SANDIA REPORT SAND97-8288 UC-721 Unlimited Release Printed September 1997 A Preliminary Analysis of the Reactor-Based Plutonium Disposition Alternative Deployment Schedules R. M. Zum Prepared by Sandia National Laboratories Albuquerque, New Mexico 87185 and Livermore, California 94550 Sandia is a multiprogram laboratory operated by Sandia Corporation, a Lockheed Martin Company, for the United States Department of Energy under Contract DE-AC04-94AL85000. Approved for pubfic releasq distribution is unlimited. ,, ,,. ,.”,, .,, ‘;, I,,z.,., ml, .s%:.: , ,:’’$;, ~~.., Sandia NationalJla&oratohes” -“. ,,, ..~ ,:$J ..”.,,,.. , - .. ,.;.. .“ .,, .

A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

SANDIA REPORTSAND97-8288 ● UC-721Unlimited ReleasePrinted September 1997

A Preliminary Analysis of theReactor-Based Plutonium DispositionAlternative Deployment Schedules

R. M. Zum

Prepared bySandia National Laboratories

Albuquerque, New Mexico 87185 and Livermore, California 94550

Sandia is a multiprogram laboratory operated by Sandia Corporation,

a Lockheed Martin Company, for the United States Department of

Energy under Contract DE-AC04-94AL85000.

Approved for pubfic releasq distribution is unlimited. ,,,,.

,.”,,

.,, ‘;,I,,z.,.,

ml,.s%:.:,,:’’$;, ‘~~..,

Sandia NationalJla&oratohes”-“.,,,..~,:$J ..”.,,,..,-....,.;...“.,, .

Page 2: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Issued by Sandia National Laboratories, operated for the United StatesDepartment of Energy by Sandia Corporation.

NOTICE: This report was prepared as an account of work sponsored by anagency of the United States Government. Neither the United States Gover-nmentnor any agency thereof, nor any of their employees, nor any of theircontractors, subcontractors, or their employees, makes any warranty,express or implied, or assumes any legal liability or responsibility for theaccuracy, completeness, or usefulness of any information, apparatus, prod-uct, or process disclosed, or represents that its use would not infi-inge pri-vately owned rights. Reference herein to any specific commercial product,process, or service by trade name, trademark, manufacturer, or otherwise,does not necessarily constitute or imply its endorsement, recommendation,or favoring by the United States Government, any agency thereof or any oftheir contractors or subcontractors. The views and opinions expressedherein do not necessarily state or reflect those of the United States Gover-nment,any agency thereof or any of their contractors.

Printed in the United States of America. This report has been reproduceddirectly from the best available copy.

Available to DOE and DOE contractors fromOffice of Scientific and Technical InformationPO BOX 62Oak Ridge, TN 37831

Prices available from (615) 576-8401, FTS 626-8401

Available to the public fromNational Technical Information ServiceUS Department of Commerce5285 Port Royal RdSpringfield, VA22161

NTIS price codesPrinted copy: A08Microfiche copy AO1

Page 3: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

SAND97-8288Unlimited Release

Printed September 1997

DistributionCategory UC-721

A Preliminary Analysis of the Reactor-BasedPlutonium Disposition Alternative Deployment

Schedules

R. M. ZurnSystems Studies Department

Sandia National Laboratories/California

ABSTRACT

This paper discusses the preliminary analysis of the implementation schedules of the reactor-based plutoniumdisposition alternatives. These schedule analyses are a part of a larger process to examine the nine decisioncriteria used to determine the most appropriate method of disposing of U.S. surplus weapons plutonium. Thepreliminary analysis indicates that the mission durations for the reactor-based alternatives range from elevenyears to eighteen years and the initial mission fuel assemblies containing surplus weapons-usable plutoniumcould be loaded into the reactors between nine and fourteen years after the Record of Decision.

3

Page 4: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Intentionally Left Blank...

4

Page 5: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

CONTENTS

1. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..lll.l Plutonium Disposition Mission ................................................................ ............................... ... 111.2 P1utoniurn Dispmition Options and the Decision Mwess ... ............... ...... ..... .. ...... ........................... 12

2. Reactor-Based Plutonium Disposition Alternatives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

2.1 GenericReactor-BasedAltemative Rfmition ................... ............... ..................... .......... ........ ........l52.2 FaciUty Destiptions .................................................. ........ ............................. .......... .......... ...... 16

2.2.1 Plutonium Processing Facilities ........................................................................................... 182.2.2Mixed-Oxide FuelFabrication Facilities ................................. ................. ....................... ........ 192.2.3ReactorFacilities ......................... ........ ...... ........................................ ...... .. ....... ........ .........2O2.2.4 Reposito~Facilities ...................... .... .......................................................... ....... .. .... .........23

3. Schedule Analyses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .25

3.1 Invduction ........................................................................ ....................... .......... ............. .......253.2 ScheddeElemenN ............................................................... .............. ........... ........ .... ........ ........253.3 General AssurnptionsandBases ............... ............. ........ ................................ ........ .. .... ....... ...... ...26

3.3.1 RecordofDecision .......... .. ........... ...... ............................... ............................ ............ .........263.3.2 Licensing ...... ............................. ..................................... ..................... ...... ...... ....... .........263.3.3PuAvailability andProduction Facility .. ............... .......................................... ...... ........ ........27

3.4 Schedule impacts oftransportation mdpachghg ............................. ....... .......... ......... .... ................27

4. Existing Light Water Reactor Alternatives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .28 ‘.

4.1 Existing LWRAltemative Base Case, 50S~5 .......................... ....................... ............. ............. ...284.1.1 PuPFacili~ .. ................ ..... .................................................................. ...... ...... ........ ........284.1.2MOXFuel Fabrication Facili~ ............................................................... ....... ...... .. ...... ........3O4.1.3 Existing PWR Facili~ ....................... ............................... ..................... ............... .............354.1.4 HLWRepositoty Facili~ ............... ..... ................ ............................................ ........... .........384.1.5 Existing LWRAlternative Base Case Schedule Summaq .......... ............. ............... ...... ..............38

4.2 Existing LWRAltemative Private MOX Plant, 50SPL5 ................... .......................... ...... ....... .......424.2.1 MOXFuelFabrication Facili~. Private O\vnersllip................. ..................... ..... .. ........... .........424.2.2 Existing LWR Al(emative Private MOXFacilily Case Schedule Su]wq ..... ......... ..... ....... ........42

4.3 Existing LWRAltemative Quick Start with EuroMOX, 50QSL5 ......................... .......... ..... ........ ......434.3.1 PuPFaciliQatiProto~pe ....................................................... ..................... ......................434.3.2 MOXFuel Fabrication Facility atiEuroMOXFuel Fabrication .................... .............................474.3.3 Existing PWR FaciliQ ............................................................ ............... ............... .............484.3.4 HLWRepository Facili~ ....... ............. ..................................... ..................... .......... ............5l4.3.SExisting LWR Alternative Quick Start with EuroMOX Schedule Summary..... ... .. .... ....... ......... ....51

4.4 Existing LWR Alternative 32.5 MT Hybrid, 33SFL3 ........................................ ......... .......... ..........554.4.1 PuPFacili~ .................. ............. ...... ............... ........ ........ ............................... ...... ......... ...554.4.2 MOXFuel Fabrication Facili~ ...................... .............. ............................ .......... ...... ............554.4.3 Existing PWR Facili~ ................................................................................. ......... .............554.4.4 HLWRepository Facili~ .......................... ............... ........................... ...... .... ......................554.4.5 Existing LWR Alternative Hybrid Schedule Summq ............ ............. ...... ................... .... ........S5

4.5 Existing LWR Alternative Collocated PuP/MOX, 50COL4 .............................. ...... ......... ................584.5.1 CollocatedPuPandMOXFuel Fabrication Facili~ ............................ ...... ...... ....... ......... .........584.5.2 Existing BWR FaciliQ ................ ..................... ............................ ...... ...... ........ ......... .........6l4.5.3 HLWRepository Facili~ ............. ........... ............................... ........ ..... .... .......... ....... .. .........644.5.4 Existing LWR Alternative Collocated PuPandMOXFacility Summary.......... .............. ......... .....66

4.6 Existing LWRAlternative S~ ................................................................. ...... ....... .............68

5

Page 6: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

5. CANDU Heavy Water Reactor Alternatives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 705.1 CANDU HWR Alternative Base Case, 50SFC2-4 ................................. ....................... ..................70

5.1.1 PuP Facility .......... .......................................... ............................. .......... ..........................7o5.1.2 MOX Fuel Fabrication Facility ...................... ..................... ........................... .. ...... ..............7o5.1.3 CANDU HWR Facility ..................................................... ................................... ........... ...725.1.4 Canadian Geological Repositoq Fmili~ ........... ....................... ............................ .......... ..... ...765.1.5 CANDUHWR Base Case Alternative Schedule Summary................... .. ... ................... .. ............ 76

5.2 CANDU IIWI? Alternative Hybrid Case, 33SFC2 ...................................................... ......... ...........785.2.1 PuP Facility .. ......................................................................................... .......... ................ 785.2.2 MOX Fuel Fabrication Facility ......... .... ................... ....................... ...... ............... ................795.2.3 CANDU HWR Facility ............................ ..................... ................................. ......... ........... 795.2.4 Canadian Geological Repositoq Facility ............................................................ .......... .. .. ......795.2.5 CANDUHWR Hybrid Alternative Schedule Summary ................................ ...... ... .. .. ........... .....79

6. Partially-Complete Light Water Reactor Alternative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 826.1 PuP Facility .............................. .. .......... ........................................................ .......... ......... .......826.2 MOX Fuel Fabrication Facility ............ ..... ........................................................ ..........................82

6.2.1 MOX Fuel Fabrication Facility Operations Schedule ............................... ........... .......... ......... ...826.2.2 MOX Fuel Fabrication Facili~ Schedule Summary ................... ....... ................... ....................82

6.3 Partially-Complete PWR Facility .............................. ............. ................ ................. .. ........ ..........836.3.1 Partially-Comple(e PWR Facility Design & Constmction .......................... ...... ......... ........... .....836.3.2 Partially-Complete PWR Facility Licensing a& Pertnitting ................................. .. ..... .. ............g56.3.3 Partially-Complete PWR Facility Operations Schedule ......................... ..... ........... ...... ..............856.3.4 Partially-Complete PWR Facility Schedule Sumq .......... ............... ................. ....................g7

6.4 HLW Repository Facility ......................................... ........ ............... .............. .......... ..................876.5 Partially-Complete LWR Alternative Schedule Summary ................... ...... .................. .... ......... .........89 --

7. Evolutionary Light Water Reactor Alternative . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 917.1 PuP Facility ..... .. .......... ..... .. ............................................. ..................................... .. ..... ...........9l7.2 MOX Fuel Fabrication Facility ..................................... ............. ................................. ..... ...........9l

