49
Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal Appendix A - A3 Sureus Hydrostatic Test Plan Page 1 of 49 HYDROSTATIC TEST PLAN Bakken Pipeline Expansion Project , Mainline Pipeline NPS 16 Prepared by: Su r erus Pipeline Inc. For: Enbridge Bakken L. P. 20'1 2-1 '1-09 2

A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Embed Size (px)

DESCRIPTION

HYDROSTATIC TEST PLAN

Citation preview

Page 1: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 1 of 49

HYDROSTATIC TEST

PLAN

Bakken Pipeline Expansion Project, Mainline Pipeline NPS 16

Prepared by: Surerus Pipeline Inc.

For: Enbridge Bakken L.P.

20'12-1 '1-09 2

Page 2: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 2 of 49

1. Scope

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

This document was prepared for the hydrostatic pressure testing of the Enbridge Bakken Mainline NPS 16 Pipeline Project planned for construction in the summer/fall of 2012 between Steelman, SK and Cromer, MB. The test shall be completed in two (2) underground sections and two (2) above-ground sections totaling approximately 123,987m in length; the test section end points are detailed within the document below. For the below-ground sections the hydrostatic test consists of a minimum 4.25 hour strength and a minimum 4.25 hour leak test to verify the integrity of the pipeline following installation. At the pipeline end points, the Steelman and Cromer terminal tie-ins, short sections of the pipeline will be tested prior to installation due to access restrictions, these segments will be tested for a minimum period of one (1) hour to permit visual inspection of the pipeline during a combined strength and leak test.

2. Safety 2.1. All personnel shall review and follow the Emergency Response Plan (ERP) developed

specifically for this project. A copy of the ERP shall be available in each vehicle used on the project and additional copies shall be posted within the test building and other appropriate locations.

2.2. A pre-phase meeting will be held at the Surerus site office for all personnel involved in the hydrostatic test prior to commencement of the test to ensure that all personnel understand their respective duties.

2.3. Surerus will install warning signs and barricades to prevent access to the vicinity of the test area. Warning signs shall indicate "DANGER - High Pressure Pipeline Test• and "Restricted Access".

2.4. All Surerus personnel not involved in the testing shall be removed from the area while the pipeline section is under a pressure equal to or greater than 2,760kPa (-400psi).

2.5. Test heads and pressurizing pipe shall be secured to limit movement. 2.6. All testing equipment including compressors, recorders, deadweights, etc. shall be set

liP a safe distance from the test section and/or test heads. 2.7. Surerus employees shall inspect all hoses, lines, and connections for faults prior to

pressurizing the lines. The Surerus Hydrotest Pre-test Checklist will be completed to ensure that all components meet the required ratings.

2.8. Surerus personnel shall ensure pressure hoses/unions are rated to twice the maximum expected hydrotest pressures, and all safety lines are firmly attached and secured with whip checks.

2.9. An Enbridge representative will be on site for the duration of test activities.

3. Equipment In addition to the details listed below, all testing materials, equipment, and instrumentation shall comply with relevant Enbridge specifications including section 6.3 of CPSC-SPEC­HYDR0-005. A detailed list of all testing equipment including make, model and recent calibration certificate shall be available for review prior to commencement of testing activities. Surerlls shall supply the following equipment for completion of the hydrostatic test:

Pumps including transfer/fill pllmp, and squeeze pump. Air compressors required for pipeline cleaning, pre-pack, and dewatering. All pipeline pigs required for line fill and dewatering. All necessary valves, hoses, and fittings reqllired to successfully complete the test. Calibrated temperature recorders, pressure recorders, ancl cleaclweights. Calibrated flow meter for preparation of the yield plot where applicable.

DA\!E 2012-'1 '1-09 REVISION 2 PAGE 2 ofB

Page 3: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 3 of 49 -------

SURI!JJ Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

Adequate lighting and light towers at all work areas.

3.1 Test Heads 3.1.1 Surerus shall supply Enbridge approved test heads which comply with a ll

requirements of relevant specifications including section 6.2 of CPSC-SPEC­HYDR0-005.

3.1.2 Test head assemblies shall comply with all requirements of CSA-2662 (latest edition). All documentation certifying test head compliance shall be available for review prior to commencement of testing.

3.1.3 Test heads will be welded to the section and the welds will be inspected by NDE prior to filling the section. A minimum of 4m of heavywall pipe which remains below 90% SMYS at the maximum anticipated test pressure shall be included in the test section immediately adjacent to the test head.

3.2 Pumps 3.2.1 Surerus shall ensure that fill and squeeze pLimps are adequately sized for the

length and diameter of the section to be tested. 3.2.2 A transfer pump shall be installed at the edge of the water source (Alameda

Reservoir). The pump shall be placed within a lined containment berm capable of containing 1.5 times the maximum volume of fuel contained within the pump. The inlet end of the pump will have a screened intake which meets regulatory requirements.

3.2.3 The f ill pump will be an 8" inlet and 6" discharge pump capable of providing a fill rate up to 7m3/min. A second fill pump will be on location for back-up.

3.2.4 Surerus anticipates that the fill pump, storage tank, squeeze pump, and test trailer will be set-up within available temporary workspace at the common test point at the junction of section 1 and section 2 near 35+500.

T bl 1 P a e - ump D t 'I e a1 s Pump Manufacturer/Model Suction Discharge Flow Transfer #1 Pioneer 10" 8" 4m"/min

PP108S17" Transfer#2 Pioneer 10" 8" 4mJ/min

PP108S1 7" Fill #1 Pioneer PP86C21· a· 6" 4.5 - 7m"/min Fill #2 (Back-up} Pioneer PP86C21' 8" 6" 4.5 - 7m"/min S_queeze _(Truck) TBD 2" 1" 500Umin

* Pump performance curves are mcluded as an attachment ·co th1s document.

3.3 Instrumentation: 3.3. 'I Surerus shall supply pressure and temperature recorders and dead weights to

provide readings for the test data. The pressure shall be measured in kPa, and the temperature measured in degrees Celsius.

3.3.2 All test charts and reports, including the depressurizing of tested lines, will be included in the document turnover package.

3.3.3 Instrumentation for the test shall be as follows: • Single pen temperature recorders will be located at the 'fill point to record

and monitor the test medium temperature through the manifold during the fil l.

DATE 2012-·11-09 REVISION 2 PAGE 3 of8

Page 4: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 4 of 49

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

Additional single pen temperature recorders wil l be located at each end of the test section and a third temperature recorder installed near the middle of the test section .

• Two dual pen temperature/pressure recorders, a digital deadweight, and a mechanical deadweight will be located at the fill point.

• Two additional dual pen temperature/pressure recorders and deadweight shall be located at the section end point.

3.3.4 All measurement equipment shall be certified for accuracy not more than 30 days prior to commencement of the pressure test. The calibration certificates and current calibration reports shall be maintained on site and included in the turnover package following completion of the test.

3.4 Cold Weather Provisions 3.4.1 To counteract the effect of below freezing ambient conditions anticipated during

testing activities, Surerus shall perform the following: • Erect shelters around or hoard-in all exposed piping on the project. • Place heaters within the hoarding to maintain the pipe temperature above

freezing at all test head locations and above ground valve sites along the project.

• Promptly drain all f ill lines following water transfer to protect fill pipe and pumps from freezing.

3.4.2 Based upon an expected minimum average ground temperature of 3°C at the time of testing , Surerus does not anticipate a requirement to heat hydrostatic test water.

4. Line Fill

4.1 Test Sections

Section Start End Length Volume Dewater Location

Steelman 1* Terminal 0+094 94m 11m3 0+094

(KPO+OOO) Alameda Landspread in

2 Reservoir East I<P0+100 35,400m 4,275m3 Vicinity of KP n<P3s+soo) 35+500

Alameda Landspread in 3 Reservoir East I<P1 23+27·l 88,350m 10,669m3 Vicinity of KP

(KP35+500) 35+500

4'' KP123+27'1 Cromer Terminal

74m 9m3 123+271 (I<P123+345)

" Note that hydrotest water for sections 1 and 4 will be provided by tankel' trucl(s. These sections shall be ·JOO% visible at the time of tesi:ing and subject to a oneg how· combined strength and leak test.

DATE 2012-'1"1-09 REVISION 2 PAGE 4 or a

Page 5: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 5 of 49 ------SUR§!Wj Bakken Mainline NPS 16

HYDROSTATIC TEST PLAN

4.2 Fill section

Test heads will be welded onto the ends of each test section and will be inspected by NDE. NDE documentation shall be retained to support acceptability of the welds. The foreman shall inspect all connections and hoses prior to filling the section. Prior to filling the pipeline, the fill line shall be leak tested for a minimum of 5min at 3,450kPa (- 500psi). To ensure a consistent fill Surerus will monitor and control pressure at the section end during fill. A pre-pack of compressed air will be established to offset the head pressure due to the water column during the line fill; this backpressure will be maintained throughout the fill at a pressure corresponding to the anticipated water pressure according to the elevation profile. The backpressure is anticipated to vary between 345 to 1 ,250Kpa (-50 to 180psi) throughout the line fill process. A single medium density pig will be pre-loaded into the test head and will be driven through the pipeline by the rate of the fluid insertion. Water shall be pumped from the Alameda Reservoir near the HOD exit location and transferred via fill line to the section fill points at KP35+500. Enbridge shall be responsible for obtaining all required water withdrawal permits. Water shall be left in the pipeline at a pressure of approximately 25% of the maximum test pressure during a stabilization period to ensure that a consistent temperature is achieved. During the line fill process fluid samples shall be obtained by Enbridge Representatives and submitted for analysis as required. The filling operation shall be continuous to prevent air ingress.

4.3 Pressurize and test the section.

Before pressurizing the section beyond a pressure of 2,760kPa, all work crews will be notified and removed from the vicinity of the test section. All pipe and fill connections shall be checked for leaks and these test areas shall be maintained as "off-limits" to non-essential personnel. Pressure will be increased to 2, 760kPa and all visible piping inspected for leaks. Upon completion of the leak checl<, the line and manifold wi ll be bled off, an inline check valve installed on the squeeze line and the squeeze pump connected to the line. Squeeze pressure will be initiated through a 1" or 2· line rated to 38,00QI(Pa (-5,500psi) ; pressure shall be increased in stages as indicated in the Hydrostatic Test Record Worksheets.

5. Test Stages

The pipeline shall be tested in the following stages: e Leak check e Strength test (including yield plot where required) e Leal< test

DATE REVISION PAGE

20'12- "11 -09 2

5 of 8

Page 6: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 6 of 49

5.1. Leak Check

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

The first stage involves a leal< check at approximately 2, 7601<Pa to allow visual inspection of exposed piping and fittings included in the test section. Any pressure lost during this period must be explained to the satisfaction of the Company's testing supervisor prior to pressurizing to the target strength test pressure

5.2. Strength Test Following satisfactory completion of the leak checl<, testing will continue by slowly raising the pressure to the strength test pressure as indicated in the attached Hydrotest Calculation Worksheets. The strength test will be held at a pressure greater than the minimum test pressure.

5.2.1 Yield plotting, if required, shall be undertaken as the section is pressurized during the strength test. Yield plotting shall commence at a pressure equivalent to 60% of the maximum anticipated test pressure. Yield plotting shall only be required where the expected maximum hoop stress in the test section during the strength test is greater than 100% SMYS of the pipe. Enbridge shall be responsible for completing all yield plots and associated documents.

5.2.2 Pumping shall continue until the selected strength test pressure is achieved or, where a yield plot is required, the point where the yield plot deviates beyond the 0.2% offset line.

5.2.3 The strength test will be held at a pressure greater than the minimum test pressure. 5.2.4 After pumping has ceased, and the selected strength test pressure has been

reached, the strength test will commence. The pressure at the highpoint shall match or exceed this minimum at both the start and the end of the test, and at no time during the test period shall the pressure at the high point drop below the required minimum.

5.2.5 The minimum duration for the hold period on the strength test is four and a quarter (4.25) hours.

5.3. Lealt Test After successful completion of the strength test, a minimum four and a quarter (4.25) hour leal< test wi ll be conducted. Pressure wi ll be dropped to a level corresponding to the leal< test pressure indicated in the attached Hydrotest Calculation Sheets.

