Upload
pragatinaresh
View
217
Download
0
Embed Size (px)
Citation preview
8/13/2019 Acc. No. DC 59
1/67
Real Power Spot Pricing using Unified Power Flow
Controller
Thesis submitted in partial ful fi llment of the requi rement for the Degree of
Master of Power Engineer ing f rom the Faculty of Engineeri ng &Technology, Jadavpur University in the year 2010
Submitted by
ARNAB BHADURI
Master of Power Engineering
Regn. No. 104350 of 2008-2009
Exam Roll No. M4POW10-09
Under the guidance of
Dr. Mousumi BasuDepartment of Power Engineering
Jadavpur University
Saltlake Campus
Kolkata-700098
8/13/2019 Acc. No. DC 59
2/67
8/13/2019 Acc. No. DC 59
3/67
Department of Power engineering
Faculty of Engineering and Technology
Jadavpur University
The foregoing thesis, ent it led as Real power spot pricing using unified power f low
controlleris hereby approved by the committee of final examination for evaluation of
thesis as a creditable study of an engineering subject carried out and presented byArnab
Bhaduri (Regn. No.104350 of 2008-2009; Exam Roll No. M4POW10-09) in a manner
satisfactory t o warrant it s acceptance as a perquisite to the Degree of Master of Power
Engineering. I t is understood that by this approval, the undersigned do not necessarily
endorse or approve any statement made, opinion expressed or conclusion drawn therein,
but approve the thesis only for t he purpose for which it is submitted.
Committee of final examination for evaluation of thesis:
-----------------------------
-----------------------------
----------------------------
8/13/2019 Acc. No. DC 59
4/67
Acknowledgement
The author remembers the with gratitude the constant guidance, suggestions and
encouragement forwarded by several respected persons and knows well that it is not
possible to express his indebt ness for all those valuable assistances by writing some
lines. Following conventions, he, therefore, acknowledges in this page, the assistance
rendered by all the concerened persons, as a token of his gratitude.
The author thankfully acknowledges the kind and persistent valuable suggestion, advice,
guidance, help and encouragement from Dr. Mousumi Basu without whom this thesis
would not have been a reality.
The author is thankful to the head of Power Engineering department for his kind
permission to carry out the project under Dr. Mousumi Basu.
The author is likely to convey his gratitude to all teachers in ME course in the Power
Engineering department of Jadavpur University for excellent teaching that helps to
complete the project smoothly.
The author would also like to express his sincere thanks to all his classmates specially
Mr. Sanjay Chauhan who came with some valuable suggestions to make this thesis
possible.
Finally, the author wishes his profound gratitude to his parents, family members for
providing constant encouragement throughout his thesis work.
Arnab Bhaduri
8/13/2019 Acc. No. DC 59
5/67
Abstract_______________________________________
This thesis proposes real power spot price analysis using Unified Power Flow Controller.
Real power spot price is analyzed and compared with the base case to the case after
implementing the Unified Power Flow Controller. Optimal placement for Unified Power
Flow Controller by analyzing the sensitivity for the UPFC parameters is also done in this
thesis work. All the proposed methods and algorithms are tested on IEEE standard 30bus
system for verification.
8/13/2019 Acc. No. DC 59
6/67
Contents_______________________________________
Subjects Page No.
Chapter 1: INTRODUCTION
1.1Introduction 1
1.2Motivation behind this work 2
1.3 Literature Survey 3
1.3Overview 4
Chapter 2: OPTIMAL POWER FLOW
2.1 Optimal power flow problem 5
2.2 Optimal power flow problem formulation 6
2.2.1 The objective function 6
2.2.2 The equality contstraints 6
2.2.3 The inequality constraints 7
2.2.3.1 Real power generation limit 8
2.2.3.2 Reactive power generation limit 8
2.2.3.3 Voltage limit 8
2.2.3.4 Line flow limit 9
2.2.3.5 UPFC parameters limit 9
2.3 Comparative study of different solution techniques for the OPF 9
2.3.1 Newtons Method 9
2.3.2 Gradient method 10
2.3.3 Lambda iteration method 10
8/13/2019 Acc. No. DC 59
7/67
2.3.4 Linear Programming method 10
2.3.5 Interior poinr method 10
2.3.6 Genetic algorithm method 11
2.3.7 PSO method 11
Chapter 3: FLEXIBLE AC TRANSMISSION SYSTEM
3.1 About FACTS 12
3.2 Classification of FACTS 12
3.2.1 Shunt controller 13
3.2.1.1 Shunt controller 13
3.2.1.2 Types 14
3.2.2 Series Controller 16
3.2.2.1 Series compensation 16
3.2.2.2 Types 17
3.3.3 Combined shunt-series controller 21
3.3 Utility of FACTS 22
3.4 Maintenance of FACTS 22
Chapter 4: UNIFIED POWER FLOW CONTROLLER
4.1 About Unified power flow controller 23
4.2 Structures and operations of UPFC 24
4.3 Equivalent circuit of UPFC 25
4.4 Modeling of UPFC 27
4.5 Location of UPFC 30
8/13/2019 Acc. No. DC 59
8/67
Chapter 5: GRADIENT METHOD
5.1 Problem formulation 35
5.2 Computational procedure 36
5.3 Inequality constraints on control variables 37
5.4 Inequality constraints on dependent variables 37
5.5 Lagrangian for solving OPF in gradient method 38
Chapter 6: SPOT PRICING
6.1 Introduction 39
6.2 Power pools 39
6.2.1 Advantages 40
6.2.2 Disadvantages 40
6.3 Spot price 41
6.4 Marginal cost 42
Chapter 7: RESULTS AND DISCUSSIONS
7.1 IEEE 30- bus test system 43
7.2 Tabulated results 43
7.3 Graphical results 49
Chapter 8: CONCLUSIONS
8.1 Conclusion 51
8.2 Future scope 51
References 52
Nomenclature 54
Appendix 55
8/13/2019 Acc. No. DC 59
9/67
1
Chapter 1: INTRODUCTION
1.1 IntroductionElectrical engineering is an essential ingredient for the industrial and all-round
development of any country. It is a one of the most desirable form of energy, since it can
be generated centrally in bulk and transmitted economically over long distances. The
system which generates controls, transmits and finally distributes electrical energy to the
consumers is called an electrical power system. Electricity cannot be stored economically
and the electric utility need some control over the load or power demand at any time.
This system therefore should be capable of matching the output from the generators to thedemand at any time at the specified voltage and frequency.
The electrical power must be transmitted in steady-state mode under their normal
operating conditions. In accordance to this, three major problems encountered in steady-
state mode of operations are: 1) load flow problem, 2) optimal load dispatch problem and
3) systems control problem. The aim of power flow calculations is to determine the
steady-state operating characteristics of a power generation or transmission system for a
given set of bus-bar loads. Active power generations are specified according to economic
dispatching. In system operation and planning, the voltages and powers are kept within
certain limits. The power system networks of today are highly complicated consisting of
hundreds of buses and transmission links. Thus the load flow study involves extensive
calculations.
With increasing pace of power system restructuring, transmission systems are being
required to provide increased power transfer capability and at the same it is also required
to accommodate a much wider range of possible generation patterns. Power systems,
throughout the world, have been forced to operate in almost full capacities due to the
environmental and/or economical constraints to build new generation centers and
transmission lines. If the power flow limit exceeds a certain permissible limit the system
is said to be congested. There is an interest in better utilization of available power system
capacities by installing new devices such as flexible ac transmission system (FACTS).
8/13/2019 Acc. No. DC 59
10/67
2
These devices are useful in modern power system operation to reduce the flows in
heavily loaded lines, resulting in increased load ability, low system loss, improved
stability of the network, reduced production cost, and fulfilled contractual requirement by
controlling the power flows in the network. If there is no congestion, the optimal location
of FACTS devices can be decided on the basis of real power flow performance index
( )PI has been used due to security and stability reasons. A definite methodology has
been used to locate the FACTS device (UPFC) for congestion management in the
deregulated power sector and in doing that a nonlinear optimization problem has been
formulated and evaluated by some certain power flow solution algorithm (Gradient
Method) with and without incorporating FACTS device (UPFC) to see the impact on
transmission real power spot pricing.
1.2 Motivation behind this work
In modern days deregulated power system environment major organizational and
structural changes has been observed. In view of this transmission pricing is an important
issue. For a participant of electric power system two things need to be fully examined,
firstly the relationship between competition requirements and the market structures and
secondly optimal operation of supply and demand in terms of social welfare. In this
respect many researchers used different methods for determining spot prices in
deregulated power systems. In competitive electricity markets, to supply deregulation, it
is important that both the producers and consumers reach an optimum goal so that both of
them get benefited. In this respect, spot price applications and participants bids must be
considered simultaneously in deregulated power market operations. FACTS device plays
an important role for improving the power pricing.