7.2.1 MOX Fuel Fabrication Facility Operations Schedule ................................................ .. ..... .........9I7.2.2 MOX Fuel Fabrication Facility ......... .................................... ................................... ......... ...9l

7.3 Evolutionary PWR Facility ........................................................... ....... ........ ...... ...... .. ....... .........937.3.1 Evolutiona~ PWR Facility Design & Construction.................................. ........... ....................937.3.2 Evolutionary PWR Facility Licensing ati Pertnitting ......................... ................. .......... ..........937.3.3 Evolutionary PWR Facility Operations Sc}ledule ......................... .................................. ..........967.3.4 Evolutionary PWR Facility Schedule SumIMq ................................. ............. .......... ...... ........g6

7.4 HLW Repository Facility .................................. ............................................ ............... .............967.5 Evolutionary LWR Alternative Schedule Summary ............................................................. ............98

8. Schedule Summaries . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101

9. References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..l O3

Page 7: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

TABLESTable 1.1: Screening criteria forsurplus plutonium deposition ................................. ....... .......... ............l2Table l.2 Plutonium dispositionoptions..........................................................................................l4Table 2.1: Deployment approaches for existing LWRS....... .. .............................. ......... ........ .................. 16

Table2.2: Reactor-basedaltematives mdvfimK ............................. .......................... ................... ....... 17Table2.3: Facilities in the reactor-based titewtives mdvtim& ......................... .......... ......... .......... ......l8Table2.4: MOXfue1assemb1yproduction schdule mdfueltw .................................. ......... ................ 19Tab1e2.5: Existing P~ch~acteristics .................................................................. .......... .......... ......2OTable2.6: Existing BWRchancterist.ics .......................... ..................... ...... .......... ............. ................2lTable 2.7: C~U~chmackristics witi Refe~nce MOX .................. ...... ......... .... ......... ................22Table 2.8: C~U~chmacteristics witi C.EX ............................. .......... .... .........................22Table 2.9: Partially-complete PWR characteristics ...................................................... ......... .......... ......23

Table 2.10: ABB-CE System 8&reactorchmc@ristics ............................. ........................... ......... .......23Table4.1 PuPfacilitydesignandconstruction schedule ................................. .... .. ............... .. ......... .......29Table 4.2PuPfacility oversightand ytiting schdule ........................... ..... .......... ........................ .....29Table4.3~Pfacifi~o~mtiondschedule.........................................................................................29Table 4.4 PuPfacility schedule s~ ................. ................................... ......... .......... ......... ...........3OTable4.5MOXfuel fabrication facility designandconstruction schedule ...................... ........... ...... ..........32Table4.6MOXfue1 fabricationfacility licensingandpermitting schedule ..... ..... ........... ........ ......... ..........32

Table 4.7 MOXfuel fabrication facility operationrd schdde ................ ................. ......... .... ............... .....33Table4.8MOXfuel fabricationfacility schtiule s~ .................. ........................... ..... ..................33Table4.9ExistingPWRfacilitydesign mdcons~ctionschtiule ......... ....................................... ... .......35Table4.10Existing PWRfacility license md~titschedule ............................... ......... .... ....................36Table4.11 Existing PWRFacility Operations Schdule ....................................... ............. .... ................37 ‘-Table4.12Existing P~facdi~schdulesum~ .............................. .......... .. ............. ...... ... ...........38Table 4.13 HLWrepositoryfacility schdule suw ........................................ ............. .......... ..........38Table 4.14 Existing LWRaltemative schedule sumW ...................................... ............. ...... ..............39Table4.15MOXfuel fabrication facilitydesignandconstruction sch~tie ....................... ............. .. ..........42Table 4.16MOX fuel fabrication facility schedule s~ ................ ................. ....... ...... .... .... ............43Table4.17PuPfacilityandprototyp& oWrationd schedule ... ................................ .............................. ...~Table4.18PuP facilityandprototype schedule sum~ ..................................... ............. .... .... .. ..........UTable4.19MOX fuel fabricationfacility operational schtiule ............................... ........ ..... ........... .........47Table4.20MOXfuel fabncationact.ivities schdule su. .............. .......................... .... ....................48Table4.21Exist.ing PWRfaciMyq uickstartlicenseand pmitwhdule .......................... .... .............. .....48Table4.22Existing PWRfacilityquickstartopemtions schedule ......... ................. .... ...... ..... ............. .....5OTable4.23 Existing PWRfacifity quick sWxhdule sum~ ............................ ........ .. .................. .....5lTable4.24Existing LWRquick start d@mativeschdule s~ ....... ................ ............... ............. .....52Table4.25 Existing PWRfacility, three reactorschedule suq ........ ............................~.. ............. .....56Table4.26Existing LWRhybrid alternative schedule su. ............ ........................... ....... ........... .....56Table 4.27 Collmatd WPmd MOXfactity desi~md cons~ction schdde .......... ................. .......... .....58Table 4.28 Collocated PuP and MOX facility licensing and permitting schedule ........ ......... .................. .....59Table4.29Collocated PuPandMOX fuel fabricationfacility operational schedule .................. .............. .....59Tab1e4.30 Collocated PuPandMOX fuel fabrication facility schedule summary ....... ........................... .....61Table4.31 Existing BWRfacility license andpermitschedule ............................... ......... .......... ......... .. ...62Table4.32 Existing BWRfacilityoperations schedule .................. ........... ..................... ................... .....63Table4.33ExistingBWRfacility schdule sm~ .......................................... ............. ............... .....WTable 4.34 Existing LWR alternative with collocated PuP and MOX facility summary .... ........ .............. .....66Table 4.35 Existing LWRdisposition alternatives schedule sum~ ................................................ ......68Table 5.1 MOXfuel fabrication facilityoperational schdule .............. ............. .......... ....... ........... ...........7OTable 5.2MOX fuel fabricationfacility schedule summary ................ ....................... ....... ...... ...... ..........72Table 5.3 CANDU facility design and construction schedule .............. .................................... ..... ...........72Tab1e5.4CANDUfacility license md~mitschdule ...... ...................................... ... .......... ................73

7

Page 8: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 5.5 CANDU facility operations schedule .............. .............. ....................... .. ............. ........... .......73Table 5.6 CANDU HWR facility schedule summary .................... ................. ...... .. ....... .. ......................74Table 5.7 Canadian geological repository facility operations schedule ...................... ... ........... ...... ......... ...76Table5.8CANDU HWRbase casealtemative schedule summary .......................... ..................... ............78Table 5.9 CANDU HWR hybrid alternative schedule summary ................................................... ............8OTable 6.1 MOX fuel fabrication facility operational schedule ... .................................... ............... ......... ...82Table 6.2 MOX fuel fabrication facility schedule summuy ......................................... ..... .............. ........83Table 6.3 Partially-complete PWR facility design and construction schedule ........ ................ .....................83Table 6.4 Partially-complete PWR facility license and permit schedule ..................... ........... ............. .......85Table 6.5 Pa.rdally-complete PWRfacility operations schdule ................................ ............. ........... .......86Table 6.6 Partially-complete PWR facility schedule surrmmy ................................. ........... .... ........... .....87Table 6.7 Partially+omplete LWR alternative schedule summary ........................ .................... .......... ......89Table 7.1 MOX fuel fabrication facility operational schedule ...................... .................. ............ ..............9lTable 7.2 MOX fuel fabrication facility schedule surnma.ry....... ................................................... ..........93Table 7.3 Evolutionary PWR facility design and construction schedule ........................... ............... ..........94Table 7.4 Evolution~ P~facility license mdpmitschtiule ........ ............................. .. .......... ..........95Table 7.5 Evolutionary PWRfacility operations schedule .......................... ............... .. .. ............... ....... ...96Table 7.6 Evolutionary PWR facility schedule summary ........................................ .. ......... .......... .. ........98Table 7.7 Evolutionary LWR alternative schedule summary ........ ....... ................................ ............... .....99Table 8.1 Reactor-based disposition alternatives schedule summary ............................ ........................ ...lol

-,

\

8

Page 9: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

FIGURESF1g~e2.1: Generic r~ctor.based dspsition dtemative . .. . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . ..l5

Figure 4.1 PuP facility schedule summary ... ........................... ................... ......... .......... .. ............. .......3lFigure 4.2 MOX fuel fabrication facility summary schedule .............................. .. ................. .. ........... .....34Figure 4.3 Existing PWRFacility License and PefitSchedtie .......................... ...................................37Figure 4.4ExistingPWRfaci1ity schedule smw ... ..................... ................................ .... ... .............4OFigure4.5Existing LWRaltemativebase caseschedulesumrnary . ................................ .. ... ............... .....41

Figure 4.6 Private MOX fuel fabrication faciti~schtiule sum~ .................. ......... ........... ........ ..... .....45Figure 4.7 PuP facility mdprototw schdule s.w ............. ............................. ............... ......... .....46Figure 4.8MOX fuel fabrication activities schdule s~ .............. .................................... ......... .....49Figure 4.9 Existing PWRfacility quick sWschdule sw~ ............................ ...... ................. ..........53Figure 4.10 Existing LWR alternative quick start case schedule sumuwy ........ .................. .... .. ......... ........54

Figure 4.11 Existing LWRaltemative hybrid case schedule s~ .................................... ............... ...57Figwe4.12CollmaEd ~Pad MOXfuel fabrication facflity schedde s~ ... ....... ................ ......... ...@Fig~e4.13Existig BWRfacfiity license mdWfitschdule ........................ ........... ............... ............63Figure 4.14 Existing BWRfacility schdule s~~ ..... ..................... ............... ..... ...... .......... ............65Figure 4.15 Existing LWRaltemative collocated PuPand MOXfacility summary .... ... ......... ............... ......67Figure 4.16 Existing LWR disposition alternatives schedule summary ............. ......... ............. .. ......... .......69Figure 5.1 MOXfuel fabrication facility schedule sumW ............. ............. ............ ............. ................7lFigure 5.2 C~UWRfacflity schdule sm~ ........ ....... .................................. .............. ............75Figure 5.3 C~UWbw* dtewtive schedule sm~ ...................................... ........... .........77Figure 5.4 CA.NDU HWR hybrid alternative schedule summary .......... ............. ......... .... ..... ............ ........8lFigure 6.1 MOX fuel fabrication facility schedule summary .......... ..... ........ ............... ........... ........... .. .....84Figure 6.2 Partially-complete PWR facility license and permit schedule ........ ........... ........................... .....86 ‘.Figure 6.3 Partially-complete PWRfacility schdule sum~ .. ...................................... .................. .....88Figwe6.4P.y.comp1ek L~dtemative schedde s~ ......... ............. ....... ...... ..... ......... .........9OFigure 7.1 MOX fuel fabrication facility schedule summary ................. ........ ..... ................... ......... .........92

, ~gwe7.2Evolution~ PWfactiity design adconsmction schdule ......... .. .... ......... ................... ........94Figure 7.3 Evolutionary PWRfacility license and permit schedule ................ ...... ......... ........... ................95Figure 7.4 Evolutionary PWRfacility schdule sum~ .............. ................... ...... .... ............... ......... ...97Figure 7.5 Evolutionary LWRaltemative schedule su~ .................................. ......... ................... . 100

