121
ACCELERATED IMPLEMENTATION OF INTELLIGENT COMPACTION TECHNOLOGY FOR EMBANKMENT SUBGRADE SOILS, AGGREGATE BASE, AND ASPHALT PAVEMENT MATERIALS: US 84 WAYNESBORO, MISSISSIPPI Final Report ER10-03 US84, Waynesboro, MS, Field Project July 13 to 17, 2009 Prepared By David J. White, Ph.D. Pavana KR. Vennapusa, Ph.D. Heath Gieselman Bradley Fleming Stephen Quist Luke Johanson Earthworks Engineering Research Center (EERC) Department of Civil Construction and Environmental Engineering Iowa State University 2711 South Loop Drive, Suite 4600 Ames, IA 50010-8664 Phone: 515-294-7910 www.eerc.iastate.edu April 1, 2010

ACCELERATED IMPLEMENTATION OF INTELLIGENT …

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

ACCELERATED IMPLEMENTATION OF

INTELLIGENT COMPACTION TECHNOLOGY

FOR EMBANKMENT SUBGRADE SOILS, AGGREGATE BASE, AND ASPHALT PAVEMENT

MATERIALS: US 84 WAYNESBORO, MISSISSIPPI

Final Report ER10-03 US84, Waynesboro, MS, Field Project

July 13 to 17, 2009

Prepared By

David J. White, Ph.D. Pavana KR. Vennapusa, Ph.D.

Heath Gieselman Bradley Fleming

Stephen Quist Luke Johanson

Earthworks Engineering Research Center (EERC) Department of Civil Construction and Environmental Engineering

Iowa State University 2711 South Loop Drive, Suite 4600

Ames, IA 50010-8664 Phone: 515-294-7910 www.eerc.iastate.edu

April 1, 2010

Page 2: ACCELERATED IMPLEMENTATION OF INTELLIGENT …
Page 3: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

TABLE OF CONTENTS

ACKNOWLEDGMENTS ............................................................................................................... I

LIST OF SYMBOLS ...................................................................................................................... II

INTRODUCTION ...........................................................................................................................1

BACKGROUND .............................................................................................................................2

Machine Drive Power (MDP) Value .......................................................................................... 3 Compaction Meter Value (CMV) and Resonant Meter Value (RMV) ....................................... 4 Roller-Integrated Stiffness (ks) Measurement Value .................................................................. 5 Roller-Integrated Compaction Control Value (CCV) ................................................................. 6 Overview of Project Earthwork Specifications ........................................................................... 6

ANALYSIS METHODS .................................................................................................................7

Regression Analysis .................................................................................................................... 7 Geostatistical Analysis ................................................................................................................ 8

EXPERIMENTAL TESTING .........................................................................................................9

Description of Test Beds ............................................................................................................. 9 Laboratory Testing .................................................................................................................... 11 In-situ Testing Methods ............................................................................................................ 13

EXPERIMENTAL TEST RESULTS ............................................................................................16

TB1 Granular Base Material (Untreated) ................................................................................. 16 Test Bed Conditions, IC-MV Mapping, and Point-MV Testing .......................................16 Test Results and Analysis ..................................................................................................16 Summary of Results ...........................................................................................................20

TB2 Treated Granular Base Material (5-day cure) ................................................................... 21 Test Bed Conditions, IC-MV Mapping, and Point-MV Testing .......................................21 Test Results and Analysis ..................................................................................................22 Summary ............................................................................................................................26

TBs 3/8 Treated Base Material ................................................................................................. 26 Test Bed Construction........................................................................................................26 Test Results and Analysis ..................................................................................................30 Summary ............................................................................................................................41

TB4 Granular Subgrade Material (Untreated) .......................................................................... 41 Test bed conditions, IC-MV mapping, and Point-MV testing ...........................................41 Test Results, Analysis, and Summary................................................................................42

TBs 5, 6, and 9 Treated Subgrade Material .............................................................................. 51 Test Bed Construction and IC-MV Mapping.....................................................................51 Test Results and Analysis ..................................................................................................53 Summary ............................................................................................................................65

TB7 Granular Subgrade Material (Untreated) .......................................................................... 66 Test Bed Conditions, IC-MV Mapping, and Point-MV Testing .......................................66

Page 4: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

Test Results and Analysis ..................................................................................................68 Summary ............................................................................................................................77

COMBINED REGRESSION ANALYSIS ....................................................................................77

FIELD DEMONSTRATION – OPEN HOUSE ............................................................................83

SUMMARY AND CONCLUSIONS ............................................................................................84

REFERENCES ..............................................................................................................................85

APPENDIX: TEST BED SUMMARY SHEETS AND EXPERIMENTAL PLAN .....................88

Page 5: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

LIST OF FIGURES Figure 1. Caterpillar CP56 (top left) padfoot, Case SV212 smooth drum, and Sakai SW880 dual

smooth drum IC rollers used on the project .........................................................................2 Figure 2. Lumped parameter two-degree-of-freedom spring dashpot model representing vibratory

compactor and soil behavior (reproduced from Yoo and Selig 1980) .................................5 Figure 3. Changes in amplitude spectrum with increasing ground stiffness (modified from

Scherocman et al. 2007) .......................................................................................................6 Figure 4. Description of a typical experimental and spherical semivariogram and its parameters .9 Figure 5. Grain-size distribution curves of base and subgrade materials ......................................12 Figure 6. Laboratory standard Proctor moisture-density relationships for base and subgrade

materials .............................................................................................................................12 Figure 7. Effect of wait time (after mixing) on dry unit weight of treated base and subgrade

materials .............................................................................................................................13 Figure 8. In-situ testing methods used on the project: (a) Humboldt nuclear gauge, (b) dynamic

cone penetrometer, (c) Zorn light weight deflectometer, (d) Dynatest falling weight deflectometer, (e) static plate load test ..............................................................................15

Figure 9. EV1 and EV2 determination procedure from static PLT for subgrade and base materials15 Figure 10. TB1 granular base material after pass 1 with Sakai smooth drum roller (left) and pass

3 with Caterpillar padfoot roller (right) .............................................................................16 Figure 11. CCV, MDP40, and CMV maps for passes 1 to 7 – TB1 granular base material ...........17 Figure 12. Semivariogram, histogram, and box plots (see description of box plots in text) of

CCV, MDP40, and CMV measurements - TB1 granular base material .............................18 Figure 13. Regression analyses between CCV and in-situ point measurements - TB1 granular

base material ......................................................................................................................20 Figure 14. Picture of the test bed – TB2 treated base material ......................................................22 Figure 15. CCV map and CBR profiles at three select locations with low, medium, and high

CCV values – TB2 treated base material (a = 0.30 mm, f = 55 Hz, v = 4 km/h nominal settings) ..............................................................................................................................23

Figure 16. Histogram (left) and semivariogram (right) of CCV measurements – TB2 treated base material ..............................................................................................................................23

Figure 17. Regression analyses between CCV and in-situ point measurements – TB2 treated base material (5 day cure) ..........................................................................................................25

Figure 18. Cracks observed on the treated base material following the Sakai vibratory roller pass – TB2 .................................................................................................................................26

Figure 19. TB3 treated base material compacted by ISU research team (section A) and contractor (section B) ..........................................................................................................................28

Figure 20. Pictures showing construction process on TB3 treated base ........................................29 Figure 21. Pictures showing construction process on TB3 treated base ........................................30 Figure 22. MDP40 and CMV maps for passes 1 to 5, and elevation and number of roller passes

maps – TB3 (section A) treated base material (a = 0.90 mm, f = 30 Hz, and v = 4 km/h nominal settings) ................................................................................................................32

Figure 23. Box plots of MDP40 and CMV measurements – TB3 treated base material (a = 0.90 mm, f = 30 Hz, and v = 4 km/h nominal settings) ..............................................................33

Figure 24. In-situ density test measurements during compaction in comparison with laboratory density measurements – TB3 treated base material ...........................................................33

Page 6: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

Figure 25. Comparison of ks, a*, and f maps obtained shortly after compaction (TB3) and after 2-day cure in manual and AFC modes (TB8) .......................................................................34

Figure 26. Histogram plots comparing measurements obtained shortly after compaction (TB3) and after 2-days curing (TB8) ............................................................................................35

Figure 27. Box plots comparing measurements obtained shortly after compaction (TB3) and after 2-days curing (TB8) ...........................................................................................................36

Figure 28. Semivariograms of ks measurements obtained on TB3 in manual mode, TB8 in manual mode, and TB8 in AFC mode ...............................................................................38

Figure 29. Regression analyses between ks and in-situ point measurements – TB3 treated base material (shortly after compaction; manual mode) ............................................................39

Figure 30. Regression analyses between ks and in-situ point measurements – TB8 treated base material (after 2-day cure; manual mode) ..........................................................................40

Figure 31. TB4 compacted granular subgrade material .................................................................42 Figure 32. CMV, MDP40, ks (and a*), and CCV maps on TB4 compacted granular subgrade

material along with DCP-CBR profiles at three selected locations ...................................44 Figure 33. Histogram and semivariogram plots of CMV, MDP40, ks and CCV measurements –

TB4 compacted granular subgrade material ......................................................................45 Figure 34. Regression analyses between ks and in-situ point measurements – TB4 granular

subgrade material ...............................................................................................................47 Figure 35. Regression analyses between CCV and in-situ point measurements – TB4 granular

subgrade material ...............................................................................................................48 Figure 36. Regression analyses between MDP40 and in-situ point measurements – TB4 granular

subgrade material ...............................................................................................................49 Figure 37. Regression analyses between CMV and in-situ point measurements – TB4 granular

subgrade material ...............................................................................................................50 Figure 38. Pictures showing construction process on TBs 5/6 treated subgrade ...........................52 Figure 39. Pictures showing construction process and final compacted surface on TBs 5/6 treated

subgrade .............................................................................................................................53 Figure 40. MDP40 and CMV maps for passes 1 to 4, and elevation and number of roller passes

maps – TB5 treated subgrade material (a = 0.90 mm, f = 30 Hz, and v = 4 km/h nominal settings) ..............................................................................................................................55

Figure 41. Boxplots of MDP40 and CMV measurements for passes 1 to 4 – TB5 treated subgrade material ..............................................................................................................................56

Figure 42. In-situ density test measurements during compaction in comparison with laboratory density measurements – TB5 treated subgrade material ....................................................56

Figure 43. Comparison of ks, a*, and f maps obtained shortly after compaction (TB5/6) and after 2-day cure in manual and AFC modes (TB9) ....................................................................57

Figure 44. Histogram plots comparing measurements obtained shortly after compaction (TB5/6) and after 2-days curing (TB9) ............................................................................................58

Figure 45. Box plots comparing measurements obtained shortly after compaction (TB5/6) and after 2-days curing (TB9) ...................................................................................................59

Figure 46. Semivariograms of ks measurements obtained on TB5 in manual mode, TB9 in manual mode, and TB9 in AFC mode ...............................................................................61

Figure 47. Regression analyses between ks and in-situ point measurements – TB5 treated subgrade material (shortly after compaction; manual mode) ............................................62

Figure 48. Regression analyses between ks and in-situ point measurements – TB9 treated

Page 7: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

subgrade material (after 2-day cure; manual mode) ..........................................................63 Figure 49. Comparison of ks and a* maps obtained in manual mode on granular subgrade

material before stabilization (TB4), shortly after stabilization (TB5/6), and 2-days after stabilization (TB9) .............................................................................................................64

Figure 50. Comparison of semivariograms of ks measurements obtained in manual mode on granular subgrade material before stabilization (TB4), shortly after stabilization (TB5/6), and 2-days after stabilization (TB9) ..................................................................................65

Figure 51. TB7 granular subgrade material (red sand subgrade with isolated white sand pocket)67 Figure 52. Roller spatial maps, MDP40, CMV, and ks measurements along the middle lane, and

DCP-CBR profiles at selected locations – TB7 granular subgrade material .....................69 Figure 53. Comparison between MDP40 and in-situ point measurements – TB7 granular subrade

material ..............................................................................................................................70 Figure 54. Comparison between CMV and in-situ point measurements – TB7 granular subrade

material ..............................................................................................................................71 Figure 55. Comparison between ks and in-situ point measurements – TB7 granular subrade

material ..............................................................................................................................72 Figure 56. Regression analyses between MDP40 and in-situ point measurements – TB7 granular

subgrade material ...............................................................................................................73 Figure 57. Regression analyses between CMV and in-situ point measurements – TB7 granular

subgrade material ...............................................................................................................74 Figure 58. Regression analyses between ks and in-situ point measurements – TB7 granular

subgrade material ...............................................................................................................75 Figure 59. ks (solid line) and a* (black circles) measurements in manual and AFC mode settings

– TB7 granular subgrade material ......................................................................................76 Figure 60. Regression analyses between CCV and in-situ point measurements – TBs 1, 2, and 479 Figure 61. Regression analyses between MDP40 and in-situ point measurements – TBs 4 and 7 .80 Figure 62. Regression analyses between CMV and in-situ point measurements – TBs 4 and 7 ...81 Figure 63. Regression analyses between ks and in-situ point measurements – TBs 3, 4, 5, 7, and 882 Figure 64. Photographs from open house on the project site .........................................................83

Page 8: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

LIST OF TABLES Table 1. Key features of the IC rollers used on the project .............................................................3 Table 2. Summary of test beds and in-situ testing .........................................................................10 Table 3. Summary of material index properties .............................................................................11 Table 4. Summary of univariate and spatial statistics – TB1 granular base material ....................19 Table 5. Summary of univariate statistics – TB2 treated base material .........................................24 Table 6. Summary of univariate statistics – TBs 3/8 treated base material ...................................37 Table 7. Summary of univariate statistics – TB4 granular subgrade material ...............................46 Table 8. Summary of spatial statistics – TB4 granular subgrade material ....................................46 Table 9. Summary of univariate statistics – TBs 5/9 treated base material ...................................60

Page 9: ACCELERATED IMPLEMENTATION OF INTELLIGENT …
Page 10: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

i

ACKNOWLEDGMENTS

This study was funded by Federal Highway Administration under the pooled fund contract DTFH61-07-C-R0032 for a research project titled “Accelerated Implementation of Intelligent Compaction Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials”. George Chang from the Transtec Group, Inc. is the Principal Investigator for this research project. Robert D. Horan is the project facilitator and assisted with scheduling rollers for the project. Caterpillar Inc., Texana Heavy Machinery, and Sakai America provided IC rollers. Nick Oetken and Candace Young with Caterpillar, Stan Rakowski (previously employed with Sakai America), and Pete Arcos from Texana provided field support on the IC rollers during the project. Tams Mullins with Spectra Measuring Systems (Trimble) provided assistance with setting up GPS on the IC rollers. Mississippi Department of Transportation (MSDOT) personnel assisted with falling weight deflectometer testing. Rick Croy, Kendall Clark, and many others with Dunn Road Builders assisted with preparation of the test beds. Several MSDOT and contractor personnel assisted with the coordination and execution of the project and participated in the field demonstrations. All their assistance and interest is greatly appreciated.

Page 11: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

ii

LIST OF SYMBOLS

a Theoretical vibration amplitude (eccentric moment divided by the drum mass) a* Actual measured vibration amplitude (double integral of acceleration data) A Acceleration at fundamental frequency AX Acceleration at X-order harmonic A’ Machine acceleration AFC Automatic feedback control b Machine internal loss coefficient used in MDP calculation b0 Intercept in a linear regression equation b1, b2, b3 Regression coefficients B Contact width of the drum C Semivariogram scale C0 Semivariogram nugget C+C0 Semivariogram sill CBR California bearing ratio (weighted average to compaction layer depth) CBR300 Weighted average CBR to a depth of 300 mm CCV Continuous compaction value CMV Compaction meter value COV Coefficient of variation (calculated as the ratio of mean and standard deviation) DPI Dynamic cone penetration index d0 Measured settlement under plate D10 Particle size corresponding to 10% passing D30 Particle size corresponding to 30% passing D60 Particle size corresponding to 60% passing E Elastic modulus ELWD-Z3 Elastic modulus determined from 300-mm plate Zorn light weight deflectometer EFWD-D3 Elastic modulus determined from 300-mm plate Dynatest falling weight

deflectometer EV1 Initial modulus from 300-mm diameter static plate load test EV2 Reload modulus from 300-mm diameter static plate load test f Vibration frequency F Shape factor Fs Drum force g Acceleration of gravity Gs Specific gravity GPS Global positioning system h Separation distance IC-MV Intelligent compaction measurement value ks Roller integrated stiffness LL Liquid limit m Machine internal loss coefficient used in MDP calculation md drum mass mere Eccentric moment of the unbalanced mass MDP Caterpillar Machine drive power MDP40 See description in text

Page 12: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

iii

MV Measurement value n Number of test measurements p Number of regression parameters Pg Gross power needed to move the machine PI Plasticity index PL Plastic limit Point-MV In-situ point measurement value r Radius of the plate R Semivariogram range R’ Radius of the roller drum R2 Coefficient of determination RMV Resonant meter value v Roller velocity w Moisture content determined from Humboldt nuclear gauge wopt Optimum moisture content W Roller weight zd Drum displacement α Slope angle (roller pitch from a sensor) Phase angle Statistical mean Statistical standard deviation0 Applied stress η Poisson’s ratio d Dry unit weight determined from Humboldt nuclear gauge (NG) dmax Maximum dry unit weight (h) Semivariogram

Page 13: ACCELERATED IMPLEMENTATION OF INTELLIGENT …
Page 14: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

1

INTRODUCTION

This report presents results from a field investigation conducted on the US84 highway project in Waynesboro, Mississippi. The machine configurations and roller-integrated measurement systems used on this project included: a Caterpillar CP56 padfoot roller equipped with machine drive power (MDP) and compaction meter value (CMV) measurement technologies, a Sakai SW880 dual vibratory smooth drum roller equipped with compaction control value (CCV) technology, and a Case/Ammann SV212 smooth drum vibratory roller equipped with roller-integrated stiffness (ks) and automatic feedback control. All the machines were equipped with real time kinematic (RTK) global positioning system (GPS) and on-board display and documentation systems. The project involved constructing and testing nine test beds with untreated and cement treated granular base and subgrade materials. The IC measurement values (IC-MVs) were evaluated by conducting field testing in conjunction with a variety of in-situ testing devices measuring density, moisture content, California bearing ratio (CBR), and elastic modulus. An open house was conducted near the end of the field investigation to disseminate results from current and previous IC projects. The Mississippi department of transportation (MSDOT), contractor’s personnel, and representatives from the IC roller manufacturers participated in the field testing phase of the project and the open house.

The goals of this field investigation were similar to previous demonstration projects and included the following:

document the impact of AFC operations on compaction uniformity, document machine vibration amplitude influence on compaction efficiency, develop correlations between IC measurement values to traditional in-situ point

measurements (point-MVs), study IC roller measurement influence depth, compare IC results to tradition compaction operations, study IC measurement values in production compaction operations, and evaluate IC measurement values in terms of alternative specification options

This report presents brief background information for the four IC-MVs evaluated in this study (MDP, CMV, CCV, and ks), documents the results and analysis from the laboratory and field testing, and documents the field demonstration activities. Geostatistical methods were used to quantify and characterize spatial non-uniformity of the embankment subgrade and subbase materials using spatially referenced IC-MV data. Regression analysis was performed to evaluate correlations between IC-MVs and in-situ soil properties determined using point-MVs. Density and moisture content tests were performed using Humboldt nuclear gauge, modulus tests were obtained using Zorn light weight deflectometer (LWD) setup with 300 mm diameter plates, Dynatest falling weight deflectometer (FWD) setup with 300 mm diameter plate, and static plate load test (PLT) setup with 300 mm diameter plate. Empirical correlations between IC-MVs and in-situ point-MVs are first evaluated independently for each test bed which were sometimes obtained over a narrow measurement range and then combined to develop site wide correlations capturing a wide measurement range. This report provides new information with respect to IC-MVs and in-situ point-MVs on cement treated

Page 15: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

2

materials. The results and correlations provided in this report should be of significant interest to the pavement, geotechnical, and construction engineering community and are anticipated to serve as a good knowledge base for implementation of IC compaction monitoring technologies and various new in-situ testing methods into earthwork construction practice. BACKGROUND

Caterpillar CP56 padfoot, Case SV212 vibratory smooth drum, and Sakai SW880 dual drum IC rollers were used on the project (Figure 1). A digital display unit employing proprietary software is mounted in the roller cabin for on-board visualization of roller position, IC-MVs, coverage information, amplitude/frequency settings, speed, etc. The rollers were outfitted with a real-time kinematic (RTK) global positioning system (GPS) to continuously record the roller position information. Some key features of the rollers are summarized in Table 1. Caterpillar CP56 roller recorded machine drive power (MDP40) and compaction meter value (CMV), Case SV212 roller recorded roller-integrated stiffness (ks), and Sakai SW880 roller recorded continuous compaction value (CCV). Brief descriptions of these IC-MVs are provided in the following discussion.

