Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
AD-A240 821 C)Assessment of Short Span Bridge Materials -
by
John R. Brown
A research paper submitted in partial fulfillmentof the requirements for the degree of
Master of Science in Engineering
University of Washington
1990
I Approved by--
Program AuthorizedIto Offer Degree
Date
9i-10899
DtIMEI NOTICE
THIS DOCUMENT IS BEST
QUALITY AVAILABLE. THE COPY
FURNISHED TO DTIC CONTAINED
A SIGNIFICANT NUMBER OF
PAGES WHICH DO NOT
REPRODUCE LEGIBLY.
Assessment of Short Span Bridge Materials
by
John R. Brown
A research paper submitted in partial fulfillmentof the requirements for the degree of
Master of Science in Engineering
University of Washington .0
1990 .. ,
Approved by---
Program Authorizedto Offer Degree-
Date
University of Washingtion
Abstract
Assessment of Short Span Bridge Materials
by John R. Brown
Chairperson of the Supervisory Committee: Associate ProfessorJimmie Hinze
Department of Civil Engineering
There are approximately 1877 substandard bridges on thefederal aid system and 2193 substandard -bridges off the federal aidsystem in Idaho, Oregon, and Washington, (Secretary ofTransportation, 1989).
In general ,a bridge can be divided into the substructure,superstructure, and decking. The choice of construction materials iscritical for the function and economics of all elements. Wood, steel,and concrete are the principle materials utilized.
Each of these materials has characteristics that add and detractfrom use in short span bridges. A review of current literatureprovided insight into what factors were considered important. Asurvey of how counties have replaced deficient structures in the pastprovides information on materials that will be in demand in thefuture.
This research focused on the criteria that county engineers inIdaho, Oregon, and Washington consider when selecting material fora short span bridge structure.
A survey was prepared and forwarded to county officials inIdaho, Oregon, and Washington to determine past practices andanticipated future trends. A response from 42% of the countiesprovided valuable insight into short span bridges in the Northwest.
One of the most significant facts is that precast concretestructures are predominately utilized for the superstructure anddecking. There are a number of counties that have specialconsiderations that allow for the use of wood and steel structures butthey are the exception. The preponderance of county officialsrecognize precast elements as the most superior material both inperformance and economics.
Table of Contents
List of Figures............................................................................1iList of Tables.............................................................................. ivIntroduction.............................................................................1.Literature Review....................................................................... 3
Wood ................................................................................ 3Steel ................................................................................. 1 3Concrete ............................................................................ 2 1
Previous Research....................................................................... 26Research Methodology ................................................................ 3 33Results..................................................................................... 41Summary................................................................................... 68Conclusions ................................................................................ 72Recommendations....................................................................... 75References ................................................................................. 78Appendix A Cover letter and survey .............................................. 8 2Appendix B Summary of responses..............................................8 7Appendix C SPSS Data Definition File and Data File......................... 134Appendix D List of Respondents................................................... 142Appendix E Summary of Costs for New Bridges ............................. 145
List of Figures
Number Page
1. Prefabricated Steel Rectangular Units ................... 20
2. Precast Element Shapes .............................................. 25
3. Utilization of Materials in the Substructure ...... 54
4. Utilization of Materials in the Superstructure ......... 54
5. Utilization of Materials in the Decking ................... 55
6. Comparison of Required Maintenance ..................... 56
7. Comparison of Material Durability ............................ 56
8. Comparison of Construction Costs ............................. 60
9. Comparison of Material Costs ..................................... 60
10. Comparison of Material Availability ........................ 62
11. Comparison of Speed of Construction ...................... 62
12. Comparison of Design Complexity ............................. 63
13. Familiarity of Materials in the Departments ...... 63
14. Familiarity of Contractors with the Materials ..... 65
15. Comparison of the Availability of Funding ............ 65
16. Relative Aesthetic Value of the Materials ............... 66
iii
List of Tables
Number Page
1. Number of Counties that Receive Federal, State,and Local Funding for Bridge Replacement ...................... 43
2. Number of Deficient Bridges by State .................................. 46
3. Number and Percentage of Bridges Constructed or
Under Construction (1988-1990) by Length .................... 47
4. Priciple Construction Materials for New Bridges ............. 49
5. Average Bridge Replacement Costs in Dollars ................... 51per Square Foot of Bridge Deck
6. Estimated Number of Material Suppliers ............................. 52
7. Averages of the Selection Factors for ................................... 56Cast-in-Place, Precast, Steel, and Wood
8. Average Responses for Substructure andSuperstructure Material Selection Factors .......................... 66
iv
ACKXNOWLEDGMENTS
The author wishes to extend a sincere thankyou to Professor Jimmie Hinze for hisassistance in the preparation of this researchpaper.
DEDICATIONA special note of appreciation goes to my wife,whose support and encouragementthroughout this project enabled me to see thelight. This research paper is dedicated to her.
vi
lntroduciien
Because of the publicity generated by bridge failures and the
deteriorating condition of the nation's bridges, Congress passed the
1968 Federal Highway Act. This statute mandated that all bridges on
the federal-aid system receive a biannual inspection and that the
Federal Highway Administration maintain records of these
inspections. With passage of the Surface Transportation Assistance
Act (SAA) of 1978, the biannual inspection requirements for bridges
were expanded to include all bridges not on the federal aid system
(TRB Special Report 202, 1984). In 1987 the Surface Transportation
and Uniform Relocation Assistance Act (STURAA) extended the
Highway Bridge Replacement and Rehabilitation Program (HBRRP) to
low water crossings (Secretary of Transportation, 1989). As of June
1988 there were 98,526 structurally deficient bridges and 62,639
functionally obsolete bridges off the Federal-aid system (Secretary of
Transportation, 1989).
Short span bridges are not as visible to the public as the
highway bridges on the Federally funded road system. However
these bridges on the secondary roads play a vital role in this
country's overall transportation system. The number that require
repair or ieplacement represents a significant expenditure of public
funds.
Out of the total of 7791 off the federal-aid system bridges in
Idaho, Oregon, and Washington approximately 1017 are structurally
deficient and 1176 are functionally obsolete (Secretary of
Transportation, 1989). Structurally deficient bridges are either
closed to traffic or are load posted for loads less than considered
adequate for the anticipated level of traffic. Bridges are classified as
functionally obsolete typically because the bridge geometry is
deficient for the intended use. Examples of functionally obsolete
bridges are those with poorly aligned roadway approaches, narrow
roadway widths, or hydraulic openings that are too small. In Idaho
40% of the bridges off the federal-aid system require replacement
while in Oregon the percentage is 24% and in Washington 22%. Many
of the bridges off the federal aid system are county bridges with
spans of less than 120 feet.
The engineers responsible for specifying replacement
structures have many variables to consider for each design.
Numerous materials are available to meet the design parameters.
Bridge structures can be constructed of any of the common
construction materials: wood, steel, and concrete. Some materials
have thousands of years of history such as the masonry arch and log
bridges while others have relatively more recent histories such as
the prestressed prefabricated concrete bridge. All of these materials
and systems have their place for a bridge structure. This research
will focus on the criteria that county engineers consider when
selecting material for a short span bridge structures.
Literature Review
A review of the literature provides insight into the factors
considered for bridge selection. Many articles have been published
highlighting how various state and county agencies have approached
their bridge replacement programs.
In general a bridge can be divided into the substructure and
superstructure. The substructure is that part of the bridge that
transmits the loads on the bridge to the bearing soil. The
substructure iacludes the tootings, breastwal's or backwalls,
wingwalls, bridge seat, piling, and bents (Ritter, 1990).
The superstructure is what a layman normally considers "the
bridge" and typically is the most visible part of the bridge. It
consists of the parts that cross the clear span such as: the stringers,
railings, guardrails/parapets, and decking. The types of
superstructures most common in short spans today are the beam,
deck slab, truss, and arch (Ritter, 1990).
The choice of construction materials is critical for the function
and economics of all elements. Wood, steel, and concrete are the
principle materials utilized in the substructure, superstructure, and
decking.
Wood
Of the three materials considered, wood by far has the longest
history as a bridge material. The earliest forms of "bridges" were
logs that naturally fell across clearspans allowing man to cross
otherwise impassable areas. Man has modified these early
structures to permit greater clear spans and ;,creased loads.
4
Timothy Palmer a civil engineer from Newburyport,
Massachusetts built a 2362 feet long by 38 feet wide wooden bridge
7 miles north of Portsmouth, New Hampshire in 1794 (Ritter, 1990).
The bridge consisted of pile trestles for the approach spans and
three arched trusses. Palmer is also credited with constructing the
first Ameri,an covered wooden bridge ove- the S4,huylkill River in
PLiladelphia tn 1806. Tis started a trend wh*ich resulted in
approximately 10,000 covered bridges being built in the United
States between 1805 and 1885 (Ritter, 1990).
This same century saw the rapid growth of the railroads and
the resultant requirements tor bridges at river crossings. Wood was
the logical choice as a building material due to its abundance and the
availability of the skilled labor necessary for bridge erection . Truss
bridges and trestle bridges were the predominant wood designs
during this period.
Even as wood bridge construction reached its zenith in number
of structures built, other materials were being considered. Irons
were begun to be utilized do to superior shear strength as compared
to wood. The first metal bridges were cast iron. However wrought
iron structures started to dominate bridge structures by the mid
19th century do to higher shear strengths. By the end of the 19th
century steel had replaced wrought iron as the primzry bridge
material. Additional de velopments in steel production resulted in
ever more economical structures. "By the mid-1930's, steel was less
expensive than wood on a first-cost basis and took the lead as the
primary bridge material" (Ritter, 1990).
I 5
Wood has many properties that make it a valuable material in
modern bridge construction. Wood is relatively light per unit of
length in comparison to concrete. Wood weighs, depending on
species, from 35-60 lbs per cubic foot. Structural lightweight
concrete, often used is long bridge decks, is 90-120 lbs per cubic foot
of material. The less weight per volume results in wood
superstructures with lower dead loads. This factor makes it possible
and more economical to utilize smaller substructures. For an
entirely new bridge this means savings due to reduced material and
construction costs. There are examples in which wood was the most
economical alternative for replacement of an substandard bridge
because the light dead load allowed use of the existing substructure
(Verna, 1983).
Lighter members also enhance the erection of the structure,
since smaller construction equipment may be utilized during
erection. This is especially important in isolated areas where
equipment availability is very limited. Transportation of lighter
structural members is also easier and more economical. This factor
becomes more critical for more isolated construction sites.
Wood lends itself to bridge systems since elements may be
pre-fabricated off site. The relatively light material weight makes is
I possible to transport large pre-assembled components. The
advantage of this is that a large part of the work for the bridge
actually takes place off site in a controlled environment. If
prefabrication of the components was correct only assembly is
required on site. This speeds erection time with resultant reduction
in construction costs (Williamson, 1972)
I 6
Assembly of a wood bridge often requires only semi-skilled
I labor. This is especially true when bridges consist of prefabricated
components that are cut to required dimensions and pre-drilled for
connections. Often times complete assembly only requires simple
I tools such as torque wrenches.
The resistance of wood to chemicals and corrosive materials
has increased interest in its use in bridge construction. The effects of
roadway chemical deicing agents on steel and concrete bridges has
been shown to reduce the life expectancy of these structures.
Barnhart (1987) has noted that nail laminated timber decks in Ohio
have lasted an average of 30 - 40 years with minimum maintenance.
However, many reinforced concrete decks showed signs of spalling
after only 5 or 10 years of attack by deicing salts and required
"considerable patching" within 20 years (Barnhart, 1987). As a
result the concrete reinforced decks had an average expected life of
30-35 years (Barnhart, 1987). Similar findings have been noted on
the 1700 bridge system of Allegheny County, Pennsylvania (Verna,
1980). In some parts of the country the deterioration to concrete
decks is so severe that replacement is required after only 15 years
(Transportation Research Board Special Report 202). Timber is often
an economical alternative solution for deteriorated bridge materials
in those sections of the country (Verna, 1983).
Wood is a renewable resource. It is a natural material that
blends well with its surroundings, presenting an aesthetically
appealing structure. Less energy is required to produce theImaterials and to erect a wood structure than one built of cast in place
concrete (Weyerhaeuser, 1980). The energy required to produce a
7
cunstruction material may become a major factor in economical
considerations for bridge material selection as it did in the early
1970's.I' Wood does have limitations that have contributed to its
decline as a bridge material. The foremost of these is its
susceptibility to decay. It is an organic material and is a food source
for a number of decay fungi, microorganisms, wood boring insects,
and marine organisms (Muchmore, 1984). This is especially true if
the untreated wood is exposed to the elements and allowed to get
wet. The functional life of wood is significantly increased if it is kept
dry. This was the purpose of the covered bridges of the 19th
century. The covered structure was built to protect the timber
structure from the deteriorating action of the elements.
Today wood is protected by pressure treating with
preservatives such as the oil based: creosote, pentachlorophenol, and
copper naphthenate or one of a number of waterborne preservatives
(Ritter, 1990). These pressure treatments, if properly performed and
if the protective envelope is maintained, can increase the life of a
wood structure by a factor of 5 to 10 (Erikson, 1989). Use of some
of the chemicals for pressuring wood is becoming more difficult as
concern arises over their impact on humans and the environment.
These is especially true for pentachlorophenol which has been placed
on the EPA list of restricted-use chemicals. This requires that the
applicator pass a test administered by the controlling state
authorities (Ritter, 1990). Preservation is rarely accomplished in the
same location where the member was sawn or fabricated. This
8I
increases the time required for delivery which is often greater than
that for a steel or concrete beam.
The strength of wood is dependent on a number of factors.
i Three of the most important are species, grade, and moisture content.
Naturally occurring knots are considered defects and reduce the
strength of the wood. Moisture content over the fiber saturation
* point also reduces its strength.
Dimensional stability is another characteristic that directly and
I indirectly can have negative effects on bridge structures. The
* dimensions of wood members are effected in all three axes by
moisture content and to a lesser extent by temperature. Sawn
lumber will expand and contract depending on moisture content of
the wood. The amount of expansion and contraction will vary for the
three axes depending on axis orientation to the wood grain. The
differential volumetric changes can result in checks and cracks in the
wood and contributes to the loosening of mechanical connections.
Mechanically connected timber structures resist impact loads
by transferring the load from the point of impact to adjacent parts
I (Hale,1977). The elastic nature of wood and the characteristic of
*] transferring impact loads has had an negative effect on the
utilization of wooden bridges. In particular it has prevented the
incorportation of an economical wooden guard into the AASHTO
bridge specifications. Lightweight wooden guardrails have been
successfully statically load tested in accordance with AASHTO
standards. However crash testing for complete AASHTO acceptance
has not been performed. Although wooden rail systems meet the
performance criteria for rail systems by containing a vehicle upon
I 9Iimpact, the defection of the wooden rails is not within current
IAASHTO standards (TIBIRC Crossings, 1990).
Wood members must be deeper than steel or concrete in order
to carry the same design load. The hydraulic opeing of the bridge
may be reduced significantly which is unacceptable if flood
conditions are critical.
The engineering community relationship with wood structures
is not as intimate as that for steel or concrete. Most college curricula
emphasize the use of steel and concrete as structural materials but
I consider wood a material for light framing, as in house construction.
Although sawn lumber and even rough logs are still utilized on
I low volume roads, most wood bridges today are constructed of
engineered wood products. The positive characteristics of wood have
been enhanced and the negative characteristics mitigated by
pressure treated engineered wood products such as glued laminated
(glulams) and laminated veneer lumber (LVL).
Glued laminated members are laminations of 1 to 2 inch
nominal strips of wood, oriented so that the grains of all the
laminations are parallel. The laminations are positioned according to
the intended use of each member. The stronger sections of wood are
in the most critical cross sectional area. In the case of a beam, lower
grade laminations are placed on the neutral axis and higher grades
are placed on the outside laminations. The laminations are bonded
I together with a waterproof adhesive. These forms of engineered
wood members have been in use since the 1940's (Erikson, 1989).
Laminated veneer lumber, as the name indicates, is produced
I from laminating veneers of wood in much the same way that
I
1 10
plywood is produced. However, unlike plywood where the wood
grains in the adjacent veneers have a perpendicular orientation, LVL
veneer grains are all in a parallel orientation.
These engineered wood products provide a number of
advantages over sawn lumber. Defects that naturally occur in wood,
such as knotholes, are not concentrated in one area in engineered
wood. They can be distributed throughout the member and placed in
areas that will not be subjected to high stress, such as the neutral
axis of a beam.
The laminations and veneers are dried to a uniform moisture
content prior to fabrication. This prevents much of the dimensional
problems noted earlier and allows for greater strength ratings.
Glued laminations and laminated veneer lumber can be
manufactured into lengths limited only by the available jig of the
fabricator, or for pressure treated members by the size of the
treatment cylinder. This is especially critical since sawn lumber is
not often available in the sizes required. Glued laminations in excess
of 120 feet have been fabricated. Laminated veneer beams have
practical limits of about 80 feet (Erikson, 1989).
* Creosote treated wood is noted for its use in bridge abutments
and bents. The abutments are the structure that support the ends of
the bridge and hold back the roadway embankment material. Bents
are the intermediate supports for multispan bridges. Wood
abutments commonly support the superstucture either by a post or
pile structure (Ritter,1990). Sawn lumber or glued-laminated posts
transfer the superstructure loads to buried spread footings that are
typically made of concrete (Ritter, 1990). Horizontal planks can be
placed behind the wooden posts to form breastwalls and wingwalls
which hold back the embankment material. Piles are driven in areas
where soils cannot support a buried footing. Pile abutments transfer
- the superstrcture loads through wood piles vice posts on spread
3 footings. Like post abutments pile abutments can be used to elevate
the superstructure (Ritter, 1990), and with the attachment of
* horizontal planks hold back the embankment material.
Wood use in bridge superstructures is almost exclusively restricted
I to clear spans under 120 feet. The trestle or truss systems utilized in
the 19th century are not the most common designs of wood bridges
today. Wood superstructures usually are glued laminated simple
* span stringers with either a transverse glued laminated deck or nail
laminated sawn lumber deck.
Glued laminated deck panels are 3 1/8 inches or thicker
depending on the spacing between stringers (Weyerhaeuser, 1980).
The panels are typically three to five feet wide with lengths set to
meet the bridge deck width requirements. The deck panels may be
placed with or without any connection between panels. Dowel
I connections are typically used between panels if the roadway surface
is finished with a bituminous wearing coat to provide for better
wheel load transfer (Ritter, 1990). Both types of deck panels are
* often utilized with steel stringers in lieu of the glued laminated
stringers (NCRP Report 222, 1980).