5.3.1 The minimum pressure at the high point shall be 110% of the intended maximum operating pressure.

5.3.2 At the end of the leak test a hold period of two (2) hours is required where no drop in pressure is experienced.

5.3.3 The test duration may be extended beyond the four (4) hour period to achieve these requirements.

6. Test Documentation

Surerus will submit all required test doCLrmentation within the turnover package. Temperature and pressure readings shall be recorded as follows:

DATE 2012-'1'1-09 REVISION 2 PAGE 6 of8

Page 7: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 7 of 49 ____ , __

SURER US ---•PipellneltJt:.•

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

• Every 5 minutes between 0-30 minutes • Every 10 minutes between 30-60 minutes • Every 15 minutes for the remainder of the test

Records shall include the start and stop times for any pumping, pressunzrng, or de­pressurizing of the test section. A copy of the test worksheet shall be made available for review prior to commencement of the test. All documentation will be turned over to Enbridge upon completion of testing to facilitate completion of required Leave To Open applications.

7. Leak Detection

During the leal< test, any drop in pressure which cannot be correlated to a change in temperature shall be considered a leak. If a leak is suspected Surerus shall notify the Enbridge Representative and further pressurizing of the pipeline shall be halted until the source of the leak can be determined. Should any failure require repair, the line pressure shall be reduced to static pressure, the section dewatered, and the repair completed.

8. Depressurizing

Upon the completion of a successful test, the pipeline w ill be depressurized slowly until the energy has reached an acceptable level prior to dewatering. The line will be depressurized into a pressure trucl< rated in excess of the maximum test pressure. Under no circumstances will valves be moved to the full open position to initiate depressurizing. The maximum depressurizing rate shall be equal to 200kPa/min.

9. Dewatering 9.1 All test water shall be disposed of in accordance with applicable regulations. 9.2 Upon successful testing of the sections the water will be discharged by means of a

controlled land release in the vicinity of KP 35+500 near the water source. Water discharge volumes correspond to the section volumes. Enbridge shall secure all necessary permits for the discharge of hydrostatic test water.

9.3 Lines will be securely fastened and supported to prevent "whipping" or sudden releases of energy during the dewater or water transfer process.

9.4 A high density coated poly pig or bi-directional multi-disc pig propelled by compressed air will be used for dewatering.

9.5 Surerus will utilize additional pigs for de-watering if insufficient volumes of f luid are received at the release point of the section during initial de-water activities.

9.6 Additional runs will be performed as required to ensure that the section is sufficiently de-watered.

9.7 No conditioners, chemicals or additives will be used to alter the natural quality of the water at any point during the hydro test

9.8 Water shall be discharged into a diffuser and then directed through filter cloth to prevent erosion at the dewater location.

1 0. Pig/Cleaning Runs '10.1 Following completion of testing of each section, multiple dewatering runs shall be

completed to remove any free-standing water within the pipe section to the satisfaction of the Enbridge Representative.

DATE 20'12-'11-09

REVISION 2 PAGE 7 of 8

Page 8: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 8 of 49

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

11 . Caliper Pigging 11 .1 Following completion of pipeline drying each section shall be inspected with an

electronic caliper pig supplied by an approved Enbridge sub-contractor. 1'1.2 Caliper pigging shall be completed in accordance with relevant Enbridge

specifications. 1'1.3 An inhibitor shall be added to the line following completion of the caliper runs as

directed by Enbridge representatives

12. fest Personnel Surerus will utilize the fol lowing l<ey personnel to complete pressure testing activities:

Telford Advent Superintendent Surerus Pipeline Inc.

Chris Fleming Project Engineer Surerus Pipeline Inc.

Ken Hawthorne Test Foreman Surerus Pipeline Inc.

Zoran Ponjevic Test Consultant Prepense Specialty Testing

13. SubDContractors

e Transfer and fill pumps along with all interconnecting piping between the pumps, tanks, and test heads shall be provided by Central Water and Equipment Services based in Saskatoon, SK.

• Electronic caliper pigging shall be completed by an approved Enbridge vendor to be determined prior to caliper pigging activities.

14. Attachments

1. Hydrostatic Test Calculation Worksheets 2. Hydrostatic Test Pressure Profiles Section 1 and Section 2 3. Water Withdrawal Sketch 4. Pump Performance Curves

15. Reference Documents 1. CPCS-SPEC-HYDR0-005 Rev. 1 Pipeline Hydrostatic Testing 2. CPCS-SPEC-PIPELINE-001 Rev. 1 - Pipeline Construction 3. CPCS-SPEC-PCCT-007 Rev. 1 -Post Construction Caliper Tool. 4. Bakken Pipeline Project Canada Alignment Sheets - D-WM057-05-500-001-A 5. GSA Z662-(Latest Edition) - Oil and Gas Pipeline Systems; Canadian Standards

Association 6. Pipeline Act and Regulation - Government of Saskatchewan (Latest Edition) 7. J..\ENV - Code of Practice for TemporanJ Diversion of Water for Hydrostatic Testing of

Pipelines 8. AENV - Code of Practice for the Release of Hydrostatic Tes·( Water from the Hydrostatic

Testing of Pe·troleum Liquid and Gas Pipelines. 9. DFO - Freshwater Intake End-of-Pipe Fish Screen Guidelines.

DATE 20•12-1·!-09

REVISION 2 PAGE 8 of 8

Page 9: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 9 of 49

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

Attachment 1 = Hydrostatic Test Calculation Sheets

Page 10: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 10 of 49

HYDROSTATIC TEST CALCULATION WORKSHEET

PROJECT NAME: jEnbrldga Bakken Mainline TEST DATE: November 18,2012 PROJECT#: 11 202 TEST#: 1

SECTION#: 1 ~ FILL FLUID SOURCE: IAiameda Reservo1r -- _.,_

DEWATER LOCATION:I35+500 --=- ,_. ~ PIPELINE DATA PIPE OD (D)= 406.4 (mm) 16.00 (in) WEST END I{ .P. LOCATION 0+094 WALL THICKNESS (I)= 7.14 (mm) 0.281 (in) EAST END K.P. LOCATION 35+500 PIPE GRADE (S) = 414 (MPa) 60 (ksi) TEST POINT IS WEST OR EAST EAST MOP= 9,928 (kPa) 1,440 (psi g) 100% SMYS = 14,547 (kPa) 2,110 (psi g) 80% SMYS = 11 ,638 (kPa) 1,688 (psig) 108% SMYS = 15,711 (kPa) 2,279 (psi g) 110% SMYS = 16,002 (kPa) 2,321 (psig) SECTION LENGTH (m) = 35,406 (m} 116,161 (ft)

SECTION VOLUME (litres) = 4,275,675 (litres) 940,536 (gal) 26,872 (bbls) 0.2% OFFSET (lilres) = 8,551 (litres) 1,881 (gal) 54 (bbls)

ELEVATION AND PRESSURE DIFFERENTIALS HP - ETP= 11 .0 (m) 108 (kPa) EAST TEST POINT (ETP) = 578.00 (m) ETP- LP = 34.0 (m) 333 (kPa) HIGH POINT (HP) = 589.00 (m) HP - LP = 45.0 (m) 441 (I<Pa) LOW POINT (LP} = 544.00 (m) HP - WTP = 2.0 (m) 20 (I<Pa) WEST TEST POINT (WTP) = 587.00 (m) WTP-LP = 43.0 (m) 421 (I<Pa)

YIELD PLOT NEEDED? YES (Yes, if Maximum Strength Test Pressure at Low Point> 100% SMYS) YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = 12,759 (I<Pa) '1,850 (psig) 87.7% (%SMYS) HIGH POINT (HP) = 12,651 (I<Pa) '1,835 (psig) 87.0% (% SMYS) LOW POINT (LP) = 13,092 (kPa) 1,899 (psig) I 90.0% I(% SMYS) WEST TEST POINT (WTP) = 12,671 (kPa) 1,838 (psig) 87.1% (% SMYS)

MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = 14,655 (kPa) 2,125 (psig) 100.7% (% SMYS) 147.6% (%MOP) HIGH POINT (HP) = '14,547 (kPa) 2,1 '10 (psi g) 100.0% (o/oSMYS) I 146.5% I (%MOP) LOW POINT (LP) = 14,988 (kPa) 2,174 (psig) 103.0% (% SMYS) '151.0% (%MOP) WEST TEST POINT (WTP) = 14,567 (kPa) 2,113 (psi g) 100.1% (o/oSMYS) 146.7% (% MOP)

COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) CUSHION=! 200 j(kPa) (The Lesser oi Min. Strength Test Pressure+ a Cushion, and 108% SMYS) EAST TEST POINT (ETP) = 14,855 (I<Pa) 2,15.!!· (psi g) 102:1% (% SMYS) HIGH POINT (HP) = 14,747 (kPa) 2,139 (psi g) 101 .4% (% SMYS) LOW POINT (LP) = 15,188 (I<Pa) 2,203 (psig) 104.4% (% SMYS) WEST TEST POINT{WTP}_ = 14,767 (kPa) 2,142 (psig) 101.5% (% SMYS)

MINIMUM 'LEAl< TEST' PRESSURE ('110% of MOP at High Point) CUSHION=! 300 i(I<Pa) EAST TEST POINT (ETP) = 11,329 (I<Pa) 1,643 (psig) 77.9% (% SMYS) 114.1% (%MOP) HIGH POINT (HP) = '11,221 (I<Pa) 1,627 (psig) 77.1% (% SMYS) I 113.0% I<% MOP) LOW POINT (LP) = '1'1,662 (I<Pa) '1,691 (psig) 80.2% (o/o SMYS) 117.5% (%MOP) WEST TEST POINT (WTP) = '11 ,2<!-0 (I<Pa) '1,630 (psi g) 77.3% (o/oSMYS) '113.2% (%MOP)

CALCULATED BY (Signature 11 Full Name): Chris Flem1ng DATE: 2012-11-09

CHECKED BY CLIENT (Signature 8: Full Name): DATE:

16/11/2012

Page 11: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 11 of 49

SURERUS ~nefnc.•

HYDROSTATIC TEST CALCULATION WORKSHEET

PROJECT NAME: I En bridge Bakken Mainline TEST DATE: November 18, 2012 PROJECT#: 11202 TEST#: 1

SECTION#: 2 -FILL FLUID SOURCE:IAiameda Reservoir ~~~ ~----:-· ~.,.-

DEWATER LOCATION: 135+500 -=; ' PIPELINE DATA PIPE OD (D) = 406.4 (mm) 16.00 (in) WEST END K.P. LOCATION 35+500 WALL THICKNESS (I) = 7.14 (mm) 0.281 (in) EAST END K.P. LOCATION 123+271 PIPE GRADE (S) = 414 (MPa) 60 (ksi) TEST POINT IS WEST OR EAST WEST MOP= 9,928 (kPa) 1,440 (psig) 100% SMYS = 14,547 (kPa) 2,110 (psi g) 80% SMYS = 11,638 (kPa) 1,688 (psig) 108% SMYS= 15,71 1 (I<Pa) 2,279 (psi g) 110% SMYS = 16,002 (I<Pa) 2,321 (psi g) SECTION LENGTH (m) = 87,771 (m) 287,963 (ft) SECTION VOLUME (lilres) = 10,599,342 (litres) 2,331,576 (gal) 66,616 (bbls) 0.2% OFFSET (litres) = 2'1 ,1 99 (litres) 4,663 (gal) 133 (bbls)

ELEVATION AND PRESSURE DIFFERENTIALS HP- ETP = 107.0 (m) 1,049 (kPa) EAST TEST POINT (ETP) = 483.00 (m) ETP-LP = 13.0 (m) 127 (kPa) HIGH POINT (HP) = 590.00 (m) HP · LP = 120.0 (m) 1.176 (I<Pa) LOW POINT (LP) = 470.00 (m) HP - INTP= 0.0 (m) 0 (kPa) WEST TEST POINT (WTP) = 590.00 (m) VI!TP · LP = 120.0 (m) 1,176 (kPa)

YIELD PLOT NEEDED? YES (Yes, if Maximum Strength Test Pressure at Low Point > 100% SMYS) YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = 12,965 (kPa) 1,880 (psi g) 89.1% (%SMYS) HIGH POINT (HP) = 11,916 (kPa) 1,728 (psi g) 81.9% (% SMYS) LOW POINT (LP) = '13,092 (kPa) 1,899 (psig) I 90.0% I (% SMYS) WEST TEST POINT (WTP) = 1'1.916 (I<Pa) 1,728 (psig) 81.9% (%SMYS)

MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = '14,852 (kPa) 2,154 (psi g) 102.1% (% SMYS) 149.6% (%MOP) HIGH POINT (HP) = 13,803 (I<Pa) 2,002 (psig) 94.9% (% SMYS) I 139.0% I (% MOP) LOW POINT (LP) = 14,979 (kPa) 2, '172 (psi g) 103.0% (% SMYS) 150.9% (% MOP) WEST TEST POINT (WTP) = '13,803 (I<Pa) 2,002 (psi g) 94.9% (% SMYS) 139.0% (% MOP)

COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) CUSHION =I 250 l<kPa) (The Lesser of Min. Strength Test Pressure., a Cushion, and '108% SMYS) EAST TEST POINT (ETP) = 15,102 (I<Pa) 2,190 (psi g) 103.8% (%SMYS) HIGH POINT (HP) = 14,053 (kPa) 2,038 (psig) 96.6% (% SMYS) LOW POINT (LP) = 15,229 (kPa) 2,209 (psig) 104.7% (%SMYS) WEST TEST POINT {VVTP) = 14·,053 (kPa) 2,038 (psi g) 96.6% (% SMYS)

MINIMUM 'LEAK TEST' PRESSURE (11 0% of MOP at High Point) CUSHION = ! 300 I(I<Pa) EAST TEST POINT (ETP) = 12,269 (kPa) 1,779 (psi g) 84.3% (% SMYS) '123.6% (%MOP) HIGH POINT (l-IP) = 11,221 (I<Pa) 1,627 (psig) 77. 1% (%SMYS) I 113.0% I<% MOP) LOW POINT (LP) = 12,397 (I<Pa) '1,798 (pslg) 85.2% (% SMYS) '124.9% (%1'v10P) WEST TEST POINT (WTP) = 1'1,22'1 (I<Pa) '1,627 (psi g) 77.'1% (% SMYS) 113.0% (%MOP)

CALCULATED BY (Signature & Full Name): Chris Fleming DATE: 2012-11-09

CHECf<ED BY CLIENT (Signature 13. Full Name): DATE:

16/11/2012

Page 12: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 12 of 49

SURERUS ---•Pft»ffM Inc.•

HYDROSTATIC TEST CALCULATION WORKSHEET

PROJECT NAME: I Enbrldge Bakken Mainline TEST DATE: November 18, 201 2 PROJECT#: 11202 TEST#: 1

SECTION#: 3 FILL FLUID SOURCE: I Tanker Truck

DEWATER LOCATION: I0+094 PIPELINE DATA PIPE OD (D) = 406.4 (mm) 16.00 (in) WEST END K.P. LOCATION 0+094 WALL THICKNESS (t) = 7.92 (mm) 0.312 (in) EAST END K.P. LOCATION 0+000 PIPE GRADE (S) = 414 (MPa) 60 (ksi) TEST POINT IS WEST OR EAST WEST MOP= 9,928 (I<Pa) 1,440 (psi g) 100% SMYS= 16,136 (kPa) 2,340 (psi g) 80% SMYS = 12,909 (kPa) 1,872 (psig) 108% SMYS = 17,427 (kPa) 2,528 (psig) 110% SMYS = 17,750 (kPa) 2,574 (psi g) SECTION LENGTH (m) = 94 (m) 308 (fl) SECTION VOLUME (litres) = 11 ,261 (litres) 2,477 (gal) 71 (bbls) 0.2% OFFSET (litres) = 23 (litres) 5 (gal) 0 (bbls)

ELEVATION AND PRESSURE DIFFERENTIALS HP - ETP = 0.0 (m) 0 (kPa) EAST TEST POINT (ETP) = 587.00 (m) ETP- LP = 0.0 (m) 0 (I<Pa) HIGH POINT (HP) = 587.00 (m) HP- LP = 0.0 (m) 0 (I(Pa) LOW POINT (LP) = 587.00 (m) HP -WTP= 0.0 (m) 0 (kPa) WEST TEST POINT (VVTP) = 587.00 (m) WTP· LP = 0.0 (m) 0 (I<Pa)

YIELD PLOT NEEDED? NO (Yes, if Maximum Strength Test Pressure at Low Point> 100% SMYS) YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = 14,523 (kPa) 2,106 (psi g) 90.0% (% SMYS) HIGH POINT (HP) = 14,523 (kPa) 2,106 (psi g) 90.0% (% SMYS) LOW POINT (LP) = 14,523 (kPa) 2, '106 (psig) I 90.0% I (% SMYS) WEST TEST POINT (VIJTP) = 14,523 (kPa) 2,106 (psig) 90.0% (% SMYS)

MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = 15,321 (I<Pa) 2,222 (psi g) 94.9% (%SMYS) 154.3% (%MOP) HIGH POINT (HP) = 15,321 (I(Pa) 2,222 (psig) 94.9% (% SMYS) I 154.3% I (%MOP) LOW POINT (LP) = 15,321 (I<Pa) 2,222 (psig) 94.9% (% SMYS) 154.3% (%MOP) WEST TEST POINT (VVTP) = 15,32'1 (I<Pa) 2,222 (psig) 94.9% (% SMYS) 154.3% (%MOP)

COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) CUSHION " ! 300 I(I<Pa) (The Lesser of Min. Strength Test Pressure,, a Cushion, and 108% SMYS) EAST TEST POINT (ETP) = 15,621 (kPa) 2,266 (psi g) 96.8% (%SMYS) HIGH POINT (HP) = 15,621 (I<Pa) 2,266 (psig) 96.8% (% SMYS) LOW POINT (LP) = 15,621 (kPa) 2,266 (psi g) 96.8% (% SMYS) WEST TEST POINT (WTP) = 15,621 (I<Pa) 2,266 (psig) 96.8% (%SMYS)

MINIMUM 'LEAK TEST' PRESSURE (110% of MOP a·t High Poini) CUSHION= ! 300 I(I(Pa) EAST TEST POINT (ETP) = 11,221 (I<Pa) 1,627 (psi g) 69.5% (% SMYS) '1 13.0% (%MOP) HIGH POINT (HP) = '1 1,221 (I(Pa) 1,627 (psi g) 69.5% (% SMYS) I 113.0% I<% MOP) LOW POINT (LP) = 1'1,221 (I(Pa) '1,627 (psig) 69.5% (% SMYS) 1 '13.0% (%MOP) liVEST TEST POINT (WTP) = j-1 ,22'1 {I(Pa) '1,627 (psig) 69.5% (%SMYS) '113.0% (%MOP)

CALCULATED BY (Signature & Full Name): Chris Fleming DATE: 2012-1 1-09

CI-IECI(ED BY CLIENT (Signaiure 1!: Full Name): DATE:

16/11/ 2012

Page 13: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 13 of 49

HYDROSTATIC TEST CALCULATION WORKSHEET

PROJECT NAME: 1 Enbrldge Bakl(en Mainline TEST DATE: November 18, 2012 PROJECT#: 11202 TEST #: 1

SECTION#: 4 FILL FLUID SOURCE: I Tanker Truck -= -.. ~

DEWATER LOCATION: j123+271 ~ ~

PIPELINE DATA PIPEOD (D) = 406.4 (mm) 16.00 (in) WEST END K.P. LOCATION 123+271 WALL THICKNESS (t) = 7.92 (mm) 0.312 (in) EAST END K.P. LOCATION 123+345 PIPE GRADE (S) = 414 (MPa) 60 (ksi) TEST POINT IS WEST OR EAST WEST MOP= 9,928 (kPa) 1.440 (psig) 100% SMYS = 16,136 (I<Pa) 2,340 (psig) 80% SMYS = 12,909 (kPa) 1,872 (psig) 108% SMYS = 17,427 (kPa) 2,528 (psi g) "I"IO%SMYS= 17,750 (kPa) 2,574 (psig) SECTION LENGTH (m) = 74 (m) 243 (ft) SECTION VOLUME (litres) = 8,865 (litres) 1,950 (gal) 56 (bbls) 0.2% OFFSET (litres) = 18 (litres) 4 (gal) 0 (bbls)

ELEVATION AND PRESSURE DIFFERENTIALS HP - ETP= 0.0 (m) 0 (I<Pa) EAST TEST POINT (ETP) = 587.00 (m) ETP· LP = 0.0 (m) 0 (I<Pa) HIGH POINT (HP) = 587.00 (m) HP · LP = 0.0 (m) 0 (I<Pa) LOW POINT (LP) = 587.00 (m) HP- WTP= 0.0 (m) 0 (I<Pa) WEST TEST POINT (WTP) = 587.00 (m) WTP -LP = 0.0 (m) 0 (I<Pa)

YIELD PLOT NEEDED? NO (Yes, if Maximum Strength Test Pressure at Low Point > 100% SMYS) YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = 14,523 (kPa) 2,106 (psig) 90.0% (%SMYS) HIGH POINT (HP) = 14,523 (I<Pa) 2, 106 (psig) 90.0% (%SMYS) LOW POINT (LP) = 14,523 (kPa) 2,106 (psi g) I 90.0% I (%SMYS) WEST TEST POINT (WTP) = 14,523 (kPa) 2.106 (psig) 90.0% (% SMYS)

MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = 15,321 (kPa) 2,222 (psi g) 94.9% (% SMYS) 154.3% (% MOP) HIGH POINT (HP) = 15,321 (kPa) 2,222 (psig) 94.9% (% SMYS) I 154.3% I (%MOP) LOW POINT (LP) = 15,321 (I<Pa) 2,222 (psi g) 94.9% (%SMYS) 154.3% (%MOP) WEST TEST POINT (WTP) = 15,321 (kPa) 2,222 (psi g) 94.9% (% SMYS) 154.3% (%MOP)

COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) CUSHION= ! 300 I (I<Pa) (The Lesser of Min. Strength Test Pressure·:· a Cushion, and 108% SMYS) EAST TEST POINT (ETP) = 15,621 (I<Pa) 2,266 (psig) 96.8% (% SMYS) HIGH POINT (HP) = 15,621 (I;Pa) 2,266 (psig) 96.8% (% SMYS) LOW POINT (LP) = 15,621 (I<Pa) 2,266 (psig) 96.8% (% SMYS) WEST TEST POINT (WTP) = 15,621 (kPa) 2,266 (psi g) 96.8% (% SMYS)

MINIMUM 'LEAl{ TEST' PRESSURE (110% of MOP at High Point) CUSHION= ! 300 j(I<Pa) EAST TEST POINT (ETP) = "1"1 ,22'1 (I;Pa) 1,627 (psi g) 69.5% (% SMYS) 113.0% (% MOP) HIGH POINT (HP) = 11.221 (I;Pa) '1,627 (psig) 69.5% (% SMYS) I 113.0% I<% MOP) LOW POINT (LP) = 1"1,221 (I;Pa) 1,627 (psig) 69.5% (% SMYS) 113.0% (%MOP) WEST TEST POINT (WTP) = 11 ,221 (I;Pa) 1.627 (psi g) 69.5% (% SMYS) '11 3.0% (%1\JlOP)

CALCULATED BY (Signature lJ, Full Nama): Chris Fleming DATE: 2012-11·09

CHECI<ED BY CLIENT (Signature lJ. Full Name): DATE:

16/11/2012

Page 14: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 14 of 49

~URERUS .lillliilliliiPiptl//ne Inc.•

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

Attachment 2- Hydrostatic Test Pressure Profiles

Page 15: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge B

akken Pipeline P

roject - Certificate O

C-058

Leave to Open B

akken Pum

p Station to E

PI C

romer Term

inal A

ppendix A - A

3 Sureus H

ydrostatic Test Plan

Page 15 of 49

TEST SECTION ,+500 TO 0+000 Bakken Mainlir •s 16 HYDROSTATIC TEST PLAN

SURERUS ELEVATION PROFILES

- Pfpeloe·.b:.:•

600 1L!·,300 I<Pa j ' i I '

14,244 kPa £ 14.,250 kPa;

High t>oint, 3+400, 589

I !