Figure 1. Caterpillar CP56 (top left) padfoot, Case SV212 smooth drum, and Sakai SW880 dual smooth drum IC rollers used on the project

Page 16: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

3

Table 1. Key features of the IC rollers used on the project

Feature Caterpillar CP56 Case SV212 Sakai SW880 Drum Type Padfoot Smooth drum Dual smooth drum

Frequency ( f ) 30 Hz 0 to 35 Hz 42, 50, and 67 Hz

Amplitude (a) Settings

Static, 0.90 mm (low amplitude), and 1.80 mm (high amplitude)

Amplitude settings using percent eccentric moments (0 to 100%) [0 represents no vibration and 100% represents high amplitude]

0.3 mm (low), 0.6 mm (high)

IC-MV MDP40 (shown as CCV in the output) and Geodynamik CMV

ks (MN/m) (ks system is developed by Ammann)

CCV

Display Software

AccuGrade® Ammann Compaction Expert (ACE) ®

Aithon MT-R®

GPS coordinates

UTM Zone Mississippi East (NAD83)

UTM Zone Mississippi East (NAD83)

UTM Zone Mississippi East (NAD83)

Output Documentation

Date/Time, Location (Northing/Easting/Elevation of left and right ends of the roller drum), Speed, CCV, CMV, RMV, Frequency, Amplitude (theoretical), Direction (forward/ backward), Vibration (On/Off)

Date/Time, Location (Latitude/Longitude/ Elevation), Machine length/width, Direction (forward/ backward), Vibration (On/Off), Stiffness (ks), Amplitude (actual), Speed, Frequency

Date/Time, Location (Northing/Easting/ Elevation), CCV, Temperature, Frequency, Direction (forward/backward), Vibration (On/Off), GPS Quality

Data frequency About every 0.2 m at the center of the drum (for a nominal v = 4 km/h)

About every 1 m at the center of the drum (for a nominal v = 4 km/h)

About every 0.3 m at the center of the drum (for a nominal v = 4 km/h)

Output Export File

*.csv *.txt *.txt

Automatic Feedback Control (AFC)

No Yes No

Machine Drive Power (MDP) Value

MDP technology relates mechanical performance of the roller during compaction to the properties of the compacted soil. Detailed background information on the MDP system is provided by White et al. (2005). Controlled field studies documented by White and Thompson (2008), Thompson and White (2008), and Vennapusa et al. (2009) verified that MDP values are empirically related to soil compaction characteristics (e.g., density, stiffness, and strength). MDP is calculated using Eq. 1.

Page 17: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

4

bmvg

'ASinWvPMDP g

(1)

Where MDP = machine drive power (kJ/s), Pg = gross power needed to move the machine (kJ/s), W = roller weight (kN), A’ = machine acceleration (m/s2), g = acceleration of gravity (m/s2), α = slope angle (roller pitch from a sensor), v = roller velocity (m/s), and m (kJ/m) and b (kJ/s) = machine internal loss coefficients specific to a particular machine (White et al. 2005). MDP is a relative value referencing the material properties of the calibration surface, which is generally a hard compacted surface (MDP = 0 kJ/s). Positive MDP values therefore indicate material that is less compact than the calibration surface, while negative MDP values indicate material that is more compacted than the calibration surface (i.e. less roller drum sinkage). The MDP values obtained from the machine were recalculated to range between 1 and 150 using Eq. 2 (referred to as MDP40). In Eq. 3, the calibration surface with MDP = 0 kJ/s was scaled to MDP40 = 150 and a soft surface with MDP = 54.23 kJ/s (40000 lb-ft/s) was scaled to MDP40 = 1.

)MDP(77.2150MDP40 (2)

Compaction Meter Value (CMV) and Resonant Meter Value (RMV)

CMV is a dimensionless compaction parameter developed by Geodynamik that depends on roller dimensions, (i.e., drum diameter and weight) and roller operation parameters (e.g., frequency, amplitude, speed), and is determined using the dynamic roller response (Sandström 1994). It is calculated using Eq. 3, where C is a constant (300), A2 = the acceleration of the first harmonic component of the vibration, A = the acceleration of the fundamental component of the vibration (Sandström and Pettersson 2004). Correlation studies relating CMV to soil dry unit weight, strength, and stiffness are documented in the literature (e.g., Floss et al. 1983, Samaras et al. 1991, Brandl and Adam 1997, Thompson and White 2008, White and Thompson 2008).

A

AC CMV 2 (3)

RMV provides an indication of the drum behavior (e.g. continuous contact, partial uplift, double jump, rocking motion, and chaotic motion) and is calculated using Eq. 4, where A0.5 = subharmonic acceleration amplitude caused by jumping (the drum skips every other cycle). It is important to note that the drum behavior affects the CMV measurements (Brandl and Adam 1997) and therefore must be interpreted in conjunction with the RMV measurements (Vennapusa et al. 2010).

A

AC RMV 0.5

(4)

Page 18: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

5

Roller-Integrated Stiffness (ks) Measurement Value

The ks measurement system was introduced by Ammann during late 1990’s based on a lumped parameter two-degree-of-freedom spring dashpot system illustrated in Figure 2 (Anderegg and Kauffmann 2004). The spring dashpot model has been found effective in representing the drum-ground interaction behavior (Yoo and Selig 1980). The drum inertia force and eccentric force time histories are determined from drum acceleration data and eccentric position (neglecting frame inertia). The drum displacement (zd) is determined by double integrating the measured peak drum accelerations. The roller-integrated stiffness (ks) is determined using Eq. 5, where f is the excitation frequency, md is the drum mass, mere is the eccentric moment of the unbalanced mass, is the phase angle, a is vibration amplitude. The ks value represents a quasi-static stiffness value and is reportedly independent of the excitation frequency between 25 to 40 Hz (Anderegg and Kaufmann 2004).

a

cosrmmf4k eed22

s

(5)

zd

csks

mf

ksuspcsusp

fe(t)

zf

Equivalent frame weight

Suspension stiffnessand damping

Drum weightand dynamicforce generated

Soil stiffnessand damping

md

Fs

Figure 2. Lumped parameter two-degree-of-freedom spring dashpot model representing vibratory compactor and soil behavior (reproduced from Yoo and Selig 1980)

The ks measurement system has the capability to perform compaction in a manual mode and in an automatic feedback control (AFC) mode. The AFC operations in the Case roller are controlled by the Ammann Compaction Expert (ACE) plus system. Three AFC operation settings are possible using the ACE plus system (Anderegg et al. 2006):

1. Low performance setting: Maximum applied force = 14 kN with vibration amplitude (a*) varying from 0.4 to 1.5 mm.

2. Medium performance setting: Maximum applied force = 20 kN with vibration amplitude (a*) varying from 1.0 to 2.0 mm.

3. High performance setting: Maximum applied force > 25 kN with vibration amplitude (a*) varying from 2.0 to 3.0 mm.

Page 19: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

6

When operated in AFC mode, as sub-harmonic vibrations occur, the roller automatically adjusts the eccentric mass moment to adjust the vibration amplitude and excitation frequency (Anderegg et al. 2006). Correlation studies relating ks to soil dry unit weight, strength, and stiffness are documented in the literature (Anderegg and Kaufmann 2004).

Roller-Integrated Compaction Control Value (CCV)

Sakai Compaction Control Value (CCV) is a vibratory-based technology which makes use of an accelerometer mounted to the roller drum to create a record of machine-ground interaction with the aid of GPS. The concept behind determination of CCV is that as the ground stiffness increases, the roller drum starts to enter into a “jumping” motion which results in vibration accelerations at various frequency components. This is illustrated in Figure 3.

f

A

2 f

A

2 f

A

2

A A

A2A2

A

32.51.50.5

A0.5

A1.5

A2.5A3

Increasing ground stiffness

Figure 3. Changes in amplitude spectrum with increasing ground stiffness (modified from Scherocman et al. 2007)

The CCV is calculated using the acceleration data from first subharmonic (0.5Ω), fundamental (Ω), and higher-order harmonics (1.5Ω, 2Ω, 2.5Ω, 3Ω) as presented in Eq. 6.

100AA

AAAAACCV

5.0

35.225.15.0

(6)

The vibration acceleration signal from the accelerometer is transformed through the Fast Fourier Transform (FFT) method and then filtered through band pass filters to detect the acceleration amplitude spectrum (Scherocman et al. 2007).

Overview of Project Earthwork Specifications

The MSDOT standard specifications for earthwork along with special provision No. 907-308-4M (Dated 08/14/2007) were implemented on the project. A typical pavement foundation layer section consisted of a 150 mm thick cement treated subgrade layer overlain by a 150 mm thick cement treated granular base material. The acceptance was based on achieving a target density and pay factors were provided in the special provision based on the achieved percent maximum density. Following were the QA and testing requirements:

Page 20: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

7

Each lot (750 m in length) is divided in to five sub lots with one density test taken at

random in each sublot. For treated subgrade layers, the average of five density tests shall equal or exceed 96% of

maximum density with no single density test below 94%. For treated base layers, the average of five density tests shall equal or exceed 97% of

maximum density with no single density test below 95%. Pay factors were provided in the special provision based on the maximum achieved percent maximum density.

Following are some of the key construction related attributes of the specification and special provision documents:

The soil to be treated should to be scarified and moisture-conditioned prior to spreading of the cement. All additional water required to bring the section to the required moisture content should to be added within one hour after the beginning of the mixing.

The soil-cement mixture should be mixed using approved soil mixers (i.e., multiple pass mixers, single pass mixers, travelling plant mixers, and central plant mixers). A multiple pass mixing method using rotary-type mixer with multiple mixing passes (2 to 3) was employed on the project.

The mixed material should to be shaped immediately after mixing. Initial compaction is should begin immediately, and machining and compacting should continue until the entire depth and width of the course is compacted to the required density within two hours of the time of beginning mixing.

Compaction by vibration is not permitted after the cement has taken its initial set (i.e., one hour).

After compaction, the surface should be reshaped to the required geometry and if necessary, shall be lightly scarified to remove imprints left by the compacting or shaping equipment. The surface should be sprinkled as necessary and thoroughly rolled with a pneumatic roller.

Each treated layer should be covered with a bituminous curing seal as soon as possible (within 24 hours) after compaction. Placement of a subsequent layer above the treated layer was not permitted for at least seven calendar days. During this 7-day cure period, no traffic was permitted on the treated layer.

ANALYSIS METHODS

Regression Analysis

Simple linear and non-linear regression relationships between IC-MVs and in-situ point measurement values (Point MVs) were developed by spatially pairing the data obtained from the test beds. The analysis was performed by considering point-MVs as “true” independent variables and IC-MVs as dependent variables using the models shown in Eqs. 7 to 9, where b0 = intercept and b1, b2 = regression parameters.

Linear model: MVintPobbMVIC 10 (7)

Page 21: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

8

Non-linear power model: 2b1 )MVintPo(bMVIC (8)

Non-linear exponential model: )MVintPob(1

2e1bMVIC (9) Statistical significance of the independent variable was assessed based on p- and t-values. The selected criteria for identifying the significance of a parameter included: p-value < 0.05 = significant, < 0.10 = possibly significant, > 0.10 = not significant, and t-value < -2 or > +2 = significant. The best fit model is determined based on the strength of the regression relationships assessed by the coefficient of determination (i.e., R2) values. For the analysis and discussion in this report, an R2 value ≥ 0.5 is considered acceptable following the guidelines from European specifications. A statistical prediction interval approach for determining “target” values from the regression relationships would account for R2 values in the relationships (see NCHRP 21-09, 2010). A regression relationship with lower R2 values would result in higher target value and a regression relationship with higher R2 value will result in lower target values.

Geostatistical Analysis

Spatially referenced IC measurement values provide an opportunity to quantify “non-uniformity” of compacted fill materials. Vennapusa et al. (2010) demonstrated the use of semivariogram analysis in combination with conventional statistical analysis to evaluate non-uniformity in QC/QA during earthwork construction. A semivariogram is a plot of the average squared differences between data values as a function of separation distance, and is a common tool used in geostatistical studies to describe spatial variation. A typical semivariogram plot is presented in Figure 4. The semivariogram (h) is defined as one-half of the average squared differences between data values that are separated at a distance h (Isaaks and Srivastava 1989). If this calculation is repeated for many different values of h (as the sample data will support) the result can be graphically presented as experimental semivariogram shown as circles in Figure 4. More details on experimental semivariogram calculation procedure are available elsewhere in the literature (e.g., Clark and Harper 2002, Isaaks and Srivastava 1989). To obtain an algebraic expression for the relationship between separation distance and experimental semivariogram, a theoretical model is fit to the data. Some commonly used models include linear, spherical, exponential, and Gaussian models. A spherical model was used for data analysis in this report. Arithmetic expression of the spherical model and the spherical variogram are shown in Figure 4. Three parameters are used to construct a theoretical semivariogram: sill (C+C0), range (R), and nugget (C0). These parameters are briefly described in Figure 4. More discussion on the theoretical models can be found elsewhere in the literature (e.g., Clark and Harper 2002, Isaaks and Srivastava 1989). For the results presented in this section, the sill, range, and nugget values during theoretical model fitting were determined by checking the models for “goodness” using the modified Cressie goodness fit method (see Clark and Harper 2002) and cross-validation process (see Isaaks and Srivastava 1989). From a theoretical semivariogram model, a low “sill” and longer “range of influence” represent best conditions for uniformity, while the opposite represents an increasingly non-uniform condition. Some of the results presented in this report revealed nested structures with short-range and long-range components in the experimental semivariograms. Nested structures have been observed in geological applications where different physical processes are responsible for spatial variations

Page 22: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

9

at different scale (see Chiles and Delfiner 1999). For the cases with nested structures, nested spherical variograms combining two spherical models (with two sill values and two range values) are fit to the experimental semivariogram data.

Range (R)

Scale, C

Nugget, C0

SillC + C0

Range, R: As the separation distance between pairs increase, the corresponding semivariogram value will also generally increase. Eventually, however, an increase in the distance no longer causes a corresponding increase in the semivariogram, i.e., where the semivariogram reaches a plateau. The distance at which the semivariogram reaches this plateau is called as range. Longer range values suggest greater spatial continuity or relatively larger (more spatially coherent) “hot spots”.

Sill, C+C0: The plateau that the semivariogram reaches at the range is

called the sill. A semivariogram generally has a sill that is approximately equal to the variance of the data.

Nugget, C0: Though the value of the semivariogram at h = 0 is strictly zero,

several factors, such as sampling error and very short scale variability, may cause sample values separated by extremely short distances to be quite dissimilar. This causes a discontinuity at the origin of the semivariogram and is described as nugget effect.(Isaaks and Srivastava, 1989)

Spherical Semivariogram

ExperimentalSemivariogram(circles)

RhCC)h(

Rh0R2

h

R2

h3CC)h(

0)0(

0

3

3

0

Se

miv

ario

gram

, (

h)

Separation Distance, h

Figure 4. Description of a typical experimental and spherical semivariogram and its parameters

EXPERIMENTAL TESTING

Description of Test Beds

A total of nine test beds including two subgrade materials (“white sand” and “red sand”), one base material, and treated subgrade and base materials were studied. A summary of test beds with material conditions and tests performed is provided in Table 2. A summary of material index properties is provided in Table 3. Details regarding construction and testing of each test bed are provided in the discussion later and in test bed summary sheets in the Appendix. The following specific objectives were targeted for the different test beds evaluated in this study:

Capture data over wide measurement range to develop IC-MV and different in-situ point-MV correlations – TBs 1, 2, 3, 4, 5, 6, 7, 8, and 9.

Demonstrate the usefulness of using IC-MV maps for selection of QA test locations – TBs 2, 4, 5, and 8.

Explore geostatistical methods to quantify and characterize spatial non-uniformity of embankment materials – TB1, 2, 3, 4, 5, 6, 8, and 9.

Evaluate AFC mode operations in comparison with manual mode operations – TBs 7, 8, and 9.

Compare IC-MVs on untreated and treated (shortly after compaction and after 2 days curing) subgrade and base layers – TBs 3 and 8 for base, and TBs 4, 5,6, and 9 for subgrade.

Page 23: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

10

Table 2. Summary of test beds and in-situ testing

TB Material Date Machine(s) Pass

Theoretical Amplitude (mm) or

setting, Speed (km/h)*

Notes/In-situ Test Measurements

1 Granular base

[existing compacted layer]

07/13 S 1 0.30, 5 ELWD-Z3, EFWD-D3, d,

w, RC, EV1, EV2, CBR C 2-7 0.90, 4

2 Cement Treated Granular base

[5 day cure] 07/13 S Map 0.30, 5

ELWD-Z3, EFWD-D3, d, w, RC, EV1, EV2,

CBR

3 Cement Treated Granular Base

[same area as TB1] 07/14

C 5 0.90, 4 —

C/A Map Ecc.= 15%, 4 ELWD-Z3, EFWD-D3, d,

w, RC, EV1, EV2, CBR

4 Granular Subgrade

[existing compacted layer]

07/14

S Map 1 0.60, 5

ELWD-Z3, d, w, RC, EV1, EV2, CBR

C/A Map 2 Ecc. = 15%, 4

C Map 3 0.90, 4

5

Cement Treated Granular Subgrade [portion of TB4: ISU

compaction]

07/15 C 1-6 Lanes 1-3: 0.90, 4

Lanes 4-6: static, 4 ELWD-Z3, EFWD-D3, d,

w, RC, EV1, EV2, CBR C/A Map Ecc. = 15%, 4

6

Cement Treated Granular Subgrade

[portion of TB4: Contractor compaction]

07/15 C/A Map Ecc. = 15%, 4 —

7 Granular Subgrade

[portion of subgrade with white sand pocket]

07/15

C/A Map 1 Ecc. = 15%, 4

ELWD-Z3, d, w, RC, EV1, EV2, CBR

C/A Map 2 AFC (Medium), 4

C Map 3 0.90, 4

8 Cement Treated Granular Base

[2 day cure on TB3] 07/16

C/A Map 1 Ecc. = 10%, 4 ELWD-Z3, EFWD-D3, d, w, RC, EV1, EV2,

CBR C/A Map 2 AFC (Low), 4

9 Cement Treated

Granular Subgrade [2 day cure on TB5]

07/17 C/A Map 1 Ecc. = 15%, 4 ELWD-Z3, EFWD-D3, d,

w, RC, EV1, EV2, CBR C/A Map 2 AFC (High), 4

Notes: TB – test bed, * - nominal, C – Caterpillar, C/A – Case/Ammann, S - Sakai ; Ecc – Percent eccentric moment setting in Case/Ammann machine for amplitude adjustment, AFC – automatic feedback control mode. C – Caterpillar, C/A – Case/Ammann, S – Sakai, w – moisture content, d – dry unit weight, RC – relative compaction, CBR – California bearing ratio determined from dynamic cone penetrometer (DCP) test, ELWD-Z3 – elastic modulus determined using 300 mm diameter plate Zorn light weight deflectometer (LWD), EV1 and EV2 – initial and reload moduli determined from static plate load test (PLT), EFWD-D3 – elastic modulus determined using 300 mm diameter plate Dynaest falling weight deflectometer (FWD) test.

Page 24: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

11

Laboratory Testing

Laboratory testing was performed on two subgrade materials and one base material obtained from the project. Testing involved conducting grain size analysis and Atterberg limits tests to classify the materials in accordance with unified soil classification system (USCS) and American association of state highway and transportation officials (AASHTO) system. A summary of the material index properties is provided in Table 3. Grain size distribution curves of the three materials are presented in Figure 5. Standard Proctor tests were conducted on untreated materials by varying the moisture content of the material and the results are presented in Figure 6. Maximum dry unit weight (dmax) and optimum moisture content (wopt) results from Proctor tests are summarized in 3. Proctor tests were also conducted on treated subgrade and base material samples obtained from the test beds during construction.