Another form of all wood superstructure is the longitudinal
deck glued laminated bridge. In this design the deck panels run in
the longitudinal direction (the same axis as the clear span and the
3roadway direction) and support the loads without any additional
I
S12
longitudinal members. Transverse beams are added to tie the
longitudinal panels together and provide distribution of wheel loads.
The advantage of this design is that it has less depth and provides
greater space between the bottom of the superstructure and the
water crossing. This increases the hydraulic opening for flood levels
(Weyerhaeuser, 1980).
Prior to the introduction of glued laminated decks, sawn
lumber planks and nailed laminated decks were in common use.
Sawn lumber planks are pieces of dimensional lumber laid flat and
nailed either transversely or longitudinally to the underlying
stringers. Nail-laminated decks are made up of dimensional lumber
placed on edge so that the wider face is in a vertical orientation. The
pieces of lumber are mechanically laminated with nails and then
nailed to the stringers . Such decks have lasted as long as 40 years.
However, their use, even on roads with light average daily traffic
(ADT), has declined significantly. Both decks are not suitable for
bituminous wearing surfaces. Loosening of the nails occurs due to
vibration, localized wheel loads, and moisture content variations
which result in dimensional changes (Peterson, 1987). The loosening
of the connections allows individual lumber pieces to deflect beyond
the tolerance of the wearing course.
Stressed laminated timber decks are being emphasized by the
timber industry. A stress laminated timber deck is similar to a nail
laminated deck in that sawn lumber planks are laid on edge and
laminated together. However, the planks are held together by the
compressive forces of transverse posttensioned high strength steel
rods (Sarisley, 1990). This form of decking eliminates nail
13
laminations which can loosen and also provide an avenue for
moisture penetration.
The stress laminated deck system was originally developed in
Ontario, Canada and has been included in the Ontario Highway Bridge
Design Code since 1983 (Ritter, 1990). The American Association of
State Highways and Transportation Officials have adopted a "Guide
Specification" for stress laminated timber decks pending approval of
the full membership (TBIRC Ritter, 1990).
Woods characteristics and availability make it a very useful
building material. It was utilized extensively in this country in the
19th century as a bridge material. Some of the characterisiics that
have detracted from its continued prominent position as a bridge
material have been mitigated by modern wood engineering
techniques. Glued laminated and laminated veneer lumber have
resulted in stronger structural members that can be produced in long
spans. Pressure treatment has increased the service life of most
bridges by preventing attack by decay organisms. The extensive use
of corrosive de-icing salts with the resultant deterioration of concrete
and steel has sparked a renewed interest in the use of wood in
bridge structures. Wood appears to be a viable option for short span
bridges on the secondary road system.
Steel
The shift to the use of steel as the primary material in bridge
superstructures occurred in the early 20th century. The railroad
expansion era had a profound influence on bridge construction
(Ritter, 1990). Speed of erection was a major consideration in bridge
14
design and material selection. Initially wrought iron trusses were
the most common metal bridges (Heins and Firmage, 1979).
However, the heavy train loads imparted on short span bridges
required members with high shear strength. The large number of
timber and wrought iron bridge failures in the latter part of the 19th
century necessitated the use of a stronger material (Heins and
3 Firmage, 1979).
Steel became readily available with the development of the
I Bessemer process in the early 19th century. This process removed
impurities from molten pig iron producing steel. Heins and Firmage
(1979) state that the properties of steel are dependent on: "... kind
and quantity of alloying elements, the amount of carbon, the cooling
rate of the steel, and the mechanical working of the steel such as
rolling and stressing." Modern steel mills can produce many
different grades of steel. The choice of steel for a bridge depends on
its intended use and availability from the mill.
Today, steel is one of the premier construction materials. The
following characteristics show some of the advantages and
drawbacks to the use of this material in short span bridges.
Strength is the principle characteristic which makes steel a
very useful bridge material. Steels most commonly used in
contemporary bridge construction have minimum yield points of
36,000 psi (A36), 50,000 psi (A572 G50), 50,000 psi (A588), and
90,000 to 100,000 psi (A514) (U. S. Steel, 1986).
Steel is a predictable and familiar engineering materiai
generally classified into one of three categories: carbon steels (A36),
high-strength low-alloy steels (A572 and A588), and heat-treated
I
15
alloy steels (A514) (Heins and Firmage, 1979). Designers know the
characteristics of a particular grade of steel and can accurately
predict its behavior in a variety of conditions. Familiarity of the
material is fostered by the extensive exposure in engineering
curriculums to the application of steel in construction.
The use of steel is very prevalent in all areas of the
construction industry. Fabricators and erectors are well versed in
the methods of steel construction. This makes steel a logical choice
for a public bridge project that will be bid upon and constructed by a
private contractor.
It is possible to produced steel in a variety of shapes. Standard
structural shapes are available that are very suitable for short span
bridge construction. Godfrey (1975) noted that prefabricated steel
bridges in the Pacific Northwest are inexpensive due to their
simplicity and minimum field work...". As much as possible, steel
bridge structures are prefabricated prior to delivery to the site. This
results in reduced construction time, shorter duration of road
closures, and less construction costs.
All materials have limitations in use and steel is no exception.
One of the principle characteristics of steel that detracts from its use
is corrosion. The combination of moisture and air cause the oxidation
of the steel resulting in the formation of ferric oxide (rust). This
process can become sufficiently severe that the structural integrity
of some members will be compromised. This process is exacerbated
with the use of de-icing salts. In order to prevent corrosion, steel
surfaces must be protected with a coat of paint which adds to the
total life cycle costs of bridges.
16
The steel industry produced a low-alloy steel, A588, in the
early 1960's. This steel oxidized like any other unprotected steel
when left exposed to the elements. However, unlike other steels the
initial thin ferric oxide film was supposed to "...remain tight to the
steel preventing any moisture penetration and further oxidation"
(Heins and Firmage, 1979). However, this has not always been the
case as determined by examining the approximately 2000 A588
bridges constructed in the United States (Robison, 1988).
A588 requires a specific combination of moisture and some
airborne contaminants to create the protective film (Robison, 1988).
If the steel is not subjected t- Ohe correct combination it may not
create the protective film and continues to corrode. Gary Kasza of
the Federal Highway Administration's Portland, Oregon office did a
survey in 1986 of 11 Washington state bridges constructed of A588.
He concluded that it should not be used in wet climates (Robison
,1988). It appears that this steel is not corrosion free in the
relatively wet western counties of Washington and Oregon.
Material availability and cost are two other factors that have
reduced the use of steel in the Northwest. Although prefabrication
has reduced the initial costs of steel bridges the initial costs of other
materials have become even more competitive. Generally there are
more concrete plants and precasting yards than steel mills in the
northwest. Local raw materials are available and utilized to produce
concrete. This reduces production and transportation costs usually
making the initial material cost of concrete more attractive.
Short span steel bridges have gone through a number of
evolutions before arriving at the common designs in use today. At
I 17
the end of thel9th century, railroads started to use steel plate
girders for short span construction. These girders could be
prefabricated and then shipped by rail to the construction site and
lifted into place by mobile steam powered railway cranes (U.S. Steel,
I 1986). The superior strength of steel in comparison to other common
materials such as wood or wrought iron made it a highly aesired
jmaterial. With the fabrication of plate girders and the heavy lift
capability of mobile steam powered railway cranes steel plate girder
I bridges became a common railroad bridge design.
IThf, early steel highway bridges consisted of through and pony
trusses. Many early bridge sites weie 'ery isolated with narrow
I roads. Heavy lift construction equipment was not available, which
necessitated small, easy to handle bridge components (U.S. Steel,
1986). Truss systems were the dominant design because they could
be constructed on site with angles and plates riveted together. Other
advantages of the through and pony truss were that they required a
"...minimum increase in approach grades..." and provided maximum
clearance between the bridge structure and potential flood levels
(U.S. Steel, 1986). The deck system typically was a nail laminated
wood deck. These designs were not an efficient use of material and
resulted in high dead loads. However, the light live loads and
inexpensive fabrication costs made them a feasible and highly
economical design at the turn of the century (U.S. Steel, 1986).
In the early 1920's the first wide-flange rolled beams capable
of being utilized in bridge superstructures became readily available.
The rolled beams could be assembled faster than plate girders,
making them more economical. The increased use of rolled beams
was facilitated by the developmei., of new heavy lift construction
equipment and more accessible bridge sites (U.S. Steel, 1986).
Deck systems of either reinforced concrete or timber became
widely utilized in conjunction with the rolled beam stringers. Simple
span designs consisting of rolled beams with a deck system were in
use in the late 1930's " .. for spans up to about 70 feet and were
sometimes used for spans up to 90 feet" (U.S. Steel, 1986). This
signaled the end of th- through truss as the predominant design in
steel briut,. Today steel trusses are predominantly utilized for
temporary bridges or in military applications (Sprinkel, 1985).
Lessons learned about welding during the second world war
1 were applied to bridge construction in post war Europe and then in
th e United States. Welding resulted in a more efficient use of
I materials which resulted in smaller dead loads and more economical
structures (U.S. Steel, 1986).
Use of prefabricated steel bridge components occurred during
I the 1950's. Prefabrication increased in the steel industry due to the
competitive nature of construction (Elasser, 1972). The use of
I prefabricated bridge components reduced on site construction time,
decreasing labor and equipment costs and bridge closer times.
Today steel continues to be a major component in bridge sub-
I structures and superstructures. One of the more common
superstructures on the secondary road system are steel stringers
with concrete decks (Better Roads, 1971; Sachse and Willis,1973;
NCHRP Report 222, 1980). These structures can be simple or
continuous spans. For span lengths of 40 ft and less non composite
I beams of A36 are very common (U.S. Steel, 1986). Up to 80 ft. wide
U 19
Iflange beams have been used economically (U.S. Steel, 1986; NCHRP
Report 222, 1980; and Taly and GangaRao,1976).
Welded plate girders of composite construction are
recommended in the U.S Steel Design Handbook for simple spans
3 greater than 80 ft. In composite construction the concrete deck slab
is connected to the steel stringers and becomes an integral part of
the beam. It not only functions as the bridge deck but also acts with
the steel stinger in carrying bridge loads.
I As mentioned previously most bridge elements are
prefabricated. These components come in a variety of shapes and
sizes. Prefabricated T-shaped units up to 80 ft. long and 6 ft. wide
can be used in multiple spans from 50 to 110 ft (NCHRP Report 222,
1980). Rectangular units either 39 ft. 4 in. or 19 ft. 8 in. long are
I combined for different site conditions and roadway widths
(see Figure 1) (NCHRP Report 222, 1980). Spokane Culvert Company
produced some 200 bridges from 1968-1975 consisting of plate
girders topped with steel bridge planks. They were used for spans
up to 100 feet in county and U.S. Forest Service bridges (Godfrey,
1 1975). Armco Steel Company of Ohio produced a similar design
utilizing rolled sections for spans up to 50 ft. Up to 1975, Wallowa
County, Oregon had constructed 150 of these steel structures utilizing
its own crews (Godfrey,1975).
A review of the literature reveals that steel is primarily
utilized in the superstructure. However examples are available of
the use of steel in the substructure and decking. Steel H beams can
be driven as piles for intermediate bents and abutments with steel
II
20
St ructra T..o*Transverse Roadway Rib
/
IStoat Plot* (Covered with 1 '14
thick modified asphalt wearing surface.)
PREFABRICATED STEEL RECTANGULAR UNITS
I
II
II
U 21
Isheet piling retaining the embankment material (Better Roads, 1971;
and NCHRP Report 222, 1980).
Steel decks usually are either steel grid or orthotropic plates.
I The primary advantage of these deck structures are that they are
light and easy to install (Spinkel, 1985). However the expense of
these decks normally do not justify their use in short span
structures, particularly in areas of light traffic.
The long span corrugated arch is a system that can be
I considered both the substructure and superstructure. This system
can be utilized for spans from 20-60 feet (NCHRP Report 222, 1980;
and Perin, 1973). The use of this system is highly dependent on
3 existing soil conditions and available fill material (Godfrey, 1975).
Steel has a long history of use in bridge construction in this
I country. It is a very familiar construction material. Certain
limitations have to be considered prior to and during its use in
bridge structures. Today, prefabricated bridge elements are the
standard method of steel bridge construction. Rolled shapes and
plate girders are utilized in prefabricated components depending on
U span length, design, and fabricator. These steel superstructures have
been a very viable option in the past in counties in the northwest.
Concrete
* Prior to the Roman empire mortar was used in construction
However modern forms of reinforced concrete were not utilized until
3 the late nineteenth century (Heins and Lawrie, 1984). Reinforced
concrete bridge structures were pioneered in Europe by Hennebique
I of France (Heins and Lawrie, 1984).
I
22
As early as 1886 prestressed concrete was being investigated.
However, it was not until 1926-1928 that the control of the loss of
the prestress with high-strength steel made the application of
prestressed concrete members practical in construction (Heins and
Lawrie, 1984). The use of prestressed concrete girders in bridg.
construction started in the U.S. 40 years ago with the construction of
the Walnut Lane bridge in Philadelphia in 1950 (GangaRao and Taly,
1976). The use and acceptance of precast prestressed concrete in
bridge structures has increased as reported by Godfrey (1975) and
Sprinkel (1985).
Concrete, in particular Portland Cement Concrete, is one of the
premier bridge construction materials. Cast-in-place bridge
structures built 65 years ago utilized mix designs that developed
I compressive strengths of 2000 psi (Pfeifer, 1972). Today modern
design mixes, placement techniques, and curing can easily produce
high-quality, high-strength concrete of 10,000 psi and greater. This
* permits designs with long clear spans eliminating intermediated
piers and bents. Some precast prestressed sections are capable of
180 foot clearspans (Prestresscd Concrete Institute, 1980). The
strength of concrete in action with prestressing steel can produce
beams with very low depth to span ratios (Prestressed Concrete
Institute, 1980). This important characteristic result in maximum
hydraulic openings.
In addition to high compressive strength concrete has many
other characteristics that make it a desirable construction material.
The majority of the weight and volume of concrete is composed of
aggregates which typically are produced locally resulting in reduced
23
production costs. Concrete can be produced in a variety of strengths
and weights to suit project requirements. Lightweight concrete can
be produced for bridge decks that has a dead load of 85 to 115
pounds per cubic foot (Kosmatka and Panarese, 1988). Fluid concrete
is moldable to many shapes providing flexibility in bridge design.
Properly mixed and placed concrete is a highly durable material with
little fatigue due to its high strength in comparison to low bridge
loads. Properly chosen aggregates provide a hard, skid resistant
I wearing surface. Concrete resists attack by many corrosive
chemicals. The thermal properties of properly cured concrete are
desirable in bridges, resisting fire as well as freeze thaw cycles.
Little to no maintenance is required of concrete bridges. Concrete
does not require painting and will not require patching unless some
I chemical attack produces spalling or cracking.
Problems can develop with any concrete bridge. Poor mix
design, improper components, and incorrect placement, finishing,
*and curing all will contribute to an unsatisfactory concrete bridge.
Cracking due to shrinkage during curing or due to high fatigue will
I allow the penetration of water resulting in reduced service life.
Concrete can be susceptible to expansion due to attacks by sulfites
present in water runoff or other sources. An excess of trapped water
in concrete will result in popping and spalling during freeze thaw
cycles. Highly permeable concrete may allow excess moisture to
penetrate to reinforcing steel. The resultant rusting and expansion of
the steel can result in spalling and other deterioration. These attacks
are exacerbated by the use of road de-icing salts (Barnhart, 1987).
II
24
Concrete construction is very dependent on weather conditions.
Heavy rains will produce complications during the placement,
finishing, and curing of concrete bridges. Cold weather is another
eivifoinntal conditioai that caa hamper if not prevent concrete
bridge construction.
Many of the problems noted with concrete can be mitigated or
eliminated in the controlled environment of a precast yard. Exact
proportioning of mixtures, combined with uniform mechanical
consolidation, and steam curing result in high strength, highly
impermeable uniform bridge components.
Precast elements are utilized in all the components of a bridge.
Concrete piling is very common for substructures. These can be
formed and poured on site or precast elements. Precast yards
produce abutments and wingwalls that can reduce on site labor
(Prestressed Concrete Institute, 1980).
Precast superstructural elements come in many different
shapes depending on span requirements and the available forms in
local precast yards (see Figure 2). Many of these shapes include an
integral decking system. Solid deck slabs are utilized in spans less
than 30 feet and voided slabs can span up to 50 feet with the
standard AASHTO HS-20 load (Prestressed Concrete Institute, 1980).
Channel sections and multi-stemmed sections can be utilized for
intermediate spans from 20 to 60 feet while double stemmed
sections can span 60 feet and more (Prestressed Concrete Institute,
1980). For longer spans exceeding 100 feet box girders, I-girder
sections, single stem sections, or bulb tee sections are available. The
bulb tee section is very common in Washington, Oregon, and Idaho
25
I ZSpread box Channel
Box Slab
24
Bulb tees
I ~ ~~AASHO -PCI _ __
Types 1-4 0 9 9 Voided slab
AASHO-PCI Box
Types 5-6
IL J Tee D 7 Double box
Composite sections Noncomposite sections
Figure 2. Precast Concrete moment Shapes
(Heins and Lawrie, 1984; Prestessed Concrete Insitute, 1980)
IIIII
26
(Godfrey, 1975). It is possible to have clear spans up to 180 foot
with bulb tee sections (Prestressed Concrete Institute, 1980). As
mentioned all of these sections have an integral bridge deck or can
I have a cast-i -place deck placed on top. This improves the bridges
* strength and provides a different wearing surface than the precast
element.
* Precast elements have many advantages over cast-in-place
concrete structures. The most important is the more consistent
I quality of the final concrete that results from the controlled
conditions of the precasting yard. In a precasting yard it is also
possible to prestress structural elements which provides additional
strength permitting longer clear spans. Precast elements can be
fabricated and assembled in a shorter period of time than
I cast-in-place structures.
Modern concrete has been refined to make it a superior bridge
material. It has many characteristics that highlight its value in
bridge construction. If not properly constructed on site or properly
prefabricated in a precasting yard concrete bridge structures may
have degraded performance that can be inferior to other materials.
Typically this is not the result and concrete construction results in
superior bridge structures. This is especially true if precast,
prestressed elements are utilized.
Previous Research
A poor bridge management program including negligent
inspections resulted in the collapse of the Silver Bridge in West
Virginia on December 15, 1967 killing 46 people. The actual cause of
27
the disaster was the failure of one of the structural eyebars due to
the joint action of stress corrosion and corrosion fatigue" (Ross,
1984). This disaster has had a ripple effect on state and county
bridge programs that continues to this day. Actions in Congress
include passing legislation aimed at identifying and rectifying the
problems with the nation's bridge infrastructure. Congress initiated
the Special Bridge Replacement Program (SBRP) in 1970 authorizing
$816.5 million over eight years. Since that first action there have
I been three modifications to the legislation. Most recently the Surface
Transportation and Uniform Relocation Assistance Act (STURAA) of
1987 extended the Highway Bridge Replacement and Rehabilitation
Program (HBRRP) authorizing $1.63 billion annually until the end of
fiscal year 1991 (Secretary of Transportation, 1989).
