Billets, blooms, rounds & rolled Products)

o Cast Ingots - 0.10 MTPA

1.2.2 Production Units:

Sl.

No.

Production

Unit

Configuration & Production capacities as per EC dated

19th January 2016

1 Coke Oven Plant 2 x 45 ovens Coke Ovens and By-Products Recovery Plant (COBP) 0.6 MTPA Gross Coke

2 Sinter Plant Pellet Plant

1 x 33 sq m + 1 x 130 sq m 1.79 MTPA 1 x 1.2 MTPA

3 Blast Furnace

1 x 750 cu m + 2 x 250 cu m + 1 x 350 cu m 1.64 MTPA Hot Metal

4 DR Plant 1 x 0.5 MTPA

Page 5: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

4

Sl.

No.

Production

Unit

Configuration & Production capacities as per EC dated

19th January 2016

5 Pig casting machine 40 TPH & 180 TPH

6 Lime/dolo Calcining Plant

2 x 300 TPD 0.17 MTPA Calcined Lime; 0.05 MTPA Calcined Dolo

7 Steel Melt Shop BOF - 2 x 60 T LF - 3 x 60 T IF - 1 x 50 T VD/RH - 2 x 60 T EAF - 1 x 60 T AOD - 1 x 60 T 1.46 MTPA Liquid Steel

8 Casting units Continuous Caster- Billet cum bloom cu m round caster Billet cum bloom caster Bloom cum round caster Ingot Casting 1.4 MTPA Crude Steel

9 Rolling Mill Bar & Wire Rod Mill 0.49 MTPA Bars, flats & Wire Rods

Heavy bar Mill 0.31 MTPA Rounds & RCS

Bar & Rod Mill 0.34 MTPA Bars & Rods

Annealing Furnace - 60 TPH Tempering Furnace - 50 TPH

10 Air Separation Plant 600 TPD (BOO basis)

11 Power Plant BF gas based - 8 MW CDQ - 6 MW (5.4 MW production capacity) TRT - 3.65 MW (3.28 MW production capacity)

Requirement of water for the expansion of ISP was estimated to be about 3.14 MGD. The total

requirement of water for existing as well as the expansion would be about 4.68 MGD which would be

drawn from Tungabhadra, at a distance of 5.2 km in south western direction of the plant site.

Total power requirement for the expansion of ISP was about 128 MW, proposed to be met through in-

plant generation and drawl of power from KPTCL grid

The capital cost was estimated to be Rs.5531 Crore and the scheduled completion period was 60

months from Go-ahead.

1.3 Description of Coke Plant & DRI included in 1.4 MTPA EC

As per the EC, KSL had proposed to install by-product Recovery type coke ovens with the following

configuration:

2 X 45 ovens, 4.3 m tall

Stamp charging

0.6 MTPA gross coke capacity

CDQ

Further, KSL had proposed 1 x 0.5 MTPA DR Plant based on Coke Oven Gas (COG) as reductant.

Page 6: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

5

1.4 Proposed Amendment

At present KSL proposed amendment in Coke Oven Configuration as follows:

a. Phase 1: 0.20 MTPA Heat Recovery coke oven with Modified Wet Quenching with 25 MW WHR

Power Plant

b. Phase 2: 0.40 MTPA Heat Recovery coke oven with Modified Wet Quenching with 50 MW WHR

Power Plant

Further, KSL requests for deletion of 1 x 0.5 MTPA DR Plant based on Coke Oven Gas (COG) as

reductant.

Detailed table with Product Configuration & Capacities of Existing EC & Proposed Amendment is given

in section 2.1 of this document.

1.5 Scope of the study:

1.5.1 Technical aspects of non-recovery with heat recovery:

KSL has decided to set up Heat-Recovery Type Coke Oven with stamp charging – technical aspects of

which are given below:

In stamp charge heat recovery type coke making process with waste heat recovery boiler, the organic

matter of the coal are combusted completely within the oven. No additional fuel is required for heating

the bottom and walls of the ovens for the process of Carbonization.

Carbonization in heat recovery type coke ovens is slow and the coke produced is hard & lumpy and

suitable for use as metallurgical coke in blast furnaces. The hot flue gas from carbonization is used to

generate power through high pressure steam in Waste Heat Recovery Boilers (WHRB). There is no

provision for recovering gas.

The basic tentative design parameters are as presented in following table:

Item Unit Phase- 1 Phase-2 Total

No. Of Ovens Nos. 11 11 11

Coke oven blocks (max)

Nos. 4 8 12

Total number of ovens

Nos. 44 88 132

Tentative Coal Cake size:

Length mm 12,200 12,200 12,200

Width mm 3,600 3,600 3,600

Height mm 1,100 1,100 1,100

Coal charged per oven

Dry T 48 48 48

Bulk density(stamped coal)

Dry T/ m3

0.9-1.1 0.9-1.1 0.9-1.1

Normal Carbonisation time

Hrs 65-67 65-67 65-67

Page 7: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

6

Yield (Dry coal to Dry Coke)

% ~70 - 74% ~70 - 74% ~70 - 74%

Days Operational

Days 365 365 365

Hrs/Day Operational

Hrs/ Day 24 24 24

Coke Production Dry TPA 200,000 400,000 600,000

The targeted tentative Coke quality is as below:

Moisture, Max % 5.00%

Ash (dry basis), % 11.5 - 12.5%

Volatile matter (dry basis), % 1 - 1.5%

Sulphur, % (Max) 0.60%

M40 % (Min) 80.00%

M10 % (Max) 8.00%

CSR, % 62 - 64%

CRI, % 23-26%

BF Grade (including Nut Coke)

6 - 80 mm

Foundry Grade > 80 mm

Coke Fines < 6 mm

Further, as the batteries of Heat Recovery Type Coke Oven operate under negative pressure and, hence,

there is no fugitive emission during operation.

1.5.2 Baseline data of EIA report submitted by KSL & post project monitoring data

The company had collected baseline data for the period of October 2014 - January 2015 during EIA

report preparation. This is elaborated in the report in section 3.1

As KSL has not implemented the project, Post Project monitoring data is not available.

However, the company regularly submits monthly monitoring data to KSPCB for its operating plant.

This is elaborated in this report in section 3.3

1.5.3 Recent baseline status of recent EIA study appraised by Ministry for the adjoining project

of M/s Mukand Ltd1

In Jun 2018, M/s Mukand Ltd in its EIA report has submitted baseline data for the period of Apr 2016 – June 2016. As M/s Mukand Ltd’s proposed Rolling Mill (for which its EIA report was prepared) is adjacent to KSL’s existing plant and expansion project location, this baseline data is used the latest

version of the baseline data prepared for the area.

The said baseline data from M/s Mukand Ltd is elaborated in this report in section 3.5

1 Ref. link: http://environmentclearance.nic.in/writereaddata/EIA/23062018F4O8I4KSAnnexure-EIAEMPdocuments.pdf

Page 8: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

7

2 - PROJECT DESCRIPTION

2.1 Changes proposed to be made in Existing EC of 1.4 MTPA Expansion Project

As explained above, KSL proposes change in Coke Oven Configuration as follows:

0.20 MTPA Heat Recovery coke oven with Modified Wet Quenching in Phase-1 with 25 MW

WHR Power Plant

0.40 MTPA Heat Recovery coke oven in Phase-2 with 50 MW WHR Power Plant (Note: Type of

quenching will be decided based on prevailing best available technology and techno-economic

feasibility at that point of time)

Further, KSL requests for deletion of 1 x 0.5 MTPA DR Plant based on Coke Oven Gas (COG) as

reductant.

