Upload
praveen-maheshwari
View
40
Download
0
Tags:
Embed Size (px)
Citation preview
Background component securities.
Banks and financial institutions experience Banks and financial institutions in
different types of risk, such as, business risk, developed as well as in underdeveloped
strategic risk, and financial risk. Financial countries are generally required by their
risk has been given more importance as it respective regulators to pass through
can be quantifiable while other risks have minimum Capital Adequacy. The 1988 Basel
some amount of subjectivity. It is caused by Capital Accord set capital requirements on
movements in financial markets. The the basis of risk adjusted assets, defined as
literature distinguishes four major the sum of asset positions multiplied by
categories of financial risk, viz., credit risk, asset-specific risk weights. These risk weights
operational risk, liquidity risk and market were intended to reflect primarily the credit
risk. Credit risk generally relates to the risk associated with a given asset. In 1996 the
potential loss due to the default on the part Accord was amended to include r market
of the counterparty to meet its obligations at risk, defined as the risk arising from
designated time. It has three basic movements in the market prices of trading
components: credit exposure, probability of positions (Basel Committee on Banking
default and loss in the event of default. S u p e r v i s i o n , 1 9 9 6 a ) . T h e 1 9 9 6
Operational risk takes into account the Amendment’s Internal Models Approach
errors that can be made in instructing (IMA) determines capital requirements on
payments or settling transactions, and the basis of the output of the financial
includes the risk of fraud and regulatory institutions’ internal risk measurement
risks. Liquidity risk is caused by an systems. Financial institutions are required
unexpected large and stressful negative cash to report daily their VaR’s at the 99%
flow over a short period. If a firm has highly confidence level over a one-day horizon and
illiquid assets and suddenly needs some over a two-week horizon (ten trading days).
liquidity, it may be compelled to sell some of Simply stated, VaR is the maximum loss
its assets at a discount. Finally, market risk of a trading portfolio over a given
estimates the loss of an investment portfolio horizon, at a given confidence level.
due to the changes in market price of Financial institutions are allowed to derive
A STEP BY STEP APPROACH TO VALUE AT RISK – RELEVANCE FOR INDIAN MARKET
Golaka.C.Nath*
*Shri Golaka C Nath is the Advisor, Economic Research & Surveillance
Department, The Clearing Corporation of India Limited.
their two-week VaR measure by scaling up suggested by the Basel Committee to address
the daily VaR by the square root of ten (see: this problem relies on “backtesting” (Basel
Basel Committee on Banking Supervision, Committee on Banking Supervision, 1996c):
1996b, p. 4). The new Capital Accord regulators should evaluate on a quarterly
(commonly known as BASEL II) likely to be basis the frequency of “exceptions” (that is,
implemented in 2006 would require the frequency of daily losses exceeding the
international banks to provide for reported VaR) for every financial institution
operations risk. in the most recent twelve-month period and
the multiplier used to determine the market The minimum capital requirement on a
risk charge should be increased (according to given day is then equal to the sum of a charge
a given scale varying between 3 and 4) if the to cover “general market risk” and a charge
frequency of exceptions is high. The reason to cover “credit risk” (or idiosyncratic risk),
to base backtesting on a daily VaR measure in where the market-risk charge is equal to a
spite of the fact that the market risk charge is multiple of the average reported two-week
based on a two-week VaR measure is due to VaR’s in the last 60 trading days and the
the fact that VaR measures are typically credit-risk charge is equal to 8% of risk-
computed ignoring portfolio revisions over adjusted assets. The US regulated banks and
the VaR horizon. The basic point to OTC derivatives dealers are subject to capital
remember here is that the bank is assumed to requirements determined on the basis of the
hold the same portfolio over a historical IMA. More precisely, the market-risk charge
time horizon from the date of VaR is equal to the larger of: (i) the average
estimation. According to the Basel reported two-week VaR’s in the last 60
Committee, “it is often argued that revalue-trading days times a multiplier and (ii) the
at-risk measures cannot be compared against last-reported two-week VaR. However, since
actual trading outcomes, since the actual the multiplier is not less than 3 (see below),
outcomes will inevitably be ‘contaminated’ the average of the reported VaR’s in the last
by changes in portfolio composition during 60 trading days times a multiplier typically
the holding period. This argument is exceeds the last-reported VaR.
persuasive with regard to the use of Value-at-
Of course, the reliance on the financial Risk measures based on price shocks
institution’s self-reported VaR to determine calibrated to longer holding periods. That is,
capital requirements creates an adverse comparing the ten-day, 99th percentile risk
selection and moral hazard problem, since measures from the internal models capital
the institution has an incentive to under- requirement with actual ten-day trading
report its true VaR in order to minimize outcomes would probably not be a
capital requirements The procedure meaningful exercise. In particular, in any
given ten day period, significant changes in through Internal Model Approach. Under
portfolio composition relative to the initial this approach, regulators do not provide any
positions are common at major trading specific VaR measurement technique to their
institutions. For this reason, the backtesting supervised banks – the banks are free to use
framework described here involves the use of their own model. But to eliminate the
risk measures calibrated to a one-day holding possible inertia of supervised banks to
period.” (Basel Committee on Banking underestimate VaR so as to reduce the capital
Supervision (1996c, p. 3). Additional requirements, BIS has prescribed minimum
corrective actions in response to a high standard of VaR estimates and also certain
number of exceptions are left to the tests, such as backtesting, of VaR models. If
discretion of regulators. VaR model of a bank fails in backtesting, a
penalty is imposed resulting to higher In recent years, VaR has become the standard
capital charge. measure that financial analysts use to
quantify the market risk. The great Thus, providing accurate estimates of VaR is
popularity that this instrument has achieved of crucial importance for all stakeholders. If
among financial practitioners is essentially the underlying risk is not properly
due to its conceptual simplicity: VaR reduces estimated, this may lead to a sub-optimal
the (market) risk associated with any capital allocation with consequences on the
portfolio to just one number that is the loss profitability or the financial stability of the
associated with a given probability and institutions. A bank would like to pick up a
horizon. model that would generate as low VaR as
possible but pass through the backtesting.VaR measures can have many applications. It
evaluates the performance of risk takers and There has been voluminous work done on
satisfies the regulatory requirements. VaR VaR in financial market all over the world,
has become an indispensable tool for the task of estimating/forecasting VaR still
monitoring risk and an integral part of remains challenging. The major difficulty
methodologies that allocate capital to lies in modeling the return series which has
various lines of business. Today regulators all normally heteroskedistic properties (being
over the globe have been forcing institutions skewed and/or having fatter tails than
to adopt internal models and calculate the normal distribution). Available VaR models
required capital charge based on VaR can be classified into four broad categories:
methodologies. The Basel Committee on the historical simulation method, the Monte
Banking Supervision of the BIS imposes Carlo simulation method, modelling return
requirements on banks to meet capital d i s t r i b u t i o n ( i n c l u d i n g t h e
requirements based on the VaR estimated variance/covariance method, which assumes
normality of the return distribution, and total exclusion of bank’s internal rating
methods under Extreme Value Theory system. However, RBI has issued detailed
(EVT). All these VaR estimation methods guidelines to Primary Dealers (PDs) for
adopt the classical approach: they deal with mandatory implementation of VaR methods
the statistical distribution of time series of while calculating the capital charge 2returns. required . The recent guidelines of RBI for
PDs states that the capital requirement will The main objective of this paper is to give a
be the higher of (i) the previous day’s value-theoretical orientation of the subject and to
at-risk number measured according to the d i s c u s s t h e s t e p s i n v o l v e d i n
above parameters specified in this section implementation of VaR models with
and (ii) the average of the daily value-at-risk backtesting as per BIS/RBI norms. Reserve
measures on each of the preceding sixty Bank of India (RBI) has issued detailed
b u s i n e s s d a y s , m u l t i p l i e d b y a guidelines on market risk for banks on the
multiplication factor prescribed by Reserve basis of the BIS framework though it has not
Bank of India (3.30 presently).become mandatory for banks to use VaR
1models . It is interesting to note that a We have restricted our analysis to only
significant number of banks in developed application of VaR methodologies using a
countries are opting for the Internal Ratings popular GOI bond index (IBEX – Principal
Based methods, while their counterparts in Return Index). The data period is from
developing countries (including India) August 1994 to June 2004, about 11 years of
follow the Standardized Approach. The data with 3622 data point. The data period is
main issue for moving towards the sufficiently large to cover various cyclical
Standardized Approach is the absence of and seasonal factors in the economy. For
rating culture in emerging markets like India the limited purpose of the study, we have
for which the unrated claims on Sovereigns, used Normal (Variance Covariance),
PSEs, banks, Security Firms and Corporates Historical Simulation and a weighted
would attract 100% risk weighting and hence Historical Simulation method for simplicity
higher capital charge requirement. The BIS and parsimony, though it is not difficult to
capital accord, for capital purposes, estimate VaR using EVT and Weighted
recognizes only external credit ratings, to the Normal.
