ADDENDUM NO. 1 TO: ALL PROSPECTIVE BIDDERS AND OTHER RECIPIENTS OF CONTRACT DRAWINGS & SPECIFICATIONS DATE: October 22, 2015 RE: ADDENDUM NO. 1 WILSON MIDDLE SCHOOL ADDITIONS CRA PROJECT NO. 2846 Receipt of this Addendum must also be acknowledged on the Proposal Form. Failure to do so may subject the bidder to disqualification.

ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA

ADDENDUM NO. 1 TO: ALL PROSPECTIVE BIDDERS AND OTHER RECIPIENTS OF CONTRACT

DRAWINGS & SPECIFICATIONS DATE: October 22, 2015 RE: ADDENDUM NO. 1

WILSON MIDDLE SCHOOL ADDITIONS CRA PROJECT NO. 2846

Receipt of this Addendum must also be acknowledged on the Proposal Form. Failure to do so may subject the bidder to disqualification.

Page 2: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA

Crabtree, Rohrbaugh & Associates

August County Public Schools Addendum No.1-2 Wilson Middle School Additions October 22, 2015 CRA Project No. 2846

ADDENDUM No. 1

OCTOBER 22, 2015

WILSON MIDDLE SCHOOL ADDITIONS

CRA PROJECT NO. 2846

TO: ALL PROSPECTIVE BIDDERS AND OTHER RECEPIENTS OF CONTRACT DRAWINGS & SPECIFICATIONS

NOTE: This Addendum is hereby made a part of the Contract Document, which will be the basis of the Contract. The Addendum is issued to modify and/or correct the original Contract Documents dated September 28, 2015. Attach this Addendum to your Contract Documents. Receipt of this Addendum must be acknowledged on the Proposal Form. Failure to do so may subject the bidder to disqualification.

GENERAL:

1. Each Bid must be submitted on the form provided by the Architect/Engineer, and must be accompanied by a bid bond, certified check, or cashier’s check equal to five percent of the total price submitted inclusive of add alternates. The Owner also reserves the right to reject any or all Bids for any reason whatsoever.

2. The last day which Contractors can ask questions in writing will be five days prior to

receipt of bids. Questions will be answered by Addendum only.

3. All bidders are hereby notified that they are responsible to review all parts of this addendum for conditions and requirements that may apply to their individual contracts. All Plan Holders shall review their Bidding Documents against the Table of Contents and List of Drawings to ensure that all Specifications Sections and Drawings are in your possession.

ARCHITECTURAL SPECIFICATIONS SECTION 000750 – Supplementary General Conditions

1. Paragraph 10.5: ADD the following sub-paragraph:

“10.5.2 Contractor may, at its option and at its own expense, perform tests to determine the presence of lead in coatings found on existing building components. In the absence of such tests, Contractor shall assume that all existing coatings are lead-based paints (LBP). Except in locations where tests have indicated that coatings are lead-based paint negative (with concentrations of lead < 1.0

Page 3: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA

Crabtree, Rohrbaugh & Associates

August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA Project No. 2846

mg/cm2), wherever work of this contract requires existing painted surfaces and components to be disturbed, Contractor shall comply with all Federal, State and Local environmental and occupational regulations applicable to the disturbance of LBP, at no additional cost to the Owner. Persons handling lead are required to be properly trained in safe handling practices, proper decontamination and disposal procedures.”

SECTION 012600 – Modification Procedures

1. Paragraph 1.4.A.2.a: ADD the following paragraph: “1. Include estimate breakdown with

hourly rates and labor time.” SECTION 012900 – Applications for Payment

1. Paragraph 1.4.B: REPLACE the number ‘25th’ in first sentence with the number “20th”.

SECTION 013100 – Project Coordination

1. Paragraph 1.6.B.1: ADD the following sentence: “j. Submittals and RFIs.”

SECTION 013200 – Construction Progress Documentation

1. Paragraph 2.12: ADD the following paragraph: “C. Copies of all inspections by

authorizations having Jurisdiction.” SECTION 013150 – Project Meetings

1. Paragraph 1.4.A: ADD the following sentence: “1. Pre-install meetings specifically

include, but not limited to, Erosion-sediment control, Site Utilities, Duct Cleaning, and Building PHASING.”