Table 3. Summary of material index properties

Parameter Subgrade

(Red Sand) Subgrade

(White Sand) Base

Standard Proctor Test Results (ASTM D698-00a)

dmax (kN/m3) 19.04 16.27 18.02

wopt 10.8 14.0 10.1

Grain-Size Analysis Results (ASTM D 422-63)

Gravel Content (%) (> 4.75mm) 0 0 0

Sand Content (%) (4.75mm – 75m) 63 92 84

Silt Content (%) (75m – 2m) 19 4 7

Clay Content (%) (< 2m) 18 4 9

D10 (mm) — 0.09 0.01

D30 (mm) 0.03 0.15 0.20

D60 (mm) 0.20 0.23 0.35

Coefficient of Uniformity, cu — 2.7 49.1

Coefficient of Curvature, cc — 1.1 17.0

Atterberg Limits Test Results (ASTM D4318-05)

Liquid Limit, LL (%) Non Plastic

Plastic Limit, PL (%)

AASHTO Classification (ASTM D3282-09) A-4 A-3 A-2-4

USCS Classification (ASTM D2487-00) SM SP-SM SM

Specific Gravity, Gs (Assumed) 2.70 2.70 2.70

Page 25: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

12

#10

#40 #10

0

#200

#43/8

"

3/4

"

0.00

2

SandGravel Silt Clay

Grain Diameter (mm)

0.00010.0010.010.1110100

Per

cent

P

assi

ng

0

20

40

60

80

100

TB1-SubbaseTB4/7-Red Subgrade SandTB7-White Subgrade Sand

Figure 5. Grain-size distribution curves of base and subgrade materials

Moisture Content (%)

0 2 4 6 8 10 12 14 16 18

Dry

Uni

t W

eigh

t (k

N/m

3)

15

16

17

18

19

20

Dry

Uni

t W

eig

ht (

pcf

)

100

105

110

115

120

125

TB1-SubbaseTB4/7-Red Subgrade SandTB7-White Subgrade Sand

ZAV Line (Gs = 2.70)

Figure 6. Laboratory standard Proctor moisture-density relationships for base and subgrade materials

To study the effect of compaction time delay on the density of the treated materials, samples were prepared in the laboratory and standard Proctor tests were conducted at various time intervals, i.e., at 0, 30, 60, 120, and 240 minutes after mixing. The treated “red sand” subgrade and base materials were prepared by adding 5.5% cement by dry weight of the soil, per project specifications. Results obtained from this study are presented in Figure 7 which indicates that the dry density of the treated materials reduce with increasing compaction delay time after

Page 26: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

13

mixing. Similar results have been demonstrated by Arman and Saifan (1967) and indicated that a delay of two or more hours in compaction after mixing results in reduced durability, compressive strength, and density of the soil-cement mixture. Arman and Saifan (1967) recommended that compaction of soil-cement mixture should not be delayed beyond 0.80 times the initial setting time of the cement gel. Cowell and Irwin (1979) noted that delays beyond 3 hours may increase the required compactive effort to a level that may be beyond the capabilities of ordinary field compaction equipment. Specifications for the project indicated that the soil-cement mixture be compacted to required density within two hours after mixing (see earlier discussion under Overview of Earthwork Specifications section).

Time (minutes) [Wait time after mixing]

0 50 100 150 200 250 300

Dry

Uni

t W

eigh

t (k

N/m

3)

17.5

18.0

18.5

19.0

19.5

20.0

20.5

Dry

Uni

t W

eigh

t (p

cf)

110

115

120

125

130Laboratory Sample; w = 10.0%In-Situ Sample; w = 11.4%

Approximate wait time after pulverizer pass

Stabilized Granular Subbase - TB3

TB1 Unstabilized Subbasedmax = 18.02 kN/m3 @ wopt = 10.1%

Time (minutes) [Wait time after mixing]

0 50 100 150 200 250 300

Dry

Uni

t W

eigh

t (k

N/m

3 )

17.5

18.0

18.5

19.0

19.5

20.0

20.5

Dry

Uni

t W

eigh

t (p

cf)

110

115

120

125

130Laboratory Sample; w = 10.0%In-Situ Sample; w = 10.2%

Approximate wait time after first pulverizer pass

Stabilized Granular Subgrade (Red Sand) - TB5

TB4 Unstabilized Subgrade (Red Sand)dmax = 19.04 kN/m3 @ wopt = 10.8%

Figure 7. Effect of wait time (after mixing) on dry unit weight of treated base and subgrade materials

In-situ Testing Methods

Eight different in-situ testing methods were employed in this study to evaluate the in-situ soil engineering properties (Figure 8): (a) Zorn light weight deflectometer setup with 300 mm

Page 27: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

14

plate diameter to determine elastic modulus (ELWD-Z3 for 300 mm plate diameter), (b) Dynamic Cone Penetrometer (DCP) to determine California bearing Ratio (CBR), (c) calibrated Humboldt nuclear gauge (NG)to measure moisture content (w) and dry unit weight (d), (d) 300-mm diameter Dynatest falling weight deflectometer (FWD) to determine elastic modulus (EFWD-D3), and (e) 300-mm plate diameter static plate load test (PLT) to determine initial (EV1) and re-load modulus (EV2). FWD tests were conducted by MSDOT personnel. All other in-situ tests were conducted by ISU research team. LWD tests were performed following manufacturer recommendations (Zorn 2003) and the ELWD

values were determined using Eq. 10, where E = elastic modulus (MPa), d0 = measured settlement (mm), η = Poisson’s ratio (0.4), 0 = applied stress (MPa), r = radius of the plate (mm), F = shape factor depending on stress distribution (assumed as ) (see Vennapusa and White 2009). The results are reported as ELWD-Z3 (Z represents Zorn LWD and 3 represents 300 mm diameter plate).

Fd

r)1(E

0

02

(10)

FWD testing was conducted by MSDOT personnel using a Dynatest trail mounted FWD by applying one seating drop using a nominal force of about 29 kN followed by three test drops each at a nominal force of about 29, 38, and 48 kN. The actual applied force was recorded using a load cell. A composite modulus value (EFWD-D3) was calculated using the measured deflection at the center of the plate, corresponding applied contact force, and Eq. 1. Shape factor F = 8/3 was assumed in the calculations similar to LWD calculations. Static PLT’s were conducted by applying a static load on 300 mm diameter plate against a 6.2kN capacity reaction force. The applied load was measured using a 90-kN load cell and deformations were measured using three 50-mm linear voltage displacement transducers (LVDTs). The load and deformation readings were continuously recorded during the test using a data logger. The EV1 and EV2 values were determined from Eq. 10 using deflection values at 0.1 and 0.2 MPa applied contact stresses for subgrade materials and at 0.2 and 0.4 MPa contact stresses for base materials, as illustrated in Figure 9. Shape factor F = 8/3 and η = 0.4 were assumed in the calculations, similar to LWD and FWD calculations. DCP tests were performed in accordance with ASTM D6951-03 to determine dynamic cone penetration index (DPI) and calculate CBR using Eq. 11. The DCP test results are presented in this report as CBR point values or CBR depth profiles. When the data is presented as point values, the data represents a weighted average CBR of the compaction layer depth or depth indicated in the subscript (e.g., CBR200 indicates weighted average CBR to a depth of 200 mm and CBR indicates weighted average CBR to the depth equal to the thickness of the compaction layer).

12.1DPI

292CBR (11)

Page 28: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

15

Figure 8. In-situ testing methods used on the project: (a) Humboldt nuclear gauge, (b) dynamic cone penetrometer, (c) Zorn light weight deflectometer, (d) Dynatest falling

weight deflectometer, (e) static plate load test

0 (MN/m2)

0 (MN/m2)

subgrade base and subbase

0.0

0.1

0.2

0.0

0.2

0.4

Deflection Deflection

EV1 EV2

EV1 EV2

Figure 9. EV1 and EV2 determination procedure from static PLT for subgrade and base materials

(a) (b) (c)

(f) (e)

Page 29: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

16

EXPERIMENTAL TEST RESULTS

TB1 Granular Base Material (Untreated)

Test Bed Conditions, IC-MV Mapping, and Point-MV Testing

TB1 consisted of mapping the existing compacted granular base layer (untreated) with the Sakai smooth dual drum IC roller for one roller pass and Caterpillar padfoot IC roller for six roller passes (Figure 10). The area was mapped in four roller lanes. CCV IC-MVs were obtained from the Sakai roller using a = 0.30 mm, f = 50 Hz, and v = 5 km/h nominal settings. MDP40 and CMV IC-MVs were obtained from the Caterpillar roller using a = 0.90 mm, f = 30 Hz, and v = 4 km/h nominal settings. Point MVs (LWD, FWD, NG, PLT, and DCP) were performed at 6 randomly selected test locations following the Sakai roller pass.

After Pass 1

After Pass 3

Figure 10. TB1 granular base material after pass 1 with Sakai smooth drum roller (left) and pass 3 with Caterpillar padfoot roller (right)

Test Results and Analysis

IC-MV maps from the Sakai and Caterpillar roller passes are shown in Figure 11. In-situ point-MV test locations are shown on the CCV map in Figure 11. Figure 12 shows semivariograms, histogram, and box plots of the IC-MV data. A summary of the univariate and the spatial statistics of IC-MV and in-situ point-MV data are presented in Table 4. The experimental semivariograms of the MDP40 values showed a nested spatial structure with short-range and long-range components. A nested spherical variogram was fit to the experimental semivariogram data. The CCV and CMV experimental semivariograms did not exhibit nested structures. Similar nested structures were observed for MDP40 measurements in an earlier field study (see NY field study report). The long-range spatial structure is attributed to the spatial variation in the underlying layer support conditions while the short-range spatial

Page 30: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

17

structure is believed to be realted to soil properties closer to the surface. This long-range component was reduced considerably from pass 1 to 2 to 6 (Figure 12). The MDP40 semivariogram showed decreasing spatial non-uniformity with increasing passes which is evidenced by the decreasing sill value (sill1 decreased from 82 to 20 and sill2 decreased from 130 to 22 from pass 2 to 6; see Table 4). CMV semivariograms did not exhibit a significant change in the sill values (varied between 4 and 8) with increasing pass. The box plots presented in Figure 12 present the range of the data observed for each pass. The bottom boundary of the box indicates the 25th percentile, the line within the box indicates the median, and the top boundary of the box indicates the 75th percentile of the IC-MV data. The error bars above and below the box indicate the 90th and 10th percentile, respectively. The circles outside the error bars are statistical outliers. On average, the MDP40 values decreased with increasing pass (pass 1 to 6 = 105.7 to 98.3), while the CMV measurements increased only slightly with increasing pass (pass 1 to 6 = 4.9 to 6.8). The decrease in MDP40 likely due to loosening of the material at the surface from padfoot indentations (see Figure 10). Regression analysis results between CCV IC-MVs and in-situ point-MVs are presented in Figure 13. The relationships showed weak correlations with R2 values ranging from 0 to 0.24. The correlations are weak because the range of measurements is narrow.

215

m

MDP40

Pass 2MDP40

Pass 3

MDP40

Pass 4MDP40

Pass 5

MDP40

Pass 6MDP40

Pass 7CMV

Pass 2CMV

Pass 3CMV

Pass 4CMV

Pass 5CMV

Pass 6CMV

Pass 7

(1)

(2)

(3)

(4)

(5)

(6)

In-Situ Test Locations

>202015105

CCV

CCVPass 1

NORTH

CMV

>2020151052<2

MDP40

>140140130120110100<100

Figure 11. CCV, MDP40, and CMV maps for passes 1 to 7 – TB1 granular base material

Page 31: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

18

Pass Number

1 2 3 4 5 6 7 8

CC

V

0

5

10

15

20

25

Pass Number

0 1 2 3 4 5 6 7 8

MD

P40

50

75

100

125

150

Pass Number

0 1 2 3 4 5 6 7 8

CM

V

0

5

10

15

20

25

CCV

0 5 10 15 20 25 30 35 40

Fre

que

ncy

0

5000

10000

15000

20000

MDP40

80 100 120 140 1600

500

1000

1500

2000Pass 2 Pass 7

Pass 1

CMV

0 10 20 30 40 50 600

500

1000

1500

2000Pass 2 Pass 7

Separation Distance, h (m)

0 20 40 60 80Se

miv

ario

gra

m, (

h) [

CC

V]2

0

10

20

30

40

50Pass 1

Separation Distance, h (m)

0 20 40 60 80Se

miv

ario

gra

m, (

h) [

MD

P40

]2

0

30

60

90

120

150

Pass 2Pass 3Pass 4Pass 5Pass 6Pass 7

Separation Distance, h (m)

0 20 40 60 80Sem

iva

riog

ram

, (

h)

[CM

V]2

0

20

40

60

80

Pass 2Pass 3Pass 4Pass 5Pass 6Pass 7

Figure 12. Semivariogram, histogram, and box plots (see description of box plots in text) of CCV, MDP40, and CMV measurements - TB1 granular base material

Page 32: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

19

Table 4. Summary of univariate and spatial statistics – TB1 granular base material

Pass Univariate Statistics Spatial Statistics

MV n COV (%) Nugget Sill1 Range1 Sill2 Range2

1 CCV 19211 6.1 2.9 47 1 6 16 —

2 MDP40 2550 105.7 8.6 8 38 82 40 130 130

2 CMV 2550 4.9 2.2 45 3 5 12 —

3 MDP40 2568 99.2 6.0 6 14 31 13 44 70

3 CMV 2568 5.6 2.4 43 4 6 15 —

4 MDP40 2499 96.0 5.5 6 8 27 13 31 48

4 CMV 2499 6.0 2.5 41 4 7 11 —

5 MDP40 2247 96.0 5.1 5 5 22 9 25 48

5 CMV 2247 6.3 2.6 41 4 7 11 —

6 MDP40 2275 96.3 4.7 5 5 20 10 22 48

6 CMV 2275 6.1 2.4 39 4 4 11 —

7 MDP40 2241 98.3 5.4 6 10 27 10 —

7 CMV 2241 6.8 2.8 41 5 8 14 —

2 d (kN/m3) 6 16.74 0.44 3

Not enough measurements

2 RC (%) 6 92.9 0.02 3

2 w (%) 6 8.5 1.5 18

2 ELWD-Z3 (MPa)

6 85 5 6

2 EV1 (MPa) 6 88 32 37

2 EV2 (MPa) 6 251 116 47

2 EFWD-D3 (MPa)

6 243 60 25

2 CBR200 (%) 6 46 7 16

Note: CCV obtained at a = 0.30 mm, f = 55 Hz, and v = 4 km/h nominal settings; MDP40 and CMV obtained at a = 0.90 mm, f = 30 Hz, and v = 4 km/h nominal settings.

Page 33: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

20

d (kN/m3)

14 15 16 17 18 19 20

CC

V

0

5

10

15

20

25ELWD-Z3 (MPa)

0 50 100 150 200

CC

V

0

5

10

15

20

25

EV1 and EV2 (MPa)

0 200 400 600 800

CC

V

0

5

10

15

20

25

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

CC

V

0

5

10

15

20

25

w (%)

0 5 10 15 20

CC

V

0

5

10

15

20

25

CBR300 (%)

0 50 100 150 200

CC

V

0

5

10

15

20

25

R2 = 0.04n = 6

EV1: R2 = 0.02

EV2: R2 = 0.00

n = 6

CCV = 0.01 EFWD-D3 + 4.5

R2 = 0.24n = 6

R2 = 0.03n = 6

R2 = 0.01n = 26

CCV = 0.04 CBR + 3.9R2 = 0.19n = 6

Figure 13. Regression analyses between CCV and in-situ point measurements - TB1 granular base material

Summary of Results

The test bed consisted of previously compacted granular base material (untreated) Measurements from TB1 involved obtaining IC-MV maps using Sakai and Caterpillar IC rollers,

Page 34: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

21

and in-situ point-MVs (ELWD-Z3, EV1, EV2, EFWD-D3, w, d, and CBR300,) at six randomly selected locations over a plan area of about 8 m x 215 m. Data analysis for this test bed comprised of geostatistical analysis of the spatially referenced IC-MV data and regression analysis between IC-MVs and in-situ point-MVs by spatially pairing the nearest point data. Following is a summary of key findings from these analyses:

The MDP40 semivariograms showed a nested spatial structure with short-range and long-range components, while the CMV and CCV semivariograms did not. The reason for long-range structure is linked to possible spatial variation in the underlying support conditions while the short-range spatial structure is likely a result of soil properties close to the surface.

The MDP40 semivariogram showed decreasing spatial non-uniformity with increasing pass. CMV semivariograms did not exhibit a significant change in the sill values with increasing passes.

On average, MDP40 decreased (from 105.7 to 98.3) while CMV increased slightly (from 4.9 to 6.8) from pass 1 to 6. MDP40 values decreased due to material loosening at the surface from padfoot indentations.

Regression analysis results between CCV IC-MVs and in-situ point-MVs showed weak correlations with R2 values < 0.24, but the measurements were obtained only over a narrow range.

TB2 Treated Granular Base Material (5-day cure)

Test Bed Conditions, IC-MV Mapping, and Point-MV Testing

The test bed was located adjacent to TB1 and consisted of a 5-day cured 150 mm thick (nominal thickness) cement treated granular base layer (Figure 14). The test bed surface was coated with an asphalt binder to help retain moisture content in the treated base layer. The area was mapped in four roller lanes with the Sakai IC roller. CCV IC-MVs were obtained from the roller using a = 0.30 mm, f = 50 Hz, and v = 5 km/h nominal settings. Following the mapping pass, in-situ point-MVs (LWD, FWD, NG, PLT, and DCP) were performed at 17 to 20 test locations selected based on the IC-MV map over a wide range of CCV measurement values (CCV range = 4 to 25).

Page 35: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

22

Figure 14. Picture of the test bed – TB2 treated base material

Test Results and Analysis

CCV map with DCP-CBR profiles at three selected locations are presented in Figure 15. In-situ point measurements (ELWD-Z3, EV1, EV2, EFWD-D3, RC, and w) at the DCP test locations are also provided in Figure 15. Figure 16 shows histogram and semivariogram plots of CCV IC-MV data. A summary of the univariate statistics of IC-MV and in-situ point-MV data are presented in Table 5. As expected, the results indicate that the CCV IC-MVs and modulus/CBR point-MVs on the treated base layer (TB2) are greater than on the untreated base layer (TB1). The average CCV on TB2 is about 2.1 times greater than on TB1. The average ELWD-Z3, EV1, EV2, EFWD-D3, and CBR point-MVs are about 1.3, 2.6, 1.7, 1.8, and 1.8 times, respectively, greater on TB2 than on TB1. RC is however greater on TB1 (93%) than on TB2 (89%). The CCV semivariogram sill on TB2 (sill = 28) showed greater non-uniformity than on TB1 (sill = 6). Regression analysis results between CCV IC-MVs and in-situ point-MVs are presented in Figure 17. The relationships showed weak correlations with R2 values in the range of 0 to 0.41. However, positive trends are evident in CCV relationships with CBR and modulus point-MVs (i.e., ELWD-Z3, EV1, EV2, and EFWD-D3). No trend is observed in CCV relationships with density point-MVs. The primary reason for weak correlations despite a wide CCV measurement range is attributed to surface cracks observed following the vibratory roller pass (see Figure 18). The vibratory roller mapping pass was performed solely for research purposes, and is not recommended on treated layers as it can potentially break the cementitious bonds and cause a reduction in the strength/stiffness properties. Further, for such conditions it is recommended that the point MVs be performed before rolling.

Page 36: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

23

CCV

Pass 1 h vs Pass 1 EXper NORTH

>202015105

CCVCBR (%)

0 50 100 150 200 250 300D

ep

th (

mm

)

0

200

400

600

800

CBR (%)

0 50 100 150 200 250 300

De

pth

(m

m)

0

200

400

600

800

CBR (%)

0 50 100 150 200 250 300

De

pth

(m

m)

0

200

400

600

800

Pt. (6)CCV = 22.3ELWD-Z3 = 142 MPa

EV1 = 598 MPa

EV2 = 550 MPa

EFWD-D3 = 608 MPa

RC = 90.2%w = 10.5%

Pt. (14)CCV = 4.7ELWD-Z3 = 76 MPa

EV1 = 111 MPa

EV2 = 309 MPa

EFWD-D3 = 409 MPa

RC = 89.2%w = 7.8%

Pt. (17)CCV = 8.5ELWD-Z3 = 142 MPa

EV1 = 334 MPa

EV2 = 467 MPa

EFWD-D3 = 407 MPa

RC = 89.7%w = 8.5%

Figure 15. CCV map and CBR profiles at three select locations with low, medium, and high CCV values – TB2 treated base material (a = 0.30 mm, f = 55 Hz, v = 4 km/h nominal

settings)

CCV

0 5 10 15 20 25 30 35 40

Fre

quen

cy

0

5000

10000

15000

20000

Separation Distance, h (m)

0 30 60 90 120 150

Sem

ivar

iogr

am, (

h) [

CC

V]2

0

10

20

30

40

50

Nugget = 20Sill = 28Range = 11

= 12.7 = 5.5COV = 44%

Figure 16. Histogram (left) and semivariogram (right) of CCV measurements – TB2 treated base material

Page 37: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

24

Table 5. Summary of univariate statistics – TB2 treated base material

Pass MV n COV (%)

1 CCV 37927 12.7 5.5 44

1 d (kN/m3) 20 16.77 0.32 2

1 RC (%) 20 88.6 0.02 2

1 w (%) 20 8.5 1.2 15

1 ELWD-Z3 (MPa) 20 111 34 31

1 EV1 (MPa) 17 227 116 51

1 EV2 (MPa) 17 420 151 36

1 EFWD-D3 (MPa) 21 433 115 26

1 CBR (%) 20 85 33 39

Page 38: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

25

d (kN/m3)

14 15 16 17 18 19 20

CC

V

0

5

10

15

20

25ELWD-Z3 (MPa)

0 50 100 150 200

CC

V

0

5

10

15

20

25

EV1 and EV2 (MPa)

0 200 400 600 800

CC

V

0

5

10

15

20

25

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

CC

V

0

5

10

15

20

25

w (%)

0 5 10 15 20

CC

V

0

5

10

15

20

25

CBR (%)

0 50 100 150 200

CC

V

0

5

10

15

20

25

CCV = 0.10 ELWD-Z3 - 0.2

R2 = 0.37n = 18

CCV = 0.02 EV1 + 5.5

R2 = 0.36n = 17

CCV = 0.03 EFWD-D3

R2 = 0.41n = 21

R2 = 0.02n = 20

CCV = 0.01 EV2 + 5.9; R2 = 0.15

CCV = 1.06 w + 1.5R2 = 0.11n = 20

CCV = 0.07 CBR + 4.3R2 = 0.32n = 20

Figure 17. Regression analyses between CCV and in-situ point measurements – TB2 treated base material (5 day cure)

Page 39: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

26

Figure 18. Cracks observed on the treated base material following the Sakai vibratory roller pass – TB2

Summary

The test bed consisted of a 5-day cured 150 mm thick cement-treated base layer. Measurements from TB2 involved IC-MV mapping using Sakai IC roller and obtaining in-situ point-MVs (ELWD-Z3, EV1, EV2, EFWD-D3, w, d, and CBR) at 17 to 20 test locations selected based on the IC-MV map. Data analysis for this test bed comprised of geostatistical analysis of the spatially referenced IC-MV data and regression analysis between IC-MVs and in-situ point-MVs by spatially pairing the nearest point data. Following is a summary of key findings from these analyses:

As expected, the CCV IC-MVs and modulus/CBR point-MVs on treated base layer (TB2) are greater than on the untreated base layer (TB1). The average CCV, ELWD-Z3, EV1, EV2, EFWD-D3, and CBR on TB2 are about 2.1, 1.3, 2.6, 1.7, 1.8, and 1.8 times, respectively, greater on TB2 than on TB1. RC is however greater on TB1 (93%) than on TB2 (89%).

