Upload
daniel-strauss
View
221
Download
0
Embed Size (px)
Citation preview
8/8/2019 AATA University Transit Study
1/33
November 10, 2010
Presentations at 4:00, 7:00
Please Sign In
Take a Comment SheetReview the Boards
Ask Questions of Staff and Consultant
Leave Comment Sheet at Sign In Table
Thanks for Coming!!
8/8/2019 AATA University Transit Study
2/33
November 10, 2010
Welcome to the Meeting!
1. Find out about the Connector study
2. Find out about alternative transittechnologies
3. Hear preliminary study findings
4. Give us your comments to help guide
our study process
Our Program Tonight:
8/8/2019 AATA University Transit Study
3/33
November 10, 2010
City ofAnn Arbor
City ofAnn Arbor
University
of Michigan
University
of Michigan
Ann ArborTransportation
Authority
Ann ArborTransportation
Authority
Downtown
DevelopmentAuthority
Downtown
DevelopmentAuthority
Study Purpose - To determine thefeasibility of advanced transit options forthe city to meet growing transportationdemands.
Supplement multi-modaltransportation system
More travel options
Convenience
Sustainability
Improve safety
Economic stability and growth
Improve overall quality of life
What is the Ann ArborConnector Feasibility Study?
Project Sponsors:
Study OverviewStudy Overview
8/8/2019 AATA University Transit Study
4/33
8/8/2019 AATA University Transit Study
5/33
8/8/2019 AATA University Transit Study
6/33
November 10, 2010
Congestion Travel Reliability Regional Policies / Goals
FindingsRecommend-
ations
FindingsRecommend-
ations
Ridership Engineering / Environmental
Challenges Costs and Funding
Is There aNeed?
Is There aNeed? Define the
MarketDefine the
Market
Trip Demand Geographic
LocationDevelop
AlternativesDevelop
Alternatives
FeasibilityAnalysis /Screening
FeasibilityAnalysis /Screening
Study OverviewStudy Overview
Project Approach
8/8/2019 AATA University Transit Study
7/33
8/8/2019 AATA University Transit Study
8/33
November 10, 2010
Defining the Need Corridor Congestion
Key Corridorsare Congested:
PlymouthRoad
State Street
DevelopmentExpected to
Occurin Corridor
8/8/2019 AATA University Transit Study
9/33
November 10, 2010
Defining the Need Corridor Congestion
Key Corridors areCongested:
Plymouth Road
State Street
Development Expected to
Occur in Corridor
Volume Forecasted toIncrease:
Plymouth Road: +10% Fuller Road: +11%
State Street: +10%
LRTP: Widening KeyRoutes is Not In Plan
8/8/2019 AATA University Transit Study
10/33
N b 10 2010
8/8/2019 AATA University Transit Study
11/33
November 10, 2010
Defining the Need Transit Utilization
Key corridors for existingAATA Service
2,7717 MinuteState Street
2,28615 MinutePlymouthRoad
Riders perWeekday
ServiceFrequency
Primary Destinations
UM Medical Center
Downtown
UM Central Campus
Standing loads occur frequently
Extra buses added to accommodate peak ridership
November 10 2010
8/8/2019 AATA University Transit Study
12/33
November 10, 2010
Defining the Need Transit Utilization
Bus Performance: Negatively
Impacted by RoadwayCongestion
Currently: 25-30% of Time isWaiting for Signals!!