SECTION 014000 – Quality Requirements

1. Paragraph 1.6.H.2: ADD the following after the word Architect in second line: “Owner,

Building Official, and other authorizations having Jurisdiction.” SECTION 014100 – Special Inspections

1. Paragraph 1.2.D: see attached “Schedule of Special Inspections,” issued as Exhibit as

part of this Addendum. SECTION 017000 – Contract Closeout

1. Paragraph 3.3: ADD the following paragraph:

“B. Obtain signature of Owner or Owner’s authorized representative on an exact duplicate of final developed attached “ACPS Sample of Attic Stock and Close-Out

List specified to be furnished directly to Owner, bound at the end of this specification section and submit two completed copies to Architect and Owner at Final

Page 4: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA

Crabtree, Rohrbaugh & Associates

August County Public Schools Addendum No.1-4 Wilson Middle School Additions October 22, 2015 CRA Project No. 2846

Completion.” This list will be similar to List issued by Addendum for the Prototypical Elementary Schools, but only with items applicable to WMS Additions.

2. Paragraph 3.4: ADD the following paragraph:

“A. Asbestos Containing Materials: "Upon substantial completion, the Contractor shall

submit a statement certifying that no materials containing asbestos in any form have been used on the project. The Owner reserves the right to take independent tests for asbestos after Substantial Completion. Any asbestos found shall be removed in accordance with Federal, State, and Local regulations at no additional cost to owner."

3. REFER to Chart 017000b and ADD the following to last page as part of items required prior to final pay application:

- 3 copies of ‘As-Built’ Documents - 5 copies of O&M Manuals - 1 copy of Asbestos Compliance Statement - 1 Final VA State Fire Marshal Inspection Approval - 1 Final ‘Attic Stock’ check-off

SECTION 017823 – Operation and Maintenance Data

1. Paragraph 1.7.B: ADD the following paragraph: “10. And other “zone” and/or location plans as indicated in the mechanical and electrical specification sections.”

SECTION 096519 RESILIENT TILE FLOORING

1. DELETE Paragraph 1.2.A.3 rubber floor tile in its entirety 2. DELETE Paragraph 1.2.A.4 rubber stair treads in its entirety.

SECTION 101100 VISUAL DISPLAY UNITS

1. REVISE Paragraph 1.2.A.3 to read as follows: Vinyl-fabric faced cork tackboards with aluminum frame.

2. DELETE Paragraph 1.3.C.4 Maple Frames in its entirety. 3. ADD Paragraph 2.1.A.1.e to read as follows: ‘Nelson Adams, NACO’ . 4. ADD Paragraph 2.1.A.2.e to read as follows: ‘Nelson Adams, NACO’ . 5. ADD Paragraph 2.1.A.3.e to read as follows: ‘Nelson Adams, NACO’. 6. DELETE Paragraph 2.2.A.3 Screen-printed Graphics in its entirety. 7. DELETE Paragraph 2.3.C in its entirety.

SECTION 123216 EDUCATIONAL CASEWORK

1. DELETE Paragraph 2.1.E.13 in its entirety. SECTION 123553 WOOD LABORATORY CASEWORK

1. REVISE Paragraph 2.6.A Countertop Materials to read as follows: Epoxy: Factory-molded, modified epoxy-resin formulation with smooth, nonspecular finish.

Page 5: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA

Crabtree, Rohrbaugh & Associates

August County Public Schools Addendum No.1-5 Wilson Middle School Additions October 22, 2015 CRA Project No. 2846

1. Manufacturers:

a. Campbell Rhea

2. Physical Properties:

a. Flexural Strength: Not less than 10,000 psi. b. Modulus of Elasticity: Not less than 2,000,000 psi. c. Hardness (Rockwell M): Not less than 100. d. Water Absorption (24 Hours): Not more than 0.02 percent. e. Heat Distortion Point: Not less than 260 deg F.