9

Page 10: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

ABB433AEAECBAECLARIEsASLBBWRCANDUCPDNFSBDOEEAEDERES&HFMDPGOCOHLw

J.TAACKDkgLAL,ANLLEULLNLLUALWRM&O

MOXMTMTHMMWdNASNEPANRCOLORNLPEISPuPUPPWRR&DRASRRFPRODSARSERSNMTVA

Acronyms and Abbreviations

Asea Brown Boveri – Combustion Engineeringarchitect engineeringAtomic Energy Control Board of CanadaAtomic Energy of Canada, Ltd.Advanced Recovexy and Integrated Extraction SystemAtomic Safety Licensing Boardboiiing water reactor

- Canadian deuterium-uranium– construction permit– Defense Nuclear Facility Safety Board– Department of Energy– Environmental Assessment– equipment delivery– Environmental Repat– Environmental, Safety, and Health– Fissile Materials Disposition Program- govemmentawned, contractor-operated facilities_ High ~veI Wrote

– Heavy Metal- heavy water reactor– Inspections, Tests and @alyses of Acceptance Criteria– key decision- kilogram– license amendment– Los Alamos National Laboratory– low-enriched uranium– Lawrence Liverrnore National Laboratory- lead use assembIy– light water reactor- management & operational- Office of Fissile Materials Disposition– mixed-oxide, (uranium oxide and plutonium oxide, UOZand PuOJ– metric tonne– metric tonne heavy metal- megawatt days– National Academy of Sciences- National Environmental Policy Act- Nuclear Regulatory Commission- operating license- Oak Ridge National Laboratory- Programmatic Environmental Impact Statement- plutonium- plutonium processing– pressurized water reactor- research and development– Reactor Alternatives Summary Report- Request for Proposal- Record of Decision- Safety Analysis Report- Safety Evaluation Report- special nuclear material- Tennessee Valley Authority

.

10

Page 11: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

1. IntroductionThis paper presents a brief overview of the plutonium disposition mission and the initial decision process todetermine the most appropriate method for disposing of surplus tissile materials. This disposition methmi willbe selected using nine decision criteria which include cost, schedule, and other issues. In the main section of thispaper, the preliminary analysis of one of these criteria, schedule, is presented for the reactor-based plutoniumdisposition method.

In the overview, a list of the possible plutonium disposition options is presented in four broad categories ofdisposition methods: placing the plutonium in long-term storage (the no action alternative); converting theplutonium into mixed-oxide (MOX) fuel and irradiating the fuel in reactors or accelerator, immobilizing theplutonium in glass, ceramic, or other materiti, and disposing of the plutonium dmt.ly with minimal pre-treatment e.g., deep space launch. Many of the initial thirty-seven options within these broad categories weredetermined to be less suitable for various reasons, listed below, and were removed from the list of possiblealternatives after completion of the initial screening process in late 1994 (l). Eleven disposition alternativesremained: one storage option, two direct disposal options, four immobilization options, and five reactor options.

The five categories of reactors in the remaining reactor-based options are: commercial existing light waterreactors (LWR), partially-complete LWRS, new advanced or evolutionary LWRS, Canadian deuteriurn-uranium(CANDU) heavy-water moderated reactors, and foreign reactors in Europe. After the initial screening process wascomplete, it was determined that the use of Europa reactors for the plutonium disposition mission was notfeasible and this alternative was not examined further.

Within the fwst four categories of reactors, nine unique variants have been defined in order to develop morecomplete analyses of the COS6schedule, and other measures for the decision criteria. These reactor-based variantsare described in Chapter 2. The preliminary analysis of the implementation schedules for all nine these variants ‘“”is presented in the six subsequent chapters of the paper. This work is a subset of the analyses descrii in theFissiie Materials Disposition Program (FMDP) Reactor Alterrmives Summary Reporr, volumes 14 (RASR)(2)

The remaining storage, borehole, and immobilization options are discussed in their res~ctive AlternativesSummary Reports (3), and all of the analyses for the eleven remaining options are summan“zealin the TechnicalSummary Report for Surplus Weapons-Usable Plutonium Disposition (4).

1.1 Plutonium Disposition Mission

The dismantlement of U.S. and Russian nuclear weapons and the clean-up of nuclear weapon production siteswill lead to 50 metric tonnes (MT) of surplus plutonium (Pu) in the US and over 100 MT of surplus Pu inRussia. As the National Academy of Sciences (NAS) report on this subject declare4 “The existence of thissurplus material constitutes a clear and present danger to national and international security” (5).’The Departmentof Energy (DOE).has created an Office of Flssile Materials Disposition (MD) with the mission to determine themost acceptable methcd for disposing of the surplus material. This decision is supported by the publication of aRecord of Decision (ROD) and a Programmatic Environmental Impact Statement (PEIS).

The PEIS was announced on December 9, 1996 in Storage and Disposition of Weapons-Usable Fissile MaterialsFinal Environmental Impact Starement (6). This PEIS describes the DOE’s dwd-tmck strategy for plutoniumdisposition which will continue to examine two disposition alternatives: immobilizing the plutonium in glassor ceramic and irradiating plutonium as mixed-oxide fuel in existing reactors. The Record of Decision was madepublic on January 14, 1997 in Record of Decision for the Storage and Disposition of Weapons-Usable FissileMaterials Final Environmental Impact Statement (7).

11

Page 12: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

In the December 1996 press release announcing the availability of the PEIS, DOE described its activities for thenext two years which will lead to the final decision concerning the disposition of rhe US surplus plutonium (8):

Technical, institutional and cost uncertainties exist with both the immobilization and sractoroptions. Accordingly, the departmen~ over the next two years, will complete the necessarytests, process development, technology demonstrations, site-specific environmental reviewsand detailed cost pro~sals for both approaches. Fma.1decisions to use either or both of rhesetechnologies depend on the results of this work as welt as nonproliferation considerations andprogress in efforts and negotiations with Russia and other nations. This approach gives thePresident the flexibility to begin plutonium disposition either multilaterally or bilaterallythrough negotiations or unilaterally as an example to Russia and other nations.

1.2 Plutonium Disposition Options and the Decision Process

The fwst step in the process to determine the most appropriate method for disposing of the surplus Pu was todetermine the decision criteria which will be used to rank the various disposition methods. The nine decisioncriteri% listed in Table 1.1, are based on the policy goals of DOE/MD, the NAS report, and public comment.

As the same time, a list of all potential plutonium disposition options was developed. This list of thirty-sevendistinct options, shown in Table 1.2, was developed by consolidating the methods discussed in several previousstudies, including the NAS study (5), and suggestions from the public which were obtained from questiomairesand public meetings held across the country in 1994. This list of options was reduced to eleven alternatives afterthe initial phase of the screening process by disqualifying or eliminating twenty-six options (l). An option was

Table 1.1: Screening criteria for surplus pIutonium disposition

Criteria Description

1. Resistance to Theft and Diversion by Each step in the dispositionprocess must be capable of providing for

Unauthorized Parties I comprehensiveprotection and control of weapons-usable fissi~ematerials.

82. Resistance to Retrieval, Extraction, I The surplus materialmust be made highly resistant to potential reuse

Reuse by Host Nation in weapons to reduce reliance on institutional control anddemonstrate that the arms reductions will not easily be reversed.

1. Technical Viability (Maturity) There shouldbe a high degree of confidencethat an alternativewill betechnically successful.

4. Environmental, Safety, and Health High standardsof public and workerhealth and safety, andenvironmentalprotection must be met, and significant additionalES&Hburdensshouldnot be created.

5. Cost Effective Dispositionshould be accomplishedin a cost-effective manner.

6. Timeliness There is an urgent need to minimize the time period that surplus

(Implementation Schedule) fissile materials remain in weapons-usable form.

7. Fosters Progress and Cooperation with The alternative must establish appropriate standards for the

Russia and Other Countries disposition of surplus weapons-usable fissile material inventories,support negotiations for bilateral or multilateral reductions in these

8. Public and Institutional Acceptance

9. Additional Benefits

materials, and each step in the disposition process must allow

international inspections.

An alternative should be able to muster a broad and sustainableconsensus on the manner in which disposition is accomplished. The

alternative must be consistent with U.S. policy.

The ability to leverage government investments for disposition ofsurplus materials to contribute to other national or internationals

initiatives should be considered.

12

Page 13: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

disqualified if it did not fulfill one or more of the decision criteria; e.g., R4, imadiating MOX fuel in navalreactors was disqualified because of the lack of transparency, as no international inspections could occur on anaval vessel. Other options were eliminated because they did not fultill some of the criteria as well as anotheroption; e.g., R5, irradiating MOX fuel in modular helium reactors was eliminated because the inventory ofsurplus plutonium would be irradiated faster using a more technically mature reactor technology.

The initial thirty-seven disposition options were defined very broadly without specifying the facilities orresources required to convert the surplus weapons-usable plutonium from its present forms into its final form.The next phase of the decision prccess involved refining the remaining eleven options by developing fullalternative descriptions which include preliminary facility layouts and operational requirements. The prccess fordefining the remaining reactor alternatives is discussed in Section 2.1.

As a part of the ROD announced on January 14, 1997, DOE declared that the department will immobilize atleast 8 MT of the surplus material that is too expensive to purify for use in MOX. Thus at most 42 MT ofsurplus plutonium will be converted into MOX fuel for use in existing light water or CANDU reactors. As aresult of this decision, additional schedule analyses will be completed using the new quantity of plutonium.These analyses will include trade-offs between the number and type of existing reactors to be used for thedisposition mission and the quantity of surplus plutonium which will be converted into MOX and irradiated inthe reactors. For the prelimimuy schedule analyses discussed in this paper, ROD was scheduled to occur onDecember 9, 1996 and the quantity of plutonium to be converted into MOX fuel was either 50 MT or 32.5 MT.

13

Page 14: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 1.2: Plutonium disposition options

ID # Disposition Option NameStatus after Initial Screening

(reason.for disqualification or elimination)

Storage Options

S1 No Disposition Action (Continued Storage) Baseline

S2 Radiation Barrier Alloy (Storage) Eliminated(Open-ended,ES&H)

Disposal Options

DI Direct Emplacement in HLW Repository Disqualified (Retrievability, Tmeliness)

D2 Deep Borehole (Mm obilized) Reasonable

D3 Deep Borehole (Direct Emplacement) Reasonable

D4 Discard to Waste Isolation Pilot Plant Disqualified (Capacity)

D5 Hydraulic Fracturing Disqualified (Technical Viability)

D6 Deep Well Injection Disqualified (ES&H)

D7 Injection into Continental Magma Eliminated (Technical Viability, ES&H)

D8 Melting in Crystalline Rock Disqualified (Technical Viability, ES&H)

D9 Disposal under Ice Caps Disqual~led (Technical Viability, ES&H)

DIO Seabed (Placement on Ocean Floor) Disqualitled (ES&H, Treaty)

Dli Sub-Seabed Emplacement Eliminated (Technical Viability)

D12 Ocean Dilution Disqualitled (ES&H, Treaty)

D13 Deep Space Launch Eliminated (Retrievability, ES&H)

Immobilization Options With Radio nuclides Options

11 Underground Nuclear Detonation Disqualified (ES&H, Licensing/Regulatory)

12 Borosilicate Glass Immobilization (existing facility) Eliminated (ES&H, Cost)

13 Borosilicate Glass Immobilization (new facility) Reasonable

14 Ceramic Immobilization Reasonable

15 Electrometallurgical Treatment Reasonable

~ 16 Borosilicate Glass Oxidation/Dissolution System ReasonableI

...