More Volume More Delay:
Congested Conditions:
Delay Increases by 2-3Times Volume Increase
Bus Times Will Become LessReliable
November 10 2010
8/8/2019 AATA University Transit Study
13/33
November 10, 2010
Defining the Need Transit Utilization
UM Inter-Campus Bus SystemOperates at Critical Capacity:
Buses run every 2 3Minutes during peakperiods
Peak periods last from
9:00 am to 4:00 pm
Buses in peak periods arestanding room only
Ridership:
North to CentralCampus: 30,700 / Day
Peak: 3,500 Riders inPeak Hour
Peak Buses betweenCampuses: 60 Per Hour
Total Number of Northbound and Southbound Bus Trips per Hour
Between CC Little and Pierpont Commons
0
10
20
30
40
50
60
70
6:00A
M 7 8 9 10 11
12:00
PM(noon) 1 2 3 4 5
6:00P
M 7 8 9 10 11
12:00
AM(m
idnigh
t) 1 2
Time of Day
NumberofB
uses
November 10 2010
8/8/2019 AATA University Transit Study
14/33
November 10, 2010
Defining the Need Community Vitality
Better transit makes Ann
Arbor a more desirableplace to live and work
Maintain jobs
Accessible work force
Stabilize tax base
Affordable housing
Transit is an alternative tobuilding more parking
November 10, 2010
8/8/2019 AATA University Transit Study
15/33
November 10, 2010
Defining the Alternatives
Intermodal Connectivity
Locations
Amenities
Hours of the Day
Frequency / Time BetweenVehicles
Fare Collection Methods
New Route(s):
Uses Existing Street?
Separate Corridor /Guideway
Changes to Existing Routes?
November 10, 2010
8/8/2019 AATA University Transit Study
16/33
,
Light Rail Transit
Bus Rapid
Transit
ElevatedAGT
Streetcar
Defining the Alternatives
November 10, 2010
8/8/2019 AATA University Transit Study
17/33
Portland, OR
Tacoma, WA
Little Rock, AR
Defining the Alternatives
Streetcars
Tacoma, WA
November 10, 2010
8/8/2019 AATA University Transit Study
18/33
Minneapolis, MN Charlotte, NC
Dallas, TX Denver, CO
Defining the Alternatives
Light RailTransit (LRT)
Dallas, TX
November 10, 2010
D fi i th Alt ti
8/8/2019 AATA University Transit Study
19/33
Kansas City, MO Cleveland, OH
Eugene, OR
Defining the Alternatives
Bus RapidTransit (BRT)
November 10, 2010
D fi i th Alt ti
8/8/2019 AATA University Transit Study
20/33
Las Vegas, NV
Detroit, MI
Defining the Alternatives
AutomatedGuideway
TransitElevated AGT
8/8/2019 AATA University Transit Study
21/33
November 10, 2010
St d Fi di
8/8/2019 AATA University Transit Study
22/33
Two Area Types:
High Demand Core
Moderate Demand
Shoulders
Because there is traveldemand between all
Activity Centers, it makessense to connect them
Study Findings
23
November 10, 2010
Study Findings
8/8/2019 AATA University Transit Study
23/33
Core :
High Capacity
High Frequency End-to-End:
Moderate Capacity
Moderate Frequency
Dual Service in Core
Study Findings
Connector Service Concept
23
November 10, 2010
Study Findings
8/8/2019 AATA University Transit Study
24/33
Light RailTransit
Bus RapidTransit
ElevatedAGT
Study Findings
Recommended CoreTechnologies
23
November 10, 2010
Study Findings
8/8/2019 AATA University Transit Study
25/33
Streetcar
Bus RapidTransit
Bus
Study Findings
Recommended End-to-EndTechnologies
23
November 10, 2010
Study Findings
8/8/2019 AATA University Transit Study
26/33
Engineering andEnvironmental Challenges
Huron River Crossing
Topography
Railroad Crossings
Roadway Crossings
Right of way
Historic districts
Floodplains
These challenges are not barriers
but will be considerations in thecost and design of a new transit
system.
