Oil Refineries upgrading Program
For the production of clean fuels
In Algeria
OPAEP Symposium – Bahrain – Oct 25th to 27th - 2010
SONATRACH – Downstream Activities
Refining Division
2
CONTENTS
1. Crude refining activity in Algeria
Existing facilities for each refinery.
Present scheme for production of gasoline and Diesel
2. Present status of motor fuels in Algeria
3. Rehabilitation and adaptation program
Principles and objectives .
History of actions .
Program for each refinery.
Future Lay outs.
4. Present status for each project
5. Other projects to be implemented
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
1- Crude Refining
Activity
In Algeria
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Skikda
Hassi Messaoud
In Aménas
2,5 MMT1973 et 1984
2,7 MMT1964
15 MMT1980
1,2 MMT1979
0,3 MMT1980
Motor fuels
Lub-oil Bitumen Aromatics
Arzew
Existing Refineries
Algiers Refinery
Location: 10 Km South of Algiers (on 200 Ha)
Final Products: Motor Fuels and LPG (For Local Market)
Naphtha et fuel oil (For Export)
Shipment: trucks (LPG)
pipelines
sea vessels
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
BLOCK FLOW DIAGRAM - ALGIERS REFINERY
To
pp
ing
Un
it
STA
BIL
ISA
TIO
N
Ga
s-
Pla
nt
Gasoline
Blending
Gas - oil
Blending
RESIDU
LPG
LPG
LPG
REFORMATE
Light Naphtha
Heavy Naphtha
KEROSENE
LGO
HGO
Cru
de.
2700.0
00
FUEL-GAZ
PROPANE
BUTANE
RegularGasolin
e
Premium
Gasoline
NAPHTHA
JET
DIESEL
Fuel - oil
(LS)
RE
FO
RM
ING
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
view of Algiers Refinery
Arzew Refinery
Location: Industrial Area in Arzew (150 Ha)
Final Products: Motor Fuels + LPG + Bitumen
(For Local Market)
Lubricants (For Local Market
and Export )
Naphtha and Fuel-oil (For Export)
Shipment: by trucks
pipelines
sea vessels
rail way
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Existing Refineries
BLOCK FLOW DIAGRAM - ARZEW REFINERY
TO
PP
ING
UN
IT
Cru
de 2,5
M
LPG
Light Naphta
LPG
Heavy Naphtha
KEROSENE
LGO
HGO
Gas - oil
Blending
Gasoline
Blending
FUEL
GAZ
PROPANE
BUTAN
E
NAPHTH
A
Regular Gasoline
Premium gasoline
JET
DIESEL
Fuel - oil (LS)
Oxydised Bitumen
Fuel - oil (HS)
Road Bitumen
RE
FO
RM
ING
CA
TA
LY
TIQ
UE
Gas P
lan
t
ST
AB
ILIS
AT
ION
ES
SE
NC
ES
Blo
win
s
Un
it
Vacu
um
Dis
till
ati
on
Imp
ort
ed
Red
uced
Cru
de
278.8
00 T
Lub 1
Lub 2
Lube
Blending
EXPORT
Lubes
Grease
Wax
Base Oils
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
view of Arzew Refinery
Skikda Refinery
Location : Industrial Area in Skikda, Land Area 190 Ha
Final Products : LPG + bitumen (For Local Market)
Motor Fuels (For Local Market
and Export)
Fuel-oil (For Local Market
and Export) and
Naphtha (For Export)
Aromatics(For Local market
and Export)
Shipment: by trucks (for Bitumen & Toluene))pipelines (Motor Fuels, LPG)sea vessels
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Existing Refineries
To
pp
ing
un
ts (
2)
GAS-PLANT
(3units)
Kerosene
Sweetening
PX
Cri
sta
llis
ati
o
n
Gasoline
blending
Gas - oil
Blending
FUEL-GAZ
PROPANE
BUTANE
NAPHTHA
BENZENE
TOLUENE
Regular Gasoline
Premium Gasoline
Unleaded Gasoline
MELANGE-XYLENES
PARA-XYLENE
JET A1
DIESEL
Fuel - oil (LS)
Fuel - oil (HS)
Oxydised Bitumen
Road Bitumen
Cru
de
Imp
ort
ed
Red
uc
ed
Cru
de
BLOCK FLOW DIAGRAM - SKIKDA REFINERY
277.1
00
RE
FO
RM
ING
CA
TA
LY
TIQ
UE
(2 u
nit
s)
BT
Ex
tra
cti
on
Va
cu
uu
m
Dis
till
ati
on
Blo
win
g
Un
it
15.0
00.0
00
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
view of Skikda Refinery
Hassi-Messaoud Nr 1 & 2 Refineries
Location: South Industrial Center (SH-DP)
Final Products: Motor fuels (For Local Market)
Shipment: trucks
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Existing Refineries
BLOCK FLOW DIAGRAM - HASSI-MESSAOUD REFINERIES
1. HASSI-MESSAOUD 1
2. HASSI-MESSAOUD 2
STA
BIL
IS.