-v~~A I 14,200 kPa I I I

J\1...,./~ I ' I '

I 14,150 kPa j

II ' 530 v '1\- I I 14,100 l<Pa!

i I I I

1L!.,050 kPa!

I

14,000 I<Pa!

i

' 13,950 kPa;

560 I \ I II i I

I I

13,900 I<Pa1

i

13,850 l<Pa; ' j

j 13,800 kPa:

13,803 kPa Low Point, 34+400, 544 I

1540 ~ 13,750 I<Pa ~ 0 0 0 0 0 0 0 ci ci ci ci ci ci 0 0 0 0 0 0 0 0

I ,_,

~· ~· ..... .-i ~· .-i ~: -:- -;- -:- -:- + + + -:-1./'l 0 1./'l 0 1./'l 0 1./'l

I .--! ~· N N m m

1205- Enbridge Bakken - Hydrotest Elevation Points- 2012-10-13

Page 16: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge B

akken Pipeline P

roject - Certificate O

C-058

Leave to Open B

akken Pum

p Station to E

PI C

romer Term

inal A

ppendix A - A

3 Sureus H

ydrostatic Test Plan

Page 16 of 49

SURERUS ·P1De/IM me..

620

600 ! High Woint, 38-:-500, 590

isoo j\ I I

!

560

·sL!.O

js2o

i isoo

1480 i I

L~.60

~ 13,803 kPa

0 0 c:i c:i 0 0 !.{] U )

.;; 2; ("() ~-

0 0 0 !.{]

j:, ':::i"

~ 0 0 Lfl

c5 Lfl

0 0 0 Lfl .;; 1./')

0 0 0 !.{]

g

0 0 0 Lfl .;.

1./') '-!:)

lEST SECTION ... ,.,5-:-500 TO 123+850

I~

0 0 0 !.{]

+ 0 r-...

0 0 0 !.{]

+ IJ'l 1 .....

0 0 0 Lfl

2; 00

0 0 0 L{)

+ 1./')

00

0 0 0 !.{]

2; "'

0 0 0 0 0 0 !.{] !.{]

+ + 1./') 0

"' 0 .-l

0 0 0 1./')

+ 1./')

0 .-l

Bakken Mainlt . ·- 1\lPS 16 HYDROSTATIC TEST PLAN

ELEVATION PROFILES

14,979 kPa

15,200 kPai

i 1 15,000 kPa !

I

: 14,800 kPa I

14,600 kPa:

' 14-,400 kPa !

14,200 kPai

! 14,000 kPa :

low Po;ot, 123•300, 470 ~ i

13,800 kPa l

0 0 0 0 0 0 1./') Lfl + + 0 1./') .-l ,...., ,...., ,_,

0 0 0 !.{] + 0 N

'""'

' ' I

13,600 kPa 1

1205 - Enbridge Bakken - Hydrotest Elevat ion Points- 2012-10-13

Page 17: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 17 of 49

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

Attachment 3 = Water Withdrawal Sketch

Page 18: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge B

akken Pipeline P

roject - Certificate O

C-058

Leave to Open B

akken Pum

p Station to E

PI C

romer Term

inal A

ppendix A - A

3 Sureus H

ydrostatic Test Plan

Page 18 of 49

i!t

BAI<I<EN PIPELINE 16"

ALAMEDA RESERVOIR

BAI<t<EN MAINLINE NPS 16 "

DETAILED DRAW ING OF TEM PORARY WATER INTAKE FOR HVDROTEST

ALL DIMENSIONS IN METERS

DATE PREPARED: 12/07/2012

PREPARED BY: JZ

PlAN V~EW SCALf 1:2000

WARNING SIGN

INTAKE SCREEN

WARNING SIGN I

FENCE

I PIPE 168.33 MM

I

35 15

PROFilE VI!EW

110

SCALE 1:2000 HORIZONTAL

1: 500 VERTICAl

TAN I(

TANK

12

4 1

Page 19: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 19 of 49

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

Attachment 4 ~ Pump Performance Curves

Page 20: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge B

akken Pipeline P

roject - Certificate O

C-058

Leave to Open B

akken Pum

p Station to E

PI C

romer Term

inal A

ppendix A - A

3 Sureus H

ydrostatic Test Plan

Page 20 of 49

140 . _?/),? ~ @ 25

~

420 ' 20 tu " UJ

120 15 LL . I

~ 360 /, 10 ~ (../)

~ CL

100 5 :z: . . 300 . 1--

80 . UJ w LL

(../)

I 240 = . u..J 1-- 0

~ I

u..J <C ::::E • LU I 60 :r:

= : <i 180 <C LU = 5 ~ _J 1--<C 1--

~ 40-120 ~

1.1£ ~

'

20 . v :: 60

0 0 800 1600 2400 3200 4000 4800 5600 6400 7200 8000 8800 FLDWRATE U. S.GALLDNS PER MINUTE

u u u a u u u a u a u a u s 1 a u a a s a 1 1 a u u o 1 u a u a u u u ' n u 1 u s B 1 1 a u a u a u o

0 200 400 600 800 1000 1200 1400 1600 1800 2000 FLDWRATE CUBIC ME TERS PER HOUR

f) Plf~~~fm'!aEfJl~f:. MODEL: PP 108Sl 7 IMPELLER OIA . 17 .5" OWG NO. A71 6SHQNI REVISION: 000

SIZE : 1 0" X 8" SOLIDS SIZE : 3.5" DRAWN BY: ESW DATE: 4/ 2/201 2

--

Page 21: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge B

akken Pipeline P

roject - Certificate O

C-058

Leave to Open B

akken Pum

p Station to E

PI C

romer Term

inal A

ppendix A - A

3 Sureus H

ydrostatic Test Plan

Page 21 of 49

NOTES : HEAD AND EFFICIENCY SHOWN

225 - REFLECT LOSSES DUE TO 700 NON-RETURN VALVE, OPEN-

CLEARANCE WEAR-RINGS AND 200 - VACUUM PUMP POWER.

600 !75

(./) !50 . 1- 500 ~ L.1J L.1J L.1J 1- L.L L.1J ::;;::: I

I 125 0 400 <(

0 L.1J <( :::r: L.1J

:::r: lOO - _.l <(

_.l 5 300 <( 1- 1-0

1- 75

200 I

50 -

25 !00

0 - 0 400 800 !200 !600 2000 2400 2800 3200 3600 4000 4400 I FLOWRATE U. S.GALLDNS PER MINUTE

I u ' u

0 !00 200 300 400 500 600 700 BOO 900 1000 FLDWRATE CUBIC METERS PER HOUR

• p IPCJtL'tcfm'!o~ {Jl:Jt:. MODEL: PPB6C21 IMPELLER DIA. 21 '0" OWG NO . 078l7HQNl

REVISION : 000

SIZE: 8" X 6 11 SOLIDS SIZE: 1 . s// DRAWN BY: ESW DATE: 41212012

Page 22: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 22 of 49

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

Attachment 1 - Hydrostatic Test Calculation Sheets

Page 23: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 23 of 49

SURERUS ____ ,.,_Inc.• HYDROSTATIC TEST CALCULATION WORKSHEET

PROJECT NAME: I En bridge Bakken Mainline TEST DATE: November 1, 2012

PROJECT#: 11202 TEST#: 1 SECTION#: 1

FILL FLUID SOURCE:IAiameda Reservoir

DEWATER LOCATION: I35+500 PIPELINE DATA PIPEOD (D)= 406.4 (mm) 16.00 (in) WEST END K.P. LOCATION 0+100 WALL THICKNESS (t) = 7.14 (mm) 0.281 (in) EAST END K.P. LOCATION 35+500 PIPE GRADE (S) = 414 (MPa) 60 (ksi) TEST POINT IS WEST OR EAST WEST MOP= 9,928 (kPa) 1,440 (psi g)

100% SMYS = 14,547 (kPa) 2,110 (psig) 80% SMYS = 11 ,638 (kPa) 1,688 (psig) 108% SMYS = 15,711 (kPa) 2,279 (psig) 110% SMYS = 16,002 (kPa) 2,321 (psig) SECTION LENGTH (m) = 35,400 (m) 116,142 (ft) SECTION VOLUME (litres) = 4 ,274,951 (Iii res) 940,376 (gal) 26.868 (bbls) 0.2% OFFSET (litres) = 8,550 (litres) 1,881 (gal) 54 (bbls)

ELEVATION AND PRESSURE DIFFERENTIALS HP- ETP = 11 .0 (m) 108 (kPa) EAST TEST POINT (ETP) = 578.00 (m) ETP- LP = 34.0 (m) 333 (kPa)

HIGH POINT (HP) = 589.00 (m) HP - LP = 45.0 (m) 441 (kPa) LOW POINT (LP) = 544.00 (m) HP - WfP = 2.0 (m) 20 (kPa) WEST TEST POINT {WTP) = 587.00 (m) WfP - LP = 43.0 (m) 421 (kPa)

YIELD PLOT NEEDED? NO (Yes, if Maximum Strength Test Pressure at Low Point> 100% SMYS)

YIELD PLOT START PRESSURE

EAST TEST POINT (ETP) = 12,759 (kPa) 1,850 (psi g) 87.7% (% SMYS) HIGH POINT (HP) = 12,651 (kPa) 1,835 (psig) 87.0% (% SMYS) LOW POINT (LP) = 13,092 (kPa) 1,899 (psi g) I 90.0% I(% SMYS) WEST TEST POINT {WTP) E 12,671 (kPa) 1,838 (psi g) 87.1% (% SMYS)

MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = 13,911 (kPa) 2,018 (psig) 95.6% (% SMYS) 140.1% (%MOP) HIGH POINT (HP) = 13,803 (kPa) 2,002 (psig) 94.9% (%SMYS) I 139.0% I (% MOP) LOW POINT (LP) = 14,244 (kPa) 2,066 (psig) 97.9% (% SMYS) 143.5% (%MOP) WEST TEST POINT {WTP) = 13,823 (kPa) 2,005 (psi g) 95.0% (% SMYS) 139.2% (%MOP)

COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) CUSHION= 300 (kPa) (The Lesser of Min. Strength Test Pressure + a Cushion, and 108% SMYS)

EAST TEST POINT (ETP) = 14,211 (kPa) 2,061 (psig) 97.7% (% SMYS)

HIGH POINT (HP) = 14,103 (kPa) 2,045 (psig) 96.9% (% SMYS) LOW POINT (LP) = 14,544 (kPa) 2,109 (psig) 100.0% (% SMYS) WEST TEST POINT {WTP) = 14,123 (kPa) 2,048 (psig) 97.1% (% SMYS)

MINIMUM 'LEAK TEST' PRESSURE (110% of MOP at High Point) CUSHION =I 300 (kPa) EAST TEST POINT (ETP) = 11 .329 (kPa) 1,643 (psig) 77.9% (% SMYS) 114.1% (%MOP) HIGH POINT (HP) = 11,221 (kPa) 1,627 (psig) 77.1% (% SMYSJ I 113.0% I(% MOP) LOW POINT (LP) = 11.662 (kPa) 1,691 (psig) 80.2% (% SMYS) 117.5% (% MOP) WEST TEST POINT (WTP) = 11 ,240 (kPa) 1,630 (psi g) 77.3% (% SMYS) 113.2% (%MOP)

CALCULATED BY (Signature & Full Name): Chris Fleming DATE: 2012-10-13

CHECKED BY CLIENT (Signature & Full Name): DATE:

15/10/2012

Page 24: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 24 of 49

SURERUS ---•Pfp«<ne Inc.•

HYDROSTATIC TEST CALCULATION WORKSHEET

PROJECT NAME: jEnbridge Bakken Mainline TEST DATE: November 1, 2012 PROJECT#: 11202 TEST#: 1