Following table delineates the changes proposed in Environment Clearance:

Page 9: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

Sl. No. Production

Unit

Configuration as per EC dated

19th January 2016

Proposed Configuration

for amendment of EC

Final Configuration

1. Coke Oven Plant

2x 45 ovens 0.6 MTPA Gross Coke By product Recovery type Coke ovens, CDQ

Phase 1: 0.20 MTPA Heat

Recovery coke oven with

Modified Wet Quenching

Phase 2: 0.40 MTPA Heat

Recovery coke oven with

Modified Wet Quenching

Phase 1: 0.20 MTPA Heat

Recovery coke oven with

Modified Wet Quenching

Phase 2: 0.40 MTPA Heat

Recovery coke oven with

Modified Wet Quenching

2. Sinter Plant Pellet Plant

1 x 33 sq m + 1 x 130 sq m 1.79 MTPA Product Sinter 1 x 1.2 MTPA

No Change 1 x 33 sq m + 1 x 130 sq m 1.79 MTPA Product Sinter 1 x 1.2 MTPA

3. Blast Furnace 1 x 750 cu m + 2 x 250 cu m + 1 x 350 cu m 1.64 MTPA Hot Metal

No Change

1 x 750 cu m + 2 x 250 cu m + 1 x 350 cu m 1.64 MTPA Hot Metal

4 DR Plant 1 x 0.5 MTPA Deletion of DR Plant Deletion of DR Plant

5 Pig casting

machine

40 TPH

180 TPH

No change 40 TPH

180 TPH

6 Lime/dolo

Calcining

Plant

2 x 300 TPD

0.17 MTPA Calcined Lime; 0.05

MTPA Calcined Dolo

No change 2 x 300 TPD

0.17 MTPA Calcined Lime; 0.05

MTPA Calcined Dolo

7 Steel Melt

Shop

1.46 MTPA Liquid Steel

BOF- 2 x 60 T No change BOF- 2 x 60 T

LF-3 x 60 T LF-3 x 60 T

IF- 1 x 50 T IF- 1 x 50 T

VD/ RH- 2 x 60 VD/ RH- 2 x 60

EAF – 1 x 60 T EAF – 1 x 60 T

AOD – 1 x 60 T AOD – 1 x 60 T

8 Casting Units Continuous Caster- Billet cum No Change Continuous Caster- Billet cum

Page 10: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

1

Sl. No. Production

Unit

Configuration as per EC dated

19th January 2016

Proposed Configuration

for amendment of EC

Final Configuration

bloom cum bloom cum round

caster- 1 x 3 strand

Billet cum bloom caster- 1 x 3

strand

Bloom cum round caster- 1 x 2

strand

Ingot Casting

1.4 MTPA Crude Steel

bloom cum bloom cum round

caster- 1 x 3 strand

Billet cum bloom caster- 1 x 3

strand

Bloom cum round caster- 1 x 2

strand

Ingot Casting

1.4 MTPA Crude Steel

9 Rolling Mill Bar & Wire Rod Mill 0.49 MTPA

Bars, flats & Wire Rods

No change Bar & Wire Rod Mill 0.49 MTPA

Bars, flats & Wire Rods

Heavy bar Mill 0.31 MTPA

Rounds & RCS

Heavy bar Mill 0.31 MTPA Rounds

& RCS

Bar & Rod Mill 0.34 MTPA Bars

& Rods

Bar & Rod Mill 0.34 MTPA Bars &

Rods

Annealing Furnace

-60 TPH

Tempering Furnace

-50 TPH

Annealing Furnace

-60 TPH

Tempering Furnace

-50 TPH

10 Air

Separation

Plant

600 TPD (BOO basis) No changes 600 TPD (BOO basis)

11 Power Plant BF gas based-8 MW

CDQ- 5.4 MW

TRT- 3.65 MW

BF gas based – No change

TRT – No change

Power plant –

BF gas based – 8 MW

TRT – 3.65 MW

Power plant –

Page 11: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

2

Sl. No. Production

Unit

Configuration as per EC dated

19th January 2016

Proposed Configuration

for amendment of EC

Final Configuration

Phase 1: 25 MW WHR PP

Phase 2: 50 MW WHR PP

Phase 1: 25 MW WHR PP

Phase 2: 50 MW WHR PP

Page 12: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

3

2.2 Basic steel plant /process flow chart (as per EC granted) with material balance

Page 13: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

4

2.3 Change in process flow sheet for the proposed coke plant

Page 14: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

5

2.3.1 Brief description of Recovery Type coke manufacturing with schematic drawings

At the start of coke manufacturing processes, the selected coals are screened, crushed to less

than 3 mm and blended based on their petrography for the production of a high-quality coke.

The coal blend is charged into the coke oven, and coke is formed by the destructive distillation

of coal at temperatures of around 1,100 deg C and higher.

At the end of the coking cycle, the hot coke is pushed from the oven into a quench car, which

transports the hot coke for its quenching and stabilizing.

Quenching is performed with either water (wet quenching) or nitrogen (dry quenching), after

which the product coke is transported to the blast furnace (BF) or stockpile.

Following figure shows a simplified conceptual coke-making flow sheet (for By-product as well

as Heat recovery type):

In the by-product recovery coke technology, coal is carbonized in by-product ovens involving

indirect heating of the coal mass. In this method coal is carbonized in the absence of air and heat

is supplied to the coal mass by burning fuel gas in the combustion chamber adjacent to the

coking chamber. The volatile matter comes out of the coal mass after attaining the required

temperature which subsequently cooled at different stages for the recovery of the by-products

in the by-product plant. The coke ovens which are based on this technology are known as by-

product coke ovens.

By-product recovery coke ovens operate under positive pressure.

Following schematic shows By-product recovery coke oven operating:

Page 15: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

6

Further, to extract usable by-products from the Coke Oven Gas, an elaborate by-product

recovery plant is needed. A schematic of the same is as below:

Page 16: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

7

2.3.2 Brief description of Non-Recovery Type coke manufacturing with schematic

drawings

The coal preparation method in Non-recovery coke-making is same as that of Recovery type

coke-making.

In the heat recovery coke technology, the heat is generated by the combustion of volatile matter

which is then penetrated into the coal mass through radiation from the oven top and also by

conduction from oven bottom & walls. The volatile matter in the coking coal evaporates have

rich combustibles. These combustibles present in the waste gas are burned and hot flue gas is

generated (which has high sensible heat). This is used for the production of steam and

generation of power

Heat recovery type coke ovens operate under negative pressure

Following diagram shows the schematic of a typical (horizontal type) Heat recovery Coke Oven:

The following diagram shows the overall working of Heat Recovery coke oven:

Page 17: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

8

As for quenching of hot Coke, there are three proven available processes for quenching of hot

coke as under:

1. Coke Wet Quenching (CWQ) :

The standard technique that is applied worldwide is the wet quenching of coke,

where quenching of hot coke is performed by spraying water on the hot coke. Water with

coke particles is then collected, settled, cooled and recycled for quenching with fresh make-

up water

2. Coke Dry Quenching (CDQ)

Coke Dry Quenching (CDQ) is an alternative to the traditional wet quenching of the coke.

Coke is cooled using an inert gas in dry cooling plant, instead of cooling by sprayed water

However, CDQ is only feasible for Coke Ovens with capacities more than 0.8 MTPA

3. Modified Wet Quenching

There exists a relatively new method of CWQ known as Modified Wet Quenching (also

known as coke stabilisation quenching), in which wet quenching of coke is done water spray

from top nozzles. The water vaporises immediately after coming in contact with hot coke.

The steam so generated is cooled and cleaned with the help two scrubber levels and two

baffle systems.

The water coming out from Modified Wet Quenching process will be taken to the multi-stage

settling pond where the coke particles are allowed to be separated and the clean water from

the decantation chamber is re-cycled with fresh make-up water.

The settled coke particles are taken out by crab bucket, air dried to reduce the moisture

content and then sent to other part of the plant (normally Sinter Plant) for recycling.

Given above background, KSL has opted for Modified Wet Quenching process.

Page 18: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

9

2.4 Basic material balance for Recovery and Non-recovery coke plant for rated capacity of 0.6 MTPA

2.4.1 Material Balance diagram for Recovery Type 0.6 MTPA Coke Oven (As per PFR & EIA report submitted for Existing EC):

Page 19: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

10

2.4.2 Material Balance diagram for Non-Recovery Type 0.6 MTPA Coke Oven (As proposed):

Page 20: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

11

2.5 Water balance flow chart

2.5.1 Water balance as per Existing EC:

2.5.2 Water balance for Proposed amendment in EC:

As shown in the diagram above, the total revised water requirement for the proposed project for 1.4 MTPA crude steel productions would be about

2.76 MGD (523cum/hr).

Page 21: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

12

Required water would be drawn from Tungabhadra River which is at a distance of 5.2 km in south west direction of the site. Water withdrawal

permission from Tungabhadra Board, Govt. of Karnataka is available with KSL – 4.8 MGD (909 cum/hr). Out of 909 cum/hr, 292 cum/hr water

required for the existing plant. Balance 617 cum/hr are available for the proposed expansion against a requirement of 523 cum/hr. No additional

water withdrawal permission required for the proposed expansion.

