Acc. No. DC 59

Embed Size (px)

Citation preview

  • 8/13/2019 Acc. No. DC 59

    1/67

    Real Power Spot Pricing using Unified Power Flow

    Controller

    Thesis submitted in partial ful fi llment of the requi rement for the Degree of

    Master of Power Engineer ing f rom the Faculty of Engineeri ng &Technology, Jadavpur University in the year 2010

    Submitted by

    ARNAB BHADURI

    Master of Power Engineering

    Regn. No. 104350 of 2008-2009

    Exam Roll No. M4POW10-09

    Under the guidance of

    Dr. Mousumi BasuDepartment of Power Engineering

    Jadavpur University

    Saltlake Campus

    Kolkata-700098

  • 8/13/2019 Acc. No. DC 59

    2/67

  • 8/13/2019 Acc. No. DC 59

    3/67

    Department of Power engineering

    Faculty of Engineering and Technology

    Jadavpur University

    The foregoing thesis, ent it led as Real power spot pricing using unified power f low

    controlleris hereby approved by the committee of final examination for evaluation of

    thesis as a creditable study of an engineering subject carried out and presented byArnab

    Bhaduri (Regn. No.104350 of 2008-2009; Exam Roll No. M4POW10-09) in a manner

    satisfactory t o warrant it s acceptance as a perquisite to the Degree of Master of Power

    Engineering. I t is understood that by this approval, the undersigned do not necessarily

    endorse or approve any statement made, opinion expressed or conclusion drawn therein,

    but approve the thesis only for t he purpose for which it is submitted.

    Committee of final examination for evaluation of thesis:

    -----------------------------

    -----------------------------

    ----------------------------

  • 8/13/2019 Acc. No. DC 59

    4/67

    Acknowledgement

    The author remembers the with gratitude the constant guidance, suggestions and

    encouragement forwarded by several respected persons and knows well that it is not

    possible to express his indebt ness for all those valuable assistances by writing some

    lines. Following conventions, he, therefore, acknowledges in this page, the assistance

    rendered by all the concerened persons, as a token of his gratitude.

    The author thankfully acknowledges the kind and persistent valuable suggestion, advice,

    guidance, help and encouragement from Dr. Mousumi Basu without whom this thesis

    would not have been a reality.

    The author is thankful to the head of Power Engineering department for his kind

    permission to carry out the project under Dr. Mousumi Basu.

    The author is likely to convey his gratitude to all teachers in ME course in the Power

    Engineering department of Jadavpur University for excellent teaching that helps to

    complete the project smoothly.

    The author would also like to express his sincere thanks to all his classmates specially

    Mr. Sanjay Chauhan who came with some valuable suggestions to make this thesis

    possible.

    Finally, the author wishes his profound gratitude to his parents, family members for

    providing constant encouragement throughout his thesis work.

    Arnab Bhaduri

  • 8/13/2019 Acc. No. DC 59

    5/67

    Abstract_______________________________________

    This thesis proposes real power spot price analysis using Unified Power Flow Controller.

    Real power spot price is analyzed and compared with the base case to the case after

    implementing the Unified Power Flow Controller. Optimal placement for Unified Power

    Flow Controller by analyzing the sensitivity for the UPFC parameters is also done in this

    thesis work. All the proposed methods and algorithms are tested on IEEE standard 30bus

    system for verification.

  • 8/13/2019 Acc. No. DC 59

    6/67

    Contents_______________________________________

    Subjects Page No.

    Chapter 1: INTRODUCTION

    1.1Introduction 1

    1.2Motivation behind this work 2

    1.3 Literature Survey 3

    1.3Overview 4

    Chapter 2: OPTIMAL POWER FLOW

    2.1 Optimal power flow problem 5

    2.2 Optimal power flow problem formulation 6

    2.2.1 The objective function 6

    2.2.2 The equality contstraints 6

    2.2.3 The inequality constraints 7

    2.2.3.1 Real power generation limit 8

    2.2.3.2 Reactive power generation limit 8

    2.2.3.3 Voltage limit 8

    2.2.3.4 Line flow limit 9

    2.2.3.5 UPFC parameters limit 9

    2.3 Comparative study of different solution techniques for the OPF 9

    2.3.1 Newtons Method 9

    2.3.2 Gradient method 10

    2.3.3 Lambda iteration method 10

  • 8/13/2019 Acc. No. DC 59

    7/67

    2.3.4 Linear Programming method 10

    2.3.5 Interior poinr method 10

    2.3.6 Genetic algorithm method 11

    2.3.7 PSO method 11

    Chapter 3: FLEXIBLE AC TRANSMISSION SYSTEM

    3.1 About FACTS 12

    3.2 Classification of FACTS 12

    3.2.1 Shunt controller 13

    3.2.1.1 Shunt controller 13

    3.2.1.2 Types 14

    3.2.2 Series Controller 16

    3.2.2.1 Series compensation 16

    3.2.2.2 Types 17

    3.3.3 Combined shunt-series controller 21

    3.3 Utility of FACTS 22

    3.4 Maintenance of FACTS 22

    Chapter 4: UNIFIED POWER FLOW CONTROLLER

    4.1 About Unified power flow controller 23

    4.2 Structures and operations of UPFC 24

    4.3 Equivalent circuit of UPFC 25

    4.4 Modeling of UPFC 27

    4.5 Location of UPFC 30

  • 8/13/2019 Acc. No. DC 59

    8/67

    Chapter 5: GRADIENT METHOD

    5.1 Problem formulation 35

    5.2 Computational procedure 36

    5.3 Inequality constraints on control variables 37

    5.4 Inequality constraints on dependent variables 37

    5.5 Lagrangian for solving OPF in gradient method 38

    Chapter 6: SPOT PRICING

    6.1 Introduction 39

    6.2 Power pools 39

    6.2.1 Advantages 40

    6.2.2 Disadvantages 40

    6.3 Spot price 41

    6.4 Marginal cost 42

    Chapter 7: RESULTS AND DISCUSSIONS

    7.1 IEEE 30- bus test system 43

    7.2 Tabulated results 43

    7.3 Graphical results 49

    Chapter 8: CONCLUSIONS

    8.1 Conclusion 51

    8.2 Future scope 51

    References 52

    Nomenclature 54

    Appendix 55

  • 8/13/2019 Acc. No. DC 59

    9/67

    1

    Chapter 1: INTRODUCTION

    1.1 IntroductionElectrical engineering is an essential ingredient for the industrial and all-round

    development of any country. It is a one of the most desirable form of energy, since it can

    be generated centrally in bulk and transmitted economically over long distances. The

    system which generates controls, transmits and finally distributes electrical energy to the

    consumers is called an electrical power system. Electricity cannot be stored economically

    and the electric utility need some control over the load or power demand at any time.

    This system therefore should be capable of matching the output from the generators to thedemand at any time at the specified voltage and frequency.

    The electrical power must be transmitted in steady-state mode under their normal

    operating conditions. In accordance to this, three major problems encountered in steady-

    state mode of operations are: 1) load flow problem, 2) optimal load dispatch problem and

    3) systems control problem. The aim of power flow calculations is to determine the

    steady-state operating characteristics of a power generation or transmission system for a

    given set of bus-bar loads. Active power generations are specified according to economic

    dispatching. In system operation and planning, the voltages and powers are kept within

    certain limits. The power system networks of today are highly complicated consisting of

    hundreds of buses and transmission links. Thus the load flow study involves extensive

    calculations.

    With increasing pace of power system restructuring, transmission systems are being

    required to provide increased power transfer capability and at the same it is also required

    to accommodate a much wider range of possible generation patterns. Power systems,

    throughout the world, have been forced to operate in almost full capacities due to the

    environmental and/or economical constraints to build new generation centers and

    transmission lines. If the power flow limit exceeds a certain permissible limit the system

    is said to be congested. There is an interest in better utilization of available power system

    capacities by installing new devices such as flexible ac transmission system (FACTS).

  • 8/13/2019 Acc. No. DC 59

    10/67

    2

    These devices are useful in modern power system operation to reduce the flows in

    heavily loaded lines, resulting in increased load ability, low system loss, improved

    stability of the network, reduced production cost, and fulfilled contractual requirement by

    controlling the power flows in the network. If there is no congestion, the optimal location

    of FACTS devices can be decided on the basis of real power flow performance index

    ( )PI has been used due to security and stability reasons. A definite methodology has

    been used to locate the FACTS device (UPFC) for congestion management in the

    deregulated power sector and in doing that a nonlinear optimization problem has been

    formulated and evaluated by some certain power flow solution algorithm (Gradient

    Method) with and without incorporating FACTS device (UPFC) to see the impact on

    transmission real power spot pricing.

    1.2 Motivation behind this work

    In modern days deregulated power system environment major organizational and

    structural changes has been observed. In view of this transmission pricing is an important

    issue. For a participant of electric power system two things need to be fully examined,

    firstly the relationship between competition requirements and the market structures and

    secondly optimal operation of supply and demand in terms of social welfare. In this

    respect many researchers used different methods for determining spot prices in

    deregulated power systems. In competitive electricity markets, to supply deregulation, it

    is important that both the producers and consumers reach an optimum goal so that both of

    them get benefited. In this respect, spot price applications and participants bids must be

    considered simultaneously in deregulated power market operations. FACTS device plays

    an important role for improving the power pricing.