SECTION#: 2 FILL FLUID SOURCE: I Alameda Reservoir

DEWATER LOCATION:IJ5+500 PIPELINE DATA PIPEOD (D)= 406.4 (mm) 16.00 (in) WEST END K.P. LOCATION 35+500 WALL THICKNESS (t) = 7.14 (mm) 0.281 (in) EAST END K.P. LOCATION 123+850 PIPE GRADE (S) = 414 (MPa) 60 (ksi) TEST POINT IS WEST OR EAST WEST MOP= 9,928 (kPa) 1,440 (psig) 100% SMYS = 14,547 (kPa) 2,110 (psig) 80% SMYS= 11,638 (kPa) 1,688 (psig) 108% SMYS = 15,711 (kPa) 2,279 (psi g) 110% SMYS = 16,002 (kPa) 2,321 (psig) SECTION LENGTH (m) = 88,350 (m) 289,862 (ft) SECTION VOLUME (litres) = 10,669,263 (litres) 2,346,956 (gal) 67,056 (bbls) 0.2% OFFSET (litres) = 21,339 (litres) 4,694 (gal) 134 (bbls)

ELEVATION AND PRESSURE DIFFERENTIALS HP- ETP = 107.0 (m) 1,049 (kPa) EAST TEST POINT (ETP) = 483.00 (m) ETP- LP = 13.0 (m) 127 (kPa) HIGH POINT (HP) = 590.00 (m) HP - LP = 120.0 (m) 1,176 (kPa) LOW POINT (LP) = 470.00 (m) HP - WTP = 0.0 (m) 0 (kPa) WEST TEST POINT (WTP) = 590.00 (m) WTP - LP = 120.0 (m) 1,176 (kPa)

YIELD PLOT NEEDED? YES (Yes, if Maximum Strength Test Pressure at Low Point> 100% SMYS) YIELO PLOT START PRESSURE EAST TEST POINT (ETP) = 12,965 (kPa) 1,880 (psig) 89.1% (% SMYS) HIGH POINT (HP) = 11,916 (kPa) 1,728 (psig) 81_9% (% SMYS) LOW POINT (LP) = 13,092 (kPa) 1,899 (psig) I 90.0% I(% SMYS) WEST TEST POINT (WTP) = 11 ,916 (kPa) 1,728 (psi g) 81.9% (% SMYS)

MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = 14,852 (kPa) 2,154 (psig) 102.1% (% SMYS) 149.6% (%MOP) HIGH POINT (HP) = 13,803 (kPa) 2,002 (psig) 94.9% (% SMYSJ I 139.0% I (%MOP) LOW POINT (LP) = 14,979 (kPa) 2,172 (psig) 103.0% (% SMYS) 150.9% (% MOP) WEST TEST POINT (WTP) = 13,803 (kPa) 2,002 (psig) 94.9% (% SMYS) 139.0% (%MOP)

COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) CUSHION= ! 250 (kPa) (The Lesser of Min. Strength Test Pressure+ a Cushion, and 108% SMYS) EAST TEST POINT (ETP) = 15,102 (kPa) 2,190 (psig) 103.8% (% SMYS) HIGH POINT (HP) = 14,053 (kPa) 2,038 (psig) 96.6% (% SMYS) LOW POINT (LP) = 15,229 (kPa) 2,209 (psig) 104.7% (% SMYS) WEST TEST POINT (WTP) = 14,053 (kPa) 2,038 (psig) 96.6% (% SMYS)

MINIMUM 'LEAK TEST' PRESSURE (1 10% of MOP at High Point) CUSHION =I 300 (kPa) EAST TEST POINT (ETP) = 12,269 (kPa) 1,779 (psig) 84.3% (% SMYS) 123.6% (%MOP) HIGH POINT (HP) = 11 ,221 (kPa) 1,627 (psi g) 77.1% (% SMYSJ I 113.0% I<% MOP) LOW POINT (LP) = 12,397 (kPa) 1,798 (psig) 85.2% (% SMYS) 124.9% (%MOP) WEST TEST POINT (WTP) = 11,221 (kPa) 1,627 (psig) 77.1% (% SMYS) 113.0% (%MOP)

CALCULATED BY (Signature & Full Name): Chris Fleming DATE: 2012-10-13

CHECKED BY CLIENT (Signature & Full Name): DATE:

15/10/2012

Page 25: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 25 of 49

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

Attachment 2 - Hydrostatic Test Pressure Profiles

Page 26: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge B

akken Pipeline P

roject - Certificate O

C-058

Leave to Open B

akken Pum

p Station to E

PI C

romer Term

inal A

ppendix A - A

3 Sureus H

ydrostatic Test Plan

Page 26 of 49

~,....,.1 TEST SECTION ... .1S+SOO TO 0+000 Bakken MainlinE:: r11PS 16

HYDROSTATIC TEST PLAN

ELEVATION PROFILES SURERUS ·~Inc.•

-I

•600 - ; 14,300 kPa

!

14,244 kPa t r 14,250 kPa i

i j

14,200 kPa ·

High Point, 3+400, 589

i 14,150 kPal

580 -------------------I

14,100 kPa '

14,050 kPa ,

I i

14,000 kPai

' _1

1 13,950 kPal

~ 13,900 kPa l

1560 --- - --- ..

I I

! 13,850 kPa 1

i !

13,803 kPa Low Point , 34+400, 544 .l 13,800 kPa i

I '

;s4o ~-----------;-------------.~-------------,,---------------r---------------.---------------.- 13,750 kPa 0 0 0 ..... +

0 0 0 ..... + U'l

0 ci 0 ..... + 0 .....

0 ci 0 ..... + U'l .....

0 0 0 ..... + 0 N

0 0 0 ci ci ci 0 0 0 ..... ..... ..... + + + U'l 0 U'l N M M

1205 - Enbridge Bakken- Hydrotest Elevation Points- 2012-10-13

Page 27: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge B

akken Pipeline P

roject - Certificate O

C-058

Leave to Open B

akken Pum

p Station to E

PI C

romer Term

inal A

ppendix A - A

3 Sureus H

ydrostatic Test Plan

Page 27 of 49

SURERUS ·P.(pefne Inc ••

!620

TEST SECTION 2 · _ _,+500 TO 123+850 Bakken Mainlint . • PS 16

HYDROSTATIC TEST PLAN

ELEVATION PROFILES

--, 15,200 kPa!

·- - - ···--------------·- --- - --- - -- ---- - - --· - ·-- -- ----------- l4,979 kPa &i 15,000 kPa l 600 High Point, 38+500, 590 if ,

: 580 . - -- -- -- ... - ,

560 - - ---- ---- ----- - -·--· \1

' 540 ---- -···--·----------------------------------

' i i520

I

isoo I

i

480

13,803 kPa

1

460 I 0 I ci

0 Lf)

+ Lf) N'\

0 ci 0 Lf)

+ 0 q-

0 ci 0 Lf)

+ Lf) q-

0 ci 0 Lf)

+ 0 Lf)

---- -·-' ' --, -,---0 0 0 0 ci ci ci ci 0 0 0 0 Lf) Lf) Lf) Lf)

+ + + + Lf) 0 Lf) 0 Lf) 1.0 1.0 r-...

-A--

-0 0 0 0 0 0 ci ci ci ci ci ci 0 0 0 0 0 0 Lf) Lf) Lf) Lf) Lf) Lf)

+ + + + + + Lf) 0 Lf) 0 Lf) 0 r-... co co en en 0 ......

---·-~--- - ------ -· - ---- - ---

Low Point, 123+300, 470

0 0 0 0 ci ci ci ci 0 0 0 0 Lf) Lf) Lf) Lf)

+ + + + Lf) 0 Lf) 0 0 ...... ...... N ...... ...... ...... ......

--- ---

14,800 kPa l

I

14,600 kPa

14,400 kPa I I I I

14,200 kPa ! I I I

14,000 kPa!

13,800 kPa '

13,600 kPa

1205 - Enbridge Bakken - Hydrot est Elevat ion Points- 2012-10-13

Page 28: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 28 of 49

~URERUS .--Pipeline Inc.•

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

Attachment 3 - Water Withdrawal Sketch

Page 29: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge B

akken Pipeline P

roject - Certificate O

C-058

Leave to Open B

akken Pum

p Station to E

PI C

romer Term

inal A

ppendix A - A

3 Sureus H

ydrostatic Test Plan

Page 29 of 49

BAKKEN MAINLINE NPS 16"

DETAILED DRAWING OF TEMPORARY WATER INTAKE FOR HYDROTEST

All DIMENSIONS IN METERS

DATE PREPARED: 12/07/2012

PREPARED BY: JZ

PLAN VIEW SCALE 1'2000

I~ "'"""''"'"'~ -------- 7 "-,. '

WARNING SIGN

ALAMEDA

RESERVOIR

EXISTING PIPELINES

- · -- > <;i < .. __

FENCE

BAKKEN PIPELINE 16" INTAKE SCREEN

WARNING SIGN

35

PROFILE VIEW

15

PIPE 168.33 MM

II 110

SCALE 1:2000 HORIZONTAl

1: 500 VERTICAL

TANK

TANK

12

4 1

Page 30: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 30 of 49

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

Attachment 4 - Pump Performance Curves

Page 31: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge B

akken Pipeline P

roject - Certificate O

C-058

Leave to Open B

akken Pum

p Station to E

PI C

romer Term

inal A

ppendix A - A

3 Sureus H

ydrostatic Test Plan

Page 31 of 49

140 ), v 25 . .

420 "' 20 tu L.U

120 IS LL I

360 vh 10 ~ (/)

CL

100 5 :z

- 300 1-- ~ tl

BO L.U L.U LL

(./)

I 240 0<: L1.J ~ - Cl L1.J S :t :::E <!;

L.U I 60 :::r::

= <i lBO <C L1.J = 1--

rJ Cl __J 1--<C

§ 40 120 1./.L

.

. 20 60 :

' 0 0 BOO 1600 2400 3200 4000 4BOC 5600 6400 7200 BODO BBOO

FLDWRATE U.S. GALLDNS PER MINUTE I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I

0 200 400 600 BOO 1000 1200 1400 1600 I BOO 2000 FLDWRATE CUBIC METERS PER HOUR

,, PIPCJ/:ff£/f,{Jo~fJ/:J~ MODEL: PP108Sl7 IMPELLER DIA . 17. 5" DWG NO. A716SHQNI REVISION: 000

SIZE: 1 0" X 8" SOLIDS SIZE: 3.5" DRAWN BY: ESW DATE: 41212012

Page 32: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge B

akken Pipeline P

roject - Certificate O

C-058

Leave to Open B

akken Pum

p Station to E

PI C

romer Term

inal A

ppendix A - A

3 Sureus H

ydrostatic Test Plan

Page 32 of 49

NOTES: HEAD AND EFFICIENCY SHOWN

225 REFLECT LOSSES DUE TO 700 NON-RETURN VALVE, OPEN-

CLEARANCE WEAR-RINGS AND 200 . VACUUM PUMP POWER.

500 175

(/)150 ..._500 c::u L.lJ L.lJ L.lJ I- L.L L.lJ :::;::: I

I 125 o400 <l:

Cl w <r: I L.lJ

I I 00 - _j

<l: _j b 300 <r: f- I-Cl

f- 75

200 I

50

25 100

0 0 400 BOO 1200 1500 2000 2400 2000 3200 3500 4000 4400 FLOWRATE U.S.GALLONS PER MINUTE

I I I T . 0 100 200 300 400 500 500 700 800 900 1000

FLOWRATE CUB IC METERS PER HOUR

~~ Plpc;//;L~/tlJo~fd!Jfo:. MODEL : PP86C21 IMPELLER DIA . 21 '0" DWG NO. 07817HQNI REVISION : 000

SIZE: 8" X 6" SOLIDS SIZE: 1 . S" DRAWN BY: ESW DATE: 41212012

-

Page 33: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 33 of 49

-------SURI!JJ

HYDROSTATIC TEST

PLAN

Bakken Pipeline Expansion Project,

HOD Sections NPS 16

Prepared by: Sure rus Pipeline Inc.

For: Enbridge Bakken L.P.

20'12-08-"14 0

Page 34: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 34 of 49

------SUR~&t~

Bakken NPS 16 HDD Sections HYDROSTATIC TEST PLAN

1. Scope This document was prepared for the hydrostatic pressure testing of the three (3) watercourse crossing sections on the Enbridge Bakken NPS 16 Pipeline Project planned for installation by Horizontal Directional Drill (HOD) methods. The three watercourse crossings include the Shepherd Creek, Moose Mountain Creek, and the Pipestone Creek. The hydrostatic test consists of a combined one (1) hour strength and leak test to verify the integrity of the pipeline following installation.