All these aspects related to deregulated electricity market and modern economic scenario
lead to this thesis work. In this work spot prices are calculated at different load buses
after formulating an optimal power flow problem. Moreover optimal placement of facts
device in a line of network also has been considered in this work to compare the spot
prices at different load buses for base case as well as with implementing the FACTS
device.
8/13/2019 Acc. No. DC 59
11/67
3
1.3 Literature survey
In 1995 Gyugyi, Rietman, Edris, Schauder, Torgerson, Williams [1] show the unique
capability of a UPFC in multiple line compensation by controlling both the transmitted
real power power and, independently, the reactive power flows at the sending-end and the
receiving end of the transmission line.
In 1996, Jenn-Huei Jeffrey Kuan [2] in his thesis work described the necessary
optimization technique for economic operations in an open-accessed transmission grid
industry and suggested a suitable supply demand curve in order to achieve social welfare.
Also gradient method based optimization solution process has been derived in the thesispaper.
In 1998, Choi et al [3]presented a theory and simulation results of real-time pricing of
real and reactive powers that maximize social benefits.
In1998 Lima et al. [4] presented the dynamic aspects of pricing and its impact on long
term expansion planning of both generation and transmission.
The basic principle and operation are discussed by J.Y.Liu and Y.H. Song [5] in 1999
and by J.Y. Liu and Y.H. Song and P.A. Mehta [6] in the same year respectively.
In April 1999, Keri, Mehraban, Lombard, Elriachy, Edris [A1] analyze a set of equations
for a system including UPFC and an equivalent two bus network.
In 2000, Srivastava and Verma [7] utilize a location based pricing concepts and suggested
a nonlinear programming problem formulation to determine real and reactive power
prices.
In July,2001, K.S. Verma, S.N. Singh and H.O. Gupta [8] proposed a method for the
suitable location of unified power flow controller.
Same year in [9] and [10] also a suitable location of unified power flow controller had
been derived, with a static point of view. The optimal location is based on real power
flow performance index sensitivity with respect to control parameters of unified power
flow controller.
8/13/2019 Acc. No. DC 59
12/67
4
In July, 2001, K.S. Verma, S.N. Singh and H.O. Gupta [11] introduced a steady-state
model of UPFC (unified power flow controller) power injection model which has been
introduced in the minimum price dispatch algorithm.
In 2006, K.S. Verma and H.O. Gupta [12] formulated a suitable method for finding the
real and reactive spot price incorporating UPFC at an optimal location after analyzing the
sensitivities with respect to the UPFC parameters.
In 2010, A.Urkmez [13] presents a new formula for determining spot price and a new
algorithm for economic dispatch in deregulated power systems.
1.4 Overview
Real power time spot prices are calculated in this thesis incorporating n unified power
flow controller (UPFC) and the results are used for a comparative study with the base
case, i.e without incorporating UPFC. While doing this optimal location of UPFC is also
calculated with the help of performance index sensitivity factors for the respective UPFC
parameters like voltage, phase angle etc. The optimal power flow problem has been
solved by gradient method for finding the respective Lagrange multipliers for the
Lagrangian function. In chapter 2 the OPF is formulated. Flexible AC Tranasmission
System (FACTS) is discussed in chapter 3. Chapter 4 describes the model, structures and
operations about UPFC and also some useful facts for finding the optimal location.
Chapter 5 describes the Gradient method for solving the OPF related to this problem
elaborately. Chapter 6 gives an idea of spot pricing. Chapter 7 concludes with a summary
and several improvements, which would aid in creating a more efficient pricing method.
8/13/2019 Acc. No. DC 59
13/67
5
Chapter 2: OPTIMAL POWER FLOW
2.1 Optimal power flow problem
The computational procedure required to determine the steady-state operating
characteristics of a power system network is termed as Load Flow. The aim of power
flow calculations is to determine the steady-state operating characteristics of a power
generation or transmission system for a given set of bus bar loads. In the past two
decades, the problem of optimal power flow (OPF) has received much attention. It is of
current interest of many utilities, and it has been marked as one of the most operational
needs. The OPF problem solution aims to optimize a selected objective function, such as
fuel cost via optimal adjustment of the power system control variables, while at the same
time satisfying various equality and inequality constraints. The equality constraints are
the power flow equations, and the inequality constraints are the limits on control
variables and the operating limits of power system-dependent variables. The problem
control variables include the generator real powers, the generator bus voltages, the
transformer tap settings, and the reactive power of switch able VAR sources, while the
problem-dependent variables include the load bus voltages, the generator reactive
powers, and the line flows. Generally, the OPF problem is a large-scale, highly
constrained, nonlinear, no convex optimization problem.
Optimal Power Flow (OPF) has been extensively used in power systems at the generation
or transmission level to designate the problem of finding the optimal value for the control
variables (real and reactive power, voltage settings, batteries set points, etc.) when
minimizing the total operation cost, while respecting the technical constraints of the
network and equipments. In distribution systems, many approaches exist dedicated to the
optimization of the configuration and the optimization of the voltage profile through
batteries. In both cases the objective function seeks for losses reduction, but in separate
ways. The recent development of distribution systems has led to the presence of
distributed generation that introduces uncertainty in the previously mentioned problems,
but may contribute to voltage control and optimization. In the same cases, regional
dispatch of this unit is possible; tuning is possible to seek for optimal operating policies.
8/13/2019 Acc. No. DC 59
14/67
6
An optimal load-flow solution gives the optimal active and reactive power dispatch for a
static power-system loading condition. Computationally, it is a very demanding nonlinear
programming problem, due to the large number of variables and in particular to the much
larger number and types of limit constraints which define the boundaries of technical
feasibility.
2.2 Optimal power flow problem formulation
2.2.1 The objective function
Generally it can be written as
min ( , , )F x u p (2.1)
Here the obejective function to be minimized is the difference of the operational cost for
the active power of pool generator to the pool load, which is given by,
( ) ( )G D
T i Pi j pj
i I j I
F C P B D
=
(2.2)
2.2.2 The equality constraints
Generally it can be written as
( , , ) 0h x u p = (2.3)
where
state vector V, , DV , D , qI
u control parameters giP , giQ
p fixed parameters diP , diQ
8/13/2019 Acc. No. DC 59
15/67
7
The objective function motioned in eq _ is subjected to equality constraints og real and
reactive power balance equations. For all buses except buses i and j between which the
UPFC device is connected, as
1
[ cos( ) sin( )]Nb
l gl dl l m lm l m lm l m
m
P P P V V G B =
= = + (2.4)
1
[ sin( ) cos( )]Nb
l gl dl l m lm l m lm l m
m
Q Q Q V V G B =
= = for l=1,2,.. bN ;but l i , j (2.5)
For buses i and j only, the equality constraints can be written as
_
1
[ cos( ) sin( )]Nb
i gi di i m im i m im i m i s
m
P P P V V G B P =
= = + (2.6)
_
1
[ sin( ) cos( )]Nb
i gi di i m im i m im i m i s
m
Q Q Q V V G B Q =
= = (2.7)
_
1
[ cos( ) sin( )]Nb
j gj dj j m jm j m jm j m j s
m
P P P V V G B P =
= = + (2.8)
_
1
[ sin( ) cos( )]Nb
j gj dj j m jm j m jm j m j s
m
Q Q Q V V G B Q =
= = (2.9)
2.2.3 The inequality constraints
While solving the OPF problem with objective function and equality constraints it is
often observed that the variables used to exceed their limits. thats why an inequality
constraints for the respective variables are included in the OPF to keep the variables
within their specified predefined limits.
8/13/2019 Acc. No. DC 59
16/67
8
In general the inequality constraints can be written as
( , , ) 0g x u p > (2.10)
where
state vector V, , DV , D , qI
u control parameters giP , giQ
p fixed parameters diP , diQ
2.2.3.1 Real power generation limit
This constitutes the upper and lower limits of real power llimit of generators
min maxgi gi giP P P , i =1, 2, 3.. g (2.11)
where mingiP and maxgiP are the minimum and maximum limits of real power
generation at bus- i respectively.
2.2.3.2 Reactive power generation limit
This constitutes the upper and lower limits of reactive power limit of generators
min maxgi gi giQ Q Q , i =1, 2, 3.. q (2.12)
where mingiQ and maxgiQ are the minimum and maximum limits of real power
generation at bus- i respectively.
