18
ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP Australian Coal Association Research Program Australian Coal Association Research Program

ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

Embed Size (px)

Citation preview

Page 1: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP

KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY

Gary Gibson, ACARP

Australian Coal Association Research ProgramAustralian Coal Association Research Program

Page 2: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 2

DECEMBER 2006 BENCHMAKING STUDY

Angus Place

Appin

Ashton

Austar

Baal Bone

Beltana

Broadmeadow

Crinum

Dendrobium

Douglas

Grasstree

Kestrel

Manadalong

Metropolitan

Moranbah North

Newlands North

Newpac No 1

Newstan

North Goonyella

Oaky No 1

Oaky North

Tahmoor

Ulan

United

West Cliff

West Wallsend

BENCHMARKING STUDY 6 MONTHS TO END DECEMBER 2006 - STATUS REPORT

Page 3: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 3

DECEMBER 2006 BENCHMAKING STUDY

Findings now to be separately reported to respondents and workshop participants, with close-off of responses 6 April 2007

Page 4: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 4

JULY 2006 BENCHMAKING STUDY

July 2006 Roadway Development Benchmarking Study

Only 15 mines responded of 26 mines surveyed Data provided for 36 continuous miner units, with

performance data provided for only 24 of those units Data analysed by UOW undergraduate mining engineer

as part of research thesis

Some interesting relationships were highlighted in the data, however broader participation required from industry to enable those relationships to be tested and quantified

Figures over show some of the relationships indicated by July 2006 survey

Page 5: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 5

JULY 2006 BENCHMAKING STUDY

“Continuous Miner Units achieving more than 1,750 m” highlighted. Figure 1 shows that “Depth of Cover” has little affect on metres achieved

0

1000

2000

3000

4000

5000

Act

ual m

etre

s

100 150 200 250 300 350 400 450 500

Typical Depth (m)

Page 6: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 6

JULY 2006 BENCHMAKING STUDY

Figure 2 demonstrates that all units mining greater than 1,750 m in the period were mining two-heading gateroads

Act

ual m

etre

s

0

1000

2000

3000

4000

5000

1 2 4 5

Number of Headings

Page 7: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 7

JULY 2006 BENCHMAKING STUDY

Figure 3 illustrates the benefit of having six bolting rigs mounted on the continuous miner (ie; 4 roof and 2 rib bolting

rigs).

Act

ual m

etre

s

0

1000

2000

3000

4000

5000

0 2 4 6

Total Number of Rigs

Page 8: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 8

JULY 2006 BENCHMAKING STUDY

Installing 1500 mm rib bolts also appears to limit development rates, with those continuous miners achieving higher production levels all installing 1200 mm rib bolts

Act

ual m

etre

s

0

1000

2000

3000

4000

5000

1.2 1.5

Rib Bolt Length (m)

Page 9: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 9

JULY 2006 BENCHMAKING STUDY

Installing 1500 mm rib bolts also appears to limit development rates, with those continuous miners achieving higher production levels all installing 1200 mm rib bolts

Act

ual m

etre

s

0

1000

2000

3000

4000

5000

1.2 1.5

Rib Bolt Length (m)

Page 10: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 10

JULY 2006 BENCHMAKING STUDY

“Continuous Miner Units that achieved less than 1,000 m”, Figure 6 shows that with the exception of one Eimco Dash 3, the continuous

miner units that achieved less than 1,000 m were all Joy 12CM30

Act

ual m

etre

s

0

1000

2000

3000

4000

5000

Eimco Dash 3 Joy 12CM12 Joy 12CM30 VAMT ABM-20 VAMT ABM-25

Continuous Miner

Page 11: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 11

JULY 2006 BENCHMAKING STUDY

However “mines producing less than 1,000 m” were all installing 2100 mm roof bolts.

Act

ual m

etre

s

0

1000

2000

3000

4000

5000

1.8 2.1 2.4

Roof Bolt Length (m)

Page 12: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 12

JULY 2006 BENCHMAKING STUDY

However “mines producing less than 1,000 m” were all installing 2100 mm roof bolts, and were only utilising 2 bolting rigs.

Act

ual m

etre

s

0

1000

2000

3000

4000

5000

1.8 2.1 2.4

Roof Bolt Length (m)

Page 13: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 13

JULY 2006 BENCHMAKING STUDY

Figure 10 illustrates that the mains development units driving five-heading mains achieved less metres overall during the 3 month period than those units that drove four-heading mains.

Act

ual m

etre

s

0

1000

2000

3000

4000

5000

1 2 4 5

Number of Headings

Page 14: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 14

JULY 2006 BENCHMAKING STUDY

Figure 11 suggests that narrower pillars

may be a factor

0

1000

2000

3000

4000

5000

Act

ual m

etre

s

20 25 30 35 40 45 50

Heading Centres (m)

Page 15: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 15

JULY 2006 BENCHMAKING STUDY

Figure 12 shows that longer pillars may also contribute to improved development rates, a factor which is at odds with current beliefs and perceptions

0

1000

2000

3000

4000

5000

Act

ual m

etre

s

70 80 90 100 110 120 130 140

Cut Through Centes (m)

Page 16: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 16

JULY 2006 BENCHMAKING STUDY

Figure 13 again illustrates the potential effect of increasing the number of roof bolting rigs on the continuous miner

Act

ual m

etre

s

0

1000

2000

3000

4000

5000

0 2 4

Number of Roof Bolting Rigs

Page 17: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 17

JULY 2006 BENCHMAKING STUDY

Figure 14 illustrated that higher roof bolting densities didn’t necessarily slow development rates, which suggested a strong relationship between bolting density and the number of bolting rigs actually fitted

Act

ual m

etre

s

0

1000

2000

3000

4000

5000

4 6 8

Number of Roof Bolts/Cycle

Page 18: ACARP KEY FINDINGS - DECEMBER 2006 BENCHMARKING STUDY Gary Gibson, ACARP

ACARP Project C15005 18

DECEMBER 2006 BENCHMAKING STUDY

PRELIMINARY PERFORMANCE DATA

0

1

2

3

4

5

6

10 20 30 40 50 60 70 80 90

Operating Hours per Week

Met

res

per

Ope

ratin

g H

our

Metres/Operating Hour SingleCM Units

Metres/Operating HourDual/Super Units

Metres/Operating Hour SingleCM within Dual Units