    All these aspects related to deregulated electricity market and modern economic scenario

    lead to this thesis work. In this work spot prices are calculated at different load buses

    after formulating an optimal power flow problem. Moreover optimal placement of facts

    device in a line of network also has been considered in this work to compare the spot

    prices at different load buses for base case as well as with implementing the FACTS

    device.

  • 8/13/2019 Acc. No. DC 59

    11/67

    3

    1.3 Literature survey

    In 1995 Gyugyi, Rietman, Edris, Schauder, Torgerson, Williams [1] show the unique

    capability of a UPFC in multiple line compensation by controlling both the transmitted

    real power power and, independently, the reactive power flows at the sending-end and the

    receiving end of the transmission line.

    In 1996, Jenn-Huei Jeffrey Kuan [2] in his thesis work described the necessary

    optimization technique for economic operations in an open-accessed transmission grid

    industry and suggested a suitable supply demand curve in order to achieve social welfare.

    Also gradient method based optimization solution process has been derived in the thesispaper.

    In 1998, Choi et al [3]presented a theory and simulation results of real-time pricing of

    real and reactive powers that maximize social benefits.

    In1998 Lima et al. [4] presented the dynamic aspects of pricing and its impact on long

    term expansion planning of both generation and transmission.

    The basic principle and operation are discussed by J.Y.Liu and Y.H. Song [5] in 1999

    and by J.Y. Liu and Y.H. Song and P.A. Mehta [6] in the same year respectively.

    In April 1999, Keri, Mehraban, Lombard, Elriachy, Edris [A1] analyze a set of equations

    for a system including UPFC and an equivalent two bus network.

    In 2000, Srivastava and Verma [7] utilize a location based pricing concepts and suggested

    a nonlinear programming problem formulation to determine real and reactive power

    prices.

    In July,2001, K.S. Verma, S.N. Singh and H.O. Gupta [8] proposed a method for the

    suitable location of unified power flow controller.

    Same year in [9] and [10] also a suitable location of unified power flow controller had

    been derived, with a static point of view. The optimal location is based on real power

    flow performance index sensitivity with respect to control parameters of unified power

    flow controller.

  • 8/13/2019 Acc. No. DC 59

    12/67

    4

    In July, 2001, K.S. Verma, S.N. Singh and H.O. Gupta [11] introduced a steady-state

    model of UPFC (unified power flow controller) power injection model which has been

    introduced in the minimum price dispatch algorithm.

    In 2006, K.S. Verma and H.O. Gupta [12] formulated a suitable method for finding the

    real and reactive spot price incorporating UPFC at an optimal location after analyzing the

    sensitivities with respect to the UPFC parameters.

    In 2010, A.Urkmez [13] presents a new formula for determining spot price and a new

    algorithm for economic dispatch in deregulated power systems.

    1.4 Overview

    Real power time spot prices are calculated in this thesis incorporating n unified power

    flow controller (UPFC) and the results are used for a comparative study with the base

    case, i.e without incorporating UPFC. While doing this optimal location of UPFC is also

    calculated with the help of performance index sensitivity factors for the respective UPFC

    parameters like voltage, phase angle etc. The optimal power flow problem has been

    solved by gradient method for finding the respective Lagrange multipliers for the

    Lagrangian function. In chapter 2 the OPF is formulated. Flexible AC Tranasmission

    System (FACTS) is discussed in chapter 3. Chapter 4 describes the model, structures and

    operations about UPFC and also some useful facts for finding the optimal location.

    Chapter 5 describes the Gradient method for solving the OPF related to this problem

    elaborately. Chapter 6 gives an idea of spot pricing. Chapter 7 concludes with a summary

    and several improvements, which would aid in creating a more efficient pricing method.

  • 8/13/2019 Acc. No. DC 59

    13/67

    5

    Chapter 2: OPTIMAL POWER FLOW

    2.1 Optimal power flow problem

    The computational procedure required to determine the steady-state operating

    characteristics of a power system network is termed as Load Flow. The aim of power

    flow calculations is to determine the steady-state operating characteristics of a power

    generation or transmission system for a given set of bus bar loads. In the past two

    decades, the problem of optimal power flow (OPF) has received much attention. It is of

    current interest of many utilities, and it has been marked as one of the most operational

    needs. The OPF problem solution aims to optimize a selected objective function, such as

    fuel cost via optimal adjustment of the power system control variables, while at the same

    time satisfying various equality and inequality constraints. The equality constraints are

    the power flow equations, and the inequality constraints are the limits on control

    variables and the operating limits of power system-dependent variables. The problem

    control variables include the generator real powers, the generator bus voltages, the

    transformer tap settings, and the reactive power of switch able VAR sources, while the

    problem-dependent variables include the load bus voltages, the generator reactive

    powers, and the line flows. Generally, the OPF problem is a large-scale, highly

    constrained, nonlinear, no convex optimization problem.

    Optimal Power Flow (OPF) has been extensively used in power systems at the generation

    or transmission level to designate the problem of finding the optimal value for the control

    variables (real and reactive power, voltage settings, batteries set points, etc.) when

    minimizing the total operation cost, while respecting the technical constraints of the

    network and equipments. In distribution systems, many approaches exist dedicated to the

    optimization of the configuration and the optimization of the voltage profile through

    batteries. In both cases the objective function seeks for losses reduction, but in separate

    ways. The recent development of distribution systems has led to the presence of

    distributed generation that introduces uncertainty in the previously mentioned problems,

    but may contribute to voltage control and optimization. In the same cases, regional

    dispatch of this unit is possible; tuning is possible to seek for optimal operating policies.

  • 8/13/2019 Acc. No. DC 59

    14/67

    6

    An optimal load-flow solution gives the optimal active and reactive power dispatch for a

    static power-system loading condition. Computationally, it is a very demanding nonlinear

    programming problem, due to the large number of variables and in particular to the much

    larger number and types of limit constraints which define the boundaries of technical

    feasibility.

    2.2 Optimal power flow problem formulation

    2.2.1 The objective function

    Generally it can be written as

    min ( , , )F x u p (2.1)

    Here the obejective function to be minimized is the difference of the operational cost for

    the active power of pool generator to the pool load, which is given by,

    ( ) ( )G D

    T i Pi j pj

    i I j I

    F C P B D

    =

    (2.2)

    2.2.2 The equality constraints

    Generally it can be written as

    ( , , ) 0h x u p = (2.3)

    where

    state vector V, , DV , D , qI

    u control parameters giP , giQ

    p fixed parameters diP , diQ

  • 8/13/2019 Acc. No. DC 59

    15/67

    7

    The objective function motioned in eq _ is subjected to equality constraints og real and

    reactive power balance equations. For all buses except buses i and j between which the

    UPFC device is connected, as

    1

    [ cos( ) sin( )]Nb

    l gl dl l m lm l m lm l m

    m

    P P P V V G B =

    = = + (2.4)

    1

    [ sin( ) cos( )]Nb

    l gl dl l m lm l m lm l m

    m

    Q Q Q V V G B =

    = = for l=1,2,.. bN ;but l i , j (2.5)

    For buses i and j only, the equality constraints can be written as

    _

    1

    [ cos( ) sin( )]Nb

    i gi di i m im i m im i m i s

    m

    P P P V V G B P =

    = = + (2.6)

    _

    1

    [ sin( ) cos( )]Nb

    i gi di i m im i m im i m i s

    m

    Q Q Q V V G B Q =

    = = (2.7)

    _

    1

    [ cos( ) sin( )]Nb

    j gj dj j m jm j m jm j m j s

    m

    P P P V V G B P =

    = = + (2.8)

    _

    1

    [ sin( ) cos( )]Nb

    j gj dj j m jm j m jm j m j s

    m

    Q Q Q V V G B Q =

    = = (2.9)

    2.2.3 The inequality constraints

    While solving the OPF problem with objective function and equality constraints it is

    often observed that the variables used to exceed their limits. thats why an inequality

    constraints for the respective variables are included in the OPF to keep the variables

    within their specified predefined limits.

  • 8/13/2019 Acc. No. DC 59

    16/67

    8

    In general the inequality constraints can be written as

    ( , , ) 0g x u p > (2.10)

    where

    state vector V, , DV , D , qI

    u control parameters giP , giQ

    p fixed parameters diP , diQ

    2.2.3.1 Real power generation limit

    This constitutes the upper and lower limits of real power llimit of generators

    min maxgi gi giP P P , i =1, 2, 3.. g (2.11)

    where mingiP and maxgiP are the minimum and maximum limits of real power

    generation at bus- i respectively.

    2.2.3.2 Reactive power generation limit

    This constitutes the upper and lower limits of reactive power limit of generators

    min maxgi gi giQ Q Q , i =1, 2, 3.. q (2.12)

    where mingiQ and maxgiQ are the minimum and maximum limits of real power

    generation at bus- i respectively.

