Upload
trinhtram
View
214
Download
0
Embed Size (px)
Citation preview
A Report on the
Internal Assessment of the Social Service Mapping Tool
Computerized Social Service Map, DamnakTrach village, DamboukRong commune, Kampong Speu province
@UNICEF/CBDA/2010/EkThinavuth
April 2011
2
CONTENTS
EXECUTIVE SUMMARY
ABBREVIATIONS and ACRONYMS
1. INTRODUCTION
Background
Objectives and rationale of the Internal SSM Assessment
Methodologies
Framework of the report
2. FINDINGS FROM THE DISCUSSIONS AND QUESTIONNAIRES
2.1 Inputs from focus group discussions
2.1.1 Assessment of the process of the SSM
Procedures
Participation
Indicators
Suggestions/Recommendations
2.1.2 Assessment on the usefulness and effectiveness of the SSM
Addressing issues and developing future plans based on the SSM
Monitoring and assisting the vulnerable
Suggestions/Recommendations
2.1.3 Lessons learnedfrom the pilot implementation of the SSM for various stakeholders
Advantages
Disadvantages
Suggestions/Recommendations
2.2 Inputs from users
Usefulness and relevance of the SSM
Suggestions/Recommendations
2.3 Inputs from supporters
SSM training workshops for supporters and CC/CCWC
Support provided to CC/CCWC
Suggestions/Recommendations
3. RECOMMENDATIONS
3.1 Recommendations based on the interviews, questionnaires and discussions
3.2 Recommendations from meetings with UNICEF sections and other development partners
4. CONCLUSION
5. ANNEXES
Questionnaire
List of participants from focus group discussions, list of interviewed users and supporters
3
ACRONYMS AND ABBREVIATIONS
CC commune council
CCWC commune committees for women and children
CDB commune database
CIP community investment plan
CWCFP commune women and children focal point
DFP district focal point
MoI Ministry of Interior
P/DFT provincial/district facilitation teams
PFP provincial focal point
PLAU provincial local administration unit
SSM social service mapping
4
EXECUTIVE SUMMARY
With support from the Ministry of Interior (MoI), commune committees for women and children
(CCWCs) were started in 2004in order to better identify critical needs of women and children in
Cambodia. In order for communes to put more emphasis on social services rather than on
infrastructure, UNICEF initiated a pilot participatory mapping tool, Social Service Mapping
(SSM) for CCWCs in 2009. The SSM is a mapping exercise conducted at the village level and led
by commune councils (CC)/CCWCs. The maps attempt to identify the most vulnerable families
in the commune, especially women and children, with indicators focusing on social sectors. So
far, the SSM exercise has been implemented in 117 villagesin 20communes in six UNICEFtarget
provinces.
In order to assess the effectiveness and quality of the SSM implementation, the Seth
KomaProgramme conducted an internal assessment of the tool in the second half of 2010. In
August and September, the assessment team, composed of MoIstaff, provincial- and district-level
focal points (P/DFPs), members of the Project to Support Democratic Development through
Decentralization and Deconcentrationand UNICEF Seth Koma staff visited villages in 11 selected
communes in the six UNICEFtarget provinces1. This report is based on data collected through
focus group discussions andkey informant interviews with supporters, users and beneficiaries of
the SSM. The assessment procedures were conducted in a participatory manner so as to gain first-
hand insight from all the stakeholders.
Findings from focus group discussions
Despite the fact that the participatory approach was a new process for many of those who
developed the maps, pilot communes followed most of the essential steps found in the guidelines.
On the other hand, there were some steps that were skipped by most of the communes, such as
note-taking and greeting and introducing. The importance and meaning of the steps should be
stressed in refresher training. During the exercise processes, level and quality of participation
exhibited both positive aspects andsome limitations that should be overcome for future
implementation. For instance, sample communes reported high female attendance rates at the
meetings, with some CC/CCWC members and village leaders commenting that women were
actively sharing their opinions related to social issues. While this good practice should be
maintained, more attention should also be paid to the participation of young people and health
staff, both of which were less well represented in many communes. It is also important that all
villages record distribution of participants to ensure variousgroups are represented. Discussion
groups attempted to generate feedback on the 13 indicators and found that all sample communes
felt that all or most of the 13 indicators were relevant to real issues they faced. However, there is
a need to further discuss the indicators so that the list is as socially and culturally sensitive, clear
and relevant as possible.
Regardingthe usefulness and effectiveness of the SSM, all sample communes except Kampong
Thom claimed that they had used the SSM information to develop community investment plans
(CIPs)in 2010. Also, regular updates of the maps and indicators seemed to help monitor progress
and changes of vulnerable families‟ situations. Although these findings demonstratethe SSMs
applicability, some UNICEF staff observed that there were not yet sufficient links between the
SSM and CIPs; instead, the information was used for ad hoc support. To strengthen the link, it
might be helpful for CC/CCWCs to betrained to analyse root causes so as to reflect them in
longer-term planning.
Focus group discussions revealed that there were both overall advantages and disadvantages of
the SSM. Advantages included promoting transparency, addressing equity in access to social
1 See Annex 3 for a list
5
services, facilitating the monitoring of vulnerable families, shifting attention from infrastructure
to social sectors, motivating CC/CCWCs to work in the field more frequently and promoting
confidence among village and commune leaders. In contrast, the few disadvantages that emerged
included the underrepresentation of certain social groups, misunderstandings in objectives and
purposes of the SSM exercise, limited capacities of key actors and difficulties in physically
maintaining the maps. These challenges need to and can be addressed via harmonization among
different stakeholders, including national and sub-national level authorities, UNICEF and other
development partners.
Findings from user interviews
Interviews with users revealed that even though the SSM was seen as useful in gathering
information and identifyingvulnerable families for interventions, certain indicators were viewed
as irrelevant to the users‟ activities. The interviews also revealed thatinformation about the SSM
has not yet been well disseminated, and many potential users do not know that the maps exist or
are not convinced of their usefulness. Thus, it will be important to seek out opportunities where
CC/CCWCs can introduce and present the importance and usefulness of the SSM at different
levels.
Findings from supporter interviews
The assessment interview with supporters focused on training at two different levels: training
received and training provided for CC/CCWCs. Subjects participating in this interview in most of
the sample provinces feltthat the training was somewhat difficult to understand and follow due to
insufficient time, trainers proceeding too quickly, and used complex methods and unfamiliar
concepts that needed more explanation. Theinterviews also showed that conducting the
CC/CCWC trainingswas not easy due to lack of CC/CCWC participation, unclearly defined roles
of district and provincial levels and a lack of capacity to understand the new concepts. However,
it has to be taken into account that at the time of the sessions, no proper, systematic training
procedures were in place. Despite this difficult situation, the SSM exercise was initiated and maps
were completed at the village level. In conclusion, the pilot communes and provinces should
receive refresher trainings and all manuals and guidelines should be reviewed and revised to ease
their implementation.
These important findings, challenges and recommendations/suggestionswill be presented in
further detail in this report, along with additional specific points. This internal SSM assessment
report aims to make recommendations to inform future strategic decisions of the UNICEF
country programme (2011-2015).
6
1. INTRODUCTION
Background
As much as the CCshave contributed to local-level development by encouraging dialogue
between citizens and government (primarily in planning and budgeting infrastructure projects),
more needs to be done to address social issues. As a response, in 2007MoIbegan supporting
establishment of the CCWCs, entities that wereinitiated in order to better identify critical needs of
women and children.
In order for communes to put more emphasis on social services rather than infrastructure,
UNICEF piloted a participatory mapping tool, called the SSM for CCWCs. The SSM was to be
drawn at the village level to identifyvillage resources such as roads, schools, wells, toilets,
hospitals, community rice banks, ponds and pagodas, as well as a numbered gridof the village‟s
homes. Each house on the map is marked with a series of numbered indicators (1 to 13) that
reflects the degree to which a household lacks access to social services and which could result
insocial issues (for example, youth drug use and gang involvement could cause a young person
todropout of school). These 13 indicators were carefully selected by each relevant UNICEF
section with special attention tovulnerable children. Development of the maps is supported and
led by commune-level members, while trainings for commune-level staff are conducted by
provincial-level members.
Social Service Map of Prey Romdoul village, Prasot commune, SvayRieng province @UNICEF/CBDA/2010/You Socheat
This tool aims to help CCWCs identify families with limited access to social services so that CCs
canefficiently develop plans and budgets in a participatory and transparent manner. A
consultancy was carried out in August/September 2009 to provide practical support to the P/DFPs
and assist the CCWCs in developing and using the maps in regular meetings. This initiative also
attempted to operationalize one of UNICEF‟s priorities with regards to equity by providing
support and services to vulnerable and unreached families.
7
The SSM initiative began with pilot mapping in 20 communes across six target provinces (Prey
Veng, Kampong Thom, Kampong Speu, OddarMeanchey, Stung Treng and SvayRieng). There
are 177 villages in these communes, but it was suggested that the pilot would initially cover about
30 to 40 per cent of villages per province in 2009 to ensure quality implementation, covering the
remaining villages in 2010. Consequently, maps were drawn in all villages between November
2009 and May 2010. Guidance materials, including the Trainers Guide for District and
Provincial Focal Points for Conducting Social Service Mapping to be used in CCWC training
and theHip Pocket Guide for CCWCs, were developed.