1RBI circular BP./21.04.103/2001 dated March 26, 2002 and RBI/2004/263/DBDO.No.BP.BC.103/21.04.151/2003-04
dated June 24, 2004.
2 RBI circular IDMC.PDRS.PDC.3/03.64.00/2000-01 dated December 11, 2000 and RBI / 2004/7/IDMD 1/(PDRS)
03.64.00 /2003-04 dated January 7, 2004.
Literature Review Andersen and Bollerslev (1998) and
Andersen, et al. (1999), who use average There has been large volume of literature on
intraday squared returns to estimate daily VaR methodologies as well as on its
volatility.implementation. The concept received
tremendous response from banks all over the Several studies such as Danielsson and de
world. Banks management can apply the Vries (1997), Christoffersen (1998), and
VaR concept to set capital requirements Engle and Manganelli (1999) have found
because VaR models allow for an estimate of significant improvements possible when
capital loss due to market risk (see Duffie deviations from the relatively rigid
and Pan, 1997; Jackson, Maude and RiskMetrics framework are explored.
Perraudin, 1997; Jorion, 1997; Saunders, Choosing an appropriate VaR measure is an
1999; Friedmann and Sanddrof-Kohle, 2000; important and difficult task, and risk
Hartmann-Wendels, et al., 2000; Simons, managers have coined the term Model Risk
2000, among others). to cover the hazards from working with
potentially mis-specified models. Beder The computation of volatility is the most
(1995), for example, compares simulation-important aspect of any VaR estimation. The
based and parametric models on fixed volatility estimation should take care of the
income and stock option portfolios and most stylized facts of any financial asset class
finds apparently economically large – the important ones being fat tailed
differences in the VaRs from different property, volati l i ty clustering and
models applied to the same portfolio. asymmetry of return distribution. Once
Hendricks (1996) finds similar results these issues are identified in the distribution,
analyzing foreign exchange portfolios. In then calculating volatility is easy. Today
Indian context, Darbha (2001) made a GARCH family models have been
comparative study of three models – increasingly used by researchers to model
Normal, HS and Extreme Value Theory volatility. An important documentation in
while studying the portfolio of Gilts held by this regard has been the J P Morgan’s
PDs. Nath and Samanta (2003a and b) RiskMetrics that applied declining weights
looked at the issues in implemention as well to past returns to compute volatility with a
as selection of VaR methodologies for the decay factor 0.94 which is a variant of
portfolio of Government of India securities.IGARCH. Other measures of volatility,
which differs from the estimation of return Theoretical Issues
variance, include Garman and Klass (1980), As stated earlier, VaR is the maximum
and Gallant and Tauchen (1998), who amount of money that may be lost on a
incorporate daily high and low quotes, and portfolio over a given period of time, with a
given level of confidence and typically The PDs should calculate the capital
calculated for a one-day time horizon with requirement based on their internal Value at
95% or 99% confidence level. The capital Risk (VaR) model for market risk, as per the
charge would be different for different following minimum parameters:
holding period. (a) “Value-at-risk” must be computed on a
BIS requires that VaR be computed daily by daily basis.
Banks, using a 99th percentile, one-tailed (b) In calculating the value-at-risk, a 99th
confidence interval with a minimum price percentile, one-tailed confidence
shock equivalent to ten trading days interval is to be used.
(holding period) and the model incorporate
(c) An ins tantaneous pr ice shock a historical observation period of at least one
equivalent to a 15-day movement in year. The capital charge for a bank that uses a
prices is to be used, i.e. The minimum proprietary model will be higher of (i) The
“holding period” will be fifteen trading previous day’s VaR and (ii) an average of the
days. daily VaR of the preceding sixty business
days, multiplied by a multiplication factor. (d) Interest rate sensitivity of the entire
The multiplication factor may be 3 and this portfolio should be captured on an
may go up if the regulators feel that 3 is not integrated basis by including all f i x e d
sufficient to account for potential income securities like G o v e r n m e n t
weaknesses in the modeling process.securities, Corporate/PSU bonds, CPs
In the case of PDs, RBI prescribes all these and derivatives like IRS, FRAs,
above criteria except that (i) minimum Interest rate futures etc., based on the
holding period would be 15 trading days; (ii) mapping of the cash flows to work o u t the minimum length of the historical the portfolio VaR. Wherever da ta for observation period used for calculating VaR calculating volatilities is not available, should be one year or 250 trading days. For PDs may calculate the volatilities of PDs who use a weighting scheme or other such instruments using the G-Securities methods for the historical observation curve with appropriate spread. period, the “effective” observation period
However, the de ta i l s of such must be at least one year (that is, the
instruments and the spreads applied weighted average time lag of the individual
have to be reported and consistency of observations cannot be less than 6 months);
methodology should be ensured . and (iii) the multiplication factor is
Instruments which are part of trading presently fixed at 3.3. The RBI guidelines of
book, but found d i ff i cu l t to be January 2004 read as:
subjected to measurement of market
risk may be applied a flat market risk (h) The capital requirement will be the
measure of 15%. The instruments likely higher of (i) the previous day’s value-at-
to be applied the flat market risk risk number measured according to the
measure are units of MF, Unquoted above parameters specified in this
Equity, etc., and added arithmetically section and (ii) the average of the daily
to the measure obtained under VaR in value-at-risk measures on each of the
respect of other instruments. preceding s i x t y b u s i n e s s d a y s ,
multiplied by a multiplication factor (e) Underwr i t ing commitments a s
prescribed by Reserve Bank of India explained at the beginning of the
(3.30 presently). Appendix should also be mapped into
t h e VaR f r amewo rk f o r r i s k (i) No particular type of model is
measurement purposes. prescribed. So long as the model
used captures all the material risks(f) The unhedged foreign exchange
run by the PDs, they will be free to use position arising out of the foreign
models, based for example, on variance-c u r r e n c y b o r r o w i n g s u n d e r
covar iance matr ices , his tor ica l FCNR(B) loans scheme would
s imula t ions , o r Monte Car lo carry a market risk of 15% as
simulations or EVT etc.hitherto and the measure obtained will
be added0 arithmetically to the VaR The RBI has not restricted PDs for any
m e a s u r e o b t a i n e d f o r o t h e r particular model but the intention is that
instruments. PDs should use the model which gives them
the best comfort level with regard to capital (g) The choice of historical observation
requirement while not violating the period (sample period) for calculating
regulatory norms on backtesting. The value-at-risk will be constrained to a
weaknesses of the VaR models may be due to minimum length of one year and not
(a) market prices often display patterns less than 250 trading days. For PDs
(heteroskedastic) that differs from the who use a weighting scheme or other
statistical simplifications used in modeling, methods for the historical observation
(b) past not being always a good period, the “effective” observation
approximation of the future (October 1987 period must be at least one year (that is,
crash happened that did not have parallel in the weighted average time lag of the
historical data), (c) most of the models take individual observations cannot be less
ex-post volatility and not ex-ante, (d) VaR than 6 months).