I The HBRRP allows for federal payment of up to 80 % of the
costs of a bridge project. Money is allocated to states by the FHWA
in accordance with an apportionment factor. The apportionment
* factor is the ratio of the states needs compared to the national needs.
States needs are defined by a standard sufficiency rating assigned to
the bridges on the national bridge inventory. The sufficiency rating
is based on the most recent AASHTO "Manual for Maintenance and
Inspection of Bridges". Bridges are evaluated for three general
categories and relative percentages: structural adequacy and safety
(55%), serviceability and functional obsolescence (30%), and
essentiality for public use (15%) (Secretary of Transportation, 1989).
The greater the number of bridges with low sufficiency the greater
the needs of the state.
28
Funding and emphasis on the national level has generated
research into all aspects of bridge programs. Some of these reports
provide insight into present practices and utilization of materials in
short span structures. In April 1974 GangaRao and Taly (1976)
conducted a national survey of short span bridges (75 feet and less).
A questionnaire was sent to the "Chief Bridge Engineers" of all 50
stateF. Useful information was obtained from Idaho and Oregon but
only general information was included about Washington state since
it was not one of the 46 respondents.
The survey revealed no national standard in bridge
construction although the majority of states utilized AASHTO and the
FHWA standards as "guiding criteria" for bridge widths. The
predominate form of bridge decks were cast-in-place concrete.
Timber decking was the only other form of bridge deck mentioned.
It was utilized under "special conditions" in Louisiana, Minnesota,
and Wisconsin despite its "high material costs" (GangaRao and Taly,
1976). The advantage of the timber decks was the simple
installation enabling the work to be accomplished by state crews.
Short span superstructures are almost exclusively "...slab or
beam-slab construction." Idaho reported 1 steel girder, 163
prestressed concrete, and 137 reinforced concrete short span bridges
3 built during the 10 year period (1964-1973). Oregon's Chief Bridge
Engineer reported 7 steel girder, 220 prestressed concrete, and 173
* reinforced concrete short span bridges built during the same time
frame (GangaRao and Taly, 1976). It was unclear from the available
I report documents if these numbers represent all bridges built in the
state or only those for which the state agency was responsible. It is
I
I 29
interesting to note that during a similar time frame Wallowa County,
Oregon constructed up to 150 prefabricated steel bridges with county
crews (Godfrey, 1975). Therefore it is believed that the information
from GangaRao and Taly's survey represents bridges constructed
only by state agencies. Washington state did not respond to the
survey, however; GangaRao and Taly noted that Washington used its
own standard prestressed concrete I and box sections for bridge
construction (GangaRao and Taly, 1976).
I A questionnaire was also utilized in the National Cooperative
Highway Research Program Report 222 "Bridges on Secondary
Highways and Local Roads Rehabilitation and Replacement". It was
sent to the 50 state highway agencies. In addition, site visits were
conducted to ten of the state transportation agencies including
I Washington Department of Transportation and one local
transportation agency, the Washington County Road Administration
Board. Information, predominantly from the state officials, indicated
* steel beam bridges were the most common type of secondary
highway bridge superstructure in the nation. Following steel beams
I in order of frequency were timber beams, concrete beams, concrete
slabs, steel trusses, prestressed concrete, concrete arch, and box
beams. The most common type of structure involved in bridge
failures were steel trusses followed by timber, steel beam,
prestressed concrete, stone arch, concrete beam, and "others". It is
* important to note that the two principle causes of failure were
believed to be overloading and collision rather than deterioration
I (NCHRP Report 222, 1980).
II
30
Hill and Shirole (1984) examined 3,692 bridge replacements in
IMinnesota from 1973 to 1983 for spans up to 100 feet. Of this total
1830 were constructed of concrete, 693 of steel , 564 of prestressed
Iconcrete, 841 were of timber and the remainder attributed to
I masonry, wrought iron, and aluminum. They found that in
Minnesota there appeared to be a trend away from cast-in-place
concrete. The reasons cited were the "... time consuming falsework,
formwork, cure, and field quality control for such construction during
Minnesota's limited construction season." Prestressed concrete
beams were found to be "...15 to 20 percent more economical..." than
steel beam superstructures. In addition with the shallow depths of
I double-T, bulb-T and quad-T precast sections, grading work for the
approaches was reduced which eliminated costly site work. One of
I the noted advantages of steel and timber bridges over concrete
structures was that these materials could be constructed year round
as opposed to concrete structures which required special
I considerations during the harsh Minnesota winters (Hill and Shirole,
1984).
I Sprinkel (1985) took the results of NCHRP Report 222 and
focused on six prefabricated systems believed to be most frequently
utilized. The six systems, all constructed of concrete, were: precast
I concrete slabs, precast box beams, prestressed I-beams, precast deck
panels, permanent bridge-deck forms, and parapet and rail systems.
I He developed a questionnaire that was sent to "most" of the bridge
engineers in the fifty states and the District of Columbia as well as
other major bridge agencies such as Alberta, Canada. Sprinkel found
I that the use of prefabricated elements has continually increased and
I 31
Iwas predicted to continue. Use of prefabricated elements increased
because of reduced first cost and accelerated construction. Sprinkel
found that first costs have far greater weight in bridge selection than
life cycle costs. However he noted that bridges on low volume roads
Ishould be designed to reduce first costs vice maintenance costs.
More money may be spent on initial construction than could ever be
I realized in reduced maintenance costs over the life of the bridge.
The inverse is true for high traffic density bridges (Sprinkel, 1985).
I The available literature revealed common characteristics
considered in bridge material selection. The Prestressed Concrete
Institute emphasized the following factors in its publication on
I selection criteria for short span bridges: "...wide use and acceptance,
low initial cost, minimum maintenance, fast easy construction,
minimum traffic interruption, simple design, minimum depth/span
ratio, assured plant quality, durability, and attractivene.s"
(Prestressed Concrete Institute, 1980).
j Report 222 of the National Cooperative Highway Research
Program, ("Brilges on Secondary Highways and Local Roads
Rehabilitation and Replacement", 1980) found the following factors
universally considered on almost all bridge designs: "... required
structural capacity, traffic volume, anticipated future use, labor
I required for replacement (in-house or contractor), and cost." In
addition the report cited other site specific factors with various
I degrees -'f importance: experience, available c, .tractors, budget
constraints, material availability, and environmental priorities
I (NCHRP Report 222, 1980).
II
32
A value engineering study conducted on the selection of low-
volume road bridges (GangaRao, Ward, and Howser; 1988)
concentrat,.d on spans of 30, 60, and 100 feet with an average dail
traffic volime of less than 200 vehicles per day. This study
identified seven criteria as the most important for bridge system
selection: "... initial material cost, ease of construction, maintenance,
durability, service life, availability of materials, and unit weight of
bridge system" (GangaRao, Ward, and Howser; 1988). Twenty eight
designs were analyzed and estimated for first and life cycle costs.
These costs were nJLed as a function of six factors: supply an.
demand for the bridges, familiarity of local contractors with the
design, long term performance, ease of erection, maintenance and
rehabilitation, infltionary -rends of materials used in bridge
components, and availability of materials in the local area (GangaRao,
Ward, and Howser; 1988).
All of these studies provided a good foundation for research
into short span bridge materials in the northwest. They provided
insight into what has been accomplished in this field for other
geographic locations.
IResearch Methodology
Many short span bridges are off the primary road system.
County public works authorities are primarily responsible for these
I bridges and were chosen as the primary source of information for
this research. Various methods were considered to collect the
required information. Phone interviews were considered impractical
considering the total number of counties (119) in Idaho, Oregon, and
Washington and the restricted time for the study. A survey was
considered the most efficient way to gather information on short
span bridges.
The maximum length of the survey was limited to three pages
with a total of 20 questions. A questionnaire of this length could
include all desired questions and could be answered by a
knowledgeable county engineer in 15 to 20 minutes. A longer
survey would have added limited additional information but would
have added additional response time. It was felt the additional time
would discourage more officials from responding.
The original questions were formulated into a trial survey. In
order to confirm that the research objectives would be met by the
questions and that all questions were clear and answerable this
survey was reviewed by two Snohomish County bridge engineers.
Both engineers were interviewed about the Snohomish County bridge
program and short span bridges in general. Then each question in
the trial survey was reviewed with them in detail. From these
interviews the trial survey was modified to form the final survey
I (Appendix A). The answers to question eight were modified as a
result of the trial survey. Cast-in-place and precast concrete were
I
I 34
Icombined into the single answer, concrete. This was done to simplify
3 the response. Most county engineers know what material an old
bridge is constructed of but do not necessarily know how it was
I constructed. For all other questions, cast-in-place and precast
3 concrete were considered separately. The literature revealed that
cast-in-place and precast have different levels of use because of the
_ different construction techniques. It served the purposes of this
research to consider them as separate materials.
IThe first six questions about staff size and work load, allocation
of funds, budget sources, code requirements, number of bridges, and
average daily bridge traffic (ADT) were developed to determine if
3 these factors influence material selection. Additionally this
information provided background information on each county and
I the emphasis which each county placed on bridge replacement.
It was desirable to determine what type of materials were
used in existing bridges and those proposed for future bridges.
* Questions eight and nine probed the number of deficient bridges and
the characteristics of those requiring replacement. Typically a
Idistinction is made between structurally deficient and functionally
obsolete bridges. To simplify the responses this was not done. It
was assumed that the number of structurally deficient and
functionally obsolete bridges was distributed in the nearly 1:1 ratio
as reported by the Secretary of Transportion in 1989.
-- The objectives of questions ten and twelve were to determine
present and future trends in material selection. Question ten focused
on future choices and question twelve focused on bridges constructed
35
in the previous three years. The impact that length of span has on
bridge material selection was another aspect of question twe!ve.
In the literature review, a number of citations emphasized the
advantage of erecting wood and steel bridges with "in house"
personnel. Question eleven was specifically written to determine
how recently completed county bridges were erected.
Costs were a primary focus in most of the literature on bridge
repair and replacement. Typically these costs included only those
related to the construction of a new bridge. Life cycle costs and user
costs were rarely considered in documented bridge costs. The
established standard in the literature expressed costs in units of
dollars per square foot of bridge deck. Typically these costs were
taken from the final price of a construction contract. In question
thirteen the average costs for bridges construrted from 1988
through 1990 were requested in units of dollars per square foot of
bridge deck.
Material availability can influence material selection. The
number and proximity of material suppliers in a region are
significant indicators of material availability in a county. This
information was requested in question fourteen.
U Respondents were requested in question 15 to weight the
utilization in bridge substructures, superstructures, and deckings of
cast-in-place concrete, precast concrete, steel, and wood. The scale
ranged from I (low utilization) through (10 high utilization). It was
surmized that a comparison of the average answers for each material
I -would provide information on the frequency of use of the four
primary bridge materials. Materials receiving higher averages would
I
UI 36
be considered the most desired and utilized materials for that bridge
* component.
Questions 16 through 19 individually focused on one of the
I subject materials. In each question the respondents were asked to
numerically rate one of the four materials on eleven factors. The
rating scale ranged from 1 (Disadvantage) through 5 (Advantage).
Averages would be determined for the each of the eleven factors for
the four materials. It was hypothesized that a comparison of the
averages for each factor in each question would provide information
on the perceived advantages and disadvantages of each material. A
comparison of the averages between the four materials for each
factor would provide the relative advantages and disadvantages of
each material.
The factors for questions 16 through 19 were: "simple design",
"familiarity in the department", "material cost", "material
availability", "initial construction cost", "contractors familiarity",
"speed of construction", "low maintenance", "durability", "funding
availability", and "aesthetics". Ten of the factors were those
addressed in prior research and emphasized in the literature. An
additional factor, "funding availability", was stressed as being
important by the Snohomish county bridge engineers and was
included as the eleventh factor. A twelfth answer "others" was
included for unanticipated factors.
An explanation is provided to clarify the significance of each
factor. The design of a structure varies depending on what material
is chosen. The first factor, "simple design", questioned if the design
process had any influence on material selection. Some materials are
1 37
Ueasier to utilize in bridge design because of simpler connections,
more uniform material responses, and more consistent quality of
materials.
- Often times a material is chosen because it is familiar to the
county officials and to contractors that construct bridges. Yet this
may not be the best material if all factors are considered. It is
possible materials with superior characteristics are not considered
because they are not familiar and are not utilized regularly. The
i queston about "familiarity in the department" and "contractors
* familiarity" were included to determine which materials were most
familiar to the owner and the contractors.
* The cost of a bridge is reflected both by the initial costs and
other costs extended over the service life of a bridge. How material
i• selection affects the cost of installation of a bridge is reflected by"material cost" and "initial construction costs". It can be assumed,
with all other factors being equal, the least costly combination will be
the most popular. It was assumed that respondents would consider
"in place" material costs including transportation and placement.
3 Indirectly "speed of construction" can also have immediate cost
effects although they are not as obvious. Normally, reduced
construction time equates to reduced construction costs. In addition
* faster bridge construction means reduced bridge closer time which
reduces user costs. "Low maintenance" and "durability" are
important factors effecting the economics of a bridge. Materials that
require little maintenance and have high durability will typically be
I more cost effective for the entire life cycle of a bridge.
i
I 38
"Material availability" is effected by fabrication time, shipping
distance, and the number of suppliers within close proximity to the
county. Materials that are not available cannot be utilized. Those
I that are procured from a great distance require transportation costs
that typically raise costs and make them less competitive. Long
fabrication time may make a material less attractive, particularly if a
bridge is "out" and must be replaced expeditiously. A limited
number of available suppliers may result in a backlog of orders,
reduced competition and increased cost of the material.
There are a number of sources of funding available to local
authorities other than county revenues. These funding sources may
have requirements that influence a number of aspects of a bridge
project including material selection. If a county official desires to use
state or federal funding the requirements of the funding source must
be fullfilled. For example the Highway Bridge Replacement and
Rehabilitation Program (HBRRP) requires that bridges funded under
this program must meet HBRRP standards and regulations and when
completed must no longer have any deficiencies. Since the HBRRP
I follows the AASHTO criteria for bridge design any county receiving
funding under the HBRRP program must comply with the AASHTO
criteria. It is also possible that state statutes stipulate that state
* funding be provided under the condition that bridge materials be
manufactured in state.MILEMARKER
* The objective of question 20 was to determine the relative
importance various factors had in material selection for bridge
substructures and superstructures. This question was formulated so
*respondents would weigh the importance of each of these factors
I
39
independently on a scale of 1 (least important) to 10 (most
important). The average of the answers for each factor would be
indicative of the more critical factors. Factors with higher averages
can be considered more important for superstructure or substructure
material selection. The factors were similar to those in questions 16
through 19 except for deleting "familiarity in the department" and"contractors familiarity" and including "total life cycle costs" and"environmental impact". This was done to explore the emphasis
I material selection has on total life cycle costs and the environment of
- the bridge site.
"Total life cycle" costs takes into consideration all costs of a
bridge over the required service period. This includes initial
construction costs, maintenance costs, repair costs, and replacement
costs if multiple structures are required for the service period.
During the interview of the Snohomish county engineers it was
noted that environmental concerns were having an increasing impact
on bridge designs and material selection. This was believed to be
particularly true for the substructures. Materials that are not
capable of long clearspans require intermediate bents that reduce
the hydraulic opening. Environmental concerns focus on pile driving
- that disrupts the flow of water. Additional concerns include the
possibility that substructure materials may leach chemicals due to
constant direct contact with fresh water supplies.
After completion of the final twenty questions the survey along
with a cover letter were copied in sufficient quantity to mail to the
I target sample population. County officials in Idaho, Oregon, and
* Washington were chosen because they were a manageable sample
I 40
Ithat would be representative of trends in the northwest. Most
- previous studies on short span bridges surveyed state highway
officials and did not explore county bridge programs. The
I] differences between county and state operating budgets, bridge
average daily traffic volume, staff, and maintenance organizations
may effect material selection. The counties were considered a more
n representative sample because the majority of short span bridges are
under the jurisdiction of county officials.
-- Addresses for the counties were received from the Idaho
Association of Counties, Association of Oregon Counties, and the
Washington Association of County Officials. The survey was mailed
to a total of 119 counties in the states of Idaho, Oregon, and
Washington comprised of 44 county clerks in Idaho, 36 public works
I officials in Oregon, and 39 public works officials in Washington.
From the returned surveys, the raw data was entered on a
spreadsheet to facilitate the analysis (Appendix B). In addition the
data for questions 1 throughl0 and 15 through 20 were analyzed
with the use of the microcomputer version of the Statistical Package
U for the Social Sciences (SPSS/PC+) software (see Appendix C). This
enabled analysis of the frequencies of answers to individual
questions. The low responses to questions 11 thru 14 did not justify
. the use of the SPSS/PC+ program for analysis of these questions.
Results
Out of the 119 surveys sent, 50 were returned for an overall
response rate of (42 %). The breakdowns by state are: 27 responses
(69 %) from Washington, 16 responses (43 %) from Oregon, and 7
responses (16 %) from Idaho, (Appendix D). The high response from
Washington counties may be attributed to a closer identification with
the university conducting the survey. Typically for surveys, higher
responses are anticipated when the survey is addressed to an
individual. For the counties in Oregon and Washington the surveys
were addressed to a specific individuals who was either the county
engineer, public works director, road master, or bridge engineer. The
surveys were addressed to the "county clerks" for the counties of
Idaho since the names of public works directors were not available.
This resulted in the lowest response from the counties in Idaho.
Of the 50 returned surveys two were blank ( one from
Washington and one from Idaho) because neither county was
responsible for any bridges. This resulted in a total of 48 completed
surveys with usefull information. However the total responses
varied for each question because some of the 48 respondents did not
answer all of the questions. Those questions for which information
was not provided were reflected in the raw data as blanks (see
Appendix B) and in the SPSS input as a 9 or 99 (see Appendix C).
Questions I through 10 typically had 46 to 48 useable answers.
Questions 11,13, and 14 were answered by approximately half of the
respondents. Question 12 had 43 useable answers. The questions
that rated material utilization and factors in material selection
(questions 15-20) had between 38 and 40 useable answers.
42
The majority of the counties 41 (82%) did not have a full time
bridge engineering staff. Seven counties had a staff that typically
consisted of a single engineer whose time was split between bridges
and other responsibilities. These seven counties either contained or
were in close proximity to a large population center. One of the
larger Washington counties, large in terms of number of bridges,
budget, and traffic density, had three full time bridge engineers.
However that county was the exception when compared to the other
county responses.