Following table shows the detailed calculation of revised water requirement:

MGD M3/ Day M3/ Hr

As per Existing EC Total Make-Up water req. (Exi + Expansion)

4.68 21,288 887

Less: COBP 0.68 3,090 129

Less: DRI 0.24 1,080 45

Add: CO HR 0.26 1,184 49

Add: WHR PP 0.24 1,080 45

Add: Buffer 0.04 167 6.96

Revised Make-Up water requirement

4.30 19,548 815

Existing plant requirement 1.54 7,008 292

Revised EC Facilities 2.76 12,504 521

Water Drawal permission 4.80 21,821 909

Page 22: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

13

2.6 Comparison between Non-Recovery and By-Product Recovery Type Coke

Oven

Item Non-Recovery

(Heat Recovery)

By-Product Recovery

(as per Existing EC

configuration)

Type of Battery Generally Horizontal Vertical

ovens available

All Vertical

Area Requirement More Less

Coke Quality Good Good

Coke Mean Size 55mm-60mm 45mm-50mm

Coke Yield 72%-75% 74%-76%

Process Coal burnt partially to supply

heat for carbonization

Walls are heated separately by

in-built burners. Fuel used

either coke oven gas/lean gas

Burning loss 1%-2.5% ~0.5%

Units installed Batteries, Waste Heat boilers,

Turbines,

Batteries, By-product plant,

Implementation period 18-24 months 36 – 40 months

Oven Pressure -3mm to -5mmwg 7mm to 14mmwg

Machines required Pusher Machines, Charge car, Quench car stamping machine

Pusher car, charge car transfer car , quench car, stamping machine

Power Generation from flue gasses

Possible to recover waste heat from flue gasses

Possible to generate power from Coke oven gas

Fugitive emission Nil Gadgets & specialized techniques required for control

Pushing/Charging emission

Low Substantial. Additional gadgets & specialized techniques required.

Oven construction Major Fireclay, minor silica Major silica, minor fire clay

Effluent generation Nil Generation of phenolic effluent containing cyanide, which requires extensive treatment in BOD plant

Impact on Air:

Emissions from

Batteries

Leakage from doors, lids, off take & others (Max %) • Leakage from Door

– 5 (PLD) • Leakage from

Charging lid – 1 (PLL)

• Leakage from AP covers – 4 (PL0)

Nil (As ovens operate under negative pressure)

Negligible Negligible

Yes, Emission of dust and PAH (BaP) (As ovens operate under positive pressure) Additional equipment and specialized techniques adopted to keep emissions within Regulatory norms

Yes Yes

Pushing emission PM during coke pushing – 5gm/ton coke

Charging emission

Page 23: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

14

Charging emission (seconds/charge) – 16 (with HPLA)

Emissions from Stack

Flue Gasses CO2,NOx, SO2 Desulphurization of waste gas done before venting out

CO2,NOx, SO2, Sulfur is recovered in Coke oven gas using ‘Claus Process’ and sold off

Estimated controlled emission to air

Within prescribed CPCB Standards for Iron & Steel Plant (2012) PM = 7.8 Kg/hr SO2= 19.5 Kg/hr NOx= 58.5 Kg/hr

Within prescribed CPCB Standards for Iron & Steel Plant (2012) PM =34 Kg/hr SO2=8.5 Kg/hr NOx=44 Kg/hr

Net Carbon Footprint (0.6 MTPA gross coke)

92,258 TPA 244,263 TPA

Green Pushing Avoided, because of clear visibility inside oven

Often possible when coke is pushed before thermal distillation is complete. Emission of benzene and HAP takes place

Liquid Waste

Waste water from primary gas cooling (Max values: pH – 6 - 8.5 TSS - 100 mg/l BOD 3 – 30 mg/l COD – 250 mg/l O & G – 10 mg/l

Cyanide as CN- - 0.2

mg/l Phenol – 1.0 mg/l)

No process waste water generated as by-products not required

Effluent containing cyanide & phenol and treated in BOD plant. The treated water from BOD plant would still contain cyanide & phenols, the outlet concentration of which should conform to the Effluent standards

Waste water from equipment cooling

Waste water is treated and reused. Waste water is treated and reused.

Solid Waste

Coal Tar sludge & BOD sludge

No generation Mixed with feed coal and recycled

2.7 Brief on demonstrated experience worldwide

Through literature survey, it is found that Non-Recovery type (or Heat Recovery type) Coke

Ovens are found more environmentally friendly.

Excerpts of opinions regarding the same have been given below:

(Mentioned reference reports can be provided on request)

1. “With respect to emission, there are two major advantages of non-recovery process: 1)

The ovens operate under negative pressure which eliminates leaks from doors, lids and

offtakes and 2) waste water and solid wastes associated with by-product recovery plants are absent”

Page 24: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

15

(National Emission Standards for Hazardous Air Pollution (NESHAP) for Coke Ovens;

United States Environmental Protection Agency; EPA-453/R-01-006 February 2001,

Final Report)

2. The U.S.Environmental Protection Agency recognizes the heat-recovery process as

meeting the Maximum Achievable Control Technology (MACT)

(Presented at AISTech 2010 – The Iron and Steel Technology Conference and Exposition,

Pittsburgh - Presented at AISTech 2010 – The Iron and Steel Technology Conference and

Exposition, Pittsburgh)

3. “That means , in practise, that in USA, the non-recovery technology is the only one,

which is allowed by the US EPA for the new greenfield plants because of the prevailing

negative pressure and consequently prevention of leaks at the ovens” - Environmental

Control and Emission Reduction for Coking Plants

(By: Michael Hein and Manfred Kaiser- DMT GmBH and Co.KG, Coke Making Technology

Division, Essen, Germany)

4. “The non-recovery/heat recovery oven batteries are expanding in Australia, Brazil,

China, Colombia, India and the USA, because they demand smaller investment and they

are less polluting, because of the operation with negative pressure.

(Jorge Medias, Metallon, San Nicolas, Buenos Aires, Argentina and Mariano Cordova-

Independent Consultant, San Nicolas, Buenos Aires, Argentina.) - AISTech 2011

Proceedings, Vol -1)

5. “These non-recovery coke ovens complied with stringent pollution control regulations.

These non-recovery ovens are the heat recovery ovens since they are used not only for

production of coke, but also for generation of power by means of waste heat recovery.

Hence, the heat recovery type of coke ovens is energy efficient and environment friendly”

(Comparison of By-Product coke oven and Heat Recovery Coke Oven – Satyendra; Feb

15, Ispat Digest, Ispat Guru)

Page 25: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

16

3 - BASELINE ENVIRONMENT

3.1 Baseline Air Environment as per the EIA appraised for earlier KSL’s Existing EC

The specific station wise recorded ambient air quality (AAQ) values for the monitoring period

(October 2014 - January 2015) are presented in the Table below:

Parameters Code Monitoring Locations Direction

from site

Distance

from site,

km

Air

A1 Ginigera village N 0.7 A2 Hirebagnal village S 2.3 A3 Kunikera village SW 5.7 A4 Tanakanakal village NW 9.3 A5 Guddanahalli village NE 4.6 A6 Budhguppa village NE 8.7 A7 Hosakankapur village E 0.4 A8 Hosaningapur village SE 7.5

Table: Ambient Air Quality in Koppal Study Area:

Station

Code

Location Monitored

values

Max Min Average

A1 GINIGERA VILLAGE

PM10 94.7 70.8 84.2

PM2.5 51.3 37.0 43.8

SO2 11.2 7.4 8.8

NOX 39.2 25.0 33.5

CO (8 hrs) 1650 460 930

O3 (8 hrs) 36.5 <10.0

A2 HIRE BAGHNAL

VILLAGE

PM10 96.8 67.4 84.8

PM2.5 50.2 37.1 43.8

SO2 11.3 7.5 8.6

NOX 40.9 27.2 33.7

CO (8 hrs) 1680 450 948

O3 (8 hrs) 38.5 <10.0

A3 KUNIKERI VILLAGE

PM10 91.4 67.4 80.1

PM2.5 59.8 38.6 46.0

SO2 12.9 7.2 8.5

NOX 42.1 5.0 32.1

CO (8 hrs) 1620 380 860

O3 (8 hrs) 35 <10.0

A4 TANAKANAKAL

VILLAGE

PM10 88.5 58.9 75.0

PM2.5 45.6 32.8 38.8

SO2 8.2 7.1 7.5

NOX 30.0 21.8 24.9

CO (8 hrs) 680 <10.0

O3 (8 hrs) <10.0

A5 GUDDANAHALI

VILLAGE PM10 95.3 72.1 83.9

PM2.5 52.0 38.8 44.7

Page 26: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

17

Station

Code

Location Monitored

values

Max Min Average

SO2 8.4 7.2 7.7

NOX 28.3 21.7 24.9

CO (8 hrs) <100.0

O3 (8 hrs) <10.0

A6 BUDHGUPPA VILLAGE

PM10 86.8 60.9 71.9

PM2.5 43.7 27.9 36.1

SO2 7.6 7.1 7.3

NOX 26.7 21.7 23.7

CO (8 hrs) <100.0

O3 (8 hrs) <10.0

A7 HOSA KANKAPUR

VILLAGE

PM10 97.1 68.6 82.7

PM2.5 49.5 41.4 45.1

SO2 12.8 7.2 8.3

NOX 38.2 27.0 31.4

CO (8 hrs) 1680 720 1048

O3 (8 hrs) 38.0 <10.0

A8 HOSA NINGAPUR

VILLAGE

PM10 94.7 67.7 83.8

PM2.5 53.2 39.1 46.9

SO2 10.2 7.9 8.7

NOX 42.6 31.2 36.6

CO (8 hrs) 1420 580 935

O3 (8 hrs) 35.0 <10.0

It may be seen that the average concentration (24 hrs) of PM10 and PM2.5 are in the range of

71.9 - 84.8 mcg/cu m and 36.1 - 46.9 mcg/cu m respectively. The SO2 and NOX values are well

within the permissible values as set by NAAQS.