estimations normally is based on end-of-day
positions and not take into account intra-
day risk, (e) models can not adequately
capture event risk arising from exceptional (3)
market circumstances. Since VaR heavily Where s is the covariance and r is the ij,t+1 ij,t+1relies on the availability of historical market
correlation between security i and j on day price data on the portfolio to understand its 2t+1 and for r = 1 and we write s = seffectiveness, it would be appropriate to use ij,t+1 i,t+1 ij,t+1
for all i.the long historical data to see if the stress
conditions can be replicated. The VaR of the portfolio is simply
The logic behind VaR is to consider today’s (4)
portfolio and find out what would have been
where Fp-1 is the p’th quantile of the rescaled its historical values (time series) and then
portfolio returns.construct the return series and then calculate
the VaR numbers. We have used a bond index When we use HS method, we write the VaR
that represents the most liquid basket of equation as
underlying Government securities and has a
long historical price sereis.
Select VaR MethodologiesBasic Statistics Related to VaR
There are few VaR methodologies that are The portfolio consists of many securities very simple and easy to implement, to name and in our case we are concerned with only a few are (a) Normal (parametric using Gilts. The basic price equation of the variance and covariance approach) and (b) portfolio can be written as follows:Historical simulation. Cleverly these simple
(1) methods have been extended with
application of weights – recent events are and the return on the portfolio is at time
given more weight and past is given less. defined as
However, different people have used (2)
different weighting methodologies .
Riskmetrics has used ‘exponentially moving Where the sum is taken over n securities in
average’ where the decay factor (l) has been the portfolio, wi denotes the proportionate
considered as 0.94 while Boudoukh, et al. value of the holding of security i at the end of
(1997) fixed it at 0.98. day t.
Variance-Covariance (Normal) MethodAnd the variance of the portfolio should
be written as The Variance-Covariance (Normal) method
}100,}{{ 11,pR m
rtFP =+1, percentileVaR tPFp
+ -=
1,1
1, * +=
+ å= ti
n
iitpf RwR
1p1tF,P1tPF,
p F*óVaR -
++ =
is the easiest of the VaR methodologies. Since and then revalues the same using the
we are considering a sovereign bond index historical price series. Once we calculate the
for our analysis, it is known that interest rate daily returns of the price series, then sorting
movement in sovereign bond market is the same in an ascending order and find out
unidirectional at any point of time. For our the required data point at desired percentiles.
purpose, the plain standard deviation would Linear interpolation can be used if the
be useful to calculate the require VaR. But required percentile falls in between 2 data
whether to take static variance of the entire points. The moot question is what length of
time series or conditional variance is a point price series should be used to compute VaR
for debate. It is argued that variance changes using HS method and what we should do if
over time horizons and hence we should not the price history is not available. It has to be
rely on unconditional variance for kept in mind that HS method does not allow
measuring VaR. for time-varying volatility.
Historical Simulation Method Another variant of HS method is a hybrid
approach put forward by Boudhoukh, et al. Historical simulation approach provides
(1997), that takes into account the some advantages over the normal method, as
exponential declining weights as well as HS it is not model based, although it is a
by extimating the percentiles of the return statistical measure of potential loss. The
directly, using declining weights on past main benefit is that it can cope with all
data. As described by Boudhoukh et al. portfolios that are either linear or non-
(1997, pp. 3), “the approach starts with linear. The method does not assume any
ordering the returns over the observation specific form of the distribution of price
period just like the HS approach. While the change/return. The method captures the
HS approach attributes equal weights to each characteristics of the price change
observation in building the conditional distribution of the portfolio, as VaR is
empirical distribution, the hybrid approach estimated on the basis of actual distribution.
attributes exponentially declining weights to This is very important, as the HS method
historical returns”. The process is simplified would be on the basis of available past data.
as follows:•Calculate the return series of If the past data does not contain highly
past price data of the security or the volatile periods, then HS method would not
portfolio from t-1 to t. be able to capture the same. Hence, HS
should be applied when we have very large • To each most recent K returns: R(t), R(t-
data points that are sufficiently large to take 1), ……R(t-K+1) assign a weight
into account all possible cyclical events. HS
method takes a portfolio at a point of time 1kk l)]l(1--k /l)[(1)],l/(1l)[(1 k /l)l,.....[(1)]l(1 -----
r e s p e c t i v e l y . T h e c o n s t a n t the risk of low-probability events that could
simply ensures that the lead to catastrophic losses. Yet traditional
weights sum to 1. VaR methods tend to ignore extreme events
and focus on risk measures that • Sor t the re turns in a scending
accommodate the whole empirical order.
distribution of returns. For example, it is
• In order to obtain p% VaR of the often assumed that returns are normally or
portfolio, start from the lowest lognormally distributed, and little attention
return and keep accumulating the is paid to the distribution of the extreme
we i gh t s un t i l p% i s re a ch ed . returns we are most concerned about. The
Linear interpolation may be used danger is then that our models are prone to
to achieve exac t ly p% of the fail just when they are needed most – in large
distribution. market moves, when we can suffer very large
losses. • In many studies lambda (l) has
been used as 0.98. One response to this problem is to use stress
tests and scenario analyses. These can Another Hybrid method is a weighting
simulate the changes in the value of our scheme suggested by Hull and White that
portfolio under hypothesized extreme allows us to transform the returns by
market conditions. These are certainly very multiplying the return series with a vector of
useful. However, they are inevitably limited – ratios of last day’s (the day for which VaR is
we cannot explore all possible scenarios – estimated) VaR and conditional volatilities
and by definition give us no indication of (using the Riskmetrics method with a decay
the likelihoods of the scenarios considered. factor) calculated for previous ‘n’ days.
