ABB REC 670 Synchrocheck

Embed Size (px)

Citation preview

  • 8/10/2019 ABB REC 670 Synchrocheck

    1/21

    1

    AB

    B

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Substation

    Automation Products

    Training

    Control IED

    REC 670

    Synchrocheck

  • 8/10/2019 ABB REC 670 Synchrocheck

    2/21

    2

    AB

    B

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Contents

    Synchrocheck and energizing check

    Application Functionality

    Voltage selection

    Function block

    Settings

    Interaction with apparatus control

  • 8/10/2019 ABB REC 670 Synchrocheck

    3/21

    3

    ABB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    The main purpose of the SCfunction is to provide control

    of the CB closing in order toprevent closing if conditionsfor synchronism are not

    detected.

    Synchrocheck (SC/VC) Application

  • 8/10/2019 ABB REC 670 Synchrocheck

    4/21

    4

    ABB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Synchronism Check

    , f, U and Uhigh

    are within set values

    SC/VC

    25

    AB

    ILoad

    UA UB

    UAL

    d

    dU

    Icap

  • 8/10/2019 ABB REC 670 Synchrocheck

    5/21

    5

    ABB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    The main purpose of the ECfunction is to facilitate the

    controlled re-connection ofdisconnected lines andbusses to energized lines and

    busses.

    Energizing Check Application

  • 8/10/2019 ABB REC 670 Synchrocheck

    6/21

    6

    ABB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Energizing Check

    The dead line and Live

    bus conditions arechecked.

    Uhigh and Ulow areverified

    SC/VC

    27

    AB

    ILoad

    UA UB

    Ulow

    Uhigh

    Inductive and Capacitive

    charging of dead line

  • 8/10/2019 ABB REC 670 Synchrocheck

    7/217

    ABB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Synchrocheck Voltage selection

    SYN1SYN1 SYN2

    1 U 1 U1 U

    IED

    3 U

    1 U

    3 U

    B2QB1Q

    UB1 UB2

    ULN1

    ULN1

    UB1 UB2

    LN1Q

    Single Breaker Double Breaker

    IED

  • 8/10/2019 ABB REC 670 Synchrocheck

    8/218

    ABB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Synchrocheck Voltage selection

    SYN1

    IED 1

    SYN1

    IED 2

    SYN1

    IED 3

    1 U

    1 U3 U

    3 U

    SYN1

    IED

    SYN2

    3 U

    1 U

    1 U

    1 U

    1 U

    1 U

    1 U

    1 U

    B2Q

    UB1UB2

    ULN1

    LN1Q

    LN2Q

    ULN2 UB2

    B1Q

  • 8/10/2019 ABB REC 670 Synchrocheck

    9/219

    ABB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Synchrocheck Voltage selection

    SYN1

    REC670

    SYN2

    SYN3

    3 U

    3 U

    1 U

    1 U

  • 8/10/2019 ABB REC 670 Synchrocheck

    10/2110

    A

    BB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Synchrocheck Function block

    Fuse fail on sel fuse

    Information that the voltageis included in the

    synchrocheck

    Information that the

    conditions for voltage, diff

    voltage phase angle diff etc

    are out of limit

    Conditions for AR

    Conditions for Man close

    Test conditions fulfilled

    DS Bus 1 at DB arrangement

    DS Bus 2 at DB arrangement

    DS Line at 1 1/2 arrangement

    DS alt Line at 1 1/2 arrangement

    Bus1 VT Fuse fail alt. OK

    Bus2 VT Fuse fail alt. OK

    Line 1 VT Fuse fail alt. OK

    Line 2 VT Fuse fail alt. OK

    Block inputs

    Analogue inputs

    Test mode inputs

  • 8/10/2019 ABB REC 670 Synchrocheck

    11/2111

    A

    BB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Synchrocheck CAP-config

  • 8/10/2019 ABB REC 670 Synchrocheck

    12/2112

    A

    BB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Synchrocheck CAP-config

  • 8/10/2019 ABB REC 670 Synchrocheck

    13/2113

    A

    BB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Synchrocheck CAP-config

  • 8/10/2019 ABB REC 670 Synchrocheck

    14/2114

    A

    BB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Synchrocheck CAP-config

  • 8/10/2019 ABB REC 670 Synchrocheck

    15/2115

    A

    BB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Synchrocheck PST

    Selection of measuring phase, wich can be a

    single-phase or phase-phase voltage

    Type of voltage selection

    Base voltage

    Compensation for a phase shift caused by a

    line transformer between the twomeasurement points for bus voltage and line

    voltage.

    Uratio=bus voltage/l ine voltage

    Compensation for voltage difference

  • 8/10/2019 ABB REC 670 Synchrocheck

    16/2116

    A

    BB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Synchrocheck - PST

    Setting for voltage difference between line andbus

    The frequency difference level

    The phase angle difference level

    Voltage level in relation to bus/line network

    voltage

    Timer delay settings is to ensure that the

    synchro check conditions remains constant

  • 8/10/2019 ABB REC 670 Synchrocheck

    17/2117

    A

    BB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Synchrocheck - PST

    Energizing directions

    Voltage level in relation to bus/line network

    voltage

    Timer delay settings is to ensure that the

    energ. check conditions remains constant

    Manual closing is enabled when DBDL

    conditions are detected

    Block the closing when the voltage is above

    the set value

  • 8/10/2019 ABB REC 670 Synchrocheck

    18/2118

    A

    BB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    REC670 can handle up to6 SC functions!

    Synchrocheck

  • 8/10/2019 ABB REC 670 Synchrocheck

    19/2119

    A

    BB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Synchrocheck & Apparatus Control

    SynchroCheck

    OR

    SCSWI SXCBR

    CLOSE

    SYNC_OK

    EXE_CL

    Synchronizingfunction

    .

    SY_INPRO

    START_SY

    CLOSE CB

    SECRSYN

    Interaction with synchrocheck and synchronizing functions

  • 8/10/2019 ABB REC 670 Synchrocheck

    20/2120

    A

    BB

    PowerTechnologiesAB,

    2005

    2005-03-04 Substation Automation Products Training

    Exercise time

    Exercise 10

    Synchrocheck and energizing check

  • 8/10/2019 ABB REC 670 Synchrocheck