A Presentation on Bored Cast-in-Situ Piles

Embed Size (px)

Citation preview

Page 1: A Presentation on Bored Cast-in-Situ Piles

Welcome

Page 2: A Presentation on Bored Cast-in-Situ Piles

A Seminar on the Basis of the

Construction of Bored Cast-in-Situ Piles

Subham Kundu (CE - 33)Subhankar Karmakar (CE - 34)Supriya Chowdhury (CE - 35)

IMPS College of Engineering and Technology, Malda.

Page 3: A Presentation on Bored Cast-in-Situ Piles

Content: INTRODUCTION TERMINOLOGY PILE CLASSIFICATION GENERAL DESCRIPTION OF WORK WORKMANSHIP PILE COMPRESSION LOAD TEST BY KENTLEDGE SYSTEM EXECUTION OF CONSTRUCTION WORKS AT SITE PICTURES PILE CUT OFF, EXCAVATION AND CLEAN-UP

Page 4: A Presentation on Bored Cast-in-Situ Piles

THE EQUIPMENTS OF PILING VERTICAL PILE LOAD TEST (INITAIL AND ROUTINE) (COMPRESSION TEST OF CONCRETE) CUBE TEST THE SLUMP TEST OF CONCRETE FINENESS MODULUS TEST FOR COARSE AGGREGATE REQUIREMENTS OF DRILLING MUD (BENTONITE) CONCLUTION REFERENCES

Content:

Page 5: A Presentation on Bored Cast-in-Situ Piles

Introduction: Classification based on the function Classification based on material and

composition

Page 6: A Presentation on Bored Cast-in-Situ Piles

Terminology: Bored Cast In-situ Pile Cut-off Level Diameter of Piles Factor of Safety Initial Load Test Initial Test Pile Load Bearing Pile Pile Spacing Routine Test Pile Safe Load Ultimate Load Capacity Working Load Working Pile Negative Skin Friction or Drag down Force

Page 7: A Presentation on Bored Cast-in-Situ Piles

Pile Classification:

Main Functions of Piles – End Bearing (left) and Friction (right)

Page 8: A Presentation on Bored Cast-in-Situ Piles

General Description Of Work:

Location Piling Work Materials Dewatering Back Filling Power and Water Period of Completion

Page 9: A Presentation on Bored Cast-in-Situ Piles

Workmanship: Control of Piling Installation Use of Drilling Mud Cleaning of Borehole Tremie Concreting Defective Pile Recording of Data

Page 10: A Presentation on Bored Cast-in-Situ Piles

Pile Compression Load Test by Kentledge System :

General Frequency Prerequisite Method

KENTLEDGE

Page 11: A Presentation on Bored Cast-in-Situ Piles

Section view of Tension Test Setup using reaction pile and a Hydraulic jack

View of Tension Test Setup system

Page 12: A Presentation on Bored Cast-in-Situ Piles

DIAL GUAGE HYDROLIC PUMP TESTING PILE

Page 13: A Presentation on Bored Cast-in-Situ Piles

Execution of construction works at site :

Preliminary Works Piling Work Steps of Piling

Page 14: A Presentation on Bored Cast-in-Situ Piles

RIG(TRIPOD WITH WINCH)

Page 15: A Presentation on Bored Cast-in-Situ Piles

BAILERCASING

Page 16: A Presentation on Bored Cast-in-Situ Piles

DMC PIPES CHISEL

Page 17: A Presentation on Bored Cast-in-Situ Piles

TREMIE PIPE REINFORCEMENTS

Page 18: A Presentation on Bored Cast-in-Situ Piles

HYDROMETERHOPPER

Page 19: A Presentation on Bored Cast-in-Situ Piles

COVER BLOCKCONCRETE MIXING MECHINETOTAL STATION

Page 20: A Presentation on Bored Cast-in-Situ Piles

Pile Cut Off, Excavation And Clean-up:

Pile Cut off Level Excavation Cleaning of Work Site

PILE CUT OFF

Page 21: A Presentation on Bored Cast-in-Situ Piles

The Equipments Of Piling : Reinforcements (Stirrups & Stiffeners) DMC Pipes Development Length & Lap Length Tremie Pipes Chisel Bailer Casing Hopper Cement & Admixture

Page 22: A Presentation on Bored Cast-in-Situ Piles

REINFORCEMENTSStirrups & Stiffeners

Page 23: A Presentation on Bored Cast-in-Situ Piles

DMC PIPESTREMIE PIPES

HOPPER

CHISELBAILER CASING

Page 24: A Presentation on Bored Cast-in-Situ Piles

Vertical Pile Load Test (Initial & Routine) :

Definition Process

Page 25: A Presentation on Bored Cast-in-Situ Piles

TEST PILE

PILE LOAD TEST

LOAD vs SETTLEMENT GRAPH

Page 26: A Presentation on Bored Cast-in-Situ Piles

Compression Test Of Concrete (Cube Test) :

Aim Equipments Procedure Precaution Information Results Judgments

UNIVERSAL TESTING MACHINE

Page 27: A Presentation on Bored Cast-in-Situ Piles

CONCRETE CUBES CUBE MOULDS

Page 28: A Presentation on Bored Cast-in-Situ Piles

The Slump Test Of Concrete : Aim Equipments Procedure Precaution Information

True Slump Shear Slump Collapse

Results Judgments

SLUMP CONE

Page 29: A Presentation on Bored Cast-in-Situ Piles

MEASUREMENT OF SLUMP SLUMP CLASSIFICATION

Page 30: A Presentation on Bored Cast-in-Situ Piles

Fineness Modulus of Coarse Aggregate :

Aim Equipments Procedure Precaution Information Results Judgments

Sieve

Page 31: A Presentation on Bored Cast-in-Situ Piles

Requirements Of Drilling Mud (Bentonite):

Properties Functions Requirements

BENTONITE

Page 32: A Presentation on Bored Cast-in-Situ Piles

Conclusion: Bored Cast in situ piling is favourable than other piling

processes. Because there is no waste of time and materials so it is economical and can be cast into exact length. It can bear heavier load and transfer it to the ground soil. Also the transportation cost is not high.

It is not necessary to reinforce the pile in normal cases or in places where the pile is completely submerged in the soil. But for more stability and durability of structure we use reinforcement. Over all, Bored cast in situ is preferable for bearing huge amount of load as it can be cast deep inside the ground.

Page 33: A Presentation on Bored Cast-in-Situ Piles

References : MURTHY V.N.S – SOIL MECHANICS AND

FOUNDATION ENGINEERING SHETTY M.S – CONCRETE TECHNOLOGY IS 2911 (Part 1/Sec 2) : 2010

Page 34: A Presentation on Bored Cast-in-Situ Piles

Thank You