Then take the appropriate percentile values This type of problem is not unique to risk
to represent the VaR numbers. The weighting management, but also occurs in other
scheme is justified on the ground that if the disciplines as well, particularly in hydrology
volatility on a previous day in the sample is and structural engineering, where the failure
lower than the current period volatility, VaR to take proper account of extreme values can
would be underestimated. The weighting have devastating consequences. Researchers
scheme makes them comparable during the and practitioners in these areas handle this
entire period. This is a method of problem by using Extreme Value Theory
normalizing the return series. (EVT) – a specialist branch of statistics that
attempts to make the best possible use of Extreme Value Theory (EVT)
what little information we have about the
Risk managers are primarily concerned with extremes of the distributions in which we are
)]l/(1l)[(1 k--
interested. To put it in simple, suppose we have 1000
data points of historical prices and we have The key to EVT is the extreme value theorem
some idea how to divide the period into – a cousin of the better-known central limit
smaller time buckets of, say,10-15 days. Once theorem – which tells us what the
we have a rationality of diving the entire distribution of extreme values should look
period into optimal time buckets (we may like in the limit, as our sample size increases.
use some statistical tests to identify the Suppose we have some return observations
optimal number), we take the extreme high but do not know the density function from
and low values and combine all these which they are drawn. Subject to certain
extreme high values – one from each time relatively innocuous conditions, this
bucket, to estimate the distribution theorem tell us that the distribution of
properties of the extreme series and estimate extreme returns converges asymptotically to:
the VaR using this extreme series as these are
If the tails in which we are interested rather
than taking the entire sample of 1000 data The parameters µ and s correspond to the points to estimate the tail.mean and standard deviation, and the third
EVT provides a natural approach to VaR parameter, x gives an indication of the
estimation, given that VaR is primarily heaviness of the tails: the bigger, x the
concerned with the tails of our return heavier the tail. This parameter is known as
distributions. To apply to VaR, we first the tail index, and the case of most interest in
estimate the parameters of the distribution, finance is where , x>0 which corresponds to and there are a number of standard the fat tails commonly founded in financial estimators available (in one of the earlier return data. In this case, our asymptotic work, the author has used Gauss codes to distribution takes the form of a Fréchet estimate EVT VaR). Once we have these, we distribution. can plug them into a number of alternative
formulas to obtain VaR estimates. To give a This theorem tells us that the limiting simple example, if we want to estimate a VaR distribution of extreme returns always has that is out of (i.e., more extreme than) our the same form – whatever the distribution of sample range, we can project the tail out the parent returns from which our extreme from an existing in-sample quantile Xk+1 – returns are drawn. It is important because it
where Xk+1 is the k+1-th most extreme allows us to estimate extreme probabilities
observation in our sample – and infer the and extreme quantiles, including VaRs,
(asymptotic) VaR from the projected tail without having to make strong assumptions
using the formula: about an unknown parent distribution.
H xx
e xxms
x
m s
x m s, ,
/
( )/( )exp( [ ( ) / ]
exp( )=
- + -
-
-
- -
1 1x
x
¹
=
0
0
ˆ-Xk+1[CL/k] x
VaR = Robust VaR Models - Backtesting
Where CL is the confidence level on which Any method used for VaR estimation need to
the VaR is predicated. EVT also gives us satisfy the criteria of back testing using the
expressions for the confidence intervals current data set. Suppose we calculate the
associated with our VaR estimates. VaR numbers with probability level 0.01. We
can check the accuracy of a VaR model by The EV approach to VaR has certain
counting the number of times VaR estimate advantages over traditional parametric and
fails (i.e. actual loss exceeds estimated VaR), non-parametric approaches to VaR.
say in 100 days. If we want to calculate VaR Parametric approaches estimate VaR by
of a one-day holding period with 99% fitting some distribution to a set of observed
confidence level, logically, we are allowing 1 returns. However, since most observations lie
failure in 100 days. But if the number is more close to the centre of any empirical
than 1, then the model is under predicting distribution, traditional parametric
VaR numbers and if we find less number of approaches tend to fit curves that
failures the model is over predicting. The accommodate the mass of central
Basle Committee provides guidelines for observations, rather than accommodate the
imposing penalty leading to higher tail observations that are more important for
multiplication factor, when the number of VaR purposes. Traditional parametric
failure is too high. However, no penalty is approaches also suffer from the drawback
imposed when the failure occurs with less that they impose distributions that make no
frequency than the expected number. Thus, sense for tail estimation and fly in the face of
selection of VaR model is a very difficult task. EV theory. By comparison, the EV approach
A model, which overestimates VaR, may is free of these problems and specifically
result in reduced number of failure but designed for tail estimation.
increase the required capital charge directly.
On the other hand if a model underestimates Non-parametric or historical simulation
VaR numbers, the number failures may be approaches estimate VaR by reading off the
too large which ultimately increases the VaR from an appropriate histogram of
multiplying factor and hence the required returns. However, they lead to less efficient
capital charge. Thus an ideal VaR model VaR estimates than EV approaches, because
would be the one, which produces VaR they make no use of the EV theory that gives
estimates, as minimum as possible and also us some indication of what the tails should
pass through the backtesting. Samanta and look like. More importantly, these
Nath (2003) have discussed the issue of approaches also have the very serious
selecting models on the basis of robust loss limitation that they can tell us nothing
functions.whatever about VaRs beyond our sample
range.
The BIS requires that models must For carrying out the Backtesting of a VaR
incorporate past 250 days data points (one model, realized day-to-day returns of the
year assuming Saturday/Sundays being non- portfolio are compared to the VaR of the
trading days). In Indian market, RBI has portfolio. The number of days when actual
issued guidelines for PDs to use one year and portfolio loss was higher that VaR provides
not less than 250 trading days for VaR an idea about the accuracy of the VaR model.
estimation. Since Saturday is a trading day in For a good VaR model, this number would
bond market in India, we have taken 290 approximately be equal to the 1 per cent (i.e.
days (a period of about one year) for our 100 times of VaR probability) of back-test
analysis. Accordingly the capital charge is trading days. If the number of violation (i.e.
the higher of (i) the previous day’s value-at- number of days when loss exceeds VaR) is too
risk number measured according to the high, a penalty is imposed by raising the
above parameters specified in this section multiplying factor (which is at least 3),
and (ii) the average of the daily value-at-risk resulting in an extra capital charge. The
measures on each of the preceding sixty penalty directives provided by the Basle
b u s i n e s s d a y s , m u l t i p l i e d b y a Committee for 250 back-testing trading days
multiplication factor prescribed by RBI is as follows; multiplying factor remains at
(3.30 presently for Pds). minimum (i.e. 3) for number of violation
upto 4, increases to 3.4 for 5 violations, 3.5 Basle Committee (1996b) provides following
for 6 violations, 3.65 for violations 8, 3.75 backtesting criteria for an internal VaR
for violations 8, 3.85 for violation 9, and model (see van den Goorbergh and Vlaar,
reaches at 4.00 for violations above 9 in 1999; Wong et al., 2003, among others)
which case the bank is likely to be obliged to
(1) One-day VaRs are compared with actual revise its internal model for risk
one-day trading outcomes. management (van den Goorbergh and Vlaar,
1999). (2) One-day VaRs are required to be correct
on 99% of backtesting days. There For the limited purpose of this paper, to do
should be at least 250 days (around one the back testing, we can think of an indicator
year) for backtesting.variable I(t) which is one if return of the day
(3) A VaR model fails in Backtesting when it is more than the VaR for the previous day provides 5% or more incorrect VaRs. and zero otherwise. Average of the indicator
(4) If a bank provides a VaR model that fails variable should be our VaR percent. in backtesting, it will have its capital
Datamultiplier adjusted upward, thus
increasing the amount of capital We have estimated VaRs as on June 30, 2004
charges. for two important asset classes relevant for
banks and institutions. We have used GOI the backtesting, we have used the full period
bond index (IBEX) developed by ICICI as well as various rolling periods of 500, 750,
Securities and the INR-USD Exchange rate. 1000, 1250, 1500 days. For example, rolling
The exchange rate has been taken from 500 days means, we will take 1 to 500
various RBI publications and website and observations and compute the VaR and
the data is from march 01, 1993. We have compare the same with next day’s losses and
chosen this data as our starting point then 2 to 501,……and so on. However, the use
because the unified exchange rate system was should see how the models work over various
introduced from this date. This IBEX index back periods with respect to estimation and
is widely used by market participants and has backtesting. All our calculations are for June
a long time series. The index as of June 2004 30, 2003.
has 19 underlying liquid bonds covering all The Chart-I gives the movement of IBEX PRI
the time buckets upto 15 years. The longest index used for the study while Chart-2 gives
maturity underlying is 2019 while the the daily return distribution during the
shortest underlying is 2005. For the details period. The Chart-3gives the movement of
on construction of IBEX, readers are exchange rate while Chart 4 gives the daily
requested to look at the website of ICICI returns of exchange rates.