In order to assess the tool‟s effectiveness and quality, the Seth KomaProgramme conducted an
internal assessment during the second half of 2010. In August and September, a team composed
of four representatives from MoI, fourP/DFP members, two members of the Project to Support
Democratic Development through Decentralization and Deconcentrationand five UNICEF Seth
Koma staff visited villages in 11 selected communes in the six UNICEFtarget provinces. The
assessment is based on 11 focusgroup discussions and interviews with key actors: 6 with
supporters, 6 with users and 26 with beneficiaries.
The assessment focuses on the process and impact of the SSM. In this report, data mainly
collected during the focus groups and interviews with supporters and users will be analysed and
used. Data collected during interviews with beneficiaries will be recorded and analysed through
case studies by a consultant. The main purpose of this report is not to evaluate and document the
final outcomes of the use of the tool, but rather to make recommendations to informfuture
strategic decisions of the country programme (2011-2015).
Objectives and rationale of the internal SSM assessment
The objectives of the internal SSM assessment are to learn from the process and quality of SSM
implementation as well as to measure effectiveness and evaluate the tool‟s usefulness in order to
inform future strategic decisions.
To strengthen the CCWC focus on the needs and universal rights of women and children, the
committees must better identify families that do not have sufficient access to social services. The
SSM has the potential to improve the targeting and identifying of those most in need. This
internal assessment will illustrate lessons learned in the pilot and raise recommendations to
further improve the quality of the tool and broadenits effectiveness and practicality. As the
quality and applicability improve, the model can be expanded to other villages.
While the questionnaires and discussion questions were carefully developed in consultation with
the UNICEF M&E and Child Protection sections and MoI‟Seth Koma team, there are some
reservations/limitations to note: 1. Kampong SpeuProvince carried out their mapping exercise
before the guidelines were prepared, which accounts forTang Krouch and DamboukRoung
communes not following certain steps; and 2. Some communes completed the assessment long
after they had drawn their maps, making it difficult for them to recall the procedures or elements
of the exercise.
Methodologies
This report is based on data collected through focus group discussions and interviews with key
supporters, users and beneficiaries of the SSM. All the assessment procedures were conducted in
a participatory manner so as to gain first-hand insight from all the stakeholders.
1. Focus group discussions with CCWC members were organized in August 2010. The
participants included commune chiefs, commune seconddeputy chiefs, commune women and
children focal points (CWCFP), clerks, teachers, health centre staff, commune police, village
chiefs, village vice-chiefs and village assistants. Discussions soughtto assess the process of
8
developing the SSM, including the level and quality of participation and the usefulness and
effectiveness of the SSM in addressing social issues.
Focus Group Discussion in Prosot Commune, SvayRieng@UNICEF/CBDA/2010/YouSocheat
2. Interviews were conducted with key supporters, users and beneficiaries on an individual basis.
The first interviewed group, supporters, consisted of provincial local administration unit
(PLAU) officers, P/DFPs and Provincial/District Facilitation Teams (P/DFTs) who were in
charge of training CC/CCWCs and supporting the implementation process. The main focus of
the interviews was therefore on the SSM training of trainers and the subsequent training
workshops conducted for CC/CCWCs.The second group, the users, included sub-national
authorities, local service providers and NGO representatives who used the SSM. During the
interview, they were asked how they used the SSM and for their opinions on the tool in terms
of usefulness for other interventions. Lastly, individual interviews with beneficiaries were held
to assess their level of participation in the SSM development process and its effectiveness in
identifying and reaching vulnerable families.
The assessment was done in 11 communes, or 55 per cent of the 20 pilot communes in the six
UNICEF target provinces. Focus discussion groups with CCWCs were carried out in all 11
communes. Interviews with supporters were done in each of the six provinces, whileinterviews
with user groups were carried out in Prey Veng, SvayRieng, Kampong Speu and Stung
Trengprovinces (not in OddarMeancheyand Kampong Thom). Names of the communes, villages,
line departments and NGOs that participated in the discussions and interviews are listed in Annex
6.
To complement the collected data, a number of field visits were conducted to clarify key concerns
emanating from the findings. Visits were made to Kampong Speu, Prey Veng and
SvayRiengprovinces in November and December 2010. During the Kampong Speuvisit, a
meeting in KhsemKhsam commune was organized, where participants included a commune
chief, commune clerk, CWCFP, CC members, a PFP and a DFP. The meeting was followed by a
short question-and-answer session with two PFP members (one male and one female). A
discussion was also held between UNICEF provincial staff and the PFPs. During visits to SpirKor
and BeungPreah communes in Prey Veng, CC/CCWCs, commune chiefs, commune clerks,
village chiefs and other key sources joined discussions as necessary. Likewise, in SvayRieng,
Prasout and Sambor communes, discussions were held with key sources, including CC/CCWCs,
commune chiefs, deputy commune chiefs and commune clerks.
9
In addition, a few meetings and consultations were held between UNICEF staff in Seth Koma,
Child Protection and HIV/AIDS sections to include practical recommendations for future
interventions.
Framework
This introductory section will be followed by sections that address findings, recommendations
and conclusions. The section on findingsis divided into three parts:
1) Inputs from focus group discussions
2) Inputs from users
3) Inputs from supporters
In each part, findings from the assessment process will be illustrated, highlighting some of the
crucial elements of the SSM preparation and usage.This section attempts to specifically examine
whether the tool has been effectively and efficiently implemented from the preparation phase to
the actual map drawing, as well as whether the SSM successfully fulfilled its objectives to better
identify target families and to address the issues.
The recommendations section will be divided into suggestions drawn from the findings (including
feedback reports by interviewers) and from inputs provided during additional discussions and
meetings with UNICEF programme sections, government counterparts and other development
partners. Lastly, the report will summarize the key points and provide conclusions.
2. FINDINGS FROM THE DISCUSSIONS AND QUESTIONNAIRES 2.1 Inputs from focus group discussions
2.1.1 Assessment of the process
Procedures
The SSM development process had two major steps: 1) CC/CCWCs preparation prior to a
village-level meeting and SSM drawing and 2) development of the SSM in a participatory manner
that involved multiple village representatives. Each step involves a number of procedures, though
it appears that fewcommunes followed all of them. There are a number of possible explanations
for this: first, discussion participants were not directly asked if they followed particular steps, but
rather the question was presented as an open one. Thus, even though they might have carried out
certain procedures, they might have simply not mentioned them. For example, the data shows that
only 3 of 11 communes followed the step to “Prepare objectives of drawing the map on a
flipchart.” This could be attributedto the fact that this particular step was not explicitly conducted
as a separate step.
Secondly, some communes had already started preparing their map before the guidelines were
distributed, so they did not have clear guidance on ways toorganize the preparation. Also, since
these communes prepared their map more than one year before the assessment, it is possiblethat
respondents could no longer recall all the specifics of the methodology used. In contrast, all
communes except one organized a pre-meeting to divide and share responsibility. It is not clear
what was discussed in the pre-meetings, but they are important inestablishing a consensus on who
should be included in drawing the map in order to produce the best outcome. While these points
could be indicated on the questionnaires, each province did manage to organize trainings and
SSM exercises despite the fact that neither clear guidelines nor a manual were available at
thetime.All communes in the pilot provinces also managed to conduct the SSM exercise for most
of their villages.
10
SSM field practice of a Training workshop inTrabekKeut village, Angkor Tret commune, Prey Veng province
@UNICEF/CBDA/2009/Mark Munoz
In step two, developing the SSM at the village level, the first procedure: “Greet and introduce
participants,” was skipped by six communes. This might be accounted for by the fact that the
villagers were already well acquainted with each other and there was no need for a formal
introduction. Data shows that note-taking was completed in only 1 of 11 communes, even though
commune members themselves were in charge of this task. When this issue was raised during the
field visit to Kampong Speu in November, the UNICEFprovincial staff explained that the
participants understood that the final objective of the discussion was to draw a map, and they did
not think recording the process was important. In SvayRieng, UNICEF provincial staff observed
that commune members did not take notes because map drawing meetings were not seen as
formal meetings but rather as informal fieldwork. Another reason might be the existence of an
internalized culture in which communes operate on an ad hoc basis. This is likely to be the case
for other communes as well.
According to the questionnaires, three communes raised sensitive issues during discussions,
which included domestic violence, drug use and youth gangs. While some sensitive issues remain
taboo subjects that cannot be easily discussed, various interventions by NGOs, international
organizations and/or communes to address these issues seem to havepositively influenced
people‟s perceptions. For example, the visited commune in Kampong Speureported that in the
first SSM exercise, there were no cases of drug use, but in the second round, three cases of drug
use by youth were recorded. The increase in the number of cases was attributed to increased
involvement by the police in investigating and reporting, and reflects improvement in cooperation
and systematic reporting by relevant actors. The new cases do not necessarily indicate a
worsening situation. Still, UNICEF staff members observed that some families had to be
convinced to allow their sensitive issues to be reflected on the maps, for fear of stigmatizationin
the community. While some CC/CCWCs and commune chiefs seemed to prioritize exposure of
all information on the maps, sensitivity to privacy issues has to be reconsidered. This is a
challenging aspect for UNICEF due to the fact that sensitivity is subjective, and certain issues
might seem to be more taboo to villagers than others. A consensus among the UNICEF team in
needed on this issue.