T
O
P
P
I
N
G
Crude
LPG
RHM2
LPG
Unit
FUEL.GAS.
BUTANE
NAPHTHA
JET
DIESEL
RESIDU
T
O
P
P
I
N
G
R
E
F
O
R
M
I
N
G
Gasoline
Blending
G P LUNIT LPG/RHM1
NAPHTHASLOPS
REFORMATE
Regular gasoline
Premium Gasoline
JET
DIESEL
RESIDU TO SLOPS
Crude
10
0.0
00
In-Amenas Refinery
Location: Industrial Area of In- Amenas (SH-DP))
Final Products: Motor Fuels (For Local market)
Shipment: by Trucks
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Existing Refineries
Crude
300.00
0
MTA
Fuel-Oil
Naphtha
Kerosen
eDiesel
T
O
P
P
I
N
G
Gasoline Blending
sweetening
Fuel-
Gaz
JET
Diesel
Slops
Vers Slops
Regular
Gasoline
Premium
Gasoline
BLOCK FLOW DIAGRAM - IN AMENAS REFINERY
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
2- Present status
of Motor fuels
in Algeria
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Present status of motor fuels in Algeria
Gasoline
At the present time the local market consumption is about 2,3
million Tons/Year of gasoline including 3 types:
Regular leaded gasoline RON 89 (20 % of the market),
Premium leaded gasoline RON 96 (70 % of the market),
Unleaded gasoline RON 95/MON 85 (10 % of the market),
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Leaded Gasoline Specifications for the local market
Specification Unit Regular Gasoline
Premium Gasoline
Specific gravity Kg/m3 710 – 765 730 – 770
RON 89 96
RVP up to 37.7 °C (summer/winter)
Max Bar 0.65 / 0.80 0.65 / 0.80
10 % vol 70°C max 70°C max
50 % vol 140°C max 140°C max
95 % vol 195°C max 195°C max
Distillation ASTM D86
PF 205°C max 205°C max
Sulphur content ppm 100 max 100 max
Lead content g/l 0.40 0.40
Limits Premium 95 Specs Units
Min Max
RON
MON
95
85
Benzene % Vol 5
Specific gravity Kg/m3 725 780
Sulphur ppm 100
Distillation ASTM 86 70°C 100°C 180°C
210°C Final Poi nt
% Vol
15 40 85
90
47 70
215
Reid Vapor Pressure Winter / Summer
Kpa
80 / 65
Unleaded Gasoline Spécifications for the local market
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Comments:
The specification of unleaded gasoline in Algeria doesn’t
mention any limit for aromatics, olefins and oxygen ( the
unleaded gasoline RON 95, is similar to leaded premium
gasoline RON 96, with a quite wide gravity gap).
The benzene content is limited to 5 % vol. (means in
the limit of the skikda refinery production quality)
Gasoline Status in Algeria (cntd)
Unleaded gasoline specifications (cntd)
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Gasoline Status in Algeria (cntd) Gasoline Average Qualities for the Local Market
lead content was reduced by the Regulation from 0.65 to
0.40 g/l. max, from the year 2000
According to the regional demand of gasoline and the
available basestocks in each refinery for gasoline
blending, lead content at the present time is as follows:
0.10 to 0.15 g/l at Skikda refinery,
0.20 to 0.30 g/l at Arzew,
0.40 g/l at both Algiers and Hassi-Messaoud
refineries.
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Sulphur average content : less than 30 ppm (due to
good crude quality and good quality of basestocks),
Aromatics content : 50 to 60 % vol. (due to use of
reformate or aromatic byproducts as basestocks),
Benzene content : 2 to 3 % vol.
Gasoline status in Algeria (cntd.)
Gasoline Average Qualities / Local Market (cntd.)
