Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Achieving High Reliability: Design Considerations for Microgrids29th November 2017 Samson Shih
Why Microgrid• Improve operational security & reliability (SS / transient)
• Adoption of renewables to reduce environmental impact and improve self sustainability, reduce dependencies of fuel supply
• Especially beneficial for remote and critical infrastructures (eg. hospitals, airports, military applications)
2
Microgrid
Image:DillonThompsonDesign
Microgrid Design Dilemma
0.940.960.981.001.021.041.06
0.940.960.981.001.021.041.06
Frequency(HighPenetration)
Frequency(Low/Med.Penetration)
Irradiance(Wm-2)
200400600800100012001400
11:00 11:05 11:10 11:15 11:20 11:25 11:30 11:35 11:40 11:45 11:50 11:55
vSustainabilityvs.systemstability
3
[Wm
-2]
[p.u.]
[p.u.]
Microgrid Design Dilemma
Irradiance
Low/Med.Penetration
HighPenetration
-2.5
-2
-1.5
-1
-0.5
0
0.5
1
1.5
0
250
500
750
1000
1250
1500
1750
2000
0:00 3:00 6:00 9:00 12:00 15:00 18:00 21:00 0:00
PowerFactor
Irrad
iance(W
m-2)
>Sustainabilityvs.systemstability
vMoreeffectivepowerfromrenewablesvs.powerquality
4
Microgrid Design DilemmaRe
liabiltiyInde
x
InvestmentCost
>Sustainabilityvs.systemstability
>Moreeffectivepowerfromrenewablesvs.powerquality
vReliabilityvs.economy
5Graphextractedfrom:Mosteller R.,Budget-constrainedPowerSystemReliabilityOptimization
Improving Power Reliability
• Modification or New Design
• Power availability requirements
• Renewables intermittency and desired penetration
• Operation mode (islanded, grid-connected or both)
v BasicDesignConsiderations
6
Improving Power Reliability
• ‘Strength’/‘rigidity’ of microgrid– Electrical inertia
• Network protection requirements– Bidirectional power flow requires bidirectional protection consideration– Non-radial network further complicate the problem
• Load demand & type
• Placement / Sizing of ESS & required functionalities
>BasicDesignConsiderations
v FurtherDesignConsiderations
7
Improving Power Reliability
• Impact of geographic and temporal characteristics of the renewables on the scheduling & dynamic behavior
• Interconnection of multiple microgrids
>BasicDesignConsiderations
>FurtherDesignConsiderations
v OperationConsiderations
8
Case Study
HIGH ADOPTION OF RENEWABLES IN A TRADITIONAL DISTRIBUTIONLEVEL MICROGRID
Case Network
• Distributionlevel(6.6kV– 400V)
• Radialnetwork
• SinglePointofFailure
• Critical/Non-criticalLoads
• ModelledinPowerFactory
10
Design Requirements• High reliability and resiliency against internal and external failures
– Unplanned islanding– Faults on microgrid network– Potential communication failure
• Integrate as much PV as possible
• Ensure system remains stable
• Minimise fuel cost during islanded scenario
11
Network Modification
• PVInstallation
• LoopCableInstallation
• LVDGInstallation
• ESSInstallation
• AdjacentMGCableInstallation
• Distributedcontrolarchitecture
12
PV Penetration Study
TxfPG-A
TxfB-LVBTxfQ-LVQTxfH-LVHPVLimit
0.0
1.2
2.4
0%
20%
40%
0%
40%
80% Transformers
LineCables
TotalPV
13
[Loa
ding]
[Loa
ding]
[MW
p]
PV Penetration Study (Islanded)
TxfGen-B
TxfB-LVBTxfE-LVETxfH-LVHPVLimit
0.0
1.2
2.4
0%
5%
10%
0%
40%
80% Transformers
LineCables
TotalPV
14
[Loa
ding]
[Loa
ding]
[MW
p]
Component Failure RateComponent FailureRate,λ"#$%& (1/y) MTTR(h)
Cable(LV/HV) 0.02670/0.02017 7.60/5.13
Switchgear(LV/HV) 0.00949/0.01794 7.29/2.27
DGs 0.58269 25.74
Inverters 0.00482 26.00
Failure(f)Theterminationoftheabilityofacomponent/systemtoperformarequiredfunction
Failurerate(λ)Arithmeticaveragefailureperunitexposuretime
λ'()%& =+,-./012+321.45
orλ"#$%& =+,-./012
+321.45∗789:
MeanTimetoRepair(MTTR)Totaldowntimeforunscheduledmaintenance(excludinglogisticstime)foragivenperiod
𝑀𝑇𝑇𝑅 =𝑅>(?@ABC#𝑇D$BE)%#
IEEEStandard493-2007 15
Power Security Improvement
SAIFI SAIDI
Base 0.028813 0.181
Loop 0.021437 0.147
ESS 0.009490 0.069
SYSTEM AVERAGE INTERRUPTION FREQUENCY INDEX= ∑ +(A$EH(.(DJ)&A(C#%K@A#%%)LA#>�
�+(A$EH(.(DJ)&A(C#%&N#%O#>
SYSTEM AVERAGE INTERRUPTION DURATION INDEX= ∑ J)&A(C#%PB@)A#&(DK@A#%%)LAB(@�
�+(A$EH(.(DJ)&A(C#%&N#%O#>
IEEEStandard1366
16
Seamless Unplanned Islanding
ESSPower
PCCPower
Voltage
Frequency
0.0
37.5
75.0
0.9975
1.0000
1.0025
Islanding
0 5 10 15 20 25 30 35 40 45 50 55 60 s17
[p.u.]