11
While more than half the communes said that vulnerable families could be identified in smaller,
separate meetings, only two communes reported that the privacy of vulnerable families was
protected. This contradictory data could indicate that although vulnerable families might be more
inclined to discuss their situations in private meetings, CC/CCWC members engaged in drawing
maps were not as concerned about maintaining confidentiality. While privacymight be a foreign
concept in Cambodian villages,it is important to ensure that vulnerable families are not put into
situations where their issues are openly discussed. During field visits, it was observed that most
communes conducted individual home visits to help families more comfortably discuss their
situation. In addition to holding separate meetings and individual home visits, one effective way
of identifying vulnerable families appears to be asking neighbours and relatives for information.
This provides interviewers with access to information that target families may be ashamed to
mention on their own.
The pilot SSM is a recent initiative, and among officials from provincial and district Local
Administration Unit and CC/CCWC, there remains a lack of understanding of its overall purpose
and consensus about its process. Having looked at procedures related to the SSM tool, the next
section examines the level and quality of participation in the SSM exercise.
Participation
Most communes encouraged village chiefs, the elderly, teachers and health centre staff to
participate in the drawing process; in 7 of 11 communes, villagers took part in the mapping.
However, young people were not included in the exercise in 8of 11 communes. UNICEF
provincial staff in Kampong Speu also mentioned that in general, young people did not show
interest in attending meetings.The underrepresentationcouldindicate that these meetings do not
actively encourage youth participation, or that there is a lack of organized youth groups, making
it difficult for CC/CCWCs and village leaders to identify youth candidates. In 7 of 11communes,
ID poor recipient families participated in this exercise.However, the exact distribution of
participants is not clear because the communes did not record specificnumbers.
Keyinformation sourcesin the SSM development/map drawing included village chiefs/deputies,
chief/assistants, elderly people, schoolmaster/teachers and community members/villagers
considered to be most “familiar with the situations of the people in villages.” In comparison,
youth representatives and health centre staff were absent in four and five communes, respectively.
The low level of youth participation could reflect an aspect of Cambodian society described in the
CCWC Capacity Report (p.14): “an education system that discourages questioning reinforces
attachment to hierarchy and results in a reluctance to openly oppose, disagree with or even
question those who have power and a reticence to try out new ways of learning.” On the other
hand, reasons for absence of health centre staff might be attributed to time constraints, given the
fact that one health centre covers two villages. It could also be accounted for by a lack of
coordination, as it is not clear whether health staff were properly informed about the purpose of
the SSM exercise.
Furthermore, attendance does not necessarily mean active participation. In a few cases,
participants reported a fear of speaking up in meetings due to hierarchy. For example, feedback
from SvayRieng noted, “The village chiefs were afraid of commune chiefs.” Also, a provincial
UNICEF staff member in Kampong Speusaidthat when he is present, some people appear
reluctant to express their ideas and thoughts.
Regarding female participation, 7of 11communes had more than 50 per cent female participants
in the meetings. Though this ratio is impressive, it is even more important to ensure that women
actively take part in preparing and drawing the maps. In Kampong Speu and SvayRieng, female
PFP, CWCFP and CC members described how women were very active in presenting their views
on household issues in the context of the indicators. They also said that if needed, they would
12
visit individual households in order to directly talk to women for additional information when
husbands were not present. This aspect should be more closely monitored and followed-up on to
ensure women‟s ideas are well represented in the SSM.
SSM field practice of a Training workshop inTrabekKeut village, Angkor Tret commune,
PreyVengprovince @UNICEF/CBDA/2009/Mark Munoz
In this assessment, it has also been noted thatthe number of participants in most communes
declined when the maps were updated. All seven communes that updated village maps
includedparticipants such as CCWC members, CC members, commune clerks, commune chiefs
and commune deputy chiefs, suggesting that the update process was most likely initiated at the
commune level rather than by villagers.
As already discussed, the level and quality of participation is affected by gender and traditional
cultural norms. The SSM was initially designed to encourage women and young people to
participate, and the introduction of new norms of active participation need to be carefully taken
into consideration.
The next section will discuss the 13 indicators used in the SSM. The focus group discussions
encouraged participants to share insights about the indicators‟usefulness and relevance.
13
Indicators
13 SSM Indicators
1. Household whose children (under one year old) have NOT
had birth registrations yet.
2. Household whose one-year-old children have NOT had
seven vaccinations.
3. Household with pregnant women who have NOT accessed
health services.
4. Household whose three- to five-year-old children have
NOT attended preschool.
5. Household whose 6- to 11-year-old children have NOT
attended school or have dropped out of school.
6. Household that does NOT have access to clean water.
7. Household that does NOT have a latrine.
8. Household that has orphans or abandoned children.
9. Household that has children living with chronically ill
parents or caregivers.
10. Household that has children with disabilities.
11. Household with children who have been exposed to and/or
directly impacted by violence or abuse (migration, rape,
child labour).
12. Household that has poor ID cards.
13. Household that has youth involved in gang and/or drug-
related activity.
All communes agreed that the 13 indicators are all “relevant/associated with the real issues in the
village.” These indicators do not just spell out the visible issues, but also highlight and bring
attention to sensitive issues such as domestic violence or drug use.
However, a few communes suggested indicator 11 (household with children who have been
exposed to and/or directly impacted by violence or abuse [migration, rape, child labour]) should
be divided into more specific indicators because each of the three issues is distinctive. Though the
likelihood of an individual becoming a victim of one or more of those issues is not small, these
suggestions are worth considering since the various issues are not necessarily interrelated. For
example, it was evident in the individual interviews that some children work as construction
workers or other types of labourers. One commune pointed out that indicator 13 (household that
has youth involved in gang and/or drug-related activity) also should be separated into two
indicators, since youth problemsare more complex than suggesting that being in a gang also
means being a drug user. Another commune suggested that indicator 7 (household that does not
have a latrine) should specify a dry latrine versus a pour-flush latrine. This suggestion is however
not a top priority, because either type of latrine can be very functional depending on the
surrounding environment.
One commune had already added two extra indicators while drawing the SSM map: “single
parent-headed family with children under five years old” and “households with 12- to 17- year-
old children dropping out of lower secondary school.” The suggestion raises significant points.
As can be seen from the individual interviews, single parents are prevalent in rural areas of
Cambodia due to domestic violence, husbands‟ internal migration for employment and 30 years
of civil turmoil in the past. It has been said that widows are one of the most economically
14
vulnerable groups in society2. They mostly live in rural areas and face a lifetime of economic
challenges, a situation that would most likely also apply tosingle parents whose husbands have
left for various reasons. Regarding the second indicator, it is important to note that enrolment
ratios in primary and secondary show an acute decline from 94.8 per cent to 31.9 per cent (lower
secondary) (EMIS), demonstrating that despite the fact that primary-level attendancehas
improved significantly, the transition from primary to secondary school remains an important
challenge. The new country programme prioritizes this issue.
Most communes also suggested the addition of the following indicators:
Construction materials used for houses
Household that has not had enough to eat for the past six months
Household headed by a single parent (with many children)
Household with elderly people living alone
The first three indicate economic situations that greatly affect children‟s health, schooling or
security. The last one suggests that in addition to women and children, elderly people are also a
vulnerable group that should be monitored.
There is also a concern about the terminology and wording in indicator 9, “household that
haschildren living with chronically ill parents or caregivers.” There seems to be a lack
ofunderstanding of the meaning of“chronic illness”among CC/CCWCs. A UNICEF staff member
onthe assessment team observed that “households with chronically ill caregivers/parents (were)
rather identified as households with parents/caregivers who (were) HIV positive or have AIDS.”
These points illustrate the key findings from interviews and focus groups, brief field visits to
provinces and discussions with UNICEF provincial staff, PFPs, CCWCs and other key actors.
Some of the suggestions and recommendations raisedin terms of process, participation and SSM
indicators will be introduced in future training package and resource materials.
Suggestions/Recommendations
Based on these observations, the following suggestions/recommendations are being put forth to
improve quality of the overall exercise.
CC/CCWCs should put more effort into making the pre-meetings (step 1) more inclusive
and organized. Using the village database, they should select meeting participants that
represent the community well. For example, in case a health chief is not a member of the
CCWC, he/she should be invited to the pre-meetings. These meetings can also serve as an
effective platform to select participants for step 2.
Regardingstep 2, the two processes that were most often left out--“greet and introduce
participants” and “note-taking” should be more strongly emphasized. First, though
participants might already know one another, a formal introduction and greeting session
could serve to encourage everyone‟s active participation. Making each participant
speaking front of everyone else at the onset of discussions would help make each person
more comfortable and confident to share their views during the meeting. This
introduction session should also be combined with a presentation of the map-drawing
objectives to ensurethey are considered early on.Facilitators should ensure that everyone
contributes to the meeting and understands the basic purpose of the mapping exercise.
2 Lee, Susan H., The Long-Term Effects of War on Rural Cambodian Widows, p. 1
PROCESS
15
As instructed in the Hip Pocket Guide, communes and villages should ensure that they
assign a commune member as a note-taker/recorder who records the „soft information.‟ It
is important for the recorder “to remain aware and listen at all times in order to note the
„soft‟ information or comments,” for “the notes from the recorder will be very
important”during later analysis of the SSM. They should take also notes on processes
carried out during SSM development and how they were organized. These notes will
allow villagers and commune members to refer back to their procedures when updating
the tool. The importance of note-taking needs tobe re-emphasized in refresher trainings or
provincial meetings and workshops.