Page 27: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

18

3.2 Post project monitoring data

As KSL has not implemented the said 1.4 MTPA Expansion project, post project monitoring data

is not available.

3.3 KSL’s Existing Plant’s Half Yearly Monitoring Data

As per the Half Yearly (1st Half) Compliance Report of Kalyani Steels Limited, Ginigera Village,

Koppal Taluk & District, Karnataka for April 2018 to September 2018, the baseline data for AAQ

and Noise are presented below:

Page 28: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

19

Page 29: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

20

3.4 Baseline Soil, Water and Noise as per the EIA appraised for earlier KSL’s Existing EC

The monitoring locations for various parameters are presented below.

Parameters Code Monitoring Locations Direction

from site

Distance from

site, km

Soil S1 Tanakanakal village NW 9.3 S2 Budhguppa village NE 7.8 S3 Ginigera village W 0.5

Surface Water

SW1 Intake point of Tungabhadra SE 8.5 SW2 Tawargera village lake N 9.4 SW3 Kukanapalli village pond NE 9.6 SW4 Kerahalli village lake NE 7.2 SW5 Tungabhadra canal in Agalkera village E 6.7 SW6 Reservoir outlet of Tungabhadra

pipeline

E Within premises SW7 Raw water (intake) process make up E Within premises SW8 Ginigera lake N 1.5

Ground Water

GW1 Ginigera village - Tubewell NW 0.5 GW2 Hirebagnal village - Tubewell S 5.6 GW3 Kunikera village - Borewell SW 5.7 GW4 Tanakanakal village - Tubewell NW 9.3 GW5 Guddanahalli village - Tubewell NE 4.6 GW6 Agalkera village - Tubewell E 7.3 GW7 Hosakankapur village - Borewell E 0.4 GW8 Hosaningapur village - Tubewell SE 7.5

Noise

N1 Hospet Steels Ltd, Main gate N 0.1 N2 Kirloskar Ferrous Industries,

Bevinahalli

E 3.6 N3 Koppal District Hospital W 8.1 N4 Primary School, Kunikera village SW 5.7 N5 Guddanahali village NE 4.6 N6 Hosakankapur village E 0.5 N7 Koppal market area W 9.7 N8 Ginigera Market NW 0.5

Page 30: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

21

The soil monitoring data for the period October 2014 - January 2015 is presented below:

Table: Soil Quality in Koppal Study Area

The soil in the study area is slightly blackish in colour and clayey in texture. The soil is also

slightly basic in nature & rich in calcium. The fertility of soil is average due to low moisture

content and mediocre concentrations of nitrogen, potassium and organic carbon. Iron content

varies from 980 mg/kg to 1,280 mg/kg. The concentration of other heavy metals is well below

the acceptable range.

Key Parameters

Tanakanakal

village(S1)

Budugumpa

village (S2) Project site (S3)

Physical:

Colour Slightly Blackish Slightly Blackish Slightly Blackish

pH (1:2) 7.72 7.68 7.6

Alkanity/Acidity Slightly Basic Slightly Basic Slightly Basic

Soil Texture Clay Clay Clay

Sand (%) 20 30 30

Silt (%) 20 25 20

Clay (%) 60 45 50

Hydraulic conductivity (cm/sec.) 1.65 x 10-3 1.60 x 10-3 1.56 x 10-3

Bulk Density (gm/cc) 1.36 1.3 1.26

Moisture (%) 25 18 12

Porosity (%) 56 46 48

Infiltration rate(cm/hrs) 0.26 0.23 0.2

Chemical:

Available N2 (mg/kg) 280 236 180

Available P2O5 (mg/kg) 120 90 42

Available K2O (mg/kg) 750 620 480

Chloride (mg/kg) 712 820 925

Sulphate (mg/kg) 112 83 210

Sodium absorption ratio (SAR) 4.71 5.7 6.18

Available Organic Carbon (gm/kg) 3.2 2.5 1.2

Calcium (mg/kg) 3182 2386 2580

Magnesium (mg/kg) 1280 850 950

Iron (mg/kg) 980 1128 1280

Copper (mg/kg) 10.5 9.5 10.8

Lead (mg/kg) <3.0 <3.0 <3.0

Chromium (mg/kg) <0.20 <0.20 <0.20

Microbial Population (No./ gm) 2.8 x 103 3.6 x 103 1.6 x 103

Page 31: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

22

Surface Water Quality monitoring data for the period of October 2014- January 2015 is

presented below:

Table: Surface Water Quality in Koppal Study Area

Parameters SW1 SW2 SW3 SW4

Physical

Odour (TON) No Odour No Odour No Odour No Odour

Temperature °C 27 26.7 25.67 25.33

Total Dissolved Solids (mg/l) 128.3 290.7 286.00 281.00

Total Suspended Solids (mg/l) 12.7 12.8 13.90 14.67

Chemical (mg/l)

pH 7.69 7.98 8.04 8.10

Total Hardness 38.00 114.67 101.33 114.00

Dissolved Oxygen 5.93 5.47 5.87 5.93

BOD at 270C for 3 days 5.00 8.33 5.67 5.67

COD 19.53 30.90 22.87 17.83

Oil & Grease <1.0 <1.0 <1.0 <1.0

Salinity (ppt.) Nil Nil Nil Nil

Kjeldahl Nitrogen 4.00 8.83 4.73 6.03

Chloride 19.95 31.44 34.34 39.82

Sulphates as SO4 17.50 25.42 28.33 31.82

Bicarbonate 37.74 100.94 99.96 106.30

Phosphate 0.30 0.30 0.31 0.58

Calcium 10.69 28.85 24.58 26.19

Magnesium 2.72 10.24 9.60 11.68

Sodium 15.00 37.50 41.00 42.33

Manganese <0.03 <0.03 <0.03 <0.03

Zinc 0.07 0.09 0.07 0.13

Iron 0.43 0.59 0.93 1.04

Chromium (Total) <0.2081 <0.2081 <0.2081 <0.2081

Chromium (Hexavalent) <0.01 <0.01 <0.01 <0.01

Bacteriological (CFU/100ml)

Total Coliform 630.0 913.3 560.00 733.33

Faecal Coli 283.3 450.0 240.00 330.00

Page 32: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

23

Table: Surface Water Quality in Koppal Study Area

Parameters SW5 SW6 SW7 SW8

Physical

Odour (TON) No Odour No Odour No Odour No Odour

Temperature °C 25.3 26 26.3 25.67

Total Dissolved Solids (mg/l) 115.3 122 127 210.33

Total Suspended Solids (mg/l) 16.3 12.7 <10 18.53

Chemical (mg/l)

pH 7.79 7.88 8.19 8.08

Total Hardness 52.67 46.67 47.33 54.00

Dissolved Oxygen 5.53 5.93 5.67 5.27

BOD at 270C for 3 days 7.00 4.67 6.33 8.67

COD 27.73 14.63 29.33 32.67

Oil & Grease <1.0 <1.0 <1.0 <1.0

Salinity (ppt.) Nil Nil Nil Nil

Kjeldahl Nitrogen 5.53 3.67 3.57 8.20

Chloride 25.56 24.82 22.29 18.57

Sulphates as SO4 22.33 21.25 22.17 29.08

Bicarbonate 39.20 38.39 35.09 116.39

Phosphate 0.29 0.14 0.16 0.60

Calcium 13.90 12.56 12.29 14.43

Magnesium 4.32 3.68 4.00 3.99

Sodium 13.50 15.50 13.67 36.83

Manganese <0.03 <0.03 <0.03 <0.03

Zinc 0.21 0.10 0.18 0.11

Iron 0.88 0.31 0.94 3.23

Chromium (Total) <0.2081 <0.2081 <0.2081 <0.2081

Chromium (Hexavalent) <0.01 <0.01 <0.01 <0.01

Bacteriological (CFU/100ml)

Total Coliform 783.3 650.00 576.00 920.00

Faecal Coli 380.0 276.67 253.33 526.67

The total hardness of all surface streams as reported in the aforementioned Tables ranges from

38 - 114.7 mg/l. The average DO level for all surface streams ranges between 5.3 - 5.9 mg/l

whereas average BOD level ranges between 4.7 - 8.7 mg/l. Total coliform count ranges from 560

- 920 CFU/100 ml across various surface water sampling locations. It has been observed that

the Faecal coliform is also on the higher side and hence, not fit for human consumption without

disinfection.