2. Safety

2.1. All personnel shall review and follow the Emergency Response Plan (ERP) developed specifically for this project. A copy ·of the ERP shall be available in each vehicle used on the project and additional copies shall be posted within the test building and other appropriate locations.

2.2. A pre-phase meeting will be held at the Surerus site office for all personnel involved in the hydrostatic test prior to commencement of the test to ensure that all personnel understand their respective duties.

2.3. Surerus will install warning signs and barricades to prevent access to the vicinity of the test area. Warning signs shall indicate "DANGER - High Pressure Pipeline Test" and "Restricted Access".

2.4. All Surerus personnel not involved in the testing shall be removed from the area while the pipeline section is under a pressure equal to or greater than 2,760kPa (400psi).

2.5. Test heads and pressurizing pipe shall be secured to limit movement. 2.6. All testing equipment including compressors, recorders, deadweights, etc. shall be set

up a safe distance from the test section and/or test heads. 2.7. Surerus employees shal l inspect all hoses, lines, and connections for faults prior to

pressurizing the lines. The Surerus Hydrotest Pre-test Checl{list will be completed to ensure that all components meet the required ratings.

2.8. Surerus personnel shall ensure pressure hoses/unions are rated to twice the maximum expected hydrotest pressures, and all safety lines are firmly attached and secured with whip checi\S.

2.9. An Enbridge representative will be on site for the duration of test activities.

3. Equipment

Surerus shall supply the following equipment for completion of the hydrostatic test: Pumps including transfer/fill pump, and squeeze pump. Air compressors required for pipeline cleaning, pre-pack, and dewatering. 1-\11 pipeline pigs required for line fill and dewatering. All necessary valves, hoses, and fittings required to successfully complete the test. Calibrated temperature recorders, pressure recorders, and deadweights. Calibrated flow meter for preparation of the yield plot where applicable. Adequate lighting and light towers at all worl\ areas.

3. 1 Test Heads

3:1."1 Surerus shall supply Enbriclge approved i:est heads.

DA l E 2012-08-1 <!· REVISION 0 PAGE 2 of6

Page 35: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 35 of 49

-------SURiJWJ

3.1 .2

3.1 .3

Bakken NPS 16 HDD Sections HYDROSTATIC TEST PLAN

Test head assemblies shall comply with all requirements of CSA-Z662 (latest edition). All documentation certifying test head compliance shall be available prior to commencement of testing. Test heads will be welded to the section and the welds will be inspected by NDE prior to filling the section.

3.2 Pumps

3.2.1 Surerus shall ensure that fill and squeeze pumps are adequately sized for the length and diameter of the section to be tested.

3.2.2 Water for the hydrostatic test will be withdrawn from the approved water source (Shepherd's Creek) into tanker trucks and transferred to the test sections according to the details in section 4 below.

3.3 Instrumentation:

3.3.1 Surerus shall supply pressure and temperature recorders and dead weights to provide readings for the test data. The pressure shall be measured in psi or kPa, and the temperature measured in degrees Celsius.

3.3.2 All test charts and reports, including the depressurizing of tested lines, will be included in the document turnover package.

3.3.3 Instrumentation for the test shall be as follows: • Two dual pen temperature/pressure recorders and a digital dead weight will

be located at the fill point. 3.3.4 All measurement equipment shall be certified for accuracy not more than 30 days

prior to commencement of the pressure test. The calibration certificates and current calibration reports shall be maintained on site and included in the turnover package following completion of the test.

4. Line Fill

4.1 Test Sections

Section Length Volume Source Dewater Location

1 Shepherd's Creel{ 377m 44m3 Shepherd's Creel( Transfer to Moose Min. Creek Section

2 Moose Mountain 725m 85m3 Shepherd's Creek Landspread in

Creek HOD Section SE1/4 27-4-2W2

3 Pipestone Creel( 211m 25m3 Pipestone Creek Landspread in SW1 /4 17 -9-28WPM

DATE 20'12-08- ·1 t!· REVISION 0 PAGE 3 of6

Page 36: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 36 of 49

-------SURlBJI,! Bakken NPS 16 HDD Sections

HYDROSTATIC TEST PLAN

4.2 Fill section

Test heads will be welded onto the ends of each test section and will be inspected by NDE. NDE documentation shall be retained to support acceptability of the welds. The foreman shall inspect all connections and hoses prior to filling the section. Prior to filling the pipeline, the fill line shall be leak tested for a minimum of 5min at 3,450kPa (500psi). To ensure a consistent fill Surerus will monitor and control pressure at the section end during fill. Surerus does not anticipate that a pre-pack of the line is required due to the minimal elevation difference throughout the test section. A single medium density pig will be pre-loaded into the test head and will be driven through the pipeline by the rate of the fluid insertion. During the line fill process fluid samples shall be obtained by Enbridge Representatives and submitted for analysis as required. The filling operation shall be continuous to prevent air ingress.

4.3 Pressurize and test the section.

Before pressurizing the section beyond a pressure of 2, 760kPa (400 psi), all worl< crews will be notified and removed from the vicinity of the test section. All pipe and fill connections shall be checked for leaks and these test areas shall be maintained as "off-limits" to non-essential personnel. Pressure will be increased to 2,760kPa (400psi) and all visible piping inspected for leaks. Upon completion of the leak check, the line and manifold will be bled off, an in line check valve installed on the squeeze line and the squeeze pump connected to the line. Squeeze pressure will be initiated through a 1" or 2" line rated to 5500psi; pressure shall be increased in stages as indicated in the Hydrostatic Test Record Worl<sheets.

5. Test Stages

The pipeline shall be tested in a combined '1-hour strength and leak test. The pipe section will be available for visual inspection throughout the duration of the test.

5.1. Combined One-Hour Strength and Lealt Test The test involves a leal< check at approximately 2,760kPa (400psi) to allow visual inspection of e:<posed piping and fittings included in the test section. Following satisfactory completion of the leak checl<, testing will continue by slowly raising the pressure to the strength test pressure as indicated in the attached Hydrotest Calculation Worksheets . The strength test will be held at a pressure greater than the minimum test pressure. 5.2.1 The combined strength and leal< test will be held at a pressure greater than ths

minimum test pressure. The test pressure shall be basecl upon the ma)<imum anticipated pressure the HDD section will e:<perience during the mainline pressure test.

5.2.2 After pumping has ceased, and the selected strength test pressure has been reachecl, the combined strength and leak test will commence. The pressure at the l1ighpoint shall matcl1 or exceecl this minimum at both the start and the encl ohhe

DA l E 2012-08-"14 REVISION 0 PAGE 4 of6

Page 37: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 37 of 49

-------SUR§!IJ. Bakken NPS 16 HOD Sections HYDROSTATIC TEST PLAN

test, and at no time during the test period shall the pressure at the high point drop below the required minimum.

5.2.3 The minimum duration for the hold period on the combined strength and leal< test is one (1) hour.

6. Test Documentation

Surerus will submit all required test documentation within the turnover package. Temperature and pressure readings shall be recorded as follows:

• Every 5 minutes between 0-30 minutes • Every 10 minutes between 30-60 minutes

Records shall include the start and stop times for any pumping, pressunzmg, or de­pressurizing of the test section. A copy of the test worl<sheet shall be made available for review prior to commencement of the test. All documentation will be turned over to Enbridge upon completion of testing.

7. Leak Detection

During the leak test, any drop in pressure which cannot be correlated to a change in temperature shall be considered a leak. If a leak is suspected Surerus shall notify the Enbridge Representative and further pressurizing of the pipeline shall be halted until the source of the leak can be determined. Should any failure require repair, the line pressure shall be reduced to zero, the section dewatered, and the repair completed.

8. Depressurizing

Upon the completion of a successful test, the HOD section will be depressurized slowly until the energy has reached an acceptable level prior to dewatering. The line will be depressLirized into a pressure truck rated in excess of the maximum test pressure. Under no circumstances will valves be moved to the full open position to initiate depressurizing.

9. Dewatering 9. 'I All test water shall be disposed of in accordance with applicable regulations. 9.2 Upon successful testing of the sections, the water will be discharged by means of a

controlled land release. Water discharge volumes correspond to the section volumes noted in section 4 of this document. Enbridge shall secure all necessary permits for the discharge of hydrostatic test water.

9.3 Lines will be securely fastened and supported to prevent "whipping" or sudden releases of energy during the dewater or water transfer process.

9.4 A high density coated poly pig or bi-directional multi-disc pig propelled by compressed air will be used for dewatering.

9.5 SLirerus will utilize additional pigs for de-watering if insufficient volumes of fluid are received at the release point of the section during initial de-water activities.

9.6 Additional runs will be performed as required to ensure that the section is sufficiently cle-watered.

9.7 No conditioners, chemicals or additives will be used to alter the natural quality of the vvater ai any point during the hydro test.

DATE 20'12-08-14· REVISION 0 PAGE 5 of 6

Page 38: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 38 of 49

-------SUR§!JJ Bakken NPS 16 HDD Sections

HYDROSTATIC TEST PLAN

9.8 Water shall be discharged into a diffuser and then directed through filter cloth to prevent erosion at the dewater location.

12. Test Personnel Surerus will utilize the following key personnel to complete pressure testing activities:

Telford Advent Superintendent Surerus Pipeline Inc.

Julio Zavaleta Project Engineer Surerus Pipeline Inc.

Ken Hawthorne Test Foreman Surerus Pipeline Inc.

13. Attachments

1. Hydrostatic Test Calculation Worl<sheets - HOD Sections.

14. Reference Documents 1. CPCS-SPEC-HYDR0-005 Rev. 1 Pipeline Hydrostatic Testing 2. CPCS-SPEC-PIPELINE-001 Rev. 1 - Pipeline Construction 3. CPCS-SPEC-PCCT-007 Rev. 1 - Post Construction Caliper Tool. 4. Bakken Pipeline Project Canada Alignment Sheets - D-WM057-05-500-001-A 5. CSA Z662-(Latest Edition) - Oil and Gas Pipeline Systems; Canadian Standards

Association 6. Pipeline Act and Regulation - Government of Saskatchewan (Latest Edition) 7. AENV - Code of Practice for Temporary Diversion of Water for Hydrostatic Testing of

Pipelines 8. AENV - Code of Practice for the Release of Hydrostatic Test Water from the Hydrostatic

Testing of Petroleum Liquid and Gas Pipelines. 9. DFO - Freshwater Intake End-of-Pipe Fish Screen Guidelines.

DAlE 2012-08-'14 REVISION 0 PAGE 6 of 6

Page 39: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 39 of 49

HYDROSTATIC TEST CALCULATION WORKSHEET

PROJECT NAME: IEnbrldge Bakken Pre-Test Shepherd's Creek TEST DATE: August 16,2012 PROJECT#: 11202 TEST#: 1

SECTION#: HOD -SC FILL FLUID SOURCE: I Shepherd's Creek

DEWATER LOCATION: 130+800 PIPELINE DATA

I PIPE OD(D) = 406.4 (mm) 16.00 (in) WEST END K.P. LOCATION 30+490 WALL THICKNESS (t) = 10.31 (mm) 0.406 (in) EAST END K.P. LOCATION 30+861--.. PIPE GRADE (S) = 414 (MPa) 60 (ksl) TEST POINT IS WEST OR EAST 'WES:y-' MOP = 9,928 (kPa) 1,440 (pslg) ~

100% SMYS = 21,006 (kPa) 3,046 (psig) 80%SMYS = 16,804 (kPa) 2,437 (psig)

~ W8% SMYS= 22,686 (I<Pa) 3,290 (pslg) 110% SMYS = 23,106 (kPa) 3,351 (pslg) SECTION LENGTH (m) = 377 (m) 1,237 (ft) SECTION VOLUME (litres) = 44,067 (litres) 9,694 (gal) 277 (bbls) 0.2% OFFSET (litres) = 88 (litres) 19 (gal) 1 (bbls)

ELEVATION AND PRESSURE DIFFERENTIALS V HP - ETP = 0.0 (m) 0 (I<Pa) EAST TEST POINT (ETP) = 570.00 (m) ETP- LP = 10.0 (m) 98 (I<Pa) HIGH POINT (HP) = 570.00 (m) HP- LP = 10.0 (m) 98 (I<Pa) LOW POINT (LP) = 580.00 (m) HP- WTP = 10.0 (m) 98 (I<Pa) WEST TEST POINT (WTP) = 580.00 (m) WTP -LP = 0.0 (ml 0 (kPa)