Securities. While calculating VaR and doing
PR
I
1995 1996 1997 1998 1999 2000 2001 2002 2003 2004
900
1000
1100
1200
1300
1400
1500
Chart-1: Movement of IBEX (August 1994-June 2004)
The Table -1 gives the summary statistics of LCL Mean : 1.469139e-003
UCL Mean : 1.622274e-002The daily returns. The figures shows that the
Skewness : -1.355666e-001series can not be said to have properties that
Kurtosis : 6.392652e+001can fit a normal distribution.
Table-1 - Summary Statistics for Data: Table-2 - Summary Statistics for Data:
IBEXINR-USD Exchange Rate
PRINCIPAL RETURN Rtn
Min : -3.780000e+000Min : -3.297790e+000
1st Qu. : -2.000000e-0021st Qu. : -4.728692e-002
Mean : 8.845941e-003Mean : 1.242997e-002
Median : 0.000000e+000Median : 0.000000e+000
3rd Qu. : 5.000000e-0023rd Qu. : 5.766430e-002
Max : 3.830000e+000Max : 2.976490e+000
Total N : 3.622000e+003Total N : 2.891000e+003
NA’s : 0.000000e+000NA’s : 0.000000e+000
Variance : 5.127412e-002Variance : 8.281272e-002
Std Dev. : 2.264379e-001Std Dev. : 2.877720e-001
Sum : 3.204000e+001Sum : 3.593505e+001
SE Mean : 3.762486e-003SE Mean : 5.352103e-003
1995 1996 1997 1998 1999 2000 2001 2002 2003 2004
-5
-3
-1
1
3
PR
IRT
N
Chart-2: Distribution of Daily Returns
LCL Mean : 1.935647e-003 to estimate the VaR numbers.
UCL Mean : 2.292430e-002We first compute 1-day VaR numbers for all
Skewness : -5.563513e-002 methods and as well as the average of 1-day
Kurtosis: 2.495990e+001 VaRs in last 60 days in our sample. All VaR
estimates correspond to the probability level Estimates of VaRs and Capital Charge 0.01 (equivalently correspond to the
confidence level 0.99). For a given In this section we report our estimated VaR security/portfolio, maximum of these two figures and corresponding capital charges VaRs (i.e. 1-day VaR in last day and 60-day required All calculations are restricted to left-average of 1-day VaR) has been adjusted to tail (one tailed) of return distribution and arrive at VaR numbers corresponding to two probability level is fixed at 0.01 (equivalently alternative holding periods, viz., 10-days and confidence level of VaR estimates is set to
115-days . For calculating capital charge 0.99) strictly as per the RBI guidelines. Thus,
corresponding to a holding period h, h=10-the estimates we provide here actually refer
days or 15-days, the VaR with h-days holding to long-investment positions assuming that
period has been multiplied by the investment has been on the basis of the
multiplication factor 3.3 (as given in the RBI index. However, it is not difficult to take
circular for Pds). individual bonds or the portfolio of bonds
0 500 1000 1500 2000 2500 3000
30
35
40
45
50
Chart-3: Movement of in INR-USD Exchange Rate (March 1993-June 2004)
Pri
ce
The estimated results are given in Annexure- take only last one year data for backtesting,
1 for Normal Method and Annexure -2 for The Normal method requires less capital
Historical Simulation Method and charge vis-à-vis Historical simulation. But
Annexure-3 for Weighted Historical when we increase the backtesting horizon,
Simulation (Hull-White) Method for the Historical simulation gives better results and
GOI bond index IBEX and Annexure-4 for is more stable. Form a regulatory point of
Normal Method and Annexure -5 for view, Historical simulation would be
Historical Simulation Method and preferred.
Annexure-6 for Weighted Historical An important issue need to be mentioned
Simulation (Hull-White) Method for the here is that all VaR estimates provided in the
INR-USD exchange rate data.tables are in percentage form, and thus, may
We notice from the above tables that if we actually be termed as the relative VaR (Wong,
0 500 1000 1500 2000 2500 3000
-5
-3
-1
1
3
Rtn
Chart-4: Distribution of Daily Returns of Exchange Rate
3As per the Basle Committee guideline (1996), capital charge should be derived based on VaR numbers for
probability level 0.01 and holding periods 10-days. The VaR for 10-days holding period, however, are
calculated based on 1-day VaR numbers computed daily basis. In India, guidelines issued to PDs maintain
all attributes for capital charge computation except that VaR should have 15-days holding period (rather
than 10-days holding period prescribed in the Basle Committee).
et al., 2003), which refers to the percentage of tradeoff between the failures and higher
a portfolio value which may be lost after h- capital charge. From a regulatory point of
holding period with a specified probability view Historical Simulations and weighted
(i.e. the probability level of VaR). The historical simulations would be useful.
absolute VaR (i.e. the VaR expressed in Reference:
Rupees term) can easily be computed by
Altzner, P., F.Delbaen, J-M. Eber and D. multiplying the portfolio values with the
Heath, 1999, “Coherent Measures of Risk”, estimated relative VaR. Similarly, the capital
Mathematical Finance, 9, pp. 203-208.charge can also be represented in two
alternative forms, viz., relative (i.e. in Andersen, T. and T. Bollerslev (1998),
percentage) or absolute (i.e. in rupees terms). “Answering the Critics: Yes, ARCH Models
The additional information we require to do Provide Good Volatility Forecasts,”
convert a relative VaR/capital charge in a day International Economic Review, 39,
to a corresponding absolute term (i.e. rupees 885-905.
term) figures is the value of the portfolio.
Andersen, T., T. Bo llerslev, F. Diebold and P. The results show that normal method does
Labys (1999), “The Distribution of not provide better results and if fails in
Exchange Rate Volatility,” Journal of the backtesting when we apply the VaR methods
American Statistical Association, Website: at 99%. Historical Simulation and Weighted
http://citeseer.nj.nec.com/andersen99distriHistorical Simulation methods provide
bution.htmlbetter results.