The CCV semivariogram sill on TB2 (sill = 28) showed greater non-uniformity than on TB1 (sill = 6).

Regression analysis between CCV IC-MVs and in-situ point-MVs showed weak correlations with R2 values in the range of 0to 0.41. However, CCV relationships with CBR and modulus point-MVs (i.e., ELWD-Z3, EV1, EV2, and EFWD-D3) showed positive trends, while CCV relationship with density point-MVs did not. Cracks observed on the treated surface following vibratory rolling likely contributed to weak correlations.

TBs 3/8 Treated Base Material

Test Bed Construction

The test bed involved cement treatment of the TB1 granular base material with approximately 5.5% (of dry weight of soil) of cement. Photographs taken during the construction process are provided in Figure 19 to Figure 21. The construction sequence and time log from field observations are as follows:

Page 40: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

27

a) scarified the base layer to about 150 mm depth and moisture-conditioning the base

material to at target w = 10% [prior to 6:30 am], b) spreaded stabilizer on the test bed [6:45 to 7:45 am], c) preparing the soil-cement mixture using a rotary mixer (with two passes) [7:45 to 8:30

am], d) compacted the area using a padfoot roller for one static pass and moisture-conditioning

the soil-cement mixture with a water truck [8:30 to 9:15 am] (in-situ sample was obtained for laboratory Proctor test at 8:50 am),

e) compacted the area using padfoot roller for five to six passes [9:20 to 10:15 am], f) compacted the area using vibratory smooth drum roller for two to four passes [10:00 to

10:45 am], g) trimming the area to the desired elevation using a motor grader [10:30 to 11:00 am], h) performed final compaction passes using a pneumatic rubber tire roller [10:45 to 11:55

am]. i) obtained IC-MV map using the Case/Ammann IC roller (one pass) [11:55 am to 12:40

pm] j) obtained in-situ point-MVs (LWD, FWD, NG, PLT, and DCP) on the final compacted

surface [12:24 to 1:20 pm] The test bed was divided in to a 69 m long section (Section A) and a 130 m long section (Section B) (Figure 19). Section A was compacted using the Caterpillar padfoot IC roller using a = 0.90 mm, f = 30 Hz, and v = 4 km/h nominal settings, and the Case/Ammann smooth drum roller for using Ecc. = 15%, f = 27 Hz, and v = 4.2 km/h nominal settings, by the ISU research team. Roller measurements were continuously recorded during the Caterpillar IC roller passes. Case/Ammann smooth drum roller passes were not recorded due to data recording problems. All compaction operations on Section B were performed by the contractor. The area was compacted using a padfoot roller (in static mode) and a vibratory smooth drum roller. IC-MV roller map (on Sections A and B) was obtained using the Case/Ammann smooth drum IC roller using Ecc. = 15%, f = 27 Hz, and v = 4.2 km/h nominal settings. Two days after treatment, the area was again mapped (referred to as TB8) using the Case/Ammann smooth drum IC roller in manual and AFC mode settings. For manual mode, the nominal settings used during mapping were Ecc. = 10%, f = 27Hz, and v = 4.2 km/h. For AFC mode, a low performance level with nominal v = 4.2 km/h was used for mapping. FWD point-MVs were obtained prior to mapping operations while other Point MVs (LWD, NG, PLT, and DCP) were obtained after the mapping operations. Tests were performed at 25 locations selected using the ks IC-MV map.

Page 41: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

28

Area compacted by Contractor(~ 130 m long section; Section B)

Area compacted by ISU research teamand Contractor (~69 m long section; Section A)

Figure 19. TB3 treated base material compacted by ISU research team (section A) and contractor (section B)

Page 42: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

29

Scarified and moisture‐conditioned subbase Placement of cement stabilizer on subbase

Soil‐cement mixing process using puliverzier Moisture‐conditioning the soil‐cement mixture

Compaction using Caterpillar padfoot IC roller Moisture‐conditioning after first pass

Figure 20. Pictures showing construction process on TB3 treated base

Page 43: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

30

Compaction using Caterpillar padfoot roller

Final compaction passes using Caterpillar pneumatic tire roller

Compaction using Sakai smooth drum roller

Fine grading using motor grader

Figure 21. Pictures showing construction process on TB3 treated base

Test Results and Analysis

MDP40 and CMV IC-MV maps from compaction roller passes are presented in Figure 22. Box plots showing the range of data for each compaction pass is presented in Figure 23. Results indicate that on average MDP40 increased from about 112.4 to 115.3 from pass 1 to 5. No significant change in CMV was observed from pass 1 to 5 (average CMV = 6.2 to 6.8). In-situ density measurements taken during compaction at various times after mixing are plotted in comparison with laboratory density relationship with time delay in Figure 24. Results indicate that on average the density measurements increased with increasing compaction effort but did not achieve the 95% RC required by the specifications. ks IC-MV, a*, and f maps from TB3 (in manual mode) and TB8 (in manual and AFC modes) are presented in Figure 25. Histogram plots of ks IC-MVs and in-situ point-MVs on TB3 and TB8 showing comparison between measurements obtained shortly after compaction and after 2-day cure are presented in Figure 26. Same results are presented as box plots in Figure 27. A summary of univariate statistics of ks IC-MVs and in-situ point-MVs from TB3 and TB8 is provided in Table 6. Results indicate that on average the ks IC-MV, ELWD-Z3, EFWD-D3, EV1, EV2, and CBR

Page 44: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

31

measurement values increased by about 33%, 15%, 75%, 49%, 66%, and 320% after 2-day curing. Moisture content of the material decreased on average from about 10.5% to 7.1%. As a result of this decrease in moisture content, the average RC of the material increased slightly from about 91 to 92%. Semivariograms of ks IC-MVs obtained from TB3 in manual mode, and TB8 in manual and AFC modes are presented in Figure 28. Semivariogram plots for ks IC-MVs indicate greater non-uniformity in ks IC-MVs after two days of curing (TB8) compared to shortly after compaction (TB3). This is an important finding to note and has not been well documented in the literature. This increasing non-uniformity is attributed to various factors such as non-uniform application of cement, water content, mixing, compaction delay time, and compaction energy across the test bed area. Modulus (ELWD-Z3, EV1, EV2, EFWD-D3) and CBR point-MVs also indicated greater non-uniformity with higher COV values on TB8 compared to on TB3 (see Table 6). RC and density measurements did not show significant differences in COV between TB8 and TB3. Correlations between ks IC-MVs obtained in manual mode and in-situ point-MVs from TB3 and TB8 are presented in Figure 29 and Figure 30, respectively. Regressions on TB3 showed weak correlations with R2 < 0.13 due to narrow range of measurements. ks results on TB3 showed influence of moisture content with R2 = 0.37. Regressions on TB8 between ks IC-MVs and EFWD-

D3 showed good correlations with R2 = 0.53, while regressions with other point-MVs produced relatively weak correlations (R2 < 0.41). Note that the EFWD-D3 measurements were obtained prior to roller mapping passes, while all other point-MVs were obtained after mapping passes. Similar to observations on TB2, surface cracks were observed on TB8 following vibratory roller passes which likely affected the point MVs and therefore the correlations. Figure 28 compares ks IC-MV, a*, and f maps obtained in manual and AFC modes on TB8. The ks measurements varied from 30 to 90 MN/m and the a* measurements varied from 0.3 to 1.0 mm. The f measurements remained relatively constant at about 29 Hz. Analysis of ks and a* results indicated that the drum vibration amplitude was reduced with increase in ks. Comparison between ks and a* for different response distances (i.e., 0, 1, 2, and 3 m) indicated that the response distance for altering the amplitude was in the range of 1 to 2 m (for variation in v = 4.1 to 4.5 km/h) (note that the roller data was reported approximately every 1 m).

Page 45: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

32

69 m

MDP40

Pass 1MDP40

Pass 2

MDP40

Pass 3MDP40

Pass 4MDP40

Pass 5

CMVPass 1

CMVPass 2

CMVPass 3

CMVPass 4

CMVPass 5

Elevation

Pass Count

MDP40

>140140130120110100<100

CMV

>2020151052<2

Pass

87654321

Elev. (m)

>78.7978.7978.6478.4978.3378.1878.03<78.03

69 m

North

Figure 22. MDP40 and CMV maps for passes 1 to 5, and elevation and number of roller passes maps – TB3 (section A) treated base material (a = 0.90 mm, f = 30 Hz, and v = 4

km/h nominal settings)

Page 46: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

33

Pass Number

0 1 2 3 4 5 6

MD

P40

50

75

100

125

150

Pass Number

0 1 2 3 4 5 6

CM

V

0

5

10

15

20

25

Figure 23. Box plots of MDP40 and CMV measurements – TB3 treated base material (a = 0.90 mm, f = 30 Hz, and v = 4 km/h nominal settings)

Time (minutes) [Wait time after mixing]

0 50 100 150 200 250 300

Dry

Uni

t W

eigh

t (k

N/m

3)

16

17

18

19

20

Dry

Un

it W

eigh

t (p

cf)

110

115

120

125

130Laboratory Sample; w = 10.0%In-Situ Sample; w = 11.4%In-Situ Test Measurements

Approximate wait time after pulverizer pass

After final compactionpass; Average w = 10.1%n = 30

After 2 padfootroller passes;Average w = 10.9%n = 5

After 5 padfootroller passes;Average w = 9.7%n = 9

95% RC

Figure 24. In-situ density test measurements during compaction in comparison with laboratory density measurements – TB3 treated base material

Page 47: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

34

ks

Amp. (mm)

Freq. (Hz)

Amp. Freq.

Manual Mode - TB3Shortly after stabilization

ks Amp. Freq.

Manual Mode - TB8After 2-day cure

ks (MN/m)

201

m

213

m

ks Amp. Freq.

AFC Mode - TB8After 2-day cure

North

Figure 25. Comparison of ks, a*, and f maps obtained shortly after compaction (TB3) and after 2-day cure in manual and AFC modes (TB8)

Page 48: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

35

ks (MN/m)

0 20 40 60 80 100

Fre

quen

cy

0

200

400

600

800

1000 TB3 Manual TB8 ManualTB8 AFC

Vibration Amplitude (mm)

0.0 0.5 1.0 1.5 2.0 2.5 3.00

200

400

600

800

1000 TB3 Manual TB8 ManualTB8 AFC

Vibration Frequency (Hz)

22 24 26 28 30 32 340

200

400

600

800

1000 TB3 Manual TB8 ManualTB8 AFC

Dry Unit Weight (kN/m3)

15 16 17 18 19 20

Fre

quen

cy

0

2

4

6

8

10TB3TB8

Moisture Content (%)

5 10 15 200

5

10

15

20

TB3TB8

CBR (%)

0 50 100 150 2000

5

10

15

20

TB3TB8

ELWD-Z3 (MPa)

0 50 100 150 200

Fre

que

ncy

0

5

10

15

20

TB3TB8

EFWD-D3 (MPa)

0 200 400 600 8000

5

10

15

20

TB3TB8

EV1 (MPa)

0 200 400 600 8000

2

4

6

8

TB3TB8

EV2 (MPa)

0 200 400 600 800 1000

Fre

quen

cy

0

2

4

6

8

TB3TB8

Figure 26. Histogram plots comparing measurements obtained shortly after compaction (TB3) and after 2-days curing (TB8)

Page 49: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

36

k s (M

N/m

)

20

40

60

80

100

TB3 Manual

TB8 Manual

TB8 AFC

Vib

ratio

n A

mp

litu

de

(mm

)

0.0

0.5

1.0

1.5

2.0

2.5

3.0

TB3 Manual

TB8 Manual TB8

AFC

Vib

ratio

n F

requ

ency

(H

z)

22

24

26

28

30

32

34

TB3 Manual

TB8 Manual

TB8 AFC

Dry

Uni

t W

eigh

t (k

N/m

3)

15

16

17

18

19

20

TB3

TB8M

oist

ure

Con

tent

(%

)

0

5

10

15

20

TB3

TB8

CB

R (

%)

0

40

80

120

160

200

TB3

TB8

ELW

D-Z

3 (M

Pa)

0

40

80

120

160

200

TB3

TB8

EF

WD

-D3 (

MP

a)

0

200

400

600

800

EV

1 (

MP

a)

0

200

400

600

800

EV

2 (M

Pa)

0

200

400

600

800

1000

TB3

TB8

TB3

TB8

Figure 27. Box plots comparing measurements obtained shortly after compaction (TB3) and after 2-days curing (TB8)

Page 50: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

37

Table 6. Summary of univariate statistics – TBs 3/8 treated base material

TB Univariate Statistics

MV n COV (%)

TB3

ks (MN/m) 890 42 6 14

a* (mm) 890 1.19 0.16 13

f (Hz) 890 26 2 8

d (kN/m3) 20 17.23 0.33 2

RC (%) 20 91.1 1.7 2

w (%) 20 10.5 2.1 20

ELWD-Z3 (MPa) 19 90 15 16

EV1 (MPa) 7 109 26 24

EV2 (MPa) 7 284 54 19

EFWD-D3 (MPa) 20 267 40 15

CBR (%) 20 21 5 25

TB8

ks (MN/m) [manual] 704 56 8 15

a* (mm) [manual] 704 0.79 0.11 13

f (Hz) [manual] 704 29 1 3

ks (MN/m) [AFC] 720 64 13 20

a* (mm) [AFC] 720 0.56 0.14 25

f (Hz) [AFC] 720 29 1 3

d (kN/m3) 25 17.39 0.46 3

RC (%) 25 91.9 2.4 3

w (%) 25 7.1 1.1 16

ELWD-Z3 (MPa) 25 104 33 32

EV1 (MPa) 30 191 99 52

EV2 (MPa) 30 422 157 37

EFWD-D3 (MPa) 30 443 116 26

CBR (%) 12 88 43 50

Note: Nominal v = 4.2 km/h during roller operation

Page 51: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

38

Separation Distance, h (m)

0 10 20 30 40 50 60 70

Sem

ivar

iogr

am, (

h)

[MN

/m]2

0

30

60

90

120

150

TB3 ManualTB8 ManualTB8 AFC

TB8 AFC:Nugget = 40Sill = 130Range = 12

TB8 Manual:Nugget = 20Sill = 60Range = 12

TB3 Manual:Nugget = 20Sill = 30Range = 8

Figure 28. Semivariograms of ks measurements obtained on TB3 in manual mode, TB8 in manual mode, and TB8 in AFC mode

Page 52: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

39

d (kN/m3)

14 15 16 17 18 19 20

k s (M

N/m

)

0

20

40

60

80

100ELWD-Z3 (MPa)

0 50 100 150 200

k s (M

N/m

)

0

20

40

60

80

100

EV1 and EV2 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

w (%)

0 5 10 15 20

k s (M

N/m

)

0

20

40

60

80

100

CBR (%)

0 50 100 150 200

k s (M

N/m

)

0

20

40

60

80

100

R2 = 0.02n = 28

EV1: R2 = 0.03

n = 7

R2 = 0.00n = 29

EV2: R2 = 0.09

n = 7

ks = 1.28 w + 29.1

R2 = 0.37n = 30

R2 = 0.05n = 30

ks = 3.34 d - 14.7

R2 = 0.13n = 30

Figure 29. Regression analyses between ks and in-situ point measurements – TB3 treated base material (shortly after compaction; manual mode)

Page 53: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

40

d (kN/m3)

14 15 16 17 18 19 20

k s (M

N/m

)

0

20

40

60

80

100ELWD-Z3 (MPa)

0 50 100 150 200

k s (M

N/m

)

0

20

40

60

80

100

EV1 and EV2 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

w (%)

0 5 10 15 20

k s (M

N/m

)

0

20

40

60

80

100

CBR (%)

0 50 100 150 200

k s (M

N/m

)

0

20

40

60

80

100

R2 = 0.00n = 25

ks = 0.07 EV1 + 43.3; R2 = 0.41

n = 30

ks = 0.06 EFWD-D3 + 31.7

R2 = 0.53n = 30

ks = 0.03 EV2 + 41.9; R2 = 0.37

n = 30

R2 = 0.10n = 25

ks = 0.08 CBR + 50.8

R2 = 0.21n = 30

R2 = 0.00n = 25

Tests performed after roller mapping

Tests performed beforeroller mapping

Tests performed afterroller mapping

Tests performed afterroller mapping

Tests performed afterroller mapping

Tests performed beforeroller mapping

Figure 30. Regression analyses between ks and in-situ point measurements – TB8 treated base material (after 2-day cure; manual mode)

Page 54: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

41

Summary

TB3 consisted of construction of a 150 mm thick cement-treated base layer, obtaining MDP40 IC-MVs during compaction, ks IC-MVs along with in-situ point-MVs (ELWD-Z3, EV1, EV2, EFWD-D3, w, d, and CBR) shortly after treatment. TB8 involved obtaining ks IC-MVs after 2 days of curing along with in-situ point-MVs (ELWD-Z3, EV1, EV2, EFWD-D3, w, d, and CBR). Data analysis for TBs 3 and 8 comprised of geostatistical analysis of the spatially referenced ks IC-MV data and regression analysis between IC-MVs and in-situ point-MVs by spatially pairing the nearest point data. Following is a summary of key findings from these analyses:

During initial compaction on TB3 using Caterpillar padfoot IC roller, the average MDP40 increased from about 112.4 to 115.3, while no significant change in CMV was observed (average CMV = 6.2 to 6.8) from pass 1 to 5.

As expected, the ks IC-MVs and modulus/CBR point-MVs improved after 2 days of curing. Results indicated that on average the ks IC-MV, ELWD-Z3, EFWD-D3, EV1, EV2, and CBR measurement values increased by about 33%, 15%, 75%, 49%, 66%, and 320% after 2 days of curing. Moisture content of the material decreased on average from about 10.5% to 7.1%. As a result of decrease in the moisture content, the average RC of the material increased slightly from about 91 to 92%.

ks IC-MVs and in-situ point-MVs showed greater non-uniformity on TB8 than on TB3. This is an important finding to note and has not been well documented in the literature. The reasons for this increased non-uniformity after curing is attributed to non-uniform application of cement, water, mixing, compaction delay time, and compaction energy across the test bed area. RC and density measurements did not show significant differences in terms of variability between TB8 and TB3.

Regressions on TB3 between ks IC-MVs and in-situ point-MVs on TB3 showed weak correlations with R2 < 0.13 due to narrow range of measurements. ks IC-MV results on TB3 showed influence of moisture content with R2 = 0.37.

Regressions on TB8 between ks IC-MVs and EFWD-D3 showed good correlations with R2 = 0.53, while regressions with other point-MVs produced relatively weak correlations (R2 < 0.41). The reason for better correlations with EFWD-D3 measurements is that the measurements were obtained prior to roller mapping passes, while all other point-MVs were obtained after mapping passes. Similar to observations on TB2, surface cracks were observed on TB8 following vibratory roller passes.

