    Standard Field Quality Plan

    ACDB PANEL

    For

    Prepared By Reviewed By Approved By DOC NO :FQP/ELCTRICAL/ACDB/17

  • 8/13/2019 ACDB FQP

    2/9

    Name of document :- FQP FOR ACDB PANEL WORKSName of Client:- Reference no:FQP/ELECTRICAL/ACDB/17

    Name of project:-

    S.NO. CHARACTERISTICS/ITEM INSTRUMENTTYPE OF

    CHECK

    QUANTUM/

    FREQUENCY OF

    CHECK

    REF. DOC. &

    ACCEPTANCE

    STANDARD

    FORMAT OF

    RECORDSREMARKS

    1 RECEIPT AND STORAGE

    1.1 RECEIPT OF MATERIALS

    1.11Check for Manufacturer's name as per Purchase Order,

    Name Plate details / Details as per the test certificates /

    Delivery Challan.

    Visual 100%Delivery Challan &

    Packing ListSIR/ACDB /01

    1.12Check supply of accessories / Loose supply items (if

    any)Visual 100% Packing List / BOQ SIR/ACDB /01

    1.13 Visual examination for damage. Visual 100% No Damages SIR/ACDB /01

    If Yes, Report

    immediately to

    Project

    Manager

    1.2 STORAGE OF MATERIALS

    1.21Ensure that the material is stored on raised wooden

    platform to avoid direct contact with ground / MoistureVisual 100%

    Instruction Mannaul

    Standard engg.

    Practice

    SIR/ACDB /01

    1.22Ensure that the material is stored in systematic manner

    rating wise for easy removalVisual 100% do SIR/ACDB /01

    1.23Ensure that different accessories / loose supply materialare stored separately section and size wise labelled and

    tagged for easy identification

    Visual 100% do SIR/ACDB /01

    1.24Ensure that all hardware are tagged & kept

    separately in racks size-wise for easy identificationVisual 100% do SIR/ACDB /01

    Standard Field Quality Plan for ACDB Panel.

    Rev : 0

    AREVAT & D (India) Limited

    Name of Sub-contractor:-

    Issued on :

    SIR-Site inspection report, STR - Site Test Report, Mfr TC-Manufacture test certificate . This document shall be read in conjunction with Client's tech. spec., BOQ,

    drawing s any other relevant document. Page 2 of 9

  • 8/13/2019 ACDB FQP

    3/9

    Name of document :- FQP FOR ACDB PANEL WORKS

    Name of Client:- Reference no:FQP/ELECTRICAL/ACDB/17

    Name of project:-

    S.NO. CHARACTERISTICS/ITEM INSTRUMENTTYPE OF

    CHECK

    QUANTUM/

    FREQUENCY OF

    CHECK

    REF. DOC. &

    ACCEPTANCE

    STANDARD

    FORMAT OF

    RECORDSREMARKS

    Standard Field Quality Plan for ACDB Panel.

    Rev : 0

    AREVAT & D (India) Limited

    Name of Sub-contractor:-

    Issued on :

    2 PRE INSTALLATION

    2.01Check name plate details of the ACDB Panel with

    drawing / BOQVisual 100% Drawing / BOQ SIR/ACDB/02

    2.02Check size & type of hardware / accessories

    required as per the drawing / BOQVisual do do SIR/ACDB/02

    2.03Ensure that no physical damage to ACDB Panel

    body /insulator etc. is observed.Visual do SIR/ACDB/02

    2.04Ensure that avialbility of proper foundation and

    floor.Visual do SIR/ACDB/02

    2.05

    Check the lay out drawing with panel drawing for

    access to the location and clearences from the wall

    for panel.

    2.06Check Matching of floor / hole on ACDB Panel,

    and mounting foundation.Visual do Erection Drawings SIR/ACDB/02

    2.07Ensure availability of necessary tools &, tackles,

    crane & sling for lifting of ACDB Panel etc.Visual do SIR/ACDB/02

    2.08Ensure that room ventilation and area lighting

    available.Visual do SIR/ACDB/02

    3 INSTALLATION3.1 Check Rating Plate details Visual 100% GA Drawing SIR/ACDB/03

    3.2Check Verticality of equipment on support structure &

    LevelingVisual do do

    SIR/ACDB/03

    3.3 Check the Earth bus connection at two different point Visual do doSIR/ACDB/03

    3.4Check the clearences between phases and phase to

    earthVisual do do

    SIR/ACDB/03

    3.5Check the temporary blocking of movable parts are

    removed including relay.