2.2.3.3 Voltage Limit
This constitutes the uppermax
iV and lowermin
iV limits on the bus voltage magnitudemin maxi i iV V V i =1, 2, 3.. bN (2.13)
8/13/2019 Acc. No. DC 59
17/67
9
2.2.3.4 Line flow limit
This constraint signifies the maximum power flow is a transmission line and are usually
based on thermal and dynamic stability considerations, If maxliP is the maximum active
power flow in line-i and liP is the active power flow at any time of that particular line,then this can be written as
maxli liP P i =1, 2, 3 lN (2.14)
2.2.3.5 UPFC parameter limits
If we include some FACTS device (UPFC in this case) in between bus- i and bus- j the
device has some inequality constraints due to its own parameters like voltage magnitude
( )DV and phase angle ( )D of the series voltage source of it. Along with these two limitsthe reactive power component of shunt current ( )qI should also be less than its rating.
Mathematically, it can be written as
( ) max0 D DV V (2.15)
( ) max0 D D (2.16)
and ( )min maxq q qI I I (2.17)
2.3 Comparative study of different solution techniques for the
optimal power flow
There are various methods for solving the optimal power flow problem. Some most
common methods are described below:
2.3.1 Newtons Method
This method is used to to speed up the convergence [14]. But at the same time handling
inequality constraints is very difficult in this method. Inequality constraints must be
handled by some additional means in terms of adding a constraint penalty function to
8/13/2019 Acc. No. DC 59
18/67
10
the objective function. Furthermore the matrix equation for this method is extremely
sparse and requires special sparsity logic as the size of the Hessian matrix can be very
large.
2.3.2 Gradient Method
Gradient method is easy to compute. It requires only the first order derivative of the
Lagrangian function with respect to the state vector and control variables. It has the
difficulty in determining the step size because small step size will give slow convergence
whereas larger step size will make the system oscillatory. Is also has the problem for
solving with inequality constraints.
2.3.3 Lambda iteration method
[B] matrix is developed[14] to represent the losses of the system. Also beside this penalty
factors may be calculated outside by the power flow.
2.3.4 Linear Programming (LP) method
The difficulty of handling the inequality constraints is easily overcome in this method as
this method is very adaptive in handling inequality constraints [14], as long as the
problem to be solved is such that it can be linearized without loss of accuracy.
2.3.5 Interior Point (IP) method
It is comparatively a new solution algorithm [16] derived from the linear programming
problems that did not solve for the optimal solution by following a series of points that
were on the constrained boundary but, rather followed a path through the interior of the
constraints [15] directly toward the optimal solution on the constrained boundary. This
load flow solution technique is much faster than the conventional Linear programming
algorithm.
8/13/2019 Acc. No. DC 59
19/67
11
2.3.6 Genetic Algorithm (GA) method
It is mainly used in large scale systems for solving the economic dispatch problem. It is a
new type of encoding method in which a set of chromosome [15] contains only an
encoding of the normalized system incremental costs. Genetic algorithm is integrated
with conventional OPF to select the best control parameters to minimize the total
generation fuel cost and keep the line flows within permissible limits. It is faster than
lambda iteration method in large systems.
2.3.7 Evolutionary Programming (EP) method
It is a genetic population based metaheuristic [15] optimization algorithm. In this method
fitness function converges smoothly without any oscillations.
2.3.8 Particle Swarm Optimization (PSO) method
This method is inspired by the social behavior and movement dynamics of insects, birds
and fish. It is very simple method to implement. It is derivative free. Another advantage
of this method is that it has very few algorithm parameters [17]. PSO is an efficient
global optimizer for continuous variable problems and can accommodate constraints by
using a penalty method.
8/13/2019 Acc. No. DC 59
20/67
12
Chapter 3: FLEXIBLE AC TRANSMISSION SYSTEM
3.1 About FACTS
Most of the worlds electric power supply systems are widely interconnected for
economic reasons, to reduce the cost of electricity and to improve reliability of power
supply. The purpose of transmission network is to pool power plant and load centres in
order to minimize the total generation capacity and fuel cost. On the other hand, as the
power transfers grow, the power system becomes increasingly more complex to operate
and the system can become less secure due to the probability of major outages. As a
result full potential of transmission interconnection cannot be envisaged. In modern day,
greater demands on the transmission network and the most importantly the introduction
of deregulated environment, a tendency towards less security and reduced quality of
supply is evoked. A flexible alternating current transmission system (FACTS) is a
technology is essential to fulfill all these drawbacks mostly. It is a system composed of
static equipment used for the AC transmission of electric energy. It is meant to enhance
the controllability and increase the power transfer capability of the network. It is first
proposed by Dr. N. Hingorani.
3.2 Classification of FACTS
In broader sense FACTS controller can be classified into three categories:
1) Shunt controllers
2) Series controllers
3) Combined shunt-series controllers
8/13/2019 Acc. No. DC 59
21/67
13
3.2.1 Shunt controller
3.2.1.1 Shunt compensation
Shunt controller provides the shunt compensation [18] of an AC network. As the name
suggests it is connected in shunt (or parallel) to the transmission line. It works as acontrollable current source. It may have variable impedance. It injects current into the
system at the point of connection. As long as the injected current is in phase quadrature
with the line voltage, the shunt controller only supplies or consumes variable reactive
power.
Shunt compensation is of two types
Shunt capacitive compensation
This method is used to improve the power factor. Whenever an inductive load is
connected to the transmission line, power factor lags because of lagging load current.
To compensate, a shunt capacitor is connected which draws current leading the
source voltage. The net result is improvement in power factor.
Fig. 3.1: Shunt compensation circuit and phasor diagram
8/13/2019 Acc. No. DC 59
22/67
14
Shunt inductive compensation
This method is used either when charging the transmission line, or, when there is very
low load at the receiving end. Due to very low, or no load , very low current flows
through the transmission line. Shunt capacitance in the transmission line causes
voltage amplification (Ferranti Effect). The receiving end voltage may become
double the sending end voltage (generally in case of very long transmission lines). To
compensate, shunt inductors are connected across the transmission line.
3.2.1.2 Types of shunt controllers
i. Static synchronous compensator (STATCOM):It is previously known as static
condenser (STATCOM). It is a static synchronous generator operated as a shunt-
connected static var compensator whose capacitive or inductive output current can
be controlled independent of the ac system voltage. It is based on a power
electronics voltage-source converter and can act as either a source or sink of
reactive AC power to an electricity network. If connected to a source of power it
can also provide active AC power.
Fig. 3.2(a) Fig. 3.2(b)
Fig 3.2: STATCOM controller (a) voltage source converter based
(b) current source converter based
8/13/2019 Acc. No. DC 59
23/67
15
ii. Static var compensator (SVC): It is a shunt connected static var generator or
absorber whose output is adjusted to exchange capacitive or inductive current so
as to maintain or control specific parameters of the power system.
Some most common types of SVCs are as follows:
a. Thyristor controlled reactor (TCR): It is connected in series with a
bidirectional thyristor valve[19]. The thyristor valve is phase-controlled.
Equivalent reactance is varied continuously. Its effective reactance is
varied in continuous manner by partial conduction control of the thyristor
valve.
Fig. 3.3: Thyristor controlled reactor
b. Thyristor-switched reactor (TSR): Same as TCR but thyristor is either in
zero- or full- conduction [19]. Equivalent reactance is varied in stepwise
manner. It,s effective reactance is varied in stepwise manner by full or
zero conduction operation of thyristor valve.
c. Thyristor-switched capacitor (TSC):A capacitor is connected in series with
a bidirectional thyristor valve [19]. Thyristor is either in zero- or full-
conduction. Equivalent reactance is varied in stepwise manner.
8/13/2019 Acc. No. DC 59
24/67
16
Fig.3.4: Thyristor switched capacitor
d. Mechanically-switched capacitor (MSC): capacitor is switched by circuit-
breaker. It aims at compensating steady state reactive power. It is switched
only a few times a day.
iii. Static Var Generator or absorber (SVG):It is a static electrical device capable
of drawing controlled[19] capacitive and/or inductive current from an electrical
power system and thereby generating or absorbing reactive power.
iv. Thyristor Controlled Braking Resistor(TCBR): A shunt-connected thyristor-
switched resistor[19], which is controlled to aid stabilization of a power system or
to minimize power acceleration os a generating unit during a disturbance.
3.2.2 Series controller
3.2.2.1 Series compensation
In series compensation, the FACTS is connected in series with the power system. It
works as a controllable voltage source [18]. Series inductance occurs in long transmission
lines, and when a large current flow causes a large voltage drop. To compensate, series
8/13/2019 Acc. No. DC 59
25/67
17
capacitors are connected. As long as the voltage is in phase quadrature with the line
current, the series controller only supplies or consumes variable reactive power.