To identify and follow-up with vulnerable families, separate meetings/visits should be
encouraged if possible to provide families‟ with a comfortable environment that allows
them to speak openly. Individual interviews revealed that vulnerable people like single
parents are more likely to miss information about the SSM, so the separate
meetings/visits would help keep them informed while allowing communes and villages to
more accurately assess individuals‟ situations. In order to avoid stigmatization for
families facing sensitive issues, CCWCs should collaborate with specialized institutions
and experts in line departments or provincial/district social workers. UNICEFshould also
ensure that training is conducted so as to sensitize CC/CCWCs about stigma and
confidentiality norms. It would be helpful if the training included concrete examples of
sensitive information being raised so that participants can appropriately face these
situations.This kind of training and information should also be provided to commune and
village leaders. It is important thattheselead actors understand that information cannot be
forcibly extracted from people.
In summary, the CCs/CCWCs need to be aware of the importance of each process, for they were
designedto serve certain purposes that will add value to the map quality and effectiveness. Also, a
more systematic mechanism for conducting the exercise and building consensus among key
actors should be put into place.
Numbers of participants from various social/age/professional groups should be
recordedso that underrepresentation among specific groups can be identified. Since
certain sourceslike young people or health centre staff tend to be underrepresented in the
drawing process, it might be a good idea for these groups to organize their own
discussions before the village meetings/discussions. In that way, they could meet on their
own time and increase the chance fortheir views to be heard. One representative could be
chosen from each group to participate in the village-wide meetings to share the issues
discussed during the group session. This would prevent the villages and communes from
having too many participants while still reflecting the ideas of various people. These
separate discussions would also allow people to talk more openly without of the fear of
socially and occupationally higher-ranking villagers or commune staff. It is also
important to work with organizedyouth groups rather than attempting to randomly
identify young people for participation. Because youth groups do not exist in every
village, one suggestion is to reach out to schools andmeet with school associations.
Finally, though selection criteria for the SSM meetings do not include ID-poor recipient
families, it is encouraging to see these families participating in the exercise as they are
likely to be beneficiaries and would likely have great insight. This also helps update the
status of ID holders, which are officially updated only biannually. Their inclusion should
be stated in the guidelines.
PARTICIPATION
16
Two of the existing indicators, 11 and 13, should be reviewed and adjusted to make them
more specific and sensitized. Indicator 11 attempts to cover a few different issues
butshould be broken down or revised. Separating out the individual issues might,
however, raise other concerns. Firstly, an indicator about “rape” would be too sensitive to
be identified on the maps, and issues like this need different approaches requiring
expertise. Secondly, “child labour” would be too broad and requires a clearer definition.
Due to the sensitivity of the issues covered by this indicator, UNICEF needs to review it
carefully before making any changes. Indicator 13 on drug use and gangs should either be
divided in two or removed from the list.
As to the four additional indicators suggested, while theyraise important issues, allare
alsoincluded in either the CDB (commune database) or the ID-poor methodology. The
first one is included under “house situations” in the ID-poor and under “housing” in the
CDB. The second is partially represented in ID-poor families, as question 8asks, “During
the last 12 months, did your household owe rice or borrow rice from other people?” The
third can be also addressedbyboth sources. The ID-poorrecords heads of families
whilethe CDB notesthe number of “female-headed families.” The CDBalso attempts to
shed light on elderlypeople as seen in the indicator, “number of elderly persons without
guardian.” However, one concern in relying on thisdata is that data related to ID-poor
families is updated only once every two years, while theCDBis updated once a year.
Nevertheless, if the various data sources are fully taken in account, there should be
sufficient indicators to cover a wide range of social and economic aspects. Communes
should closely consult with line departments to work as one.
Indicators do not necessarily have to be identicalacross communes or provinces. Different
regions willhave different issues and concerns. For example, two communes in
SvayRiengboth mentioned that their village chiefs are well aware of and knowledgeable
about border issues. This illustrates the fact that border provinces will have their own
unique issues.The list of indicators could therefore be flexible and, as one commune did,
communes and villages should be encouraged to add indicators as needed. However, they
should be careful not to add new indicators without proper consideration to avoid
overcomplicatinglists. Villages and communes should keep three things in mind:1.Be
clear about who would follow-up and monitor progress and changes for additional
indicators; 2.Check other data sources to avoid duplication of indicators; and 3.Ensure
that additional indicators are related to social sectors and are backed by reasonable
rationale.
All indicators should be properly worded and translated into Khmeras accurately as
possible. In case of more technical terminology – words like “chronic illness” – UNICEF
should provide clear definitions. Time can be taken during training to clearly explain the
terms used to key SSM participants.
2.1.2 Assessment on usefulness and effectiveness of the SSM
Addressing issues and developing future plans based on the SSM
Although the maps aloneare not enough to address the various social issues, data from focus
group discussions implies that communes and villages use the maps as an initiative to identify
targets and address social issues.
INDICATOR
SS
17
All 11communes, except one in Kampong Speu,said that the CC/CCWCs used the SSM to
identify priorities in order to address the issues. Onecommune provided specific numbers of
prioritized households in 2009 and 2010, noting that 23 households prioritized in 2009 and 2010
received direct assistance whilesome 13 priority households in 2010 had not yet received support.
This informationshows that this commune targets new households every quarter to support the
vulnerable. The maps seem to help the communerespond to the needs of target families promptly
when sufficient resources were available.The commune‟s experience also reveals that support is
ad hoc and limited to a one-time provision of aid. Another example of how the map is used to
address an issue can beseen in Kampong Speu, where a village used it to identify families that are
affected by domestic violence. Once identified, the police or CCs made sure the husbands (who
committed violence) attended trainings organized by UNDP (see Box 1).
BOX 1: Benefit of SSM to other programme intervention
The CC/CCWCs in all 11communes except Kampong Thom used the SSM information to
prepare their community investment plans (CIP) in 2010. Based on the map, communes identified
some issues to include in the CIP. Among the many concernsidentified, violence, hygiene and
sanitation, and school drop-outs appeared in a number of communes. One commune described
how theissues that arose fromthe maps were brought to CCWC monthly meetings in order to find
solutions to address them.Ifthe issues were found to be too difficult to solve due to technical and
financial constraints, they were included in the CIP.For example, commune chiefs in a few
communes visited mentioned that lack of latrines is a challenging issue to solve on their own
because building such facilities requires technical skills and money to buy the proper materials.
While the communes‟ attempt to utilize the SSM is encouraging, UNICEF staff observed that
links between the SSM and the CIP were not systematic nor clear enough, resulting in a lack of
long-termplanning.
The SSM can, however,help planning at both the village and commune levels. Villages tend to
identify and prioritize households that are affected by a larger number of the 13 indicators so that
they can attempt toaddress issues according to the needs of each family. At the commune level,
on the other hand, specific indicators that affect more households than others are typically singled
out. Those indicators can then be incorporated into the CIP as an overall strategy.
Commune chiefs in two communes in Prey Veng explained that when they identified priority
issues inthe SSM, they contactedNGOs that had been operating in their communes for support.
They mentioned that the maps made it easier to share their concerns and present the data. This
example illustrates howthe SSM also helped to build confidence and stronger ownership among
communes and village leaders.
Overall, it can be observed that while communes and villages are willing to use the maps and are
starting to identify issues related to social services, they stillface challenges when trying to
incorporate the SSM information into long-term planning.
In the visited commune in Kampong Speu, the SSM data complemented and strengthened
strategies and activities launched by donors and/or government to assist the vulnerable.
For example, UNDP organizes a monthly training on domestic violence in some villages,
and the villages try to make sure that those people who have been identified as victims or
violators on the maps participate in them. As a result, the commune chief said that cases
of domestic violence seemed to have decreased and that the situation was improving.
18
Monitoring and assisting the vulnerable
The maps do not only identify social issues and target families, but also aim to help monitor
progress and changes as stated in step 5 of the Hip Pocket Guide for CCWCs. In the focus group
discussions, four communes commented that mapping enabled them to monitor progress and see
changes.Generally, these communes had already updated the maps at least once. This data shows
that the maps can be useful in monitoring identified targets over time when they are adequately
and periodically updated.
Though the SSM is a recent initiative, communes seem to have an idea as to how frequently the
maps should be updated in order for them to efficiently capture changes and be of the utmost use.
To date, seven communes have updated the SSM at least once. The frequency differed between
communes, but in four communes, updates were completed every six months. Of these, three
communes said that six-month updates were adequate. Six communes in total, including those
that had not updated the SSM, said that updates every half-yearshould be ideal. Two PFPs in
Kampong Speu interviewed during an additional field visit also agreed that every six months is
the ideal frequency. However, they also expressed concern about possible material, financial and
time constraints for the villages to maintain this schedule. In contrast, in Prey Veng, it has been
agreed to update the map every quarter. Similarly, in SvayRieng, communes were being
encouraged to update every three months.
