© ABB Group November 13, 2014 | Slide 1
ABB in Azerbaijan Renewable Energy
AZERBAIJAN - SWITZERLAND BUSINESS CONFERENCE, Nov 11, 2014 Zurich Igor Almazov
ABB in the World Key Facts and Figures
© ABB Group
November 13, 2014 | Slide 2
A global leader in power and automation technologies Leading market positions in main businesses
+145,000 employees
Present
in
countries +100
Formed
in
1988 merger of Swiss (BBC, 1891)
and Swedish (ASEA, 1883)
engineering companies
In revenue
(2013)
billion 42 $
© ABB Group
November 13, 2014 | Slide 3
Power and productivity for a better world ABB’s vision
As one of the world’s leading engineering companies, we
help our customers to use electrical power efficiently, to
increase industrial productivity and to lower environmental
impact in a sustainable way.
© ABB Group
November 13, 2014 | Slide 4
© ABB Group
November 13, 2014 | Slide 5
Ground-breaking and nation-building projects Pushing the boundaries of technology
Longest undegraund
power link
Longest underwater
power link
Largest Static Voltage
Compensator
Most remote offshore
wind farm linked to grid First platform connected
to mainland grid
Europe’s largest thermal
solar power plant
First commercial wave
power plant
Substation in world’s
tallest building
Automation of largest
alumina plant
Largest battery
Largest reverse-
osmosis
desalination plant
Commissioning of world
longest transmission line
ABB in Azerbaijan What We Are
© ABB Group
November 13, 2014 | Slide 6
ABB in Azerbaijan
ABB is active in Azerbaijan since 1995
Two legal entities of ABB
ABB Global Marketing FZ-LLC
Azerbaijan Representative office
ABB limited Caspian Project Office,
PSA company having service
contract with BP
Head office in center of Baku
More than 90 employees
80 MUSD annual turn-over in 2013
ABB Global Marketing FZ-LLC
Azerbaijan Representative office
“Bridge Plaza” Business center, 12th Floor
Bakikhanov Street, 6, Baku
Tel : +994 (12) 404 52 00
ABB Global Marketing FZ-LLC Azerbaijan Representative office activities
Power and Automation Products and systems sales
to constructions, industries, utilities
High, medium and low voltage products
Oil immersed and dry type transformers
Motors and drives for industrial applications
Process automation systems and products
High and medium voltage distribution and transmission
substations
Distribution automation systems, protection and control
devices
Power Generation, alternative energy systems
Service for products and systems
ABB Limited Caspian Project Office, PSA company having service contract with BP
Healthcare Service contract with BP to maintain
Automation systems and products
Process automation systems and products
High and medium voltage distribution and transmission
substations
Distribution automation systems, protection and control
devices
Service contract with BP to maintain Medium voltage
products at on-shore/off-shore oil platforms
Major References in Azerbaijan
Total of 25 substations and power plants
constructed / supplied since 1998 to Azerenerji,
State Utility Company
Automation systems of the Baku-Tblisi-Ceyhan
pipeline project
Transformers and switchgear for Baku Port
Residences and shopping centers, newly
constructed Marriott hotel, Baku Metro
High Voltage Equipment for Baku-Boyuk-Kesik
Railway link
Major References in Power Sector of Azerbaijan
Imishli, Gandja, Gala, Yashma, Sabirabad, Sumgait-2 No.135, High Voltage Equipment 2007
Novaya (227), 110/35/10 kV GIS UNDERGROUND SS 2007
Guba, 110 kV S/S for 104 MW "Guba" MPP 2008
Gandja, Energy supply to "Metallurgic complex“ : 500/330/10 kV "Samukh" S/S 2008
Gandja, Energy supply to "Metallurgic complex“ : 330/110/35/10 kV GIS Gyandja 2008
Sumgait, 110/35/6 kV GIS Sumgait-3 2008
Mushfig, 220/110 kV SS 2010
Zabrat, 220/110 kV Zabrat SS, Power Transmission Enhancement Project 2010
Yeni-Yashma, 110/20 kV SS for 50 MVA Wind Park 2010
Temiz-Sheher, 110 kV Switchyard for 50 MVA Waist to Energy Power Plant 2011
Bayil, 110/35/10/6 kV GIS UNERGROUND SS 2011
Khirdalan, 35/10 kV Switchgears for 110/35/10 kV SS Khirdalan 2012
Boyuk-Shor, 15/110/220 kV GIS Step Up SS for 395 MW Boyuk Shor MPP 2012
Our Key Customers
© ABB Group
November 13, 2014 | Slide 12
Renewable Energy Integration in Azerbaijan
© ABB Group
Renewable energy share of global electricity production
Source: REN 21
Renewables 2011
Global Status Report
Fossil fuel 67,6%
Renewables 19,4%
Nuclear 13%
November 08, 2011 | Slide 14
© ABB Group November 13, 2014 | Slide 15
Renewable energy Key growth driver for both power and automation
Generation and
transmission solutions for:
Hydro
Wind
Solar
Wave
Xiangjiaba-Shanghai (China)
Wind Capital (US)
Totana solar (Spain)
Pelamis wave energy (Portugal)
Project examples ABB scope
Grid connection
Transformers
Turnkey execution
Customized generators
Yeni Yashma 50 MW Wind Farm, Baku area
Construction of 20 wind farm towers,
By 2,5 MW capacity, in total 50 MW installed
power.
Each of lattice towers has 82 meters height and
around 200 tonnes weight.
ABB 110/20 kV SS for 50 MVA Wind Park for
connection to the Grid
ABB supplied for 3 M USD
© ABB Group November 13, 2014 | Slide 17