Fig.3.5: Series compensation and its phasor diagram
3.2.2.2 Types of series controllers
i. Static synchronous series compensator(SSSC):It is a static synchronous generator
operated without an external electric energy source as a series compensator whose
output voltage is in quadrature with, and controllable independently of, the line
current for the purpose of increasing or decreasing the overall reactive voltage
drop across the line and thereby controlling the transmitted electric power [19].
SSSC is one of the most important FACTS controller. SSSC can be based onvoltage-source converter or a current source converter without an extra energy
source SSSC can only inject a variable voltage which is 90 degrees leading or
lagging the current.
8/13/2019 Acc. No. DC 59
26/67
18
Fig. 3.6: Static synchronous series compensator
ii. Thyristor-controlled series capacitor (TCSC): It is a series capacitor bank is
shunted by a thyristor-controlled reactor in order to provide smoothly variable
series capacitive reactance [19]. It is based on the thyristors without gate turn-off
capability. TCSC may be a single, large unit, or may consist of several equal ordifferent sized smaller capacitors in order to achieve a superior performance.
8/13/2019 Acc. No. DC 59
27/67
19
Fig. 3.7: Thyristor controlled series compensator
iii. Thyristor-controlled series reactor (TCSR): In this type of controller a series
reactor bank is shunted by a thyristor-controlled reactor[19]. Like TCSC, TCSR
may also be a single large unit or several smaller series units.
Fig 3.8: Thyristor controlled series reactor
iv. Interline power flow controller (IPFC): A combination of two or more static
synchronous series compensators (SSSC) which are coupled via a common dc
8/13/2019 Acc. No. DC 59
28/67
20
link to take part in bidirectional flow of real power between[19] the ac terminals
of the SSSCs, and are controlled to provide independent reactive compensation
for the adjustment of real power flow in each line and maintain the desired
distribution of reactive power flow among the lines.
Fig.3.9: Interline power flow controller
v. Thyristor-switched series reactor (TSSR): A series reactor[19] bank is shunted by
a thyristor-switched reactor in order to provide a stepwise control of series
inductive reactance.
8/13/2019 Acc. No. DC 59
29/67
21
Fig. 3.10 Thyristor-switched series reactor
3.2.3 Combined shunt-series controllers
This type of controllers mainly consist of both shunt and series type controllers. Most
important controller under this category is unified power flow controller (UPFC).
Types of combined shunt-series controllers
i. Unified power flow controller (UPFC): It is a combination of static synchronous
compensator (STATCOM-shunt type) and static series compensator (SSSC) [19].
This two controllers are coupled via a common dc-link to allow a bidirectional
flow of real power between the series and shunt output terminal of SSSC and
STATCOM reapectively. By injecting angularly unconstrained series voltage,
UPFC is able to control, selectively, the transmission line voltage, impedance and
phase angle or alternatively, the real and reactive power flow in the line. It also
independently helps to control the shunt reactive compensation.
Fig. 3.11: Unified power flow controller
There are some other types of controllers also which does not belong to these three
main categories mentioned above. Some of them are, Thyristor Control Voltage
Limiter (TCVL), Thyristor Controlled Voltage Regulator (TCVR) etc.
8/13/2019 Acc. No. DC 59
30/67
22
3.3 Utility of FACTS
I. Improve power transmission capability.
II. Improved system stability and availability.
III. Improved power quality for sensitive industries.IV. Minimized environmental impact.
V. Minimized transmission losses.
3.4 Maintenance of FACTS
Compared to shunt capacitors, reactors and transformers, the maintenance of FACTS
devices are found to be lot easier. No special training or guideline is necessary to perform
a maintenance operation on FACTS devices. The amount of maintain ace ranges from150 to 250 man-hours per year and depends upon the size of the installation and local
ambient condition.
8/13/2019 Acc. No. DC 59
31/67
23
Chapter 4: UNIFIED POWER FLOW CONTROLLER
4.1 About Unified Power Flow Controller
The Unified Power Flow Controller (UPFC) concept was first proposed by Gyugyi [22]
in 1991. Unified Power Flow controller is a novel real time power flow controlling
device. It provides full dynamic control of transmission parameters, voltage, line
impedance and phase angle by fulfilling multiple functions of power flow like reactive
shunt compensation, series compensation and phase shifting. In other words it can be said
that both the real and reactive power flow in a line is controlled independently by this
device. Thus by controlling the line power flow UPFC satisfies the load demand and
other operating conditions. With suitable electronic controls, the UPFC can cause the
series-injected voltage vector to vary rapidly and continuously in magnitude and/or phase
angle as desired. Thus it simultaneously controls the wide range of variation of active and
reactive power as well as also has the capability to transition rapidly from one such
achievable point to any other.
As the need for flexible and fast power flow controllers, such as the UPFC, is expected to
grow in the future due to the changes in the electricity markets, there is a corresponding
need for the reliable and realistic models of these controllers to investigate the impact of
them on the performance of the power system.
4.2 Structures and operations of UPFC
UPFC can be categorized under new generation of FACTS device which combines the
features of two old FACTS devices, the Static Synchronous Compensator (STATCOM)
and the Static Synchronous Series Compensator (SSSC). In practice these two devices are
two voltage source converters connected respectively in parallel with the transmissionline through a shunt connected transformer and in series with the transmission line
through a series connected transformer. The other terminals of both the converters are
connected to each other through a common dc link including a storage capacitor. This
type of arrangement functions as an ac-to-ac power converter in which the real power can
freely in either direction between the ac terminals of the two converters, and each
8/13/2019 Acc. No. DC 59
32/67
24
converter can independently generate or absorb reactive power at its own output ac
terminal.
Fig.4.1: Equivalent circuit of
STATCOM
Fig. 4.2: Equivalent circuit of SSSC
8/13/2019 Acc. No. DC 59
33/67
25
The shunt converter is primarily used to provide active power demand of the series
converter through the common dc link. Shunt converter can also provide independent
shunt reactive compensation for the line by generating or absorbing reactive power when
desired. The series converter provides the main function of the UPFC by injecting a
voltage by controllable magnitude and phase angle in series with the line via the insertion
transformer. The injected voltage acts essentially as a synchronous ac voltage source. The
transmission line current flows through this voltage source resulting in reactive and real
power exchange between it and the ac system. The reactive power exchanged at the ac
terminal of the series insertion transformer is generated internally by the converter. The
real power exchanged at the ac terminal is converted into dc power which appears at the
dc link as a positive or negative real power demand.
The basic function of shunt converter is to supply or absorb the real power demanded by
the series converter at the common dc link to support the real power exchange resulting
from the series voltage injection [19]. This dc link power demand of series converter is
converted back to ac by the shunt converter and coupled to the transmission line bus via a
shunt connected transformer. It is important to note that whereas there is a closed direct
path for the real power negotiated by the action of series voltage injection through shunt
and series converters back to the line, the corresponding reactive power exchanged is
supplied or absorbed locally by series converter and therefore does not have to be
transmitted by the line. Thus, shunt converter can be operated at a unity power factor or
be controlled to have a reactive power exchange with the line independent of the reactive
power exchanged by series converter. Most certainly there can be no reactive power flow
through the UPFC dc link.
4.3 Equivalent Circuit of UPFC [20]
As said earlier UPFC is a combination of both STATCOM and SSSC. It has both series
and shunt voltage sources as well as impedance. The equivalent circuit of STATCOM
and SSSC is shown in the Fig.4.1 and Fig. 4.2 respectively. In Fig.4.3 the equivalent
circuit of UPFC is shown.
8/13/2019 Acc. No. DC 59
34/67
26
Fig. 4.3: Equivalent circuit of UPFC
The voltage vector of series converter is se se seV V = and for shunt converter it is
sh sh shV V = .Bus voltage vector of thi bus is i i iV V = and for thj it is j j jV V = .
Active power exchange between the two converters will be
* *Re( ) 0sh sh se jiPE V I V I= =
The bus voltage control constraint is 0specified
i iV V =
The two equivalent voltage injection binding constraint is as follows:
min maxse se seV V V
min maxsh sh shV V V
min maxse se se
min maxsh sh sh
8/13/2019 Acc. No. DC 59
35/67
27
4.4 Modeling of UPFC [12]
The UPFC model is very helpful in understanding the impact of the UPFC on the power
system in the steady state. The injection model also can easily be incorporated in the
steady state power flow model. Since the series voltage source converter does the mainfunction of the UPFC, it is appropriate to discuss the modeling of a series voltage source
converter. To analyze the UPFC injection it is important to note that the series converter
is used to generate a voltage source at the fundamental frequency with variable amplitude
0 maxD DV V and phase angle 0 2D .
