Real Challenges for Civil Engineers – No.03 Client requirement – Add few floor slabs to existing building Engineering challenge – Strengthening of existing columns for new loads Conventional Solutions Provide steel columns to carry additional loads – may obstruct important areas Provide steel sheet cover around the column – welding quality, corrosion, grout infill etc will be the critical issues New Method introduced by the HILTI with the development of Technology

AD 3- Column Strengthening

Embed Size (px)

DESCRIPTION

Civil Eng

Citation preview

solex@sltnet

Real Challenges for Civil Engineers No.03Client requirement Add few floor slabs to existing buildingEngineering challenge Strengthening of existing columns for new loadsConventional Solutions Provide steel columns to carry additional loads may obstruct important areas

Provide steel sheet cover around the column welding quality, corrosion, grout infill etc will be the critical issues

New Method introduced by the HILTI with the development of Technology

Procedure 1. Consult your structural Engineer for new size of column need to sustain new floor loads and new reinforcement sizes.2. Contact one of HILTI Engineer to get necessary instructions to fix new reinforcement

3. Drill holes to specified diameter and depth

4. Clean holes with blow out pump provided

5. Insert HILTI RE 500 chemical with the use of dispenser provided ( No hand mixing)

6. Insert the column reinforcement bars and keep 8 hrs to cure

7. Roughen the concrete surface and provide some shear connectors with

HILTI HY 150 or HILTI RE 500 bonding agent

8. Arrange reinforcement as usual

9. Do the form work according to the column size

10. Apply any bonding agent if necessary and do the concreting as usual

Advantages1. Very fast construction application. Maximum 2 days to complete the total task

2. Low cost ( less than Rs.600/- to fix Y16 bar at nominal embedment depth )

3. Application is so simple and no chance for mistakes

4. No risk for the job

5. Pullout test will be done by HILTI Engineers before concreting to ensure the strength

if necessary

6. All technical support will be given by HILTI Engineers

7. Architecturally looks like originally cast column

Technical Assistance Neelanga Sooriyarachchi

B.Sc. Eng (Hons);MBA; AMIE(SL)

Engineering Service Manager

Mob 0717712968 Email . [email protected]

T.D.Wijitha Kumara

B.Sc.Eng(Hons);CEng;MIE(SL);MSSE(SL);MBA

Technical Manager

Mob. 0717772815 Email. [email protected]

Office

207, Nawala Road, Nugegoda

Te. 0114713352, 0114542320

Fax. 0114723208

Email. [email protected] Sales Engineers / Sales ExecutivesChandima Samarasinghe Colombo Area

B.Sc. Eng ( Hons)

Te. 0717579369

Lalith Chaminda Colombo Area

B.Sc. Eng ( Elec)

Te. 0718540846

Nadun Ranatunga Colombo Area

Sales Executive

Te. 0713733107

Sampath Bandara Kurunegala, Kandy, Anuradapura, Batticaloa

Sales Executive

Te. 0713733106

Tuwan Burah Southern, UvaSales Executive

Te. 0717124687

A product ofHilti Engineering Division