14

Page 15: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

2. Reactor-Based Plutonium Disposition Alternatives

2.1 Generic Reactor-Based Alternative Definition

The generic reactor-based alternative involves converting the feed material, surplus weapons-usable plutonium ina number of different forms, into plutonium oxide, PuOZ; fabricating mixed+xide fuel assemblies using thePuOZand uranium oxide, UOZ;irradiating the MOX fuel assemblies in a nuclear reacto~ and, finally, placing thespent MOX fuel in a repository. A flow diagram of this process is shown in Figure 2.1.

Feed Pu PU02 MOXin Spenl FuelinMate rial + Conversion -+ Conversion + Reactor Repository

to Oxide to MOX

Figure 2.1: Generic reactor-based disposition alternative

Within each of the four remaining broad alternative reactor categories, existing light water reactors (LWR),partially-complete LWRS, advanced or evolutionary LWRS, and CANDU heavy water reactors (HWR), there aewide disparities in cost, schedule, technical maturity, and the other deeision criteria measures. These disparitiesmay be due, for example, to the type of evolutionary LWR used as there are differences in technical maturitybetween reactor types; to the number of reactors used in the alternative which affects the duration and cost of themission; and to how many facilities will be used to process the plutonium into MOX, in one collocated facilityor two separate facilities. These different deployment approaches for existing LWRS are categorized in Table 2.1.In order to develop a reasonable estimate of the decision criteria measures, more detailed descriptions of thereactor-based alternatives have been developed. For each reactor category, several variants were defined.

,.

To begin the variant definition process, several major assumptions were made:

● All surplus plutonium forms will be processed, with either all 50 MT of the surplus plutonium beingirradiated in a reactor or 32.5 MT of the Pu being irradiated in a reactor with the other 17.5 MTdisposed of using one of the immobilization alternatives.

. All of the plutonium processing (PuP) will be done in government-owned, contractor-operated facilities(GoCO).

. All of the domestic MOX fuel will be fabricated in a building which is located on an existing federalsite. The building may be either a new facility or a modifkd existing facility. The facility may beprivately-owned or GoCo.

● All MOX fuel will be loaded into the reactors in less than twenry-five years after the initial missionfuel is loaded.

The reactor type and number used for each of the four options and their variants areas follows:

. For the existing LWR option, five pressurized water reactors (PWR) were selected to represent the basecase because there are more operating PWRS than the other LWR type, boiling water reactors (BWR).For this alternative, the MOX fuel would be fabricated in a domestic, GOCOfuel fabrication facilitylocated in an existing building on an existing federal site. Also, the MOX fuel is loaded with as muchPu as possible without having to include integral neutron absorbers. Three additional variants usingexisting PWRS were defined, one which uses a privately-owned MOX facility, the second variant usessome mission fuel which is fabricated in Europe to accelerate the mission start time, and a third variantwhich uses three PWRS and irradiates only 32.5 MT of the surplus Pu. A final existing LWR variantwas defined using four BWRS and using full MOX cores which contain integral neutron absorbers. A

full description of these variants maybe found in the RASR, vol. 1 (2).

15

Page 16: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

. For the CANDU option, the use of the CANDU HWRS at Bruce A on Lake Huron, in Ontario, Canadawas assumed for two CANDU variants, one which irradiates all 50 MT and a second which onlyirradiates 32.5 MT of the surplus Pu. A full description of these variants may be found in the RASR,vol. 2 (2).

. Two partially-complete PWRS wete selected as the representative reactors for the partially-completereactor alternative. A full description of this alternative maybe found in the RASR, vol. 3 (2).

. Two large evolutionary PWRS, ABB-CE System 80+, were selected to represent the evolutionary LWRalternative. Other possible reactor types include General Electric’s Advanced BWR and Westinghouse’sPDR-600, a plutonium-burning variant of the AP-600 reactor. A full description of this alternativemay be found in the RASR, vol. 4 (2).

Each alternative definition inchJ&s all of the facilities discussed in the generic reactor alternative above. Thenine reactor variants are shown inTable 2.2.

2.2 Facility Descriptions

In order to develop the overall alternative decision measures for each alternative and variant, several individualfacilities need to be defined more completely. The facility listings for each alternative and variant are shown inTable 2.3. As this paper only includes the implementation schedule analysis used as the performance measurefor the timeliness decision criterion, brief descriptions of each facility and its throughput or fuel loading cycleare given below. Additional schedule specific assumptions for each facility are discussed in the schedule analysissections. For complete facility descriptions including initial prccess descriptions, process flow diagrams,prelirnimuy facility layouts, and other criteria analyses see the appropriate RASR volume (2).

Parameter

‘lutonium‘recessing Facility

tiixed Oxide Fuel~abrication Facility

rype of Reactor

Number of Reactors

Core Design

Approaches

Table 2.1: Deployment approaches for existing LWRS

Range of Possible Choices

● Siting – Greenfield, new facility at a DOE site,an existing facility at an existing site

● Ownership – Privately-owned domestic,Government-owned domestic, existing

European facilities.

● Siting – Greenfield, new facitity at a DOE site,an existing facility at an existing site

2-5

● Amountof MOX per core – full core with

integral neu &on absorbers, full core withoutintegral neutron absorbers, partial MOX cores.

● Irradiation -25,000 to 50,000 MWd/MTHM(megawatt days / metric tonnes heavy metal)

● Fuel Cycle length – 12, 18, and 24 months.

Comments

All three options could also be doneeither in conjunction with (collocated

facilities) or separate from a MOX fuelfabrication facility.

Except for the European cases, alloptions could also be done either in

conjunction with or separate from aplutonium processing facility. For a PuPfacility collocated with the MOX fuel

fabrication activities, the facility wouldremain government-owned.

Even for a spec~lc type of reactor, many

core designs are available. Both types

could operate with or without integralneutron absorbers.

Two reactors is the minimum number. Themaximum number is limited by thenumber of reactors available.

16

Page 17: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 2.2: Reactor-based alternatives and variants

ID50SFL5

50SPL5

50QSU

33SFL3

50COL4

50SFP2

50SFE2

0SFC2-4

33SFC2

CategoryExisting LWR

Base Case

Existing LWRVariant 1

Existing LWRVariant 2

Existing LWRVariant 3 .

Existing LWRVariant 4

Partially-complete

LWR

Evolutionary LWR

CANDUBase Case

XtwXJVariant 1

Description● Process 50 MT Pu

● Pu processing

● Halide Processing at LANL.

● Modified existing facility on an existing federal site which operates

for 10 years.

● MOX Fuel Fabrication

● Domestic, GOCO fuel fabrication facility located in an existing

building on an existing federal site.

. Reactors

● Five privately-owned domestic PWRS.

● No integral neutron absorbers in the fuel,

● Spent fuel to federally-owned geological repository in western U.S.

● Same as 50SFL5 except:

● Privately-owned MOX fuel fabrication facility located in a new building on

an existing federal site.

● Same as 50S FL5 except:

● Early PU02 available from Pu processing pro to~ype operations

● Early MOX fuel fabrication in existing European fuel fabrication facilities.

● Same as 50S FM except:

● Process 32.5 MT of Pu.

● Three privately-owned PWRS

● Same as 50SFL5 except:

● GoCo, collocated Pu processing and MOX fuel fabrication facility located in

a new building on an existing federal site.

● Reactors

● Four privately-owned domestic BWRS.

● Maximum Pu cores with integral neutron absorbers.

~ Same as 50SFL5 except:

o Reactors

● Two GoCo, partially-complete PWRS which are completed and

employed for tire mission.

● Maximum Pu cores with integral neutron absorbers.

B Same as 50S FL5 except:

1 Reactors

● Two new GOCO PWRS which are built on an existing federal site.

● Maximum Pu cores with integral neutron absorbers.

~ Same as 50SFL5 except:

~ Reactors

● Two Bruce-A CANDU reactors, irradiating Reference MOX fuel for five

years followed by

● Four CANDU units irradiating CANFLEX fuel for the remainder of the

mission.

~ Spent fuel to Canadian geological repository.

~ Same as 50 SFC2-4 excepb

~ Process 32.5 MT of Pu.

~ Two Bruce-A CANDU reactors, irradiating Reference MOX fuel.

17

Page 18: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 2.3: Facilities in the reactor-based alternatives and variants

ID Category Facility Name ~acility description heading)

50SFL5 Existing LWR ● GOCO Plutonium Processing Facility (2.2.1)Base Case ● GOCO MOX Fuel Fabrication Facility in an existing building (2.2.2)

● Five Commercial PWRS (2.2.2.2)

● High Level Waste Repository Facility (2.2.4.1)

50SPL5 Existing LWR ● GOCO Plutonium Processing FaciLity (2.2.1)Variant 1 ● Privately-owned MOX Fuel Fabrication Facility in a new building (2.2.2.1)

● Five Commercial PWRS (2.2.2.2)

● High Leve 1 Waste Repository Facility (2.2.4.1)

50QSL5 Existing LW ● GOCO Plutonium Processing Facility, with early material available from theVariant 2 prototype processing line (2.2. 1.1)

● Private European MOX Fuel Fabrication Facitity (2.2.2.2)

● GOCO MOX Fuel Fabrication Facility in an existing building (2.2.2)

● Five Commercial PWRS (2.2.2.2)

● High Level Waste Repository Facility (2.2.4,1)

33SFL3 Existing LWR ● GOCO Plutonium Processing Facility (2.2.1)Variant 3 ● GOCO MOX Fuel Fabrication Facility in an existing building (2.2.2)

● Three Commercial PWRS (2.2.2.2)

● High Level Waste Repository Facility (2.2.4,1)

50COL4 Existing LJWl ● GoCo, Collocated PuP and MOX Fuel Fabrication Facility (2.2.1.2)Variant 4 ● Four Commercial BWRS (2.2.3.2)

● High Level Waste Repository Facility (2.2.4.1)

50 SFC2-4 CANDU ● GOCO Plutonium Processing Facility (2.2.1)33SFC2 Base Case and ● GOCO MOX Fuel Fabrication Facility in an existing building (2.2.1.2)

Variant 1● Two and/or Four Bruce-A CANDU reactors (2.2.3.3)

● Canadian Geological Repository Facility (2.2.4.2)

50SFP2 partially-complete ● GOCO Plutonium Processing Facility (2.2.1)LWR . GOCO MOX Fuel Fabrication Facility in an existing building (2.2.1.2)

● TWO Goco PWRS (2.2.3.3)

● High Level Waste Repository Facility (2.2.4.1)

50SFE2 Evolutionary LWR ● GOCO Plutonium Processing Facility (2.2.1)

● GOCO MOX Fuel Fabrication Facility in an existing building (2.2.2)

Q Two GOCO ABB-CE System 80+ Reactors (2.2.3.5)

● High Level Waste Repository Facility (2.2.4.1)

2.2.1 Plutonium Processing Facilities

All plutonium will be processed in government-owned contractor-operated (GoCO) facilities located on existingfederal sites. All of the disposition options assume that arty surplus plutonium which is in the form of a halidesalt or oxide will be processed at Los Alamos National Laboratory (LANL). The rest of the surplus plutonium,in the form of pits, Pu metal and oxide, and a variety of scraps and residues, will be converted into PuOZthrough either stabilization and conversion or pit disassembly in a moditied existing building. This plutoniumprocessing (PuP) facility is assumed to operate for ten years at a nominal annual throughput of 5 MT.