    Visual doManufacturer instruction

    manual SIR/ACDB/03

    SIR-Site inspection report, STR - Site Test Report, Mfr TC-Manufacture test certificate . This document shall be read in conjunction with Client's tech. spec., BOQ,

    drawing s any other relevant document. Page 3 of 9

  • 8/13/2019 ACDB FQP

    4/9

    Name of document :- FQP FOR ACDB PANEL WORKS

    Name of Client:- Reference no:FQP/ELECTRICAL/ACDB/17Name of project:-

    S.NO. CHARACTERISTICS/ITEM INSTRUMENTTYPE OF

    CHECK

    QUANTUM/

    FREQUENCY OF

    CHECK

    REF. DOC. &

    ACCEPTANCE

    STANDARD

    FORMAT OF

    RECORDSREMARKS

    Standard Field Quality Plan for ACDB Panel.

    Rev : 0

    AREVAT & D (India) Limited

    Name of Sub-contractor:-

    Issued on :

    3.6Check the tightness of bus bar joints terminal joints at

    breaker fixed pads in switchgear panels.Visual do _

    SIR/ACDB/03

    3.7Check the inter panel bus bar alignment is OK in

    switchgear panel.Visual do _

    SIR/ACDB/03

    3.8Check all bus bar supprot insulator and bus bar

    insulation in the panel.Visual do Schematic drawing.

    SIR/ACDB/03

    3.9

    Clean the bus bar duct thoroughly and ensure that all

    component of bus duct are installed as per approved

    drawing.Visual do

    Manufacturer instruction

    manualSIR/ACDB/03

    3.10Check all wiring of circuit breaker and its fixed chasis are

    as per drawingSchematic drawing.

    3.11 Check all limit switches,auxiliary switches,micro switchesare mounted and aligned properly.

    do

    3.12Ensure that power and control cables are terminated

    with proper ferrulingVisual do do

    SIR/ACDB/03

    3.13Ensure correct sizes of cable are used and properly

    tagged.Visual do do

    SIR/ACDB/03

    3.14 Check for proper ratings of fuses. Visual do do SIR/ACDB/03

    3.15

    Check healthiness of fuses, links, MCBS, Switches,

    indication lamps, push buttons, space heater &

    illumination circuit.Visual do do

    SIR/ACDB/03

    3.16 Check the CT and PT circuits are as per drawing. Visual do do SIR/ACDB/03

    3.17 Check the wires are dressed & routed properly. Visual do do SIR/ACDB/03

    3.18 Check cables are supported properly Visual do do SIR/ACDB/03

    3.19 Check the healthiness of AC & DC supply Multimeter Measurment do do SIR/ACDB/03

    3.20 Check the metering circuit Multimeter Measurment do do SIR/ACDB/03

    3.21 Check the polarity of ammeter, voltmeter etc. Multimeter Measurment do do SIR/ACDB/03

    3.22 Check space heater for continuity Multimeter Measurment do do SIR/ACDB/03

    3.23Check indicating lamps rating and their circuits and

    ensure their colours are in orderVisual do do

    SIR/ACDB/03

    SIR-Site inspection report, STR - Site Test Report, Mfr TC-Manufacture test certificate . This document shall be read in conjunction with Client's tech. spec., BOQ,

    drawing s any other relevant document. Page 4 of 9

  • 8/13/2019 ACDB FQP

    5/9

    Name of document :- FQP FOR ACDB PANEL WORKS

    Name of Client:- Reference no:FQP/ELECTRICAL/ACDB/17Name of project:-

    S.NO. CHARACTERISTICS/ITEM INSTRUMENTTYPE OF

    CHECK

    QUANTUM/

    FREQUENCY OF

    CHECK

    REF. DOC. &

    ACCEPTANCE

    STANDARD

    FORMAT OF

    RECORDSREMARKS

    Standard Field Quality Plan for ACDB Panel.