3. Chemical Resistance: Epoxy-resin material has the following ratings when tested with indicated reagents according to NEMA LD 3, Test Procedure 3.4.5:

a. No Effect: Acetic acid (98 percent), acetone, ammonium hydroxide (28 percent), benzene, carbon tetrachloride, dimethyl formamide, ethyl acetate, ethyl alcohol, ethyl ether, methyl alcohol, nitric acid (70 percent), phenol, sulfuric acid (60 percent), and toluene.

b. Slight Effect: Chromic acid (60 percent) and sodium hydroxide (50 percent).

4. Color: As selected by Architect from epoxy manufacturer's full range

2. REVISE Paragraph 2.10 Countertops to read as follows: Epoxy Countertops and Sinks:

1. Countertop Fabrication: Fabricate with factory cutouts for sinks, holes for service fittings and accessories, and butt joints assembled with epoxy adhesive and concealed metal splines.

a. Countertop Configuration: Flat, 1-inch-thick, with beveled edge and corners, and with drip groove and applied backsplash.

b. Countertop Configuration: As indicated. c. Countertop Construction: Uniform throughout full thickness.

2. Sink Fabrication: Molded in one piece with smooth surfaces, coved corners, and bottom sloped to outlet; 1/2-inch minimum thickness.

d. Provide with polypropylene strainers and tailpieces. e. Provide sinks for drop-in installation with 1/4-inch-thick lip around perimeter

of sink. CONSULTANT SPECIFICATIONS SECTION 230000 – HVAC

Page 6: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA

Crabtree, Rohrbaugh & Associates

August County Public Schools Addendum No.1-6 Wilson Middle School Additions October 22, 2015 CRA Project No. 2846

1. ADD the following paragraph B. to section 3.18 COORDINATION WITH HVAC SYSTEMS CLEANING CONTRACTOR: As each HVAC Zone within the building is completed, the Mechanical Contractor shall notify the Building Owner’s Indoor Environmental Professional (IEP), who will then conduct a Visual Inspection of that Zone (Zone Check) in strict accordance with ACR 2006, Chapter 2.

SECTION 230130 – HVAC AIR DUCT CLEANING REQUIREMENTS

1. ADD the following paragraph B. to section 1.3 DOCUMENTS: Coordinate with the Mechanical Contractor and the Owners Indoor Environmental Professional (IEP) to determine size, quantity, and location of cleaning access point requirements; physically marking the location of each opening on the project documents.

2. ADD the following paragraph K. to section 2.3 GENERAL HVAC SYSTEM CLEANING REQUIREMENTS: The ductwork will not be cleaned during the duct installation process. The Building Owner does not consider the cleaning of ductwork (concurrent with its installation) to be sufficient.

SECTION 233000 – HVAC AIR DISTRIBUTION

1. ADD the following paragraph 2. to section 1.5 SUBMITTALS: Coordinate with the HVAC System Cleaning Contractor and the Owners Indoor Environmental Professional (IEP), Specification Section 23 01 30 HVAC AIR DUCT CLEANING, and provide and submit duct floor plan shop drawings showing cleaning access locations on the drawings; physically marking the location of each opening.

2. ADD the following paragraph P. to section 3.1 INSTALLATION:

All duct ends shall be sealed to prevent the intrusion of dust, dirt, and construction debris prior to installation. During installation, the open end of each duct segment shall remain sealed to prevent the intrusion of dust, dirt, and construction debris until the next segment is ready to be installed. This process will repeat until installation is complete and the whole system (including all supply and return devices) is sealed and fully protected. All duct sections shall be stored with both ends sealed as aforementioned in a fully protected, clean and dry location until the actual time of installation. All return air inlets shall be covered with MERV-8 filters, properly sealed to the air inlet device to prevent the bypass of dust, dirt, and construction debris. MERV-8 filters shall be changed every two weeks and replaced with new MERV-8 filters (after initial installation) for the duration of the project for the respective HVAC Zone’s system until final project final completion is achieved. All supply air diffusers shall be sealed to prevent the intrusion of dust, dirt, and construction debris until HVAC system start-up. Just prior to building occupancy (all ductwork having been installed and inspected in each zone and all construction work having been completed), the Owner’s IEP will conduct a final visual inspection of the entire HVAC system. If the IEP finds a difference between the Visual Zone Check and the Final Visual Inspection (in either particulates or microbials), the