Study Findings
November 10, 2010
Study Findings
8/8/2019 AATA University Transit Study
27/33
Capital Costs depend ontechnology and alignment
BRT $15-20M per mile
LRT $50-60M per mile
Elevated $200M+ per mile
Operating Costs
Net new costs of operatingand maintaining an advancedtransit system would rangefrom $0.5 to $1.5 M/mileannually, depending on
technology and alignment
Study Findings
Capital and Operating Costs
November 10, 2010
Study Findings
8/8/2019 AATA University Transit Study
28/33
Funding for major transit investments typically comesfrom multiple sources
Project could qualify for federal funding of up to 50%
Federal
MnDOTFederal Grant forCongestion Mitigation
and Air Quality
Metropolitan AirportsCommission
Hennepin CountyRegional Rail Authority
State of Minnesota
Federal
MnDOTFederal Grant forCongestion Mitigation
and Air Quality
Metropolitan AirportsCommission
Hennepin CountyRegional Rail Authority
State of Minnesota
Parking Fund
(Cash)
Tax
Increment
HUD Grant
Parking Fund
(Bonds)
Local ImprovementDistrict PrivateSector Funds
Federal Transportation
Funds Agreement withTri-Met Reallocated as
Local Funds
Portland
Transportation
Resources
Parking Fund
(Cash)
Tax
Increment
HUD Grant
Parking Fund
(Bonds)
Local ImprovementDistrict PrivateSector Funds
Federal Transportation
Funds Agreement withTri-Met Reallocated as
Local Funds
Portland
Transportation
Resources
Hiawatha Light Rail Portland Streetcar
Study Findings
Funding
November 10, 2010
Study Findings
8/8/2019 AATA University Transit Study
29/33
There are two distinct areasof travel demand:
High Demand Core
warrants high capacityservice
Moderate Demand
Shoulders warrantend-to-end connection
Study Findings
Summary
23
November 10, 2010
Study Findings
8/8/2019 AATA University Transit Study
30/33
End-to-end service should be integrated with the core
service. Appropriate end-to-end technologies are:StreetcarBus Rapid
TransitBus
Bus RapidTransit
Light RailTransit
ElevatedAGT
Study Findings
Summary
Within the High Demand Core, appropriatetechnologies are:
November 10, 2010
Study Findings
8/8/2019 AATA University Transit Study
31/33
The engineering and
environmental challengesare not barriers but will beconsiderations in the costand design of a new transitsystem.
Funding for major transitinvestments typically comesfrom multiple sources
Project could qualify for federal funding of up to 50%
Implementing an advanced transit system would help moveAnn Arbor to achieving long term transportation goals
SustainableTransportation
SustainableTransportation
MinimizeRoad
Expansion
Minimize
RoadExpansion
Support Non-motorized
Travel
Support Non-motorized
Travel IncreasedUse ofTransit
IncreasedUse ofTransit
IncreasedUse ofTransit
IncreasedUse ofTransit
Study Findings
Summary
November 10, 2010
Next Steps
8/8/2019 AATA University Transit Study
32/33
AlternativesAnalysis
PreliminaryEngineering
Construction
EnvironmentalReview
Final Design
If Community SupportsNext Steps
This feasibility study is thefirst of a number of stepsrequired to implement anadvanced transit system.
If feasible, more detaileddesign studies andadditional communityworking sessions will be
required.
Identification of fundingsources is a critical step
to implementation.
Feasibility
Study
CurrentProject
FutureActivities
These futuresteps cantake 5 to 20years tocompletedependingon thetechnology,alignmentand funding
Develop
mentandrefinem
entof
capitalandoperatingfinan
cialplan
Next Steps
November 10, 2010
Discussion
8/8/2019 AATA University Transit Study
33/33
1. From the information that we presented, have we made thecase for why some kind of new alternative transit technology
in the Plymouth Road / downtown / State Street corridorswould be advantageous to the community?
2. If further study occurs what issues are important to beaddressed?
3. Would you be interested in seeing a new form of transittechnology used in the Plymouth Road / downtown / StateStreet corridors and if so, why?
4. Do you have any other comments or questions for usregarding this Connector Study?
5. Should the community continue with the next steps to
implement an alternative transit technology?
Discussion