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Gasoline blending
Butane
Light Naphta
Reformate
Raw Toluene
Heavy aromatics
rafinate
Leaded Regular
RON 89
leaded Premium
RON 96
Typical scheme for gasoline blending in Algeria
Unleaded
Gasoline
RON 95
Isopentane
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Basestocks for gasoline blending for local market
RA1K RA1G RA1Z RHM2
Butane X X X
Light Naphta X X X X
Naphta ex-deIsoC5 X
Reformate X X X X
Iso-pentane X
Pentane ex-Reformate
X
Raffinate X
Raw Toluene X
Heavy aromatics. X
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
The Algerian market consumes currently up to 7 millions Tons / year of Diesel
Specification Unit Gasoil
Specific density Kg/m3 810 – 860
Cetane number 48 min
Flash point °C 55 min
Pour point /winter. °C -12 max
Pour point /summer. °C -7 max
65 % vol 250°C min
90 % vol 350°C max Distillation ASTM D86
PF 390°C max
Sulphur content ppm 1 500 max
Diesel fuel :
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Diesel status as fuel in Algeria .(cntd.)
Average quality of diesel / Local market
Real sulphur contents :
Less than 800 ppm at Skikda,
Between 900 to 1200 ppm at the other refineries.
Nota:
Before Year 2005, Skikda refinery has produced Diesel for
export (in the limit of 350 ppm max sulphur content ) from SR
Gas-oil mixed with kerosene.
This was achieved with an adequate selection of crude fields to
feed the refinery (less than 500 ppm of sulphur).
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Gas-oil blending
SR Light Gas-oil
SR Heavy Gas-oil
Vacuum Gas-oil
Diesel
SR Kerosene
Typical scheme for Diesel blending in Algeria
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Basestocks for Diesel production for Local Market
RA1K RA1G RA1Z RHM2
SR Kerosene X X X X
SR Light Gas-oil X X X
X
SR Heavy Gas-oil X X
Vacuum Gas-oil X
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
3- Rehabilitation
And Adaptation Program
of the existing Facilities
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Main objectives of the Rehabilitation
and Adaptation Program
Proceed with a large refurbishment program in order to sustain the production level of the refineries for the medium and long term,
Modernize the instrumentation for a better
optimization of the various Units,
Produce clean fuels for the local market and for export, for a better environment
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
33
This program deals with the achievement through the company own means
and other specialized companies in the sector of tehnical diagnosis studies,
debottlenecking of process Units and definition of the master plan of the
instrumentation modernization.
From October 2001 to March 2003, we worked after an open tender for
each subject:
For Skikda Refinery: with Foster Wheeler France (for the process and
technical study and instrumentation study)
For Arzew Refinery: with KBR (USA) and Honeywell-Belgium,
For Algiers Refinery: with Sofresid (France) and Foxboro-France
For Hassi-Messaoud Refinery: with the same two companies
History of the activities
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
1. Evaluation of the various reports and options proposed by the
consultancy companies
Selection of the options to be implemented in each refinery
Identification of all the small projects which do not need deep
engineering work, in order to implement them immediately
Agglomerate all the other subjects in one, two, or three major
EPC projects, including capacity increase
Minimize the shutdown duration for construction and tie-ins
History of activities (ctnd)
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
2. Issuance of call for tenders for selection of consultancy companies (one
for each refinery) which will be involved in three stages :
Preparation of FEED package,
Technical support for the evaluation of the bids to be received for
the EPC projects,
Follow up of projects by the consultancy companies
History of activities (ctnd)
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
The rehabilitation program will be implemented simultaneously
in the three coastal refineries,
Shutdowns of existing units will be minimized for the
rehabilitation work,
The normal investment program for maintenance purposes will
be continued in parallel at each refinery,
Rehabilitation Program for each Refinery
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Skikda Refinery
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Revamp and Expansion• Existing CDUs/ Gas Plants with 10% capacity increase
•Add / Modify existing utilities / offsite facilities.
MODERNISATION
• Of the Instrumentation with
DCS / APC/Optimisation type
.New Blast Resistant
Control Room.
• Electrical network with
ECS .