Basel Committee on Banking Supervision, Conclusion:
1996a Amendment to the Capital Accord to
Incorporate Market Risk.This paper has experimented with two most
widely used VaR models, such as, variance-Basel Committee on Banking Supervision,
cova r i ance/normal and h i s to r i ca l 1996b Overview of the Amendment to the
simulation for estimating VaR using GOI Capital Accord to Incorporate Market Risk.
bond index IBEX as well as INR-USD
Basel Committee on Banking Supervision, exchange rate data. The results are given in
1996c Supervisory Framework for the Use of annexure I to 6. Historical simulation and
‘Backtesting’ in conjunction with the weighted historical simulations methods
Internal Models Approach to Market Risk provide better results in terms of back testing
Capital Requirements. in general and they require higher capital
charge while normal method requires less Basel Committee on Banking Supervision,
capital charge. It is upto the banks to decide 2001, The Standardized Approach to Credit
which method to choose depending on the
Risk. Duff, D. and J. Pan (1997), “An Overview of
Value at Risk,” Journal of Derivatives, Basle Committee on Banking Supervision
4, 7-49. (1995), An Internal Model-Based Approach
to Market Risk Capital Requirements, Basle, Embrechts, P. [Ed.] (2000), Extremes and
Bank for International Settlements. Integrated Risk Management, UBS Warburg.
Basle Committee on Banking Supervision Engle, R. and S. Manganelli (1999), “CAVaR:
(1996), Supplement to the Capital Accord Conditional Autoregressive Value at Risk by
to Incorporate Market Risks, Basle, Bank for Regression Quantiles,” Manuscript, UCSD.
International Settlements.Gallant, R. and G. Tauchen (1996), “Which
Boudoukh J., Matthew Richardson, and R. F. Moments to Match?,” Econometric Theory,
Whitelaw (1997), “The Best of both Worlds: 12,657-681.
A Hybrid Approach to Calculating Value at Gallant, R. and G. Tauchen (1998),
Risk”, Stern School of Business, NYU“Reprojecting Partially Observed Systems
Christoffersen, P. (1998), “Evaluating with Application to Interest Rate Diffusions,
Interval Forecasts,” International Economic Journal of the American Statistical
Review, 39, 841-862. Association, 93, 10-24.
Cruz, M (2002), Modeling, measuring and Garman, M. and M. Klass (1980), “On the
hedging operational Risk, John Wiley & Estimation of Security Price Volatilities
Sons, Ltd. ISBN no. 0471515604 from Historical Data,” Journal of Business,
53, 67-78.Danielsson, J. 2000, “The Emperor has no
clothes: limits to risk modelling”, Hull, John and Allan White, 1998, “Value at
Mimeog r aph , London S choo l o f Risk When daily Changes in market
Economics . (Internet site http:// Variables are not normally distributed”
www.riskresearch.org). Journal of Derivatives (Spring), 9-19.
Danielsson, J. and C.G. de Vries, 2000, Hull, John and Allan White, 1998,
“Value-at-Risk and Extreme Returns”, “Incorporating Volatility Updating into the
Mimeog r aph , London S choo l o f Historical Simulation Method for Value at
Economics . ( Internet s i t e ht tp :// Risk” Journal of Risk (Fall), 5-19.
www.riskresearch.org.Hendricks, D. (1996), “Evaluation of Value-
Darbha G, 2001, Value-at-Risk for Income at-Risk Models Using Historical Data,”
portfolios: A comparison of alternative Federal Reserve Bank of New York Economic
models, (www.nseindia.com) Policy Review, April, 39-70.
Hendricks, D., and B. Hirtle, 1997, “Bank Pagan, A., 1998, “The Econometrics of
Capital requiremnts for market risk: The Financial Markets”, Journal of Empirical
Internal models approach.”, Federal Finance, 1, 1-70.
Reserve Bank of New York Economic Policy Reserve Bank of India (RBI), Handbook of
Review, 4, 1-12.Statistics, 2002-03 and various other
Lopez, J.A, 1999, “Regulatory Evaluation of publications and circulations.
Value-at-Risk models”, Journal of Risk, 1, Samanta, G P & Nath G C, 2003, Selecting
201-242.Value-at-Risk Models for Government of
Longin, F., 1996, “The asymptotic India Fixed Income Securities, ICFAI
distribution of extreme stock market Journal of Applied Finance (forthcoming)
returns”, Journal of Business, 63, 383-406. (http://gloriamundi.org/detailpopup.asp?I
D=453056896)Longin, F., 2000, “From Value-at-Risk to
Stress testing: The Extreme Value Tsay, Ruey S. , 2002, Analysis of Financial
Approach”, in Embrechts, P. [Ed.], Extremes Time Series, Wiley Series in Probability and
and Integrated Risk Management, UBS Statistics, John Wiley & Sons, Inc.
Warburg.van den Goorbergh, R.W.J. and P.J.G. Vlaar
Nath, G C and Samanta, G P, 2003, Value at (1999), “Value-at-Risk Analysis of Stock
Risk: Concept and Its Implementation for Returns Historical Simulation, Variance
Indian Banking Sys t em, UTIICM Techniques or Tail Index Estimation?”, DNB
conference paper (http:// gloriamundi.org/ Staff Reports, No. 40, De Nederlandsche
detailpopup.asp?ID=453056842) Bank.
Nath G C and Reddy Y V, 2003, Value at Risk: Wong, Michael Chak Sham, Wai Yan Cheng
Issues and Implementation in Forex Market and Clement Yuk Pang Wong (2003),
in India, ICFAI Journal of Applied Finance, “Market Risk Management of Banks:
Nov 2003, http://gloriamundi.org/ Implications from the Accuracy of Value-at-
detailpopup.asp?ID=453056841 Risk Forecasts”, Journal of Forecasting, Vol.
22, pp. 23-33.Nelson, C.R. and A. F. Siegel, 1987,
“Parsimonious Modelling of Yield Curves”, Amexur 2: VaR estimation using Normal
Journal of Business, Vol. 60, pp. 473-89. Method as of June 30, 2004 (IBEX)
Ann
exur
e 1:
VaR
est
imat
ion
usin
g N
orm
al M
etho
d as
of
June
30, 2
004
(IB
EX
)
Vari
ance
-Cov
aria
nce
(Nor
mal
) M
etho
d
Des
crip
tion
of
Est
imat
es
Full
(9
9%)
Full
(95%
) R
ollin
g500
(9
9%)
Rol
ling
500
(95%
) R
ollin
g 75
0 (9
9%)
Rol
ling
750
(95%
)
Rol
ling
1000
(9
9%)
Rol
ling
1000
(9
5%)
Rol
ling
1500
(9
9%)
Rol
ling
1500
(9
5%)
Rol
ling
2000
(9
9%)
Rol
ling
2000
(9
5%)
DE
aR
0.51
87
0.42
48
0.56
47
0.47
38
0.55
04
0.46
09
0.60
06
0.50
25
0.53
81
0.45
02
0.48
74
0.40
76
60-d
ay A
vera
ge3.
3 1.
7075
1.
4001
2.
0270
1.
5602
2.
0270
1.
5602
1.
9884
1.
6616
1.
7543
1.
4663
1.
5870
1.
3262
Max
1.
7075
1.
4001
2.
0270
1.
5602
2.
0270
1.
5602
1.
9884
1.
6616
1.
7543
1.
4663
1.
5870
1.
3262
Cap
Cha
rge,
H=1
0-da
y (%
) 5.
3996
4.
4275
6.
4100
4.
9337
6.
4100
4.
9337
6.
2877
5.
2546
5.
5476
4.
6370
5.
0186
4.
1937
Cap
Cha
rge,
H=1
5-da
y (%
) 6.
6131
5.
4226
7.
8507
6.
0425
7.
8507
6.
0425
7.
7009
6.
4355
6.
7943
5.
6791
6.
1465
5.