    2.2.3.3 Voltage Limit

    This constitutes the uppermax

    iV and lowermin

    iV limits on the bus voltage magnitudemin maxi i iV V V i =1, 2, 3.. bN (2.13)

  • 8/13/2019 Acc. No. DC 59

    17/67

    9

    2.2.3.4 Line flow limit

    This constraint signifies the maximum power flow is a transmission line and are usually

    based on thermal and dynamic stability considerations, If maxliP is the maximum active

    power flow in line-i and liP is the active power flow at any time of that particular line,then this can be written as

    maxli liP P i =1, 2, 3 lN (2.14)

    2.2.3.5 UPFC parameter limits

    If we include some FACTS device (UPFC in this case) in between bus- i and bus- j the

    device has some inequality constraints due to its own parameters like voltage magnitude

    ( )DV and phase angle ( )D of the series voltage source of it. Along with these two limitsthe reactive power component of shunt current ( )qI should also be less than its rating.

    Mathematically, it can be written as

    ( ) max0 D DV V (2.15)

    ( ) max0 D D (2.16)

    and ( )min maxq q qI I I (2.17)

    2.3 Comparative study of different solution techniques for the

    optimal power flow

    There are various methods for solving the optimal power flow problem. Some most

    common methods are described below:

    2.3.1 Newtons Method

    This method is used to to speed up the convergence [14]. But at the same time handling

    inequality constraints is very difficult in this method. Inequality constraints must be

    handled by some additional means in terms of adding a constraint penalty function to

  • 8/13/2019 Acc. No. DC 59

    18/67

    10

    the objective function. Furthermore the matrix equation for this method is extremely

    sparse and requires special sparsity logic as the size of the Hessian matrix can be very

    large.

    2.3.2 Gradient Method

    Gradient method is easy to compute. It requires only the first order derivative of the

    Lagrangian function with respect to the state vector and control variables. It has the

    difficulty in determining the step size because small step size will give slow convergence

    whereas larger step size will make the system oscillatory. Is also has the problem for

    solving with inequality constraints.

    2.3.3 Lambda iteration method

    [B] matrix is developed[14] to represent the losses of the system. Also beside this penalty

    factors may be calculated outside by the power flow.

    2.3.4 Linear Programming (LP) method

    The difficulty of handling the inequality constraints is easily overcome in this method as

    this method is very adaptive in handling inequality constraints [14], as long as the

    problem to be solved is such that it can be linearized without loss of accuracy.

    2.3.5 Interior Point (IP) method

    It is comparatively a new solution algorithm [16] derived from the linear programming

    problems that did not solve for the optimal solution by following a series of points that

    were on the constrained boundary but, rather followed a path through the interior of the

    constraints [15] directly toward the optimal solution on the constrained boundary. This

    load flow solution technique is much faster than the conventional Linear programming

    algorithm.

  • 8/13/2019 Acc. No. DC 59

    19/67

    11

    2.3.6 Genetic Algorithm (GA) method

    It is mainly used in large scale systems for solving the economic dispatch problem. It is a

    new type of encoding method in which a set of chromosome [15] contains only an

    encoding of the normalized system incremental costs. Genetic algorithm is integrated

    with conventional OPF to select the best control parameters to minimize the total

    generation fuel cost and keep the line flows within permissible limits. It is faster than

    lambda iteration method in large systems.

    2.3.7 Evolutionary Programming (EP) method

    It is a genetic population based metaheuristic [15] optimization algorithm. In this method

    fitness function converges smoothly without any oscillations.

    2.3.8 Particle Swarm Optimization (PSO) method

    This method is inspired by the social behavior and movement dynamics of insects, birds

    and fish. It is very simple method to implement. It is derivative free. Another advantage

    of this method is that it has very few algorithm parameters [17]. PSO is an efficient

    global optimizer for continuous variable problems and can accommodate constraints by

    using a penalty method.

  • 8/13/2019 Acc. No. DC 59

    20/67

    12

    Chapter 3: FLEXIBLE AC TRANSMISSION SYSTEM

    3.1 About FACTS

    Most of the worlds electric power supply systems are widely interconnected for

    economic reasons, to reduce the cost of electricity and to improve reliability of power

    supply. The purpose of transmission network is to pool power plant and load centres in

    order to minimize the total generation capacity and fuel cost. On the other hand, as the

    power transfers grow, the power system becomes increasingly more complex to operate

    and the system can become less secure due to the probability of major outages. As a

    result full potential of transmission interconnection cannot be envisaged. In modern day,

    greater demands on the transmission network and the most importantly the introduction

    of deregulated environment, a tendency towards less security and reduced quality of

    supply is evoked. A flexible alternating current transmission system (FACTS) is a

    technology is essential to fulfill all these drawbacks mostly. It is a system composed of

    static equipment used for the AC transmission of electric energy. It is meant to enhance

    the controllability and increase the power transfer capability of the network. It is first

    proposed by Dr. N. Hingorani.

    3.2 Classification of FACTS

    In broader sense FACTS controller can be classified into three categories:

    1) Shunt controllers

    2) Series controllers

    3) Combined shunt-series controllers

  • 8/13/2019 Acc. No. DC 59

    21/67

    13

    3.2.1 Shunt controller

    3.2.1.1 Shunt compensation

    Shunt controller provides the shunt compensation [18] of an AC network. As the name

    suggests it is connected in shunt (or parallel) to the transmission line. It works as acontrollable current source. It may have variable impedance. It injects current into the

    system at the point of connection. As long as the injected current is in phase quadrature

    with the line voltage, the shunt controller only supplies or consumes variable reactive

    power.

    Shunt compensation is of two types

    Shunt capacitive compensation

    This method is used to improve the power factor. Whenever an inductive load is

    connected to the transmission line, power factor lags because of lagging load current.

    To compensate, a shunt capacitor is connected which draws current leading the

    source voltage. The net result is improvement in power factor.

    Fig. 3.1: Shunt compensation circuit and phasor diagram

  • 8/13/2019 Acc. No. DC 59

    22/67

    14

    Shunt inductive compensation

    This method is used either when charging the transmission line, or, when there is very

    low load at the receiving end. Due to very low, or no load , very low current flows

    through the transmission line. Shunt capacitance in the transmission line causes

    voltage amplification (Ferranti Effect). The receiving end voltage may become

    double the sending end voltage (generally in case of very long transmission lines). To

    compensate, shunt inductors are connected across the transmission line.

    3.2.1.2 Types of shunt controllers

    i. Static synchronous compensator (STATCOM):It is previously known as static

    condenser (STATCOM). It is a static synchronous generator operated as a shunt-

    connected static var compensator whose capacitive or inductive output current can

    be controlled independent of the ac system voltage. It is based on a power

    electronics voltage-source converter and can act as either a source or sink of

    reactive AC power to an electricity network. If connected to a source of power it

    can also provide active AC power.

    Fig. 3.2(a) Fig. 3.2(b)

    Fig 3.2: STATCOM controller (a) voltage source converter based

    (b) current source converter based

  • 8/13/2019 Acc. No. DC 59

    23/67

    15

    ii. Static var compensator (SVC): It is a shunt connected static var generator or

    absorber whose output is adjusted to exchange capacitive or inductive current so

    as to maintain or control specific parameters of the power system.

    Some most common types of SVCs are as follows:

    a. Thyristor controlled reactor (TCR): It is connected in series with a

    bidirectional thyristor valve[19]. The thyristor valve is phase-controlled.

    Equivalent reactance is varied continuously. Its effective reactance is

    varied in continuous manner by partial conduction control of the thyristor

    valve.

    Fig. 3.3: Thyristor controlled reactor

    b. Thyristor-switched reactor (TSR): Same as TCR but thyristor is either in

    zero- or full- conduction [19]. Equivalent reactance is varied in stepwise

    manner. It,s effective reactance is varied in stepwise manner by full or

    zero conduction operation of thyristor valve.

    c. Thyristor-switched capacitor (TSC):A capacitor is connected in series with

    a bidirectional thyristor valve [19]. Thyristor is either in zero- or full-

    conduction. Equivalent reactance is varied in stepwise manner.

  • 8/13/2019 Acc. No. DC 59

    24/67

    16

    Fig.3.4: Thyristor switched capacitor

    d. Mechanically-switched capacitor (MSC): capacitor is switched by circuit-

    breaker. It aims at compensating steady state reactive power. It is switched

    only a few times a day.

    iii. Static Var Generator or absorber (SVG):It is a static electrical device capable

    of drawing controlled[19] capacitive and/or inductive current from an electrical

    power system and thereby generating or absorbing reactive power.

    iv. Thyristor Controlled Braking Resistor(TCBR): A shunt-connected thyristor-

    switched resistor[19], which is controlled to aid stabilization of a power system or

    to minimize power acceleration os a generating unit during a disturbance.

    3.2.2 Series controller

    3.2.2.1 Series compensation

    In series compensation, the FACTS is connected in series with the power system. It

    works as a controllable voltage source [18]. Series inductance occurs in long transmission

    lines, and when a large current flow causes a large voltage drop. To compensate, series

  • 8/13/2019 Acc. No. DC 59

    25/67

    17

    capacitors are connected. As long as the voltage is in phase quadrature with the line

    current, the series controller only supplies or consumes variable reactive power.