AFC operations on TB8 indicated that the vibration amplitude was reduced with increase in ks measurement values and the response distance for altering the amplitude was in the range of 1 to 2 m (for variation in v = 4.1 to 4. 5 km/h)

TB4 Granular Subgrade Material (Untreated)

Test bed conditions, IC-MV mapping, and Point-MV testing

The test bed consisted of a 530 m long section of existing compacted granular subgrade layer (untreated) (Figure 31). The area was mapped using Sakai smooth dual drum, Case/Ammann smooth drum, and Caterpillar padfoot IC rollers. Nominal machine settings used for mapping were as follows:

Page 55: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

42

Sakai: a = 0.60 mm, f = 50 Hz, v = 5 km/h Case/Ammann: Ecc. = 15%, f = 27Hz, v = 4.2 km/h Caterpillar: a = 0.90 mm, f = 30 Hz, v = 4 km/h

Following Sakai and Case/Ammann IC roller mapping passes, in-situ point-MVs (LWD, NG, PLT, and DCP) were performed at 39 test locations selected based on the IC-MV maps. Caterpillar padfoot IC roller mapping pass was performed following the in-situ point-MV testing.

Figure 31. TB4 compacted granular subgrade material

Test Results, Analysis, and Summary

IC-MV maps and DCP-CBR profiles at three selected locations are presented in Figure 32. Histogram plots of MDP40, CMV, ks, and CCV IC-MVs and corresponding semivariograms are presented in Figure 33. A summary of univariate and spatial statistics o f IC-MVs are provided in Table 7 and Table 8, respectively. A summary of univariate statistics of in-situ point-MVs are provided in Table 7. Correlations between IC-MVs and in-situ point-MVs are provided Figure 34 to Figure 37. Following are some key observations: MDP40 measurements:

On average, the MDP40 measurements on this test bed are about 1.4 times greater than on TB1 untreated granular base layer.

MDP40 semivariograms indicate comparatively lower non-uniformity on this test bed (sill = 35) compared to on TB1untreated granular base (sill1 = 82 and sill 2 = 130 for pass 1).

Non-linear exponential relationships are observed in correlations between MDP40 and ELWD-Z3, EV1, EV2, and CBR point-MVs. R2 values for these relationships varied from 0.48 to 0.73. MDP40 values tend to reach an asymptotic value of 150, which is set as the maximum value in the AccuGrade software. Linear regression relationship is observed

Page 56: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

43

between MDP40 and d with relatively low R2 value (0.32). No influence of w is observed in the relationships. It appears that the MDP measurement was not set to provide an adequate measurement range relative to the measurement range of plate load test modulus values.

CCV measurements:

On average, the CCV measurements on this test bed are about 1.5 times greater than on TB1 untreated granular base layer.

CCV semivariograms indicate comparatively higher non-uniformity on this test bed (sill = 20) compared to on TB1untreated granular base (sill = 6).

Linear regression relationships with right trends are observed in correlations between CCV and ELWD-Z3, EV1, EV2, and CBR point-MVs. Relationship with EV1 showed R2 = 0.66, while relationship with ELWD-Z3, EV2, and CBR showed R2 values in the range of 0.21 to 0.31. No trend is observed in relationship with d. No influence of w is observed in the relationships.

CMV measurements:

On average, the CMV measurements on this test bed are about 3.6 times greater than on TB1 untreated granular base layer.

CMV semivariograms indicate comparatively greater non-uniformity on this test bed (sill = 50) compared to on TB1untreated granular base (sill = 5). This finding is similar to that of CCV semivariogram.

Linear regression relationships are observed in correlations between CMV and ELWD-Z3, EV1, EV2, d, and CBR point-MVs. Relationships with EV1 and CBR showed R2 > 0.50, while relationship with other point-MVs showed R2 < 0.20. No influence of w is observed in the relationships.

ks measurements:

Linear regression relationships are observed in correlations between ks and ELWD-Z3, EV1, EV2, d, and CBR point-MVs. Relationships with EV1and ELWD-Z3 showed R2 = 0.61 and 0.40, respectively, while relationship with other point-MVs showed R2 < 0.30. No influence of w is observed in the relationships.

Page 57: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

44

529

m

MDP40

>140140130120110100<100

CMV

>2020151052<2

MDP40CMV

530

m

ks (MN/m)

Amp. (mm)

ks (MN/m)Amp. (mm)

>202015105

CCV

530

m

NORTH

In-SituTest

Locations

CBR (%)

0 20 40 60 80 100 120

De

pth

(mm

)

0

200

400

600

800

MDP40 = 143.4

CMV = 24.0ks = 56.6 MN/m

CCV = 16.5ELWD-Z3 = 148 MPa

EV1 = 165 MPa

EV2 = 342 MPa

RC = 98.2%w = 9.0%

CBR (%)

0 20 40 60 80 100 120

Dep

th (

mm

)

0

200

400

600

800

MDP40 = 115.7

CMV = 2.0ks = 31.3 MN/m

CCV = 4.6ELWD-Z3 = 45 MPa

EV1 = 31 MPa

EV2 = 120 MPa

RC = 81.7%w = 6.2%

CBR (%)

0 20 40 60 80 100 120

Dep

th (

mm

)

0

200

400

600

800

MDP40 = 137.4

CMV = 9.0ks = 37.1 MN/m

CCV = 7.9ELWD-Z3 = 76 MPa

EV1 = 75 MPa

EV2 = 165 MPa

RC = 93.0%w = 10.9%

Figure 32. CMV, MDP40, ks (and a*), and CCV maps on TB4 compacted granular subgrade material along with DCP-CBR profiles at three selected locations

Page 58: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

45

ks (MN/m)

0 20 40 60 80 100

Fre

que

ncy

0

300

600

900

1200

1500

MDP40

80 100 120 140 160

Fre

quen

cy

0

2000

4000

6000

8000

CMV

0 10 20 30 40 50 60

Fre

que

ncy

0

500

1000

1500

2000

2500

Separation Distance, h (m)

0 50 100 150 200Sem

iva

riog

ram

, (

h) [

MD

P40

]2

0

30

60

90

120

150

Separation Distance, h (m)

0 50 100 150 200Se

miv

ario

gra

m, (

h) [

CM

V]2

0

20

40

60

80

Separation Distance, h (m)

0 50 100 150 200Se

miv

ario

gra

m, (

h)

[MN

/m]2

0

30

60

90

120

150

CCV

0 5 10 15 20 25 30 35 40

Fre

quen

cy

0

10000

20000

30000

40000

Separation Distance, h (m)

0 50 100 150 200Sem

iva

riog

ram

, (

h) [

CC

V]2

0

10

20

30

40

50

Figure 33. Histogram and semivariogram plots of CMV, MDP40, ks and CCV measurements – TB4 compacted granular subgrade material

Page 59: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

46

Table 7. Summary of univariate statistics – TB4 granular subgrade material

MV n COV (%)

CMV 8125 18.2 7.0 39

MDP40 8125 144.8 5.8 4

ks (MN/m) 2366 46.2 6.2 13

CCV 59405 9.0 4.4 49

d (kN/m3) 39 17.69 0.73 4

RC (%) 39 92.9 3.8 4

w (%) 39 9.1 1.8 20

ELWD-Z3 (MPa) 35 103 36 34

EV1 (MPa) 36 121 49 41

EV2 (MPa) 36 305 162 53

CBR200 (%) 39 66 42 63

Table 8. Summary of spatial statistics – TB4 granular subgrade material

MV Nugget Sill Range

CMV 25 50 45

MDP40 17 35 40

ks 16 38 40

CCV 14 20 40

Page 60: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

47

d (kN/m3)

14 15 16 17 18 19 20

k s (M

N/m

)

0

20

40

60

80

100ELWD-Z3 (MPa)

0 50 100 150 200

k s (M

N/m

)

0

20

40

60

80

100

EV1 and EV2 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

w (%)

0 5 10 15 20

k s (M

N/m

)

0

20

40

60

80

100

CBR300 (%)

0 50 100 150 200

k s (M

N/m

)

0

20

40

60

80

100

ks = 0.11 ELWD-Z3+35.7

R2 = 0.40n = 33

ks = 0.09 EV1 + 35.5; R2 = 0.61

n = 34

No Data

ks = 0.02 EV2 + 39.4; R2 = 0.27

n = 34

R2 = 0.00n = 36

R2 = 0.10n = 35

R2 = 0.10n = 36

Figure 34. Regression analyses between ks and in-situ point measurements – TB4 granular subgrade material

Page 61: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

48

d (kN/m3)

14 15 16 17 18 19 20

CC

V

0

5

10

15

20

25ELWD-Z3 (MPa)

0 50 100 150 200

CC

V

0

5

10

15

20

25

EV1 and EV2 (MPa)

0 200 400 600 800

CC

V

0

5

10

15

20

25

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

CC

V

0

5

10

15

20

25

w (%)

0 5 10 15 20

CC

V

0

5

10

15

20

25

CBR300 (%)

0 50 100 150 200

CC

V

0

5

10

15

20

25

CCV = 0.04 ELWD-Z3 + 5.2

R2 = 0.31n = 32

CCV = 0.04 EV1 + 4.8

R2 = 0.66n = 34

No Data

R2 = 0.10n = 35

CCV = 0.01 EV2 + 6.7; R2 = 0.24

R2 = 0.00n = 35

CCV = 0.03 CBR + 7.7R2 = 0.21n = 35

Figure 35. Regression analyses between CCV and in-situ point measurements – TB4 granular subgrade material

Page 62: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

49

d (kN/m3)

14 15 16 17 18 19 20

MD

P40

80

100

120

140

160ELWD-Z3 (MPa)

0 50 100 150 200

MD

P4

0

80

100

120

140

160

EV1 and EV2 (MPa)

0 200 400 600 800

MD

P4

0

80

100

120

140

160

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

MD

P40

80

100

120

140

160

w (%)

0 5 10 15 20

MD

P4

0

80

100

120

140

160

CBR300 (%)

0 50 100 150 200

MD

P4

0

80

100

120

140

160

No Data

R2 = 0.00n = 35

MDP40 = 147.0 (1-e(-0.05 ELWD-Z3))

R2 = 0.48n = 32

MDP40 = 145.4 (1-e(-0.06 EV1))

R2 = 0.53MDP440 = 146.9 (1-e(-0.02 EV2))

R2 = 0.67

n = 34

MDP40 = 5.64 d + 43.9

R2 = 0.32n = 35

MDP40 = 145.0 (1-e(-0.19 CBR))

R2 = 0.73n = 35

Figure 36. Regression analyses between MDP40 and in-situ point measurements – TB4 granular subgrade material

Page 63: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

50

d (kN/m3)

14 15 16 17 18 19 20

CM

V

0

10

20

30

40

50ELWD-Z3 (MPa)

0 50 100 150 200

CM

V

0

10

20

30

40

50

EV1 and EV2 (MPa)

0 200 400 600 800

CM

V

0

10

20

30

40

50

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

CM

V

0

10

20

30

40

50

w (%)

0 5 10 15 20

CM

V

0

10

20

30

40

50

CBR300 (%)

0 50 100 150 200

CM

V

0

10

20

30

40

50

R2 = 0.10n = 32

CMV = 0.13 EV1 + 1.9; R2 = 0.57

CMV = 0.03 EV2 + 10.1; R2 = 0.16

n = 34

No Data

R2 = 0.12n = 35

R2 = 0.01n = 35

CMV = 0.17 CBR + 6.1R2 = 0.58n = 35

Figure 37. Regression analyses between CMV and in-situ point measurements – TB4 granular subgrade material

Page 64: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

51

TBs 5, 6, and 9 Treated Subgrade Material

Test Bed Construction and IC-MV Mapping

TBs 5 and 6 involved cement treatment of a portion of the TB4 granular subgrade material with 5.5% (of dry weight of soil) of cement. Photographs taken during the construction process are provided in Figure 38 and Figure 39. TB5 was compacted by the ISU research team and the contractor, while TB6 was compacted solely by the contractor. The construction sequence followed in these test beds was similar to that of TB3 construction. Following is the construction sequence with time log from field observations on TB5:

a) scarified the subgrade layer to about 150 mm depth and moisture-conditioning he material to a target w = 10% [prior to 6:30 am],

b) spreaded stabilizer on the scarified test bed [6:45 to 7:45 am], c) prepared the soil-cement mixture using a rotary mixer (with two passes) [7:45 to 8:15

am], d) compacted the area using a padfoot roller for one static pass and moisture-conditioning

the soil-cement mixture with a water truck [8:20 to 8:50 am] (in-situ sample was obtained for laboratory Proctor test at 8:30 am),

e) compacted the area using padfoot roller for 4 to 6 passes [8:55 to 10:15 am], f) compacted the area using vibratory smooth drum roller for 4 passes [10:15 to 10:45 am], g) trimmed the subgrade to desired elevation using motor grader [10:30 to 10:45 am], h) in-situ density testing at 7 random test locations [10:30 to 11:00 am] i) performed final compaction passes using pneumatic rubber tire roller [10:45 to 11:05

am]. j) performed in-situ point-MV testing at 7 random test locations [11:10 to 11:20 am] k) obtained Case/Ammann IC roller map (one pass) [11:10 to 11:40 am] l) performed in-situ point-MV testing (LWD, FWD, NG, PLT, and DCP) on the final

compacted surface from 20 test locations selected based on the IC-MV map [1:15 to 2:25 pm]

On TB5, roller measurements were recorded during Caterpillar padfoot IC roller compaction. Three roller lanes on TB5 were compacted in static mode while the other three lanes were compacted in vibratory mode (low amplitude setting: a = 0.90 mm and f = 30 Hz). Case/Ammann IC-MV roller mapping was obtained using Ecc = 15%, f = 27 Hz, and v = 4.2 km/h nominal settings. Two days after treatment, the area was again mapped (referred to as TB9) using the Case/Ammann IC roller in manual and AFC mode settings. For manual mode, the nominal settings used during mapping were Ecc. = 15%, f = 27Hz, and v = 4.2 km/h. For AFC mode, a high performance level with nominal v = 4.2 km/h was used for mapping. Point MVs (FWD, LWD, NG, PLT, and DCP) were obtained after the mapping operations. Tests were performed at 20 test locations (same locations as TBs 5 and 6).

Page 65: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

52

Placement of cement stabilizer on moisture‐conditioned subgrade

Soil‐cement mixing using rotary mixer

Moisture‐conditioning after first compaction pass with padfoot roller

Compaction using Caterpillar padfoot IC roller

Compaction using Sakai smooth drum roller

Trimming process using motor graderCompaction using Sakai smooth drum roller

Figure 38. Pictures showing construction process on TBs 5/6 treated subgrade

Page 66: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

53

Final compaction using Caterpillar pneumatic rubber tire roller

Compaction using Caterpillar padfoot roller

Final compacted stabilized subgrade – TBs 5/6

Figure 39. Pictures showing construction process and final compacted surface on TBs 5/6 treated subgrade

Test Results and Analysis

MDP40 and CMV IC-MV maps from compaction roller passes are presented in Figure 40. Box plots showing the range of data for each compaction pass is presented in Figure 41. Results indicate that on average MDP40 in static mode increased from about 115.8 to 130.5 while in vibratory low amplitude setting increased from about 111.6 to 122.4, from pass 1 to 5. No significant change in CMV was observed from pass 1 to 5 (average CMV = 4.9 to 5.5). In-situ density measurements taken during compaction at various times after mixing are plotted in comparison with laboratory density relationship with time delay in Figure 42. Results indicate that on average the density measurements generally increased with increasing compaction effort but did not achieve the 95% RC required by the specifications. ks IC-MV, a*, and f maps from TBs 5 and 6 (in manual mode), and TB8 (in manual and AFC modes) are presented in Figure 43. Histogram plots of ks IC-MVs and in-situ point-MVs on TBs 5 and 6, and TB9 showing comparison between measurements obtained shortly after compaction and after 2-day cure are presented in Figure 44. Same results are presented as box plots in Figure 45. A summary of univariate statistics of ks IC-MVs and in-situ point-MVs from TBs 5, 6, and 9

Page 67: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

54

is provided in Table 9. Results indicate that on average the ks IC-MV increased by about 18% after the 2-day curing period. CBR, ELWD-Z3, EFWD-D3, EV1, and EV2 point-MVs showed a small increase or a decrease (-11% to +11%) on TB9 compared to TB5. Moisture content of the material increased on average from about 10.6% to 13.7%, and as a result the average RC of the material decreased slightly from 89 to 87%. Note that all in-situ point-MVs were obtained after roller mapping passes. Similar to observations on TBs 2 and 8, cracks were observed on TB9 following the vibratory roller passes which likely lowered the strength/stiffness at the surface of the treated subgrade layer. Semivariograms of ks IC-MVs obtained from TBs 5 and 6 in manual mode and from TB9 in manual and AFC modes are presented in Figure 46. Similar to findings from cement treated base layer test beds (TBs 3 and 8), semivariogram plots for ks IC-MVs indicated greater non-uniformity in ks IC-MVs after two days of curing (TB9) compared to shortly after compaction (TBs 5 and 6). As noted in TBs 3 and 8, this increased non-uniformity is likely caused because of various factors as non-uniform application of cement, water content, compaction delay time, and compaction energy across the test bed area. Correlations between ks IC-MVs obtained in manual mode and point-MVs from TB 5 and TB9 are presented in Figure 47 and Figure 48, respectively. Regressions on TB5 with ELWD-Z3, EV1, EFWD-D3, and CBR showed good correlations with R2 > 0.50, while with EV2, d and w showed weak correlations with R2 < 0.30. Regressions on TB9 showed relatively weak correlations with all in-situ point-MVs (R2 < 0.5), which is likely due to cracks observed on the treated surface following the mapping passes. Figure 43 compares ks IC-MV, a*, and f maps obtained in manual and AFC modes on TB9. The ks measurements varied from 17 to 60 MN/m, the a* measurements varied from 0.5 to 3.0 mm, and the f measurements varied from 20 to 35 Hz. Analysis of ks, a*, and f results indicated that the vibration amplitude was decreased and the excitation frequency was increased with increase in ks. Comparison between ks and a*, and ks and f for different response distances (i.e., 0, 1, 2, and 3 m) indicated that the response distance for altering the amplitude and frequency was in the range of 1 to 2 m (for variation in v = 4.1 to 4.5 km/h) (note that the roller data was reported approximately every 1 m). ks IC-MV maps for TB4 subgrade material (untreated), TBs 5 and 6 treated subgrade material (shortly after treatment), and TB9 treated subgrade material (after 2-days curing), for the same spatial area is presented in Figure 49. Semivariograms of ks IC-MVs for these test beds are presented in Figure 50, which indicates that the spatial non-uniformity was greater after 2-day curing on the treated subgrade layer compared to on subgrade layer before treatment and shortly after treatment.

Page 68: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

55

169

m

CMVPass 1

CMVPass 2

CMVPass 3

CMVPass 4

Elevation

Pass Count

MDP40

>140140130120110100<100

CMV

>2020151052<2

Pass

>654321

Elev. (m)

>84.1283.5282.9182.3081.6981.08<81.08

169

m

MDP40

Pass 4

MDP40

Pass 3MDP40

Pass 2MDP40

Pass 1

NORTH

Lanes 1 to 3a = 0.90 mm

Lanes 4 to 6Static

Figure 40. MDP40 and CMV maps for passes 1 to 4, and elevation and number of roller passes maps – TB5 treated subgrade material (a = 0.90 mm, f = 30 Hz, and v = 4 km/h

nominal settings)

Page 69: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

56

Pass Number

0 1 2 3 4 5 6

MD

P40

50

75

100

125

150

Pass Number

0 1 2 3 4 5 6

CM

V

0

5

10

15

20

25

Pass Number

0 1 2 3 4 5 6

MD

P40

50

75

100

125

150

Lanes 1 to 3a = 0.90 mm

Lanes 4 to 6Static

Lanes 1 to 3a = 0.90 mm

Figure 41. Boxplots of MDP40 and CMV measurements for passes 1 to 4 – TB5 treated subgrade material

Time (minutes) [Wait time after mixing]

0 100 200 300 400 500

Dry

Un

it W

eigh

t (k

N/m

3)

15

16

17

18

19

20

21

Dry

Un

it W

eigh

t (p

cf)

110

115

120

125

130Laboratory Sample; w = 10.0%In-Situ Sample; w = 10.2%In-Situ Test Measurements

After 4 padfootroller passes;Average w = 11.5%n = 7

Radom pointsduring compactionAverage w = 12.8%n = 9

After final compactionpass; Average w = 10.6%

n = 2095% RC

Figure 42. In-situ density test measurements during compaction in comparison with laboratory density measurements – TB5 treated subgrade material

Page 70: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

57

ks Amp. Freq.

Manual Mode - TBs 5,6Shortly after stabilization

304

m

Static pass after vibratory compaction pass

ks Amp. Freq.

Manual Mode - TB9After 2-day cure

ks Amp. Freq.