In addition to update frequency, methods of recording data are issues to be discussed for quality
monitoring. It is essential that all villages keep initial data as baselines, be it the map itself or
records of figures. Though this may seem like a logical practice, some visited villages in
Kampong Speu, Prey Veng and SvayRieng had forgotten to date their maps.In these villages, the
commune chief presentedrecorded data from the first and second quarters, demonstrating that it
was easy and simple to track changes and progress in terms of the 13 indicators. Data was
recorded in a way that resembled the method introduced in the Hip Pocket Guide, which
highlights households affected by many indicators as well as indicators that are prevalent for the
entire village. Information from all villages was also stored at the provincial level, along with the
maps.
Suggestions/Recommendations
Practical guidance on how to use SSM to develop plan should be strengthened. This
requires stronger collaboration between village, commune, district and provincial levels.
At the commune level, a monthly reporting format should be established to allow changes
and progressin challenged households to be recorded. Many communes are already
conducting frequent home visits, which should be reported in some way. For example, a
checklist that includes a section to take notes on visitfindings could be introduced.
It is also crucial that communes link the SSM to the CIPs in order to appropriately
allocate funds for vulnerable households. Although all communes indicated that they
used the SSM information during 2010 CIP preparation, a UNICEF Seth Koma staff
member observed that the CCs were not using the SSM to plan long-term objectives but
rather for ad hoc support. Some commune chiefs in Prey Veng said that they tried to
contact NGOs, pagodas and other development organizations every month to seek
support for issues identified on the maps. Thus, while the communes should continue the
good practice of using the SSM to inform the CIPs, this link needs to be strengthened
with long-term objectives in mind. All stakeholders – UNICEF sections, provinces,
communes and villages – should be reminded that the map drawing is not an end in itself,
butrather aims to identify vulnerable families so that communes can allocate the budget
or generate additional support from NGOs, pagodas and private institutions to genuinely
support those in need.To assesshow strong the linkages are, UNICEF should select
sample communes and compare theirCIPs and maps.
19
UNICEF should encourage communes to establish systematic updates at two levels. First,
maps should be renewed in such a way that the timing aligns with CIP development and
commune data base CDB updates. CIPs are developed every June (process begins in
May)and the CDB is updated in December, so the maps should also be updated
aroundthese times. In this way, the latest SSM information can be available for the CDB
and CIPs. Updating along this schedule would simplify data collectionand help
streamline existing data.Furthermore, sincethe CDB is maintained by the Ministry of
Planningand is used to produce the poverty index for the allocation of investment funds
for communes, more unified data would enhance SSM mainstreaming. At the second
level, status of the SSM indicators should be monitored more frequently -- ideally, once
every quarter.
For better monitoring, all villages should record the date of map drawing and data entry.
Though this might sound like standard practice, a number of villages visited in Kampong
Speu, Prey Veng and SvayRieng did not date their maps. Such information would also be
helpful for users. It is important to explain to villagers why suchdates are necessary.
All provinces should be encouraged to compile copies of every village map in one place,
as was done in Kampong Speu. This good practice should be shared with all
provinces.Kampong Speu‟s method forenteringquarterly data can also be adopted by
others. Thus, at the provincial, commune and possibly village level, there should be
horizontal and vertical communication so lessons learned and good practices can be
shared.
CDB
Jan
Feb
Mar
Apr
CIP PROCESS
beginsCIPs
developed
Jul
Aug
Sept
Oct
Nov
Map
Review
Data
Entry Data
Entry
Map
Review
The SSM update cycle
20
To ensure the sustainable use of SSMs in villages, support for updating should be
considered. As one commune clerk indicated, time constraints are a challenge; a possible
solution might be the use of reusable stickers to put on the maps for indicators. Though
this would mean that the initial maps would be altered, communes would still maintain
figures collected in each quarter to use as baselines. For example, Prey Veng holds
quarterly district meetings on CCWC function, and it was suggested that the progress and
changes identified on the SSM be included in the meeting reports.
2.1.3 Lessons learned from the pilot implementation of the SSM for various stakeholders
In addition to the specific topics described above, there have been both positive and negative
lessons learned in general from the pilot implementation of the SSM.
Advantages
Overall, there have been a number of direct positive reactions or comments about the SSM from
the communes and villages, and positive effects could be observed from discussions and
questionnaires.
One advantage of the SSM was that by sharing information and speaking openly about other
families‟ conditions, asense of fairness was created among villagers. Before the SSM, some
villagers might have felt jealous or that it was unfair that only some people received special
support, but the visualized situations made discrepancies between households more transparent,
creating feelings of sympathy with neighbours.
Secondly, the SSM has made villagers more open to various issues and helped them realize the
importance of acknowledging them to improve lives. Eight of 11 communes answered that
awareness-raising campaignsaboutviolence would help address the reasons why some families are
in vulnerable situations. Benefits of schooling, health and sanitation, and general laws were also
seen to beimportant issues that should be promoted. While villagers and commune members have
to be very cautious about stigmatizing issues, buildingawareness through effective campaigns
could help eliminate/mitigate some of these problems.
Thirdly, communes felt thatthe SSM does help identify target families. All 11 communes agreed
that the SSM made it possible to spotand support vulnerable households. Also, four communes
feltthat the SSM made it easy to monitor development, changes and progress. This is a positive
sign because it shows thatcommunes and villages are now more informed of the issues affecting
their villages and feel a greaterresponsibility to face them. This createsastronger base for the
community that promotes community-based development.
Furthermore, as the SSM focuses on social issues, it helps CC/CCWCs promote their role in
strengthening social services. It was observed in SvayRieng that the mind set of CC/CCWCs in
terms of prioritizing issues has shifted from infrastructure to social sectors. Regular updates also
encourage them to pay more attention to vulnerable families and to work in the field more. In
Prey Veng and SvayRieng, the P/DFPs reported that CC/CCWCs are visiting villages more
frequently. As the SSM improves, the role of CC/CCWCs will become more distinct and could
help them more deeply engage in working forthe social welfare of people.
Lastly, as briefly mentioned it was observed that the SSM restored the confidence of leaders at
the commune and village levels and inspired them to improve the situations of their people due to
the sense of ownership promoted by the mapping exercise. While identifying the root causes of
the issues remains a challenge, it is a positive step for local leaders to be able to visualize the
village situation and the issues that need to be tackled.
21
Disadvantages
As already mentioned in the participation section of this report, there is a risk that certain voices
are not being heard. In Cambodian villages, a participatory approach can be a novel concept and
it is inevitable that some people will adhere to hierarchical tradition. Specifically, the quality of
participation in drawing the map (step 2) could be disappointing if pre-meetings, during which
drawing participants are identified, are not well organized.Women, children, youth and even men
without prestigious jobs or titles may be at a higher risk of being ignored.
Secondly, as mentioned in the process section of this report, some communes and villages
perceive developing and having the maps at hand as their final objective. However, the ways in
which they effectively and efficiently use the maps to address the issues is more important. It is
therefore essential to convey the importanceof not only drawing, but also making use of the maps.
Thirdly, the capacities of those involved in the exercise are very limited, which might affect their
ability to conduct the exercise and react to unexpected challenges. For example, as CCWC
facilitationskills are lacking, they may be ill prepared to deal with issues that have not been raised
before,even if theseissuesare critical to children and women‟s rights.
Lastly, there were communes that expressed concern about the maps being difficult to preserve
due to dusty environments or the lack of proper materials. A few communes requested plastic
covers or computer-based maps.
Suggestions/Recommendations
As the SSM helps to promote confidence and responsibility at thesub-national level, it
has thepotential to further empower the CC/CCWCs and village and commune leaders.
UNICEF should enhance this practice by stressing the fact that local leadersshould feel
comfortable taking initiative in future SSM activities and making improvements to the
maps. At the same time, all UNICEF staff should be aware of the hierarchy culture and
thepotential impact of their presence. It is important for us to be sensitive and step aside,
focusing on facilitation andnot decision-making.
For all stakeholders, there should be regular update/refresher workshops or training
sessions to maintainmotivationand build capacities. Study tours to other provinces could
be organized to observe what others are doing and illustratesuccessful work.
For the villages to improvethe map‟s physical integrity, protective plastic covers should
be used. When stored, the maps should be kept from direct sunlight to preserve the
colours.
2.2 Inputs from Users
As illustrated in Annex 2, there were six user groups identified in four provinces for interviewing.
As SSM is a new tool, the assessment team met difficulties in identifying user groups (NGO or
provincial Departments). The six identified users provided useful insight on user perspectives.
22
Usefulness and relevance of the SSM
Six users of the SSM, mainly NGOs, were identified and interviewed in six communes in four
provinces: Prey Veng, SvayRieng, Kampong Speu and Stung Treng. They all said that they were
aware of the existence of the maps in the villages they support.
The majority of them acquired information about the maps from either the village leaders or the
commune chiefs. Considering that development organizations are likely to first go to a village
chief when starting activities in a village, it seems as though keeping the map in the village
chief‟s home is the most logical. Nine of 11communes do this.
Most respondents did not only use the maps to gather information, but also to identify target
families. In this regard, the SSM is well received and its objectives are understood among users.
Users had some positive comments to share. One mentioned that s/he could perceive the progress
on the indicators in a “transparent” manner. This map belonged to a commune that updated their
map every three months, further illustrating the importance of regular map updates to enable
development agencies to monitor progress. The fact that the map is drawn and updated in a
participatory manner gavethe user a sense of transparency and accountability. Another user said
that s/he could get more information from the SSM and that it was easier to use than other maps
created by NGOs. Other users felt that the maps provided very clear and quick information,
suggesting that the maps led to more efficient work. While these comments applaud the SSM for
its quality in terms of content and structure, they alsoimply that users are looking for as much
clear and quick information as possible to provide aid more efficiently and effectively.