    Fig.3.5: Series compensation and its phasor diagram

    3.2.2.2 Types of series controllers

    i. Static synchronous series compensator(SSSC):It is a static synchronous generator

    operated without an external electric energy source as a series compensator whose

    output voltage is in quadrature with, and controllable independently of, the line

    current for the purpose of increasing or decreasing the overall reactive voltage

    drop across the line and thereby controlling the transmitted electric power [19].

    SSSC is one of the most important FACTS controller. SSSC can be based onvoltage-source converter or a current source converter without an extra energy

    source SSSC can only inject a variable voltage which is 90 degrees leading or

    lagging the current.

  • 8/13/2019 Acc. No. DC 59

    26/67

    18

    Fig. 3.6: Static synchronous series compensator

    ii. Thyristor-controlled series capacitor (TCSC): It is a series capacitor bank is

    shunted by a thyristor-controlled reactor in order to provide smoothly variable

    series capacitive reactance [19]. It is based on the thyristors without gate turn-off

    capability. TCSC may be a single, large unit, or may consist of several equal ordifferent sized smaller capacitors in order to achieve a superior performance.

  • 8/13/2019 Acc. No. DC 59

    27/67

    19

    Fig. 3.7: Thyristor controlled series compensator

    iii. Thyristor-controlled series reactor (TCSR): In this type of controller a series

    reactor bank is shunted by a thyristor-controlled reactor[19]. Like TCSC, TCSR

    may also be a single large unit or several smaller series units.

    Fig 3.8: Thyristor controlled series reactor

    iv. Interline power flow controller (IPFC): A combination of two or more static

    synchronous series compensators (SSSC) which are coupled via a common dc

  • 8/13/2019 Acc. No. DC 59

    28/67

    20

    link to take part in bidirectional flow of real power between[19] the ac terminals

    of the SSSCs, and are controlled to provide independent reactive compensation

    for the adjustment of real power flow in each line and maintain the desired

    distribution of reactive power flow among the lines.

    Fig.3.9: Interline power flow controller

    v. Thyristor-switched series reactor (TSSR): A series reactor[19] bank is shunted by

    a thyristor-switched reactor in order to provide a stepwise control of series

    inductive reactance.

  • 8/13/2019 Acc. No. DC 59

    29/67

    21

    Fig. 3.10 Thyristor-switched series reactor

    3.2.3 Combined shunt-series controllers

    This type of controllers mainly consist of both shunt and series type controllers. Most

    important controller under this category is unified power flow controller (UPFC).

    Types of combined shunt-series controllers

    i. Unified power flow controller (UPFC): It is a combination of static synchronous

    compensator (STATCOM-shunt type) and static series compensator (SSSC) [19].

    This two controllers are coupled via a common dc-link to allow a bidirectional

    flow of real power between the series and shunt output terminal of SSSC and

    STATCOM reapectively. By injecting angularly unconstrained series voltage,

    UPFC is able to control, selectively, the transmission line voltage, impedance and

    phase angle or alternatively, the real and reactive power flow in the line. It also

    independently helps to control the shunt reactive compensation.

    Fig. 3.11: Unified power flow controller

    There are some other types of controllers also which does not belong to these three

    main categories mentioned above. Some of them are, Thyristor Control Voltage

    Limiter (TCVL), Thyristor Controlled Voltage Regulator (TCVR) etc.

  • 8/13/2019 Acc. No. DC 59

    30/67

    22

    3.3 Utility of FACTS

    I. Improve power transmission capability.

    II. Improved system stability and availability.

    III. Improved power quality for sensitive industries.IV. Minimized environmental impact.

    V. Minimized transmission losses.

    3.4 Maintenance of FACTS

    Compared to shunt capacitors, reactors and transformers, the maintenance of FACTS

    devices are found to be lot easier. No special training or guideline is necessary to perform

    a maintenance operation on FACTS devices. The amount of maintain ace ranges from150 to 250 man-hours per year and depends upon the size of the installation and local

    ambient condition.

  • 8/13/2019 Acc. No. DC 59

    31/67

    23

    Chapter 4: UNIFIED POWER FLOW CONTROLLER

    4.1 About Unified Power Flow Controller

    The Unified Power Flow Controller (UPFC) concept was first proposed by Gyugyi [22]

    in 1991. Unified Power Flow controller is a novel real time power flow controlling

    device. It provides full dynamic control of transmission parameters, voltage, line

    impedance and phase angle by fulfilling multiple functions of power flow like reactive

    shunt compensation, series compensation and phase shifting. In other words it can be said

    that both the real and reactive power flow in a line is controlled independently by this

    device. Thus by controlling the line power flow UPFC satisfies the load demand and

    other operating conditions. With suitable electronic controls, the UPFC can cause the

    series-injected voltage vector to vary rapidly and continuously in magnitude and/or phase

    angle as desired. Thus it simultaneously controls the wide range of variation of active and

    reactive power as well as also has the capability to transition rapidly from one such

    achievable point to any other.

    As the need for flexible and fast power flow controllers, such as the UPFC, is expected to

    grow in the future due to the changes in the electricity markets, there is a corresponding

    need for the reliable and realistic models of these controllers to investigate the impact of

    them on the performance of the power system.

    4.2 Structures and operations of UPFC

    UPFC can be categorized under new generation of FACTS device which combines the

    features of two old FACTS devices, the Static Synchronous Compensator (STATCOM)

    and the Static Synchronous Series Compensator (SSSC). In practice these two devices are

    two voltage source converters connected respectively in parallel with the transmissionline through a shunt connected transformer and in series with the transmission line

    through a series connected transformer. The other terminals of both the converters are

    connected to each other through a common dc link including a storage capacitor. This

    type of arrangement functions as an ac-to-ac power converter in which the real power can

    freely in either direction between the ac terminals of the two converters, and each

  • 8/13/2019 Acc. No. DC 59

    32/67

    24

    converter can independently generate or absorb reactive power at its own output ac

    terminal.

    Fig.4.1: Equivalent circuit of

    STATCOM

    Fig. 4.2: Equivalent circuit of SSSC

  • 8/13/2019 Acc. No. DC 59

    33/67

    25

    The shunt converter is primarily used to provide active power demand of the series

    converter through the common dc link. Shunt converter can also provide independent

    shunt reactive compensation for the line by generating or absorbing reactive power when

    desired. The series converter provides the main function of the UPFC by injecting a

    voltage by controllable magnitude and phase angle in series with the line via the insertion

    transformer. The injected voltage acts essentially as a synchronous ac voltage source. The

    transmission line current flows through this voltage source resulting in reactive and real

    power exchange between it and the ac system. The reactive power exchanged at the ac

    terminal of the series insertion transformer is generated internally by the converter. The

    real power exchanged at the ac terminal is converted into dc power which appears at the

    dc link as a positive or negative real power demand.

    The basic function of shunt converter is to supply or absorb the real power demanded by

    the series converter at the common dc link to support the real power exchange resulting

    from the series voltage injection [19]. This dc link power demand of series converter is

    converted back to ac by the shunt converter and coupled to the transmission line bus via a

    shunt connected transformer. It is important to note that whereas there is a closed direct

    path for the real power negotiated by the action of series voltage injection through shunt

    and series converters back to the line, the corresponding reactive power exchanged is

    supplied or absorbed locally by series converter and therefore does not have to be

    transmitted by the line. Thus, shunt converter can be operated at a unity power factor or

    be controlled to have a reactive power exchange with the line independent of the reactive

    power exchanged by series converter. Most certainly there can be no reactive power flow

    through the UPFC dc link.

    4.3 Equivalent Circuit of UPFC [20]

    As said earlier UPFC is a combination of both STATCOM and SSSC. It has both series

    and shunt voltage sources as well as impedance. The equivalent circuit of STATCOM

    and SSSC is shown in the Fig.4.1 and Fig. 4.2 respectively. In Fig.4.3 the equivalent

    circuit of UPFC is shown.

  • 8/13/2019 Acc. No. DC 59

    34/67

    26

    Fig. 4.3: Equivalent circuit of UPFC

    The voltage vector of series converter is se se seV V = and for shunt converter it is

    sh sh shV V = .Bus voltage vector of thi bus is i i iV V = and for thj it is j j jV V = .

    Active power exchange between the two converters will be

    * *Re( ) 0sh sh se jiPE V I V I= =

    The bus voltage control constraint is 0specified

    i iV V =

    The two equivalent voltage injection binding constraint is as follows:

    min maxse se seV V V

    min maxsh sh shV V V

    min maxse se se

    min maxsh sh sh

  • 8/13/2019 Acc. No. DC 59

    35/67

    27

    4.4 Modeling of UPFC [12]

    The UPFC model is very helpful in understanding the impact of the UPFC on the power

    system in the steady state. The injection model also can easily be incorporated in the

    steady state power flow model. Since the series voltage source converter does the mainfunction of the UPFC, it is appropriate to discuss the modeling of a series voltage source

    converter. To analyze the UPFC injection it is important to note that the series converter

    is used to generate a voltage source at the fundamental frequency with variable amplitude

    0 maxD DV V and phase angle 0 2D .