The majority of the counties (77%) spent between l and 75
thousand dollars on bridge repairs. One county had a repair budget
of 1.5 million dollars. Almost half (49%) of the counties spent f.:jm
30 to 200 thousand dollars on bridge replacement. The replacement
budgets of the other counties ranged in 50 to 100 thousand dollar
increments, from 250 thousand dollars up to the largest replacement
budget of 2.0 million dollars. Eight of the respondents did not have
any money budgeted for replacement.
The majority of the money available for bridge replacement
came from the federal government (Table 1). More than half of the
respondents (24 out of 43) received 75 to 80 % of bridge project
funds from the federal government. Thirty five (81%) of the
respondents received some amount of federal funding. In most
cases the next largest portion of a bridge project was contributed by
the county responsible for the project. Counties have provided
between 10 and 100 % of the funds of bridge projects. However;
67% of the respondents have provided no more than 25% of the costs
of a project. Washington, Oregon, and Idaho provided varying
I 43
IIIII
TABLE 1. Number of Counties that Receive Federal. State.and Local Funding for Bridge Replacement
Percentage of Federal State CountyFunding:
0% 8 (18%) 26 (61%) 2 (5%)
1-19% 2 (5%) 10 (23%) 8 (18%)
20% 2 (5%) 1 (2%) 14 (32%)
21-79% 12 (28%) 4 (10%) 14 (32%)
80% 19 (44%) 1 (2%) 0 (0%)
81-100% 0 (0%) _1 (2%) 5 (13%)
Totals 43 43 43
I 44
degrees of financial support. Washington state provided relatively
little funding for bridge replacement. The majority of the
Washington respondents indicated a typical funding apportionment
Iof 20% County and 80% Federal. Oregon counties also reported only a
I nominal amount of state funding. The counties in Idaho recorded the
highest amounts and frequency of state support.
I Fifteen years ago short span bridges were not constructed to
any national standard (GangaRao and Taly, 1976). Today, the
AASHTO bridge specifications are the most common standard.
According to this survey 24 respondents (54%) utilized AASHTO
codes and an additional 9 (20%) used the AASHTO codes in
I conjunction with state requirements. Of the remainder, 10 utilized
state codes and one indicated it followed FHWA requirements.
i The counties were responsible for a total of 4584 bridges. The
number of bridges in each county jurisdiction varied from zero to
350. The majority of the counties were responsible for less than 100
bridges. As expected, the majority of the bridges had low average
daily traffic (ADT). The breakdown of the number of bridges by
traffic volume is as follows:
*2928 low volume bridges (less than 400 ADT) (70%)
*1000 bridges with ADT between 400 and 2000 (24%)
*233 bridges with ADT greater than 2000 ( 6%)
Most counties (42) had at least one low volume bridge. Only 25
of the counties reported having at least one bridge with traffic
volume over 2000 ADT. Almost half (112) of the bridges with ADT
I greater than 2000 were in four counties that contained or were near
3 a large population centers.
I
46
TABLE 2. Number (and percentage) of Deficient Bridges by State
Material Washington Oregon Idaho Totals
Concrete 136 (31%) 18 ( 8%) 33 (37%) 187 (24%)
Steel 118 (27%) 29 (12%) 26 (29%) 173 (23%)
Wood 188 (42%) 184 (80%) 30 (34%) 402 (53%)
Totals 442 231 89 762
Note that information regarding the number of existing bridges of
each type of material was not obtained in the suivey.
47
III
TABLE 3. Number and Percentage of Bridges Constructed orUnder Construction (1988-1990 )by Length
Material Less than 30 to 60 ft. 61-120 ft. TotalsI 30 ft.
Precast 9 (38%) 23 (53%) 45 (83%) 77 (64%)
Cast in F.ace 2 ( F%) 6 (14%) 6 (11%) 14 (11%)
Steel 0 (0%) 12 (28%) 2 (4%) 14 (11%)
Wood 13 (54%) 2 (5%) . ._ (2%) 16 (14%)
Totals 24 (20%) 43 (35%) 54 (45%) 12iIIIIIIII
1 48
indicated that precast concrete beams were used on six 160 foot
spans..
Precast concrete will continue to be the dominate short span
-- bridge material. Four out of five new short span bridges will be
* constructed of precast concrete (Table 4). Only a few counties in
Washington state will use steel or wood for future bridges. Counties
I in Oregon indicate the number of steel and wooden bridges
constructed will small compared to concrete structures. The counties
_ in Idaho seem more flexible in the choice of bridge material.
Question eleven proved to be ambiguous, since there are two
possible ways of interpreting the question. The question was
intended to request the percentage of all new bridges constructed by
contract or county crews. For example the responses from one
county in Washington indicate 80% of ali new bridges were precast
concrete constructed by contractors, 5% were steel constructed by
contractors, 10% were precast concrete constructed by county crews,
- and 5% were wooden bridges constructed by county crews (see
Appendix B). This interpretation of the question reveals the most
*- information about the proposed materials and methods of bridge
replacement. However the majority of the counties interpreted the
requested percentage to be for each material. As an example one
county indicated that 100% of the cast-in-place, 100% of the precast
concrete, 100% of the steel, and 75% of the wooden bridges will be
constructed by contractors and 25% of the wooden bridges will be
constructed by county crews (see Appendix B). In either case a
I- review of the answers indicated the majority of new bridges
n typically will be contractor built precast concrete structures. The
I
49
I
I
H TABLE 4. Principle Construction Materials for New Bridges
i Material Washington Oregon Idaho Totals
U Precast 315 (90%) 152 (81%) 27 (36%) 494 (80%)
Cast in Place 21 (6%) 3 (1%) 26 (36%) 50 ( 8%)
U Steel 3 (1%) 16 (9%) 15 (20%) 34 (6%)
Wood 11 3%) 16 (9%) 7 (8%) 34 (6%)
Totals 350 (57%) 187 (31%) 75 (12%) 612
I
III
I
- 50
counties that do utilize "in house" personnel typically will construct
wooden bridges. A small number of precast bridges may be
constructed by county personnel.
I Most of the cost information was for precast concrete bridges
indicating that it was the most common bridge material (see
Appendix E). Bridge project costs varied a great deal due to the
effect of site conditions. A comparison of material costs within
counties indicated that wood was the least expensive bridge material
I followed by precast concrete. Averages for each material are
* presented in Table 5. The averages are deceptive because they are
based on relatively few responses and a small number of bridges.
* However individual county costs can be compared to the average
costs to determine if the bridge costs for that county are
i comparitively high. Only half of the respondents provided
information on bridge material suppliers. Comments made by the
respondents indicated that the degree of confidence
* confidence in the answers decreased as the distance in the question
increased. Respondents either knew the number of suppliers in the
local area (< 10 miles) or made educated estimates. However, as the
distance increased up to 200 miles, respondents had less information
I and made less accurate estimates (Table 6). Most of the county
bridges are replaced by contractors and it can be assumed that
county officials do not procure the bridge materials. Rather,
contractors are responsible for procurement of the spccified material
under the conditions of the construction contract.
To determine the future use of cast-in-place concrete, precast
concrete, steel, and wood in substructures, superstructures, and
II 51
Table 5. Average Costs in Dollars per Square foot of bridge deck.
UB _Cast-in-Place Concrete1988 1989 1990$70.00 (4 responses) $65.60 (5 responses) $112.5 (2 responses)
_ _ _ Precast Concrete1988 1989 1990$60.24 (15 $92.87 (15 $91.71 (10responses) responses) responses)
___Steel
1988 1989 1990$90.33 (3 responses) $89.00 (4 responses) $72.50 (2 responses)
_ _ _ Wood1988 1989 1990
$30.00 (4 responses) I$62.20 (5 responses) $49.00 (4 responses)IIIIII
U 52
IIII
I TABLE 6. Estimated Number of Material Suppliers
Material Less than 10 mi 10 to 100 mi, 100-200 mi..
I Precast 2 38 38
Cast in Place 28 57 26
Steel 3 23 21
Wood 9 35 27IIIIIIIII
53
decking county officials were requested to rate the subject materials
on a scale from 1 (low utilization) to 10 (high utilization). The most
highly utilized material in the substructure will be cast-in-place
concrete (Figure 3). Precast concrete will be the most utilized
material in the superstructure (Figure 4), and decking (Figure 5).
Steel will rarely be used for decking and only five respondents
* indicated it will have limited future application in substructures and
superstructures (Figures 3, 4, and 5). Wood will rarely be utilized in
the substructure and only four respondents indicated that it would
be utilized in the superstructure (Figures 3 and 4). Similarly only
four respondents indicated that wood will be utilized for bridge
* decks (Figure 5).
The advantages and disadvantages of cast-in-place concrete,
precast concrete, steel, and engineered wood were rated on a scale
from 1 (disadvantage) to 5 (advantage). The responses are
presented as; bar graphs in Figures 6 through 16. Average responses
for each factor are shown on the bar graphs under the material keys.
Examination of these bar graphs reveals the relative advantages and
disadvantages of each material. It is apparent that precast concrete,
with the highest average answers for nine out of eleven "actors (see
Table 7), dominates all the other materials. Only cast-in-place
* concrete is considered a more available material and wood a more
aesthetically pleasing bridge material.
* Both low maintenance and durability are important factors for
the selection of both substructure and superstructure materials.
I Precast and cast-in-place concrete exhibit lower maintenance and
I
I= 54
I N 3U 30M 27
* BE 24R 21
o 18f
15R12"ES 9P
I 06
N 3SE 01 .. I=XMALS34 7-'8 9-10
RESPONSES (10 -High Utilization)O Wood OSteel F3Cast in Place OPrecast
Average Values: 2.29 3.66 8.53 3.31
Uz n Figure 3.Utilization of Materials in the Substructure
INN 30
M 27BE 24
21
o 18f
15
R 12E -
SPI 0N 3SE-- S O 'J
0-2 3-4 5'6 7-8 9-'10
RESPONSES (10 -High Utilization)I OWood GSteel 0 Cast in Place OPrecast
Average Values: 2.96 3.17 5.61 8.58
I IFigure 4.Utilization of Materials in the Superstructure
* 55
UUM 27BE 24R 21
o 18
0 15R 12 .E
* S9P
6N3
* SE0S
I RESPONSES (10= High Utilization)OWood OSteeI [SCast in Place ElPrecast
Average Values: 3.32 2.86 6.59 7.72FiF .a 5.l
*Utilization of Materials in the Bridge Deck
i 56
III
TABLE 7. Averages for the Prioritized MaterialSelection Factors
Priority Material Engineered 51&d Cast-Steleal PrecastSelection Wood Concrete ConcreteFactors
I I Low 2.1 2.27 4.09 4.37
Maintenance
2 Durability 2.07 3.12 4.22 4.28
3 Construction 3.49 2.66 2.91 3.53Costs
4 Material Cost 3.41 2.61 3.27 3.63
i 5 Material 3.51 2.98 4.13 3.67Availability
6 Speed of 3.59 3.22 2.41 4.57Construction
7 Simple Design 3.54 2.95 3.41 4.09
8 Familiarity in 2.9 2.54 3.42 3.79Dpt.
9 Contractor 2.88 2.78 3.77 3.87Familiarity
10 Funding 2.88 3.05 3.42 3.55Availability
i 11 Aesthetics 3.59 3.02 3.3 3.53
Scale for Answers 1= Disadvantage, 3=Neutral, 5= Advantage
III
II 57
have higher durability in comparison to wood or steel (Table 7,
Figures 6 and 7). These factors have a substantial influence on the
engineering economics of a structure. As mentioned previously the
I importance of these factors is magnified since counties typically fund
* all maintenance costs.
The differences in the maintenance and durability of concete,
steel, and engineered wood can be attributed to material properties.
Corrosion diminishes the durability of steel necessitating painting. A
I number of counties commented in the survey that the painting
* requirement of steel increased maintenance costs which eliminated it
as a bridge material. Although treated wood does not require
painting, maintenance costs for wooden bridge in general were still
considered too costly by the respondents. Comments in the survey
I indicated that more frequent inspections were necessary with
wooden bridges to insure that all connections remained tight. It was
felt that engineered wood was subject to deterioration and was not
considered as durable a material as concrete or steel. County officials
stated it was "...difficult to detect deterioration" in a wooden
structure. One official preferred to use wood more often but did not
because of the lingering concerns about longevity. Another official
- commented that the "...costs were high relative to life" and that
wooden bridges were not much cheaper than concrete. The
difference in maintenance and durability between precast concrete
and cast-in-place concrete is explained by the differences in the final
quality of the material. The controlled environment of a precast
yard usually results in a higher quality product than can be
*. produced with concrete placed under field conditions.
IN 3058M 27B2TE 24R 21
0 18f
R 12
S
EN 0 *..
RESPONSE VALUES (5- Low Maintenance)I0Engineered Wood 0 Steel ~Cast-in-Place *PrecastAverage Values: 2.10 2.27 4.09 4.37
-Cmaio Figure 6.Compaisonof RequiredManenc
N N0U 3M 27BR 24
0 18
R 12E
N 3
SI123 4 5RESPONSE VALUES (5= High Durability)
E3 Engineered Wood MSteeI K3Cast-in-Place 0PrecastAverage Values: 2.07 3.12 4.22 4.28
Comparison of Material Drblt
59
The next most important factor was construction costs (Table 7 and
Figure 8). Here there is a marked difference between precast and
cast-in-place concrete. The higher average for precast concrete
indicates that the prefabrication of bridge components greatly
reduces construction costs. One county noted that the trend has been
away from cast-in-place concrete because of the time required for
formwork, the fact that falsework can interfere with stream flows,
and the poor quality of the finished concrete.
Material cost is one of the major components of construction
costs. Some respondents may have considered these factors too
closely enmeshed to be able to distinguish them individually. This is
most evident by noting the neglible difference in the average
answers for "construction costs" and "material cost" for steel in Table
7 and Figures 9 and 10. Steel has high construction costs which is
partly due to low material availability and high material cost.
Conversely precast concrete and engineered wood had the lowest
construction costs and were the least expensive materials.
Cast-in-place concrete appears to be a more expensive material than
* precast concrete and engineered wood even though it is considered
the most available material (see Table 7 and Figures 9 and 10). It
appears that respondents typically consider "in place" material costs
I such as placement and finishing for cast-in-place concrete which
includes labor costs. This would make cast-in-place concrete a more
I expensive material.
Speed of construction can be expected to have a direct
I relationship with the cost of construction and the availability of
material. Materials that can be constructed in a shorter period of
N 3060U 3M 27B IE 24R 21
0 18f
15R 12ES 9P
06N 3
E ME....0S
4 235RESPONSE VALUES (5=Low Costs)
0Engineered Wood ~Steel gCast-in-Place 0 Precast
Average Values: 3.49 2.66 2.91 3.53
Compriso ofConstruction Css
*N 30UM 27B
R 21
0 18f
15R 12E
0 6 nN S
* 1 2 345
RESPONSE VALUES (5=Low Material Costs)
E0 Engineered Wood ~Steel ICast-in-Place 03 Precast
Awerage Values: 3.41 2.61 3.27 3.63
Figure 9.Comparison of Material Costs
61
time can have lower construction costs. Projects will be completed in
a shorter period of time if material is readily available. Precast
concrete and engineered woxd both are readily available and have
relatively lower construction costs (Figures 8 and 10). As predicted
they also have the shortest construction times (Table 7 and Figure
11). Conversely cast-in-place concrete appears to have the longest
construction time. This is not due to long lead time in procurement
or material characteristics, rather it is due to construction methods.
A great deal of time is required to build the forms; install the
re'iforcing steel; place, finish, and cure the concrete; and finally strip
the forms.
The design of a structure and l'ow familiar the material was to
county o.-icials and contractors did not have the same economic
emphasis as the previous six factors and therefore was not as critical
in material selection. County officials felt concrete design was
familiar both in the department and to contractors who bid upon
county contracts (Table 7, Figures 12, 13, and 14). Steel designs
appear to be more complex. Steel is not as familiar to county
engineers and contractors as concrete (Table 7, Figures 12, 13, and
14). It appears that with the increased utilization of precast concrete
I county officials have not considered short span steel bridges and
have become unfamiliar with the material.
Replacement of county bridges are funded to a large degree
from sources outside county revenues. The federal government is
the primary source of funding. Funding is readily available for
I concrete bridges and to a lesser extent for steel structures. It
appears that more respondents felt that less funding was available
III I IIII
I 62NU 30
M 27BE 24R 21_
o 18
i 15
R 12E
*S 9P
o 6N 3
ES 2 3 45
RESPONSE VALUES (5=High Availability)
0 Engineered Wood MSteel 0 Cast-in-Place E3 PrecastAverage Values: 3.51 2.98 4.13 3.67
U Figure 10i IComparison of Material Availability
I NN 30U
M 27BE 24
RIR 21
o 18
15
R 12ESP0N 3SE0
2 3 45
RESPONSE VALUES (5= Fast Construction)
0 Engineered Wood M Steel O Cast-in-Place 0 PrecastAverage Values: 3.59 3.22 2.41 4.57
Figure 11.Comparison of Speed of Construction
II
63NN 30M 27BE 24R 2 1 _
o 18f
15R 12
ES .
06N 3S .
E 0M1 2 3 5
RESPONSE VALUES (5=Simple Designs)
0 Engineered Wood 0 Steel MCast-in-Place 0 PrecastAverage Values: 3,54 2.95 3.41 4.09
Figure 12.Comparison of Design Complexity
! NU 30U-
M 27BE 24R 21
o 18f
15
R 12ES 9N,Po 6N 3SE 0 .S f ; 3 45
RESPONSE VALUES (5=Familiar Material)
03 Engineered Wood C3 Steel Ed Cast-in-Place 0 PrecastAverage Values- 2.9 2.54 3.42 3.79
'i Figure 13.Familiarity of the Materials in the Departments
II
65N 30UM 27-BE 24_R 21_
o 18f* 15R 12P..E
P6
N 3
S
1 2 3 4 5RESPONSE VALUES (5= Familiar Material)
03 Engineered Wood DSteeI 0 Cast-in-Place 0l P recastAverage Values: 2.88 2.78 3.77 3.87
Famliaityof Figure 14.FamliaityofContractors with the Materials
N 30M 27-BE 24_
0 18
15R 12E
6IN 3 ....