While this group of NGOs expressed that the maps are useful, there were also some negative
observations in feedback reports after the assessment. According to reports in Stung Treng, the
team wasinformed that there was no NGO using or interested in the SSM in the particular
commune where they tried to approach a user. Similarly, inOddarMeanchey, the team found that
NGOs have been made aware of the SSM, but have not used yet one. The findings show that
information is not well disseminated to encourage all stakeholders to make use of the maps. In
Kampong Speu, despite efforts by the province to store all maps at the provincial office, most
development partners have not been informed about their existence. During the discussion, one
village chief said that one NGO working in the health sector asked for copies of the maps, but had
not been contacted since obtaining them. This incident reveals that there is a lack of cooperation
between development institutions and villages and a lag in ownership of villages and communes.
Overall, these findings also indicate that the SSM is potentially useful when trying to address
issues. However, due a lack of harmonization between stakeholders, there is a risk that the maps
will be valuable in theory only.
Despite the fact that the users found the SSM “useful,” the indicators did not appear to be very
“relevant” to the issues they are trying to tackle. Only two users of six said that some of the
indicators were related to their activities, and two answered that none of the indicators were
related to their work. This is a predictable result since these organizations‟ activities are often
focused on either very specific themes or broad areas that cut across different indicators. For
example, one of the users that said that no indicators were illustrative is a health-related NGO that
targets families with “specific health problems.”
Suggestions/Recommendations
Because the interview sample is so small, results should not be overgeneralized. However, in
order to improve the effectiveness and quality of the SSM, it is integral to consider incorporating
users‟ inputs into the current system, to encourage users to be more involved in the SSM process
and to promote the maps‟ use.
23
If relevance is an issue, users could be invited to map drawing or other related meetings
(separate meetings might also work) so they can improvethe maps from a user‟s point of
view. In Kampong Speu, some NGOs saidthat they would like to add specific indicators
on the maps. A user in one commune said that s/hewould put additional information
about the NGO‟sactivities onto a copy of the SSM. In this way, the maps can adjust and
become more relevant to each village. Also, with villagers leading these meetings, the
recipient-provider relationship could change, resulting in more cooperative practices and
more villager ownership.
Though the six organizations identified and interviewed were aware of existence of the
maps, field visits revealed that there were more organizations that did not know about the
maps. It has been less than two years since the implementation, so it is understandable
that the news has not yet been widelydisseminated. One solution would be to invite
provincial-level NGOs to a meeting or workshop that would highlight the usefulness and
effectiveness of the maps.
Distributing related materials like the Hip Pocket Guideor a training manual to users
would give the mapsmore accountability and could attract theattention of users. Provinces
should also compile and store copies of all village maps so that the users couldmore
efficiently access this information at the provincial level. This practice is already in place
in Kampong Speu.
A more systematic relationship between users and developers (province, commune and villages)
of the maps needs to be established. Users must be informed of the maps‟ existence and
usefulness.
2.3 Inputs from supporters
Interviews were carried out with a supporter group who had assisted in the development and use
of the SSM, consisting of PLAU officers, P/DFPs and/or P/DFTs in each ofthe six provinces.
This set of interviews aimed at assessing the quality of the trainings received as well as trainings
they conducted for the CC/CCWCs.
SSM trainings for supporters
All supporters found the training entirely or partially easy, although supporter groups in two
communes found a few points to be challenging. Some comments provided by the communes that
found the training easy were very passive, such as, “It is easy because it was a pilot and the
training was not the real training,” and, “It was the discussion and orientation by the consultants.”
Responses that said the training was challenging were about the procedures: “It is not so easy
because steps 3 to 5 are difficult in the training,” and “It is not so easy because the table for
commune workplan is difficult to understand.” These comments encourage us to modify the
guidelines, manuals and training procedures so as to be more user-friendly.
When asked if they need to have a refresher training to support the SSM process, all six groups
answered “Yes”. One commune stated that they should have a follow-up session because they did
not clearly understand all the points. Two other communes implied that the training was too short
(suggesting a seven-day training instead) and that the facilitator was going too fast and using
methods that were too complex. Furthermore, supporters in OddarMeancheyinformed the
interviewers that there was no official provincial level training for them, so only onePFP attended
the training.He was the only person who coordinated and conducted the training for CC/CCWC,
without any support from the DFP or P/DFTs. Taking these points into account, the length and
methodologies might need to be reconsidered and adjusted.Trainingsshould also be organized at
the provincial level with mandatory participation. In contrast, one commune realized that the
24
refresher should help “mainstream the process and importance of the maps among the sectoral
departments and development partners.”
Support provided to CC/CCWC and villages
All interviewed supporters in the six provinces found the training they conducted for CC/CCWC
to be not so easy. The most common concern was capacities of CCs/CCWCs in understanding the
concepts and contents of the SSM. Specific comments included: “Some of the contents are
difficult to understand,” “Participants‟ capacities were limited,” “No clear understanding in
benefits of the maps,” and “Difficult terms.” Others worth mentioning are, “Participants did not
share their ideas,” and “New topics for them.” As explained in the participation section of this
report, it is possible that the CC/CCWCs were afraid to speakup in front of supporters who were
higher in the hierarchical order. But the same commune also noted that the training was not easy
because of “new topics for them,” so the CC/CCWCs might have been unable to learn the new
concepts in such a short time. Also, a lack of adequate support was voiced: “Practical
exerciseswould help to understand” and “No support from P/DFPs.” Lastly, there were supporter
groups that raised concerns about certain indicators: “Difficult to understand indicators 11 and 13
because they seem to overlap,” and “Difficult to monitor indicator 11.” In terms of the training
conducted for the CC/CCWCs by supporters, further adjustments and improvements seem
necessary.
Given the supporters‟ concernfor the CC/CCWCs‟ lack of capacities, it is also important to
consider the supporters‟ facilitation skills. To encourage participation and instruct people on new
concepts requiressignificant facilitation experience. The fact that the map introduces new
concepts even for supportersmakes it even more challenging.
In addition, the assessment team that visited Stung Treng learned that the CCWCs had received
technical and financial support from provincial and district levels separately during the SSM
development in 2009. While PLAU allocated a budget for provincial training only, the Provincial
Department of Planning allocated funds to cover development of the SSM at the village level.
These different mechanisms of support created some confusion as to who would follow-up after
completion of SSM development. The Stung Trengcase indicates that responsibilitiesand roles
among the various stakeholders are not clearly defined.
The training to commune/village was seen as “not so appropriate” by four out of six supporter
groups. One of the main reasons cited was that the training was too short. Another prime reason
was again capacity and competency; one commune felt “a number of points are difficult for
commune and village leaders” and “CC/CCWC members have different knowledge and skills.”
Also, capacities of facilitators to conduct the training need improvement since they felt it was
“difficult to explain the 13 indicators” and there are “too many documents.”
Suggestions/Recommendations
One supporter group recommended a longer period for the trainings they received. They
felt that a one-day course with a one-day exercise was too short to absorb all the
information. The suggested length was threedays. On the other hand, since supporters as
well as CC/CCWCs facetime constraints, it might not be feasible to make the training
longer.Materials could however be revisited, removing unnecessary contents so as to
simplifythe trainings. The training could also be broken down into shorter segments and
conducted over the course over several days. The same can be said for training for
commune/villages. Supporter suggestions ranged from three to seven days, but the
adequate period should be discussed with trainees and trainers.
Supporters in one commune suggested that there should be more
awarenessraisingamongCCWC members. In order to communicate the importance of the
25
SSM, it is recommended to review the exercise in monthly meetingsto emphasize the fact
that the mapping is not simply an ad hoc experiment. They could also use the annual
meetings as an opportunity to makea presentation on the SSM.
In order to avoid the confusion observed in Stung Treng, roles/responsibilities of all
involved in provincial and district departments should be discussed and decided on.
These should include how and who will deal with all financial and technical support for
CCWCs/CCs before/during/after the SSM development.
Inregard to capacities, the Department of Planning specializes in analyzing/formulating
development plans and monitoring implementations. It could contribute to the
improvementof the capacity of P/DFPs or CC/CCWCs in data analysis. This might have
to wait for the new provincial structure in 2011, but MoI should nevertheless establish
systematic training sessions.
3 RECOMMENDATIONS 3.1 Recommendations based on the interviews, questionnaires and discussions
Based on the findings and information gathered during the assessment, there are a few more
recommendations that should be mentioned:
A supporter group in one commune commented on the size of villages, which can be
quite varied: small villages generally consist of50 households, while large ones might be
as large as400 households. The supporter groups suggested that it would be better to
firstdrawmaps forsmaller villages, indicating that in larger villages, it could be more
challenging to collect data or gather participants. When a village is as large as 200 or
more households, it might be useful to divide the map intwo during thedrawing phase.
This could ease the issue of meeting and discussion sitesbeing too far for participants.
In terms of the assessment process itself, Stung Treng reported that communication
between the province, district and commune was not conveyed clearly, which affected the
selection of beneficiaries in accordance withthe SSM indicators. Furthermore, the
respondents noted that some important figures missed the discussion; some of them did
not even providereasons for their absence. The assessment team responded: “Such an
event does not happen very often, so P/DFP needs to discuss with communes and
prioritize it as a special event to be put into their work plans.”