AFC Mode - TB9After 2-day cure

ks (MN/m)

Amp. (mm)

Freq. (Hz)

ks (MN/m)

Figure 43. Comparison of ks, a*, and f maps obtained shortly after compaction (TB5/6) and after 2-day cure in manual and AFC modes (TB9)

Page 71: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

58

ks (MN/m)

0 20 40 60 80 100

Fre

que

ncy

0

500

1000

1500

2000TB5/6 Manual TB9 ManualTB9 Auto

Vibration Amplitude (mm)

0.0 0.5 1.0 1.5 2.0 2.5 3.00

500

1000

1500

2000TB5/6 Manual TB9 ManualTB9 Auto

Vibration Frequency (Hz)

22 24 26 28 30 32 340

500

1000

1500

2000TB5/6 Manual TB9 ManualTB9 Auto

Dry Unit Weight (kN/m3)

15 16 17 18 19 20

Fre

quen

cy

0

2

4

6

8

10TB5/6TB9

Moisture Content (%)

0 5 10 15 200

5

10

15

20

TB5/6TB9

CBR (%)

0 50 100 150 2000

5

10

15

20

TB5/6TB9

ELWD-Z3 (MPa)

0 50 100 150 2000

5

10

15

20TB5/6TB9

EFWD-D3 (MPa)

0 200 400 600 8000

5

10

15

20

TB5/6TB9

EV1 (MPa)

0 200 400 600 8000

2

4

6

8

10

12

TB5/6TB9

EV2 (MPa)

0 200 400 600 800 10000

2

4

6

8

10

12

TB5/6TB9

Figure 44. Histogram plots comparing measurements obtained shortly after compaction (TB5/6) and after 2-days curing (TB9)

Page 72: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

59

k s (M

N/m

)

20

30

40

50

60

70

80

TB 5/6 Manual

TB9 Manual

TB9 Auto

Vib

ratio

n A

mpl

itud

e (m

m)

0.0

0.5

1.0

1.5

2.0

2.5

3.0

Vib

ratio

n F

requ

enc

y (H

z)

22

24

26

28

30

32

34

Dry

Un

it W

eigh

t (k

N/m

3 )

15

16

17

18

19

20

Moi

stur

e C

ont

ent

(%)

0

5

10

15

20

CB

R (

%)

0

40

80

120

ELW

D-Z

3 (M

Pa

)

0

40

80

120

160

200

EF

WD

-D3

(MP

a)

0

200

400

600

800

EV

1 (

MP

a)

0

200

400

600

800

EV

2 (M

Pa

)

0

200

400

600

800

1000

TB 5/6 Manual

TB9 Manual

TB9 Auto

TB 5/6 Manual TB9

ManualTB9 Auto

TB 5/6 TB9

TB 5/6

TB9

TB 5/6

TB9

TB 5/6 TB9

TB 5/6 TB9

TB 5/6 TB9

TB 5/6 TB9

Figure 45. Box plots comparing measurements obtained shortly after compaction (TB5/6) and after 2-days curing (TB9)

Page 73: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

60

Table 9. Summary of univariate statistics – TBs 5/9 treated base material

TB Univariate Statistics

MV n COV (%)

TB5

ks (MN/m) 1472 38 5 12

a* (mm) 1472 0.76 0.07 9

f (Hz) 1472 30 1 3

d (kN/m3) 20 17.10 0.28 2

RC (%) 20 88.7 1.5 2

w (%) 20 10.6 1.1 10

ELWD-Z3 (MPa) 18 106 31 29

EV1 (MPa) 19 102 50 49

EV2 (MPa) 17 220 84 38

EFWD-D3 (MPa) 20 249 73 29

CBR (%) 20 44 16 37

TB9

ks (MN/m) [manual] 1514 45 8 18

a* (mm) [manual] 1514 0.81 0.09 11

f (Hz) [manual] 1514 29 1 2

ks (MN/m) [AFC] 1534 35 8 21

a* (mm) [AFC] 1534 1.56 0.44 28

f (Hz) [AFC] 1534 26 2 9

d (kN/m3) 20 16.85 0.30 2

RC (%) 20 87.4 1.60 2

w (%) 20 13.7 1.11 8

ELWD-Z3 (MPa) 20 112 26 23

EV1 (MPa) 20 113 54 48

EV2 (MPa) 20 219 65 30

EFWD-D3 (MPa) 20 223 50 23

CBR (%) 20 39 12 31

Note: Nominal v = 4.2 km/h during roller operation

Page 74: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

61

Separation Distance, h (m)

0 10 20 30 40 50 60 70 80 90 100

Sem

iva

riogr

am

, (

h) [M

N/m

]2

0

30

60

90

120

150

TB5/6 ManualTB9 ManualTB9 AFC

Figure 46. Semivariograms of ks measurements obtained on TB5 in manual mode, TB9 in manual mode, and TB9 in AFC mode

Page 75: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

62

d (kN/m3)

14 15 16 17 18 19 20

k s (M

N/m

)

0

20

40

60

80

100ELWD-Z3 (MPa)

0 50 100 150 200

k s (M

N/m

)

0

20

40

60

80

100

EV1 and EV2 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

w (%)

0 5 10 15 20

k s (M

N/m

)

0

20

40

60

80

100

CBR (%)

0 50 100 150 200

k s (M

N/m

)

0

20

40

60

80

100

ks = 0.19 ELWD-Z3+ 20.2

R2 = 0.69n = 17

ks = 0.10 EV1+ 28.4; R2 = 0.57

ks = 0.02 EV2 + 32.7; R2 = 0.15

n = 13

ks = 0.07 EFWD-D3+ 23.2

R2 = 0.76n = 19

R2 = 0.00n = 20

ks = 0.42 CBR + 24.6

R2 = 0.65n = 20

ks = 11.7 d - 159.6

R2 = 0.29n = 20

Figure 47. Regression analyses between ks and in-situ point measurements – TB5 treated subgrade material (shortly after compaction; manual mode)

Page 76: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

63

d (kN/m3)

14 15 16 17 18 19 20

k s (M

N/m

)

0

20

40

60

80

100ELWD-Z3 (MPa)

0 50 100 150 200

k s (M

N/m

)

0

20

40

60

80

100

EV1 and EV2 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

w (%)

0 5 10 15 20

k s (M

N/m

)

0

20

40

60

80

100

CBR (%)

0 50 100 150 200

k s (M

N/m

)

0

20

40

60

80

100

R2 = 0.03n = 22

ks = 0.05 EV1+ 37.8; R2 = 0.26

EV2: R2 = 0.15

n = 22

R2 = 0.06n = 22

R2 = 0.00n = 22

ks = 0.30 CBR + 32.6

R2 = 0.44n = 22

ks = 7.26 d - 77.9

R2 = 0.25n = 22

Figure 48. Regression analyses between ks and in-situ point measurements – TB9 treated subgrade material (after 2-day cure; manual mode)

Page 77: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

64

Manual Mode – TB4Before Stabilization

Manual Mode – TBs 5,6Shortly After Stabilization

Manual Mode – TB 9After 2‐Day Cure

ks Amp. ks Amp. ks Amp.ks (MN/m)

Amp. (mm)

Freq. (Hz)

ks (MN/m)

Figure 49. Comparison of ks and a* maps obtained in manual mode on granular subgrade material before stabilization (TB4), shortly after stabilization (TB5/6), and 2-days after

stabilization (TB9)

Page 78: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

65

Separation Distance, h (m)

0 10 20 30 40 50 60 70 80

Sem

ivar

iogr

am, (

h) [

MN

/m]2

0

30

60

90

120

150

TB4 - before StabilizationTB5/6 - shortly after stabilizationTB9 - after 2-day cure

Figure 50. Comparison of semivariograms of ks measurements obtained in manual mode on granular subgrade material before stabilization (TB4), shortly after stabilization

(TB5/6), and 2-days after stabilization (TB9)

Summary

TBs 5 and 6 consisted of construction of a nominal 150 mm thick cement-treated base layer. TB5 was compacted by the ISU research team and the contractor, and TB6 was compacted solely by the contractor. MDP40 IC-MVs were obtained during padfoot roller compaction passes on TB5, ks IC-MVs along with in-situ point-MVs (ELWD-Z3, EV1, EV2, EFWD-D3, w, d, and CBR) were obtained from TBs 5 and 6 shortly after treatment. TB9 involved obtaining ks IC-MVs after 2 days of curing along with in-situ point-MVs (ELWD-Z3, EV1, EV2, EFWD-D3, w, d, and CBR). Data analysis for TBs 5, 6, and 9 comprised of geostatistical analysis of the spatially referenced ks IC-MV data and regression analysis between IC-MVs and in-situ point-MVs by spatially pairing the nearest point data. Following is a summary of key findings from these analyses:

During initial compaction on TB5, results indicate that on average MDP40 in static mode increased from about 115.8 to 130.5, while in vibratory low amplitude setting increased from about 111.6 to 122.4, from pass 1 to 5. No significant change in CMV was observed from pass 1 to 5 (average CMV = 4.9 to 5.5).

As expected, the ks IC-MVs improved after 2 days of curing. Results indicated that on average the ks IC-MV increased by about 18% after 2 days of curing.

ELWD-Z3, EFWD-D3, EV1, EV2, and CBR point-MVs showed a small increase or a decrease (-11% to +11%) on TB9 compared to TB5. Note that the in-situ point-MVs were obtained after roller mapping passes, and the surface cracks observed after vibratory rolling is attributed to lowering the strength/stiffness of the treated subgrade layer. Moisture content of the material increased on average from about 10.6% to 13.7%, and as a result the average RC of the material decreased slightly from 89 to 87%.

Page 79: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

66

ks IC-MVs showed greater non-uniformity on TB9 than on TBs 5 and 6. This is an important finding to note and has not been well documented in the literature. The reasons for this increased non-uniformity after curing are attributed to non-uniform application of cement, water content, mixing process, compaction delay time, and compaction energy across the test bed area.

Regressions on TB5 with ELWD-Z3, EV1, EFWD-D3, and CBR showed good correlations with R2 > 0.50, while with EV2, d and w showed weak correlations with R2 < 0.30. Regressions on TB9 showed relatively weak correlations with all in-situ point-MVs (R2 < 0.5), which is likely due to cracks observed on the treated surface following the mapping passes.

AFC operations on TB9 indicated that the vibration amplitude was reduced and the excitation frequency was increased with increase in ks measurement values and the response distance for altering the amplitude and frequency was about 1 to 2 m (for variation in v = 4.1 to 4. 5 km/h)

TB7 Granular Subgrade Material (Untreated)

Test Bed Conditions, IC-MV Mapping, and Point-MV Testing

The test bed consisted of compacted existing granular subgrade material (untreated) over a length of about 110 m. The subgrade material was variable across the test bed with a portion containing white subgrade sand and a portion containing red subgrade sand (Figure 51). Laboratory gradation analysis results (Table 3) indicated that the white subgrade sand material (classified as SP-SM according to USCS) contained about 8% of fines while the red subgrade sand material (classified as SM according to USCS) contained about 37% fines passing the #200 sieve. The portion of the test bed with white sand was unstable under construction traffic (see Figure 51) due to relatively low shear strength in the material from lack of fines. The area was mapped in three roller lanes with Case/Ammann smooth drum roller for one pass each in manual mode (Ecc. = 15%, f = 27Hz, and v = 4.2 km/h) and in AFC mode (medium performance level, and v = 3.2 km/h) settings, and Caterpillar padfoot roller for one roller pass (a = 0.90 mm, f = 30 Hz, and v = 4 km/h). In-situ point-MVs (LWD, NG, PLT, and DCP) were obtained at 10 test locations along one roller lane.

Page 80: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

67

Red Sand

White Sand Pocket

Figure 51. TB7 granular subgrade material (red sand subgrade with isolated white sand pocket)

Page 81: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

68

Test Results and Analysis

IC-MV maps, linear plots along one roller lane, and DCP-CBR profiles at six selected locations along the test bed are presented in Figure 52. Comparison between MDP40, CMV, and ks IC-MVs and in-situ point-MVs are presented in Figure 53, Figure 54, and Figure 55, respectively. Results indicate that in-situ point-MVs and IC-MVs track well together with relatively soft conditions in the area with white subgrade sand material compared to the area with red subgrade sand material. Correlations between MDP40, CMV, and ks IC-MVs and in-situ point-MVs are presented in Figure 56, Figure 57, and Figure 58, respectively. Due to the wide range of measurements, regression relationships showed good correlations with R2 > 0.70 for this test bed. Figure 59 shows comparison between ks and a* measurements obtained in manual and AFC modes in all three roller lanes. During AFC mode operation, the ks measurements varied from 15 to 50 MN/m and the a* measurements varied from 0.4 to 1.8 mm. The f measurements remained relatively constant at about 30 Hz. Analysis of ks and a* measurements indicate that the a* is reduced with increase in ks. Comparison between ks and a* for different response distances (i.e., 0, 1, 2, and 3 m) indicated that the response distance for altering the amplitude and frequency was in the range of 1 to 2 m (for variation in v = 3.8 to 4.2 km/h) (note that the roller data was reported approximately every 1 m).

Page 82: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

69

MDP40

>140140130120110100<100

CMV

>2020151052<2

MDP40 CMV ks

Amp. (mm)

Freq. (Hz)

Amp. Freq. ks Amp. Freq.Manual Mode AFC Mode

Static pass after vibratory compaction pass

110

m

In-Situ TestLocations

(1)(2)

(3)(4)

(5)

(6)

(7)

(8)

(9)

(10)

CBR (%)

0 50 100 150 200 250

0

200

400

600

800

(1)(2)

CBR (%)

0 50 100 150 200 250

0

200

400

600

800

(5)(6)

(CBR%)

0 50 100 150 200 250

Dep

th (

mm

)

0

200

400

600

800

(9)(10)

Distance (m)

0 20 40 60 80 100 120

MD

P40

80

100

120

140

160

CM

V0

10

20

30

40

50

k s (M

N/m

)

20

30

40

50

60

70MDP40

CMVks

(1)(2)(5)(6)(9)(10)

Padfoot indentationson Red Sand Subgrade

Padfoot indentationson White Sand Subgrade

White Sand

Red Sand Subgrade

White SandSubgrade

Red Sand Subgrade

Figure 52. Roller spatial maps, MDP40, CMV, and ks measurements along the middle lane, and DCP-CBR profiles at selected locations – TB7 granular subgrade material

Page 83: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

70

0 20 40 60 80 100 120

MD

P4

0

80

100

120

140

160

EL

WD

-Z3

(MP

a)

0

30

60

90

120

150

0 20 40 60 80 100 120

MD

P4

0

80

100

120

140

160

EV

1 (M

Pa)

-50

0

50

100

150

0 20 40 60 80 100 120

MD

P40

80

100

120

140

160

EV

2 (

MP

a)

0

100

200

300

400

0 20 40 60 80 100 120

MD

P4

0

80

100

120

140

160

CB

R (

%)

-40

0

40

80

120

Distance (m)

0 20 40 60 80 100 120

MD

P40

80

100

120

140

160

d (

kN/m

3 )

14

16

18

20

22

Red Sandw = 7.2%

White Sandw = 3.9%

Red Sandw = 7.8%

Figure 53. Comparison between MDP40 and in-situ point measurements – TB7 granular subrade material

Page 84: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

71

0 20 40 60 80 100 120

CM

V

0

10

20

30

40

50

ELW

D-Z

3 (M

Pa)

0

50

100

150

200

250

0 20 40 60 80 100 120

CM

V

0

10

20

30

40

50

EV

1 (

MP

a)

0

50

100

150

200

250

0 20 40 60 80 100 120

CM

V

0

10

20

30

40

50

EV

2 (M

Pa)

0

100

200

300

400

500

0 20 40 60 80 100 120

CM

V

0

10

20

30

40

50

CB

R (

%)

0

30

60

90

120

150

Distance (m)

0 20 40 60 80 100 120

CM

V

0

10

20

30

40

50

d (

kN/m

3 )

14

16

18

20

22

24

Red Sandw = 7.2%

White Sandw = 3.9%

Red Sandw = 7.8%

Figure 54. Comparison between CMV and in-situ point measurements – TB7 granular subrade material

Page 85: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

72

0 20 40 60 80 100 120

k s (M

N/m

)

20

30

40

50

60

70

EL

WD

-Z3 (

MP

a)

0

50

100

150

200

250

0 20 40 60 80 100 120

k s (M

N/m

)

20

30

40

50

60

70

EV

1 (

MP

a)

0

50

100

150

200

250

0 20 40 60 80 100 120

k s (M

N/m

)

20

30

40

50

60

70

EV

2 (

MP

a)

0

100

200

300

400

500

0 20 40 60 80 100 120

k s (M

N/m

)

20

30

40

50

60

70

CB

R (

%)

0

30

60

90

120

150

Distance (m)

0 20 40 60 80 100 120

k s (M

N/m

)

20

30

40

50

60

70

d (

kN/m

3)

14

16

18

20

22

24

Red Sandw = 7.2%

White Sandw = 3.9%

Red Sandw = 7.8%

Figure 55. Comparison between ks and in-situ point measurements – TB7 granular subrade material

Page 86: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

73

d (kN/m3)

14 15 16 17 18 19 20

MD

P40

80

100

120

140

160ELWD-Z3 (MPa)

0 50 100 150 200

MD

P4

0

80

100

120

140

160

EV1 and EV2 (MPa)

0 200 400 600 800

MD

P40

80

100

120

140

160

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

MD

P4

0

80

100

120

140

160

w (%)

0 5 10 15 20

MD

P4

0

80

100

120

140

160

CBR300(%)

0 50 100 150 200

MD

P40

80

100

120

140

160

No Data

MDP40 = 0.56 ELWD-Z3 + 83.7

R2 = 0.97n = 10

MDP40 = 0.35 EV1 + 101.3

R2 = 0.91MDP40 = 0.25 EV2 + 85.7

R2 = 0.84

MDP40 = 10.41 d - 58.34

R2 = 0.88n = 10

MDP40 = 85.2 CBR0.13

R2 = 0.95n = 10

n = 9

MDP40 = 10.07 w + 68.3

R2 = 0.93n = 10

Figure 56. Regression analyses between MDP40 and in-situ point measurements – TB7 granular subgrade material

Page 87: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

74

d (kN/m3)

14 15 16 17 18 19 20

CM

V

0

10

20

30

40

50ELWD-Z3 (MPa)

0 50 100 150 200

CM

V

0

10

20

30

40

50

EV1 and EV2 (MPa)

0 200 400 600 800

CM

V

0

10

20

30

40

50

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

CM

V

0

10

20

30

40

50

w (%)

0 5 10 15 20

CM

V

0

10

20

30

40

50

CBR300 (%)

0 50 100 150 200

CM

V

0

10

20

30

40

50

CMV = 0.20 ELWD-Z3 - 1.5

R2 = 0.85n = 10

CMV = 0.14 EV1 + 4.4; R2 = 0.92

CMV = 0.09 EV2 - 0.6; R2 = 0.72

n = 9

No Data

CMV = 3.38 d - 46.1

R2 = 0.61n = 10

CMV = 3.64 w - 6.9R2 = 0.79n = 10

CMV = 0.23 CBR + 5.5R2 = 0.96n = 10

Figure 57. Regression analyses between CMV and in-situ point measurements – TB7 granular subgrade material

Page 88: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

75

d (kN/m3)

14 15 16 17 18 19 20

k s (M

N/m

)

0

20

40

60

80

100ELWD-Z3 (MPa)

0 50 100 150 200

k s (M

N/m

)

0

20

40

60

80

100

EV1 and EV2 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

w (%)

0 5 10 15 20

k s (M

N/m

)

0

20

40

60

80

100

CBR300 (%)

0 50 100 150 200

k s (M

N/m

)

0

20

40

60

80

100

ks = 0.27 ELWD-Z3+16.9

R2 = 0.94n = 10

ks = 0.18 EV1 + 24.9; R2 = 0.94

ks = 0.12 EV2 + 17.3; R2 = 0.83

n = 9

No Data

ks = 4.75 w + 10.3

R2 = 0.84n = 10

ks = 0.29 CBR + 26.7

R2 = 0.96n = 10

ks = 4.85 d - 48.5

R2 = 0.78n = 10

Figure 58. Regression analyses between ks and in-situ point measurements – TB7 granular subgrade material

Page 89: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

76

k s (M

N/m

)

0

20

40

60

a* (

mm

)

0.0

0.5

1.0

1.5

2.0

0 20 40 60 80 100 120

k s (M

N/m

)

0

20

40

60

a*

(mm

)

0.0

0.5

1.0

1.5

2.0

Lane 1 - Manual mode setting Ecc. = 15%

Lane 1 - AFC (Medium) setting

k s (M

N/m

)

0

20

40

60

a*

(mm

)

0.0

0.5

1.0

1.5

2.0

0 20 40 60 80 100 120

k s (M

N/m

)

0

20

40

60

a* (

mm

)

0.0

0.5

1.0

1.5

2.0

Lane 2 - Manual mode setting Ecc. = 15%

Lane 2 - AFC (Medium) setting

k s (M

N/m

)

0

20

40

60

a* (

mm

)

0.0

0.5

1.0

1.5

2.0

Distance (m)

0 20 40 60 80 100 120

k s (M

N/m

)

0

20

40

60

a* (

mm

)

0.0

0.5

1.0

1.5

2.0

Lane 3 - Manual mode setting Ecc. = 15%

Lane 3 - AFC (Medium) setting

Roller Direction of Travel

Roller Direction of Travel

Roller Direction of Travel

Roller Direction of Travel

Roller Direction of Travel

Roller Direction of Travel

Figure 59. ks (solid line) and a* (black circles) measurements in manual and AFC mode settings – TB7 granular subgrade material

Page 90: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

77

Summary

The test bed consisted of compacted existing granular subgrade material (untreated) with variable material conditions (soft white subgrade sand and stiff red subgrade sand) over a length of about 110 m. The white subgrade sand material contained about 8% of fines while the red subgrade sand material contained about 37% fines passing the #200 sieve. MDP40, CMV, and ks IC-MV maps were obtained from this test bed in three roller lanes, and in-situ point-MVs were obtained along one roller lane from 10 test locations. Following are key findings from this test bed:

Comparison of MDP40, CMV, and ks IC-MVs and in-situ point-MVs indicated that they both tracked well together by clearly distinguishing the soft (white subgrade sand) and stiff (red subgrade sand) conditions encountered on the test bed.