1362
Bac
ktes
ting
-Fai
lure
s
Ove
r 1Y
ear
(4/1
9)
2 3
1 2
1 2
1 3
2 3
3 4
Ove
r 50
0 da
ys (
5/25
) 9
14
6 7
6 9
7 11
9
15
10
16
Ove
r 75
0 da
ys (
8/38
) 16
23
10
14
13
18
14
20
18
26
18
25
Ove
r 10
00 d
ays
(10/
50)
34
49
34
42
37
47
40
54
42
57
41
53
Ove
r 15
00 d
ays
(15/
75)
38
56
44
56
49
68
55
77
47
67
47
64
Ove
r 20
00 d
ays
(20/
100)
40
62
66
87
57
81
58
85
52
75
49
68
Full
(31/
156)
54
86
91
12
4 75
10
8 70
10
2 52
75
49
68
For
IBE
X, d
ata
is c
onti
nuou
s an
d he
nce
365
days
are
tak
en f
or 1
yea
rs
Ann
exur
e 2:
VaR
est
imat
ion
usin
g H
istor
ical
Sim
ulat
ion
as o
n Ju
ne 3
0, 2
004
(IBEX
)
Hist
oric
al S
imul
atio
n
Des
crip
tion
of E
stim
ates
Full
(99%
) Fu
ll (9
5%)
Rol
ling5
00 (9
9%)
Rol
ling5
00
(95%
) R
ollin
g750
(9
9%)
Rol
ling7
50 (9
5%)
Rol
ling1
000
(99%
)
Rol
ling
1000
(9
5%)
Rol
ling1
500
(99%
)
Rol
ling
1500
(9
5%)
Rol
ling2
000
(99%
) R
ollin
g200
0 (9
5%)
DEa
R
0.72
85
0.25
36
0.66
63
0.28
92
0.76
13
0.27
68
0.79
98
0.37
76
0.76
18
0.32
401
0.75
91
0.27
06
60-d
ay A
vera
ge3.
3 2.
4134
0.
8071
2.
6911
1.
0256
2.
5615
0.
9306
2.
5139
1.
2165
2.
5139
0.
9750
3 2.
5049
0.
8588
Max
2.
4134
0.
8071
2.
6911
1.
0256
2.
5615
0.
9306
2.
5139
1.
2165
2.
5139
0.
9750
3 2.
5049
0.
8588
Cap
Cha
rge,
H=1
0-da
y (%
) 7.
6319
2.
5523
8.
5100
3.
2432
8.
1002
2.
9429
7.
9497
3.
8470
7.
9497
3.
0833
3 7.
9212
2.
7157
Cap
Cha
rge,
H=1
5-da
y (%
) 9.
3471
3.
1259
10
.422
6 3.
9720
9.
9207
3.
6043
9.
7364
4.
7116
9.
7364
3.
7762
9 9.
7015
3.
326
Bac
ktes
ting
-Fai
lure
s
Ove
r 1Y
ear
(4/1
9)
1 11
1
8 1
4 1
4 1
8 1
10
Ove
r 50
0 da
ys (5
/25)
6
25
4 15
6
14
6 17
6
21
6 23
Ove
r 75
0 da
ys (8
/38)
8
49
4 24
7
26
7 31
9
45
8 44
Ove
r 10
00 d
ays (
10/5
0)
16
107
12
72
14
76
19
88
21
103
17
101
Ove
r 15
00 d
ays (
15/7
5)
18
137
14
103
19
121
25
139
23
132
19
133
Ove
r 20
00 d
ays (
20/1
00)
20
161
27
159
22
153
27
165
25
162
21
147
Full
(31/
156)
31
24
3 42
24
9 33
22
6 35
21
2 25
16
3 21
14
7
For
IBEX
, dat
a is
cont
inuo
us a
nd h
ence
365
day
s are
take
n fo
r 1
year
s
Ann
exur
e 3:
VaR
est
imat
ion
usin
g W
HS
Met
hod
as o
n Ju
ne 3
0, 2
004
(IBE
X)
Wei
ghte
d H
isto
rica
l Sim
ulat
ion
Met
hod(
Hul
l-Whi
te -
Lam
bda
= 0.
94)
Des
crip
tion
of
Estim
ates
Fu
ll (9
9%)
Full
(95%
) R
ollin
g500
(9
9%)
Rol
ling5
00
(95%
)
Rol
ling
750
(99%
)
Rol
ling7
50
(95%
) R
ollin
g100
0 (9
9%)
Rol
ling1
000
(95%
) R
ollin
g150
0 (9
9%)
Rol
ling1
500
(95%
) R
ollin
g200
0 (9
9%)
Rol
ling2
000
(95%
)
DEa
R
0.66
57
0.34
25
0.57
70
0.40
40
0.57
65
0.33
65
0.57
66
0.34
59
0.62
13
0.34
97
0.62
13
0.34
96
60-d
ay A
vera
ge3.
3 2.
1984
1.
1002
2.
0815
1.
2024
1.
8739
1.
0387
1.
9492
1.
0847
2.
0257
1.
0895
2.
0256
1.
0855
Max
2.
1984
1.
1002
2.
0815
1.
2024
1.
8739
1.
0387
1.
9492
1.
0847
2.
0257
1.
0895
2.
0256
1.
0855
Cap
Cha
rge,
H=1
0-da
y (%
) 6.
9519
3.
4790
6.
5823
3.
8025
5.
9257
3.
2847
6.
1639
3.
4301
6.
4058
3.
4454
6.
4054
3.
4328
Cap
Cha
rge,
H=1
5-da
y (%
) 8.
5143
4.
2609
8.
0616
4.
6571
7.
2575
4.
0229
7.
5492
4.
2010
7.
8455
4.
2197
7.
8450
4.
2043
Bac
ktes
ting
-Fai
lure
s
Ove
r 1Y
ear
(4/1
9)
1 8
2 8
2 9
2 9
1 8
1 8
Ove
r 50
0 da
ys (5
/25)
6
21
8 21
8
22
8 22
6
21
6 21
Ove
r 75
0 da
ys (8
/38)
9
33
13
33
12
34
12
34
10
33
9 33
Ove
r 10
00 d
ays
(10/
50)
17
66
24
71
21
67
22
66
19
68
18
66
Ove
r 15
00 d
ays
(15/
75)
19
77
26
82
23
78
24
79
21
79
20
78
Ove
r 20
00 d
ays
(20/
100)
21
86
28
94
25
90
26
89
23
88
22
84
Full
(31/
156)
28
13
2 39
14
2 35
13
7 34
12
1 23
89
22
84
For
IBEX
, dat
a is
con
tinuo
us a
nd h
ence
365
day
s ar
e ta
ken
for 1
yea
rs
Ann
exur
e-4: V
aR e
stim
atio
n us
ing
Nor
mal
Met
hod
as o
n Ju
ne 3
0, 2
004
(INR-U
SD E
xcha
nge
Rat
e)
Vari
ance
-Cov
aria
nce
(Nor
mal
) Met
hod
Des
crip
tion
of E
stim
ates
Full
(9
9%)
Full
(95%
) R
ollin
g500
(9
9%)
Rol
ling
500
(95%
)
Rol
ling
750
(99%
)
Rol
ling
750
(95%
)
Rol
ling
1000
(9
9%)
Rol
ling
1000
(9
5%)
Rol
ling
1500
(9
9%)
Rol
ling
1500
(9
5%)
Rol
ling
2000
(9
9%)
Rol
ling
2000
(9
5%)
DEa
R
0.76
31
0.62
87
1.06
70
0.89
96
0.42
13
0.35
48
0.39
50
0.33
18
0.36
52
0.30
63
0.48
51
0.40
61
60-d
ay A
vera
ge3.