The feedback report from SvayRieng points out: “There should be more questions related
to achange in the situation of children in these families.” The analysis would allow the
team to assess the SSM‟s impacts on villagers, especially vulnerable children.
The most difficultchallenge is capacity building. Refresher trainings and regular updates
should help improve skills. In addition, study sessions in participatory approaches,
facilitation and decentralization could help leaders from the provincial to the village level
become aware of the important concepts and improve their capacity to lead meetings.
When maps and indicator data are updated, it should be recommended to also record the
kind of support each household receives in order to avoid duplication of assistance. When
different development agencies operate in the same village, there is a risk of uneven and
unfair distribution of support, with households with more evident issues receiving
duplicated support. To enhance equity, the communes could ensure that the whole picture
of distribution of support is reflected during data entry.
26
3.2 Recommendations from meetings with UNICEF staff and other development partners
After the assessment, follow-up meetings and discussions were held to come up with practical
future steps to be taken to further the use of the SSM.
The guidelines should be amended so that they include statements to remind CC/CCWCs
and villagers to use the SSM with other data, such as ID poor families and the CDB.
Young people are perceived as akey source of information, so the guidelines should
indicate the ideal percentage of youth participation in the mapping to remind and
encourage the CC/CCWCs and village leaders to include them. For the purpose of
revising all the SSM materials and documents, UNICEF should recruit a consultant.
Young people shouldplay a significant role in sustaining and disseminating the tools. It
was also suggested that the commune/villages collaborate closely with schools to
organize occasions where youth participants could present and share their experiences in
discussions and meetings with other students.
There have been various suggestions as to how to disseminate and promote wider use of
the SSM among different organizations. One suggestion was that there should be a
national level workshop where the SSM is presented to all line departments, international
organizations, NGOs and other relevant partners in coordination meetings led by
WCCCS. At the sub-national level, for example, SvayRieng holds monthly NGO
meetings that can be an opportunity for CC/CCWCs to share their experiences. In
summary, whenever there are meetings at different levels with national or sub-national
departments and development organizations, efforts should be made to allot time for a
SSM presentation. Another suggestion is to prominently display a sample of the SSM at
commune officesso that when development partners visit these offices for information,
they will become aware of the existence of the maps. Commune offices should also post a
brief explanationof the SSM and how copies can be obtained.
The analytical skills of CC/CCWCs and villagers should be improved. They should better
understand the ways in which data is interrelated to assist them in tackling the underlying
causes of a number of issues. The analytical process in the guidelines can be used as a
guide in capacity building.
All the maps should indicate location of service providers,including volunteers, NGOs,
police stations, chiefs‟ houses, clerks, schools and health centres, even if they are located
offof the map, so that users of the maps easily know where to go. They could illustrate
the distance and directions toservice providers that villagers and users can access.This
would not only make the map more effective for users, but also better reflect the name of
the tool,Social ServiceMapping.
27
Sample of Social Service Mapping showing service providers
Updated on Jan. 11, 2011
Communes should be encouraged to start putting aside a portionof the commune annual
development fund to use for social sectors that are highlighted in the SSM.
In SvayRieng, although health centre staff cannot participate in the meetings in every
village, they provide inputs to every village before finalizing the maps. This good
practice should be encouraged in other provinces.
Finally, UNICEF might need to hold further meetings to discuss the suitability of the list
of 13 indicators. As mentioned earlier, some indicators might need to be clarified,
elaborated, added or taken out. Also, each indicator should be clearly stated so that all
stakeholders can easily understand its meaning. Annex 3 include suggested changes made
to the list of indicators.
4 CONCLUSION
While a number of challenges still remain, the SSM has made positive impacts on the
wayscommunes and villages perceive and provide support to people.
Overall, the most positive achievement of the SSM pilot implementation is that the tool played an
important role in shifting many key actors‟ attention from infrastructure to social sectors,
especially at the commune and village levels. The tool helped them realize the importance of
focusing on individual vulnerable people and families. As the quality of the maps differs from
commune to commune and village to village, overgeneralization shouldbe avoided. The SSM,
however, while needed to be improved, seems to help leaders at village and commune levels
focus on how and what issues they should prioritize. The SSM also seems to positively impact
commune and village leaders‟ attitudes, as they gain confidence when put in the position of
explaining the situations of their communitiesto others. In turn, this confidence seems to create a
sense of responsibilitytoseek necessary support for the poor and encourage leaders to contact
Indicators
1
.
.
.
.
13
School
Health Centre
1
5
1.5 km E
2.0
km
S
pagoda
28
relevant assistanceagencies. Furthermore, visualizing the village‟s situation in the form of a map
helps the key actors acknowledgethe coreissues to be tackled and identify the most vulnerable
families.
On the other hand, some challenges need to be addressed to improve future interventions: 1.
Increase the capacities of key actors who develop the maps, 2. Improve coordination of different
tools, and 3. Bolster dissemination of the SSM to different development partners.
1. Interviews with supporters as well as UNICEF staff involved in the SSM exercise
showed concern about CC/CCWC and villager capacities in understanding the new
concepts (including indicators) and SSM process. It is crucial for CC/CCWCs to fully
understand the purposes and procedures of the SSM, for they are in charge of conducting
the exercise at the village level and of monitoring. In order to maximize usage of the
materials, UNICEF should amend them to accommodatethe capacities of the users.
Specifically, the Hip Pocket Manual should be simplified so that CC/CCWCs can easily
follow the instructions while conducting the exercise in the field. Close consultations
should be also made with CC/CCWCs and P/DFPs to identifytheareas that are difficult to
understand and how they can be improved. In short, all the manuals and guidelines
should be more user-friendly. Furthermore, capacity building, especially in facilitation
skills, needs to be enhanced throughclose collaboration with line departments.
2. Different data sources are currently used to identify the poor and vulnerable and do not
complement each other well. In order to avoid duplication of indicators, the SSM should
better complement the CDB and ID poor so that the information can be more effectively
used in CIPs. To strengthen coordination of the tools and link with the CIPs, timing of the
SSM updates should be aligned with development and annual updates of CIPs and CDB.
Village maps should be renewed in June and December, when CIPsaredeveloped and the
CDB is updated, respectively. As ID poor list of beneficiaries isonly updated biannually,
the SSM information can help assess the situations of equity card recipient families.
3. Dissemination is also a key factor that could improve the SSM‟s effectiveness and
usefulness. At this point, the maps have not been widely used by development partners.
In order to spread the word about the SSM, key stakeholders should try to
makepresentations at different levels, illustrating the tool‟s usefulness and effectiveness.
Better coordination among stakeholders is necessary to mainstream and strengthen the
map.
While taking the next steps to improve SSM implementation for future interventions, it has to be
kept in mind that concepts such as participation, stigma and confidentiality have been newly
introduced to rather traditional Cambodian villages.CC/CCWCs should be encouraged to
carefully follow-up on sensitive issues. UNICEF should also be aware that sub-national officials,
including CC/CCWCs and P/DFPs and even village leaders, can be empowered and their
capacities developed.
Finally, this SSM tool is potentially useful and effective inidentifyingand better targeting
vulnerable people, especially children and women. In order to make the most use of the tool,
working in harmony with different stakeholders will be increasingly important. And, with
improvements, this initiative can help to operationalize UNICEF‟s priority, “equity” in providing
support to the most vulnerable.
5 ANNEXES
Annex 1- Original and Revised Indicators
Indicator
No. Original
New
No. Revised/New
1 Household with under-one-year old children who have
NOT been registered. 1
Household with children who do NOT have a birth
certificate.
2 Household with one-year old children who have NOT been
fully immunized. 2
Household with one-year old children who have NOT been
fully immunized.
3 Household with pregnant women who have NOT accessed
health services. 3 Household with pregnant women who have NOT made an
antenatal visit to a health clinic.
4 Household with 3-5 year-old children who do NOT attend
preschool. 4
Household with 3-5 year old children who do NOT attend
preschool.
5 Household with 6-11 year-old children who do NOT attend
school or have dropped out of school. 5
Household with 6-11 year old children who do NOT attend
school or have dropped out of school.
6 Household with 12-14 year old children who do NOT
attend or have dropped out of lower secondary school.
7 Household with children involved in harmful and
hazardous work.
6 Household with NO access to clean water. 8 Household with NO access to safewater.
7 Household with NO latrine. 9 Household with NO latrine.
8 Household with orphan(s) or abandoned children. 10 Household with orphan(s) or abandoned children.
9 Household with children living with chronically ill parents
or care-givers. 11
Household with chronically ill family member.
12 Household with malnourished children.
10 Household with children with disabilities. 13 Household with mentally or physically challenged children.
11
Household with children who have been exposed to and/or
directly impacted by violence or abuse (migration, rape,
child labor).
14 Female-headed household.
12 Household which have poor ID cards. 15 Household with ID poor cards.
13 Household which have youth involved in gang and/or drug-
related activity.
30
Annex 2- Questionnaire
Updated on 19 July 2010
Internal assessment of social service mapping in 2010
Questionnaires for focus group discussion
Name of interviewer: Telephone #
Date of data collection:
Province:
District:
Commune:
Village:
Members of FGD:
CCWC members:
Commune chief:
Commune 2nd Deputy chief
CWCFP
Clerk
Teacher
Health centre staff
Village chief/s
Village vice-chief
Village assistant
Others: ..................................................................................................................