The equivalent circuit model of UPFC is shown in the fig 4.4. It has three parameters
namely inserted voltage magnitude and phase angle ( DV , D ) and the magnitude of the
reactive power component of shunt current qI . The device is connected between two
nodes i andj . The buses situated in these two nodes have voltage magnitudes of iVfor
thi bus and jV for the thj bus. The transmission line connected between these two buses
is l (say).The transmission line has an impedance ij ij ijz r jx= + where ijr is theresistance of the transmission line and ijx is the reactance of that line. The total line
charging B is equally divided in two parts between the transmission line and each part is
known as half line charging of transmission line.
Fig.4.4: Equivalent model of UPFC
8/13/2019 Acc. No. DC 59
36/67
28
From the UPFC vector diagram the mathematical formulation from the above diagram
can be written as:
'
i i DV V V= + (4.1)( ) ( ) / 2q iArg I Arg V = (4.2)
Because of the voltage vector can be leading or lagging in nature with respect to the
series transformer current vector.
The voltage vector at bus i and the current vector for the shunt converter DI are in phase
so that,
( ) ( )D irg I Arg V = , (4.3)
where,
*'Re[ ]D i
D
i
V II
V= (4.4)
Now apparent power flows from bus i to bus j will be,
*'
* ' * ' *Re[ ]( /2 ) ( /2 )D i
ij ij ij i ij i D q i i i q iV I
S P jQ VI V jViB I I I V jVB I I Vi
= + = = + + + = + + + (4.5)
and apparent power flows from bus j to bus iwill be,
* *' *( / 2 )ji ji ji j ji j ji j j iS P jQ V I V I V jV B I = + = = = (4.6)
Separating the real part and imaginary part from both left and right hand side of the
equation_ and comparing, we get the active and reactive power flow of the line having
UPFC.
The active power flow from thi bus to thj bus for the line having UPFC is,
8/13/2019 Acc. No. DC 59
37/67
29
2 2( ) ( ) 2 cos( )ij ij i D ij i D ij D iP real S V V g V V g = = + + (4.7)
[ cos( ) sin( )] ( cos sin )j D ij D j D j i j ij ij ij ijV V g bij V V g b + + (4.8)
The reactive power flow from thi bus to thj bus for the line having UPFC is,
2( ) ( / 2)ij ij i q i ijQ imag S V I V b B= = +
[ sin( ) ( / 2) cos( )]i D ij D i ij D iV V g b B + + (4.9)
The active power flow from thj bus to thi bus for the line having UPFC is,
2( ) [ cos( ) sin( )]ji ji j ij j D ij D ij D iP real S V g V V g j b = =
( sin cos )i j ij ij ij ijV V g b (4.10)
The reactive power flow from thj bus to thi bus for the line having UPFC is,
2( ) ( / 2) ( sin( ) cos( ))ji ji j ij j D ij D j ij D iQ imag S V b B V V g b = = + + +
(( sin cos )j ij ij ij ijV V g b + + (4.11)
Where, ij i j =
The injected equivalent circuit from the principle of basic circuit theory can be obtained
as given below:
Fig.4.5: Injection model of UPFC
8/13/2019 Acc. No. DC 59
38/67
30
The injected active power at bus i , _i sP for the UPFC line l is,
2_ 2 cos( ) [ cos( ) sin( )]s D ij i D ij D i j D ij D j ij D jP V g VV g VV g b = + + (4.12)
The injected reactive power at bus i , _i sQ , for the UPFC line l is,
_ [ sin( ) ( / 2)cos( )]s i q i D ij D i ij D iQ V I V V g b B = + + + (4.13)
The injected active power at bus j , _j sP ,for the UPFC line l is,
_ [ cos( ) sin( )]j s j D ij D j ij D jP V V g b = (4.14)
The injected reactive power at bus , _j sQ ,for the UPFC line l is,
_ [ sin( ) sin( )]j s j D ij D j ij D jQ V V g b = + (4.15)
4.5 Location of UPFC[12]
4.5.1 Contingency Selection and Performance Index
For consistent service, power system must remain intact and be able to endure a wide
variety of disturbances. It should operate in normal and secured condition. Therefore, it is
important that the system to be designed and operated so that the more possible
contingencies can be sustained with no loss of load. Operating conditions of power
system can be determined if the network model and complex phasor voltages at every
system bus is known.If all the loads in the system can be supplied power without
violation of any operational constrains, then the system is in normal state. Examples of
these operational constrains include the limits on the transmission line flow, as well as
upper and lower (i.e. limits) on bus voltage magnitudes.
8/13/2019 Acc. No. DC 59
39/67
31
It should be noted that, line or generation outage may cause flow or voltages to fall
outside limits. The contingency analyses (CA) are used to predict the effect of these
outages. The state estimators solutions are used to perform contingency analysis in
power systems.
We would like to get some measure as to how much a particular outage might affect the
power system. The idea of a performance index (PI) seems to fulfill this need. The
definition for the overload performance index is as follows:
max1
22
Nlm lk
lkm
w PPI n
n P=
= (4.16)
Where lkP is the real power flow and maxlkP is the rated capacity of line-k,n is the
exponent, and mw is a nonnegative weighting coefficient that may be used to reflect the
importance of the lines. lis the total number of lines in the network.
Various techniques have been tried to obtain the value of PIwhen a branch is taken out.
These calculations can be made exactly if n=1, that is, a table of PI values, one for
each line in the network can be calculated quite quickly. However when n=1, the PI
does not snap from near zero to near infinity as the branch exceeds its limit. Instead, it
rises as a quadratic function. A line that is just below its limit contributes to PIalmost
equal to one that is just below their limit. Thus the PIs ability to distinguish or detect
bad cases is limited when n=1.
Using the second order performance indices in contingency selection algorithm can be
suffered from the masking effects. The lack of discrimination, in which the performance
index for a case with many small violations may be comparable in value to the index for
a case with one huge violation, is called the masking effect. The masking effect can be
minimized by choosing higher values of n (>1). In this case it is taken as 2 and mw istaken as1.0 .
In a line of networks there are some lines which are found to be weaker than the other
lines in terms of line power flow and injected bus power. We have to include the device
in that weaker line (say l ) in between 2 buses (say i andj ) after calculating the
8/13/2019 Acc. No. DC 59
40/67
32
sensitivities for each UPFC parameters. Sensitivity matrix helps to find the weakest line
among the network of lines. Performance index sensitivities factors are calculated by
partially differentiate the performance index with respect to each of the UPFC control
parameters ( DV , D , q ) and can be defined as
1
0
l
D VD
PIc
V =
=
(4.17)
2
0
l
D DD
PIc
V
=
=
(4.18)
3
0
l
q Iq
PIcI =
= (4.19)
where 1lc , 2lc and 3lc arePIsensitivity with respect to UPFC parameters l( DV , D
and q ) respectively connected between bus i and bus j . Using Equation_, we get
4
3
max1
1Nl
lkk lk
l lk l k
PI Pw PP R=
= (4.20)
The real power flow in line-k ( lkP ) can be represented in terms of real power injections
using dc power flow equations wheres is the slack or reference bus, as
1
_1
Nbkn n
nn slk
Nbkn n j sn
n s
S PP
S P P
=
=
=
+
(4.21)for k = l
for k l
8/13/2019 Acc. No. DC 59
41/67
33
Where knS is the knthelement of matrix [ ]S that relates line flow with power injections
at the buses without UPFC, and bN is the number of buses in the system. _j sP ,
therefore, is the additional power flow, at bus-j , in the line containing UPFC, due to the
presence of the device.Using equation 4.20 and 4.21, the following relationship can be obtained
_ _
_ _ _
i s j ski kj
l llk
l i s j s j ski kj
l l l
P PS S
R RP
R P P PS S
R R R
+ = + +
(4.22)
where , ,l D D qR V I= .
Now if we put these three control parameters one by one in equation 4.22, we get the the
partial differentiation of lkP with respect to the UPFC control parameters.