3 2.
1694
1.
7832
1.
4873
1.
2600
1.
2606
1.
0633
1.
2606
1.
0232
1.
2239
1.
0268
1.
5721
1.
3161
Max
2.
1694
1.
7832
1.
4873
1.
2600
1.
2606
1.
0633
1.
2606
1.
0232
1.
2239
1.
0268
1.
5721
1.
3161
Cap
Cha
rge,
H=1
0-da
y (%
) 6.
8604
5.
6389
4.
7033
3.
9846
3.
9863
3.
3623
3.
9863
3.
2357
3.
8703
3.
2471
4.
9714
4.
1620
Cap
Cha
rge,
H=1
5-da
y (%
) 8.
4022
6.
9062
5.
7603
4.
8801
4.
8823
4.
1180
4.
8823
3.
9629
4.
7401
3.
9769
6.
0887
5.
0974
Bac
ktes
ting
-Fai
lure
s
Ove
r 1Y
ear
(3/1
5)
6 6
14
15
15
19
15
20
12
15
8 10
Ove
r 50
0 da
ys (5
/25)
6
6 18
19
17
23
19
24
12
15
8
10
Ove
r 75
0 da
ys (8
/38)
6
6 27
29
27
33
21
28
12
17
8
10
Ove
r 10
00 d
ays (
10/5
0)
6 7
44
50
29
37
23
31
13
18
8 10
Ove
r 15
00 d
ays (
15/7
5)
7 8
46
53
31
40
25
33
14
20
8 10
Ove
r 20
00 d
ays (
20/1
00)
15
23
56
71
39
55
37
50
14
20
8 10
Full
(28/
140)
29
43
79
10
0 44
61
37
50
14
20
8
10
Anne
xure
- 6:
VaR
esti
mat
ion
usin
g W
HS
Met
hod
as o
n Ju
ne 3
0, 2
004
(INR-U
SD E
xcha
nge
Rate
)
Wei
ghte
d H
istor
ical
Sim
ulat
ion
Met
hod(
Hul
l-Whi
te -
Lam
bda
= 0.
94)
Des
crip
tion
of
Estim
ates
Fu
ll (9
9%)
Full
(95%
) Ro
lling
500
(99%
) Ro
lling
500
(95%
)
Rolli
ng
750
(99%
)
Rolli
ng75
0 (9
5%)
Rolli
ng10
00
(99%
) Ro
lling
1000
(9
5%)
Rolli
ng15
00
(99%
) Ro
lling
1500
(9
5%)
Rolli
ng20
00
(99%
) Ro
lling
2000
(9
5%)
DEa
R 0.
8298
0.
5407
0.
9225
0.
6546
0.
8501
0.
6157
0.
8378
0.
5955
0.
8378
0.
5385
0.
8370
0.
5382
60-d
ay A
vera
ge3.
3 2.
7421
1.
7875
3.
0444
2.
1588
2.
8053
2.
0278
2.
7863
1.
9671
2.
7649
1.
7771
2.
7620
1.
7768
Max
2.
7421
1.
7875
3.
0444
2.
1588
2.
8053
2.
0278
2.
7863
1.
9671
2.
7649
1.
7771
2.
7620
1.
7768
Cap
Cha
rge,
H=1
0-day
(%
) 8.
6713
5.
6527
9.
6272
6.
8269
8.
8711
6.
4125
8.
8112
6.
2205
8.
7433
5.
6196
8.
7344
5.
6188
Cap
Cha
rge,
H=1
5-day
(%
) 10
.620
1 6.
9231
11
.790
9 8.
3612
10
.864
8 7.
8537
10
.791
4 7.
6185
10
.708
3 6.
8825
10
.697
4 6.
8816
Back
test
ing
-Fai
lure
s
Ove
r 1Ye
ar (3
/15)
4
6 2
6 4
6 4
6 4
7 4
6
Ove
r 500
day
s (5/
25)
4 6
2 6
4 6
4 6
4 7
4 6
Ove
r 750
day
s (8/
38)
4 7
2 7
4 7
4 7
4 8
4 7
Ove
r 100
0 da
ys (1
0/50
) 4
9 3
10
4 12
4
10
4 10
4
7
Ove
r 150
0 da
ys (1
5/75
) 5
13
4 14
5
16
5 14
5
13
4 7
Ove
r 200
0 da
ys
(20/
100)
15
34
14
37
15
39
15
38
5
13
4 7
Full
(28/
140)
30
60
29
64
21
46
15
38
5
13
4 7
Anne
xure
- 5:
VaR
esti
mat
ion
usin
g H
istor
ical
Sim
ulat
ion
as o
f Jun
e 20
04 (I
NR-U
SD E
xcha
nge
Rate
)
Hist
oric
al S
imul
atio
n
Des
crip
tion
of
Estim
ates
Fu
ll (9
9%)
Full
(95%
) Ro
lling
500
(99%
) Ro
lling
500
(95%
) Ro
lling
750
(99%
) Ro
lling
750
(95%
) Ro
lling
1000
(9
9%)
Rolli
ng10
00
(95%
) Ro
lling
1500
(9
9%)
Rolli
ng15
00
(95%
) Ro
lling
2000
(9
9%)
Rolli
ng20
00
(95%
)
DEa
R 0.
9587
0.
2950
0.
5054
0.
2418
0.
4857
0.
1922
0.
4598
0.
1898
0.
3981
0.
1708
0.
5038
0.
2069
60-d
ay A
vera
ge3.
3 3.
1622
0.
9681
1.
6179
0.
6433
1.
4260
0.
5824
1.
3267
0.
5778
1.
3203
0.
5624
1.
6407
0.
6639
Max
3.
1622
0.
9681
1.
6179
0.
6433
1.
4260
0.
5824
1.
3267
0.
5778
1.
3203
0.
5624
1.
6407
0.
6639
Cap
Cha
rge,
H=1
0-day
(%
) 9.
9997
3.
0615
5.
1161
2.
0343
4.
5093
1.
8418
4.
1955
1.
8272
4.
1753
1.
7783
5.
1884
2.
0994
Cap
Cha
rge,
H=1
5-day
(%
) 12
.247
1 3.
7495
6.
2659
2.
4915
5.
5227
2.
2558
5.
1384
2.
2378
5.
1136
2.
1780
6.
3544
2.
5712
Back
test
ing
-Fai
lure
s
Ove
r 1Ye
ar (3
/15)
2
17
11
32
11
37
12
37
10
35
8 26
Ove
r 500
day
s (5/
25)
2 18
15
44
15
50
15
49
10
39
8
30
Ove
r 750
day
s (8/
38)
2 24
23
68
24
75
18
65
10
49
8
40
Ove
r 100
0 da
ys (1
0/50
) 2
30
39
102
26
95
20
84
10
61
8 42
Ove
r 150
0 da
ys (1
5/75
) 2
34
41
111
29
102
22
90
10
64
8 42
Ove
r 200
0 da
ys
(20/
100)
7
57
50
145
34
135
28
132
10
64
8 42
Full
(28/
140)
16
81
69
19
1 39
14
2 28
13
2 10
64
8
42