    Rev : 0

    AREVAT & D (India) Limited

    Name of Sub-contractor:-

    Issued on :

    3.24 Check door alignment Visual do do SIR/ACDB/03

    3.25 Check door lock facility Visual do do SIR/ACDB/03

    3.26 Check panel to panel bolting for tightness Visual do do SIR/ACDB/033.27 Check cleanliness of the board. Visual do do SIR/ACDB/03

    3.28 Check function of all switch fuse units Visual do do SIR/ACDB/03

    3.29 Check rating of all fuses Visual do do SIR/ACDB/03

    3.30Checked for broken gIass, switch handle, lamp cover

    elc.Visual do do

    SIR/ACDB/033.31 Check the completeness of supply Visual do Drawing / BOQ SIR/ACDB/03

    3.32 Ensure Glanding of external cables Visual do GA Drawing SIR/ACDB/03

    3.33 Ensure blanking of unused cable entry holes Visual do do SIR/ACDB/03

    3.34 Ensure proper sealing and locking arrangement of paneldoor

    Visual do doSIR/ACDB/03

    3.35Ensure removal of top and side blanking plates, if

    applicableVisual do do

    SIR/ACDB/03

    3.36Provide danger board ,rubber mat ,etc,at required

    location.Visual do do

    SIR/ACDB/03

    3.37 Check the auto changeover if any. Schematic drawing.

    4 TESTING

    4.1 IR Value test Megger Measurment 100% Test Report STR/ACDB/01

    4.2 Bus Bar contact resistance test. Test Kit Measurment do Test Report STR/ACDB/01

    4.3 Commissioning check Test Kit Measurment do Test Report STR/ACDB/01

    4.2 Protection relays and schemes test. Test Kit Measurment do Test Report STR/ACDB/01

    4.4Carry out all tests as per Client Specification or

    AREVA'S standard test format.Test Kit Measurment do Test Report

    STR/ACDB/01

    SIR-Site inspection report, STR - Site Test Report, Mfr TC-Manufacture test certificate . This document shall be read in conjunction with Client's tech. spec., BOQ,

    drawing s any other relevant document. Page 5 of 9

  • 8/13/2019 ACDB FQP

    6/9

    AREVAAREVAAREVAAREVAT & D India Limited

    Sh. 1

    Total Sh. 1

    Voltage Level

    Make:

    1

    1.1.1

    1.1.2

    1.2

    1.3

    DateDate

    Performed by Verified byAccepted by

    Agency AgencyAgency

    Name Name

    Name

    Date

    RECEIPT

    Proper storage

    All items are stored properly.

    Specific instruction from manufacturer on the wooden packing crates/instruction manual regarding storage (Outdoor/lndoor/Semicovered) of any individual item to be followed

    strictly.

    Remarks:

    Shortages and damages.

    Material verification report no.

    Visual ExaminationShortages and damages checked w.r.t packing list. Yes/No.

    Applicable instructions.

    Delivery challan nos.

    Documents

    REMARK

    Receiving Inspection

    All items are received with respect to following delivery challans:

    MDCC NO:

    LR NO.

    TRUCK NO

    Location/Bay

    INVOICE NO

    NO OF PAKAGES.

    Project Name:

    Project Ref

    Rating

    Customer PO Ref

    RECEIPT AND STORAGE INSPECTION FQP ref. No. FQP/ELECTRICAL/ACDB/17

    GENERAL INFORMATION Equipment SI. No.

    STANDARD SITE INSPECTION RECORD OF ACDB WORKS

    Form No. SIR/ACDB /01

    Instruction Manual Received/Not received

    Test Certificate Received/Not received

  • 8/13/2019 ACDB FQP

    7/9

    AREVAAREVAAREVAAREVAT & D India Limited

    Sh. 1Total Sh. 1

    4.1

    4.2

    4.4

    Applied rated AC supply voltages at the incoming supply terminals in the panel and switched on the supply ON/OFF switches withstood.

    4.5 OPERATIONAL TEST OF FITTINGS ON THE PANELChecked for operation of Interior Illumination lamp, Space heaters, Thermostat,socket outlet supply, switches etc. in the panel.

    4.6 FINAL DOCUMENT REVIEWInspection record of Installation & equipment testing checked for completeness & approval.

    4.7 Carry out all tests as per Client Specification or AREVA'S standard test format.

    Date DateDate

    AgencyAgency

    Name NameName

    Agency

    Remarks:

    Performed by Verified byAccepted by

    AUXILIARY POWER SUPPLY TEST

    Verified Mimic on ACDB panels as per the station layout, if any.

    Checked earthing of ACDB panel earth bus.

    CIRCUIT DIAGRAM TEST

    Panel wiring checked as per wiring diagram using a multimeter or continuity tester including alarm system .