    The equivalent circuit model of UPFC is shown in the fig 4.4. It has three parameters

    namely inserted voltage magnitude and phase angle ( DV , D ) and the magnitude of the

    reactive power component of shunt current qI . The device is connected between two

    nodes i andj . The buses situated in these two nodes have voltage magnitudes of iVfor

    thi bus and jV for the thj bus. The transmission line connected between these two buses

    is l (say).The transmission line has an impedance ij ij ijz r jx= + where ijr is theresistance of the transmission line and ijx is the reactance of that line. The total line

    charging B is equally divided in two parts between the transmission line and each part is

    known as half line charging of transmission line.

    Fig.4.4: Equivalent model of UPFC

  • 8/13/2019 Acc. No. DC 59

    36/67

    28

    From the UPFC vector diagram the mathematical formulation from the above diagram

    can be written as:

    '

    i i DV V V= + (4.1)( ) ( ) / 2q iArg I Arg V = (4.2)

    Because of the voltage vector can be leading or lagging in nature with respect to the

    series transformer current vector.

    The voltage vector at bus i and the current vector for the shunt converter DI are in phase

    so that,

    ( ) ( )D irg I Arg V = , (4.3)

    where,

    *'Re[ ]D i

    D

    i

    V II

    V= (4.4)

    Now apparent power flows from bus i to bus j will be,

    *'

    * ' * ' *Re[ ]( /2 ) ( /2 )D i

    ij ij ij i ij i D q i i i q iV I

    S P jQ VI V jViB I I I V jVB I I Vi

    = + = = + + + = + + + (4.5)

    and apparent power flows from bus j to bus iwill be,

    * *' *( / 2 )ji ji ji j ji j ji j j iS P jQ V I V I V jV B I = + = = = (4.6)

    Separating the real part and imaginary part from both left and right hand side of the

    equation_ and comparing, we get the active and reactive power flow of the line having

    UPFC.

    The active power flow from thi bus to thj bus for the line having UPFC is,

  • 8/13/2019 Acc. No. DC 59

    37/67

    29

    2 2( ) ( ) 2 cos( )ij ij i D ij i D ij D iP real S V V g V V g = = + + (4.7)

    [ cos( ) sin( )] ( cos sin )j D ij D j D j i j ij ij ij ijV V g bij V V g b + + (4.8)

    The reactive power flow from thi bus to thj bus for the line having UPFC is,

    2( ) ( / 2)ij ij i q i ijQ imag S V I V b B= = +

    [ sin( ) ( / 2) cos( )]i D ij D i ij D iV V g b B + + (4.9)

    The active power flow from thj bus to thi bus for the line having UPFC is,

    2( ) [ cos( ) sin( )]ji ji j ij j D ij D ij D iP real S V g V V g j b = =

    ( sin cos )i j ij ij ij ijV V g b (4.10)

    The reactive power flow from thj bus to thi bus for the line having UPFC is,

    2( ) ( / 2) ( sin( ) cos( ))ji ji j ij j D ij D j ij D iQ imag S V b B V V g b = = + + +

    (( sin cos )j ij ij ij ijV V g b + + (4.11)

    Where, ij i j =

    The injected equivalent circuit from the principle of basic circuit theory can be obtained

    as given below:

    Fig.4.5: Injection model of UPFC

  • 8/13/2019 Acc. No. DC 59

    38/67

    30

    The injected active power at bus i , _i sP for the UPFC line l is,

    2_ 2 cos( ) [ cos( ) sin( )]s D ij i D ij D i j D ij D j ij D jP V g VV g VV g b = + + (4.12)

    The injected reactive power at bus i , _i sQ , for the UPFC line l is,

    _ [ sin( ) ( / 2)cos( )]s i q i D ij D i ij D iQ V I V V g b B = + + + (4.13)

    The injected active power at bus j , _j sP ,for the UPFC line l is,

    _ [ cos( ) sin( )]j s j D ij D j ij D jP V V g b = (4.14)

    The injected reactive power at bus , _j sQ ,for the UPFC line l is,

    _ [ sin( ) sin( )]j s j D ij D j ij D jQ V V g b = + (4.15)

    4.5 Location of UPFC[12]

    4.5.1 Contingency Selection and Performance Index

    For consistent service, power system must remain intact and be able to endure a wide

    variety of disturbances. It should operate in normal and secured condition. Therefore, it is

    important that the system to be designed and operated so that the more possible

    contingencies can be sustained with no loss of load. Operating conditions of power

    system can be determined if the network model and complex phasor voltages at every

    system bus is known.If all the loads in the system can be supplied power without

    violation of any operational constrains, then the system is in normal state. Examples of

    these operational constrains include the limits on the transmission line flow, as well as

    upper and lower (i.e. limits) on bus voltage magnitudes.

  • 8/13/2019 Acc. No. DC 59

    39/67

    31

    It should be noted that, line or generation outage may cause flow or voltages to fall

    outside limits. The contingency analyses (CA) are used to predict the effect of these

    outages. The state estimators solutions are used to perform contingency analysis in

    power systems.

    We would like to get some measure as to how much a particular outage might affect the

    power system. The idea of a performance index (PI) seems to fulfill this need. The

    definition for the overload performance index is as follows:

    max1

    22

    Nlm lk

    lkm

    w PPI n

    n P=

    = (4.16)

    Where lkP is the real power flow and maxlkP is the rated capacity of line-k,n is the

    exponent, and mw is a nonnegative weighting coefficient that may be used to reflect the

    importance of the lines. lis the total number of lines in the network.

    Various techniques have been tried to obtain the value of PIwhen a branch is taken out.

    These calculations can be made exactly if n=1, that is, a table of PI values, one for

    each line in the network can be calculated quite quickly. However when n=1, the PI

    does not snap from near zero to near infinity as the branch exceeds its limit. Instead, it

    rises as a quadratic function. A line that is just below its limit contributes to PIalmost

    equal to one that is just below their limit. Thus the PIs ability to distinguish or detect

    bad cases is limited when n=1.

    Using the second order performance indices in contingency selection algorithm can be

    suffered from the masking effects. The lack of discrimination, in which the performance

    index for a case with many small violations may be comparable in value to the index for

    a case with one huge violation, is called the masking effect. The masking effect can be

    minimized by choosing higher values of n (>1). In this case it is taken as 2 and mw istaken as1.0 .

    In a line of networks there are some lines which are found to be weaker than the other

    lines in terms of line power flow and injected bus power. We have to include the device

    in that weaker line (say l ) in between 2 buses (say i andj ) after calculating the

  • 8/13/2019 Acc. No. DC 59

    40/67

    32

    sensitivities for each UPFC parameters. Sensitivity matrix helps to find the weakest line

    among the network of lines. Performance index sensitivities factors are calculated by

    partially differentiate the performance index with respect to each of the UPFC control

    parameters ( DV , D , q ) and can be defined as

    1

    0

    l

    D VD

    PIc

    V =

    =

    (4.17)

    2

    0

    l

    D DD

    PIc

    V

    =

    =

    (4.18)

    3

    0

    l

    q Iq

    PIcI =

    = (4.19)

    where 1lc , 2lc and 3lc arePIsensitivity with respect to UPFC parameters l( DV , D

    and q ) respectively connected between bus i and bus j . Using Equation_, we get

    4

    3

    max1

    1Nl

    lkk lk

    l lk l k

    PI Pw PP R=

    = (4.20)

    The real power flow in line-k ( lkP ) can be represented in terms of real power injections

    using dc power flow equations wheres is the slack or reference bus, as

    1

    _1

    Nbkn n

    nn slk

    Nbkn n j sn

    n s

    S PP

    S P P

    =

    =

    =

    +

    (4.21)for k = l

    for k l

  • 8/13/2019 Acc. No. DC 59

    41/67

    33

    Where knS is the knthelement of matrix [ ]S that relates line flow with power injections

    at the buses without UPFC, and bN is the number of buses in the system. _j sP ,

    therefore, is the additional power flow, at bus-j , in the line containing UPFC, due to the

    presence of the device.Using equation 4.20 and 4.21, the following relationship can be obtained

    _ _

    _ _ _

    i s j ski kj

    l llk

    l i s j s j ski kj

    l l l

    P PS S

    R RP

    R P P PS S

    R R R

    + = + +

    (4.22)

    where , ,l D D qR V I= .

    Now if we put these three control parameters one by one in equation 4.22, we get the the

    partial differentiation of lkP with respect to the UPFC control parameters.

    The partial differentiation of _i sP and _j sP with respect to each control parameters can

    be evaluated distinctly as follows

    _

    0

    2 cos( ) [ cos( ) sin( )]D

    i si ij D i ij D ij D j

    D V

    PV g Vj g j b

    V

    =

    = + +

    (4.23)

    _

    0

    2 sin( ) ( sin cos )

    D

    i si ij j ij j ij j

    D D

    PV g Vj g b

    V

    =

    = + + (4.24)

    _

    0

    0i s

    qIq

    P

    I =

    = (4.25)

    _

    0

    ( cos sin )D

    j sj ij j ij j

    D V

    PV g b

    V

    =

    = + (4.26)

    for k l

    for k = l

  • 8/13/2019 Acc. No. DC 59

    42/67

    34

    _

    0

    ( sin cos )D

    j sj ij j ij j

    D

    PV g b

    V

    =

    = (4.27)

    _

    0

    0j sq

    Iq

    PI =

    = (4.28)

    Thus the sensitivity factors can be obtained from equation 4.23 to 4.28. In this case

    equation 4.25 and 4.28 the partial differentiation of injected bus power with qI gives

    zero value. It suggests that the sensitivities are calculated for DV and D only.

