Upload
agus-suwandi
View
215
Download
0
Embed Size (px)
Citation preview
8/2/2019 AAC_SPEC_412010
1/11
AAC_SPEC_41201002.DOC APPROVED 11 July 1994 Page 1 of 11
Anglo Technical Division accepts no liability for any damage whatsoever that may result from the use of this material orthe information contained therein, irrespective of the cause and quantum thereof.
AAC SPECIFICATION 412010
ISSUE 2THERMAL INSULATION FOR CHILLED WATERPIPING COPYRIGHT
CONTENTS PAGE
1 SCOPE 22 TECHNICAL REQUIREMENTS TO BE SPECIFIED BY THE ENGINEER 22.1 PIPE OUTSIDE DIAMETER 22.2 INSULATION SECTION LENGTHS 22.3 TOTAL LENGTH OF PIPING 22.4 BEND OR PIPE FITTING DETAILS 22.5 PIPE MATERIAL 22.6
PIPE JOINT DETAILS (FLANGED OR SHOULDERED) 2
2.7 REQUIRED LIFE OF CORROSION PROTECTION 22.8 THE PREVAILING AMBIENT CONDITIONS AFFECTING CORROSION 22.9 PACKAGING REQUIREMENTS. 22.10 PIPES TO BE PRE-INSULATED ON SURFACE OR INSULATION TO BE INSTALLED IN-SITU
UNDERGROUND. 23 DEFINITIONS 24 REQUIREMENTS 34.1 GENERAL 34.2
MATERIALS 3
4.3 INSULATION SYSTEM 44.4 CONSTRUCTION 54.5 DESIGN 55 QUALITY ASSURANCE REQUIREMENTS 75.1 QUALITY MANAGEMENT SYSTEM 75.2 QUALITY PLAN 75.3 INSPECTION 75.4 SAMPLING 76 INSPECTION AND TEST 86.1 TYPE TESTS 86.2 PRODUCTION TESTS 87 MARKING AND PACKING 97.1 MARKING 97.2 PACKING 10APPENDIX A : RELATED DOCUMENTS 11APPENDIX B : RECORD OF AMENDMENTS 11
8/2/2019 AAC_SPEC_412010
2/11
AAC_SPEC_41201002.DOC APPROVED 11 July 1994 Page 2 of 11
Anglo Technical Division accepts no liability for any damage whatsoever that may result from the use of this material orthe information contained therein, irrespective of the cause and quantum thereof.
AAC SPECIFICATION 412010
ISSUE 2THERMAL INSULATION FOR CHILLED WATERPIPING COPYRIGHT
1 SCOPE
This specification details the requirements for the thermal insulation of chilled water pipesinstalled underground and covers pre-insulation of pipes on surface and in-situapplications underground.
2 TECHNICAL REQUIREMENTS TO BE SPECIFIED BY THE ENGINEER
2.1 PIPE OUTSIDE DIAMETER
2.2 INSULATION SECTION LENGTHS
2.3 TOTAL LENGTH OF PIPING
2.4 BEND OR PIPE FITTING DETAILS
2.5 PIPE MATERIAL
2.6 PIPE JOINT DETAILS (FLANGED OR SHOULDERED)
2.7 REQUIRED LIFE OF CORROSION PROTECTION
2.8 THE PREVAILING AMBIENT CONDITIONS AFFECTING CORROSION
2.9 PACKAGING REQUIREMENTS.
2.10 PIPES TO BE PRE-INSULATED ON SURFACE OR INSULATION TO BE INSTALLED IN-SITUUNDERGROUND.
3 DEFINITIONS
ACCEPTABLE/APPROVED : Acceptable to and approved by the Engineer
CSIR MINING TEK : Council fir Scientific and Industrial Research MiningTek
ENGINEER : The Consulting Engineer, Consulting Mechanical andElectrical Engineer of AAC or their appointedrepresentative
INSULATION SYSTEM : Combination of one or more of sleeve, vapour barrierand insulant so providing required properties
INSULANT : Material providing thermal insulation through low heattransfer
NBS : National Building Standards
NES : Naval Engineering Standard (Royal Navy)
8/2/2019 AAC_SPEC_412010
3/11
AAC_SPEC_41201002.DOC APPROVED 11 July 1994 Page 3 of 11
Anglo Technical Division accepts no liability for any damage whatsoever that may result from the use of this material orthe information contained therein, irrespective of the cause and quantum thereof.