E 1 3 ..SJ 4 5-
RESPONSE VALUES (5= Funding Available)QEngineered Wood OSteel ~Cast-in Place DOPrecast
Average Values; 2.88 3.05 3.42 3.55
H ComprisonFigure 15.ICompaisonof the Availability of Funding
0 N8
R B2E 2R 21
N 13
SI E 0FT1 2 345
RESPONSES VALUES(5=Aesthetir. Appeal)
03 Engineered Wood USteeI 63Cast-in-Place 0 PrecastAverage Values: 3.59 3.02 3.30 3.53
* Figure 16.Relative Aesthetic Value of the Materials
I 66
Table 8. Average Responses for Substructure andSuperstructure
Material Selection Factors (l=least important, 1O=most important)
FACTOR IMPORTANCE in IMPORTANCE inI SUBSTRUCIUIRE SUPERSTLJCTUREMATERIAL MATERIALSELECTION SELECTION
Maintenance Costs 8.43 8.57Durability 8.44 8.26IConstruction Costs 8.08 8.07Total Life Cycle Costs 7.95 8.07Material Costs 7.58 7.45
Material Availability 7.24 7.28Speed of Construction 6.80 7.07Familiarity of Design 6.18 6.32Funding 6.18 6.00RequirementsIEnvironmental 5.74 5.49ImpactAesthetics 4.30 4.55
II
III
67
as the number of material suppliers, was not as readily available and
were not answered with the same frequency or degree of confidence.
However all the responses proved valuable in determining which
materials are being utilized in short span bridges and what factors
influence material selection.
I
Summary
Rarely does a county public works director assign an
engineering staff full time to the county bridge program. Time
constraints and other responsibilities may limit county engineers
from exploring multiple bridge replacement options, choosing instead
an expedient "standard design" commonly utilized in the county.
_- Federal funding of county bridge projects was anticipated since
the HBRRP authorizes the FHWA to fund up to 80 % of projects on the
- national bridge inventory. This may result in many counties
deferring bridge work until federal funds become available,
allocating limited county resources to other equally or less pressing
requirements. In Washington, Oregon, and Idaho; state funding
typically is not allocated to bridges off the Federal-aid system.
I County officials are responsible for funding the maintenance of
the bridges under county jurisdiction. Limited maintenance budgets
I influence county bridge designs and material selection. County
* engineers are encouraged to choose materials that require low
maintenance despite high initial costs because the federal
government will fund up to 80% of a bridge project. These low
maintenance costs reduce the total annual county maintenance
expenditures. In some locations bridge materials with high initial
costs and low maintenance requirements may not be the most
economical in terms of overall life cycle costs. However, such
materials are attractive to county officials because a larger portion of
the total life cycle costs are funded by the federal government "up
I front" thereby reducing county expenditures.
II
n 69
U There are twice as many existing wooden bridges requiring
replacement than either concrete or steel. This may be due to the
total number of existing wooden bridges being greater than the total
I number of existing concrete or steel bridges. It is also possible that
the majority of existing wooden bridges are older than existing
concrete and steel bridges. Wooden bridges may not be as durable
3 for the majority of site conditions encountered. Most respondents
indicated that wood is not as durable as steel, cast-in-place concrete,
* or precast concrete and has the highest maintenance costs of all three
materials. Inadequate maintenance would have the most significant
impact on wooden bridges resulting in deterioration and earlier
replacement. Limited county budgets may have restricted the
minimum levels of required maintenance.
Most bridge costs are established from the final price of
construction contracts. However each bridge site is unique with
many variables that effect design and make it difficult at best to
compare costs between materials. Bridge costs are influenced by:
site conditions, time of construction, design, material costs, and
competition. Material cost is only one of many factors that
determine the overall cost of a bridge project. The costs provided by
the county officials (see Appendix E) reflect this variability. The true
indication of the economics of the different materials can only be
determined by considering each bridge site individually and
performing an economic analysis on each site fui each material.
Bridge selection is significantly influenced by economics This
is readily apparent from the priority and weight given to factors in
Table 7. County officials gave greater emphasis to long term
70
expenditures such as maintenance and durability rather than short
term expenditures such as construction or material costs.
Upon completion, a bridge funded under the Highway Bridge
Replacement and Rehabilitation Program (HBRRP) must comply with
all HBRRP standards and regulations and be free of deficiencies.
Unlike concrete and steel wooden guard rails do not meet the criteria
of the HBRRP. The HBRRP follows the AASHTO codes as do the
majority of counties. Wooden guard rails do not meet the crash test
criteria of AASHTO and therefore do not meet the requirements of
the HBRRP. Since federal funding under the HBRRP is not available
for wooden bridges they will not often be considered.
- Conclusions
Concrete is the material of choice for most short span bridges.
Durability and low maintenance are the two key factors delineating
its superiority over steel and wood. Most substructures are
cast-in-place concrete while superstructures show a high utilization
of precast elements. For decking there is a slightly higher preference
for precast deck panels. In the future, four out of five new
superstructures will be built of precast concrete elements. The large
majority of bridges will be built by contractors and not county crews.
Precast concrete was considered the material with the greatest
number of advantages for utilization in short span bridge
superstructures and decking. Superior quality control of the finished
concrete along with faster construction has contributed to its
dominance over cast-in-place concrete. In forty years it has become
the dominant material for short span bridge construction and will
I show increasing use in the future.
* Cast-in-place concrete was the material with the second
greatest number of advantages. The noted disadvantages of
cast-in-place concrete are related to construction. Construction is
slower and construction costs are considerbly higher than precast
concrete for superstructures and bridge decking. However it is
easier and more cost effective to form and place concrete
substructures than it is to assemble precast elements. Cast-in-place
concrete does not require heavy lifting equipment which reduces the
placing cost in comparison to precast elements. This accounts for the
predominant use of cast-in-place concrete for bridge abutments,
footings, and retaining walls.
I73
Engineered wooden bridges have many positive factors that
warrant consideration. Wooden bridges have simple designs, low
construction costs, and can be constructed in a relatively short time.
I The initial costs for engineered wood superstructures may be
*economically competitive with precast concrete elements and more
economical than cast-in-place concrete or steel superstructures. A
number of counties use wood for superstructures and decking in low
volume spans under 30 ft. There is a potential for greater utilization
of engineered wood bridges considering the majority of low volume
bridges that exist and the fact that approximately one third of the
county bridges requiring replacement are under 30 ft.
Despite these observations, wood will rarely be utilized in
substructures and superstructures. Other factors outweigh the low
initial cost for wooden bridges. The maintenance required on
wooden bridges and their poor durability discourages greater
utilization. Although wooden bridges can be assembled with
semi-skilled labor, such as county crews, the majority of county
bridges are built by contract instead of by county personnel.
Wood preservers claim that wooden bridges can be expected to
last 50 years with contemporary preservation methods. However
the general consensus of county officials is that wooden bridges are
still subject to decay. This conception needs to be dispelled before
wooden bridges will be considered a viable choice for short span
bridges.
Steel is generally not considered by county officials for
substructures or superstructures of short span bridges, due to high
initial costs as well as painting requirements. The initial cost of
74
construction and long term expenditures are higher than concrete.
The small number of counties that do utilize steel structures consider
them only for spans between 30 and 60 feet.
Twenty two years after the Silver Bridge collapse in West
Virginia, county officials in the Northwest are very sensitive to the
importance and cost of bridge maintenance. Low maintenance and
* high durability are the two principle factors that influence the
selection of bridge materials. Materials that have these
* characteristics such as precast concrete and cast-in-place concrete
are typically chosen by county officials, even for bridges with low
traffic volumes. However, in isolated areas wooden or steel bridges
are still preferred over precast or cast-in-place structures because of
low initial costs and ease of erection. These counties are aware, as
recommended by Sprinkel, (1985) , that it is more economical to
reduce first costs rather than long term maintenance costs for low
volume bridges. The higher initial cost of a more durable and easier
to maintain bridge may never be recovered in the service life of the
structure.
Maintenance costs are funded completely by the counties,
however; the federal government will pay, through the Highway
Bridge Replacement and Rehabilitation Program, up to 80% of the
cost of a new bridge or rehabilitation of an old bridge. This funding
structure influences county officials to choose materials that have
low maintenance cost even if the initial costs are higher in
comparison to other materials. The federal government will pay a
large portion of the "up front" costs and county expenditures on
maintenance will be reduced over the life of the bridge. More of the
75
- total life cycle costs of the structure are paid "up front" by the
*federal government in lieu of over the life of the bridge by the
county.
The bridge infrastructure in Idaho, Oregon, and,Washington
_ still requires extensive rehabilitation and replacement. However
federal programs are in place that provide funding for county bridge
projects both on and off the Federal aid system. The HBRRP will
assist counties in funding bridge rehabilitation and replacement but
I additional funding is necessary if all existing ano future deficient
bridges are to be corrected.
Recommendations
Funding sources for bridge rehabilitation and replacement will
become exceeaingly limited with legislated reductions in the federal
budget. County officials may be forced to make bridge selections
that have lower initial costs. Shifting economic conditions may ha,'e
I a marked influence on the initial cost of materials. In particular,
rising energy costs will impact the cost of construction materials in
varying degrees. County officials should be aware of the ripple effect
that rising energy costs have on total life cycle costs for precast
concrete, cast-in-place concrete, steel, and wooden bridges. Economic
I analyses should be performed with designs of concrete, steel, and
wood to determine if reduced expenditures on maintenance justify
higher initial construction costs.
* Concrete clearly has many advantages over steel and wood for
short span bridges; however, it is still the material with the heaviest
dead load. Bridges that utilize existing substructures typically are
more economical. Due to the heavier dead load, concrete may not be
I
76
used on substructL :es which were constructed for steel or wooden
superstructures. County officials may need to work closely with
concrete producers to determine if a economical lightweight concrete
is available to utilize existing substructures.
Couity officials receive a large portion of rehabilitation and
replacement funding under the HBRRP. Bridges funded under this
Iprogram must comply with AASHTO criteria. Since wooden guard
rails have not been crash tested in accordance with the AASHTO
criteria they are not eligible for federal funding. Wooden bridge
fabricators should have a standard rail design tested and accepted in
accordance with the AASHTO criteria. Thi,; w-'uld make it possible
Ifor counties to seek funding for wooden bridges under the HBRRP.
Steel maintenance and fabrication costs must be reduced if
steel is to become a practical short span material. Steel producers
should concentrate on developing a true weathering steel for the
climates encountered in the Pacific Noithwest. This would eliminate
the painting requirement and would make steel a more economical
choice for the county engineers.
Further Research
Twice as many wooden bridges require replacement as
concrete or steel bridges. This wzuid appcar to validate the
consenisus of county officials who do nct believe wood is a durable
bridge material. Further investigation is warranted to determine the
I-eason more wooden bridges are in need of replacement than steel or
concrete
ICounty officials felt that steel and woou, n bridges were not as
economical as concrete bridge,. However few if any counties actually
I
I77
U keep records of complete life cycle costs. It would be beneficial to
conduct further research into life cycle costs. Case studies could be
performed on wooden steel and concrete bridges under similar
I conditions. All costs associated with these bridges could be
reconstructed to determine estimated life cycle costs. This would
provide further insight into which materials are the most economical.
IIII
IIIII
I
II
I
IReferences
Elsasser, H.B.,"Current Practices in Steel Construction", HRB SpecialReport 132. Systems Building for Bridges, Highway Research Board,National Research Council, Washingtion D.C., (1972) pp. 31, 32
I Erikson, Mervin 0., "Engineered Timber Systems for Short SpanBridges",(1989)
Godfrey, K.A., Jr., "Cutting Cost of Short Span Bridges", CivilEngineering ,(July 1975) pp. 42-46.
Hale, Charles C., "Static Load Test of Weyerhaeuser Bridge RailSystem", Weyerhaeuser Company Research and Development, April1977.
Heins, C.P. and Firmage, D.A., Design of Modern Steel Highway
Bridges, John Wiley and Sons, (1979)
Heins, C.P. and Lawrie, R.A., Design of Modern Concrete HighwayCBridges, John Wiley and Sons, (1984)
Hill, J.J., and Shirole, A.M., "Economic and Performance considerationsfor short-span bridge replacement structures", TransportationResearch Record 950, (1984), pp 33-38.
Kosmatka, Steven H., and Panarese, William C., Design and Control ofConcrete Mixtures 13 Edition ., Portland Cement Association, Skokie,
I Illinois, (1988)
"Low Cost, No-Care Bridge", Better Roads , (Feb. 1971) p.1 1 .
H "Modern Timber Highway Bridges a State of the Art Report",American Institute of Timber Construction, (1973).
Muchmore, F.W., "Techniques to Bring New Life to Timber Bridges",Journal of Structural Engineering , ASCE , vol 110 (Aug 1984)
Perin, S. "Multi-Plate Arch Bridge Replaces Old One Lane Bridge",Better Roads, (Jan. 1973) p. 20-21.
II
I 79
Peterson, Gary., " Timber Bridges: A Manual To Detail Easily Built,Long-Lasting Structures", Engineering Field Notes, Volume 19, UnitedStates Department of Agriculture, Forest Service (1987)
Pfeifer, Donald W., "Concrete in Systems Bridges", HRB Special Report132: Systems Building for Bridges, Highway Research Board, NationalResearch Council, Washingtion D.C., (1972) pp. 62-65Prestressed Concrete Institute., "Short Span Bridges Spans to 100feet", (1980)
Ritter, Michael A., "Timber Bridges Design, Construction, Inspe ction,and Maintenance", Jun., (1990).
Robison, Rita., "Weathering Steel: Industry's Stepchild"., CivilEngineering Oct., (1988).
Ross, Steven S., Construction Disasters: Design, Failures, Causes, andPrevention, McGraw-Hill Book Co., New York, N.Y., (1984)
I Sack, R.L., "Investigation of Precast and Prestressed Concrete Bridgesfor Low-Volume Roads"., TRB Special Report 160: Low-Volume Roads,Transportation Research Board, National Research Council,Washingtion D.C. (1975) pp 105-115
Sarisley, Edward F., "Construction Methods and Costs of Stress-Laminated Timber Bridges", Journal of Construction Engineering andManagement, ASCE Sept., (1990).
Sprinkle, M. M., "Prefabricated Bridge Elements and Systems." NCHRPReport 119, Transportation Research Board, Washington D. C., (1985).
"The Status of the Nation's Highways and Bridges: Conditions and3 Performance" and "Highway Bridge Replacement and RehabilitationProgram 1989" Report of the Secretary of Transportation to theUnited States Congress June., (1989).
Taly, N.B., and GangaRoa, H.V.S., "Survey of Short Span BridgeSystems in the United States," WVDOH 50-Interim Report 2, CivilEngineering Department, West Virginia University, Morgantown, W.Va. Jan., (1976).
Timber Bridge Information Center, "Crossings", Issue 1, Aug., (1990).
II
I 80
TRB Special Report 202: "America's Highways Accelerating theSearch for Innovation", Transportation Research Board , WashingtonD. C., (1985).
U.S. Steel, Highway Structures Design Handbook Volume 11, (1986).U
3 Virginia Highway and Tranportation Research Council, NCHRP Report222: "Bridges on secondary highways and local roads, rehabilitationand replacement", Transportation Research Board, National ResearchCouncil, Washington D. C., (1980).
3. "Weyerhaeuser Glulam Wood Bridge Systems, Technical Manualabout new and rehabilitated bridges"., Weyerhaeuser Company,(1980).
Williamson, Thomas G., "Steel, concrete, aluminum, and timber insystem bridges.", Highway Research Board Special Reports N132,(1972) ,pp 67-71
IIIIIIl
I
II Appendix A Cover Letter and Stirvey
IUIIUIIIIIIIIIIII
I UNIVERSITY OF WASHINGTONSEATTLE, WASHINGTON 98195
-- Departnent 01 C iil Engineering
September 4, 1990
Dear Sir,
We at the University of Washington (Graduate Program of Construction Engineering andManagement) are conducting a study of short span (less than 120 feet) bridges in counties inIdaho, Oregon, and Washington. The attached survey is focused on materials used in constructionof new short spans. The questions focus on the use of cast in place (CIP) concrete, precastconcrete, steel, and wood. The purpose of the study is to determine the role that various factorsplay in the selection of short span bridge materials.
This survey has been formulated so that it will take an individual familiar with the countybridge program approximately 15-20 minutes to complete. Your participation in the survey isI important for the success of this study. It is important that the survey be returned even if somequestions cannot be answered. !t will be most helpful ii the survey is returned by October 1,
* 1990.
In appreciation of your participation in this study a summary report of this research will beprovided. This report will provide you with information on how other counties are addressingthe replacent of their short span bridges. Your individual responses will be kept confidential.
We would personally like to thank you for taking the time to complete the enclosed survey.
Sincerely,
Jim Hinze John R. Brown
Associate Professor Graduate Student(206)-543-761 2 (206)-742-5605
II
SHORT SPAN BRIDGE SURVEY of IDAHO, OREGON and WASHINGTONCOUNTIES
INFORMATION ABOUT COUNTY BRIDGE PROGRAMCounty Name: State:1) Does the County Public Works Department have a full time bridge engineering staff?2) Number of county engineers assigned full time to bridge program?3) Typically how much is spent annually for bridge: Repair? $
Replacement? $.4) By percentage what have been the sources of funding for replacement?: % County
I_ _% State% Federal
5) What code or codes are used to design new bridges?(AASHTO, State, Other):
INFORMATION ABOUT COUNTY BRIDGESi 6) How many BRIDGES are under your county jurisdiction?
7) How many bridges have AVERAGE DAILY TRAFFIC less than 400 vehicles per day400 - 2000 vehic!es per day
more than 2000 vehicles per day
8) How many BRIDGES, which are predominately of the following materials, require REPLACEMENT?Concrete---> bridgesSteel -.. > bridgesWood -..... > bridges
9) What are the LENGTHS of the bridge-, requiring REPLACEMENT?Less than 30 feet bridges or %30-60 feet ----> bridges or .%60-120 feet---> bridges or %
10) How many new bridges will be made predominately of the following materials?Cast in Place Concree bridges or °/oPre-cast Concrete--> bridges or %Steel ----------- > bridges or %Wood --------.. > ..... bridges or _ %
11) What percentage of new bridges are typically built by the followi-ig sources?Contractor County Crews Other (.
Cast in Place Concrete % % %Pre-cast Concrete--> % % %Steel -----------... . > % %%Wood ----------- > % % %
12) How many new bridges were built or are under construction during 1988-1990 and what are theirlengths? total
Less than 30 feet 30-60 feet 60-120 feetCast in Place Concrete bridges bridges bridgesPre-cast Concrete--> bridges bridges bridgesSteel ----------.... > bridges bridges bridgesWood ------------... > bridges bridges bridges
II
13) What was the AVERAGE COST of new bridges (in $ PER FT of deck surface) for the followingmaterials? LM 18 i9Cast in Place Cc,'crete $_$ $Pre-cast Concrete--> $_$ $Steel ----------- > $. $ $Wood ----------- > $_$ $COMMENTS:
14) Please indicate the number of suppliers of the following bridge materials and proximity to thecounty?