Page 33: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

24

Ground Water Quality monitoring data for the period of October 2014- January 2015 is

presented below:

Table: Ground Water Quality in Koppal Study Area

Parameters GW1 GW2 GW3 GW4

Physical

Colour(Hazen) 1 1 1 1

Odour Odourless Odourless Odourless Odourless

Taste Acceptable Acceptable Acceptable Acceptable

Turbidity (NTU) 1.7 1.8 2.7 2.9

Total Dissolved Solids (mg/l) 689.3 1027.8 2935.8 1567.2

Temperature (°C) 26.2 26.7 26.7 26.7

Chemical (mg/l)

pH 7.22 7.36 6.71 7.26

Alkalinity 248.4 426.3 510.5 287.0

Total Hardness 210.7 314.7 1506.7 716.7

Residual Chlorine <0.01 <0.01 <0.01 <0.01

Nitrate 4.60 5.83 6.50 6.70

Fluoride <0.02 <0.02 <0.02 <0.02

Phenol <0.001 <0.001 <0.001 <0.001

Total Nitrogen 5.9 7.2 18.2 7.9

Boron <0.1 <0.1 <0.1 <0.1

Chloride 48.50 96.15 897.72 301.50

Sulphate 120.08 89.50 169.67 111.08

Bicarbonate 303.0 520.0 622.9 350.1

Cyanide <0.05 <0.05 <0.05 <0.05

Calcium 61.42 49.70 302.97 200.40

Magnesium 13.76 45.76 136.48 52.00

Manganese 0.07 <0.03 <0.03 <0.03

Zinc 0.76 0.24 0.06 5.58

Aluminium <0.006 <0.006 <0.006 <0.006

Iron 0.43 0.60 0.26 0.92

Chromium (Hexavalent) <0.01 <0.01 <0.01 <0.01

Copper <0.05 <0.05 <0.05 <0.05

Mercury <0.001 <0.001 <0.001 <0.001

Cadmium <0.01 <0.01 <0.01 <0.01

Sodium 103.00 158.00 290.00 54.00

Arsenic <0.01 <0.01 <0.01 <0.01

Lead <0.03 <0.03 <0.03 <0.03

Bacteriological (CFU/100ml)

Total Coliform nil nil nil nil

Faecal Coliform nil nil nil nil

Page 34: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

25

Table: Ground Water Quality in Koppal Study Area

Parameters GW5 GW6 GW7 GW8

Physical

Colour(Hazen) 1 1 1 1

Odour Odourless Odourless Odourless Odourless

Taste Acceptable Acceptable Acceptable Acceptable

Turbidity (NTU) 6.6 1.7 2.7 5.1

Total Dissolved Solids (mg/l) 1402.2 896.3 1359.5 758.2

Temperature (°C) 26.7 27.0 26.7 26.8

Chemical (mg/l)

pH 6.90 7.28 7.24 6.81

Alkalinity 319.0 311.7 409.5 181.2

Total Hardness 686.7 390.0 526.7 230.7

Residual Chlorine <0.01 <0.01 <0.01 <0.01

Nitrate 8.77 6.10 6.50 5.37

Fluoride <0.02 <0.02 <0.02 <0.02

Phenol <0.001 <0.001 <0.001 <0.001

Total Nitrogen 10.5 7.5 21.0 6.9

Boron <0.1 <0.1 <0.1 <0.1

Chloride 301.14 136.60 302.75 146.88

Sulphate 116.00 77.25 90.83 122.00

Bicarbonate 389.2 380.3 499.6 181.2

Cyanide <0.05 <0.05 <0.05 <0.05

Calcium 209.75 81.76 82.56 82.83

Magnesium 39.20 44.64 76.96 12.16

Manganese 0.11 <0.03 <0.03 0.10

Zinc 1.91 1.47 0.06 1.90

Aluminium <0.006 <0.006 <0.006 <0.006

Iron 1.52 0.74 0.30 1.73

Chromium (Hexavalent) <0.01 <0.01 <0.01 <0.01

Copper <0.05 <0.05 <0.05 <0.05

Mercury <0.001 <0.001 <0.001 <0.001

Cadmium <0.01 <0.01 <0.01 <0.01

Sodium 81.67 92.33 183.33 101.67

Arsenic <0.01 <0.01 <0.01 <0.01

Lead <0.03 <0.03 <0.03 <0.03

Bacteriological (CFU/100ml)

Total Coliform nil nil nil nil

Faecal Coliform nil nil nil nil

The total hardness (TH) and total dissolved solids (TDS) content in ground water were found to

be in the range 210 - 1,506 mg/l and 689 - 2,936 mg/l respectively at the selected locations as

against the allowable standards of 300 mg/l for TH and

500 mg/l for TDS. Chromium, lead, arsenic and other heavy metals are found to be below

detection limit (bdl).

Page 35: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

26

The recorded Noise level for the period October 2014 - January 2015 is given below:

Table - Recorded Noise Level in Koppal Study Area

Recorded Values (Leq)

Sampling Station

Day Time

Night Time

dB (A) dB (A)

Industrial Area:

Hospet Steels Limited, Main gate 68 61

Kirloskar Ferrous Industries, Bevanalli village. 67 61

Residential Area:

Guddanahali village 52 44

Hosa Kankarpur village 57 46

Commercial Area:

Koppal Market area 64 57

Ginigera Market 62 47

Silence zone:

Koppal District Hospital 61 51

Primary school, Kunikeri village 54 46

In the industrial areas noise level were recorded to be about 68 dB (A) during day time and 61

dB (A) during night as against the Regulatory standard of 75 dB (A) and 70 B (A) respectively.

On the other hand, in the residential areas like Guddanahali & Hosa Kankarpur villages, the day

time Leq were recorded in between 52-57 dB(A) and night time Leq around 46 dB(A) as against

allowable limit of 55 dB(A) and 45 dB(A) respectively. The daytime Leq for sensitive areas like

Koppal District Hospital & Primary school, Kunikeri village was recorded to be between 54-61

dB(A) and 46-51 dB(A) during night, however regulatory stipulations being

50 dB(A) and 40 dB(A) respectively. Thus, both for residential and sensitive areas, both day

time and night time Leq have been recorded to be above the stipulations

Page 36: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

27

3.5 Recent baseline data from M/s Mukand Ltd2 (Generated for period Apr

2016 - June 2016)

The ambient air quality (AAQ) data for the following eight (8) stations for the Monitoring period

1st April – 30th June 2016 as submitted by M/s Mukand Ltd. is present in table 1 & 2 below:

Sample ID Name of the location Distance & Direction Latitude & Longitude

AAQ1 Project Site - 15°20'7.01"N, 76°15'22.58"E

AAQ2 Kanakapur 0.92 km, NNE 15°20'4.24"N, 76°15'38.62"E

AAQ3 Ginigera 2.80 km, NNW 15°21'4.87"N, 76°14'56.70"E

AAQ4 Bevinhalli 3.97 km, ENE 15°20'0.16"N, 76°17'25.36"E

AAQ5 Agalkera 7.30 km, ENE 15°20'19.30"N, 76°19'41.58"E

AAQ6 Halwarti 5.29 km, WSW 15°19'19.21"N, 76°12'36.04"E

AAQ7 Hirekhasankandi 3.75 km, SSE 15°17'58.35"N, 76°16'12.03"E

AAQ8 Allanagar 1.59 km, WSW 15°19'33.93"N, 76°14'44.38"E

2 Ref. link: http://environmentclearance.nic.in/writereaddata/EIA/23062018F4O8I4KSAnnexure-EIAEMPdocuments.pdf

Page 37: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

28

Page 38: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

29

Table: Ambient Air Quality Monitoring Results (24-hour average)

Page 39: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

30

Table: Ambient Air Quality Monitoring Results

Page 40: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

31

The Ambient Noise Quality is presented below:

Page 41: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

32

The ground & surface water quality for the following stations are presented below:

Page 42: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

33

Table: Surface Water Quality Monitoring Results

Page 43: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

34

The total hardness of all surface streams as reported in the aforementioned Tables

ranges from 40 - 112 mg/l. The average BOD level ranges between 6 - 8 mg/l. Total coliform

count ranges from 79 - 140 MPN/100 ml across various surface water sampling locations. It has

been observed that the Faecal coliform is alsoon the higher side and hence, not fit for

human consumption without disinfection.