    Verified interpanel wirings and bus wire interconnections (where applicable) as per wiring diagrams and schematics.

    Checked rating of fuses and also checked soundness of fuses and links.

    Location/BayGENERAL INSPECTION

    Ensured all devices and fittings are mounted and not physically damaged.

    Customer PO Ref Voltage Level

    Make:

    Project Name: FQP ref. No.

    Project Ref Rating

    TESTING FQP ref. No. FQP/ELECTRICAL/ACDB/17

    GENERAL INFORMATION Equipment SI. No.

    STANDARD SITE INSPECTION RECORD OF ACDB WORKS

    Form No. SIR/ACDB /04

  • 8/13/2019 ACDB FQP

    8/9

    AREVAAREVAAREVAAREVAT & D India Limited

    Sh. 1

    Total Sh. 1

    2

    2.1

    2.2

    2.3

    2.4

    2.5

    2.6

    2.7

    Agency

    Name Name

    Date DateDate

    Agency

    Name

    Agency

    Performed by

    Remarks:

    Verified by Accepted by

    PRE-INSTALLATION CHECKS

    Ensured that room ventilation and area lighting is available.

    Checked availability of GA drawings and supplier's instruction manual / Test Procedure.

    Checked availability of materials as per B0Q / and drawings.

    Checked equipment foundaiton is properly levelled as per foundation civil drawing and channel, bolts etc.are installed as per drawing.

    Checked name plate details of the ACDB Panel with drawing / BOQ

    Checked size & type of hardware / accessories required as per the drawing / BOQ

    Ensured that no physical damage to ACDB Panel body /insulator etc. is observed.

    Customer PO Ref Make:

    Location/Bay

    Project Name: Rating

    Project Ref Voltage Level

    PRE-INSTALLATION / INSTALLATION VERIFICATIONFQP ref. No. FQP/ELECTRICAL/ACDB/17

    GENERAL INFORMATION Equipment SI. No.

    STANDARD SITE INSPECTION RECORD OF ACDB WORKS

    Form No. SIR/ACDB /01

  • 8/13/2019 ACDB FQP

    9/9

    AREVAAREVAAREVAAREVAT & D India Limited

    Sh. 1

    Total Sh. 1

    3

    3.1

    3.23.3

    3.4

    3.5

    3.6

    3.7

    3.8

    3.9

    3.10

    3.11

    3.12

    3.13

    3.14

    3.15

    3.16

    3.173.18

    3.19

    3.20

    Date Date Date

    Agency Agency Agency

    Name Name Name

    Checked that top and side blanking plates have been removed, if applicable.

    Checked the clearences between phases and phase to earth

    Checked availability of all catalogues / Equipment manual

    Performed by Verified by Accepted by

    Remarks:

    Clean the bus bar duct thoroughly and ensure that all component of bus duct are installed as per approved drawing.

    Checked all wiring of circuit breaker and its fixed chasis are as per drawing

    Checked all limit switches,auxiliary switches,micro switches are mounted and aligned properly.

    Checked Rating Plate details

    Checked verticality, alignment and leveling of support structure, fixing and tightening of foundation fasteners and sequence of erected panel.

    Ensured connection of earthbus of all panels through coupling links and connection to station earth.

    Checked the polarity of shunt, ammeter, voltmeter etc.

    Ensured correct sizes of cable are used and properly tagged.

    Checked and replace broken glass, switch handle,lamp cover etc. if any.

    Checked compeleteness of supply.

    Checked glanding of all external cables entering the panel.

    Checked blanking of all unused cable entry holes after completion of cabling as per cable schedule.

    Checked for proper sealing and locking arrangement of panel doors.

    Make:

    Location/Bay

    INSTALLATION CHECKS

    Project Name:

    Project Ref

    Rating

    Customer PO Ref

    Voltage Level

    PRE-INSTALLATION / INSTALLATION VERIFICATION FQP ref. No. FQP/ELECTRICAL/ACDB/17

    GENERAL INFORMATION Equipment SI. No.

    STANDARD SITE INSPECTION RECORD OF ACDB WORKS

    Form No. SIR/ACDB /01

    Checked the temporary blocking of movable parts are removed including relay.

    Checked the inter panel bus bar alignment is OK in switchgear panel.

    Checked the tightness of bus bar joints terminal joints at breaker fixed pads in switchgear panels.

    Checked all bus bar supprot insulator and bus bar insulation in the panel.