< 10 miles 10 - 100 miles 100 - 200 milesCast in Place ConcretePre-cast Concrete-->Steel -------------- >Wood ------------- >
15) WEIGHT, [FROM 1 (Low Utilization) THROUGH 10 (High Utilization], the USE of the followingI materials in the components of new bridges:Substructure Superstructure Decking
Cast in Place ConcretePre-cast Concrete-->Steel -------------- Wood -------------
3 16) Rate the advantages of Cast In Place Concrete as a bridge material?Disadvantage Neutral Advantage
Simple Design 1 2 3 4 5Familiarity in Department 1 2 3 4 5Material Cost 1 2 3 4 5Material Availability 1 2 3 4 5Initial Construction Cost 1 2 3 4 5Contractor's Familiarity 1 2 3 4 5Speed of Construction 1 2 3 4 5Low Maintenance 1 2 3 4 5Durability 1 2 3 4 5Funding Available (State/Fed) 1 2 3 4 5Aesthetics 1 2 3 4 5Other( ) 1 2 3 4 5COMMENTS:
17) Rate the advantages of Pre-Cast/ Prefabricated Concrete as a bridge material?Disadvantage Neutral Advantage
Simple Design 1 2 3 4 5Familiarity in Department 1 2 3 4 5Material Cost 1 2 3 4 5Material Availability 1 2 3 4 5
Construction Cost 1 2 3 4 5Contractor's Familiarity 1 2 3 4 5Speed of Con,ruction 1 2 3 4 5Low Maintenance 1 2 3 4 5Durability 1 2 3 4 5Funding Available (State/Fed) 1 2 3 4 5Aesthetics 1 2 3 4 5Other( ) 1 2 3 4 5COMMENTS:
I
18) Rate the advantages of Steje as a bridge material?I Disadvantage Neutral Advantage
Simple Design 1 2 3 4 5Familiarity in Department 1 2 3 4 5Material Cost 1 2 3 4 5Material Availability 1 2 3 4 5Construction Cost 1 2 3 4 5Contractor's Familiarity 1 2 3 4 5Speed of Construction 1 2 3 4 5Low Maintenance 1 2 3 4 5Durability 1 2 3 4 5Funding Available (State/Fed) 1 2 3 4 5Aesthetics 1 2 3 4 5Other( ) 1 2 3 4 5
* COMMENTS:
19) Rate the advantages of Engineered Wood as a bridge material?Disadvantage Neutral Advantage
Simple Design 1 2 3 4 5Familiarity in Department 1 2 3 4 5Material Cost 1 2 3 4 5Material Availability 1 2 3 4 5Construction Cost 1 2 3 4 5Contractor's Familiarity 1 2 3 4 5Speed of Construction 1 2 3 4 5Low Maintenance 1 2 3 4 5Durability 1 2 3 4 5Funding Available (State/Fed) 1 2 3 4 5Aesthetics 1 2 3 4 5
Other( ) 1 2 3 4 5* COMMENTS:
20) WEIGHT, [FROM 1 (LEAST important) THROUGH 10 (MOST important], the RELATIVE IMPORTANCEof the following factors in the selection of new bridge MATERIAL:
for SUPERSTRUCTURE: for SUBSTRUCTURE:-FAMILIARITY OF DESIGN-MATERIAL COSTS-MATERIAL AVAILABILITY-CONSTRUCTION COSTS-SPEED OF CONSTRUCTION-MAINTENANCE COSTS-DURABILITY-TOTAL LIFE CYCLE COSTS-REOUIRED BY STATE/FEDERAL FUNDING SOURCE-AESTHETICS-ENVIRONMENTAL IMPACT-OTHER( ) -
If you would like a copy of the summary report, p;, ase provide the following information:(ALL OF YOUR RESPONSES WILL REMAIN CONFIDENTIAL)
Name ---- > TitleAddress---> Telephone->(-)
> _Zip
---> ____Zip_______
I
II Appendix B Summary of Responses
IUIIIIIIIIIIIIIII
a3 . . 1
~~O o~~ 0:00 ) N N OU
IN;-
~o C.4 OD
a In :: c -. . . . ..O
... .. ... .. .. .. ... ... .. .. ... .. ... .. .. .. .. .. .. ..... ... .. ... ... . .. ..... .. . .... ... .. ..C.. .. .... .. .. .. ... . ... .. ...... .. ..L...J. .. .. .
g3) oo oor-z~w) 00 Ngo tN0 C 0)0 )~C
b±.. : :~ : -
C: . . . .A.n, (D: in 0 :
&~o rOoO. -0!I
Z), ow
IP . .. ., . . . 2. .
o a
U..... ..................... .....................-- ------.. ... ... .
ODz 0' 0: to X:
C.4
w f,) M : tt)t
a w4
00:
L-1 0 : (N O : L
00 w
10! 0 0
0 0
I 0:CS: Lo . . .
*0 0
4 Intoy)4 t( : r ):D
~~'C ..w .8a . .
fA '.: : p a
4D 4F
41 (%' 4S 4' C. 4 15 V 6 a 6
3-W - ] 6 .g.
WI. 0 .w k: 0 *t (A aN. 0 -*634p8 £,..o m 40 2 I nC.s
. .0 -% 6A 6. 6 P , -. 6,.I,4. W*~~p :08 z; Cw g ' ' Sv
c 6. a Of 6P 6 : 40 o:P !
6. _ : 0)_ > ;I I:VI,4 A
.~ . . ..2.C 0) o
00
.............. ... . ...
0 00 lo:
c0 o00 :(4 0: t10 -CA:kAc)utt It C: 0Iw
o w)
a o a
0 r ' w w.
*0 0 ..2. . .. . . . .*~ on w~,.
a a w w ..z~~ a..a
'*4. (,4;wC
co: C4 :0:00
on~ w~*4
qS a
w2 .~ .zL..
0 £ : ao: ;aa
-~ qp
I. ...............w. .....a. .....m. .......................................................................... ....
Lo; Lf : . - . 'oy.4
m
a q i m a
0 0
... . .-o 0 OD. 4 vo1 .0
C.0 04: 00q
00'
-: *4: k'-
0: : z): C-)
00C
n~ w-
0 0a w
C) :4:: . . 0 '
; .
_ a
.D C .) 0C . . . . . .
*5- 3 Ca. -t: m
0: 0 . .::. .
~3 .c~CD .3f0 ( 54 4
Cr'
. . .~ . . . . .U
C:C
4o::-
4, .l i S1
I p p
O :wO .: 0 0:0'0: o.*~0 *o: 000f
..........................................................................0 0
0: 0 0: 0:
0:0:0:
00 0: 0'
6:0:0
00 ID:0
_a a
0 a a aI., o 0 0 0 0404:0)4
U.(A)0
o oo
a 00:
a :~ 0- epi
-C.. !c m eq3:-~~~40 0 : 0:
a~ *. .5 .~ N00 - OD: ci:0- *): C4: c. L6.: t
ao zW , rO:0A0&* c
: si:. j
Zi. i Go .-
3 1 : : 0: 0:.0; 0 0-.0.
. 0 : .. .0 .. . .N
0:0
o: 0:IA. 4, : :0
0F 00: 0: .). 0:.0: 0 0-C Go: O:
o ~: . ~OC-t 006
*~ Ia
CD
I 0: :0C C), inwD 0 ~ : D 0~jl:f: o )
c):: 0o t t : ::...t
0C :1) E) CA U') . .: : 6 : : :.. . 0 0
CC 0)
0:0 0
0:Z L : : o: uW7h' '
A:or C.6' i oAl640;
22 zz;ob:g. o4: :
C. - C : IA: :v GoC 2- oof Lw c .gw Si~ L.
6i o n.W ah d W ,- 6 i
4 h. *6L6 66 * 'A
U m 21: 1~ £A d 'A :00 :SfiIO .r . . . . .'of E u c o:M3l C.6 . (:u s;- 0
, 6E
U W U
0*0
0 *:
o 7-o -
o 0
,. ointo (A : N ) N ojlf tO . : : : : 'r- n ) 0:0 C:) tO tO10
0:0.
o: .D .) .
q 00 0 19C:0 ) o D n 0:0:
in:o to 00
:.qrp 40Ir
00 0o~ ~ 000a
......... 0..0. .... ...-...... ... ... ... ...... ... ...... ...... ...)... ... .......... ... ... ...... ........... ......
p o d v w .-
'cr A: ow, t
sq 0: 0:~
0 ~ p .a . a .. . ~. .~ A.7 .~ - L:
OV: 46- g*C : a Ck- r
m C 4 IA A" IA4 LiG:
6 . . . 6:. p:6i :6
A:I p ' l
a. . .
in~~~ 0; o 0; D
0 00 :N)
*:, 0 0 :0:0
000 pp:0W
. : : : : : 0
(=) 0 000 0D
0 0 0 0
:000
IA_ .~J . .
A :___________________ _____________________ ________________ ____________ _______________ ___________________________________
_________________3_________ ___________________________ f i__________________ lob i____________ I i__________________ ___________________________________________I .- 1 i6 0Iv E 6 op :2
-0 0000
00:0: 0::0 0:0 :0
32~ 000
...... ... ........ ...00 0 0 .m... ... ...... ... ...... ... ......0 0 0 0... ... ... ....... . .........
wI
'0 0 00
0:
0I 0 :0..........
0;~
IL _
vi
-4:a 6 :: II ~_ __ _ _ __ __A_ _
I4
IJD0 0)w0 0
00
0 : 0: 0
0w 0: 0 0
t'.A IT :
I' ..1 0
CD: o I 0 :: 0:
0; 0 :
44* 'A:
II 40:00 . . .
a 'A_____________________ _________________________I __________________________________ __________________________________________I ~k 6: VI:__ _ __ _ _
Ip
0 0 0 0: a w w m
0 0 c) o:w0
'T; :0:0 0: 0:000 a
0 0 0 : 0
0 0
00:
0: c o 0; 0
0;J 0 0::C
-: 0 0:
00000~ 0:
0: 000
............m. a
0:0
r a:
4p: 0. 10h b
IAIImL -_ _ _ _A_ _
I
q w0 0 0 0
o0
0
0:0
a a
*a
.. . ... . . .. .. .. . .. . . .. ... . ... ... .
6 ~ ~ .- ioI . __ _ _ _ _ _ _ _ _ __q0 :N O:
U';
.......I...... ..... ...... ... ... ...... ...... ...... ...... ...... ......... ......aI
.. . .. . .. . .. . .. . . .. . . .. . . .. . .. .. . . .. . . ..
0 0 q00
0 0 000
I a1q: :V : :_ : : :0
0400 0 0:
Ha.. ....... ...... . ..... ..... ... .......... ....... ...... .... .. . ... .. ... .... ... ... ...... .... .. . ..... ..... ........ ....
Ir4 O A: A:
.. .......*. ..... ...... .........-- -.... ....... ... ... ..... .... ... .. ... ... .. .. ..... ... .... ... .... .. ............
0 ~ ~*P ~:a :~ ) U ) a * ~ ~ a
:0:*
ii6 1A It 1 6:.'I64I_ C 0
.:0.
to 0
.D 0 0
n:o : 00 0:
~~ w~
00 0 0:0
0::0 0:0:
4-a
a . .. . . . . .
IA:
0 4.p
qo CL
F6 o, 0. 0 L 0
> -C ; 'A:.o
Of IA a W Ow' 0 'W.
I* IV&.A
0*0:
I0 IIL G
cI r 00
0:0
0: 0, 0
- C)O 0
.. ...... . ...0 0. ..... ...0 0. ... . ...... ... ... ... . ...
In...... . 0. .. .. .. ....... .... ...... ... ......
* 05
I 40
k" 4- 4p A, 4 4*V 6 : ) j 6- 4 -j 64 -F 3
-W: po.E:40 C: ~L)
40 40 o 0 i i
I ~c -W -W IA_ _ _ _ _ _ _ _ _
,VIA A
.. .....I. ...... ......m. .a. ......q .. ......... ........ ...... ...
..
tor
IA40 040
40 4: p jG 0 A 10 0
A. 6.*; P; a0*.:co r : :C: U.u 41 4P:40: 1: 0c c
IA IA:~0 %.4 UM IA M @
c 6
46
w .......m... ... .......... ... ....... ... ... .............. ... ....... ... .......... ... ....... ... ..... ...... ...... ...... ............
............. ............. ..... .......... . .... ....................................................................
C* o
0 0 co
q a (, -. :
..................U.. .....U. ............... ...........a .........
0: 00
M): 0: 0: 004 0 : 0
400
0IA * F
_____ a.__ ______ 41:.
I6
qI
Lnto OO 4
wI.. ..... .....w. .. .... ...... .. . ...... ... ... .... ...... .. . ...... ..... ............ .. . ...... .... ......0. .....
0w
In3
aIIw
w aiIa w
z a wQ
m q0
PA -WI.
I0I0G:J:I p , p
I :oU.91 06*
ar a0
........... ...... ...0...... ... ..........0.......... .......... ... ...... ... 1........ ........ .................a0mI
m
U..............
aI wm
............ 0 . 0. .......
0m a
C) 0 \: tn (4
wII
.4941~ 41
.- a
*p 40 0
*~ 1 i o* E . ~S
A:J 'A;. (M A O
: : . h. £ : I.
I . *'. .g . 0.V a.:a
0@ 0m- a
A. 01a
m1
3 1 0000.: 000 0 0fLn:Ifl.0 0Q 0 o 0 0 0H LO: 0: U): lo: . : N!:0: :: PA):I VO: : qD: t4::
00 0A
N~ a.
c)N)
'W N00):N
4*0
66
* .
I. ................................ ................................C
IA * wCS *o 6'U
Sob
I~~A 0.'.c ' 1 ~~
6 6 6 6 6.0.. 6i j A. 0 0 : : v 0 : ow
ob ; : ::a00.
*~~o .'A::3 .I, OA: 09: -p- IA A:
I A:'
w' 0
wit
0:o 00
: 000 0'd 0 :
c o)to 6icIto: ,o:4:I4:*
Caa
0a wHC
I I£
&L 'A . . ..00 . . . ... . .0 00
s. .. .. . .h. . . .
4p~~~~~ -4, * ,i- p4 A Gh.)
c ~1 I. c4~Li 0@
-4 1: E OO
____ ___, j__
I:cC: :r
... ... ..
* . ... : 84 3 0to m ~ 0 0.
tom a
6a a
ca. 0 0.-co Zi. . Ec8c cic1 O
cc)
a. .. . . .j>0
.0
0: I~~A.6.-1A ,_ _ 46! A6 *
ofCa., Av tIv 4 I.IIL.c, C
0*: 00 M0:Q
(N~~;0 0 : flf
M0D 0: ) 0 04 00 V:~~U U ~ NIt:W: )
.I . . . . . . . .
Im I _
* _ _ _ _ _ __ _ __ IU1 f - iiim iIia 6 ,o 6idi iO i6
i.~ . . .. . ... .. .. . . . . . . . .. . . .. . . . .. .
ImI t t4 rv.--t-V "t to
n00 C. 0 : 0 : 0 t): In :0I~~ IA C'J :l LONNCN) ;I
Ii
I) I .If tI tI )
I .. : . ... . .O .I .ON. C.4.2
c :0:0 3: 6DUO' u.: c : 0 4q;~t cfl1
IAI6
C) w3. wtootttC o ow
Mt V:o ('4: to) (,4 Vt V: t to
fI to: as: OD% z 0a' Kco 10tooi Un int c
IA
nop . *MN0 .i .w .! ....... b. ..i
CP. - 0 u4 *i A i(J6.: 6 l:
I SIl !2 g 6
vII.~ a w.
~0 0' U-C4C' UIf)0) V) N) 041 .N)N
*~ au
7 =w3: (Ai 3t . o m t4 )i:v 4;t
C:) 0. 0:I- rq.W)P) L7:M :M 1:1: tM~~~ a~U
m ..................... ...... ...... ...... ... ..
oIr )f)t )i . -U r i
I)I OD: ON: k__O__D(I_) 4 4I 1_ ptotnP mC -
0i 0 o:M 14) in: 02 mU)ttrV r):
a a
In t,3 -: o] to to: CI U) )
('4:
C: CL0: 4p: *o: 0: : )~L.:. W . ,*i*'
2 0 : of 4c : aiI o AI ~4 of_ _ _ __ _ _
Io ,r
Iw v
- -! -~ tO r) :N U) to - : - r4 : )
Iq
I ~ q1............. .. .. .. .. ... . .. .... .... ... .. ... ... ... . .. .. .. .. .. .. w. .... ..... ....
Imao - a
7 a............~~~~* .... ... ... ....... ...... ... ...... .......... ....... ... ... .... ..........C... ...... ..
wS a w0% (T'f0* o U),
m~~ 0 y*
*w a
0 C, (vc U n D
OD: OD O ) :LO ).O O L P'r rU
aI
t4): K) f4): tO f I)I) t4) t4)
.. .....I. ... ........................................................................... ......K) 4: r j) rIwtw
Um.. ..... . .. .. .....
Krr
I w:.,t <,:r) 4:(4 4T () U, .:r)I -! :
. .... .... .... .... .. .. .. .. ..... .... .... .. .. .... .... ......
... .... .... .... .... ...
m a £I nDr~lin r-S):in r- - u 1): : r) r~, n:r4 if .I) o ~
.. .............. ...... ...... ...... ............ .. .........................................Lba
IIT 1 O N.0r )C4 4 4:,,P)( ' r ,
... .. .. .. ... ... .... .... .... .. .... ..I.. .... .... .... .. ...... ..
1~ ~~~~~~~~~~ w__________________ a_________ ____________a__________a___
I.I~~ ~ ~~~ m qi ~*dtO~ -t
I~, oo : u0UU
IIN : -
a . :
... . . . . . . ..4. .. . ..-. . . .. . . ... . . . . . . .. . . . . . . . .. . .. . . . . . . . . .
r a z
....... ...... ... ...... ...... ...w.......... ......
aCD.
7 ) r r- tn r , : t;tr r V W N N W
I............................ ...W1 ....... .......... .......... ... ........ .............. .
t6i
Ii
N:) PA to A V: ;r Vf) t %t : V) to ('J. t 4 o ot w: N. toIt
KI IT toili ) t o ) M ' t4 O0 f4 ' i r4(4 tJ (4): r4
Iq
I
a 1 a
z qono
pn : :-r 0 j) r :n :. (1 : £ £4:f) : n :T
*~~~~~~ w.* T . ~q
w m aq~7- ....... .... ....... ......... ...... ...... ....w m1±.~~ wL. b
(I _____ ________tIL)V VU : N 4 ) 4 4
Iz
I I. ..........
I-:v q:h) ) -n r:v:t:0
to t n tvt t~ v h)c'0N K ~)k MI ~ to
I.......... ...... ...... ...... ... ......... ............. .......... ... ...... ...... .......