The site selection process for this facility will begin after the ROD and will be completed with a site-specificEnvironmental Impact Statement (EIS). The implementation schedule for t.hk facility is discussed in Section4.1.1.

2.2.1.1 Prototype Plutonium Processing

For the early start option, 50QSL5, a small supply of PuOZis required for the European fuel fabrication facilitybefore the full PuP facility is operational. This material will be available from the demonstration and prototype

-..s

18

Page 19: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

phases of the FMDP. The changes in the plutonium processing activities schedule with the addition of theprototype operation are discussed in Section 4.3.1.

2.2.1.2 Collocated Plutonium Processing and MOXFuel Fabrication Facility

The collocated PuP and MOX fuel fabrication facility will be located in a new building on an existing fedemlsite. This facility combines the PuP facility described above and the MOX fuel fabrication facility describedbelow into one facility. This reduces some duplication of waste handling processes as well as reducing theshipping and receiving requirements. The implementation schedule for this facility is discussed in Section 4.5.1.

2.2.2 Mixed-Oxide Fuel Fabrication Facilities

The MOX fuel fabrication facility receives the PU02 and converts it into MOX fuel for the specified reactor atthe rate required by the reactor loading schedule &scrikd below for each reactor type. The MOX fuel assemblyproduction schedule and operation duration for each option are shown in Table 2.4. For all of the options, exceptfor the CANDU and evolutionary reactor options, the initial assemblies produced will be used as lead useassemblies (LUAS) to confum the performance of the fuel.

For most of the reactor-based disposition options, the MOX fuel will be fabricated in a GOCOfacility located ina modh%d building on an existing fedeml site. The site selection process for this facility will begin after theROD and will k completed with a site-specific EIS. The implementation schedule for this base case facility isdiscussed in Section 4.1.2.

2.2.2.1 Private Mized-Oxide Fuel Fabrication Facility

The privately-owned MOX fuel fabrication facility will be located in a new building on an existing feded site.It is assumed that the change in ownership of the fuel fabrication facility does not have any major scheduleimpacts. Also, the change from modifying an existing building to building a new facility is assumed to not -.significantly affect the construction schedule. The minor changes in the implementation schedule for this facilityare discussed in Section 4.2.1

Table 2.4: MOX fuel assembly production schedule and fuel type

annual total # of mission averageAlternative assembly mission Pu operation throughput fuel use of

output assemblies (MT/y r.) (years) (MTHM/yr.) type INA? t

50SFL5, 50SPL5 280 2756 5 9.8. 118 PWR no

50QSL5 Europs 85 375 1.5 4.5 “ 35.8 PWR no

domestic 280 2381 5 8.5. 118 PWR no

50COL4 570 9416 3.2 16.5 “ 107 BWR yes

33SFL3 175 1819 3.2 10.4 “ 71.7 PWR no

50 SFC2-4 9200 45250 2.9 5 138 CANDU no

10450 75279 5 7.2 150 CANFLEX no

33SFC2 9200 98485 2.9 11.5 138 CANDU no

50SFP2 175 2692 3.2 15.4” 69 PWR yes

50SFE2 135 1807 3.8 14 53 PWR yes

‘INA – integral neutron absorbers- For all of the reactor options except the CANDU and evolutionary LWR options, there is anadditional six months of operation to produce the lead use assemblies.

19

Page 20: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

2.2.2.2 European Mi..wd-OxideFuel Fabrication Facility

The European fuel fabrication facility is an existing facility and it is assumed that no additional capacity will bem@red to supply the mixed-oxide fuel at the specified rate. Any modifications to the existing license at theEuropean facility will be overseen by the appropriate European regulator. The production schedule and opesationduration are shown in Table 2.4. An additional American facility maybe required for lag storage of the outgoingPuOz and the incoming MOX fuel assemblies. The changes in the MOX fuel fabrication schedule are discussedin Section 4.3.2.

2.2.3 Reactor Facilities

All of the reactor facilities receive fresh MOX fuel from the fuel fabrication facility and irradiate the fuel until itreaches the end of its economic energy value. The spent MOX fuel is discharg~ from the reactor and placed inan on-site cooling pool for a minimum often years. For planning purposes, the reactors are assumed to operateat 809Lcapacity factor and the number of reactors have been selected to pmnit the loading of the entire inventoryof surplus plutonium in less than twenty-five years.

2.2.3.1 Privale Existing Light Water Reactor Facilities – Pressurized WaterReactors

The base case and the fwst variant existing LWR alternatives, 50SFL5 and 50SPL5, assume the use of five,commercial, 3411 MWt (1150 MWe) PWRS. The plutonium disposition capacity and fuel cycle characteristics,shown in Table 2.5, are based upon a Westinghouse design for MOX cores which have as high a Pu-loading aspossible without integral neutron absorbers. Each reactor begins MOX operation with a partial core loading of84 MOX fuel assemblies. The five reactors are brought up sequentially in a 13.5 month perid 4.5 monthsapr@ with the last two reactors loaded at the same time. The last reload of 68 MOX fuel assemblies and 16 low-enriched uranium (LEU) assemblies is loaded into the third reactor 9.75 years after the initial MOX load. Theseassemblies are discharged 4.5 years later. After the last reload of MOX fuel, the reactors sequentially reconvert tothe use of LEU fuel assemblies. ‘he PWR facilities schedule is discussed in Section 4.1.3. -.

For the “quick start” variant 50QSL5, the initial MOX loads contain only 25 MOX fuel assemblies which havebeen fabricated in Europe. At the fourth reload of each reactor, the number of MOX fuel assemblies in the reloadis increased to 84 and this fuel will have been fabricated in the domestic facility. The duration of MOX fuelloading for this alternative is 13.125 years, with the last MOX assemblies leaded into the fourth reactor. Thequick start alternative schedule is discussed in Section 4.3.3.

For the 32.5 MT alternative, 33SFL3, three PWRS are loaded sequentially in a one year period six monthsaparg and each reload contains 84 MOX fuel assemblies. The last MOX assemblies are loaded sixteen years afterthe frostMOX load and into the third reactor. This alternative schedule is discussed in Section 4.4.3.

Table 2.5: Existing PWR characteristics

Plutoniumcapacify and rate.for one reactor

Pu per assembly (kg) 18.1

% Pu in heavy metal 4.3%

Pu dispositioned per year per reactor (MT) 1

Pu dispositioned per cycle/reload (MT) 1.5

Fuel cycle characteristics

Total cycle length (days) 548

Effective full power days (EFPD) 438

Planned / unplanned outage (days) 110Reload batch size (bundles) 84

Full core size (bundles) 193

Average discharge exposure (MWd/kg) 45

20

Page 21: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

2.2.3.2 Private Existing Light Water Reactor Facilities – Boiling Water Reactors

The last existing LWR varian~ 50COL4, assumes the use of four, commercial, 3484 MWt (1165 MWe)BWRS. The plutonium disposition capacity and fuel cycle chamcteristics, shown in Table 2.6, are based uponthe General Electric BWR-5 design for full MOX cores which include integral neutron absorbers in the fueldesign. Each reactor begins MOX operation with a partial core loading of 176 MOX fuel assemblies and buildsup to a full MOX core over a five year period. After the f~st reactor begins MOX operation, each additionalreactor begins MOX operations one year after the start-up of MOX operations in the previous reactor. A three-month cortfumatory period is included in the operating schedule for each reactor. The last reload of 88 MOX and88 LEU fuel assemblies occurs 16.6 years after the initial MOX load and these assemblies are discharged 5.8years later. After the last reload of MOX fuel, the reactors sequentially reconvert to the use of LEU fuel. TheBWR facilities schedule is discussed in Section 4.5.2. It should also be noted that a MOX fuel assemblywithout integral neutron absorbers could be designed for the BWRS, Wls design change would shorten theexpected licensing process duration and change the reactor loading schedule.

Table 2.6: Existing BWR characteristics

Plutoniumcapacitv and rate for one reactor

Pu per assembly (kg) 5.31

% Pu in heavy metat 3%

Pu dispositioned per year per reactor (MT) 0.80

Pu dispositioned per cyclekeload (MT) 0.93

Fuel qcle characteristics

Total cycle length (days) 425

Effective futl POwer days (EFPD) 340

Cumulative downtime per cycle (days) 85

Reload batch size (bundles) 176

Full core size (bundles) 764

Average discharge exposure (MWd/kg) 33.7

2.2.3.3 Canadian CANDUHeavy Water Reactor Facili~ – Bruce A Reactors

The loading cycles defined for the CANDU HWR alternatives are based on the reactor characteristics for a 2832MWt (769 MWe net) Bruce A heavy-water moderated CANDU ~ctor. The base case, 50SFC2-4, assumes twoCANDU reactors will irradmte Reference MOX fuel for five years and then four CANDU reactors will irradiate anew hybrid fuel, known as CANFLEX, for the rest of the program for a total loading duration of 12.2 years toirradiite the fuU 50 MT of surplus weapons-usable plutonium. Tbe variant case, 33SFC2, assumes that onlytwo CANDU reactors will be used for the entire 32.5 MT disposition mission with no changeover to the newfuel design for a total loading duration of 11.6 years. Since CANDU reactors operate on a continuous refuelingprogram, there are no planned shutdowms for refueling as in U.S. reactors. Peritiic outages are planned formaintenance purposes, however, these downtimes are accounted for in the 8070 capacity factor assumption. Theplutonium loading capacity and fuel cycle characteristics for the CANDU reactors are shown in Table 2.7 and themoditled characteristics for CANDU reactors using CANFLEX fuel are shown in Table 2.8. The CANDU HWRfacility schedule is discussed in Section 5.1.3.