  • 8/13/2019 Acc. No. DC 59

    43/67

    35

    Chapter 5: GRADIENT METHOD

    5.1 Problem formulation

    The objective function is to be minimized the difference of the operational cost for the

    active power of pool generator to the pool load.

    The optimization problem can be restated as

    min ( , , )F x u pu

    (5.1)

    Subject to equality constraints( , , ) 0g x u p = (5.2)

    To solve the optimization problem, we define Lagrange functions as

    ( , , ) ( , , ) ( , , )TL x u p F x u p g x u p= + (5.3)

    where is the vector of Lagrangian multipliers [21] of the same dimensionas ( , , )g x u p .

    The necessary conditions to minimize the unconstrained Lagrangian function are

    0

    TL F g

    x x x

    = + = (5.4)

    0

    TL F g

    u u u

    = + = (5.5)

    ( , , ) 0L

    g x u pu

    = =

    (5.6)

  • 8/13/2019 Acc. No. DC 59

    44/67

    36

    Equations 5.4, 5.5 and 5.6 are nonlinear algebraic equations and can only be solved

    iteratively. A simple yet efficient iteration scheme, that can be employed, is the steepest

    descent method (also called the gradient method). The basic technique is to adjust the

    control vector u, so as to move from one feasible solution point (a set of values of x

    which satisfies eq.5.6 for given u andp ; it indeed the load flow solution) in the direction

    of negative gradient to a new feasible set of solution with lower value of objective

    function.

    5.2 Computational Procedure [21]

    1) Make an initial guess for u, the control variables.

    2) Find a feasible load flow solution by Newton-Raphson iterative method. The

    method improves the solution as follows:

    1r rx x+ = + (5.7)

    3) Where x is obtained by soling the set of linear equations given below:

    ( , ) ( , )r rg

    x y x g x yx

    = (5.8)

    1

    ( , ) ( , )r rg

    x x y g x yx

    =

    (5.9)

    4) The end result of Step 2 is a feasible solution of x and the Jacobian matrix,

    5) Solve eq 5.4 for

    1F

    x

    =

    (5.10)

    6) Put the values of obtained from eq. 5.10 to eq. 5.5 and compute the gradient

    TF g

    L u u = + (5.11)

    7) If L equals are within prescribed tolerance, the minimum has been reached.

    Otherwise:

    8) Find a new set of control variables

    new old u u u= + where u L = (5.12)

  • 8/13/2019 Acc. No. DC 59

    45/67

    37

    Here u is a step in negative direction of the gradient. The step size is adjusted by thepositive scalar .In this algorithm, the choice of is very critical. Too small a value of

    guarantees the convergence, but slows down the rate of convergence. Too high a value

    causes oscillations around the minimum.

    5.3 Inequality constraints on control variables

    Though in the previous discussion, the variables are assumed unconstrained, the

    permissible values are, in fact, always constrained, i.e.

    min maxu u u

    e.g min maxgi gi giP P P These inequality constraints on control variables can be easily handled. If the correction

    u in eq. 5.12 causes u to exceed one of the limits, u is set equal to the

    corresponding limit, i.e.

    max

    min

    i

    i i

    oldi i

    u

    newu u

    u u

    = +

    After a control variables reaches any of the limits, its component in the gradient should

    continue to be computer in lated iterations, as the variables may come within limits at

    some later stage.

    5.4 Inequality constraints on dependent variables

    Often, the upper and lower limits on dependent variables are specified as:

    min maxx x x e.g min maxi i iV V V

    Such inequality constraints can be conveniently handles by the penalty function methods.

    The objective function is augmented by penalties for inequality constraints violations.

    If oldi iu u+ > maxiu

    If oldi iu u+ < miniu

  • 8/13/2019 Acc. No. DC 59

    46/67

    38

    This forces the solution to lay sufficiently close to the constraint limits, when these limits

    are violated. In this problem all iV are within the specified limit. So that no penalty

    function has been included.

    5.5 Lagrangian for solving the OPF in gradient method

    The objective function is

    ( ) ( )G D

    T i Pi j pj

    i I j I

    F C P B D

    =

    (5.13)

    The equality constraints for i thbus are

    _

    1

    [ cos( ) sin( )]Nb

    i i m im i m im i m i s

    m

    P V V G B P =

    +

    (5.14)

    and _

    1

    [ sin( ) cos( )]Nb

    i i m im i m im i m i s

    m

    Q V V G B Q =

    (5.15)

    Hence the Lagrange function will be

    ( , ) ( ) ( )G D

    i Pi j pj

    i I j I

    L P Q C P B D

    =

    ( ) _1

    [ cos( ) sin( )]Nb

    i i m im i m im i m i s

    i Nb m

    p P V V G B P

    =

    + +

    ( ) _1

    [ sin( ) cos( )]Nb

    i i i m im i m im i m i s

    i Nb m

    q Q V V G B Q =

    +

    (5.16)

  • 8/13/2019 Acc. No. DC 59

    47/67

    39

    where pi and qi are the Lagrange multipliers of respective equality

    constraints. The Lagrange multiupliers for the real power equations of the load flow

    are invariably positive; however, for reactive power, the multipliers can either be

    positive or negative.

  • 8/13/2019 Acc. No. DC 59

    48/67

    40

    Chapter 6: SPOT PRICING

    6.2 Introduction

    The spot price or spot rate of a commodity, a security or a currency is the price that

    is quoted for immediate (spot) settlement (payment and delivery). Spot settlement is

    normally one or two business days from trade date. Spot rates are estimated via the

    bootstrapping method, which uses prices of the securities currently trading in

    market, The result is the spot curve, which exists for each of the various classes of

    securities.

    In modern world transmission open access has become an important issue on

    deregulated electrical sector [13]. In a generation marketplace, the agents will

    maximize their individual revenues not taking into account the social welfare. So

    there should be a valid coordination between the generation marketplace and the

    centralized or deregulated transmission open access. In a competitive market

    environment, no participant can absolutely control the power system operation.

    That is the existing spot price cannot be changed by adjusting the bids which mostly

    matches a single participants marginal cost. Therefore the minimum power system

    operation cost and the maximum participant benefit are reached at the same time ina real competitive market.

    6.2 Power pools

    Interchange of power between systems can be economically advantageous.

    However, when a system is interconnected with many neighbors, the process of

    setting up one transaction at a time with each neighbor can become very time

    consuming and will rarely result in the optimum production cost [14]. To overcomethis burden, several utilities may form a power pool which incorporates a central

    dispatch office. The power pool is administered from a central location that has

    responsibility for setting up interchange between members. The pool members take

    certain responsibilities to the pool operating office in return for greater economies

    in operation.

  • 8/13/2019 Acc. No. DC 59

    49/67

    41

    6.2.1 Advantages of power pools

    1) The certain advantages for centrally dispatched power pools are as follows:

    2) Minimize operating costs (or maximize operating efficiency alternatively)

    3) Perform a system-wide unit commitment.

    4) Minimize the reserves being carried throughout the system.

    5) Coordinate maintenance scheduling to minimize costs and maximize

    reliability by sharing reserves during maintenance periods.

    6) Maximize the benefits of emergency procedures.

    6.2.2 Disadvantages of power pools

    There are some disadvantages that should be included along with the advantages

    like economic operation. Some of the disadvantageous factors are as follows:

    1) The complexity of the pool agreement and the continuing costs of

    supporting the interutility structure required to manage and administer thee

    pool.

    2) The operating and investment costs associated with the central dispatch

    office and the needed communication and computation facilities.

    3) The relinquishing of the right to engage in independent transactions outside

    of the pool by the individual companies to the pool office and the

    requirement that any outside transactions be priced on a split-saving basis

    based on pool members costs.

    4) The additional complexity that may result ion dealing with regularity

    agencies if the pool operates in more than one state.

  • 8/13/2019 Acc. No. DC 59

    50/67

    42

    6.3 Spot price

    For decades, power factor penalties have been used in providing reactive power

    pricing. It has been shown that the practice of power factor penalties is unable to

    provide accurate price signals to customers. Spot pricing means that electricityprices to the customer follow as closely as technically practical the real cost of

    electricity at the time that it is produced and supplied. Most findings in real-time

    pricing of reactive power are closely related to those of active power pricing. Spot

    prices as defined are change according to power production units and transmission

    lines in the power system. If total power demand is higher than participants offer,

    spot price will increase [13]. Conversely, if total power demand is lower than

    participants offer, spot price will decrease. All electrical power producers want to

    run their units in the most productive operating conditions in every period.