Correlations between MDP40, CMV, and ks IC-MVs and in-situ point-MVs showed good correlations R2 > 0.70.

Analysis of ks and a* results from AFC mode operation indicated that the vibration amplitude was effectively decreased with increase in ks, and that the response distance for altering the amplitude was in the range of 1 to 2 m (for variation in v = 3.8 to 4.2 km/h).

COMBINED REGRESSION ANALYSIS

Data presented above captured IC-MVs and corresponding in-situ point-MVs over a wide measurement range. The data from multiple test beds are combined in this section to develop site wide correlation results. As discussed above, some of the test bed results only represented a narrow range of measurement values. Combining results should provide a perspective of more general trends and associated variability. Note that for the relationships between IC-MVs and CBR, the weighted average CBR values were obtained for different depths for different test beds. For example, for TB2 with treated base layer the CBR was averaged over the compaction layer depth while for TB1 with untreated base layer the CBR was averaged over 300 mm depth (reported in the discussion as CBR300). Relationships between CCV and in-situ point-MVs based on the data obtained from TBs 1, 2, and 4 are presented in Figure 60. Correlation with EFWD-D3 showed the best relationship with R2 = 0.50 compared to other point-MVs. Correlations with EV1 and ELWD-Z3 yielded R2 = 0.40 and 0.31, respectively. Relationships with EV2 and CBR were relatively weak with R2 < 0.30. No trend was observed in relationship with d. Relationships between MDP40 and various point-MVs based on the data obtained from TBs 4 and 7 are presented in Figure 61. Non-linear exponential relationships are observed in correlations between MDP40 and all in-situ point-MVs. R2 values for relationships with ELWD-Z3, EV1, EV2, and CBR300 point-MVs varied from 0.49 to 0.76. R2 values for relationships with d and w varied from 0.49 and 0.69, respectively. MDP40 values tend to reach an asymptotic value of 150, which is the maximum value set in the AccuGrade software. This observed non-linearity has practical implications as the MDP40 scaling used on the project (described in the background section of the report). For example, the MDP40 values are relatively insensitive (MDP40 ranged from about 140 and 150) to change in in EV1 from about 70 to 200 MPa while the MDP40 values

Page 91: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

78

are very sensitive (MDP40 ranged from about 100 to 140) to change in EV1 from about 10 to 70 MPa. Similar findings are reported by White et al. (2009) from a field study in Minnesota. It appears that the MDP measurement was not set to provide an adequate measurement range relative to the measurement range of plate load test modulus values. Relationships between CMV and various point-MVs based on data obtained from TBs 4 and 7 are presented in Figure 62. Correlation with EV1 showed the best relationship with R2 = 0.64 compared to other point-MVs. Relationships with EV2 and ELWD-Z3 yielded relatively weak correlations with R2 = 0.24. Relationship with d was also relatively weak with R2 = 0.21. No trend was observed in relationship with w. Relationships between ks and various point-MVs based on data obtained from TBs 3, 4, 5, 7, and 8 are presented in Figure 63. In-situ point-MVs obtained after vibratory roller passes on TBs 8 and 9 were deliberately ignored in the correlations analysis due to the effect of surface cracking observed on the treated surfaces following the roller passes. Correlation with EFWD-D3 showed the best relationship with R2 = 0.74 compared to other point-MVs. Correlations with EV1, EV2, and ELWD-Z3 yielded R2 = 0.68, 0.52, and 0.49, respectively. Relationship with d was relatively weak with R2 = 0.30. Some influence of w was noted with R2 = 0.22.

Page 92: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

79

d (kN/m3)

14 15 16 17 18 19 20

CC

V

0

5

10

15

20

25ELWD-Z3 (MPa)

0 50 100 150 200

CC

V

0

5

10

15

20

25

EV1 and EV2 (MPa)

0 200 400 600 800

CC

V

0

5

10

15

20

25

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

CC

V

0

5

10

15

20

25

w (%)

0 5 10 15 20

CC

V

0

5

10

15

20

25

CCV = 0.06 ELWD-Z3 + 3.1

R2 = 0.31n = 56

CCV = 0.03 EFWD-D3

R2 = 0.50n = 27

R2 = 0.00n = 62

R2 = 0.00n = 62

CCV = 0.02 EV1 + 6.2; R2 = 0.40

CCV = 0.01 EV2 + 6.3;

R2 = 0.18n = 56

TBs 1, 2, 4 TBs 1, 2, 4

TBs 1, 2 TBs 1, 2, 4

TBs 1, 2, 4

CBR (%)

0 50 100 150 200

CC

V

0

5

10

15

20

25

TB2TBs 1, 4

CCV = 0.04 CBR + 6.4R2 = 0.26n = 60

TB2: Compaction layer ~150 mmTBs 1, 4:Compaction layer ~300 mm

Figure 60. Regression analyses between CCV and in-situ point measurements – TBs 1, 2, and 4

Page 93: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

80

d (kN/m3)

14 15 16 17 18 19 20

MD

P40

80

100

120

140

160

ELWD-Z3 (MPa)

0 50 100 150 200

MD

P4

0

80

100

120

140

160

EV1 and EV2 (MPa)

0 200 400 600 800

MD

P4

0

80

100

120

140

160

EV1

EV2

w (%)

0 5 10 15 20

MD

P4

0

80

100

120

140

160

TBs 4,7

TBs 4,7

TBs 4,7

TBs 4,7

MDP40 = 148.8 (1-e(-0.04 ELWD-Z3))

R2 = 0.75n = 42

MDP40 = 80.0 (EV1)0.12

R2 = 0.49MDP40 = 146.9 (1-e(-0.02 EV2));

R2 = 0.78

n = 42

MDP40 = 3.0 (d)1.34

R2 = 0.49; n = 46MDP40 = 77.5 (w)0.28

R2 = 0.69; n = 46

CBR300 (%)

0 50 100 150 200

MD

P4

0

80

100

120

140

160

TBs 4,7

MDP40 = 147.9 (1-e(-0.16 CBR300))

R2 = 0.76n = 44

Figure 61. Regression analyses between MDP40 and in-situ point measurements – TBs 4 and 7

Page 94: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

81

d (kN/m3)

14 15 16 17 18 19 20

CM

V

0

10

20

30

40

50

ELWD-Z3 (MPa)

0 50 100 150 200

CM

V

0

10

20

30

40

50

EV1 and EV2 (MPa)

0 200 400 600 800

CM

V

0

10

20

30

40

50

EV1

EV2

w (%)

0 5 10 15 20

CM

V

0

10

20

30

40

50

CMV = 0.12 ELWD-Z3 + 4.7

R2 = 0.24n = 42

CMV = 3.91 d - 52.4

R2 = 0.21n = 46

R2 = 0.05n = 46

CMV = 0.12 EV1 + 3.5; R2 = 0.64

CMV = 0.03 EV2 + 8.6; R2 = 0.24n = 42

TBs 4,7 TBs 4,7

TBs 4,7 TBs 4,7

CBR300 (%)

0 50 100 150 200

CM

V

0

10

20

30

40

50

TBs 4,7

CMV = 0.18 CBR300 + 6.1

R2 = 0.65n = 46

Figure 62. Regression analyses between CMV and in-situ point measurements – TBs 4 and 7

Page 95: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

82

d (kN/m3)

14 15 16 17 18 19 20

k s (M

N/m

)

0

20

40

60

80

100ELWD-Z3 (MPa)

0 50 100 150 200

k s (M

N/m

)

0

20

40

60

80

100

EV1 and EV2 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

EV1

EV2

EFWD-D3 (MPa)

0 200 400 600 800

k s (M

N/m

)

0

20

40

60

80

100

w (%)

0 5 10 15 20

k s (M

N/m

)

0

20

40

60

80

100

ks = 8.7 (ELWD-Z3)0.35

R2 = 0.49n = 88

ks = 3.1 (EFWD-D3)0.47

R2 = 0.74n = 77

ks = 4.54 (d) - 36.0

R2 = 0.30n = 97

ks = 22.9 (w)0.28

R2 = 0.22n = 97

ks = 15.7 (EV1)0.22; R2 = 0.68

ks = 9.2 (EV2)0.28

; R2 = 0.52

n = 63

TBs 3, 4, 5, 7 TBs 3, 4, 5, 7

TBs 3, 5, 8 TBs 3, 4, 5, 7

TBs 3, 4, 5, 7

CBR (%)

0 50 100 150 200

CC

V

0

20

40

60

80

100

TBs 3,5TBs 4,7

ks = 25.3 (CBR)0.15

R2 = 0.44n = 95

TBs 3,5: Compaction layer ~150 mmTBs 4,7:Compaction layer ~300 mm

Figure 63. Regression analyses between ks and in-situ point measurements – TBs 3, 4, 5, 7, and 8

Page 96: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

83

FIELD DEMONSTRATION – OPEN HOUSE

An open house was conducted on 05/21/2009 as part of this field investigation which included dissemination of results from previous IC field studies and results from the current field study as part of a presentation. Demonstration of the two IC rollers, a tour of the Iowa State University geotechnical mobile lab with several laboratory and in-situ testing methods followed the presentation and were conducted at the project location. About 50 people attended the open house including New York DOT, contractor, and roller manufacturer personnel. Photographs from the open house are presented in Figure 64. Some of the attendees operated the IC rollers and received hands-on-experience.

Figure 64. Photographs from open house on the project site

Page 97: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

84

SUMMARY AND CONCLUSIONS

Results from a field study conducted on the US84 project in Waynesboro, MS from July 13–17, 2009 are presented in this report. The project involved evaluating Caterpillar CP-56 padfoot, Case/Ammann SV212 smooth drum, and Sakai SW880 dual drum IC rollers on cement-treated and untreated sandy subgrade and base materials. A total of 9 test beds involving calibration and production operations on treated and untreated subgrade and base materials were constructed by obtaining IC-MVs in conjunction with various in-situ point-MVs (i.e., LWD, FWD, PLT, DCP, and NG). IC-MVs maps on the on-board computer display unit were utilized in selecting field QA test locations in production areas. Results obtained from various test beds contributed to developing empirical relationships between IC-MVs and various in-situ point-MVs. Empirical correlations between IC-MVs and different point-MVs sometimes showed weak correlations when evaluated independently for each test bed, because of the narrow measurement range. The correlations improved when data are combined for site-wide correlations with a wide measurement range. IC-MVs generally correlated better with modulus based in-situ point-MVs (i.e., ELWD-Z3, EFWD-K3, EV1, and EV2) and CBR point MVs than with dry density point-MVs. Correlations between IC-MVs and EFWD-K3, and IC-MVs and EV1 showed strongest correlation coefficients. IC-MV mapping operations were performed in AFC mode using low, medium, and high performance settings on TB8, TB7, and TB9, respectively. When operated in high performance setting, the vibration amplitude was decreased and the excitation frequency was increased with increase in ks. When operated in low and medium performance settings, the vibration amplitude was decreased with increase and ks while the frequency remained relatively constant. Data indicated that the response distance for altering the amplitude and/or frequency was about 1 to 2 m for a roller travel speed of about 4 km/h. Case/Ammann machine on this project reported IC-MVs every 1 m. Denser sampling rate is required to accurately evaluate the response distance. Geostatistical analysis methods were utilized to analyze spatially referenced IC-MV data to assess spatial non-uniformity of the untreated and treated subgrade and base materials. Results indicated that the spatial non-uniformity is higher on the treated subgrade and base layers after two days of curing compared to shortly after compaction and untreated layers. A number of construction related factors likely contribute to this increased non-uniformity which includes non-uniform application of cement, water content, compaction delay time, and compaction energy across the test bed area. This is an important finding and has not been well documented in the technical literature. While the implications of this increased non-uniform support conditions on the performance of the pavements is not well understood, this finding is in contrary to the common presumption that stabilization creates a more “uniform” working platform. More research is warranted to further investigate this topic. The results from this study provided new information with application of IC-MVs in conjunction with various QA test devices on cement treated subgrade and base materials, which to the authors’ knowledge, has not been previously documented in the United States. The study demonstrated several potential advantages of implementing IC roller operations and various in-situ testing methods into earthwork construction QC/QA practice.

Page 98: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

85

REFERENCES Arman, a., and Saifan, F. (1967). “The effect of delayed compaction on stabilized soil-cement,” Highway Research Board No. 198, Washington, D.C., 30-38. ASTM D6951-03. (2003). “Standard test method for use of the dynamic cone penetrometer in shallow pavement application.” American Standards for Testing Methods (ASTM), West Conshohocken, Pennsylvania. ASTM D698-07e1. (2007). “Standard test method for laboratory compaction characteristics of soil using standard effort.” American Standards for Testing Methods (ASTM), West Conshohocken, Pennsylvania. ASTM D422-63. (2007). “Standard test method for particle-size analysis of soils.” American Standards for Testing Methods (ASTM), West Conshohocken, Pennsylvania. ASTM D4318-05 (2005). “Standard test methods for liquid limit, plastic limit, and plasticity index of soils.” American Standards for Testing Methods (ASTM), West Conshohocken, Pennsylvania. ASTM D3282-09. (2009). “Standard practice for classification of soils and soil-aggregate mixtures for high construction purposes.” American Standards for Testing Methods (ASTM), West Conshohocken, Pennsylvania. ASTM D2487-10. (2010). “Standard practice for classification of soils for engineering purposes (unified soil classification system).” American Standards for Testing Methods (ASTM), West Conshohocken, Pennsylvania. Anderegg R., and Kaufmann, K. (2004). “Intelligent compaction with vibratory rollers - feedback control systems in automatic compaction and compaction control,” Transportation Research Record No. 1868, Journal of the Transportation Research Board, National Academy Press, 124-134. Anderegg, R., von Felten, D., and Kaufmann, K. (2006). “Compaction monitoring using intelligent soil compactors.” Proc., GeoCongress 2006: Geotechnical Engineering in the Information Technology Age, February, Atlanta, CD-ROM. Brandl, H., and Adam, D. (1997). “Sophisticated continuous compaction control of soils and granular materials.” Proc. 14th Intl. Conf. Soil Mech. and Found. Engrg., Hamburg, Germany, 1–6. Chilès, J-P., and Delfiner, P. (1999). Geostatistics – Modeling Spatial Uncertainty. John Wiley & Sons, Inc., New York. Clark, I., and Harper, W. (2002). Practical geostatistics 2000. 3rd reprint, Ecosse North America Llc, Columbus, Ohio.

Page 99: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

86

Cowell, M.J., and Irwin, L.H. (1979). “Effects of compaction delays and multiple treatments on the strength of cement stabilized soil,” Transportation Research Record No. 702, Washington, D.C., 191-198. Floss, R., Gruber, N., Obermayer, J. (1983). “A dynamical test method for continuous compaction control.” Proc. 8th European Conf. on Soil Mech. and Found. Engg, H.G. Rathmayer and K. Saari, eds., May, Helsinki, 25-30. Hertz, H. (1895). Über die Berührung fester elasticscher Körper, Gesammelte Werke, Bd. 1. Leipzig. Isaaks, E. H., and Srivastava, R. M. (1989). An introduction to applied geostatistics. Oxford University Press, New York. Kröber, W. (1988). “Untersuchung der dynamischen Vorgänge bei der Vibrationsverdichtung von Böden,” Ph.D. Dissertation, Schriftenreihe, Heft 11, Lehrstuhl und Prüfamt für Grundbau, Bodenmechanik und Felsmechanik der Technischen Universität München (in German). Kröber, W., Floss, R., Wallrath, W., (2001). “Dynamic soil stiffness as quality criterion for soil compaction." Geotechnics for Roads, Rail Tracks and Earth Structures, A.A. Balkema Publishers, Lisse / Abingdon / Exton (Pa) / Tokyo. Lundberg, G. (1939). Elastische Berührung zweier Halbräume, Forschung, auf dem Gebiete des Ingenieurwesens, Band 10, Göteborg, 201–211. NCHRP 21-09. (2010). Intelligent soil compaction systems – NCHRP 21-09, National Cooperative Highway Research Program, Transportation Research Board, Washington, D.C. (in print). Samaras, A.A., Lamm, R., Treiterer, J. (1991). “Application of continuous dynamic compaction control for earthworks in railroad construction.” Transp. Res. Rec., 1309, Journal of the Transportation Research Board, Washington, D.C., 42–46. Sandström, Å. (1994). Numerical simulation of a vibratory roller on cohesionless soil, Internal Report, Geodynamik, Stockholm, Sweden. Sandström Å., and Pettersson, C. B., (2004). “Intelligent systems for QA/QC in soil compaction”, Proc. TRB 2004 Annual Meeting (CD-ROM), Transportation Research Board, Washington, D. C. Thompson, M., and White, D. (2008). “Estimating compaction of cohesive soils from machine drive power.” J. of Geotech. and Geoenv. Engrg., ASCE, 134(12), 1771-1777.

Page 100: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

87

Vennapusa, P., White, D.J., and Gieselman, H. (2009). “Influence of support conditions on roller-integrated machine drive power measurements for granular base.”, Intl. Found. Cong. and Equip. Expo (IFCEE) 2009, 15-19 March, Orlando, Florida. Vennapusa, P., and White, D. J. (2009). “Comparison of light weight deflectometer measurements for pavement foundation materials.” Geotech.Test. J., ASTM, 32(3), 239-251. Vennapusa, P., White, D.J., Morris, M. (2010). “Geostatistical analysis for spatially referenced roller-integrated compaction measurements, J. of Geotech. and Geoenv. Engrg., ASCE, (in print). White, D. J., Jaselskis, E., Schaefer, V., Cackler, T. (2005). “Real-time compaction monitoring in cohesive soils from machine response.” Transp. Res. Rec., 1936, Journal of the Transportation Research Board, Washington D.C., 173–180. White, D.J., and Thompson, M. (2008). Relationships between in situ and roller-integrated compaction measurements for granular soils. J. of Geotech. and Geoenv. Engrg., ASCE, 134(2), 1763-1770. White, D., Thopmson, M., Vennapusa, P., and Siekmeier, J. (2008). “Implementing intelligent compaction specifications on Minnesota TH 64: Synopsis of measurement values, data management, and geostatistical analysis.” Transp. Res. Rec., 2045, Journal of the Transportation Research Board, Washington, D.C, 1-9. White, D.J., Vennapusa, P., Gieselman, H., Johanson, L., Siekmeier, J. (2009). “Alternatives to heavy test rolling for cohesive subgrade assessment,” Eighth Intl. Conf. on the Bearing Capacity of Roads, Railways, and Airfields (BCR2A’09), June 29 – July 2, Champaign, Illinois. Zorn, G. (2003). Operating manual: Light drop-weight tester ZFG2000, Zorn Stendal, Germany.

Page 101: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

APPENDIX: TEST BED SUMMARY SHEETS AND EXPERIMENTAL PLAN

Page 102: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-1

Test Bed # 1 (07/13/2009) Photos

Description: The test bed consisted of mapping an existing compacted granular subbase layer (unstabilized) with the Sakai smooth dual drum IC roller for one roller pass and Caterpillar padfoot IC roller for six roller passes. Nominal machine settings during passes are provided below. In-situ point measurements (LWD, FWD, NG, PLT, and DCP) were performed at 6 test locations. LWD and FWD tests were conducted at the surface and about 50 to 75 mm below the surface. The objectives of testing on this test bed were to obtain correlations between IC measurement values (IC-MVs) MDP40, CCV and in-situ point measurements.