AAC SPECIFICATION 412010
ISSUE 2THERMAL INSULATION FOR CHILLED WATERPIPING COPYRIGHT
PIPE : Water reticulation pipe
SLEEVE : Outer covering which provides protection to the insulant
UPVC : Unplasticised poly-vinyl chloride
VAPOUR BARRIER : Layer of continuous impermeable material sealing theinsulant
The following terms are defined in the General Conditions of Contract:
AAC, Company, Contractor.
4 REQUIREMENTS
4.1 GENERAL
4.1.1 Insulants produced by the chemical reaction of two or more constituents, whichduring the chemical action produce a water vapour: shall not be injected or cast into aclosed void unless:
4.1.1.1 Provision is made: to vent this moisture from the insulant to ensure that the coefficient ofconductivity specified by the manufacturer is obtained.
This conductivity must be stabilised after the insulation has been used in the conditionsshown in table 5 for a period of 200 hours.
4.1.2 Insulants produced by the chemical reaction of two or more constituents, one ofwhich is an acid, shall not be used as slab stock in voids, or be injected into voids whichhave metallic walls unless the walls are suitably protected against corrosion.
4.2 MATERIALS
4.2.1 Sleeve: the sleeve shall comply with the requirements specified in Table 1.
TABLE 1: SLEEVE REQUIREMENTS
1 2 3
MATERIAL REQUIREMENTS TEST METHOD
UPVC
(See note below)
1. Maximum thickness 3,2mm
2. Impact resistanceminimum value 50 kJ/m
3. Comply with AECISpecification No. 130/S/03or approved equivalent
4. UPVC sleeves must becolour coded blue
DIN 53448
8/2/2019 AAC_SPEC_412010
4/11
AAC_SPEC_41201002.DOC APPROVED 11 July 1994 Page 4 of 11
Anglo Technical Division accepts no liability for any damage whatsoever that may result from the use of this material orthe information contained therein, irrespective of the cause and quantum thereof.
AAC SPECIFICATION 412010
ISSUE 2THERMAL INSULATION FOR CHILLED WATERPIPING COPYRIGHT
Steel Minimum thickness 0,3mm
Phoenolic Resin Glassreinforced
See AAC Specification 173/1
Note: Where UPVC sleeved piping is routed closer than 2,0m from fuelling bays, oilstores, conveyor belts, oil filled transformers and switchgear, timber supports, etc,external steel cladding shall be applied. See AAC Drawing No Y1903.
4.2.2 Vapour barrier: the vapour barrier shall comply with the requirements specified inTable 2.
Where pipe insulation is purchased without a mechanical protective sleeve, the vapourbarrier material shall comply with the AAC Specification No 412/9.
TABLE 2: VAPOUR BARRIER REQUIREMENTS
1 2 3
PROPERTY REQUIREMENTS TEST METHOD
Water Vapour 0,2g maximum per m/24h at38C 2% and 90% R.H. 5% R.H.
ASTM E96
4.2.3 Insulant: the insulant shall comply with the requirements specified in Table 3.
TABLE 3: INSULANT REQUIREMENTS
1 2 3
PROPERTY REQUIREMENTS TEST METHOD
Combustibility Pass SABS 0177 Part V
(Modified) CSIR
Test Method
Toxicity Maximum Index of 2 SABS Test Method TI (NES)
Thermal Conductivity 0,05 W/mC Max ASTM C177
Smoke Production SpecificOptical Density Value
Maximum index of 10,0 NBS Smoke Density TestMethod
Min Compressive Strength(Parallel to Rise)
175 kPa
Density Max 200kg/m
4.3 INSULATION SYSTEM
The insulation system shall comply with the requirements specified in Table 4.
8/2/2019 AAC_SPEC_412010
5/11
AAC_SPEC_41201002.DOC APPROVED 11 July 1994 Page 5 of 11
Anglo Technical Division accepts no liability for any damage whatsoever that may result from the use of this material orthe information contained therein, irrespective of the cause and quantum thereof.