./h

YIELD PLOT NEEDED? p_NO~Y (Yes. if Maximum Strength Test Pressure at Low Point> 100% SMYS) YIELD PLOT START PRESSURE ~

EAST TEST POINT (ETP) = '18,807 (I<Pa) 2,728 (psig) 89.5% (% SMYS) HIGH POINT (HP) = 18,807 (I<Pa) 2,728 (psi g) 89.5% (%SMYS) LOW POINT (LP) = 18,905 (I<Pa) 2,742 (psig) I 90.0% I (%SMYS) WEST TEST POINT (WTP) = 18.905 (I<Pa) 2,742 (psig) 90.0% (%SMYS)

MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = '15,24·0 (I<Pa) 2.210 (psig) 72.6% (% SMYS) 153.5% (%MOP) HIGH POINT (HP) = '15,240 (I<Pa) 2,210 (psig) 72.6% (% SMYS) I 153.5% I (%MOP) LOW POINT (LP) = 15,338 (kPa) 2,225 (psig) 73.0% (% SMYS) 154.5% (%MOP) WEST TEST POINT JVVT_Pl = 15,338 (I<Pa) 2,225 (psig) 73.0% (%SMYS) 154.5% (%MOP)

s COMMENCEMEN 1 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) CUSHION • I 300 l(i<Pa) (The Lesser or Min. Strength Tes~ Pressure,. a Cushion, and '108% SMYS) EAST TEST POINT (ETP) = '15,540 (I<Pa) 2,254 (psig) 74.0% (% SMYS) HIGH POINT (HP) = 15,5-'1·0 (I<Pa) 2,254 (psig) 74.0% (% SMYS) LOW POINT (LP) = 15,638 (I<Pa) 2,268 (psig) 74.4% (% SMYS) WEST TEST POINT (WTP) = 15,638 (I<Pa) 2,268 (psig) R4% (% SMYS)

MINIMUM 'LEAK TEST' PRESSURE (110% of MOP a1 High Point) CUSHION =I 300 l(kPa) EAST TEST POINT (ETP) = '1'1,22'1 (I<Pa) 1,627 (psig) 53.4% (%SMYS) '113.0% (%MOP) HIGH POINT (l-IP) = '1'1 .22'1 (I<Pa) 1,627 (psig) 53.4% (%SMYS) I '1'13.0% I<% MOP) LOW POINT (LP) = 11.31 g (I<Pa) '1,642 (psi g) 53.9% (%SMYS) 114.0% (%MOP) WEST TEST POINT (WTP) = '1 1,3'19 (I<Pa) '1,6~2 (psig) 53.9% (% SMYS) 1'1-4.0% (%MOP)

CALCUIJ\TED BY (Signature B, Full Name): Chns Flem1ng DATE: 2012-08-15

CHECf<ED 8Y CLIENT (Signature 1!, Full Name): DATE:

15/08/2012

Page 40: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 40 of 49

HYDROSTATIC TEST CALCULATION WORKSHEET

PROJECT NAME: IEnbridge Bakken Pre-Test Alameda Res TEST DATE: August 23, 2012 PROJECT#: 11202 TEST#: 1

SECTION#: HDD- AR FILL FLUID SOURCE: !Moose Mountain Creek

DEWATER LOCATION: 135+800 -,.

PIPELINE DATA PIPE OD(D) = 406.4 (mm) 16.00 (in) WEST END K.P. LOCATION 35+048 WALL THICKNESS (t) = 10.31 (mm) 0.406 (in) EAST END K.P. LOCATION 35+773 PIPE GRADE (S) = 414 (MPa) 60 (ksi) TEST POINT IS WEST OR EAST WEST MOP= 9,928 (kPa) 1,440 (psig) 100% SMYS = 21,006 (kPa) 3,046 (ps ig) 80% SMYS= 16,804 (kPa) 2,437 (psig) 108% SMYS = 22,686 (kPa) 3,290 (psig) 110% SMYS = 23, 106 (kPa) 3,351 (psi g) SECTION LENGTH (m) = 725 (m) 2,379 (ft)

SECTION VOLUME (litres) = 84,744 (litres) 18,641 (gal) 533 (bbls) 0.2% OFFSET (litres) = 169 (litres) 37 (gal) 1 (bbls)

ELEVATION AND PRESSURE DIFFERENTIALS HP · ETP = 0.0 (m) 0 (kPa) EAST TEST POINT (ETP) = 580.00 (m) ETP-LP = 5.0 (m) 49 (I<Pa) HIGH POINT (HP) = 580.00 (m) HP- LP = 5.0 (m) 49 (I<Pa) LOW POINT (LP) = 575.00 (m) HP-WTP = 5.0 (m) 49 (I<Pa) WEST TEST POINT (WTP) = 575.00 (m) WTP- LP = 0.0 (m) 0 (kPa)

YIELD PLOT NEEDED? NO (Yes, if Maximum Strength Test Pressure at Low Point > 100% SMYS) YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = '18,856 (kPa) 2,735 (psig) 89.8% (% SMYS) HIGH POINT (HP) = 18,856 (kPa) 2,735 (psig) 89.8% (%SMYS) LOW POINT (LP) = 18,905 (kPa) 2,742 (psig) I 90.0% I(% SMYS) WEST TEST POINT (WTP) = 18,905 (kPa) 2.742 (psig) 90.0% (% SMYS)

MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = 15,240 (kPa) 2,210 (psig) 72.6% (% SMYS) 153.5% (%MOP) HIGH POINT (HP) = 15,240 (I<Pa) 2,210 (psig) 72.6% (% SMYS) I 153.5% I (%MOP) LOW POINT (LP) = 15,289 (I<Pa) 2,2"17 (psig) 72 .8% (% SMYS) 154.0% (%MOP) WEST TEST POINT (WTP) = 15,289 (kPa) 2,217 (psig) 72.8% (% SMYS) 154.0% (%MOP)

COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 103% SMYS) CUSHION =I 300 l(kPa) (The Lesser of Min. Strength Test Pressure ·:- a Cushion, and 108% SMYS) EAST TEST POINT (ETP) = '15,540 (I<Pa) 2,254 (psig) 74.0% (% SMYS) HIGH POINT (HP) = 15,540 (I<Pa) 2,254 (psig) 74.0% (% SMYS) LOW POINT (LP) = 15,589 (I<Pa) 2,261 (psig) 74.2% (% SMYS) WEST TEST POINT (WTP) = 15,589 (I<Pa) 2,261 (psig) 74.2% (% SMYS)

MINIMUM 'LEAK TEST' PRESSURE (11 0% of MOP at High Point) CUSHION= I 300 I(I<Pa} EAST TEST POINT (ETP} = '1'1,22'1 (I<Pa} ·1,627 (psig} 53 A% (% SMYS) "113.0% (%MOP} HIGH POINT (HP} = 11 ,221 (I<Pa) 1,627 (psig) 53.4% (% SMYS) I "113.0% IC%MOP) LOW POINT (LP) = "11 ,270 (I<Pa) '1,634 (psig} 53.7% (% SMYS) 113.5% (%MOP) WEST TEST POINT (WTP) = '1'1,270 (I<Pa) '1,63•!· (psig) 53.7% (% SllilYS) 1"13.5% (%MOP}

CALCULATED BY (Signature 8. Full 1\lame): Chris Fleming 01-\TE: 2012-08-15

CHECI~ED BY CLIENT (Signa·iure (!, Full Name): DATE:

15/08/2012

Page 41: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 41 of 49

SURERUS ~lno.•

HYDROSTATIC TEST CALCULATION WORKSHEET

PROJECT NAME: IEnbrldge Bakl:en Pre-Test Pipestone Crk TEST DATE: September 1, 2012 PROJECT#: 11202 TEST#: 1

SECTION#: HOD -PC FILL FLUID SOURCE: {Pipestone Creek

DEWATER LOCATION:I123+500 PIPELINE DATA PIPE OD (D) = 406.4 (mm) 16.00 (in) WEST END K.P. LOCATION 123+289 WALL THICKNESS (t) = 10.31 (mm) 0.406 (in) EAST END K.P. LOCATION 123+500 PIPE GRADE (S) = 41 4 (MPa) 60 (ksi) TEST POINT IS WEST OR EAST WEST MOP = 9,928 (kPa) 1,440 (pslg) 100% SMYS = 21,006 (I<Pa) 3,046 (psig) 80% SMYS = 16,804 (kPa) 2,437 (psig) 108% SMYS = 22,686 (kPa) 3,290 (psi g) 110% SMYS = 23,106 (kPa) 3,351 (psig) SECTION LENGTH (m) = 211 (m) 692 (ft) SECTION VOLUME (litres) = 24,663 (lilres) 5,425 (gal) 155 (bbls) 0.2% OFFSET (litres) = 49 (litres) 11 (gal) 0 (bbls)

ELEVATION AND PRESSURE DIFFERENTIALS HP - ETP= 0.0 (m) 0 (kPa) EAST TEST POINT (ETP) = 474.00 (m) ETP- LP = 4.0 (m) 39 (kPa) HIGH POINT (HP) = 474.00 (m) HP- LP = 4.0 (m) 39 (I<Pa) LOW POINT (LP) = 470.00 (m) HP - WTP = 4.0 (m) 39 (I<Pa) WEST TEST POINT (WTP) = 470.00 (m) WTP - LP = 0.0 (m) 0 (kPa)

YIELD PLOT NEEDED? NO (Yes, if Maximum Strength Test Pressure at Low Point> 100% SMYS) YIELD PLOT START PRESSURE EAST TEST POINT (ETP) = 18,866 (I<Pa) 2,736 (psig) 89.8% (% SMYS) HIGH POINT (HP) = 18,866 (I<Pa) 2,736 (psig) 89.8% (% SMYS) LOW POINT (LP) = 18,905 (I<Pa) 2,742 (psig) I 90.0% I (% SMYS) WEST TEST POINT (WTP) = 18,905 (I<Pa) 2,742 (psig) 90.0% (% SMYS)

MINIMUM 'STRENGTH TEST' PRESSURE EAST TEST POINT (ETP) = 15,24·0 (I<Pa) 2,210 (psig) 72.6% (% SMYS) 153.5% (% MOP) HIGH POINT (HP) = 15,240 (I<Pa) 2,210 (psig) 72.6% (% SMYS) I 153.5% I (% MOP) LOW POINT (LP) = 15,279 (I<Pa) 2,216 (pslg) 72.7% (% SMYS) 153.9% (%MOP) WEST TEST POINT (WTP) = 15,279 (I<Pa) 2,216 (psig) 72.7% (% SMYS) 153.9% (% MOP)

COMMENCEMENT 'STRENGTH TEST' PRESSURE (LIMIT IS 108% SMYS) CUSHION =I 300 l(i<Pa) (Tha Lesser of Min. Strength Test Pressure-:- a Cushion, and 108% SMYS) EAST TEST POINT (ETP) = '15,540 (kPa) 2,254 (psig) 74.0% (% SMYS) HIGH POINT (HP) = 15,540 (I<Pa) 2,254 (psig) RO% (% SMYS) LOW POINT (LP) = 15,579 (I<Pa) 2,259 (psig) 74.2% (% SMYS) WEST TEST POINT (WTP) = 15,579 (I<Pa) 2,259 {psig) 74.2% (% SMYS)

MINIMUM 'LEAK 1 EST' PRESSURE (11 0% of MOP ai High Poini) CUSHION =I 300 I(I<Pa) EAST TEST POINT (ETP) = 11 ,221 (I<Pa) '1,627 (psig) 53.4% (% SMYS) 113.0% (%MOP) HIGH POINT (HP) = 11,221 (I<Pa) 1,627 (psig) 53.4% (% SMYS) I 1'13.0% l (%MOP) LOW POINT (LP) = 11,260 (I<Pa) 1,633 {psig) 53.6% (% SMYS) 113.4% (%MOP) WEST TEST POINT (\/IJTP) = '11,260 (I<Pa) '1,633 (psig) 53.6% (% SMYS) '1 13.4% (%MOP)

CALCULATED BY (Signature 1!: Full Name): Chris Flem1ng DATE: 2012-08-15

CHECI~ED BY CLIENT (Sigi1ature B. Full Name): DATE:

lS/08/2012

Page 42: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 42 of 49

SURERUS - --l'lptl/lte lilt.• DATE 15/08/2012

SECTION# NPS 16 TH-001/006

VOLUME 2.0 m3 TEST LOCATION .:...F.;..;:roc;;.b;.:.;ishc.;.;e"-r...;..Y;;;.;ar..::.d _ ____ _

TEST STAGES

1) 2) 3)

Combined Leak/StrenQth kPa psi

2,760 400 8,000 1,160

19,300 2,799

Test Head Pre~ Test Hydrostatic Pressure Test Record

FROM 0+000 TO 0+016

LENGTH

Target Test Pressure(+/- 10psi)

16 m

TEMPERATURE DEADWEIGHT 1-\MCit:N I t;;t-<UUND VOLUME

TIME PRESSURE (kPa) (•C) (· c ) (m3) NOTES

SURERUS REPRESENTATIVE CLIENT REPRESENTATIVE

HYDROSTATIC TEST PRESSURE RECORD

Page 43: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 43 of 49

SECTION# NPS 16 TH-004/005

VOLUME 2.0 m3 TEST LOCATION ..:...F.:.::ro:.::;b:.:::ishe:.:.:::.:...r..:...Y::.:ar.::.d _____ _

TEST STAGES

1) 2)

3)

Combined Leak/StrenQth kPa psi

2,760 400 8,000 1,160

19,300 2,799

Test Head Pre-Test Hydrostatic Pressure Test Record

FROM IO+OOO TOI0+016

LENGTH !