Machine Nominal settings:Sakai smooth SW880: Low amp – a = 0.30 mm, f = 50 Hz (3000vpm), v = 5 km/hCaterpillar padfoot CP56: Low amp – a = 0.90 mm, f = 30 Hz, v = 4 km/h

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

Caterpillar CP-56 roller used on the test bed

In-situ testing methods used on the test bed (left to right): Static plate load test (PLT), Nuclear moisture-density gauge (NG), Dynatest falling weight deflectometer (FWD), FWD measurements in excavation

Sakai SW880 roller used on the test bedPicture of Test Bed 1

Test Bed 1

Page 103: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-2

Test Bed # 1 (07/13/2009): IC-MV (MDP40 and CMV) Maps

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

After Pass 1

After Pass 3 North

215

m

MDP40

Pass 2

MDP40

Pass 3

MDP40

Pass 4MDP40

Pass 5

MDP40

Pass 6MDP40

Pass 7CMV

Pass 2CMV

Pass 3CMV

Pass 4CMV

Pass 5CMV

Pass 6CMV

Pass 7

(1)

(2)

(3)

(4)

(5)

(6)

In-Situ Test Locations

>202015105

CCV

CCVPass 1

NORTH

CMV

>2020151052<2

MDP40

>140140130120110100<100

Page 104: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-3

Test Bed # 2 (07/13/2009) Photos

Description: The test bed was located adjacent to test bed 1 and consisted of a 5-day cured cement stabilized granular subbase layer surfaced with an asphalt binder coat. The area was mapped with Sakai smooth dual drum IC roller. Nominal machine settings during passes are provided below. In-situ point measurements (LWD, FWD, NG, PLT, and DCP) were performed at 21 test locations selected based on the IC map. The asphalt binder coat was reportedly sprayed at the surface of the test bed af ter the stabilization work, to help retain moisture content in the stabilized material. The objectives of testing on this test bed were to obtain correlations between IC measurement values (IC-MVs) CCV and in-situ point measurements.

Machine Nominal settings:Sakai SW880: Low amp – a = 0.30 mm, f = 50 Hz (3000vpm), v = 5 km/h

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

In-situ testing methods used on the test bed (left to right): Dynatest falling weight deflectometer (FWD), Nuclear moisture-density gauge (NG), 300mm plate Zorn light weight deflectometer (LWD)

Sakai SW880 roller used on the test bed

Picture of Test Bed 2

Test Bed 2

Page 105: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-4

Test Bed # 3 (07/14/2009) Photos

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

In-situ testing methods used on the test bed (left to right): Dynatest falling weight deflectometer (FWD), Nuclear moisture-density gauge (NG), 300mm plate Zorn light weight deflectometer (LWD)

Area compacted by Contractor(~ 130 m long section; Section B)

Area compacted by ISU research teamand Contractor (~69 m long section; Section A)

Machine Nominal settings (Section A):Caterpillar padfoot CP56: low amp – a = 0.90 mm, f = 30 Hz, v = 4 km/h.Case/Ammann smooth SV212: Ecc = 15% – a ~0.9 mm, f = 27 Hz, v = 4 km/h. Caterpillar pneumatic tire PS360C: Static. Machine Nominal settings (Section B):Caterpillar padfoot CP563: Static.Sakai smooth SV505T: Static. Caterpillar pneumatic tire PS360C : Static.

Description: The test bed involved stabilizing the TB1 granular subbase material with 5.5% (of dry weight of soil) of cement stabilizer. The stabilization process involved: (a) moisture-conditioning the subbase material to approximately w = 10%, (b) spreading stabilizer on the test bed, (c) preparing the soil-cement mixture using a pulverizer (two passes), (d) compacting the area using padfoot roller (one pass) (e) moisture-conditioning the soil-cement mixture with a water truck, and (f) compacting the area. The test bed was divided in to a 69 m long section (Section A) and a 130 m long section (Section B). Section A was compacted using Caterpillar padfoot IC roller for five roller passes, and Case/Ammannsmooth drum roller for five roller passes by the ISU research team. Roller measurements were continuously recorded during Caterpillar padfoot roller compaction. Following smooth drum roller compaction, Section A was trimmed using a motor grader to the design grade and the area was compacted using a rubber tire pneumatic roller for 6 to 8 passes by Contractor personnel. Compaction on Section B was performed by Contractor personnel. The area was compacted using a Caterpillar padfoot roller for eight roller passes and followed by a Sakai smooth drum roller for two passes. The area was trimmed to the design grade using a motor grader. Then, the area was compacted using Sakai smooth drum roller for two passes and a rubber tired pneumatic roller for six to eight passes. Following pneumatic roller compaction , the area was mapped using Case/Ammann smooth drum IC roller and in-situ point measurements (LWD, FWD, NG, PLT, and DCP) were performed at 30 test locations. The objectives of testing on this test bed were to obtain correlations between IC measurement values (IC-MVs) and in-situ point measurements, and obtain IC-MVs shortly after stabilization to compare with results after two-day curing (see TB8).

Page 106: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-5

Test Bed # 3 (07/14/2009): Construction Photos

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

Scarified and moisture‐conditioned subbase Placement of cement stabilizer on subbase

Soil‐cement mixing process using puliverzier Moisture‐conditioning the soil‐cement mixture

Compaction using Caterpillar padfoot IC roller Moisture‐conditioning after first pass

Page 107: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-6

Test Bed # 3 (07/14/2009): Construction Photos (Continued)

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

Compaction using Caterpillar padfoot roller

Final compaction passes using Caterpillar pneumatic tire roller

Compaction using Sakai smooth drum oller Fine grading using motor grader

Page 108: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-7

Test Bed # 3 (07/14/2009): IC-MV maps

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS69

m

MDP40

Pass 1MDP40

Pass 2

MDP40

Pass 3MDP40

Pass 4MDP40

Pass 5

CMVPass 1

CMVPass 2

CMVPass 3

CMVPass 4

CMVPass 5

Elevation

Pass Count

MDP40

>140140130120110100<100

CMV

>2020151052<2

Pass

87654321

Elev. (m)

>78.7978.7978.6478.4978.3378.1878.03<78.03

69 m

North

IC-MV, Elevation, and Pass Count maps of Section A compacted by ISU research team

Page 109: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-8

Test Bed # 3 (07/14/2009): IC-MV maps

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

IC-MV, Amplitude, Frequency, Pass Count, and Speed maps of Case/Ammann roller pass performed shortly after completion of pneumatic tire roller passes

ks (MN/m)

Amp. (mm)

Freq. (Hz)

Pass

Speed (km/h)

North201

m

Area compacted by Contractor

Area compacted by ISU research team and Contractor

ks (MN/m) Amp. (mm) Freq. (Hz) Pass Speed

Page 110: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-9

Test Bed # 4 (07/14/2009) Photos

Description: The test bed consisted of mapping a 530 m long section of existing compacted granular subgrade layer (unstabilized) with Sakai smooth dual drum IC roller, Case/Ammannsmooth drum IC roller, and Caterpillar padfoot IC roller for one roller pass each. Nominal machine settings during roller passes are provided below. In-situ point measurements (LWD, NG, PLT, and DCP) were performed at 39 test locations selected base on IC maps. The objectives of testing on this test bed were to obtain correlations between IC measurement values (IC-MVs) MDP40, CCV, ks and in-situ point measurements.

Machine Nominal settings:Sakai smooth SW880: High amp – a = 0.60 mm, f = 50 Hz (3000vpm), v = 5 km/hCase/Ammann smooth SV212: Ecc. = 15% - a ~ 0.90 mm, f = 27Hz, v = 4 km/hCaterpillar padfoot CP56: Low amp – a = 0.90 mm, f = 30 Hz, v = 4 km/h

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

In-situ testing methods used on the test bed (left to right): 300mm plate Zorn light weight deflectometer (LWD), Dynamic Cone Penetrometer (DCP), Nuclear moisture-density gauge (NG), and Static Plate

Load Test (PLT).

Sakai SW880, Case/Ammann SV212, and Caterpillar CP56 rollers (left to right) used for mapping

Picture of test bed

Page 111: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-10

529

m

MDP40

>140140130120110100<100

CMV

>2020151052<2

Elev. (m)

>78.7978.7978.6478.4978.3378.1878.03<78.03

MDP40CMV Elev. (m)

530

m

ks (MN/m)

Amp. (mm)

Speed (km/h)

ks (MN/m)Amp. (mm)

Speed (km/h)

Test Bed # 4 (07/14/2009): IC-MV maps

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

CCV

>2020151196<3

530

m

CCV

Page 112: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-11

Test Beds # 5 and 6 (07/15/2009) Photos

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

In-situ testing methods used on the test bed (left to right): Dynatest falling weight deflectometer (FWD), Nuclear moisture-density gauge (NG), 300mm plate Zorn light weight deflectometer (LWD)

Machine Nominal settings (Section A):Caterpillar padfoot CP56: low amp – a = 0.90 mm, f = 30 Hz, v = 4 km/h on lanes 1 to 3 and static, v = 4 km/h on lanes 4 to 6Case/Ammann smooth SV212: Ecc = 15% –a ~0.9 mm, f = 27 Hz, v = 4 km/h. Caterpillar pneumatic tire PS360C: Static. Machine Nominal settings (Section B):Caterpillar padfoot CP563: low amp.Sakai smooth SV505T: low amp. Caterpillar pneumatic tire PS360C : Static.

Description: Test beds 5 and 6 involved stabilizing a portion of TB4 granular subgrade material with 5.5% (of dry weight of soil) of cement stabilizer. The stabilization process involved: (a) moisture-conditioning the subgrade material to approximately w = 10%, (b) spreading stabilizer on the test bed, (c) preparing the soil-cement mixture using a pulverizer (two passes), (d) compacting the area using padfoot roller (one pass), (e) moisture-conditioning the soil-cement mixture, and (f) compacting the area. Test bed 5 was compacted by both ISU research team and Contractor personnel, while test bed 6 was compacted by Contractor personnel. Test bed 5 was compacted using Caterpillar padfoot IC roller for four roller passes, and Case/Ammann smooth drum roller for three roller passes by ISU research team. Roller measurements were recorded only during Caterpillar padfoot roller compaction. Then, the Contractor personnel used Sakai smooth drum roller for four roller passes. Following smooth drum roller compaction, the area was trimmed using a motor grader and then compacted using a rubber tire pneumatic roller for 6 to 8 passes. Compaction on test bed 6 was performed using a Caterpillar padfoot roller for four to six roller passes and followed by a Sakai smooth drum roller for four passes. The area was trimmed to the design grade using a motor grader in between the smooth drum roller passes. The area was then compacted using rubber tired pneumatic roller for six to eight passes. Following pneumatic roller compaction, test beds 5 and 6 were mapped using Case/Ammann smooth drum IC roller and in-situ point test measurements (LWD, FWD, NG, PLT, and DCP) were performed at 20 test locations selected based on the IC-map. The objectives of testing on this test bed were to obtain correlations between IC measurement values (IC-MVs) and in-situ point measurements, and obtain IC-MVs shortly after stabilization to compare with results after two-day curing (see TB9).

TB5TB6

Page 113: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-12

Test Bed # 5 (07/15/2009): Construction Photos

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

Placement of cement stabilizer on subgrade Pulverizing and moisture‐conditioning process

Pulverizing and moisture‐conditioning process

Moisture‐conditioning process Compaction using Caterpillar padfoot IC roller

Page 114: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-13

Test Bed # 5 (07/15/2009): Construction Photos (continued)

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

Compaction using Sakai smooth drum roller

Trimming process using motor grader Final compaction using Caterpillar pneumatic rubber tire roller

Page 115: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-14

Test Bed # 6 (07/15/2009): Construction Photos

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

Compaction using Caterpillar padfoot roller

Trimming process using motor grader

Compaction using Caterpillar padfoot roller

Soil‐cement mixing process using pulverizer

Page 116: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-15

169

m

CMVPass 1

CMVPass 2

CMVPass 3

CMVPass 4

Elevation

Pass Count

MDP40

>140140130120110100<100

CMV

>2020151052<2

Pass

>654321

Elev. (m)

>84.1283.5282.9182.3081.6981.08<81.08

169

m

MDP40

Pass 4

MDP40

Pass 3MDP40

Pass 2MDP40

Pass 1

Test Beds # 5 and 6 (07/15/2009): IC-MV maps

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

ks (MN/m)

ks (MN/m)

169

m

ks (MN/m)

ks (MN/m)

169

m

TB5

TB6

TB5

Area compacted by Contractor

Area compacted by ISU research team and Contractor

Area compacted by ISU research team and Contractor

Static(lanes 4 to 6)

a = 0.9 mm(lanes 1 to 3)

Lane

123

45

6

Page 117: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-16

109.

5 m

MDP40

>140140130120110100<100

CMV

>2020151052<2

MDP40 CMV ks

Amp. (mm)

Freq. (Hz)

Amp. Freq. ks Amp. Freq.Manual Mode AFC Mode

Static pass after vibratory compaction pass

Test Bed # 7 (07/15/2009) Photos

Description: This test bed contained compacted existing granular subgrade material over a length of about 110 m. The subgrade material was variable across the test bed. Portion of the subgrade contained white poorly graded sand pocket that was unstable under traf f ic wheel loads. The area was mapped with Case/Ammannsmooth drum roller for two passes (f irst pass in manual mode and second pass in AFC mode) and Caterpillar padfoot roller for one roller pass. In-situ testing (LWD, NG, PLT, and DCP) were performed at 10 test locations along middle lane of the test bed. The objectives of testing on this test bed were to evaluate the ef fectiveness of IC roller to indicate unstable/sof t areas, correlate in-situ test measurements with IC-MVs, and to evaluate AFC mode compaction. Machine Nominal settings:Case/Ammann smooth SV212: Manual Ecc. = 15% - a ~ 0.90 mm, f = 27Hz, v = 4 km/h; AFC, v = 4 km/h. Caterpillar padfoot CP56: Low amp – a = 0.90 mm, f = 30 Hz, v = 4 km/h

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

Page 118: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-17

ks

Amp. (mm)

Freq. (Hz)

Amp. Freq.

Manual Mode - TB3Shortly after stabilization

ks Amp. Freq.

Manual Mode - TB8After 2-day cure

ks (MN/m)

201

m

213

m

ks Amp. Freq.

AFC Mode - TB8After 2-day cure

Test Bed # 8 (07/16/2009) Photos

Description: This test bed contained 2-day cured stabilized granular subbase material f rom TB3. The area was mapped with Case/Ammannsmooth drum roller in manual and AFC modes and in-situ testing (LWD, FWD, NG, PLT, and DCP) was performed at 25 test locations selected using the IC-Map. The objectives of testing on this test bed were to evaluate strength gain in stabilized granular subbase layer by comparing IC-MVs obtained on TB3 shortly af ter stabilization and af ter 2-day curing, and to obtain correlations between in-situ test measurements and IC-MVs.

Machine Nominal settings:Case/Ammann smooth SV212: Manual Ecc. = 10% - a ~ 0.90 mm, f = 27Hz, v = 4 km/h; AFC, v = 4 km/h.

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

In-situ testing methods used on the test bed

Case/Ammann roller used for mapping

North

Page 119: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-18

Test Bed # 9 (07/17/2009) Photos

Description: This test bed contained 2-day cured stabilized granular subgrade material f rom TBs 5 and 6. The area was mapped with Case/Ammannsmooth drum IC roller in manual mode and AFC mode, and in-situ testing (LWD, FWD, NG, PLT, and DCP) were performed at 22 test locations selected using the IC-Map. The objectives of testing on this test bed were to evaluate strength gain in the stabilized granular subgrade layer by comparing IC-MVs obtained on TBs 5 and 6 shortly af ter stabilization and af ter 2-day curing, and to obtain correlations between in-situ test measurements and IC-MVs.

Machine Nominal settings:Case/Ammann smooth SV212: Manual Ecc. = 15% - a ~ 0.90 mm, f = 27Hz, v = 4 km/h; AFC, v = 4 km/h.

Accelerated Implementation of IC Technology for Embankment Subgrade Soils, Aggregate Base, and Asphalt Pavement Materials

Iowa State University Research Team Field Testing, US84, Waynesboro, MS

ks

Amp. (mm)

Freq. (Hz)

Amp. Freq.

Manual Mode - TB4Shortly after stabilization

ks Amp. Freq.

AFC Mode - TB9After 2-day cure

ks (MN/m)

304

m

ks Amp. Freq.

Manual Mode - TB9After 2-day cure

Static pass after vibratory compaction pass

In-situ testing methods used on the test bed

Case/Ammann roller used for mapping

Page 120: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-19

ISU

Res

earc

h T

eam

Co

nta

cts:

David J. W

hite, Associate Professor, djwhite@

iastate.edu, (515) 290‐1080 (cell)

Heath Gieselman, Assistant Scientist, [email protected], (515) 450‐1383 (cell)

Em

ban

kmen

t/Sub

grad

e(S

tabi

lized

)

Sta

biliz

ed B

ase

(5%

cem

ent)

12

Pa

ve

me

nt F

ou

nd

ati

on

La

yers

Acc

eler

ated

Im

ple

men

tati

on

of

IC T

ech

no

log

y fo

r E

mb

ankm

ent

Su

bg

rad

e S

oil

s, A

gg

reg

ate

Bas

e, a

nd

Asp

hal

t P

avem

ent

Mat

eria

lsU

S 8

4, W

ayn

e C

o,

MS

–M

issi

ssip

pi

Dep

artm

ent

of

Tra

nsp

ort

atio

n[J

un

e 1-

Jun

e 5,

200

9]

Notes:

A. M

oisture condition calibration test strip areas ±1.5% optimum except as noted.

B. M

SDOT assistance

requested for FW

D testing and inform

ation on project QA testing requirements.

C. As time perm

its repeatability passes for roller will be perform

ed on embankm

ent and aggregate base.

6” ~8”

Dat

eT

BM

ach

ine

Am

p

(mm

)S

po

t T

ests

No

tes/

Co

mm

ents

06/01

ISU arrives at site to setup mobile

lab (7 am)

Meet with Contractor and identify potential test areas (7am

)Setup CASE/CAT/SAKAI rollers and make trial runs with GPS (8 am)

Collect material sam

ples for on‐site laboratory characterization (10 am)

06/01

1CAT

(padfoot)

Static,

0.9, 1.8

DCP,LWD, N

G, and

PLT

8 m

x 60 m

calibration test area.

1.Prepare then compact foundation layer with 8

roller passes and map

for untreated subgrade.

2.Place

one 200 to 300 mm loose

lift of untreated

subgrade.

3.Create variable m

oisture conditions.

4.Compact in three lanes using static, medium, and

high amplitude @

8‐12passes + 3mapping passes

5.Develop compaction curves

6.Repeat compaction for 3 liftsin sam

e area

2Case

(smooth)

TBD

DCP,LWD, N

G,

PLT, FWD

Roller m

apping in production areas of (1) untreated

and (2) stabilized subgrade. M

onitor existing

practice and perform

in‐situ tests for comparison.

Use

data for test run on IC

QC/Q

A specification.

06/02

‐06/03

3Case

(smooth)

Low,

High,

Feedback

control

DCP,LWD, N

G, PLT

12 m

x 60 m

calibration test area.

1.Compact foundation layer with 8 roller passes and

map.

2.Place

150 mm lift of stabilized subgrade

3.Create variable m

oisture conditions.

4.Compact in three lanes using low, high, and

feedback control @

8‐12passes + 3mapping

passes

5.Develop compaction curves

4CAT

(padfoot)

Static,

0.9, 1.8

DCP,LWD, N

G, PLT

06/03 to

06/05

5/6

Case

(smooth)/

CAT

(padfoot)

TBD

DCP,LWD, N

G,

PLT, FWD

Roller m

apping in production areas of (1) untreated

and (2) stabilized subgrade. M

onitor existing practice

and perform

in‐situ tests for comparison. Use

data

for test run on IC

QA specification.

06/04

Open House

–presentation of prelim

inary results and roller demonstrations.

d&

ELW

D

IC ‐MVs

IC-T

V

QA-TV Fu

ll P

ave

me

nt W

idth

( ~

8 to

12

m)

~ 60 m for Calibration areas and up to 300 m for Production areas

Pro

duc

tion

Are

a s

of

(1) u

ntr

eate

d a

nd

(2)

stab

ilize

d s

ubgr

ade

Cal

ibra

tion

Are

as

-2%

wo

pt

-0%

+2%

Sub

gra

de

calib

ratio

n st

rip

3 m

6 m

Page 121: ACCELERATED IMPLEMENTATION OF INTELLIGENT …

A-20

MS

DO

T -

Pro

ject

Goa

ls

1.D

ocum

ent

impa

ct o

f va

riabl

e fe

edba

ck c

ontr

ol o

n co

mpa

ctio

n un

iform

ity

2.D

ocum

ent

mac

hine

vib

ratio

n am

plitu

de in

fluen

ce o

n co

mpa

ctio

n ef

ficie

ncy

3.S

tudy

IC r

olle

r m

easu

rem

ent

influ

ence

dep

th

4.D

evel

op c

orre

latio

nsb/

w I

C r

olle

r va

lues

to

trad

ition

al m

easu

rem

ents

5.C

ompa

re I

C r

esul

ts t

o tr

aditi

on c

ompa

ctio

n op

erat

ions

6.S

tudy

IC r

olle

r m

easu

rem

ent

valu

es in

pro

duct

ion

com

pact

ion

oper

atio

ns

7.E

valu

ate

IC m

easu

rem

ent

valu

es in

ter

ms

of a

ltern

ativ

e sp

ecifi

catio

n op

tions