AAC SPECIFICATION 412010
ISSUE 2THERMAL INSULATION FOR CHILLED WATERPIPING COPYRIGHT
TABLE 4: SYSTEM REQUIREMENTS
1 2 3
PROPERTY REQUIREMENT TEST METHOD CLAUSE
Fire Resistance Pass CSIR Mining Tek/CSIR Fire Lab.Tunnel tests
Thickness of insulant Clause 4.4.2 To be specified byContractor
CSIR Mining Tek Dynamic Test(see Clauses 6.2.8 and 4.4.2)
Thermal Conductivity 0.05 W/m C max ASTM C177
Heat gain Table 6 CSIR Mining Tek Dynamic Test
Distortion (Pre-insulated pipes) 10mm Clauses 6.2.5
Note: The overall length of insulation system on pre-insulated pipes shall allow adequateaccess to flange bolt holes etc.
4.4 CONSTRUCTION
4.4.1 Insulant: shall be homogenous, free of voids and shall occupy all cavities within theprotective sleeve.
4.4.2 Thickness of insulant: shall be such that the heat gain values detailed in Table 6 shallnot be exceeded after ageing and after use for 200 hours in conditions as set out inTable 5.
4.4.3 Water vapour protection: of the insulant shall be such that it is encapsulated in amaterial which complies with the requirements for a water vapour barrier as detailed inTable 2. Where this material is joined, the joint shall exhibit the same characteristics asthe parent material.
4.4.4 Products of organic nature: polyurethane or polystyrene based materials shall not beused.
The density of the insulant: shall not be greater than 200 kg/m3.
4.4.5 The complete product: comprising insulant, water vapour barrier and sleeve shall not
show any deformation greater than 5 mm nor any permanent visible deterioration whentested in accordance with the requirements of Clause 6.2.7.
4.4.6 Glass reinforced organic material: if used as a protective sleeve shall comply with therequirements of AAC Specification 173/1.
4.5 DESIGN
The Contractor shall provide for approval, dimensioned drawings and design calculationsat time of tender response accompanied by an SABS certificate stating that an insulationsystem complying with the design has been tested by SABS and complies with therequirements of Clause 4.2 and 4.3. The results of the heat gain tests and fire
performance tests conducted by CSIR Mining Tek and CSIR Fire Lab. shall be included.
8/2/2019 AAC_SPEC_412010
6/11
AAC_SPEC_41201002.DOC APPROVED 11 July 1994 Page 6 of 11
Anglo Technical Division accepts no liability for any damage whatsoever that may result from the use of this material orthe information contained therein, irrespective of the cause and quantum thereof.
AAC SPECIFICATION 412010
ISSUE 2THERMAL INSULATION FOR CHILLED WATERPIPING COPYRIGHT
The Contractor shall also provide for approval the methods and materials used for fixing in-
situ type insulation to the pipes.
4.5.1 Calculations: the parameters detailed in Table 5 shall be used for design purposes.
TABLE 5: CALCULATIONS PARAMETERS
1 2
PARAMETER VALUES
Water velocity
Water Temperature
Pipe diameter range
Pipe wall thickness
Pipe thermal conductivity
Air temperature
Air velocity
1m/s
5C
100 - 300mm
6mm
45W/m C
(Mild steel)
32C
5m/s
Note: If pipes of different thermal conductivity are used this shall be specified by theCompany.
4.5.2 Design performance requirements: maximum heat gain per linear metre of insulatedpipe shall not exceed the value given in Table 6.
Note: Value given is for the combined insulating value of pipe wall, vapour barrier andsleeve and is based on a dry clean sleeve outer surface.
TABLE: 6 HEAT GAIN
1 2 3
PIPE: NOMINAL SIZE(mm)
HEAT GAIN(W/LINEAR m)
TEST METHOD
100
150
200
250
300
14
19
24
29
34
See Clause
6.1.2
4.5.3 Designed maximum outside diameter: of insulation shall comply with the requirementsof Table 7.
8/2/2019 AAC_SPEC_412010
7/11
AAC_SPEC_41201002.DOC APPROVED 11 July 1994 Page 7 of 11
Anglo Technical Division accepts no liability for any damage whatsoever that may result from the use of this material orthe information contained therein, irrespective of the cause and quantum thereof.