RECONFIGURATION
• Revamp of Reformer Nr 1
• Reconfiguration of aromatics
chain (revamp of the Benzene
/Toluene recovery unit
• Addition of a cristallization
unit and a mixed xylene
isomerisation unit
CLEAN FUELS
• 02 New NHT/ light naphta isom Units
• 02 New DHDS Units
Rehabilitation
Program
The rehabilitation and adaptation program includes three main EPC
projects:
Project 1: Electrical network for common facilities,
Project 2: Rehabilitation and increase capacitiy for fire fighting network,
Project 3: includes the following operations,
Rehabilitation of existing facilities (Toppings and gas-plants) for the
treatment of the future crude (with upgrading and modernisation of
obsolete equipments),
Rehabilitation and upgrading of Magnaforming Unit,
Upgrading of aromatics production units, with production
maximisation (supply by the two reformings, and setting up of xylene
isomérisation unit) with upholding a significant production of gasoline
Rehabilitation of Utilities production and distribution,
Rehabilitation and modernization of electrical equipments, upgrading
Rehabilitation program of Skikda refinery
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Achievement of two Units for light naphta isomerisation,
Rehabilitation of electrical equipments, upgrading of electrical
network ,
Achievement of two Hot Oil systems,
Achievement of new unit for hydrogen purification,
Achievement of new unit for demineralizing Boiler Water,
Achievement of a unit for condensat recovery and treatment,
Instrumentation modernization (implementation of DCS with a
centralized control room),
Upgrading of the Quality control laboratory,
Rehabilitation program of Skikda refinery (cntd)
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Achievement of a new unit for acid water treatment
Achievement of a new unit for effluent treatment
Achievement of new unit for nitrogen production,
Laying out and extension of various reception, storage,
shipping facilities of oil products,
Rehabilitation program of Skikda refinery (cntd)
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Arzew Refinery
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Revamping• Existing CDU/ Gas Plants for 50% higher crude oil processing capacity
•Add / Modify existing utilities / offsite facilities.
MODERNISATION
• Of the Instrumentation with
DCS / APC/Optimisation type
.Main opérating
Central Room.
• Of the Electrical network with
ECS type.
ADAPTATION FUELS
•01 New Unit for Isomerization
Gasoline to improve the
LSRN characteristics
•01 New Unit for Diesel
Hydrodesulphurized
Rehabilitation
Programme
The rehabilitation and adaptation program includes three major EPCprojects
Project 1: Instrumentation modernisation (implementation of DCS + APC
+ optimisation with a centralized control room),
Project 2: Rehabilitation of electrical equipments, upgrading of electrical
network
Project 3: Main EPCC
Capacity increase for Topping and Gas plant,
Adaptation for utilities and storage units,
Adaptation and modernization of effluent treatment unit,
Setting up of Hot Oil unit,
Setting up of light naphta isomerisation unit,
Setting up of gas turbine for electricity production,
Rehabilitation program of Arzew refinery
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Algiers Refinery
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Revamping• Existing CDU/ Gas Plants for 35% higher crude oil processing capacity
•Add / Modify existing utilities / offsite facilities.
MODERNISATION
• Of the Instrumentation with
DCS / APC/Optimisation type
.Main opérating Central Room.
• Of the Electrical network with
ECS type.
RECONFIGURATION
• New Reforming Unit (CCR mode).
• New RFCC Unit for the gasoline
and Diesel production.
ADAPTATION FUELS
•01 New Unit for Isomerization Gasoline to improve the
LSRN characteristics
•01 New Unit for clean Diesel
Rehabilitation
Programm
The rehabilitation and adaptation program includes one large EPCproject:
Topping and gas plant capacity increase.
New MS Block (NHT + Isom + CCR Reforming)
RFCC and Merox Units
Rehabilitation of Utility production and distribution facilities
MOderniztion of the Instrumentation (implementation of DCS with a
centralized control room),
Rehabilitation of electrical equipments , upgrading of electrical network, and
setting up of a gas turbine,
New Waste Water Treatment Unit (biological type)
Rehabilitation program of Algiers refinery
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Opérations included in one large EPC project:
Rehabilitation of existing facilities (Topping Unit and Reforming Unit with a
new catalyst).
Rehabilitation of the Utility production facilities and distribution network,
Rehabilitation of electrical equipments, upgrade of electrical network.
Instrumentation modernization ( DCS with a blast resistant control room),
Rehabilitation of underground piping
Rehabilitation program of Hassi Messaoud refinery
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
future configuration
of the refineries
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
GP – I
BBU
KTU-I
CD
U -
I
LNHT-I/
LNISOM-I
LNHT-II/
LNISOM-II
DHDS-I
DHDS-II
GP – II
NHDS/
REFORM-I/
PLAT SPL
NHDS/
REFORM-II
ARU
PX
REC.