Target Test Pressure(+/- 10psi)

16m

TEMPERATURE DEADWEIGHT AMI:!It:N I GKOUNU VOLUME

TIME PRESSURE (kPal (•C) ("C) (m3} NOTES

SURERUS REPRESENT.IHIVE CLI ENT REPRESENTATIVE

HVDROSTA TIC TEST PRESSURE RECORD

Page 44: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 44 of 49

HYDROSTATIC TEST PLAN

Bakken Pipeline Expansion Project, Mainline Pipeline NPS 16

Steelman Section

Prepared by: Surerus Pipeline Inc.

For: Enbridge Bakken L.Pm

DATE 2012-1·1-16 REVISION 0

I

Page 45: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 45 of 49

1. Scope

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

Steelman Section

This document was prepared for the hydrostatic pressure testing of the En bridge Bakl<en Mainline NPS 16 Pipeline Project planned for construction in the summer/fall of 2012 between Steelman, SK and Cromer, MB. This test plan encompasses approximately 94m of pipe from the Steelman terminal eastbound; the test section end points are detailed within the document below. The Steelman section of the pipeline will be tested above ground prior to installation due to access restrictions. The segment will be tested for a minimum period of one (1) hour to permit visual inspection of the pipeline during a combined strength and leak test utilizing a water/methanol mix to prevent freezing during testing.

2. Safety 2.1. All personnel shall review and follow the Emergency Response Plan (ERP) developed

specifically for this project. A copy of the ERP shall be available in each vehicle used on the project.

2.2. A pre-phase meeting will be held at the Surerus site office for all personnel involved in the hydrostatic test prior to commencement of the test to ensure that all personnel understand their respective duties.

2.3. Surerus will install warning signs and barricades to prevent access to the vicinity of the test area. Warning signs shall indicate "DANGER - High Pressure Pipeline Test" and "Restricted Access".

2.4. All Surerus personnel not involved in the testing shall be removed from the area wh ile the pipeline section is under a pressure equal to or greater than 2,760kPa (-400psi) .

2.5. Test heads and pressurizing pipe shall be secured to limit movement. 2 .6. All testing equipment including compressors, recorders, deadweights, etc. shall be set

up a safe distance from the test section and/or test heads. 2.7. Surerus employees shall inspect all hoses, lines, and connections for faults prior to

pressurizing the lines. The Surerus Hydrotest Pre-test Checklist will be completed to ensure that all components meet the required ratings.

2.8. Surerus personnel shall ensure pressure hoses/unions are rated to twice the maximum expected hydrotest pressures, and all safety lines are firmly attached and secured with whip checks.

2.9. Test crews shall review the requirements for working with methanol and wear appropriate PPE at all times where the risk of exposure to the test fluid exists.

2.1 0. An En bridge representative will be on site for the duration of test activities.

3. Equipment Surerus shall supply the following equipment for completion of the hydrostatic test:

Tanker trucks to transfer test fluid. Truck-mounted squeeze pump to complete pressure testing. Air compressor required for pipeline cleaning and dewatering. All pipeline pigs required for line fill and dewatering. All necessary valves, hoses, and fittings required to successfully complete the test. Calibrated temperature recorders, pressure recorders, and deadweights. Calibrated f low meter for preparation of the yield plot wl1ere applicable. Adequate lighting and light towers at all work areas.

DATE 2012-1·1-"16 REVISION 0 PAGE 2 of6

Page 46: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 46 of 49

Bakken Mainline NPS 1 6 HYDROSTATIC TEST PLAN

Steelman Section

3.1 Test Heads 3.1 .1 Surerus shall supply Enbridge approved test heads which comply with all

requirements of re levant specifications including section 6.2 of CPSC-SPEC­HYDR0-005.

3.1 .2 Test l1ead assemblies shall comply with all requirements of CSA-Z662 (latest edition). All documentation certifying test head compliance shall be available for review prior to commencement of testing.

3.1. 3 Test heads will be welded to the section and the welds will be inspected by N DE prior to filling the section.

3.2 Pumps 3.2.1 Test fluid shall be transferred to the pipeline segment via tanker truck. A truck

mounted squeeze pump shall be utilized to increase pressure up to the required test pressure.

3.3 Instrumentation: 3.3.1 Surerus shall supply pressure and temperature recorders and dead weights to

provide readings for the test data. The pressure shall be measured in kPa, and the temperature measured in degrees Celsius.

3.3.2 All test charts and reports, including the depressurizing of tested lines, will be included in the document turnover package.

3.3.3 Instrumentation for the test shall be as follows: e A dual pen temperature/pressure recorder and a digital deadweight will be

located at the fill point. e An additional dual pen temperature/pressure recorder shall be located at the

section end point. 3.3.4 All measurement equipment shall be certified for accuracy not more than 30 days

prior to commencement of the pressure test. The calibration certificates and current calibration reports shall be maintained on site and included in the turnover package following completion of the test.

4. Line Fill

4.1 Test Sections

Section Start End Length Volume De water location

Steelman Tanker Truck 1 ,, Terminal 0+094 94m 11m3

(KPO+OOO) at Section End

... ·· Note that hycl rotest flu1d for section 1 w 111 be provaded by tanker trucks .

4.2 Fill section

Test heads will be welded onto the ends o-r each test section and will be inspected by NDE. NDE documentation shall be retained to support acceptability of the welds. The foreman shall inspect all connections and hoses prior to filling the section.

DATE 2012-11-·16 REVISION 0 PAGE 3 of 6

Page 47: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 47 of 49

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

Steelman Section

The filling operation shall be continuous to prevent air ingress.

4.3 Pressurize and test the section.

Before pressurizing the section beyond a pressure of 2,760kPa, all work crews will be notified and removed from the vicinity of the test section. All pipe and fill connections shall be checked for leal<s and these test areas shall be maintained as "off-limits" to non-essential personnel. Pressure will be increased to 2,760kPa and all visible piping inspected for leaks. Upon completion of the leak check, the line and manifold will be bled off, an in line check valve installed on the squeeze line and the squeeze pump connected to the line. Squeeze pressure will be initiated through a 1" or 2" line rated to 38,000kPa (- 5,500psi); pressure shall be increased in stages as indicated in the Hydrostatic Test Record Worksheets.

5. Test Stages

The pipeline shall be tested in the following stages: • Leak check • Combined Strength and Leak test (including yield plot where required.

5.1. Leak Check The first stage involves a leak checl< at approximately 2,760kPa to allow visual inspection of exposed piping and fittings included in the test section. Any pressure lost during this period must be explained to the satisfaction of the Company's testing supervisor prior to pressurizing to the target strength test pressure

5.2. Combined Strength and Leak Test The minimum duration for the combined strength and leak test is one (1) hour. Following satisfactory completion of the leak checl<s, testing will continue by slowly raising the pressure to the test pressure.

5.2.1 Yield plotting, if required , shall be undertaken as the section is pressurized during the strength test. Yield plotting shall commence at a pressure equivalent to 60% of the maximum anticipated test pressure. Yield plotting shall only be required where the expected maximum hoop stress in the test section during the strength test is greater than 100% SMYS of the pipe. En bridge shall be responsible for completing all yield plots and associated documents.

5.2.2 Pumping shall continue until the selected strength test pressure is achieved or, where a yield plot is required, the point where the yield plot deviates beyond the 0.2% offset line.

5.2.3 The strength test will be held at a pressure greater than the minimum test pressure. 5.2.4 After pumping has ceased, and the selected strength test pressure has been

reached, the strength test will commence. The pressure at the highpoint shall match or e}cceed this minimum at both the start and the end of the test, and at no time

DATE 2012-'1'1- '16 REVISION 0 PAGE 4 of6

Page 48: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 48 of 49

Bakken Mainline NPS 1 6 HYDROSTATIC TEST PLAN

Steelman Section

during the test period shall the pressure at the high point drop below the required minimum.

5.2.5 The minimum duration for the hold period on the strength test is one (1) hour.

6. Test Documentation

Surerus will submit all required test documentation within the turnover package. Temperature and pressure readings shall be recorded as follows:

• Every 5 minutes between 0-30 minutes • Every 15 minutes for the remainder of the test

Records shall include the start and stop times for any pumping, pressunzmg, or de­pressurizing of the test section. A copy of the test worksheet shall be made available for review prior to commencement of the test. All documentation will be turned over to Enbridge upon completion of testing to facilitate completion of required Leave To Open applications.

7. Leak Detection

During the leal< test, any drop in pressure which cannot be correlated to a change in temperature shall be considered a leak. If a leak is suspected Surerus shall notify the Enbridge Representative and further pressurizing of the pipeline shall be halted until the source of the leal< can be determined. Should any failure require repair, the line pressure shall be reduced to static pressure, the section dewatered, and the repair completed.

8. Depressurizing

The line will be depressurized into a pressure truck rated in excess of the maximum test pressure. Under no circumstances will valves be moved to the full open position to initiate depressurizing.

9. Dewatering 9.1 Upon completion of the test, the test fluid will be transferred into tanker trucl<s for

disposal. 9.2 All transfer lines will be securely fastened and supported to prevent "whipping" or

sudden releases of energy during the dewater process. 9.3 The pipeline will be dewatered with a high density coated poly pig or bi-directional

multi-disc pig propelled by compressed air.

12, Test Personnel Surerus will utilize the following l<ey personnel to complete pressure testing activities:

Telford Advent Superintendent Surerus Pipeline Inc.

Julio Zavaleta Project Engineer Surerus Pipeline Inc.

Ken Hawtl1orne Test Foreman Surerus Pipeline Inc.

DATE 2012-1'1- '16 REVISION 0 PAGE 5 of6

Page 49: A3E4U9 - Appendix a - A3 Surerus Hydrostatic Test Plan

Enbridge Bakken Pipeline Project - Certificate OC-058 Leave to Open Bakken Pump Station to EPI Cromer Terminal

Appendix A - A3 Sureus Hydrostatic Test Plan Page 49 of 49

Bakken Mainline NPS 16 HYDROSTATIC TEST PLAN

Steelman Section

13. Reference Documents 1. CPCS-SPEC-HYDR0-005 Rev. 1 Pipeline Hydrostatic Testing 2. CPCS-SPEC-PIPELINE-001 Rev. 1 - Pipeline Construction 3. CPCS-SPEC-PCCT-007 Rev. 1 - Post Construction Caliper Tool. 4. Bakken Pipeline Project Canada Alignment Sheets - D-WM057-05-500-001-A 5. CSA Z662-(Latest Ed ition) - Oil and Gas Pipeline Systems; Canadian Standards

Association 6. Pipeline Act and Regulation - Government of Saskatchewan (Latest Edition)

DATE 2012-1'1-16 REVISION 0 PAGE 6 o·r-6