AAC SPECIFICATION 412010
ISSUE 2THERMAL INSULATION FOR CHILLED WATERPIPING COPYRIGHT
TABLE 7
MAXIMUM INSULATION SYSTEM OUTSIDE DIAMETERS
1 2
NOMINAL PIPE SIZE (mm) INSULATIONS, SYSTEMOUTSIDE DIAMETER (mm)
100
150
200
250300
225
290
350
420470
5 QUALITY ASSURANCE REQUIREMENTS
5.1 QUALITY MANAGEMENT SYSTEM
The requirements of SABS ISO 9001 shall apply. All volitional requirements in SABSISO 9001 shall be mandatory for material supplied against this specification.
5.2 QUALITY PLAN
The Contractor shall compile and submit a quality plan which shall be approved prior tocommencement of manufacture. The quality plan shall list all major works, specifications,tests, methods of test and equipment to be used and acceptance/rejection criteria.
5.3 INSPECTION
The Contractor shall provide SABS certification to the effect that items supplied to theCompany comply with the requirements of this specification.
The Company's representative shall have access at all reasonable times to those parts ofthe manufacturing facilities engaged in the manufacture of items to this specification. He isauthorised to witness any stage of manufacture, tests and inspection documentation.
The representative is authorised to reject any items not manufactured to the requirements ofthis specification.
All quality costs including SABS certification shall be for the account of the Contractor.
5.4 SAMPLING
5.4.1 Sampling for type testing: shall be as determined by the AAC Consulting EnvironmentalEngineer.
5.4.2 Sampling for production testing: shall be in accordance with the requirements detailedin the approved Quality Plan.
8/2/2019 AAC_SPEC_412010
8/11
AAC_SPEC_41201002.DOC APPROVED 11 July 1994 Page 8 of 11
Anglo Technical Division accepts no liability for any damage whatsoever that may result from the use of this material orthe information contained therein, irrespective of the cause and quantum thereof.
AAC SPECIFICATION 412010
ISSUE 2THERMAL INSULATION FOR CHILLED WATERPIPING COPYRIGHT
6 INSPECTION AND TEST
6.1 TYPE TESTS
6.1.1 CSIR Mining Tek tunnel testing
Full scale pipe insulation tests shall be performed on two 200 mm diameter insulatedpipes complete with vapour barriers and external protective sheaths. The pipes shall beinstalled in parallel.
6.1.2 CSIR Mining Tek heat gain test
An insulated 6m length of 150 mm nominal bore pipe shall be submitted to CSIR Mining Tekfor the determination of the thermal conductivity of the insulation system at conditions as set
out in Table 5.
6.2 PRODUCTION TESTS
Production tests shall be performed on samples as detailed in the Quality Plan and at thefrequency specified in Table 8.
TABLE 8
SAMPLING PLANS FOR TEST CLAUSE, 6.2
1 2 3
LOT SIZE SAMPLE SIZE DEFECTIVE ACCEPTABLE
3 - 25 3 0
26 - 50 13 0
51 - 150 20 0
6.2.1 Combustibility
Combustibility shall be tested in accordance with the requirements of SABS 0177 Part V.(Modified) CSIR method.
6.2.2 Toxicity
Toxicity shall be tested in accordance with the requirements of SABS Method T1 (NES 713).
6.2.3 Smoke density
Smoke density production shall be tested according to the NBS Smoke Density Testmethod.
6.2.4 Conductivity
The conductivity of a sample of the insulant shall be tested according to ASTM C177.
6.2.5 Water vapour transmission
8/2/2019 AAC_SPEC_412010
9/11
AAC_SPEC_41201002.DOC APPROVED 11 July 1994 Page 9 of 11
Anglo Technical Division accepts no liability for any damage whatsoever that may result from the use of this material orthe information contained therein, irrespective of the cause and quantum thereof.