Page 44: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

35

Table: Ground Water Quality Monitoring Results

Page 45: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

36

Ground water was found to be fit for human consumption only after adequate treatment. The

Total Hardness were found to be in the range of 212 to 690 mg/L at he select locations as

against the allowable standard of 600 mg/L.

Page 46: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

37

The Soil monitoring for the following stations are presented below:

It is observed from the analysis report that taxonomically soils are mostly sandy loam.

pH ranges from 7.5 to 7.70, which means soils are moderately alkaline in nature. Organic carbon

ranges from 1.2 to 3.2mg/kg. Total Kjelhahl nitrogen ranges from 189 to 282 mg/kg.

Page 47: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

38

4 - IMPACT ASSESSMENT

4.1 Results of impact assessment made with respect to Air Environment in the

EIA as per Existing EC

Air dispersion modeling using BREEZE ISC Suite (ISC-ST3) was done to predict the ground level

concentrations (glcs) of respirable suspended particulate matters of size below 10 microns

(PM10), SO2 and NOx respectively, from the emission figures, the site recorded meteorological

recordings and the relative disposition of stacks. The glcs have been interpreted and the relative

impacts for setting up the brown field project have been assessed for various locations in the

study area and presented below.

Table 4-3 - Predicted pollution level of ambient air during Operational stage (24 hrs

average)

Zone outside the

Plant boundary

Pre-project

status

(Baseline)

Predicted

Post-project status

mcg/cu m mcg/cu m ● Up to 2 km PM10 82.7-84.2 88.7-93.2 SO2 8.3-8.8 9.3-11.3 NOx 31.4-33.5 34.4-38.5 ● 2 km to 5 km PM10 83.9-84.8 92.9-96.8 SO2 7.7-8.6 9.2-10.6 NOx 24.9-33.7 28.9-38.7 ● beyond 5 km PM10 71.9-83.8 77.9-86.8 SO2 7.3-8.7 8.3-10.2 NOx 23.7-36.6 26.7-37.6

From the above Table, it appears that though PM10, SO2 and NOx levels in the ambient air during

operation of the plant would rise, but would remain within the allowable limits of PM10, SO2

and NOx of 100 mcg/cu m, 80 mcg/cu m and 80 mcg/cu m respectively as per the latest

Notification on National Ambient Air Quality Standards (NAAQS) by MoEFCC on 16th November

2009.

Page 48: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

39

Fig. - Predicted 24-hrly average glcs of PM10 in mcg/cu m for the proposed expansion to

1.4 MTPA capacity of Steel Plant at Koppal during Winter

0 2000 4000 6000 8000 10000 12000 14000 16000 18000 20000

meters

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

mete

rs

Page 49: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

40

Fig. - Predicted 24-hrly average glcs of SO2 in mcg/cu m for the proposed expansion to

1.4 MTPA capacity of Steel Plant at Koppal during Winter

0 2000 4000 6000 8000 10000 12000 14000 16000 18000 20000

meters

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

me

ters

Page 50: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

41

Fig- Predicted 24-hrly average glcs of NOx in mcg/cu m for the proposed expansion to 1.4

MTPA capacityof Steel Plant at Koppal during Winter

0 2000 4000 6000 8000 10000 12000 14000 16000 18000 20000

meters

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

20000

me

ters

Page 51: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

42

4.2 Absolute emissions calculations for Non-recovery Coke Oven with heat

recovery

The stack data for heat recovery type coke oven is as follows:

4.3 Results of impact assessment made with respect to Air Environment

considering recent baseline data from M/s Mukand Ltd3

Air dispersion modeling using BREEZE ISC Suite (ISC-ST3) was done to predict the ground level

concentrations (glcs) of respirable suspended particulate matters of size below 10 microns

(PM10), SO2 and NOx respectively, from the emission figures, the site recorded meteorological

recordings and the relative disposition of stacks for the revised configuration. The glcs have

been interpreted and the relative impacts for setting up the brown field project have been

assessed for various locations in the study area against the recent AAQ data from M/s Mukand Ltd’s EIA report and presented below.

Table 4-4 - Predicted pollution level of ambient air during Operational stage (24 hrs

average)

Zone outside the

Plant boundary

Pre-project

status (Recent

Baseline)

Predicted

Post-project status

(considering recent

Baseline)

mcg/cu m mcg/cu m ● Up to 2 km PM10 80.36-89 85.36-98 SO2 8.2-9.9 9.7-12.9 NOx 28.13-32.99 29.93-37.99 ● 2 km to 5 km PM10 71.7-87.3 74.7-96.3 SO2 7.89-9.67 9.49-12.87 NOx 24.38-32.24 26.18-35.75 ● beyond 5 km PM10 89 91-95 SO2 9.04-9.24 9.94-10.84 NOx 30.79-32.78 32.49-33.58

From the above Table, it appears that though PM10, SO2 and NOx levels in the ambient air

during operation of the plant would rise, but would remain within the allowable limits of PM10,

SO2 and NOx of 100 mcg/cu m, 80 mcg/cu m and 80 mcg/cu m respectively as per the latest

3 Ref. link: http://environmentclearance.nic.in/writereaddata/EIA/23062018F4O8I4KSAnnexure-EIAEMPdocuments.pdf

Sr.

No.

Plant No. of

Stacks

Stack Code Type of

Flue

Height Exit

Temp

Dia Gas Qty Pollution Loading

SPM SO2 NOx

(m) (°C) (m) (Nm3/hr) mg/Nm3 kg/hr mg/Nm3 kg/hr mg/Nm3 kg/hr

1 Coke Oven Heat Recovery 1 COB#1-1 C 70 200 4.16 140,000 20.00 2.80 50.00 7.00 150.00 21.00

1 COB#2-1 C 70 200 4.16 140,000 20.00 2.80 50.00 7.00 150.00 21.00

1 COB#3-1 C 70 200 4.16 140,000 20.00 2.80 50.00 7.00 150.00 21.00

Page 52: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

43

Notification on National Ambient Air Quality Standards (NAAQS) by MoEFCC on 16th November

2009.

Page 53: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

44

Fig. - Predicted 24-hrly average glcs of PM10 in mcg/cu m for the proposed expansion to

1.4 MTPA capacity of Steel Plant at Koppal for revised configuration

Page 54: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

45

Fig. - Predicted 24-hrly average glcs of SO2 in mcg/cu m for the proposed expansion to

1.4 MTPA capacity of Steel Plant at Koppal for revised coonfiguration

Page 55: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

46

Fig- Predicted 24-hrly average glcs of NOx in mcg/cu m for the proposed expansion to 1.4

MTPA capacityof Steel Plant at Koppal for revised configuration

Page 56: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

47

4.4 Comparison of air dispersion modeling results

The table below presents the comparison between the predictive values of air dispersion

modelling as per existing configuration & revised configuration

Table 4-5 – Comparison of predicted air pollution load (24 hrs average)

Zone outside

the Plant

boundary

Recent

Baseline*

Predicted

Post-project status

(As per Existing EC)

Predicted

Post-project

status

( As per

Proposed

Amendment)

NAAQS

(16th

November

2009)

mcg/cu m mcg/cu m mcg/cu m mcg/cu m

Up to 2 km

PM10 80.36-89 86.36-98 85.36-98 100

SO2 8.2-9.9 9.2-12.1 9.7-12.9 80

NOx 28.13-32.99 31.13-37.99 29.93-37.99 80

2 km to 5 km

PM10 71.7-87.3 80.7-99.3 74.7-96.3 100

SO2 7.89-9.67 9.39-13.67 9.49-12.87 80

NOx 24.38-32.24 28.38-37.24 26.18-35.75 80

beyond 5 km

PM10 89 92-95 91-95 100

SO2 9.04-9.24 9.74-10.04 9.94-10.84 80

NOx 30.79-32.78 31.79-35.78 32.49-33.58 80 *From M/s Mukand Ltd’s EIA report

From the above Table, it appears that PM10, SO2 and NOx levels in the ambient air during

operation of the plant for the existing EC proposal and the revised proposal would remain

within the allowable limits.