31
1 To assess the process to develop SSM # village
1.1 How many villages in the communes?
How many villages had drawing SSM maps in the commune?
Note: interviewer asks village chief to show the SSM (map) that had been drawn and take photo)
1.2 SSM process:
1.2.1 What did CC/CCWC prepare in advance for drawing the SSM? (step 1) Please tick below if yes:
CC/CCWC organizes a pre-meeting to share responsibility
Village chiefs inform villagers about the timing to draw SSM
Draw a preliminary map
Prepare objectives of drawing the map on a flipchart
Prepare materials for drawing the map
Other activities, please specify:
Prepare schedule, dates, organize pre-meeting with village leaders to preliminary draft the
village map, look at existing maps
Note: Look at existing map on the household coding, such as school map, census map, etc.
1.2.2 Developing the SSM at village level: (step 2)
The steps for drawing the maps Please tick below if yes:
a)Greet and introduce participants
b)Explain the objectives of SSM
c)Discuss the indicators
d)Present the draft map and begin the discussion
e)Finalize and endorse the map with all participants
How many sensitive issues such as domestic violence/abuse/illness discussed?
How were these families identified? Was this done separately or with the whole group?
Were any measures taken to protect the privacy of the families in question?
Were families in the mapping process consulted?
Participants: ...................................................................................................................
Other activities: if yes, please describe: ..........................................................................
1.3 Number of participants in the drawing process:
Who was invited in the process to develop the map?
Why were they selected?
How did you ensure women participated?
How many women participated?
How was it ensured that the poor participated (have Id Poor card)?
How many poor households participated?
Did SSM bring change to community? Such as division, fragmentation, or stigmatization in the
community?
1.4 Participants as key informants in the SSM development/drawing map Please tick
Village chief, deputy chief, assistants
Village elderly people
Youth representative
Village health support group (VHSG)
32
Schoolmaster, teacher
Health centre
Community/villagers
Others (please describe): in a number of villages, the monks also participated in the process.
Note: Representatives from rich and poor, men and women (at least 30% of the population)
1.5 Any indicators that you have added while drawing SSM map? Please tick
Yes No
if NO, which ones are complicated? please indicate:
1.6 Any indicators that you have added while drawing SSM map? Please tick
Yes No
If yes, please describe:
1.7
Do you think that you want to add anynew indicators that are relevant/associated with the real
issues in the village, if you draw the map in the future? If yes, please describe from the most
relevant to worst? Please tick
Yes No
If yes, please describe: Indicator related to the poor families that have no/less food more than six
months.
1.8
Do you think that any indicator is not relevant/associatedwith the real issues in the village? If
Yes please describe from the most relevant to worse? Please tick
Relevant Not relevant
If, no, please indicate which are the indicators in the boxes below: Please tick
1. Household whose children (under 30 days old) have NOT had birth registrations yet.
2. Household whose one-year-old children have NOT had 7 vaccinations.
3. Household with pregnant women who have NOT accessed health services.
4.Household whose 3- to 5 year-old children have NOT attended preschool.
5. Household whose 6- to 11-year-old children have NOT attended school or have dropped out
of school.
6. Household that does NOT have access to clean water for drinking and domestic.
7. Household that does NOT have a latrine.
8.Household thathas orphans or abandoned children.
9.Household thathadchildren living with chronically ill parents or caregivers.
10.Household thathaschildren with disabilities.
11.Household with children who have been exposed to and/or directly impacted by violence or
abuse (migration, rape, child labour)
12.Household thathasID poor cards.
13. Household thathasyouth involved in gang and/or drug-related activity.
Please describe the reasons:
II Assessing the usefulness and effectiveness of the SSM
33
Guiding questions for map analysis
2.1
Did CC/CCWC had been used the SSM to identify the priority in order to address the issues?
(Step 3) Please tick
Yes
No
If yes/no, please go to question ….
2.2 How CC/CCWC set or identify the priority issues?
Please describe:
2.3 Has the CC used the SSM for the CIP this year? Please tick
Yes No
If so, which activities in the CIP address SSM identified issues?
2.4 Has the CC used the SSM for another planning process? Please tick Yes and no
Yes No
If yes, what issues? Which planning process?
2.5 Using map to assist CC/CCWC to monitor the targets identified in the maps Please tick
Yes No
Does any sector department or organization use the map?
If yes, please describe
2.6
Map used for monitoring: to monitor the progress of solving the issues in each household and the
progress of the indicators
2.6.1 Did CC/CCWC update the SSM? Please tick
Yes No
If yes, when? Please tick
Once a month
Every 3months
Every 6months
Every 12 months
Please specify:
2.6.2 How often does the CC/CCWC want to update SSM? Please tick
Once a month
Quarterly
Every 6months
Every 12 months
2.6.3 Who participate in the process of updating the map?
Please describe:
2.6.4 Where did you keep the map? How? Please tick
House of village chief
House of commune chief
Commune office
Village meeting place
Other places: ..........................................................................
Please describe the reason:
34
2.6.5
Who can see the map? (There are privacy/confidentiality issues; can anyone just see the map or
only a few people?
2.7 CC/CCWC support
2.7.1 How many families receive support from CC/CCWC? Please tick
Yes No
What kind of support?
2.8 Which resources doesCC/CCWC use to support the vulnerable? Please tick
Commune fund
Please describe the service:
Sectoral budget
Please describe the service:
IO/NGOs
Please describe the service:
Generous people
Please describe the service:
2.9 General questions
2.9.1 What have you learned about families in vulnerable situations from doing the mapping?
2.9.2
What awareness-raising campaigns do you think would help to address the reasons families are
in vulnerable situations?
2.9.3
Do CC/CCWCs have any recommendation on the preparation and process to prepare SSMs in
the future?
2.9.4 What is the linkage between Prakas on Alternative Care (testing) and SSM?
Other important information:
35
Annex 3: List of participants from focus group discussions, interviewed users and supporters
Prey Veng SvayRieng Kampong Speu Stung Treng OddarMeanchey Kampong Thom
Focus group discussions
CCWC members, commune
second deputy chief,
CWCFP, clerk,
teachers, health centre staff, police, village chief, village vice-chief, village
assistant
CCWC members, commune
chief, commune
second deputy chief,
CWCFP, clerk,
teachers, health centre staff, police, village chief, village vice-chief, village
assistant
CCWC members, commune
chief, commune
second deputy chief,
CWCFP, clerk,
teachers, health centre staff, village
chief
CCWC members, commune
chief, commune
second deputy chief,
CWCFP, clerk,
teachers, health centre staff, village chief, village
vice-chief
CCWC members, commune
second deputy chief,
CWCFP, clerk,
teachers, police, village chief
CCWC members, commune chief,
commune second deputy chief,
CWCFP, clerk,police, village chief, village vice-
chief, village assistant
CCWC members, commune
chief, CWCFP,
clerk, teachers,
police, village chief, village
vice-chief
CCWC members, commune
chief, commune
second deputy chief,
CWCFP, clerk,
teachers, police, village chief, village
vice-chief
CCWC members, commune
chief, CWCFP,
clerk, health centre staff,
police, village chief, village vice-
chief
CCWC members, commune
chief, CWCFP,
Clerk, teachers,
health centre staff, police, village chief, village vice-chief, village
assistant
CCWC members, commune chief, commune second deputy
chief, CWCFP, clerk, police, village chief, village vice-chief
Commune
An
gko
r Tret
Kam
po
ng
Leav
Sp
eu K
Sam
bo
ur
Praso
ut
Prah
Po
nlea
Tan
g K
rou
ch
Dam
bo
ukR
ou
ng
Sam
Kh
uo
y
Preah
Bat
Stu
ng
Tren
Ko
rk Mo
rn
Lu
mT
orn
g
Ach
ar Leak
Village
Ko
rk
Ru
sseiTh
lork
Svay P
ork
Sp
eu L
ech
Ka L
ei Kh
ang
Tb
on
g
To
ulA
ng
kup
Po
rTh
ivon
g
O D
o A
n
An
gT
amao
O'K
orki
Dam
nakT
rach
Mean
Ch
ey
Ba D
erm
Sam
Kh
uo
y
Kain
gM
emay
Sp
ean T
hm
or
Ko
rk Mo
rn
Kan
hC
hrieb
Lu
mT
orn
gT
hm
ey
O'K
orkiL
eur
Ach
ar Leak
Krach
ab
Supporters PLAU officers, PDFPs, P/DFTs PLAU officers, P/DFPs, P/DFTs PLAU officers, P/DFPs, P/DFTs PLAU officers, P/DFPs, P/DFTs PLAU officers, P/DFPs, P/DFTs PLAU officers, P/DFPs, P/DFTs
Users
Action on D
isability and D
evelopment (A
DD
; UK
development agency)
Cam
bodian Children A
gainst S
tarvation and Violence
Association (C
CA
SV
A; local
NG
O)
Pen S
ovanny, PoS
AV
Y
NgounP
heoun
Lutheran World F
ederation C
ambodia (LW
S;
international NG
O)
MlobB
aitong (local NG
O)
Beneficiaries (26)
2 2 2 2 2 2 2 1 1 2 2 2 1 1 2