AAC SPECIFICATION 412010
ISSUE 2THERMAL INSULATION FOR CHILLED WATERPIPING COPYRIGHT
The water vapour transmission values of the water vapour barrier or outside sleeve shall be
tested according to ASTM E96.
6.2.6 Density of insulant
Remove a cube from an insulated pipe and determine its mass. Calculate the volume of thecube and determine the density of the insulant by dividing the mass by the volume. Express
the result in kg/m3. The result shall comply with the requirements of Table 3.
6.2.7 Distortion
Apply a force of 5kN, via a 50 x 50 steel angle positioned at 90o
to the pipe axis, onto theouter surface of the insulated pipe (with the point of the 'V' of the angle contacting with the
insulation). Remove the force and measure the depth of indentation. The results shallcomply with the requirements of Clause 4.4.5
6.2.8 Thickness of insulant
Measure thickness of insulant prior to encapsulation in the vapour barrier and outsideprotective sleeve, for in-situ type insulation.
For pre-insulated pipes, measure the circumference of the pipe and the outsidecircumference of the protective sleeve of the insulated pipe. Calculate the thickness ofinsulation and protective sleeve and then deduct thickness of protective sleeve.
The result shall comply with requirements to satisfy the heat gain specifications as set out inTable 6.
6.2.9 SABS 0177 Part V (Modified) CSIR combustibility
The empty sample cradle shall be introduced into the furnace and the temperaturesrecorded for 5 minutes.
When the furnace has reached equilibrium temperature a 40mm x 40mm x 40mm sampleof the test material shall be introduced into the furnace and the temperatures shall berecorded for 5 minutes.
Any material, of which the flame temperature rise exceeds that of the empty cradle for the
initial 2 minutes of the test or which exhibits a quenching effect of less than that of the emptycradle for the initial 2 minute period of the test shall be deemed to have failed.
The results shall comply with the requirements detailed in Table 6.
7 MARKING AND PACKING
7.1 MARKING
The outer surface of the insulation system shall be marked as follows.
7.1.1 Logo or name of Contractor
7.1.2 Date of manufacture
8/2/2019 AAC_SPEC_412010
10/11
AAC_SPEC_41201002.DOC APPROVED 11 July 1994 Page 10 of 11
Anglo Technical Division accepts no liability for any damage whatsoever that may result from the use of this material orthe information contained therein, irrespective of the cause and quantum thereof.
AAC SPECIFICATION 412010
ISSUE 2THERMAL INSULATION FOR CHILLED WATERPIPING COPYRIGHT
7.2 PACKING
Packing shall provide protection during transit and handling of insulation systemcomponents.
8/2/2019 AAC_SPEC_412010
11/11
AAC_SPEC_41201002.DOC APPROVED 11 July 1994 Page 11 of 11
Anglo Technical Division accepts no liability for any damage whatsoever that may result from the use of this material orthe information contained therein, irrespective of the cause and quantum thereof.
AAC SPECIFICATION 412010
ISSUE 2THERMAL INSULATION FOR CHILLED WATERPIPING COPYRIGHT
APPENDIX A : RELATED DOCUMENTS
The latest issues of the following documents shall be deemed to form part of this specification.
ASTM C177 : Test method for steady-state heat flux measurements and thermaltransmission properties by means of the guarded-hot-plate apparatus
ASTM D304 : Recommended practice for heat ageing of plastics without load
ASTM E96 : Test for water vapour transmission of materials
SABS ISO 9001 : Quality management systems
SABS 0177 : Fire testing of materials, components and elements used in buildings
SABS 0177 Part V : Fire testing of materials, components and elements (Modified) CSIRused in buildings
SABS Method T1 : Determination of the toxicity index of the products of combustion fromsmall specimens of materials
AECI 130/5/03 : Specification for PVC formulation
DIN 53448 : Testing of plastics; tensile impact test
AAC Drawing Y1903 : Cladding
AAC 412/9 : Vapour barrier for use with blanket type insulation for chilled waterreticulation piping
APPENDIX B : RECORD OF AMENDMENTS
Issue 2 : Table 8 added to Clause 6.2
Refs to COMRO changed to C.S.I.R. Mining Tek.
(P.N. Eksteen 1994-04-11)