[kW]
• TotalLoad([email protected])– [email protected]– [email protected]– [email protected]– [email protected]
• DieselGenerator– [email protected]
• PVPenetrationTest– 0.3MWp
(18.75%Penetration)– 1.5MWp
(93.75%Penetration)
PV Penetration Study
18
*PenetrationisdefinedasratioofinstalledPVcapacitytoDGrating
Power Quality Analysis
0% 10% 20% 30% 40% 50% 60% 70%
-0.075 -0.05 -0.025 0 0.025 0.05 0.075
DGInter-secondRampRate
0%
20%
40%
60%
80%
100%
0.4 0.5 0.6 0.7 0.8 0.9 1
PowerFactor
HzMW/s
cosϕ
18.75%PV
56.25%PV 93.75%
PV 0%
5%
10%
15%
20%
25%
30%
49.75 49.85 49.95 50.05 50.15 50.25
Frequency
19
Increasing PV Penetration
• Network Stability:– Introduced network instability (frequency deviations)– Constant ramping of DGs– Deterioration of power factor at PCC and DG substation– Voltage rise during low loading
• Protection:– Change in flow of power in the network (due to PV and network topology
changes)– Disparity between available fault current in grid-connected and islanded
mode & changes in fault current flow
ProblemsFaced
20
• TotalLoad([email protected])– [email protected]– [email protected]– [email protected]– [email protected]
• DieselGenerator– [email protected]
• ESS– 2MVA,1MWh
• PVPenetrationTest– 1.5MWp
(57.69%Penetration)– 2.7MWp
(103.84%Penetration)– 3.3MWp
(126.92%Penetration)
PV Penetration Study (ESS)
*PenetrationisdefinedasratioofinstalledPVcapacitytoDGrating
21
Power Quality Analysis with ESS
93.75%PV
57.69%PV
103.84%PV 126.92%
PV
0%
5%
10%
15%
20%
25%
30%
49.75 49.85 49.95 50.05 50.15 50.25
Frequency
0% 10% 20% 30% 40% 50% 60% 70%
-0.075 -0.05 -0.025 0 0.025 0.05 0.075
DGInter-secondRampRate
0%
20%
40%
60%
80%
100%
0.4 0.5 0.6 0.7 0.8 0.9 1
PowerFactor
HzMW/s
cosϕ22
Issues• Bi-directional&multiple
powerflow
• Changesinavailablefaultcurrents
Resultsin• Impartialdiscriminationof
faults
PotentialSolutions• Method1:
– Changetodifferentialprotection
– Directionalsensitivityforovercurrentrelays
– Overcurrentrelaysformsthebackupprotection
• Method2:– Makeuseof“loop”cableasa
backuptie-breaker
• Method3:– Adaptiveprotection
Protection Challenge
23
ESS Placement, Sizing & Scheduling
MULTIPLE MICROGRIDS
ESS – Multiple Microgrids
• Single ESS vs. Multiple ESS– Isolated MG with individual GESS– Connected MG with single GESS
v Placementlocation
MG1 MG2
MG3
ESS
ESS
ESSESS ESS
25
ESS – Multiple Microgrids
• Objective:– Minimise total fuel cost
• Using simple PV prediction based on ANN
• Considerations– Operations
• Load profile• PV prediction accuracy• DG fuel efficiency and ramp cost
• Simulation– 3 days with varying PV condition
>Placementlocation
v Sizing&Scheduling
• Levelised GESS cost• GESS efficiency• Power losses (transfer)
26
PV Prediction
• Consideration of time-series irradiance and weather data
• Training through backpropagation
>ArtificialNeuralNetworkbased
OutputsInputs
HiddenLayer(s)
backpropagation
27
PV Prediction
Predicted
Actual
PredictionError
-1.2
-1
-0.8
-0.6
-0.4
-0.2
0
0.2
0.4
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
01/11 02/11 03/11 04/11 05/11 06/11 07/11 08/11
Preidctio
nError/W
m-2
Irrad
iance(Predict&Actua
l)/Wm-2
v ArtificialNeuralNetworkbased
>PredictionResults
28
IndividualESS
• IndividualESSoneachMGinterconnectedtogetherreducestotalrequiredESScapacity&inverterrating
• Allowsforhigherreliability
AggregatedESS
• Loweroperatingcost
• AggregatenatureofloadandPVallowsforDGtooperateatmoreefficientpoint
ESS Study
MG1 MG2
MG3ESS
ESS
ESS
MG1 MG2
MG3ESSESS ESS
29
Summary• Determine RER capacity and variability
• Evaluate power reliability and quality requirements
• Provide network redundancy
• Provide power / energy redundancy
• Install corrective DERs
• Ensure network remains properly protected
30
End of Presentation