    10. Which organizational structure gives a project manager the most control over major project activities?

    Projectized.A projectized organizational structure gives a project manager a high degree of power due to reportingto the CEO.

    11. Which of the following best describe a project deliverable?

    Any output of a project.This is the most universal definition of a deliverable.

    12. Which statement describes the relationship between the PMBOK Guideand the Project ManagementBody of Knowledge?

    The former is a subset of the latter.See page 4 in the PMBOK Guide.

    13. How do projects and ongoing operations relate to an organization's strategic plan?

    Both support a strategic plan.A strategic plan cannot be eliminated without the support of both projects and ongoing operations.

    14. Which of the following examples best highlight the unique nature of a project?

    A new product that enables a remote controlled vehicle that motorists can ride in while they sleep.This would definitely be a unique project.

    15. What terms describes an organizational unit to centralize and coordinate projects?

    Project Management Office.A Project Management Office (PMO) oversees the management of projects, programs, or both.

    16. How are projects iterative?

    They include activities that you may do more than once.The iterative nature of a project relates to its progressive elaboration nature. See section 1.3 in thePMBOK Guide.

    17. How do standards and regulations relate to each other?

    Standards are advanced by private organizations and regulations set by the government.For example, ISO publishes standards and the U.S. Food and Drug Administration createsregulations.

    18. Which activities form the Project Integration Management section of the Project Management Knowledge

    Area?

    Develop project management plan and perform integrated change control.The other pieces of Project Integration Management are develop project charter, direct and manageproject scope execution, monitor and control project work, and close project or phase.

    19. Which of the following choices IS NOT part of Project Time Management?

    Close procurements.Close procurements are part of Project Procurement Management.

  • 7/31/2019 A03 Quiz Answers

    3/3

    20. As manager for a project concerning employee recognition in your organization, you form a team tocreate a special plaque during the next few weeks to be given out quarterly. How does the term Temporaryrelate to your project?

    It relates to your project but not your product.All projects are temporary. See page 5 of the PMBOK Guide.