The partial differentiation of _i sP and _j sP with respect to each control parameters can
be evaluated distinctly as follows
_
0
2 cos( ) [ cos( ) sin( )]D
i si ij D i ij D ij D j
D V
PV g Vj g j b
V
=
= + +
(4.23)
_
0
2 sin( ) ( sin cos )
D
i si ij j ij j ij j
D D
PV g Vj g b
V
=
= + + (4.24)
_
0
0i s
qIq
P
I =
= (4.25)
_
0
( cos sin )D
j sj ij j ij j
D V
PV g b
V
=
= + (4.26)
for k l
for k = l
8/13/2019 Acc. No. DC 59
42/67
34
_
0
( sin cos )D
j sj ij j ij j
D
PV g b
V
=
= (4.27)
_
0
0j sq
Iq
PI =
= (4.28)
Thus the sensitivity factors can be obtained from equation 4.23 to 4.28. In this case
equation 4.25 and 4.28 the partial differentiation of injected bus power with qI gives
zero value. It suggests that the sensitivities are calculated for DV and D only.
8/13/2019 Acc. No. DC 59
43/67
35
Chapter 5: GRADIENT METHOD
5.1 Problem formulation
The objective function is to be minimized the difference of the operational cost for the
active power of pool generator to the pool load.
The optimization problem can be restated as
min ( , , )F x u pu
(5.1)
Subject to equality constraints( , , ) 0g x u p = (5.2)
To solve the optimization problem, we define Lagrange functions as
( , , ) ( , , ) ( , , )TL x u p F x u p g x u p= + (5.3)
where is the vector of Lagrangian multipliers [21] of the same dimensionas ( , , )g x u p .
The necessary conditions to minimize the unconstrained Lagrangian function are
0
TL F g
x x x
= + = (5.4)
0
TL F g
u u u
= + = (5.5)
( , , ) 0L
g x u pu
= =
(5.6)
8/13/2019 Acc. No. DC 59
44/67
36
Equations 5.4, 5.5 and 5.6 are nonlinear algebraic equations and can only be solved
iteratively. A simple yet efficient iteration scheme, that can be employed, is the steepest
descent method (also called the gradient method). The basic technique is to adjust the
control vector u, so as to move from one feasible solution point (a set of values of x
which satisfies eq.5.6 for given u andp ; it indeed the load flow solution) in the direction
of negative gradient to a new feasible set of solution with lower value of objective
function.
5.2 Computational Procedure [21]
1) Make an initial guess for u, the control variables.
2) Find a feasible load flow solution by Newton-Raphson iterative method. The
method improves the solution as follows:
1r rx x+ = + (5.7)
3) Where x is obtained by soling the set of linear equations given below:
( , ) ( , )r rg
x y x g x yx
= (5.8)
1
( , ) ( , )r rg
x x y g x yx
=
(5.9)
4) The end result of Step 2 is a feasible solution of x and the Jacobian matrix,
5) Solve eq 5.4 for
1F
x
=
(5.10)
6) Put the values of obtained from eq. 5.10 to eq. 5.5 and compute the gradient
TF g
L u u = + (5.11)
7) If L equals are within prescribed tolerance, the minimum has been reached.
Otherwise:
8) Find a new set of control variables
new old u u u= + where u L = (5.12)
8/13/2019 Acc. No. DC 59
45/67
37
Here u is a step in negative direction of the gradient. The step size is adjusted by thepositive scalar .In this algorithm, the choice of is very critical. Too small a value of
guarantees the convergence, but slows down the rate of convergence. Too high a value
causes oscillations around the minimum.
5.3 Inequality constraints on control variables
Though in the previous discussion, the variables are assumed unconstrained, the
permissible values are, in fact, always constrained, i.e.
min maxu u u
e.g min maxgi gi giP P P These inequality constraints on control variables can be easily handled. If the correction
u in eq. 5.12 causes u to exceed one of the limits, u is set equal to the
corresponding limit, i.e.
max
min
i
i i
oldi i
u
newu u
u u
= +
After a control variables reaches any of the limits, its component in the gradient should
continue to be computer in lated iterations, as the variables may come within limits at
some later stage.
5.4 Inequality constraints on dependent variables
Often, the upper and lower limits on dependent variables are specified as:
min maxx x x e.g min maxi i iV V V
Such inequality constraints can be conveniently handles by the penalty function methods.
The objective function is augmented by penalties for inequality constraints violations.
If oldi iu u+ > maxiu
If oldi iu u+ < miniu
8/13/2019 Acc. No. DC 59
46/67
38
This forces the solution to lay sufficiently close to the constraint limits, when these limits
are violated. In this problem all iV are within the specified limit. So that no penalty
function has been included.
5.5 Lagrangian for solving the OPF in gradient method
The objective function is
( ) ( )G D
T i Pi j pj
i I j I
F C P B D
=
(5.13)
The equality constraints for i thbus are
_
1
[ cos( ) sin( )]Nb
i i m im i m im i m i s
m
P V V G B P =
+
(5.14)
and _
1
[ sin( ) cos( )]Nb
i i m im i m im i m i s
m
Q V V G B Q =
(5.15)
Hence the Lagrange function will be
( , ) ( ) ( )G D
i Pi j pj
i I j I
L P Q C P B D
=
( ) _1
[ cos( ) sin( )]Nb
i i m im i m im i m i s
i Nb m
p P V V G B P
=
+ +
( ) _1
[ sin( ) cos( )]Nb
i i i m im i m im i m i s
i Nb m
q Q V V G B Q =
+
(5.16)
8/13/2019 Acc. No. DC 59
47/67
39
where pi and qi are the Lagrange multipliers of respective equality
constraints. The Lagrange multiupliers for the real power equations of the load flow
are invariably positive; however, for reactive power, the multipliers can either be
positive or negative.
8/13/2019 Acc. No. DC 59
48/67
40
Chapter 6: SPOT PRICING
6.2 Introduction
The spot price or spot rate of a commodity, a security or a currency is the price that
is quoted for immediate (spot) settlement (payment and delivery). Spot settlement is
normally one or two business days from trade date. Spot rates are estimated via the
bootstrapping method, which uses prices of the securities currently trading in
market, The result is the spot curve, which exists for each of the various classes of
securities.
In modern world transmission open access has become an important issue on
deregulated electrical sector [13]. In a generation marketplace, the agents will
maximize their individual revenues not taking into account the social welfare. So
there should be a valid coordination between the generation marketplace and the
centralized or deregulated transmission open access. In a competitive market
environment, no participant can absolutely control the power system operation.
That is the existing spot price cannot be changed by adjusting the bids which mostly
matches a single participants marginal cost. Therefore the minimum power system
operation cost and the maximum participant benefit are reached at the same time ina real competitive market.
6.2 Power pools
Interchange of power between systems can be economically advantageous.
However, when a system is interconnected with many neighbors, the process of
setting up one transaction at a time with each neighbor can become very time
consuming and will rarely result in the optimum production cost [14]. To overcomethis burden, several utilities may form a power pool which incorporates a central
dispatch office. The power pool is administered from a central location that has
responsibility for setting up interchange between members. The pool members take
certain responsibilities to the pool operating office in return for greater economies
in operation.
8/13/2019 Acc. No. DC 59
49/67
41
6.2.1 Advantages of power pools
1) The certain advantages for centrally dispatched power pools are as follows:
2) Minimize operating costs (or maximize operating efficiency alternatively)
3) Perform a system-wide unit commitment.
4) Minimize the reserves being carried throughout the system.
5) Coordinate maintenance scheduling to minimize costs and maximize
reliability by sharing reserves during maintenance periods.
6) Maximize the benefits of emergency procedures.
6.2.2 Disadvantages of power pools
There are some disadvantages that should be included along with the advantages
like economic operation. Some of the disadvantageous factors are as follows:
1) The complexity of the pool agreement and the continuing costs of
supporting the interutility structure required to manage and administer thee
pool.
2) The operating and investment costs associated with the central dispatch
office and the needed communication and computation facilities.
3) The relinquishing of the right to engage in independent transactions outside
of the pool by the individual companies to the pool office and the
requirement that any outside transactions be priced on a split-saving basis
based on pool members costs.
4) The additional complexity that may result ion dealing with regularity
agencies if the pool operates in more than one state.
8/13/2019 Acc. No. DC 59
50/67
42
6.3 Spot price
For decades, power factor penalties have been used in providing reactive power
pricing. It has been shown that the practice of power factor penalties is unable to
provide accurate price signals to customers. Spot pricing means that electricityprices to the customer follow as closely as technically practical the real cost of
electricity at the time that it is produced and supplied. Most findings in real-time
pricing of reactive power are closely related to those of active power pricing. Spot
prices as defined are change according to power production units and transmission
lines in the power system. If total power demand is higher than participants offer,
spot price will increase [13]. Conversely, if total power demand is lower than
participants offer, spot price will decrease. All electrical power producers want to
run their units in the most productive operating conditions in every period.