Page 7: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA

Crabtree, Rohrbaugh & Associates

August County Public Schools Addendum No.1-7 Wilson Middle School Additions October 22, 2015 CRA Project No. 2846

Mechanical Contractor will be financially responsible for having a complete duct cleaning (at the direction of the IEP), to be conducted by the Duct Cleaning Contractor. The Mechanical Contractor shall absorb all cleaning and re-cleaning labor costs, all re-sampling labor costs (of the Building Owner’s IEP), and all samples analysis costs through successful verification of cleanliness by the IEP. If the Contractor chooses to seal the interior of duct seams with duct mastic, such mastic shall be approved for internal duct application.

SECTION 260533 – RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS

1. REVISE 3.2(C)(9) to read as follows: “Size conduits to meet NEC, except no conduit smaller than 1/2 inch shall be used unless noted otherwise. Conduits below-grade and in-slab shall be minimum 1 inch.”

SECTION 262213 – LOW-VOLTAGE DISTRIBUTION TRANSFORMERS

1. CLARIFICATION – Depending on when the transformer order is released, it is likely that transformers will need to comply with the 2016 US Department of Energy efficiency regulations. Bidders must account for this in their pricing.

ARCHITECTURAL DRAWINGS

DRAWING I4.1 LARGE SCALE LAYOUTS TYPICAL CLASSROOMS & SCIENCE LABS

1. Detail 2/I4.1 Science Lab Layout B (6th & 7th Grade)*.

a. A207 Prep: REVISE ‘Item No. 30’ to ‘Item No. 22’. b. A206 Science Lab: ADD ‘Item No. 11’ to the plan west wall below Item No. 14.

2. Detail I4.1 – General Casework and Equipment Schedule

a. Item No. 5: REVISE dimensions from ‘132”W x 30”D x 36”H’ to ‘139”W x 30”D x

36”H/30”H’.

DRAWING I7.1 FIRST FLOOR – FLOOR PATTERN PLAN – UNIT A

1. Detail Floor Pattern Legend - Transition Schedule as indicated on I7 Drawings:

a. REVISE ‘VCT to CONC’ to ‘VCT to SCONC’. b. VCT to SCONC: REVISE ‘Johnsonite No. SSR-XX-B to ‘Roppe No. #168’.

CONSULTANT DRAWINGS SECTION 230000 – HVAC

1. ADD the following paragraph B. to section 3.18 COORDINATION WITH HVAC SYSTEMS CLEANING CONTRACTOR:

Page 8: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA

Crabtree, Rohrbaugh & Associates

August County Public Schools Addendum No.1-8 Wilson Middle School Additions October 22, 2015 CRA Project No. 2846

As each HVAC Zone within the building is completed, the Mechanical Contractor shall notify the Building Owner’s Indoor Environmental Professional (IEP), who will then conduct a Visual Inspection of that Zone (Zone Check) in strict accordance with ACR 2006, Chapter 2.

SECTION 230130 – HVAC AIR DUCT CLEANING REQUIREMENTS

2. ADD the following paragraph B. to section 1.3 DOCUMENTS: Coordinate with the Mechanical Contractor and the Owners Indoor Environmental Professional (IEP) to determine size, quantity, and location of cleaning access point requirements; physically marking the location of each opening on the project documents.

3. ADD the following paragraph K. to section 2.3 GENERAL HVAC SYSTEM CLEANING REQUIREMENTS: The ductwork will not be cleaned during the duct installation process. The Building Owner does not consider the cleaning of ductwork (concurrent with its installation) to be sufficient.