    Fig.6.1: power production-bid price characteristics

    !imax

    !i2

    !i0

    !i1

    !imin

    Pimin PimaxPi0

    Ti1 Ti2Ti

  • 8/13/2019 Acc. No. DC 59

    51/67

    43

    As in Fig. 1, if the spot price for one participant is determined as optimum that

    particular participant dose not want to buy or transact any power from other

    participants. Participants will produce electrical energy for only their own

    agreement. Participants only export power after fulfilling their own internal needs if

    the spot price is higher than !i0 , the participant reduce its own local generation. As

    shown in the graph with increase in power flow power cost increase too. Power

    system must have extra supply for this lack of restriction of participants. If the

    power systems have no extra supply, then spot price applications cannot apply

    frequently.

    6.4 Marginal cost

    In purely economic point of view marginal cost can be defined as the cost of the

    additional inputs needed to produce that output. More formally, the marginal cost is

    the derivative of total production costs with respect to the level of output.

    The prices for active powers at bus- i are actually the marginal cost associated with

    the corresponding load flow equations when the OPF( with and without FACTS)

    are solved as a nonlinear programming problem [12].

    From the power system point of view, the active power marginal cost price at the

    bus- i is defined by

    i

    di

    PP

    =

    [total cost of providing electricity to all customers subject toConstraints]

    i

    i

    d

    LC

    P

    = =

    where piC is the marginal cost price of active power at bus i and L is the

    Lagrange function defined in eq.(5.16) for which the total cost to supply the

    electrical energy for all consumers and subject to operation restrictions.

  • 8/13/2019 Acc. No. DC 59

    52/67

    44

    Chapter 7: RESULTS AND DISCUSSIONS

    7.1 IEEE 30-bus test system

    The proposed method has been tested on a IEEE 30-bus system for the base case

    (without UPFC) and with incorporating UPFC. The single line diagram of a 30 bus

    system is given in figA.1 and 2. The prices bid by generators are given in table A.1,

    where P is in megawatts and cents is a monetary unit. Bus data is given in table A.2

    and line data is given in table A.3.

    7.2 Tabulated results

    Table 7.1 to 7.4 shows the test results after the proposed method is implemented on

    MATLAB 7.8 for IEEE 30 bus system and the computation is performed on a

    computer having 2.80 GHz, core 2 duo processor and 2 GB RAM.

    Table 7.1: Sensitivity table matrix for c1l

    and c2l

    Line

    nos.

    ith

    bus jth

    bus c1l

    (withrespect to VD)

    c2l

    (withrespect to !D)

    1 1 2 0.105400553705582 -0.0133720592871952

    2 1 3 0.00133199832472405 -0.000177325849024417

    3 2 4 -7.07350277184786e-07 5.97848915732095e-08

    4 3 4 -5.92411347915431e-06 5.30658325775049e-07

    5 2 5 -2.64755442531785e-05 3.09421014094045e-06

    6 2 6 0 0

    7 4 6 0 0

    8 5 7 -6.77830371534241e-07 7.66349639648712e-08

    9 6 7 -0.00564853278969574 0.000683726222919481

    10 6 8 -0.115285393796341 0.0121133089179766

    11 6 9 0 0

  • 8/13/2019 Acc. No. DC 59

    53/67

    45

    12 6 10 -0.000418200645620308 6.48355308725975e-05

    13 9 11 0.00196413791901515 -7.02601044429364e-05

    14 9 10 -0.00122302880608463 0.000225231891633056

    15 4 12 -0.00024825225853467 3.97762834798397e-05

    16 12 13 0.0864586908875991 -0.00692698291034724

    17 12 14 -0.00082000115723229 0.000129868604021993

    18 12 15 -0.0318824780904561 0.00526855828148936

    19 12 16 -3.72830064390911e-05 5.44808465509381e-06

    20 14 15 -1.01197858354723e-07 1.56359511392211e-08

    21 16 17 -8.35586841618415e-06 1.23570331144695e-06

    22 15 18 -.000102875012565942 1.71018303129115e-05

    23 18 19 -2.11151486575580e-05 3.51021581055078e-06

    24 19 20 -3.86353128575040e-06 3.51021581055078e-06

    25 10 20 -0.000118208007108670 1.99877337651416e-05

    26 10 17 -0.00407858966864019 0.000606189386310992

    27 10 21 -0.451710876271081 0.0713922481669822

    28 10 22 0 0

    29 21 22 0 0

    30 15 23 -4.92238355279217e-05 8.01072407001902e-06

    31 22 24 -.000982100994548929 0.000164976633443186

    32 23 24 -2.15948688895622e-06 3.55294032408022e-07

    33 24 25 0 0

    34 25 26 -4.93083082491196e-06 8.90526237374516e-07

    35 25 27 0 0

    36 28 27 0 0

    37 27 29 -6.82699456110101e-05 1.37196248158477e-05

    38 27 30 -0.00669484624381917 0.00150712030528960

    39 29 30 -0.000272858780586663 5.83462425139716e-05

    40 8 28 0 0

    41 6 26 0 0

  • 8/13/2019 Acc. No. DC 59

    54/67

    46

    Table 7.2:Optimum generation schedule

    Parameter Base Case (without UPFC) UPFC in line 27

    Generator 1 123.58+j4.03 124.64-j26.3Generator 2 55.26-j14.42 54.24-j10.32

    Generator 3 41.07-j4.35 40.02-j2.39

    Generator 4 12.78+j18.30 11.2+j29.26

    Generator 5 16.82-j39.20 15.76+j37.08

    Generator 6 16.89 -j23.14 15.85+j27.03

    VD(p.u) ------ 0.5

    !D(degree) ------ 5.72

    Iq(p.u) ------ 0.005

    Generation Cost (cents/h) 510.3976 499.8153

  • 8/13/2019 Acc. No. DC 59

    55/67

    47

    Table 7.3:Voltage and phase angle computed without UPFC

    Bus No. Voltage Magnitude (p.u) Phase angle (in degree)

    1 1.0500 0

    2 1.0338 -0.0388

    3 1.0245 -0.0835

    4 1.0181 -0.1000

    5 1.0058 -0.1295

    6 1.0140 -0.1192

    7 1.0025 -0.1328

    8 1.0230 -0.1272

    9 1.0001 -0.1258

    10 0.9728 -0.1844

    11 1.0713 -0.0870

    12 1.0040 -0.1690

    13 1.0400 -0.1422

    14 0.9807 -0.1868

    15 0.9807 -0.1885

    16 0.9831 -0.1806

    17 0.9701 -0.1874

    18 0.9650 -0.2008

    19 0.9589 -0.2044

    20 0.9616 -0.2005

    21 0.9249 -0.1964

    22 0.9643 -0.1890

    23 0.9699 -0.1969

    24 0.9643 -0.2014

    25 0.9853 -0.2037

    26 0.9671 -0.211627 1.0074 -0.1998

    28 1.0090 -0.1283

    29 0.9872 -0.2220

    30 0.9755 -02379

  • 8/13/2019 Acc. No. DC 59

    56/67

    48

    Table 7.4: Voltage and phase angle computed with UPFC

    Bus no. Voltage( in p.u) Phase angle (in degree)

    1 1.05 0

    2 1.0338 -0.03832

    3 1.027001 -0.08334

    4 1.021119 -0.09985

    5 1.0058 -0.12856

    6 1.017826 -0.11925

    7 1.004823 -0.13247

    8 1.023 -0.12618

    9 1.006625 -0.12577

    10 0.992189 -0.18266

    11 1.0813 -0.08754

    12 1.009206 -0.16608

    13 1.04 -0.1394

    14 0.993342 -0.18394

    15 0.987963 -0.18633

    16 0.994389 -0.17826

    17 0.987228 -0.1853418 0.976651 -0.19845

    19 0.973254 -0.20197

    20 0.977158 -0.19824

    21 0.975972 -0.19974

    22 0.977524 -0.19802

    23 0.976794 -0.19638

    24 0.970804 -0.20322

    25 0.99087 -0.20431

    26 0.972701 -0.21204

    27 1.012264 -0.1997

    28 1.012097 -0.12819

    29 0.992186 -0.22165

    30 0.980574 -0.23741

  • 8/13/2019 Acc. No. DC 59

    57/67

    49

    7.3 Graphical results

    The graph in fig. 7.1 and 7.2 shows the real power spot pricing tabulated with and

    without UPFC for each load buses.

    Fig. 7.1: Real power spot prices (cents/ MWhr) at load buses without UPFC

    Real power spot price at load buses without UPFC

    200202.5

    205

    207.5

    210

    212.5

    215

    217.5

    220

    222.5

    225

    227.5

    230

    0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30

    Bus number

    Spotprices(cents/MWh)

    Spot

    prices

  • 8/13/2019 Acc. No. DC 59

    58/67

    50

    Fig. 7.1: Real power spot prices (cents/MWhr) at load buses with UPFC

    Real power spot prices at load buses with UPFC at line-27

    200

    202.5

    205

    207.5

    210212.5

    215

    217.5

    220

    222.5

    225

    227.5

    230

    0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30

    Bus number

    Spotprices(cents/MWh)

    Spot

    prices

  • 8/13/2019 Acc. No. DC 59

    59/67

    51

    Chapter 8: CONCLUSION

    8.1 ConclusionIn this paper real power spot price has been calculated with and without implementing the

    FACTS device (UPFC). Here the OPF is solved in gradient method. Moreover a

    sensitivity based approach has been used for finding a suitable location to place UPFC.