4.5 Mitigation measures

4.5.1 By-product Recovery Coke Ovens

There would be HPLA and land based emission control system to capture the fugitive emissions

that would occur during coal charging and coke pushing as envisaged during project conceptual

stage, even then there would be emissions of particulates, volatile organic carbon (VOC) from

door, lids and off-take leakages. Some of the mitigation measures and preventive maintenance

programmes that would enhance reduction of fugitive emission have been outlined below:

Frequent cleaning of goosenecks and the main collecting passages to prevent any

obstruction

Monitoring the pushing force to discover cracks in walls and oxythermic welding of the

cracks and holes

Installation of spring loaded flexible sealing doors has to be explored to minimise door

emissions

Careful cleaning of the door and its frame at each coke push

Exploring use of high pressure water jet door cleaning at intermittent cycles

Page 57: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

48

Checking that the coke mass is fully coked to prevent emissions of VOC and combustible

products

Water sealed ascension pipes

Maintenance of proper temperature profile in the ovens

NOx emission would be due to under-firing of coke oven battery using clean coke oven gas. NOx

would be minimised by controlling excess supply of air, stage supply of combustion air and

waste gas recirculation. During coke pushing there would be particulate emissions from the

battery doors, which would be captured by land based fume extraction system with an

integrated hood on coke transfer machine. The extracted fume would pass through fabric filters

to clean particulate dust and the clean gas would be released into the atmosphere by a stack of

adequate height.

The proposed by-product recovery type coke ovens would be provided with on-main charging

with high pressure liquor aspiration (HPLA) for extraction of oven gas. Leak proof oven doors,

hydraulic door and door frame cleaner, water sealed AP caps and charging and pushing side

emission control device would be provided to control the VOC emission. In order to reduce SO2

emission from coke oven gas, the project envisages desulphurization of COG to a level below

500 mg H2S/N cu m.

4.5.2 Heat-Recovery type Coke Ovens

The ovens are operated under negative pressure (-3mm to -5mm wg), hence there are no

fugitive emissions from doors and other openings. In addition, the volatile matter from coal is

completely combusted inside the oven by introduction of primary, secondary & tertiary air. The

following pollution control measures would be adopted for adhering to the existing regulations

and for cleaner operation:

i) Improved heating control system to ensure no leakage of un-burnt hydrocarbons into the atmosphere through stack.

ii) Maintaining improved draught inside oven for ensuring total combustion of gasses before it is let out into the atmosphere after waste heat recovery in the boilers.

iii) Adequate stack height to ensure proper dispersion.

iv) Arrangement of water sprinkling facility in the yard.

v) Installation of dust suppression system for coal handling unit and dust extraction system for coke screening unit.

vi) Installation of Modified Wet Quenching system with grit arrestor and other accessories, to ensure minimum dust emission.

Wet desulphurisation using lime solution has been envisaged for desulphuring flue gas for the

proposed project. In this process, lime solution is sprayed counter current to the flow of flue gas,

after recovery of sensible heat in WHRB. The oxides of sulphur present in the flue gas, react with

the lime to produce gypsum which settles down at the bottom of the desulphurisation tower.

Page 58: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

49

5 - ALTERNATIVES OF TECHNOLOGY

5.1 Alternatives in comparison to EIA for coke plant

As per the existing EC, KSL had proposed to install by-product Recovery type coke ovens with

the following configuration:

i) 2 X 45 ovens, 4.3 m tall ii) Stamp charging iii) 0.6 MTPA gross coke capacity iv) CDQ

As explained earlier, KSL proposes change in Coke Oven Configuration as follows:

a. Phase 1: 0.20 MTPA Heat Recovery coke oven with Modified Wet Quenching with 25 MW

WHR Power Plant

b. Phase 2: 0.40 MTPA Heat Recovery coke oven with Modified Wet Quenching with 50 MW

WHR Power Plant

Further, KSL requests for deletion of 1 x 0.5 MTPA DR Plant based on Coke Oven Gas (COG) as

reductant.

The salient features of comparison between two types of ovens are presented in the table below:

Table: Comparison between by-product Recovery vs Heat Recovery Type Coke ovens

The Process Heat Recovery By-product Recovery

Type of Battery Generally Horizontal Vertical ovens available

All Vertical

Coke Quality Good Good

Coke Mean Size 55mm-60mm 45mm-50mm

Coke Yield 72%-74% 74%-76%

Process Coal burnt partially to supply heat for carbonization

Walls are heated separately by in-built burners. Fuel used either coke oven gas/lean gas

Burning loss 1%-2% ~0.5%

Units installed Batteries, Waste Heat boilers, Turbines,

Batteries, By-product plant,

Implementation period

18-24months 36-60 Months

Oven Pressure -3mm to -5mmwg 7mm to 14mmwg

Power generation

Possible to recover waste heat from flue gasses

Possible to generate power from Coke oven gas

Capital Cost Less for similar capacity of by-product type (<0.8 MTPA)

More for similar capacity (<0.8 MTPA)

A review with respect to pollution load for by-product type and heat recovery type coke is

presented in the table below.

Page 59: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

50

Heat recovery type By-product recovery type

Air

Fugitive emission

- Leakages from doors, lids, off takes

No leakage since the oven operates under negative pressure and the organic content is completely combusted inside

Yes Emission of dust and PAH (BaP) due to leakages

- Coal charging No Yes

- Coke pushing No Yes

Stack emission

- Under-firing No Emission of PM, SO2 & NOx

- Flue gas from carbonisation

The desulphurized gas after recovery of heat is vented off to the atmosphere. The flue gas would mainly contain CO2 & NOx.

The gas is collected after recovery & desulphurization of by-product and used as fuel and/or to produce power. The flue gases from end users would mainly contain CO2 & NOx and would be vented off through stack at the respective consumer end.

Water

- Wastewater from primary gas cooling

No wastewater stream is generated. There would be generation of wastewater from Modified Wet Quenching coke, which would be treated for removal of suspended solids and recycled back to the system for quenching purpose.

Yes The water used for primary gas cooling mainly contains cyanide & phenol and need to be treated in BOD plant. The treated water from BOD plant would still contain cyanide & phenols, the outlet concentration of which should conform to the Effluent standards laid down in Iron & Steel Notification (GS.R.277(E) dated 31st March,2012)

- Wastewater from equipment cooling

Yes, the wastewater from cooling circuit is treated and reused

Yes, the wastewater from cooling circuit is treated and reused

Solid waste

- Coal tar sludge & BOD sludge

Not generated These sludge are considered hazardous and generally reused by blending with coal feed to the coke ovens leading to accumulation of pollutants like cyanide in the process

The coke pushed out from the oven is around 1050°C to 1100°C. This coke need to be quenched

immediately to prevent combustion of coke. There are two proven processes available for

quenching of hot coke namely Wet Quenching or Dry quenching.

Comparative analysis between Modified Wet Quenching (which is derived from conventional

Wet Quenching) and Dry quenching is presented below.

Items Modified Wet Quenching Dry Quenching

Possible Capacity Possible for all capacities Justifiable above a capacity beyond 0.8 MTPA for obtaining full benefits

of the system

Air Pollution & Baffles for grit arresting required for DE system necessary to control

Page 60: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

51

Emission control of particulate emission particulate emission

Water Pollution Effluent containing coke particles needs recycling after settling. The settled particles are removed with

grab bucket.

No for CDQ operation. DM backwash in WHRB which needs

treatment

Water Consumption Around 0.5ton/ton of coke Nil for CDQ operation. Water for WHRB for power generation.

Burning loss of coke Nil 1%-2%

Execution Period Less More

Operating Principal Simple Complex

Coke Moisture 3% min 0.3%max

Coke Handling Normal Heat resistant belt conveyor Requires elaborate arrangement for preventing dust emission of bone

dry coke.

Storage Can be stored even in the open yard. Highly Hygroscopic. Requires bunkers or silos for coke storage

Fire Hazard No major precautions required Precautions required during storage.

Handling of Breeze/dust

Can be handled by grab crane, /pock lain/loader etc.

Dust is transported pneumatically to storage bunker from where it can be transported in covered wagons

after wetting.

Breeze /Dust Handling

Can be loaded in open wagons/truck for transportation.

Fine dust requires special covered carrier for transportation.

Usage of dust/breeze

Coke breeze from Modified Wet Quenching can be used for sinter

making after drying.

Dust has no use inside integrated steel plant and sold externally.