UNIT
KTU-II
XYL-ISOM
UNIT
CD
U -
II
IMPORTED
VAC. RESIDUE
GAS OIL
OXIDISED BITUMEN
ROAD BITUMEN
GP – III
CRUDE
RC
O
LOW SULPHUR FO
KERO
KERO
PROPANE
BUTANE
LG
O+
HG
O
PARAXYLENE
RC
OLPG
TO GASOLINE POOL
TO ATF POOL
BENZENE
TOLUENE
LGO
HGO
NAP B
NAP A
C6 CUT
C8+ CUT
TOLU. CUT
CR KERO TO DIESEL POOL
HY. AROM.
HY
. A
RO
M.
C5
CUT
NAP B
NAP A
C6 CUT
PROPANE
BUTANE
C6 CUT
LPG
C6 C
UT
TO DIESEL POOL
EXCESS
KERO
TO NAPHTHA POOL
ISO PENTANE
PSA
FG
H2 TO CONSUMERSH2 RICH GAS
H2 RICH
GAS TO PSA
HY ARO. TO GASOLINE
TO NAPHTHA POOL
CR LGO TO DHDS
CR HGO TO DHDS
EXCESS C8+ TO GASOLINE
NAP C
NAP C
LP
G
Future configuration of Skikda Refinery
EXISTING REVAMP NEWLEGENDE DES COULEURS PAGE 50
CDU
STAB.2
14 346
BPSD
LSRN 2
HSRN 2
HSRN 1
LSRN 1 STAB.1
18 982 BPSD
FUTURGas Plant
6 289 BPSD
KERO
LGO
HGO
VGO LUB
REHABILITATION ET ADAPTATION
DIESEL
HDS
36500 BPSD
Isomerisation
7500 BPSD
BHM 90 000BPSD
Propane
Butane
Naphta
Ess.Super
Ess.NormaleUnibon Platformer
8500 BPSD
Brut Résidu Atmosphérique
Kérosène
Gasoil
Fuel BTS
Arzew Refinery
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Future configuration of Algiers Refinery
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
4- Present status
of the rehabilitation
Program
at each refinery
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
For RA1K:
Project 1: Modernization of electricity
Contractor: AREVA (France) started on March 30th 2008
Physical progress : 85%
Project 2: Rehabilitation and capacity increase of fire fighting network.
Contractor: ETTERKIB (Algeria) started on February 23rd 2008
Physical progress: 77%
Project3: Rehabilitation and adaptation of production facilities.
Contractor: SAMSUNG Engineering (South Korea) started on
August 13th 2009
Physical progress: 28%
Present status of the rehabilitation program at Skikda refinery
.
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
For RA1Z:
Project 1: Instrumentation modernization,
Contractor: Honeywell (Belgium), started on February 9th,2004
Physical progress : 98%.
Project 2:Electricity modernization.
Contractor: CEGELEC SAS (France), started on March 1st 2008
Physical progress: 92% .
Project 3: Rehabilitation and adaptation of production facilities.
Contractor: Groupement HYUNDAI Eng & Co Ltd / HANWHA /
DAEWOO started on February 23rd, 2009.
Physical progress: 39%.
Present status of the rehabilitation program at Arzew refinery
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
For RA1G:
Contractor : TECHNIP France.
Physical Progress: to be launched soon.
For RHM2:
The adaptation and rehabilitation program will be conducted
according to the following planning:
Consultation for PMC: 6 months: April 2011.
FEED studies: 15 months : June 2012.
Consultation for EPC: 12 months : July 2013.
Realisation EPC: 48 months :August 2017.
Present status of the rehabilitation program at both Algiers
& Hassi-Messaoud refineries .
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Work completion:
End of 2011 for Arzew
End of 2012 for Skikda
End of 2013 for Algiers
August 2017 for Hassi-Messaoud
Present status of the rehabilitation program at each refinery
.
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
5- Other projets
to be implemented
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010
Other projects to be implemented :
new Refining at Hassi-Messaoud Area and
rehabilitation of RHM 2 (Call for tender for FEED
package)
Hydrocracking Unit at Skikda Area (Call for
tender for FEED package)
Naphta Aromizer for Aromatics production at
Skikda Area (Feasibility stage)
OAPEC Symposium - Bahrain - Oct 25 TH to 27 th - 2010