21

Page 22: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 2.7: CANDU HWR characteristics with Reference MOX

Plutoniumcapacio and rate for one reactorPu per MOX assembly (kg) 0.23

% Pu in heavy metat 1.52%

Pu dispositioned per year (Ml”) 1.06

Pu dispositioned during program life (MT) 25

Fuel cycle characteristicsFuel residence (full power days) 360

Fuel residence time - 80% capacity 450

Full core size (bundles) 6240

Reload batch size (bundles/year) 4600

Average discharge exposure (MWd/kg) 9.7

Table 2.8: CANDU HWR characteristics with CANFLEX

Plutoniumcapacity and rate for one reactor

Pu per CANFLEX assembly (kg) 0.39

% Pu in heavy metal 2.7%

Pu dispositioned per year (MT) 1.01

Pu dispositioned during program life (MT) 9.75

Fuel cycle characteristics

Reload batch size (bundles/year) 2600

Average dischwge ex~sure (MWd/kg) 17.1

2.2.3.4 GOCOPartially-Complete Liglu WaterReactor Facilities - Pressurized Water Reactors

The partially-complete LWR alternative, 50SFP2, assumes two PWR units will be completed and used for themission. The plutonium loading capacity and fuel cycle characteristics, shown in Table 2.9, are based on thereactor characteristics of the 3817 MWt (1256 MWe), ABB-CE System 80 PWR. Each reactor will beginoperation with a full core load of 241 MOX fuel assemblies with a 3.O?ZOaverage Pu-loading. The second nmctorbegins MOX operations one year after the fwst reactor. here is a t.hnx-month confiitory period included inthe schedule for each reactor. The subsequent reloads of MOX fuel contain an average of 120.5 assemblies with aI%-loading of 4.5%. The last reload of 40 MOX and 80 LEU fuel assemblies occurs 15.7 years after the initialMOX load and these assemblies are discharged 3.1 years later. After the last MOX fuel reload, the reactors willbe converted to a full LEU core. The partially-complete PWR facility schedule is discussed in Section 6.3.

22

Page 23: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 2.9: Partially-complete PWR characteristics

2.2.3.5 GOCOnew Evolutionary Reactor Facility – ABB-CE System 80+ Reactors

Alternative 50SFE2 assumes the use of two new, 3817 MWt (1256 MWe) ABB-CE System 80+ reactors. Thisreactor design is a MOX-buming variant of the commercial ABB-CE System 80+ reactor which usesconventional LEU fuel. The plutonium loading capacity and fuel cycle characteristics for these reactors atEshown in Table 2.10. The second reactor begins MOX operations two years after the frost reactor starts. Theschedule includes a six-month confirmatory period for the fwst reactor. Each reactor begins MOX operation with ‘-a full core loading of 241 MOX fuel assemblies. This load resides in the core without refueling for a period ofabout four years, during which the fuel assemblies are relocated (“reshullled”) within the core three times atnominally equal intervals in order to achieve more uniform bumup. The last reload of MOX fuel occurs 13.3years after the initial MOX load. Half of the fuel assemblies in this final reload are MOX and half are LEU,subsequent reloads are full core loads of LEU fuel. The System 80+ facility schedule is shown in Section 7.3.

Table 2.10: ABB-CE System 80+ reactor characteristics

Plutoniumcapacity and rate for one reactorPu per assembly (kg) 27.7

% Pu in heavy metal 6.8%

Pu dispositioned per year (MT) 1.8

Pu dispositioned per cycle/reload (MT) 6.7

Fuel cycle characteristicsTotal cycle length (days) 1370

Effective futl POwer days (EFPD) 1096

Fuel shufflingkefueling length (days) 274

Reload batch size (bundles) 241

Full core size (bundles) 241

Average discharge exposure (MWd/kg) 42.4

2.2.4 Repository Facilities

All of the repository facilities receive spent MOX fuel from reactors and isolate the spent fuel permanently in a

sub-surface facility. There is no description of a European repository because all of the remaining feasiblereactor-based alternatives will use either domestic or Camdian reactors.

23

Page 24: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

2.2.4.1 High Level Waste Repository Facility

The final facility for all of the alternatives which use domestic reactors is the High Level Waste (HLW)Repository Facility. After the appropriate length of time, the spent MOX fuel will be removed from the coolingpools at the reactor facilities and shipped to this facility for final disposal. The spent MOX fuel generated by theplutonium disposition mission will be a small fraction of the spent commercial fuel which will be handled eachyear. It is scheduled to be opened before any of the spent MOX fuel will be ready to be shipped to the facility.The facility schedule is discussed in Section 4.1.4.

2.2.4.2 Canadian Geological Reposito~ Facility

The final facility for the two CANDU alternatives is the Canadian Geological Repository Facility. After theappropriate length of time, the spent MOX and/or CANFLEX fuel will be removed from the cooling pools orfrom dry ask storage at the reactor facility and shipped to this facility for final disposal. It is scheduled to beopened in 2025. The facility schedule is discussed in Section 5.1.4.

..

24

Page 25: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

3. Schedule Analyses

3.1 Introduction

Astiscussed above, tie NASlabeId tieexisting in@mationd ~gtiefor s~lus plutonium to bea’’clear andpresent danger” and urged that actions should be initiated to effect the disposition of surplus plutonium withoutdelay. Thus, timeliness should be a primary determinant for the selection of approaches for plutoniumdisposition. The FMDP Reactor Alternative Team has interpreted timeliness to be comprised of threeperformance attributes:

● Time to start disDositiofl: The mission starts when the Fwstmission fuel is leaded into a reactor and the

xtxwtorreturns to or has ascended to full power operation. For the existing LWR options, the missionbegins when the fwst reactor is loaded with MOX fuel, after the initial irradiation of the lead use assemblies(LUAS). For the CANDU options, the mission begins when the fmt reactors are loaded with MOX fuel.For the pardally-complete and evolutionary reactor options, the mission begins when the fwst maetorbegins operating at full power using a full MOX core.

● Time co co@ere: For the reactor options, the mission is complete after the final load of MOX fuel in the

reaetor has been inadiated for a speeifkd period. For the existing and partially-complete LWR options, asingle reload cycle is sufficient. For the CANDU options, the mission is complete after the final RefereneeMOX or CANFLEX fuel bundles have been discharged from the reactom. For the evolutionary LWRoption, the mission is complete after the f~st reshuffle of the last core load containing MOX fuelassemblies.

● lkhedule cer@inN: A full uncertainty analysis of the implementation schedules was considered too

premature for the analysis presented below. A qualitative assessment of the schedule certainty is included. -

3.2 Schedule Elements

Each reactor-based plutonium disposition alternative deployment schedule has been developed by combining theschedules for each of the individual facilities involved in the alternative. In the sections following, theimplementation schedule for each facility in an alternative will be develop?d using the elements shown below,then a summary schedule for the alternative will be shown. Chapter 4 will present the schedules for the existingLWR options; Chapter 5, the CANDU options; Chapter 6, the partially-complete LWR option; and Chapter 7,the evolutionary LWR option. A summary of all of the reactor-based options will be discussed in Chapter 8.

The major elements for each of the facility schedules are:

. Project definition and approval

. Siting, licensing and permitting

. Research, developmen~ and demonstration

● Design

. Facility mocMication or construction, procurement and preoperational activities

. Operation

● Decontamination and decommissioning.

The completion of each of these facility elements must be sequenced properly with the other facilities. Forexample, the MOX fuel fabrication facility needs to have a sufficient supply of PuOZto operate, and the reactorsrequire a sufficient supply of fuel to meet the reload schedule.

In defining the schedule elements for a government project, there area number of activities required for federalprojects that may not apply or am less important for a private sector project. The schedules reflect thesecomplications which include the following elements:

. Congressional line item approval and funding authorization

25

Page 26: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

s Compliance with the National Environmental Policy Act QNEPA)

. Speciat procurement and vendor selection rules and regulations.

3.3 General Assumptions and Bases

3.3.1 Record of Decision

The fissile materials disposition project officially starts witi the issuance of the programmatic ROD. In theanalyses presented below, the ROD is assumed to have been issued on December 9, 1996; the actual ROD wasissued on January 14, 1997. Some of the R&D projects began earlier in October 1995. “

After ROD, conceptual design of the PuP and MOX fuel fabrication facilities and the line item approval processbegin. The line item approval process is assumed to have a three year duration and to proceed in stages. Contractnegotiations with management & operating (M&O) contractors may start after two years. Detailed design of newand/or rnodifled facilities may start once the line item funding is approved.

3.3.2 Licensing

All of the facilities in each alternative will be licensed by the NRC except for the plutonium processing facilitywhich is assumed to be overseen by the Defense Nuclear Facilities Safety Board (DNFSB); and the Cmadian andEuropean facilities, which will be regulated by the appropriate national or European agency. The NRC licensingprocess used for each reactor faciIity follows the analysis presented in the Fluor Daniel Report: Regulatory Plansfor NRC Licensing of Fi.rsile Materials Disposition Ahernarives (9). For the PuP facility, a five year DNFSBreview Pried has been assumed, ~is review is assumed to begin immediately after ROD. For the MOX fuelfabrication facility and the collocated PuP and MOX fuel fabrication facility, the NRC licensing process is alsoassumed to be five years. The process for modifying the existing license of a European fuel fabrication facilityfor this mission is not discussed in this document due to the prelimimuy nature of this analysis. The five yearlicensing and permit schedule for the domestic fuel fabrication facility will be discussed in Section 4.1.2.2.

The licensing processes for the different reactom vary depending on several factors: reactor type, existing or newreactor, and fuel design.

● For the existing LWR reactors, the NRC license modification process is assumed to require 4.25 years forthe PWR options which do not have integral neutron absorbers, and to require 5.25 years for the BWRoption which includes integral neutron absorbers in the MOX fuel assembly. For all of the existing LWRoptions, the initial reload permit for MOX fuel is not granted until after the lead use assemblies (ML%)have been irradiated for two cycles. There is also a three year LUA license process which begins part waythrough the fuel qua.lifkation and demonstration process before the LUA may be loaded into the reactor.However, this process is completed well in advance of the availability of domestically fabricated fuel, and ayear after a European LUA would be available. The licensing and permitting schedule for the existing PWRoptions is discussed in Sections 4.1.3.2 and 4.3.3.1, and in Section 4.5.2.2 for the existing BWR option.

. For the partially-complete LWR option, the construction permit (CP) is transferred to the new contractorapproximately one year after the contnctor is selected. Once the CP is tmnsfened the construction mayproceed. The operating license for each reactor is granted after its completion. The LUAS for this reactcroption will be imadii in a sister reactor as soon as the assemblies are available. The licensing rmdpermitting schedule for the partially-complete LWR option is discussed in Section 6.3.2.

. For the new evolutionary LWR option, a three year licensing process is assumed before any sitepreparations may begin. The combined construction permit and operating license is issued eighteen monthslater, after which, the fwst nuclear concrete may be poured. The licensing and permit schedule for theevolutionary LWR option is discussed in Section 7.3.2.