II taf) n )f) tf) 4:f) 4 4K
w w
a .... . . .. . . . .. .. .w . . .. . .. . . . . . . .. . . . .. . . .. . . .. . . ... . . .. . ... . . . . . . .. . .. . . . . . . . . . . .. . . ..a
w£0 E : :t:N:v U)j)V:K K )t 4:K )V 101'rt)K
C*d mmi:.w
pg6~*1 @ O .0 *cL' i.' O~,4 0 6* 60
q @ 0: r 011 f'" u s - - -5 0 :piC
: ." a - b *.w.6. 0 6*.Cc:4a
IA 'A
:a rI..: : : :0CL o:u . . U
I~~~ _ __ w
Iew
I ::
Ia w
I...... .... ...............
r4) ?n to t to U)n Ur ) wyt' t 1)C e )(4:4t)N M N f
in:)I tot : if) t: C4 (4:C CU-41 44U (4 )M: :
I..... .......... ...... ...... ...... ...... ...... ...... ...... ...... .......... ......4'w
4-7
0VVE l 4:Ni:I V n:i) V:Z:
% .... .... ....
a: a~w ~-2 .w~ 6 2
4. : 0 : 0
* .w~ .. . :4 . 4-. . .
6 i 6i M: pMe .ECE3:0#:A :f.Ewj, L&i Ui .. : i6 . 6 : ME61gC MiJ4 CIAE.V C E C i: of .. . . . .; 0: -P- 6 0 : .:6v S t 0*1 4 P*i) , i S EV EI*G P
)..w j~ C:o 0: E i :Q aIi iC w ' :0 i :Ai4 :C .*0 .P -__ _ _ -w : 4c 0 . : .I : : :*_i W EL_ _ __0: i p E 1
IQ q
-4v)to : (N N to I 4 ( to t: N, K N I
H.... .. . . . .. t ~ t ........ ... ..... .... .... ........N....
Nr: xr m v to: (4:~~tt N : : N : PAtN ; t : (N
IIAU~otttoUV~ttto NN Nto t toto Nto o t
I.... .. ...... .... .......ti: 0'": n: n n ) ) (N 4 4 :V
I...... .......... ... ...... ... ...... ...... ... ... .......................
0w. .~a .t!. .* .@ .*S..C A..S
I* I _ .
I o f
Iz
H Dini if))Ui )U) V) it U W f) VA) 10
.......I.............. ... ...... ... ...... ......
C.
C U
m .0
* Ut EA ~ Eq OE: 0i ** 0i 0
0: in r 0 g0 40 n. r. 0 .
h. .. P:-
c :"
I t6 Wi m0 .i*6 - 6 :*.: : - : : : : : :sql:0:6:IC:0
I0 .: . .0
II...... .... .............. ...... ... .......... ......
I.......................... .................... ....... ... ... .......... ......)~ iN .... .... .... ....
H~~ ~ w aN)NN
Ir:i : :JA r:j) -:i :in n :p : - :,r r ,r
.............. ........ ........)...U.... ......)...I....).-.........-.................-........N........-........N..-. .........tt...-..t
Io .........:T 4 o oIN : N:IN : :N:e.CJN)N)
.......N... ...)... ..... . ... ....... ...... .............. ......i... ....... .... .... ... ......... .
I .L:L:P:t:t:t n ) U) n 4:t:f) 'Z1)14:M t 4:N:1) f:t)In InIn InN) I
I a.
-0: - ..
:A u: I. -.. Ik * w .ioi u i6 4 U .
-- Lb. 4Fs:d PAUii:: o: :c A cA. C A: -
6i : *c f 0 u ! m6 i tin.6 I:: M
a$'I 'A:U1
I...... ....to t -In to (n In: In to to:t:t:m 0
I 4 to U-) h~rl ) to K)to - *14U) M: f4:tolO (,4op 4M. N
CD: jrtoMtteqiuC4:t' %:Jr:Uuu w:V I) U)utoU:1): M: U)) t o14:T:
J0.0 C ...
I4
a ' 6:w a ' E
0-w 4'i 0:fl - 0 'A
*wg6: *Q io: iZ]0 . a i VE' 0-~ : 00: a:P:ii 6
C. C @ C s: ci C4*. Se-*w"C 'A'. :;6.19E C
6i 4' 3 W" C 4':,a.6: i to 061 E 6 IGO4, i* CI _ _ o_ _ _ ~k A - :0 o-:E
IW E I W Wi* .
I D r.. .....I. ........... .... ............. ............. ............ .... ..
I ) r o w-:,omowot M:
t N ) In 4-t-4-4
5F 41 uuou
Ib6:O)IIAt6
i i6oi a i0 AC : :0I I p J4. 40
op: a 4, a 3 j' ON
c ~ .V 6 i I 0 i i pL.i o
_~W 4c.3~ * '.I' a" 'A :CU o IV;tm 4,~i.: Ca~~E 4p <2* 0 .g go"4 ~@ *::4~aof: of J: *L- **Vq" O.
. .S . .
NY Io (14 to4 (14 Mt Nl N- ON OD LO Nm r- r-Er-U3L fliE-oDo o -r r- r--U U f u ) tr
t4o to) N('A N C t (74 'tI in :0: O O0:0:0 oo) oooo) (ir,
I. .........................---............. ...........................
*w a
1D o D: U.. I 'N . M) N ', L Vt M 4I oV V )L: 0: (0 % :O: r: (% D
4? a h. .a . . .a * I .P
.m *0iW.g ' 'k 'A I.0 . .w:
I,. do: __ __ *_ _ A IAi0 ioI - = o *. 0 -
I0 D D 0 D D:0:t)N:h) DIw
In ol OD V) V)N tG o ) J'4 03' ) rd. ).... .... ..... .......... .....
I. ................ ...........................................03~~~~~" N))))):'NN ff
0 0b
0 0U:' US0O MO in
a hi C: 6Ja iA062i $A* _S 'A'
as~ Nim * 6 ; *CiE
a c
If *' __
U 0
............. ~w o o u .... ....... ..... 0....0....0.....
N. .r tn Ain: A 0 IAOv0 0 0 I vI inaIA 'O.2 a -):U-)
0) N~O tO N N t0 tA M: N) N NA N 03 IAU- 0% r-N WA 00 fIf
.. .. .. .... .... .. .. .... .... ..... .... .... .... .... .... .... ..... ..... ... .. .. .... .... .. .. ...
I.. o£t U) -:t :M r:0 :U) - :r ;U) (N r:U) -:f :v :r :j) % -: F
I................. .......... ...... ...... ...1r) rr W IT T:M t 000-3 3 0! 030 00 00 03
I
3m C: *ao . :% a
. .~* .w . . . ~ IA0- : C c
0 cI IA_ _I 'Ii$ Ad
N N to t o to 't c'4 (14 to *co vo ODt in r- in i&0):o o : '03:. oD
I.......
Int f t 1.rttt.o t' (4: 4t4) t: 0 0 0 0,7: O c i,0 c 0 0 n
I-O -iinnoDt 0 0
I0 .
*1D . 0
w wt (
......... ... ... ... .................................---- --------.... ............. ... ................ ...
U) LO 4 ~ *r) PO M) K) K )OD , )DO:
!OcO:!EN.,D:r::%D O: :oikD: D.. ...... .. .. ......~i
hw.
I ~UE
IA 4-_ U__40 F 01 C
IV1 i6Eo:i:o~ E0 A0 L A I I e
CT. ....... .................l~ f .. r64~ ~~~~ fa) to) Wo t qr mor ou-: - a' D - o s
IwI~~~~ ~~~ wl)f~bt~l~ofbJIl~Oo~lftlf
I('4~~~~ ....'o2 ~ 2 ' .... ...2u m
I3 .~tt t t n t~ . . . . . . . . . . . . .
r a 0
a w ~............... .......... .... ... ... .............. ... ....u :. ..... ............. ..
aZL.'o .w*' 7
oD .,@ M:":C
0. c" CD wOw
w w
Ita__ _ _ a_ _ w ___a
Iw
to' H 4) r ut in to nintointo to f4l)lfinninflnroet
int M to ftJo) ~ H)m 0 ~r erctl u-:o0 - nL) - - ~ e ~
to~~~~f~ W_ W) 0r t. r. Crm r0%
To t (N N Ito IN M- t O :N : : r:O (I OD:: :: o- -N Nr ,O(r:t 0co
........ .........................................
m qII 8:) a -- T U)w0 V ) r. )., 4 L r ) f ) ) ) C D L)i) U UU)L - O o 0 , '
.. . .. .. .. .. .. ..
: 'f'n w: inJ~ b i l N (4 p) - r -R
*w aw aU
I~~~~~~~ _______________________________Iq
U) ) N L ) LIN N)oo If)- O~rC N)-W N LOW ODU)%D0
I........
N N):
0i 0
@ .h. . . -k ' :0$A ON .£. . .. P- IA * %A i @i atj
A; ai a ' 0FAtiC.U:6IA
qpi ~ ~ ~ ~ ~ ~ ~ ~ ~ I iv. t ij W ziC p64:4:A -0-* 0i0:A A: M O:IA Sa ~~
I6i 'A_ _ :_ _ :6 W 4a fi E k'0 . ,
I: (:P: j ;C
w
t: .7 hij hL0 00 0 0 0 00 000000 0 0-
I ) D: r(' I0 0)NPe OE-:,: -'l NUh0 O:r-f-OD:--t r
I(4 1 r *1tf: r r 4: L)0 f%OJ '0) '0 '1o %fiDD O '0' 0c i ih u'
m a
. .. . .0 ( . . . . .
0~O ~ OD::V :-I~
IO (I% CK 0% Sr: Ou: M I) % S:a:r;00 - )
ME gi .. .g.u.;.;pc .: :: .5 . . ~it~ .6 EE Mi Cn : 0: ; j c
VIE~ SEo Im: PA0 #I*A-06~ . . SIi 6LI-:0 : :o 0 A E I'
I _ _W j-"0:A u mIic:m ~AE iw iC !0 E E G:4:*:A 0
I 134
I Appendix C SPSS Data Definition File and Data File
1
IIII
I
II
III
I include "bridgesl.def".DATA LIST FILE="BRIDGESI.DAT"/COUNTY 1-2 STAFF 4 STAFFNUM 6-7 MONEYRPR 9-12 MONEYRPL 14-17FUNDSCOU 19-21 FUNDSSTA 23-25 FUNDSFED 27-29 CODES 31 NUMBRIDG 33-35I ADTLT400 37-39 ADTBTWN 41-43 ADTGT200 45-47 REPLCONC 49-50REPLSTEE 52-53 REPLWOOD 55-56 REPL30 58-59 REPL60 61-62 REPL120 64-65NEWCIP 67-68 NEWPRE 70-71 NEWSTEEL 73-74 NEWWOOD 76-77I /SUBCIP 1-2 SUBPRE 3-4 SUBSTEEL 5-6 SUBWOOD 7-8SUPERCIP 9-10 SUPERPRE 11-12 SUPERSTE 13-14 SUPERWOO 15-16DECKCIP 17-18 DECKPRE 19-20 DECKSTEE 21-22 DECKWOOD 23-24CIPDESIG 26 CIPFAMIL 27 CIPMATCO 28 CIPMATAV 29 CIPCONST 30I CIPCONTR 31 CIPSPEED 32 CIPMAINT 33 CIPDURAB 34 CIPFUNDI 35CIPAESTH 36/PREDESIG 1 PREFAMIL 2 PREMATCO 3 PREMATAV 4 PRECONST 5PRECONTR 6 PRESPEED 7 PREMAINT 8 PREDURAB 9 PREFUNDI 10PREAESTH 11STEDESIG 13 STEFAMIL 14 STEMATCO 15 STEMATAV 16 STECONST 17STECONTR 18 STESPEED 19 STEMAINT 20 STEDURAB 21 STEFUNDI 22
I STEAESTH 23/WOODESIG 1 WOOFAMIL 2 WOOMATCO 3 WOOMATAV 4 WOOCONST 5WOOCONTR 6 WOOSPEED 7 WOOMAINT 8 WOODURAB 9 WOOFUNDI 10WOOAESTH 11SUPDESIG 13-14 SUPMATCO 15-16 SUPMATAV 17-18 SUPCONST 19-20SUPSPEED 21-22 SUPMAINT 23-24 SUPDURAB 25-26 SUPLIFEC 27-28SUPFUNDI 29-30 SUPAESTH 31-32 SUPENVIR 33-34I SUBDESIG 36-37 SUBMATCO 38-39 SUBMATAV 40-41 SUBCONST 42-43SUBSPEED 44-45 SUBMAINT 46-47 SUBDURAB 48-49 SUBLIFEC 50-51SUBFUNDI 52-53 SUBAESTH 54-55 SUBENVIR 56-57/DUMMY 1-19.
VARIABLE LABELS/STAFF "DOES COUNTY HAVE A FULL TIME STAFF"E /STAFFNUM "NUMBER OF ENGINEERS ON THE STAFF"/MONEYRPR "HOW MUCH IS SPENT ANNUALLY ON BRIDGE REPAIR IN K $/MONEYRPL "HOW MUCH IS SPENT ANNUALLY ON BRIDGE REPLACEMENT IN K $"/FUNDSCOU "SOURCES OF FUNDING % COUNTY"/FUNDSSTA "SOURCES OF FUNDING % STATE"/FUNDSFED "SOURCES OF FUNDING % FEDERAL"/CODES "WHAT CODES ARE USED TO DESIGN NEW BRIDGES?"I /NUMBRIDG "HOW MANY BRIDGES ARE UNDER COUNTY JURISDICTION"/ADTLT400 "# BRIDGES WITH AVERAGE DAILY TRAFFIC LESS THAN 400"/ADTBTWN "#BRIDGES WITH AVERAGE DAILY TRAFFIC BETWEEN 400 AND 2000"/ADTGT200 "#BRIDGES WITH AVERAGE DAILY TRAFFIC GREATER THAN 2000"I /REPLCONC "# CONCRETE BRIDGES THAT REQUIRE REPLACEMENT"/REPLSTEE "# STEEL BRIDGES THAT REQUIRE REPLACEMENT"/REPLWOOD "# WOOD BRIDGES THAT REQUIRE REPLACEMENT"I /REPL30 "# BRIDGES LESS THAN 30 FEET REQUIRING REPLACEMENT"/REPL60 "# BRIDGES BTWN 30 AND 60 FT THAT REQUIRE REPLACEMT"/REPLl20 "# BRIDGES > 60 FT < 120 FT THAT REQUIRE REPLACEMENT"/NEWCIP "# NEW CAST IN PLACE CONCRETE BRIDGES"I /NEWPRE "# NEW PRECAST CONCRETE BRIDGES"/NEWSTEEL "# NEW STEEL BRIDGES"/NEWWOOD "# NEW WOOD BRIDGES"I /SUBCIP TO SUBWOOD "WEIGHT THE USE IN THE SUBSTRUCTURE"/SUPERCIP TO SUPERWOO "WEIGHT THE USE IN THE SUPERSTRUTURE"/DECKCIP TO DECKWOOD "WEIGHT THE USE IN THE DECKING"/CIPDESIG TO CIPAESTH "RATE CAST IN PLACE BRIDGES FOR THE CHARACTERISTIC OF"I /PREDESIG TO PREAESTH "RATE PRE CAST CONCRETE BRIDGES FOR THE CHARACTERISTIC OF"/STEDESIG TO STEAESTH "RATE STEEL BRIDGES FOR THE CHARACTERISTIC OF"/WOODESIG TO WOOAESTH "RATE ENGINEERED WOOD BRIDGES FOR THE CHARACTERISTIC OF"I /SUPDESIG TO SUPENVIR "WEIGHT THE RELATIVE IMPORTANCE FOR SUPERSTRUCTURES"/SUBDESIG TO SUBENVIR "WEIGHT THE RELATIVE IMPORTANCE FOR SUBSTRUCTURES".
I
MISSING VALUE/STAFF(9) STAFFNUM TO FUNDSFED (99) CODES (9)NUMBRIDG TO DECKWOOD (99) CIPDESIG TO WOOAESTH (9)SUPDESIG TO SUBENVIR (99).
j VALUE LABELS/STAFF 1 "NO" 2 "YES"/CODES 1 "AASHTO" 2 "STATE" 3 "AASHTO and STATE" 4 "COUNTY" 5 "FHWA"
* /SUBCIP TO DECKWOOD 1 "LOW UTILIZATION" 10 "HIGH UTILIZATION "/CIPDESIG TO WOOAESTH 1 "DISADVANTAGE" 3 'NEUTRAL' 5 "ADVANTAGE"/SUPDESIG TO SUBENVIR I "LEAST IMPORTANT" 10 "MOST IMPORTANT".
I
aa
ERROR 1, Text: AAINVALID COMMAND--Check spelling. If it is intended as a continuation of aprevious line, the terminator must not be specified on the previous line.If a DATA LIST is in error, in-line data can also cause this error.This command not executed.