Maintenance requirement

Simple arrangement. Requires simple maintenance like lubrication

and dusting.

Complicated arrangement. Requires thorough maintenance for smooth

operation regularly.

Coke size Lumpy Smaller due to high soaking.

Manpower Requirement

Nil (Total automation) 6-8 Trained Personnel required for (Total automation).

Additional factors for coke production in Heat Recovery coke ovens are as follows:

1. Heat Recovery type ovens offsets the CO2 generation by generating steam and subsequently

power in WHRB, which in turn saves fossil fuel use for generating equivalent power for

conventional Thermal PP.

2. Heat Recovery type coke oven produces larger coke size which results in increasing yield of

hard coke.

In CDQ with Heat Recovery coke oven the run-off-oven coke has to be reduced in size in

order to charge into the CDQ chamber. This size reduction involves another process and

increases generation of under size of coke which is not operationally desired.

3. In HR type coke ovens the coking time is around 50-67 hours whereas in recovery type coke

ovens it is from 19-24 hours. Hence, the pushings are more for recovery type ovens which

results in continuity in steam generation and has an effect in pressure as well as

temperature, whereas for HR ovens, in order to keep the continuity of hot coke charge in the

Page 61: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

52

CDQ chamber, the capacity has to be increased beyond 0.8 MTPA for generation of HP

steam.

It may be inferred that heat recovery type coke oven has the following advantages over by-

product recovery type coke ovens:

i. For a production of 0.6 MTPA gross coke, the specific requirement of make-up water for by-product recovery type coke oven is much higher at about 1.9 cum/ton as against 0.72cum/ton of water requirement for heat recovery type

ii. There is no net discharge of waste water as the wastewater generated within the plant is treated and recycled. BOD plant is not required and there would be no cyanide & phenolic effluent generation.

iii. Since non-recovery ovens work under negative pressure, there is no fugitive emission from the ovens during operation.

iv. Organic compounds (VOCs) are fully oxidised during carbonisation, thereby eliminating its release to the atmosphere.

v. Efficient utilisation of energy to produce low cost electrical power reducing sourcing of the same from external sources.

vi. Production of gypsum during desulphurisation, which can be used for various sealing purposes of the oven and may be sold off to cement manufacturers

vii. Reduction of pollution load due to deletion of DRI plant which includes DRI exhaust emission and reduction of pollution load due to raw material and DRI handling in DRI circuit.

Regarding Quenching of hot coke, we wish to submit that CDQ may be considered for minimum

capacity beyond 0.8 MTPA coke production, but in any case there would be some loss of coke

due to burning in air for the purpose of breaking the coke cake into suitable size for charging

into CDQ chamber. It is therefore suggested that for HR type coke ovens, Modified Wet

Quenching (described in 2.3.2 of this document) may be considered as the best possible option.

Page 62: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

53

5.2 Alternatives for pollution control equipment etc.

The pollution control measures for heat recovery coke oven are:

a. Improved heating control system to ensure no leakage of un-burnt hydrocarbons into the atmosphere through stack.

b. Maintaining improved draught inside oven for ensuring total combustion of gasses before it is let out into the atmosphere after waste heat recovery in the boilers.

c. Adequate stack height to ensure proper dispersion. d. Arrangement of water sprinkling facility in the yard. e. Installation of dust suppression system for coal handling unit and dust

extraction system for coke screening unit. f. Installation of Modified Wet Quenching system with grit arrestor and other

accessories, to ensure minimum dust emission. g. Desulphurisation of flue gas with lime spray h. Closed conveyors for all material handling conveyors

The above mentioned pollution control equipment/measures are well established for heat

recovery type coke ovens and are standardized internationally. Therefore, alternatives for these

pollution control equipment were not explored further.

As mentioned earlier, there are two options for coke quenching viz. Coke Dry Quenching and

Modified Wet Quenching. The two options are almost similar with respect to pollution potential

with CDQ having the additional benefit of energy recovery from hot coke. However for the

proposed capacity, as shown earlier, Modified Wet Quenching is the techno-economically

feasible option.

Page 63: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

54

6 - ENVIRONMENTAL MONITORING PROGRAMME

Environmental Monitoring should be carried out during construction and operation phase of the

project.

6.1 Ambient Air Quality Monitoring

Besides on-line monitoring devices fitted with major stacks and effluent discharge, it is

proposed to have continuous monitoring of ambient air quality (AAQ) at four different locations

within the plant area. The pollutants to be monitored would include PM10, PM2.5, SO2, NOx, CO

and O3 as per the MoEF&CC Notification No. GSR 826(E) dated 16th November 2009.

The online stack monitoring devices, continuous AAQ stations and continuous effluent analysis

sensors would be directly connected to the central monitoring system. These permanent AAQ

monitoring locations would be suitably distributed based on coverage factor and exposure to

human settlements. A permanent meteorological station needs to be set up to record dry bulb

temperature, relative humidity, wind speed, wind direction and rainfall. The wind sensor shall

be preferably at 10 m height above the ground without any surrounding hindrances that may

affect free flow of wind.

KSL will monitor ambient air quality with respect to NOx, SO2, Particulate Matter (PM10 and

PM2.5) at around 4-6 locations in and around the project site through a reputed environmental

laboratory recognized by MoEF/NABL. Monitoring will be carried out for a period of 24 hours,

every month during construction phase and quarterly in operation phase.

6.2 Water Quality Monitoring

The water coming out from Modified Wet Quenching process will be taken to the multi-stage

settling pond where the coke particles are allowed to be separated and the clean water from the

decantation chamber is re-cycled with fresh make-up water.

The settled coke particles are taken out by crab bucket, air dried to reduce the moisture content

and then sent to other part of the plant (normally Sinter Plant) for recycling

KSL will monitor this recycled water along with effluent from Guard pond once a month on

parameters such as pH, TSS, TDS, Oil & Grease, Phenolic Compounds, Cynide, Hardness,

Chloride, and Heavy metals (Mercury, Chromium, Arsenic, Nickel, Iron), COD etc.

Page 64: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

55

7 - ENVIRONMENTAL COST BENEFIT ANALYSIS

Following table shows comparison between Heat Recovery and By-Product Recovery Type Coke

oven on Capital Cost, Operating Cost, Power Generation, Water requirement and Carbon

Footprint.

Capital Cost Heat Recovery Type By-Product Recovery Type

Project Cost including Power Plant

Approx. Rs. 750 Cr.

Including

Heat Recovery Coke Ovens

Modified Wet Quenching

WHR PP

Approx. Rs. 850 Cr.

Including

By-product Recovery Coke

Ovens

Coke Dry Quenching

By-product Recovery Plant

CDQ based PP

Operating Cost

(Benchmarked)

Heat Recovery Type By-Product Recovery Type

Capacity Stamp Charged Top Charged Stamp Charged

0.6 MTPA 1.00 1.18 1.19

Production for Heat Recovery Coke Oven is lower than that of By-Product Recovery by ~15-18%

Power Generation Heat Recovery Type By-Product Recovery Type

For 0.6 MTPA Capacity

75 MW ~45 MW (from COG – if it is not used for any other purpose e.g. in DRI)

Water

Requirement

Heat Recovery Type By-Product Recovery Type

For 0.6 MTPA Capacity

49 M3/ Hr (additional 45 M3/ Hr for 75 MW WHR PP)

129 M3/ Hr

Carbon Footprint Heat Recovery Type By-Product Recovery Type

For 0.6 MTPA Capacity

92,258 TPA of CO2 (Considering 69.6 MW WHR PP (75 MW less 5.4 MW CDQ PP) from Flue Gas)

244,263 TPA of CO2 (Considering 45 MW PP from COG)

Page 65: Addendum to Environmental Impact Assessment (EIA) For … · 2019-04-12 · BF Grade (including Nut Coke) 6 - 80 mm Foundry Grade > 80 mm Coke Fines < 6 mm Further, as the batteries

56

8 - CONCLUSION

Given the details submitted in this document, it may kindly be seen that the proposal for

amendment in configuration of coke ovens from by-product recovery type to heat recovery type

of identical production capacity would be beneficial.

There would also be no generation of wastewater containing toxic components like cyanide and

phenol, which may be considered as a major environmental advantage.

We also wish to submit that the Carbon footprint of the proposed configuration (Heat Recovery

Type Coke Oven with 75 MW WHR PP) is lower than that of By-Product Recovery Type Coke

Oven.

In view of the above, amendment of configuration in the EC dated 19th January, 2016 may

kindly be considered under clause 7 (ii) of EIA Notification 2006 & its subsequent amendments.