Fig.6.1: power production-bid price characteristics
!imax
!i2
!i0
!i1
!imin
Pimin PimaxPi0
Ti1 Ti2Ti
8/13/2019 Acc. No. DC 59
51/67
43
As in Fig. 1, if the spot price for one participant is determined as optimum that
particular participant dose not want to buy or transact any power from other
participants. Participants will produce electrical energy for only their own
agreement. Participants only export power after fulfilling their own internal needs if
the spot price is higher than !i0 , the participant reduce its own local generation. As
shown in the graph with increase in power flow power cost increase too. Power
system must have extra supply for this lack of restriction of participants. If the
power systems have no extra supply, then spot price applications cannot apply
frequently.
6.4 Marginal cost
In purely economic point of view marginal cost can be defined as the cost of the
additional inputs needed to produce that output. More formally, the marginal cost is
the derivative of total production costs with respect to the level of output.
The prices for active powers at bus- i are actually the marginal cost associated with
the corresponding load flow equations when the OPF( with and without FACTS)
are solved as a nonlinear programming problem [12].
From the power system point of view, the active power marginal cost price at the
bus- i is defined by
i
di
PP
=
[total cost of providing electricity to all customers subject toConstraints]
i
i
d
LC
P
= =
where piC is the marginal cost price of active power at bus i and L is the
Lagrange function defined in eq.(5.16) for which the total cost to supply the
electrical energy for all consumers and subject to operation restrictions.
8/13/2019 Acc. No. DC 59
52/67
44
Chapter 7: RESULTS AND DISCUSSIONS
7.1 IEEE 30-bus test system
The proposed method has been tested on a IEEE 30-bus system for the base case
(without UPFC) and with incorporating UPFC. The single line diagram of a 30 bus
system is given in figA.1 and 2. The prices bid by generators are given in table A.1,
where P is in megawatts and cents is a monetary unit. Bus data is given in table A.2
and line data is given in table A.3.
7.2 Tabulated results
Table 7.1 to 7.4 shows the test results after the proposed method is implemented on
MATLAB 7.8 for IEEE 30 bus system and the computation is performed on a
computer having 2.80 GHz, core 2 duo processor and 2 GB RAM.
Table 7.1: Sensitivity table matrix for c1l
and c2l
Line
nos.
ith
bus jth
bus c1l
(withrespect to VD)
c2l
(withrespect to !D)
1 1 2 0.105400553705582 -0.0133720592871952
2 1 3 0.00133199832472405 -0.000177325849024417
3 2 4 -7.07350277184786e-07 5.97848915732095e-08
4 3 4 -5.92411347915431e-06 5.30658325775049e-07
5 2 5 -2.64755442531785e-05 3.09421014094045e-06
6 2 6 0 0
7 4 6 0 0
8 5 7 -6.77830371534241e-07 7.66349639648712e-08
9 6 7 -0.00564853278969574 0.000683726222919481
10 6 8 -0.115285393796341 0.0121133089179766
11 6 9 0 0
8/13/2019 Acc. No. DC 59
53/67
45
12 6 10 -0.000418200645620308 6.48355308725975e-05
13 9 11 0.00196413791901515 -7.02601044429364e-05
14 9 10 -0.00122302880608463 0.000225231891633056
15 4 12 -0.00024825225853467 3.97762834798397e-05
16 12 13 0.0864586908875991 -0.00692698291034724
17 12 14 -0.00082000115723229 0.000129868604021993
18 12 15 -0.0318824780904561 0.00526855828148936
19 12 16 -3.72830064390911e-05 5.44808465509381e-06
20 14 15 -1.01197858354723e-07 1.56359511392211e-08
21 16 17 -8.35586841618415e-06 1.23570331144695e-06
22 15 18 -.000102875012565942 1.71018303129115e-05
23 18 19 -2.11151486575580e-05 3.51021581055078e-06
24 19 20 -3.86353128575040e-06 3.51021581055078e-06
25 10 20 -0.000118208007108670 1.99877337651416e-05
26 10 17 -0.00407858966864019 0.000606189386310992
27 10 21 -0.451710876271081 0.0713922481669822
28 10 22 0 0
29 21 22 0 0
30 15 23 -4.92238355279217e-05 8.01072407001902e-06
31 22 24 -.000982100994548929 0.000164976633443186
32 23 24 -2.15948688895622e-06 3.55294032408022e-07
33 24 25 0 0
34 25 26 -4.93083082491196e-06 8.90526237374516e-07
35 25 27 0 0
36 28 27 0 0
37 27 29 -6.82699456110101e-05 1.37196248158477e-05
38 27 30 -0.00669484624381917 0.00150712030528960
39 29 30 -0.000272858780586663 5.83462425139716e-05
40 8 28 0 0
41 6 26 0 0
8/13/2019 Acc. No. DC 59
54/67
46
Table 7.2:Optimum generation schedule
Parameter Base Case (without UPFC) UPFC in line 27
Generator 1 123.58+j4.03 124.64-j26.3Generator 2 55.26-j14.42 54.24-j10.32
Generator 3 41.07-j4.35 40.02-j2.39
Generator 4 12.78+j18.30 11.2+j29.26
Generator 5 16.82-j39.20 15.76+j37.08
Generator 6 16.89 -j23.14 15.85+j27.03
VD(p.u) ------ 0.5
!D(degree) ------ 5.72
Iq(p.u) ------ 0.005
Generation Cost (cents/h) 510.3976 499.8153
8/13/2019 Acc. No. DC 59
55/67
47
Table 7.3:Voltage and phase angle computed without UPFC
Bus No. Voltage Magnitude (p.u) Phase angle (in degree)
1 1.0500 0
2 1.0338 -0.0388
3 1.0245 -0.0835
4 1.0181 -0.1000
5 1.0058 -0.1295
6 1.0140 -0.1192
7 1.0025 -0.1328
8 1.0230 -0.1272
9 1.0001 -0.1258
10 0.9728 -0.1844
11 1.0713 -0.0870
12 1.0040 -0.1690
13 1.0400 -0.1422
14 0.9807 -0.1868
15 0.9807 -0.1885
16 0.9831 -0.1806
17 0.9701 -0.1874
18 0.9650 -0.2008
19 0.9589 -0.2044
20 0.9616 -0.2005
21 0.9249 -0.1964
22 0.9643 -0.1890
23 0.9699 -0.1969
24 0.9643 -0.2014
25 0.9853 -0.2037
26 0.9671 -0.211627 1.0074 -0.1998
28 1.0090 -0.1283
29 0.9872 -0.2220
30 0.9755 -02379
8/13/2019 Acc. No. DC 59
56/67
48
Table 7.4: Voltage and phase angle computed with UPFC
Bus no. Voltage( in p.u) Phase angle (in degree)
1 1.05 0
2 1.0338 -0.03832
3 1.027001 -0.08334
4 1.021119 -0.09985
5 1.0058 -0.12856
6 1.017826 -0.11925
7 1.004823 -0.13247
8 1.023 -0.12618
9 1.006625 -0.12577
10 0.992189 -0.18266
11 1.0813 -0.08754
12 1.009206 -0.16608
13 1.04 -0.1394
14 0.993342 -0.18394
15 0.987963 -0.18633
16 0.994389 -0.17826
17 0.987228 -0.1853418 0.976651 -0.19845
19 0.973254 -0.20197
20 0.977158 -0.19824
21 0.975972 -0.19974
22 0.977524 -0.19802
23 0.976794 -0.19638
24 0.970804 -0.20322
25 0.99087 -0.20431
26 0.972701 -0.21204
27 1.012264 -0.1997
28 1.012097 -0.12819
29 0.992186 -0.22165
30 0.980574 -0.23741
8/13/2019 Acc. No. DC 59
57/67
49
7.3 Graphical results
The graph in fig. 7.1 and 7.2 shows the real power spot pricing tabulated with and
without UPFC for each load buses.
Fig. 7.1: Real power spot prices (cents/ MWhr) at load buses without UPFC
Real power spot price at load buses without UPFC
200202.5
205
207.5
210
212.5
215
217.5
220
222.5
225
227.5
230
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30
Bus number
Spotprices(cents/MWh)
Spot
prices
8/13/2019 Acc. No. DC 59
58/67
50
Fig. 7.1: Real power spot prices (cents/MWhr) at load buses with UPFC
Real power spot prices at load buses with UPFC at line-27
200
202.5
205
207.5
210212.5
215
217.5
220
222.5
225
227.5
230
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30
Bus number
Spotprices(cents/MWh)
Spot
prices
8/13/2019 Acc. No. DC 59
59/67
51
Chapter 8: CONCLUSION
8.1 ConclusionIn this paper real power spot price has been calculated with and without implementing the
FACTS device (UPFC). Here the OPF is solved in gradient method. Moreover a
sensitivity based approach has been used for finding a suitable location to place UPFC.