SPSS/PC+
This procedure was completed at 15:00:07set printer off.01 1 00 0015 0075 050 030 020 1 138 132 006 000 05 05 15 04 03 18 00 25 00 00100101010110010101100101 5555459443355454454433 2222222232244424342214 1009100910070908080105 1009100910090910080105
02 1 00 0014 0100 020 000 080 2 015 013 001 001 01 03 00 01 03 99 00 02 00 02100101010210010105050101 3534252454345334455443 3233334455432434243455 0510091008090809100908 0710091008101010100508
03 1 01 0035 0200 020 000 080 1 056 030 020 006 01 01 06 04 03 01 00 08 00 00100401010110010108080101 1515252443435554554434 2124232124431252421145 1005061010101010050105 1010100810101010050505
04 1 00 0050 0500 025 000 075 1 042 025 014 003 02 04 00 00 04 02 00 06 00 00080299990109999902089999 2234432333354433453333 2232333233322323231133 0504060607090810050302 0504060607080910050302
05 1 00 0000 0200 040 000 060 1 041 015 025 001 01 03 02 00 02 02 00 04 00 02100005050108020601080006 3435341333344343453332 1132333113355333453234 0909070909080805010505 0906050707070705010105
06 1 01 0099 0099 025 000 075 1 069 028 029 012 02 01 02 00 03 02 00 05 00 00070701010806010107050101 4435343444332334344443 3223232143343433342223 0507080805070707070505 0507080805070707070505
07 1 00 0020 0100 020 000 080 1 065 065 000 000 01 00 12 00 13 00 00 13 00 00109999999910999999109999 5444444444399999999999 99999999999
-- 99999999999 9999999999999999999999 9999999999999999999999
08 1 00 0050 0200 050 000 050 3 060 044 008 008 00 00 01 00 00 01 00 00 01 00100105019999999999999999 3434332553344343345533 3333334343333233242233 0510101005101010050506 0509101005101010050106
09 1 00 0003 0075 020 000 080 2 014 010 004 000 01 02 00 00 00 03 00 03 00 00060499990401990503039905 3123233453431444344534 3333121142331554342234 0208061003070409010305 0208061003070409010305
10 2 15 0030 0600 025 000 075 3 152 100 042 010 02 05 10 04 05 08 00 17 00 00100309050910010110090101 5555341553555544444434 5333234233355554452233 1005081008101010100505 1005081008101010100505
11 9 99 0099 0099 099 099 099 9 099 099 099 099 99 99 99 99 99 99 99 99 99 99999999999999999999999999 9999999999999999999999 9999999999999999999999 9999999999999999999999 9999999999999999999999
12 1 00 0010 0565 020 000 080 5 024 010 011 003 99 99 99 99 99 99 99 99 99 99050005009910999999109999 9999999999955334444453 9999999999999999999999 0808080506080805030308 9999999999999999999999I
I
SPSS/PC+
This procedure was completed at 15:00:07set printer off.01 1 00 0015 0075 050 030 020 1 138 132 006 000 05 05 15 04 03 18 00 25 00 00100101010110010101100101 5555459443355454454433 2222222232244424342214 1009100910070908080105 1009100910090910080105
02 1 00 0014 0100 020 000 080 2 015 013 001 001 01 03 00 01 03 99 00 02 00 02OnljO!02lC.10!050rO!n1 3514?525i3
45334455443 3233334455432434243455 0510091008090809100908 0710091008101010100508
03 1 01 0035 0200 020 000 080 1 056 030 020 006 01 01 06 04 03 01 00 08 00 00100401010110010108080101 1515252443435554554434 2124232124431252421145 1005061010101010050105 1010100810101010050505
04 1 00 0050 0500 025 000 075 1 042 025 014 003 02 04 00 00 04 02 00 06 00 00080299990109999902089999 2234432333354433453333 2232333233322323231133 0504060607090810050302 0504060607080910050302
05 1 00 0000 0200 040 000 060 1 041 015 025 001 01 03 02 00 02 02 00 04 00 02
100005050108020601080006 3435341333344343453332 1132333113355333453234 0909070909080805010505 0906050707070705010105
06 1 01 0099 0099 025 000 075 1 069 028 029 012 02 01 02 00 03 02 00 05 00 00070701010806010107050101 4435343444332334344443 3223232143343433342223 0507080805070707070505 0507080805070707070505
07 1 00 0020 0100 020 000 080 1 065 065 000 000 01 00 12 00 13 00 00 13 00 00109999999910999999109999 5444444444399999999999 9999999999999999999999 9999999999999999999999 9999999999999999999999
08 1 00 0050 0200 050 000 050 3 060 044 008 008 00 00 01 00 00 01 00 00 01 00100105019999999999999999 3434332553344343345533 3333334343333233242233 0510101005101010050506 0509101005101010050106
09 1 00 0003 0075 020 000 080 2 014 010 004 000 01 02 00 00 00 03 00 03 00 00060499990401990503039905 3123233453431444344534 3333121142331554342234 0208061003070409010305 0208061003070409010305
10 2 15 0030 0600 025 000 075 3 152 100 042 010 02 05 10 04 05 08 00 17 00 00100309050910010110090101 5555341553555544444434 5333234233355554452233 1005081008101010100505 1005081008101010100505
11 9 99 0099 0099 099 099 099 9 099 099 099 099 99 99 99 99 99 99 99 99 99 99999999999999999999999999 9999999999999999999999 999999999991 99999999999 9999999999999999999999 9999999999999999999999
12 1 00 0010 0565 020 000 080 5 024 010 011 003 99 99 99 99 99 99 99 99 99 99050005009910999999109999 9999999999955334444453 9999999999999999999999 0808080506080805030308 9999999999999999999999
13 2 10 0099 0099 050 000 050 1 195 099 099 099 02 10 03 04 05 06 04 06 02 01099901010999080109990801 2335151549355311349292 5324232259542323334195 1010101008080810991099 0810101010101008990899
14 1 00 0010 0100 099 099 099 3 025 099 099 099 20 00 05 01 04 00 00 05 00 00089999999910999999999999 3334242443343244455444 9999999999954444341222 9999999999999999999999 9999999999999999999999
I1 00 uo 0275 025 uou u05 9 22U 100 110 010 99 99 99 99 99 99 99 99 99 99999999999999999999999999 4434232443343444355544 2222232233344555352111 0507050705091010100505 0507050705091010100505
16 1 00 0005 0150 020 000 080 1 063 063 000 000 00 10 00 00 00 10 05 05 00 00100199990604999909029999 4333432444333333454443 3233223232333444332223 0108050903070502100406 0108050903070502100406
17 2 10 0099 0200 050 000 050 1 213 134 070 009 03 07 03 03 03 07 00 13 00 00100105011010999910109903 5455434554355554455454 3133313113354333121121 0505100509101010050501 0509050909101009050501
18 1 01 0099 0099 020 000 080 1 135 134 001 000 05 16 04 06 15 04 00 25 00 00100101010310040101011001 5555555555355555555555 4234425555452333212355 0810101008101005050507 0810101008101005050507
19 1 00 0020 0300 020 000 080 1 063 061 002 000 00 03 16 03 04 12 07 12 00 00100505011005050110100101 5555355555353545555555 1111111111111435222224 0505050505101010100505 0505050505101010100210
20 1 00 0003 0000 050 050 000 2 013 013 000 000 00 00 00 00 00 00 00 00 00 00100501011010070310109999 4535343554355343355433 2223333233345553331133 1008080806080806100506 1008080806080806100506
21 2 20 0099 0099 020 000 080 1 126 053 041 032 02 04 04 00 02 00 00 09 01 00100000021010020210050003 3333333553334333455533 2222224233343344342333 0810101008101010050710 0810101008101010050710
22 1 00 0001 0000 000 000 000 2 003 001 001 001 02 00 00 02 00 00 00 00 00 02999999109999991099999910 5135322555221111144443 2123213244241444444444 0709090910101009051010 0809090910101008061010
23 1 00 0140 0040 020 000 080 1 091 041 040 010 02 00 03 02 02 01 00 05 00 00080501010510010110050101 4334241333523323252332 2123224123453444342234 0809080806101010050805 0610090806101010050805
24 2 03 0650 2000 020 000 080 3 190 099 099 099 04 08 27 03 03 09 02 38 00 00999999999999999999999999 4434232453344343434543 2322234234322333342234 0607071005101005080508 0607071005101005080508
25 1 00 0225 0550 020 000 080 3 102 030 048 024 60 24 18 03 01 07 03 08 00 00100101011010010110060101 3355552553533323455534 3243324113333544341133 0105050805101010100608 0105050805101010100608
26 1 00 0050 0700 010 090 080 3 320 300 020 000 70 10 50 40 20 20 00 75 00 05090105030109010301090103 1113121555544343444444 4114234334343333454444 0510060907080403060201 0510060907080403060201
27 1 00 0000 0000 020 000 080 2 086 086 000 000 00 02 04 00 05 00 00 06 00 00999999999999999999999999 2425232443354555555555 4533345453314121431112 0910090908101010100706 0810080802100810100506
28 1 00 0060 0080 100 000 000 1 112 078 022 012 00 01 07 01 04 03 00 06 01 01011010010710080909109908 2335353441523555555515 4335455551355545353355 0510081008101005050505 0510081008101005050505
29 1 99 0015 0200 040 010 050 1 070 050 018 002 02 00 15 03 10 02 00 15 00 00109901999910999999999999 3333333333343333343333 2224333133333344321132 9907060704100910090303 9907060704100910090303
30 1 00 0354 1500 075 005 020 1 300 180 160 027 01 06 24 09 11 06 00 31 00 00090209060809060508090506 2425332323454544554432 3533222143334454442234 0806070809091008060707 0808070809070909070708
31 1 00 0002 0000 010 020 070 9 018 018 000 000 13 03 02 00 00 18 00 18 00 00109999999910999999109999 33112424453I43443444444 3344344334333453242213 0107070710020410080101 0107070706020410080101
32 1 00 0050 0000 025 025 050 2 039 039 000 000 01 00 00 00 00 01 00 01 00 00101008081010080810100808 53353555544--: 55335555553 3433343335334453333353 0505050508080808060505 0505050508080808060505
33 1 00 0005 0030 005 005 080 1 018 012 006 000 00 00 01 01 00 00 99 99 99 99999999999999999999999999 1134332443331313144433 3231313223333343443233 0503020305101010100305 0503020305101010100308
34 1 00 0015 0060 010 010 080 1 165 145 018 002 00 01 02 99 99 99 01 03 00 00100000009909000009099999 5544452333355343555555 4232344444442244342234 0810090907101010070408 0910090506101010050408
35 2 50 1500 0000 010 010 080 1 042 005 008 029 00 01 01 00 01 00 01 01 00 00999999999999999999999999 4435253444353454353333 5533355123351334352324 9905090410060701020803 9905090410060701020703
36 1 01 0099 0099 099 099 199 1 140 070 070 005 00 00 35 21 07 07 00 31 02 02999908999910999999109999 1113111333355555553333 1133333133331333133333 0505050505050505030303 0505050505050505030303
37 1 00 0100 0450 094 003 003 3 091 058 032 001 00 05 12 03 06 03 00 27 00 00040105000003020001070002 1233232554354342455543 3333334234312322221139 9999999999999999999999 9999999999999999999999
38 1 00 0030 0100 090 005 005 3 350 332 145 004 00 01 25 68 10 06 00 00 42 42100706050607100506071005 5335352553353442525554 55353355534
II
55353331339 0508081010101010050510 0508081010101010050510
39 1 00 0040 0000 100 000 000 2 089 060 024 005 01 01 40 25 08 09 99 99 99 99999999999999999999999999 4233234553332333445533 1133332233231332331135 0306051002090708990104 0205041003090807990106
40 1 00 0099 0099 099 099 099 9 052 000 052 000 00 08 04 00 00 12 99 99 99 99999999999999999999999999 5553451553435534555534 55135342332R 5c539235 0508080805100810050602 05090809051009]0050703
41 2 01 0050 0075 010 010 080 2 080 060 019 001 00 00 10 06 03 01 01 09 00 00091001010910010109100101 3344344445455555355534 3333332223433333322234 06040507080903100 0199 9999999999999999999999
42 1 00 0200 0600 008 012 080 2 134 097 035 002 00 00 02 02 00 00 00 02 00 00011001010110010101100101 3333333333345443455545 33333333333i 33333333333 0807030706080709010101 0601040703010604010101
43 1 00 0005 0003 000 100 000 1 041 027 014 000 00 01 05 00 04 02 00 06 o no049999999999999999109999 3344333233233254455523 9999999999999 99999999 0509100909070807100399 0509100909070807100399
44 1 99 0099 0099 099 099 099 9 042 040 0U2 000 00 00 05 02 02 01 01 04 00 00109999990799999910999999 9555991559955359955599 99q9999999999999999999 1099109908991010999999 1099109910991010999999
45 1 00 0015 0035 010 015 075 1 100 065 025 010 25 05 05 23 09 05 00 25 10 00999999999999999999999999 5344443343343223344444 9999999999999999999999 0606060608050505060606 0606060608050505060606
46 9 99 0099 0099 099 099 099 9 000 099 099 099 99 99 99 99 99 99 99 99 99 99999999999999999999999999 99999999999i 99999999999 99999999999
I9999999999999999999999999999999999999999999999999999999
47 1 00 0040 0000 050 050 000 1 035 015 020 000 04 15 01 00 05 15 00 05 15 00999999999999999999999999 9999999999955555555535 5534333443451115151135 1010101010101010000110 1010101010101010000110
i 48 1 00 0012 0099 020 080 000 1 071 061 010 000 00 01 02 02 00 01 00 01 00 02100000020110010204080008 9999999999995999945999 99999999999I99999999999 9999999999999999999999 999999999999999999999949 1 99 0099 0099 099 099 099 3 056 033 020 003 00 02 07 01 03 05 00 09 00 00999999999999999999999999 344435144431 54433555545 1111111111199999999999 9999999999999999999999 9999999999999999999999
50 1 00 0075 0060 100 000 000 2 018 013 005 000 04 04 12 03 02 01 00 01 00 05090309030703030707030804 4444532251232433343312 4444444441223244342315 0709051008070708010409 0709051008070708010409
* 51
II
1* AppendixDList of Respondents
IIIIIIIIIIIIIIIII
Appendix D List of Respondents
SPSS County Name Address City State ZipNumber
1 Adams County, WA Walt Olsen 210 W. Broadway Ritzville, WA. 991692 Asotin Cnunty, WA Richard Weaver, PI P.O. Box 160 Asotin, WA. 994023 Benton County, WA Dennis Skeate, PE P.O. Box 110 Prosser, WA. 993504 Chelan County, WA Lloyd Berry, PE/L: Courthouse, Wenatc Wenatchee, WA. 988015 Clallam County, WA Don Mclnnes 223 E. 4th Port Angeles, WA. 983626 Columbia County, WA Gary Gasaway, PE 341 E. Main St. Dayton, WA. 99328U 7 Cowlitz County, WA Kenneth C. Stone 207 N. 4th Kelso, WA. 986268 Ferry County, WA Greg Pezoldt, Eng - P.O. Box 344 Republic, WA. 991669 Grays Harbor, WA Russ Esses P. 0. Box 511 Montesano, WA 9856310 Island County, WA Roy Allen, PE Box 5000 Coupeville, WA 9823911 Jefferson County, WA Bruce Laurie P.O. Box 1220 Port Townsend, WA 9836812 King County, WA Doug Mattoon, PE 500 4th Avenue Seattle, WA 98104I 13 Kitsap County, WA David E. Dickson, 614 Division Port Orchard, WA 9836614 Kittitas County, WA John Nixon 205 W.5th, Room 1 Ellensburg, WA 9892615 Klickitat County, WA Ed Hoyle, PE 205 So. Columbus Goldendale, WA 98620I16 Lewis County, WA Darrel 0. McMurpP P.O. Box 899 Chehalis, WA. 9853217 Lincoln County, WA Glen Oliver, PE Box 368 Davenport, WA 9912218 Pacific County, WA John Bay Box 66 South Bend, WA 98586
19 Pend Oreille County, W Michael Rabe, PE P.O. Box 5000 Newport, WA 9915620 Pierce County, WA Don Peterson, P.E. 2401 So. 35th Tacoma, WA 98409-748721 Sar County, IWA David 0' Kane Box 729 Friday Harbor, WA 98250
22 Skagit County, WA Chet Reid Rm 203 Co. Admin. Mt. Vernon, WA 9827323 Snohomish County, WA Darrell Ash, PE 2918 Colby Street Everett, WA 9820124 Thurston County, WA Dale Rancour 2000 Lakeridge Dr. Olympia, WA 9850225 Whitman County, WA Lon R. Pedersen P.O. Box 430 Colfax, WA 9911126 Baker County, OR William S. McHane 3050 E Street Baker City, OR 9781427 Benton County, OR Roger Irvin, Assist 360 S.W Avery Av Corvallis, OR 9733328 Clatsop County, OR Randy Trevillian 1100 Olney Ave. Astoria, OR 9710329 Douglas County, OR Morrie Chappel 219 County Courthc Roseburg, OR 9747030 Gilliam County, OR John Russum P.O. Box 427 Condon, OR 9782331 Grant County, OR Doug Kruse P.O. Box 190 Canyon City, OR 9782032 Hood River County, OR James F. Lyon, Di 918 18th Street Hood River, OR 97031
33 Malheur County, OR Ray Stooks, Bridg, 251 'B' St. West, B. Vale, OR 97913-135734 Multnomah County, OR Stan M. Ghezzi, P.E 1629 S.E. 190th Portland, OR 9723335 Polk County, OWayne L. Rickert Jr., Director 206 County Courthc Dallas, OR 97338
36 Tillamook County, OR Jon Oshel, Directo 503 Marolf Loop Tilamook, OR 97141
37 Umatilla County, OR Ivan E. Pointer 3920 Westgate Pendleton, OR 9780138 Union County, OR Richard Comstock P.O. Box 1103 La Grande, OR 97850
39 Wallowa County, OR Merlin 'Skip' Lovel P.O. Box 219 Enterprise, OR 9782840 Wasco County, OR Daryl Ingebo, Bride County Courthouse, The Dalles, OR 9705841 Yamhill County, OR Dan Linscheid 2060 Lafayette AvE McMinnville, OR 97128
42 Lewis County, ID Director of County Lewis County Cour Nezperce, ID 8354343 Jim Stackhouse Box 1418 Bonner's Ferry, ID 83805I
I
Appendix D List of Respondents
SPSS County Name Address City State ZipNumber
44 Fremont County, ID Lyle I. Thompson 215 Farnsworth WE Rigby, ID 83442
45 Shoshone County, ID Shoshone County Drawer A Shoshone, ID 8335246 Nez Perce County, ID R.N. Flowers Couni 805 26th St North Lewiston, ID 83501
47 Canyon County, ID48 Mason County, ID Elden L. Reed P.O. Box 357 Shelton, WA 9858449 Clark County, WA Brian Vincent, PE P.O. Box 5000 Vancouver, WA. 98668
50 Boise County, ID Director of Public P. 0. Box 156 Idaho City, ID 83631
I;I
I
I3 Appendix E Summary of Costs for New Bridges
UIIIUUIIIIIIIUIII
o) 0 0o00 0:
p.. .-.......-. .. .... .... *...
0:) 0 0 0
0: C0E:) .j . . .0 .: :)0 0 0)
N0 0'. U4, 4, 0, 4,
. . 4 ... . . . .... 4. . . . . . .4* ** .-. * S 4 . . . 4 . 4
: 0 0 0:
0) f: :0 0:
0*o:o .0 14) o 0
c): c): 0:0 :C 0 N
C1 00
tp Ns C, Ci.) " :0 :0
,4 4 4 4 .
0000
... ..... * ..*. 4.. . ... 4... *.. 4 ... .........-. .... .. -. .
IS2 0
I14 inc .4.......... ..... . J ....-.. ,
CL. . . . . .< .
<<.4 :4js o sx : _
. ~ J ... s . .......... ... ...... ... ... ... ... ... ... ....... ... ...
__r!_ 0 :a 0 : CD 0 . a. a. .)c i a.dJ
ID
*) .. . .00D
NW4-
4.... .....4.....4...... .....
0 0
0: 0:0
4*
...I...T...t T t -.. ......00::0p.00t
~0
-~ 0000
* '04* *0 -:
04
*0 4 . .0A
IcR 0 :"O: (~~0 0t0 0(
v)-f: : :: 0Q% ::) :4 :0
... -i... .. .. . ....... ... ... ......
-0 00LA) cw
L: CS
0 't OA~ oo 0
-C 5: 00 L 4