ABP/RTL. Main RTL Activities for 2007/8:- Shutdown Co-ordination and Planning for PSB, PS, LEIR, TT2, AD, SPS, TT40 & TI8 CTF3 and CLEX installation 3 MeV test stand installation LHC Installation (Including TI2) Preparation for LINAC4 construction AB Consolidation project - PowerPoint PPT Presentation
Citation preview
1/6/20071/6/2007 ABP group meeting ABP group meeting
ABP/RTLABP/RTL
• Main RTL Activities for 2007/8:-– Shutdown Co-ordination and Planning for
PSB, PS, LEIR, TT2, AD, SPS, TT40 & TI8– CTF3 and CLEX installation – 3 MeV test stand installation– LHC Installation (Including TI2)– Preparation for LINAC4 construction– AB Consolidation project – TSO support for accelerators and service
buildings
1/6/20071/6/2007 ABP group meeting ABP group meeting
ABP/RTLABP/RTL
Simon Baird Section Leader & AB ConsolidationRaymond Brown PS Sven De Man PSB & LHC Installation Nicolas Gilbert SPS, TT40, TI2 & TI8Christian Lacroix LEIR, TT2, AD & 3MeV test standJosé Monteiro CTF3, CLEX* & Planning supportBernard Pires SPS Surface buildings Rosario Principe PS, 3MeV test stand & LINAC4Michel Samson SPS, TI2 installation, AB Space
Management for ADM* (CLIC Experimental Area)
1/6/20071/6/2007 ABP group meeting ABP group meeting
Shutdown/Installation Co-ordinationShutdown/Installation Co-ordination• 2006/7 Shutdown
– 8 PS main magnets renovated & re-installed– Some MTE preparatory work was completed but
the main MTE work will still take place in the 2007/8 shutdown
– 76 SPS main magnet water manifolds repaired – INB cable loop installed at the SPS– Major tunnel repairs in TT2– New beam stopper in BTP line– PSB main magnet water cooling renovation– CTF3 Combiner ring ejection line completed– CLEX building completed (June 07)
1/6/20071/6/2007 ABP group meeting ABP group meeting
Shutdown/Installation Co-ordinationShutdown/Installation Co-ordination• 2007/8 Shutdown (Minimum length = 12
weeks)– MTE installation
• Essential for full CNGS beam operation– PS Main magnet renovation (8 units?)– SPS main magnet manifold repairs (80 planned)– Move 8 PSB wire scanners?– 3MeV test stand installation
• CTF– Installation of CLEX equipment– Installation of the TL2 line (from the Combiner Ring to
the CLEX)• LINAC4
– Choice of site– Technical coordination for the project
1/6/20071/6/2007 ABP group meeting ABP group meeting
• AB Consolidation– There are 44 active Work Units in 2007
• By the end of 2007 a total of 36.8 MCHF will/should have been spent (total budget at present is 50 MCHF )
– A full review of all outstanding Consolidation items has been completed:-
• White Paper request for 27 MCHF & 70 FTE’s• Waiting for the “green light”
• TSO’s for Accelerators and the Service Buildings
• LHC activities– One RTL section member is detached (60%) to TS for the
Coordination of LHC installation activities– TI2 installation and commissioning coordination– No decision on “How an LHC shutdown will be managed”