. For the CANDU HWR, the license modification process is based on analysis by AECB and Ontario Hydroand has been estimated to require four years. The process will begin after the intermediate congressional lineitem funding is approved.

-,

26

Page 27: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

3.3.3 Pu Availability and Production Facility

All the schedules assume sufficient PU02 will be avaiIable to fabricate any initial LUAS txfo~ the productionfacility at an existing DOE site is operational. For most of the options, the PuP facility operates for ten years.

For the quick start case, 50QSL5, the plutonium will be processed in a staged start, because this alternativerequires plutonium oxide (Pu02) feed before the PuP facility could provide it. It is expected that a sufficientquantity of PU02 will be available from the Advanced RecoveV and Integrated Extraction System (ARIES)prototype, which is being developed to demonstrate the ARIES process and for design support for the productionfacility. Using the prototype ARIES line to process some of the mission material rdso shortens the operatiomdduration of the prediction facility to 9.1 years.

3.4 Schedule impacts of transportation and packaging

In terms of significantly impacting the overall schedule of the fissile materials disposition mission,transportation and packaging provides no sensitivity to any of the end-to-end alternatives chosen. In general, it isa safe assumption that any transportation and packaging activities that could impact the schedule (e.g., delays inpackage certification, or&lays due to insufficient number of available packages) will be eliminated by the fhctthat there is (a) suftlcient time to design, develop, and certify appropriate packages and (b) sufficient planningand resources available to acquire adequate numbem of certitled packages to accommodate the mission’s schedule.Therefore, the schedule specifics of transporting material from one facility to another are not included in theschedule analysis except for tmnsportation to and from Europe in the quick start case.

27

Page 28: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

4. Existing Light Water Reactor AlternativesThe implementation schedules for each of five existing LWR options shown inTable 2.2 is presented below. For complete descriptions of each of the facilities and for the cost and otheranalyses for the existing LWR options, see the RASR, volume 1 (2).

4.1 Existing LWR Alternative Base Case, 50SFL5

The base case for the existing LWR alternative uses four separate facilities: a PuP facility to process theweapons-usable plutonium from the various feed materials to PuOZ, a federally-owned MOX fuel fabricationfacility to convert the PU02 into MOX fuel, five existing PWRS to irradiate the MOX fuel, and a HLWrepository for ultimate emplacement of the spent MOX fuel. The implementation schedule for each of thesefacilities is developed below, followed by a summary schedule for the overall alternative.

4.1.1 PuP Facility

4.1.1.1 PuP Facility Design & Construction Schedule

The duration and path of the design and construction tasks for the PuP facility are based on a generic DOE MajorSystem Acquisition – Capital Construction Project. The design and construction process will begin at RODwith the start of the selection process for an Architect Engineering (AE) fwrn. This contractor will kresponsible for developing the mqirecl designs for the facility moditlcation and for completing thesemodifications. Work on the conceptual design will begin as soon as the AE contractor has been selected. Thefust key decision (KD-1) to start work on the Titte I design will be made after the conceptual design is completeand the initial line item funding has been approved. With the approval of the ThJe I design (KD-2) and final lineitem funding approval, work on Title 11design starts. The facility modifications and equipment procurementstart after Title II has been approved (KD-3). The equipment installation will proceed in a staged process so that ‘“”the preoperational checkout of the facility will start six-months before completion of the installation. Thedesign and construction schedule is shown in Table 4.1 and in the PuP facility summary discussion in Section4.1.1.5. A one-yea site and facility selection process will begin after ROD to determine the most appropriateexisting facility on a federal site for the PuP facility.

4.1.1.2 PuP FaciliQ Oversight& Permitting Schedule

For this analysis, it has been assumed that the DNFSB oversight review will start at ROD and will require fiveyears. The NEPA process and other site-spec~lc permitting will require three years and will start after the sitehas been selected. The oversight and permitting schedule is shown in Table 4.2 and in the PuP facility summarydiscussion in Section 4.1.1.5.

4.1.1.3 PuP Facility Operations Schedule

The preo~rational checkout of the PuP facility will start six-months before the equipment installation iscomplete and will take one year. The facility is scheduled to operate for ten years with an annual plutoniumthroughput of 5 MT. The f~st PuOZwill be available for shipment two months after the start of operation. Theoperational schedule is shown in Table 4.3 and in the PuP facility summary discussion in Section 4.1.1.5.

4.1.1.4 PuP Facility Decontamination & Decommissioning Schedule

Decontamination and decommissioning is projected to take two years for removal of contaminated equipmentand return of the building to an appropriate condition for geneml use.

2%

Page 29: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.1 PuP facility design and construction schedule

TaskTask Name

DurationID (months)

Start Finish

1. R&D Funding Available 10/1995

2. FMDP Record of Decision 12/1996

3. Congressional Funding Approval 36 12/1996 12/1999

4. Initial Funding Process 24 12/1996 12/1998

5. Final Line Item Funding Approval 12 12/1998 12/1999

6. Research, Development & Demonstration 36 10/1995 9/1998

7. Site & Facility Selection 12 12/1996 12/1997

8. Design Process 61 12/1996 1/2002

9. AE Selection 3 12/1996 2/1997

10. Conceptual Design 25 3/1997 3/1999

11. Approval of New Start (lCD-l) 3/1999

12. Title I 12 3/1999 3/2000

13. Approval to Commence Title II (KD-2) 3/2000

14. Title II 22 3/2000 1/2002

15. Facility Modification 48 1/2002 1/2006

16. Approval to Start Construction (KD-3) 1/2002

17. Construction, P~curement & Equipment Installation 48 1/2002 1/2006

Table 4.2 PuP facility oversight and permitting schedule -.r

Task DurationID Task Name

(months) Start Finish

1. Oversight and Permitting 60 12/1996 12/2001

2. DNFSB Review of Existing DOE Facility 60 12/1996 12/2001

3. Environmental/ NEPA / DOE 36 12/1997 12/2000

Table 4.3 PuP facility operational schedule

TaskTask Name

DurationID (months)

Start Finish

1. Preoperatlonal Phase 12 8/2005 7/2006

2. Operation 120 7/2006 7/2016

3. Approval to Commence Operation (KD-4) 7/2006

4. Pu Processing Duration 120 712006 7/2016

5. First PuO, Available 2 7/2006 9/2006

4.1.1.5 PuP Facility Schedule Summary

The ovetall PuP facility implementation schedule is summarized in Table 4.4 and shown in Figure 4.1, Thisfacility schedule is also shown in the discussion of the overall alternative schedule in Section 4.1.5. Thisschedule dces not include any contingency for schedule slip due to site selection difficulties, redesign,construction delays, or a delay in the approval of line item funding.

The critical path through the development of this facility is through the design and construction process. If anyof these tasks slip in their schedule, the rest of the implementation process will also be delayed. This criticalpath is shown in Figure 4.1. If the start of operations at the PuP facility slips more than three months, the start

29

Page 30: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

of operations at the MOX fuel fabrication facility will also slip because the PuOZwill not be available to beginfuel fabrication.

Table 4.4 PuP facility schedule summary

TaskTask Name

Duration

ID (months)Start Finish

1. R&D Funding Available 10/1995

2. FMDP Record of Decision 12/1996

3. Congressional Funding Approval 36 12/1996 12/1999

4. Research, Development & Demos 36 10/1995 9/1998

5. Site & Facility Selection 12 12/1996 12/1997

6. Oversight and Permitting 60 12/1996 12/2001

7. Design Process 61 12/1996 1/2002

8. Facility Modification 48 1/2002 1/2006

9. Preoperational Phase 12 8/2005 7/2006

10. Facility Operation 120 7/2006 7/2016

11. Decontamination & Decommission 24 8/2016 7/2018

4.1.2 MOX Fuel Fabrication Facility

4.1.2.1 MOX Fuel Fabrication Facility Design& Construction Schedule

The duration and path of the design and construction tasks for the MOX fuel fabrication facility are based on ageneric DOE Major System Acquisition – Capital Construction Project. The design and construction processwitl begin at ROD with the conceptual desi=gtwhich will be completed by the National Laboratories in order to

..

start the NRC licensing process as som as possible. The one-year site and facility seIection process to determinethe most appropriate existing facility on a federal site for the MOX fuel fabrication facility will stast after thecompletion of the conceptual design. The selection process for the M&O contractor will start after theintermediate approval for line item funding. This contractor will be responsible for developing the Title I and IIdesigns and for completing the facility modifications nxpircd for the MOX fuel fabrication facility. Work onTitle II starts after approval of the Title I design and final line item funding. The facility modifications andequipment procurement starts after completion of TMe II design and up to one year before the completion of theNRC licensing process. However, no safety-related construction may be done until after the license has beengranted. The design and construction schedule is shown in Table 4.5 and in the MOX fuel fabrication facilitysummary figure in Section 4.1.2.5.

The fuel qualification demonswation has begun with the production of the test assemblies and is scheduled to lxi!completed in 2001.

30

Page 31: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

-.—S

-–.-—..+$j

..~..b...

..W.......

..b..

..D

....

...........

...........

........

..—

._...—

._.-_

—.--_.

_.._

—In—

——

——

—u-l

N—

Page 32: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.S MOX fuel fabrication facility design and construction schedule,

TaskTask Name

DurationID (months)

Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Approval 36 12/1996 12/1999

3. Initial Funding Process 24 12/1996 12/1998

4. Final Line Item Funding Approval 12 12/1998 12/1999

5. Fuel Qualification Demonstration 60 4/1996 4/2001

6. Site and Facility Selection 12 12/1997 12/1998

7. Select M&O Contractor 12 12/1998 12/1999

8. Design Process 60 12/1996 1 1/20019. Conceptual Design 12 12/1996 12/1997

10. Title I 12 12/1999 12/2000

11. Title II 12 12/2000 1 1/2001

12. Facility Modificatione

36 12/2001 1212004

13. Construction 36 12/2001 1212004

14. Procurement 24 12/2001 12/2003

15. Equipment Installation 12 12/2003 1212004

4.1.2.2 MOX Fuel Fabrication Facility Licensing & Permitting Schedule

For this analysis, it has been assumed that the duration of the NRC licensing prmss will be five ye~ and hat --

the process will start after the conceptual design is complete. The NEPA process and the other site-specific

permitting will require three years; each process will start after the site has been selected. The licensing scheduleis shown in Table 4.6 and in the MOX fuel fabrication facility summary figure in Section 4.1.2.5.