SECTION 233000 – HVAC AIR DISTRIBUTION

1. ADD the following paragraph 2. to section 1.5 SUBMITTALS: Coordinate with the HVAC System Cleaning Contractor and the Owners Indoor Environmental Professional (IEP), Specification Section 23 01 30 HVAC AIR DUCT CLEANING, and provide and submit duct floor plan shop drawings showing cleaning access locations on the drawings; physically marking the location of each opening.

2. ADD the following paragraph N. to section 3.1 INSTALLATION:

All duct ends shall be sealed to prevent the intrusion of dust, dirt, and construction debris prior to installation. During installation, the open end of each duct segment shall remain sealed to prevent the intrusion of dust, dirt, and construction debris until the next segment is ready to be installed. This process will repeat until installation is complete and the whole system (including all supply and return devices) is sealed and fully protected. All duct sections shall be stored with both ends sealed as aforementioned in a fully protected, clean and dry location until the actual time of installation. All return air inlets shall be covered with MERV-8 filters, properly sealed to the air inlet device to prevent the bypass of dust, dirt, and construction debris. MERV-8 filters shall be changed every two weeks and replaced with new MERV-8 filters (after initial installation) for the duration of the project for the respective HVAC Zone’s system until final project final completion is achieved. All supply air diffusers shall be sealed to prevent the intrusion of dust, dirt, and construction debris until HVAC system start-up. Just prior to building occupancy (all ductwork having been installed and inspected in each zone and all construction work having been completed), the Owner’s IEP will conduct a final visual inspection of the entire HVAC system. If the IEP finds a difference between the Visual Zone Check and the Final Visual Inspection (in either particulates or microbials), the Mechanical Contractor will be financially responsible for having a complete duct cleaning (at the direction of the IEP), to be conducted by the Duct Cleaning Contractor. The Mechanical Contractor shall absorb all cleaning and re-cleaning labor costs, all re-

Page 9: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA

Crabtree, Rohrbaugh & Associates

August County Public Schools Addendum No.1-9 Wilson Middle School Additions October 22, 2015 CRA Project No. 2846

sampling labor costs (of the Building Owner’s IEP), and all samples analysis costs through successful verification of cleanliness by the IEP. If the Contractor chooses to seal the interior of duct seams with duct mastic, such mastic shall be approved for internal duct application.

DRAWING E0.1 – ELECTRICAL LEGEND, ABBREVIATIONS, GENERAL NOTES AND DETAILS

1. MODIFICATION - Revise General Note 7 to state, “Exact location and orientation of occupancy sensors shall be as recommended by manufacturer to obtain complete coverage. Sensors must have a coverage pattern such that they can cover the spaces indicated without having to increase sensor quantities. All occupancy sensor time delays shall be set to no more than 30 minutes.

2. MODIFICATION – Revise General Note 23 to state, “Each EF will have its own motor operated damper (MOD) – power the MOD from the fan circuit unless noted otherwise. Each EF (except for EF-A10 and EF-B10) will also have its own line-voltage wall switch by Division 23 – wire through these switches to power the fan and associated MOD.”

DRAWING E1.1 – FIRST FLOOR PLAN – UNIT A – LIGHTING

1. MODIFICATION – Revise the note regarding the 3 existing lighting bollards and the wiring to the 4 new type D1 fixtures to require 1” conduit where underground (instead of 3/4").

DRAWING E2.3 – SECOND FLOOR PLAN – UNIT A – POWER

1. MODIFICATION – Power the REF-SCI1 MOD from 2LAA1-21 downstream from the hood switch, instead of from 2LAA1-33.

END OF ADDENDUM NO. 1 ATTACHMENTS This addendum includes the following attachments: Specifications: SECTION 014100 WMS Schedule of Special Inspections Attachment Exhibits: Copy of Pre-Bid Sign-in Sheet

Page 10: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA
Page 11: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA
Page 12: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA
Page 13: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA
Page 14: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA
Page 15: ADDENDUM NO. 1 - Mathers-Team.com · 2015-10-23 · Crabtree, Rohrbaugh & Associates August County Public Schools Addendum No.1-3 Wilson Middle School Additions October 22, 2015 CRA