    Test results obtained on test systems show that the new sensitivity factors could be

    effectively used for placement in response to required objectives. The placement of a

    UPFC in a particular line affects both the real power and reactive power prices. It can be

    concluded that by incorporating UPFC in the OPF model, significant reduction occurs in

    real power loss and generation cost.

    8.2 Future Scope

    Only real power pricing is dealt with in this paper. There are many approaches towards

    the reactive power pricing has also been done in recent years and in future with

    increasing demand of electric power and more competitive power market. The reactive

    power pricing should play an important role beside real power pricing. By knowing the

    bid price for the reactive power generation reactive power price can be determined after

    formulating a corresponding OPF for the reactive power.

  • 8/13/2019 Acc. No. DC 59

    60/67

    52

    REFERENCES

    [1]L.Gyugyi, T.Rietman , A.Edris, C. D. Schauda . S.L.Williams, The unified powerflow controller: A new approach to power transmission control, IEEE Transactions onPower Delivery, Vol. 10, No. 2, April 1995.

    [2] Jenn- Huei Jeffrey Kuan, Optimal power flow with price elastic demand, Thesis

    report ,dept. of Master of Science in Electrical Engineering, Massachusetts Institute ofTechnology, August 1996.

    [3] J. Y. Choi, S.-H. Rim, and J.-K. Park, Optimal real time pricing of real and reactive

    powers,IEEE Trans. Power System., vol. 3, no. 4, pp., 12261231, Nov. 1998.

    [4] J. W. Marangon Lima and E. J. de Oliveira, The long-term impact of transmission

    pricing,IEEE Trans. Power Syst., vol. 13, no. 4, pp.15141520, Nov. 1998.

    [5] J. Y. Liu and Y. H. Song, Comparison studies of unified power flow controller with

    static var compensators and phase shifters, Elect. Mach. Power Syst., vol. 27, pp. 237251, 1999.

    [6]J. Y. Liu, Y. H. Song, and P. A. Mehta, Strategies for handling UPFC constraints in

    the steady state power flow and voltage control,IEEE Trans. Power Syst., vol. 15, no. 2,pp. 566571, May 2000.

    [7]S. C. Srivastava and R. K. Verma, Impact of FACTS devices on transmission pricing

    in a de-regulated electricity market, in Proc. IEEE Int. Conf. Electric UtilityDeregulation Restructuring Power Technologies, London, U.K., Apr. 2000, pp. 642648.

    [8] K. S. Verma, S. N. Singh, and H. O. Gupta, Optimal location of UPFC for

    congestion management,Elect. Power Syst. Res., vol. 58, no. 2, pp. 8996, Jul. 2001.

    [9]-----, FACTS device location for enhancement of total transfer capability, in Proc.IEEE Power Eng. Soc.Winter Meeting, vol. 2, Columbus, OH, pp. 522527, Jan. 28Feb.

    1 2001.[10]-----,Location of UPFC for power systems security in deregulated environment,

    inProc. Int. Conf. EAIT-2001. Kharagpur , West Bengal, Dec. 2001, pp. 149154.

    [11] S. N. Singh, K. S. Verma , and H. O. Gupta, Optimal power flow control in openpower market using unified power flow controller, in Proc. IEEE Power Eng. Soc.

    Summer Meeting, vol. 3, Vancouver, BC, Canada, Jul. 1519, 2001, pp. 16981703.

    [12] K.S. Verma and H.O.Gupta, Impact on real and reactive power pricing in openpower market using unified power flow controller, Trans. On power systems, vol. 21,

    no. 1, February 2006.

  • 8/13/2019 Acc. No. DC 59

    61/67

    53

    [13] Abdullah Urkmez, Determined spot price and economic dispatch in deregulatedpower systems, Mathematical and Computational Applications, Vol. 15, No. 1, pp. 25-

    33, 2010.

    [14] A. J. Wood and B. F. Wollenberg, Power Generation, Operation, and Control,

    2nd edn. Wiley India (P) Ltd., New Delhi, 2007.

    [15] K.S.Pandya, S.K.Joshi, A survey of optimal power flow methods, Journal of

    Theoretical and Applied Information Technology.

    [16] J.A. Momoh, J.Z. Zhu, Improved interior point method for OPF problem,IEEETransactions on Power Systems, Vol. 14, No. 3, August 1999.

    [17] Jaco F. Schutte, The particles swarm optimization algorithm, EGM 6365 -

    Structural Optimization, Fall 2005.

    [18] www.wikipedia.com

    [19] Hingorani N.G. and Gyugyi L., Understanding FACTS: concepts and technologyof flexible ac transmission systems.New York: IEEE Press; 1999.

    [20] Xiao-Ping Zhang, Edmund Handschin, Transfer capability computation of powersystems with comprehensive modeling of FACTS controllers, 14thPSCC,Sevilla, Section 30.paper 2, page no. 1-4, 24-28 June, 2002.

    [21] D. P. Kothari and J. S. Dhillon, Power System Optimization,Prentice Hall ofIndia Pvt. Ltd., New Delhi, 2006.

    [22] L. Gyugyi, A unified power flow control concept for flexible AC transmissionsystems,Proc. Inst. Elect. Eng., pt. C, vol. 39, no. 4, pp. 323331, Jul. 1992.

    [23]The IEEE 30bus test system available at:http://ee.washington.edu/research/pstca/pf30/pg_tca30bus.htm

    http://www.wikipedia.com/http://ee.washington.edu/research/pstca/pf30/pg_tca30bus.htmhttp://ee.washington.edu/research/pstca/pf30/pg_tca30bus.htmhttp://www.wikipedia.com/
  • 8/13/2019 Acc. No. DC 59

    62/67

    54

    NOMENCLATURE

    iC Bid price of pool generator-i.

    pi Active power of pool generator-i

    jB Bid price of pool load-j

    pj Active power of pool load-j

    GI Set of pool generator buses

    DI Set of pool load buses

    DV Voltage magnitude of UPFC series controller

    D Phase angle magnitude of UPFC series controller

    qI Shunt current

    gi Generated active power at bus-i

    iQ Generated reactive power at bus-i

    di Active power demand at bus-i

    diQ Reactive power demand at bus-i

    bN Total number of buseslN Total number of lines

    qN Number of reactive power sources

    iV Bus voltage magnitude at bus-i

    i Phase angle at bus-i

    mingiP Minimum active power generation limit at bus-i

    maxgiP Maximum active power generation limit at bus-i

    mingiQ Minimum reactive power generation limit at bus-i

    maxgiQ Maximum reactive power generation limit at bus-i

  • 8/13/2019 Acc. No. DC 59

    63/67

    55

    APPENDIX

    Table A.1:Generator data

    Bus no. Pgmin(MW) Pgmax(MW)b(cent/MW-

    hr) c(cent/MW2-hr)

    1 50 200 2 0.00375

    2 20 80 1.75 0.0175

    5 15 50 1 0.0625

    8 10 35 3.25 0.00834

    11 10 30 3 0.025

    13 12 40 3 0.025

  • 8/13/2019 Acc. No. DC 59

    64/67

    56

    Table A.2: IEEE 30 bus characteristics

    BusNo.

    Active powerdemand(MW)

    Reactive powerdemand(MVAR)

    Bus voltagemagnitude(in p.u)

    Bus voltageangle

    Yshunt

    1 0 0 1.05 0 0

    2 21.70 12.70 1.0338 0 0

    3 2.40 1.20 1.0 0 0

    4 7.60 1.60 1.1.00580 0 0

    5 94.20 19.00 1.0 0 0

    6 0 0 1.0 0 0

    7 22.80 10.90 1.0230 0 0

    8 30.00 30.00 1.0 0 09 0 0 1.0 0 0

    10 11.9 2.00 1.0913 0 00

    11 0 0 1.0883 0 0.19

    12 11.2 7.50 1.10 0 0

    13 0 0 1.0 0 0

    14 6.20 1.60 1.0 0 0

    15 8.20 2.50 1.0 0 0

    16 3.50 1.80 1.0 0 0

    17 9.00 5.80 1.0 0 0

    18 3.20 0.90 1.0 0 0

    19 9.50 3.40 1.0 0 0

    20 2.20 0.70 1.0 0 0

    21 34.3 11.20 1.0 0 0

    22 0 0 1.0 0 0

    23 3.20 1.60 1.0 0 0

    24 8.70 6.70 1.0 0 0.04

    25 0 0 1.0 0 0

    26 3.50 2.30 1.0 0 0

    27 0 0 1.0 0 0

    28 0 0 1.0 0 0

    29 2.40 0.90 1.0 0 0

    30 10.60 1.90 1.0 0 0

  • 8/13/2019 Acc. No. DC 59

    65/67

  • 8/13/2019 Acc. No. DC 59

    66/67

    58

    Fig. A1:Single line diagram of IEEE 30-bus system [23]

  • 8/13/2019 Acc. No. DC 59

    67/67