Test results obtained on test systems show that the new sensitivity factors could be
effectively used for placement in response to required objectives. The placement of a
UPFC in a particular line affects both the real power and reactive power prices. It can be
concluded that by incorporating UPFC in the OPF model, significant reduction occurs in
real power loss and generation cost.
8.2 Future Scope
Only real power pricing is dealt with in this paper. There are many approaches towards
the reactive power pricing has also been done in recent years and in future with
increasing demand of electric power and more competitive power market. The reactive
power pricing should play an important role beside real power pricing. By knowing the
bid price for the reactive power generation reactive power price can be determined after
formulating a corresponding OPF for the reactive power.
8/13/2019 Acc. No. DC 59
60/67
52
REFERENCES
[1]L.Gyugyi, T.Rietman , A.Edris, C. D. Schauda . S.L.Williams, The unified powerflow controller: A new approach to power transmission control, IEEE Transactions onPower Delivery, Vol. 10, No. 2, April 1995.
[2] Jenn- Huei Jeffrey Kuan, Optimal power flow with price elastic demand, Thesis
report ,dept. of Master of Science in Electrical Engineering, Massachusetts Institute ofTechnology, August 1996.
[3] J. Y. Choi, S.-H. Rim, and J.-K. Park, Optimal real time pricing of real and reactive
powers,IEEE Trans. Power System., vol. 3, no. 4, pp., 12261231, Nov. 1998.
[4] J. W. Marangon Lima and E. J. de Oliveira, The long-term impact of transmission
pricing,IEEE Trans. Power Syst., vol. 13, no. 4, pp.15141520, Nov. 1998.
[5] J. Y. Liu and Y. H. Song, Comparison studies of unified power flow controller with
static var compensators and phase shifters, Elect. Mach. Power Syst., vol. 27, pp. 237251, 1999.
[6]J. Y. Liu, Y. H. Song, and P. A. Mehta, Strategies for handling UPFC constraints in
the steady state power flow and voltage control,IEEE Trans. Power Syst., vol. 15, no. 2,pp. 566571, May 2000.
[7]S. C. Srivastava and R. K. Verma, Impact of FACTS devices on transmission pricing
in a de-regulated electricity market, in Proc. IEEE Int. Conf. Electric UtilityDeregulation Restructuring Power Technologies, London, U.K., Apr. 2000, pp. 642648.
[8] K. S. Verma, S. N. Singh, and H. O. Gupta, Optimal location of UPFC for
congestion management,Elect. Power Syst. Res., vol. 58, no. 2, pp. 8996, Jul. 2001.
[9]-----, FACTS device location for enhancement of total transfer capability, in Proc.IEEE Power Eng. Soc.Winter Meeting, vol. 2, Columbus, OH, pp. 522527, Jan. 28Feb.
1 2001.[10]-----,Location of UPFC for power systems security in deregulated environment,
inProc. Int. Conf. EAIT-2001. Kharagpur , West Bengal, Dec. 2001, pp. 149154.
[11] S. N. Singh, K. S. Verma , and H. O. Gupta, Optimal power flow control in openpower market using unified power flow controller, in Proc. IEEE Power Eng. Soc.
Summer Meeting, vol. 3, Vancouver, BC, Canada, Jul. 1519, 2001, pp. 16981703.
[12] K.S. Verma and H.O.Gupta, Impact on real and reactive power pricing in openpower market using unified power flow controller, Trans. On power systems, vol. 21,
no. 1, February 2006.
8/13/2019 Acc. No. DC 59
61/67
53
[13] Abdullah Urkmez, Determined spot price and economic dispatch in deregulatedpower systems, Mathematical and Computational Applications, Vol. 15, No. 1, pp. 25-
33, 2010.
[14] A. J. Wood and B. F. Wollenberg, Power Generation, Operation, and Control,
2nd edn. Wiley India (P) Ltd., New Delhi, 2007.
[15] K.S.Pandya, S.K.Joshi, A survey of optimal power flow methods, Journal of
Theoretical and Applied Information Technology.
[16] J.A. Momoh, J.Z. Zhu, Improved interior point method for OPF problem,IEEETransactions on Power Systems, Vol. 14, No. 3, August 1999.
[17] Jaco F. Schutte, The particles swarm optimization algorithm, EGM 6365 -
Structural Optimization, Fall 2005.
[18] www.wikipedia.com
[19] Hingorani N.G. and Gyugyi L., Understanding FACTS: concepts and technologyof flexible ac transmission systems.New York: IEEE Press; 1999.
[20] Xiao-Ping Zhang, Edmund Handschin, Transfer capability computation of powersystems with comprehensive modeling of FACTS controllers, 14thPSCC,Sevilla, Section 30.paper 2, page no. 1-4, 24-28 June, 2002.
[21] D. P. Kothari and J. S. Dhillon, Power System Optimization,Prentice Hall ofIndia Pvt. Ltd., New Delhi, 2006.
[22] L. Gyugyi, A unified power flow control concept for flexible AC transmissionsystems,Proc. Inst. Elect. Eng., pt. C, vol. 39, no. 4, pp. 323331, Jul. 1992.
[23]The IEEE 30bus test system available at:http://ee.washington.edu/research/pstca/pf30/pg_tca30bus.htm
http://www.wikipedia.com/http://ee.washington.edu/research/pstca/pf30/pg_tca30bus.htmhttp://ee.washington.edu/research/pstca/pf30/pg_tca30bus.htmhttp://www.wikipedia.com/8/13/2019 Acc. No. DC 59
62/67
54
NOMENCLATURE
iC Bid price of pool generator-i.
pi Active power of pool generator-i
jB Bid price of pool load-j
pj Active power of pool load-j
GI Set of pool generator buses
DI Set of pool load buses
DV Voltage magnitude of UPFC series controller
D Phase angle magnitude of UPFC series controller
qI Shunt current
gi Generated active power at bus-i
iQ Generated reactive power at bus-i
di Active power demand at bus-i
diQ Reactive power demand at bus-i
bN Total number of buseslN Total number of lines
qN Number of reactive power sources
iV Bus voltage magnitude at bus-i
i Phase angle at bus-i
mingiP Minimum active power generation limit at bus-i
maxgiP Maximum active power generation limit at bus-i
mingiQ Minimum reactive power generation limit at bus-i
maxgiQ Maximum reactive power generation limit at bus-i
8/13/2019 Acc. No. DC 59
63/67
55
APPENDIX
Table A.1:Generator data
Bus no. Pgmin(MW) Pgmax(MW)b(cent/MW-
hr) c(cent/MW2-hr)
1 50 200 2 0.00375
2 20 80 1.75 0.0175
5 15 50 1 0.0625
8 10 35 3.25 0.00834
11 10 30 3 0.025
13 12 40 3 0.025
8/13/2019 Acc. No. DC 59
64/67
56
Table A.2: IEEE 30 bus characteristics
BusNo.
Active powerdemand(MW)
Reactive powerdemand(MVAR)
Bus voltagemagnitude(in p.u)
Bus voltageangle
Yshunt
1 0 0 1.05 0 0
2 21.70 12.70 1.0338 0 0
3 2.40 1.20 1.0 0 0
4 7.60 1.60 1.1.00580 0 0
5 94.20 19.00 1.0 0 0
6 0 0 1.0 0 0
7 22.80 10.90 1.0230 0 0
8 30.00 30.00 1.0 0 09 0 0 1.0 0 0
10 11.9 2.00 1.0913 0 00
11 0 0 1.0883 0 0.19
12 11.2 7.50 1.10 0 0
13 0 0 1.0 0 0
14 6.20 1.60 1.0 0 0
15 8.20 2.50 1.0 0 0
16 3.50 1.80 1.0 0 0
17 9.00 5.80 1.0 0 0
18 3.20 0.90 1.0 0 0
19 9.50 3.40 1.0 0 0
20 2.20 0.70 1.0 0 0
21 34.3 11.20 1.0 0 0
22 0 0 1.0 0 0
23 3.20 1.60 1.0 0 0
24 8.70 6.70 1.0 0 0.04
25 0 0 1.0 0 0
26 3.50 2.30 1.0 0 0
27 0 0 1.0 0 0
28 0 0 1.0 0 0
29 2.40 0.90 1.0 0 0
30 10.60 1.90 1.0 0 0
8/13/2019 Acc. No. DC 59
65/67
8/13/2019 Acc. No. DC 59
66/67
58
Fig. A1:Single line diagram of IEEE 30-bus system [23]
8/13/2019 Acc. No. DC 59
67/67