Table 4.6 MOX fuel fabrication facility licensing and permitting schedule

TaskTask Name

DurationID (months) Start Finish

1. Licensing and Permitting 60 12/1997 1212002

2. NRC Licensing 60 12/1997 1212002

3. Environmental / NEPA / DOE 36 12/1998 1 1/2001

4. Permitting 36 12/1998 1 1/2001

4.1.2.3 MOX Fuel Fabrication Facility Operations Schedule

The pmo~rational checkout of the facility starts as soon as the construction is complete and will take twoyears. The LUAS are fabricated in the MOX fuel fabrication facility during the six-monti start-up period. Then,this facility will operate for 9.8 years with an annual plutonium throughput rate of 5 MT, supplying fuel for the5 existing PWRS at the specified loading rate. This throughput assumes an annual output of 280 assemblies fora mission total of 2756 assemblies. The operational schedule is shown in Table 4.7 and in the MOX fuelfabrication facility summary figure in Section 4.1.2.5.

4.1.2.4 MOX Fuel Fabrication Facility Decontamination & Decommissioning Schedule

The duration for the decontamination and decommissioning of the MOX facility has been estimated to be twoyears.

32

Page 33: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.7 MOX fuel fabrication facility operational schedule

Task DurationID

Task Name(months)

Start Finish

1. Preoperational Phase 24 12/2004 12/2006

2. PuP Facility Lead Time Complete 9/2006

3. MOX Facility Ready for PuO, 12/2006

4. Operation 124 12/2006 4/2017

5. MOX Facility Operation Start 1212006

6. LUA Fabrication 6 12/2006 6/2007

7. Operation 118 612007 4/2017

4.1.2.5 MOX Fuel Fabrication Facility Schedule Summary

The overall MOX fuel fabrication facility implementation schedule is summarized in Table 4.8 and shown inFigure 4.2. This facility schedule is also shown in the discussion of the overall alternative schedule in Section4.1.5. This schedule dces not include any contingency for schedule slip due to site selection difficulties,redesign, construction delays, or a delay in the approval of line item funding.

The critical path through the development of this facility is through tie conceptual design and the NRClicensing process. If either of these tasks slip in their schedule, the rest of the implementation prccess will alsobe delayed. This critical path is shown in Figure 4.2.

Table 4.8 MOX fuel fabrication facility schedule summary

Task DurationID

Task Name(months)

Start Firiish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Approval 36 12/1996 12/1999

3. Fuel Qualification Demonstration 60 4/1996 4/2001

4. Site and Facility Selection 12 12/1997 12/1998

5. Select M&O Contractor 12 12/1998 12/1999

6. Licensing and Permitting 60 12/1997 1212002

7. Design Process 60 12/1996 11/2001

8. Facility Modification 36 12/2001 12/2004

9. Preoperational Phase 24 1212004 12/2006

10. PuP Facility Lead Time Complete 9/2006

11. MOX Facility Ready for PU02 12/2006

12. LUA Fabrication 6 1212006 6/2007

13. MOX Fuel Fabrication Operation Duration 118 6/2007 4/2017

14. Decontamination & Decommission 24 4/2017 4/2019

...

33

Page 34: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

+ew=ww~xselIEWIJCI

=

x

m

,Je

IJI

1

se

c—

I

-EI

a9alf.zIla

E—

N

I

L—

uollemauot]aopqe~IenjKM!9Z

I

w

w

nd

OJC

WI@J%l‘JW.lP-WINll=jdnd12

aaaqdleuqiemdwdw

Isul

u

U1m

Ieli!,

IIeli!lIS1

Iell!l*L

310aIvd3rdIiewewu04Au3=

~ulJe,17~HN

k

6!JUL

1opelwo~ow

u<

LOIL

0,90,so,

lauol]eql!lenolandE

Ilv~/wn,

L

:Sa,old~1

*

PAt

uolslo,aa10pIOo~Hdc

PO!so,Zot10,00.66,S&

IH\@s2

,14mw

‘“+=

leAOJddv6UfXJnjIau!jv

I

mlIImolddv8ulpunjIWOPWJ6UO0Iz

—to,

Page 35: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

4.1.3 Existing PWR Facility

4.1.3.1 Existing PWR Facili~ Design & Construction Schedule

After the intermediate approval of line item funding, the project begins with a year-long process to select theutility or utilities. The reactor modifications, which primarily consist of the construction of a new fuel storagefacility, are estimated to take four years. The design and construction schedule is listed in Table 4.9 and in thePWR reactor facility schedule shown in Section 4.1.3.4.

Table 4.9 Existing PWR facility design and construction schedule

Task DurationID Task Name

(months)Start Finish

1. FMDP Record of Decision 12/1996

2. Intermediate Funding Approval 24 12/1996 12/1998

3. Utility Selection 12 12/1998 12/1999

4. Reactor Modifications 48 12/1999 11/2003

4.1.3.2 Existing PWR Facility Licensing and Permitting Schedule

For this analysis, a schedule developd by Fluor Daniel (9) for mcdifying an existing LWR facility license topermit the use of MOX fuel without integral neutron absorbers was followed. The process to obtain a relmdpermit for a new fuel fabricator is also included in the permit schedule. The license and permit schedule is shownin Table 4.10 and Figure 4.3. ‘

After the utility or utilities have been selected the license amendment process is SW with the preparation of .-the Safety Analysis Report (SAR), the license amendment application, and the Environmental Report (ER). TheNRC issues the Safety Evaluation Report (SER) and the Environmental Assessment (EA) after completing thereview of the application. The amended license is issued after the reactor facility moditlcations are complete. Inaddition, a reload license process is followed because of the use of a new MOX fuel fabrication facility. Thisanalysis assumes a three year LUA license process is followed prior to inserting the LUAS into the reactor. Afterthe LUAS have been irradiated for one cycle, 1.5 years in this case, a review of the LUA performance iscompleted. The reload permit for use of MOX fuel is granted after this review.

4.1.3.3 Existing PWR Facility Operations Schedule

The LUAS are loaded into the fwst unit as soon as they me available and during a normal refueling period for thereactor. After the completion of the LUA review during the second irradiation cycle, the fwst mission fuel isloaded at the next scheduled refueling period in May 2010. The MOX fuel load and discharge schedule for thefive reactors was discussed in Section 2.2.3.1. After three irradiation cycles, 4.5 years, the spent MOX fuelassemblies are discharged from the reactors, and stored in the spent fuel storage pool for a minimum of ten yearsbefore being shipped to the HLW repository facility. The existing LWR facility operational schedule is shownin Table 4.11 and in the PWR reactor facility schedule shown in Section 4.1.3.4.

4.1.3.4 Existing PWR Facility Schedule Summary

The overall existing PWR facility implementation schedule is summarized in Table 4.12 and shown in Figure4.4. This facility schedule is also shown ‘in the discussion of the overall alternative schedule in Section 4.1.5.The critical path for this facility is the availability of the LUAS and is shown in Figure 4.4. The reactors areready KSaccept MOX LUAS over three years before they are available.

35

Page 36: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.10 Existing PWR facility license and permit schedule

TaskTask Name

DurationID (months)

Start Finish

1. NRC InteractIons 51 12/1999 2/2004

2 Licensee Prepares SAR & License Amendment 12 12/1999 12/20003 Licensee Files Application 12/20004 Public Notice of App. for LicenseAmendment 3 12/2000 3/20015 NRC Review 9 3/2001 1 1/2001

6 NRC kslles SER 11/2001

7 NRC Issues License Amendment 3 12/2003 2/2004

8 Notice of Amendment to Operating License 212004

9 Environmental / NEPA / NRC 24 12/1999 11/2001

10 Licensee Develops & Prepares ER 6 12/1999 6/2000

11 Licensee Files Report with NRC 12/2000

12 NRC Prepares & Issues Draft EA 6 12/2000 6/2001

13 NRC Issues Final EA 3 9/2001 1 1/2001

14 LUA & Reload Licenses 126 12/1999 5/2010

15 LUA Licensing 36 12/1999 1 1/2002

16 Reload Approval 18 12/2008 5/2010

17 Reactor Modifications 48 12/1999 11/2003

18 Fuel Qualification - LUAS 54 6/2007 12/2011

19 LUA Arrives 6/2007

20 LUA Irradiation 54 6/2007 12/2011

36

Page 37: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

1 NRC Interactions

2 Licensee Prepares SAR & License Amandm(

~

Licensee Files Application

Public Notice of App. for License Arswndrnen

I ID Task Name @99]2000\2001 ]2002]2002 2004] 200S]2006]200712008] 2009/201(,,, :,

# 1 Iii~~

‘[-~repa/esSP!R& l!icen~ehend~n! ~

F‘#Lc! ‘ : 1 I ~

I nsee Files Application ! ]’

I& Pul!lic Nc!iice of Appi for L!cen~ Amdndme’nt ~

Iiii!j i~iii~; NRC Review\~~.

~ ++ +’s+’+ ~,, ]

11!1 h NRC lss~es License Amendmaril

6 NRC Issues SER

7 NRC Issues License Arrwndmant

I 8 I Notice of Amandmant to Operating License I

9 Environmental / NEPA / NRC

10 Licensee Develops & Prepares ER

[ 11 / Licensee Files Reportwith NRC

12 NRC Prepares & Issues Draft EA

13 NRC Issues Final EA

37 Reactor Modifications

18 Fuel Qualification - LUAe

I 19 I LUAAnivesI

I 20 I LUA Irradiation I

per n9

ii—

:en

TaskPmlect: Reactor License& Permit

~ Milestone +

Critical Task ~ Summary ~

>a(

iii—

ppl

.U1

.

ii—

al

rac.

ii—

ion.

Figure 4.3 Existing PWR Facility License and Permit Schedule

Table 4.11 Existing PWR Facility Operations Schedule

TaskTask Name

DurationID (months)

Start Finish

1. Reactor “ready” to accept MOX 212004

2. Fuel Qualification 54 6/2007 12/2011

3. Reactor Facility Operation 171 5/2010 812024

4. Unit 1 Loading Duration 108 5/2010 5/2019

5. Unit 2 Loading Duration 108 10/2010 10/2019

6. Unit 3 Loading Duration 108 2/201 1 212020

7. Units 4&5 Loading Duration 88 7/201 1 11/2018

8. Last Assemblies - single cycle 18 312020 8/2021

9. Last Assembly Discharged 54 312020 812024

10. Spent Fuel Storage 237 12/2014 912034 ,11. First MOX in Spent Fuel Pool 120 12/2014 11/2024 112. I Last MOX 120 912024 912034 1

..

37

Page 38: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.12 Existing PWR facility schedule summary

TaskTask Name

DurationID (months)

Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Approval 36 12/1996 12/1999

3. Utility Selection 12 12/1998 12/1999

4. Licensing and Permitting 51 12/1999 212004

5. Reactor Modifications 48 12/1999 11/2003

6. LUAS Arrive from MOX facility 6/2007

7. Fuel Qualitlcation - LUAS 54 6/2007 12/2011

8. Reactor Operation 171 5/2010 812024

9. Last Assemblies - first cycle 18 3/2020 8/2021

10. Spent Fuel Storage 237 12/2014 912034

4.1.4 HLW Repository Facility

For this analysis, it has been assumed that the licensing process for the HLW Repository facility will begin inMarch 2002 and will require 8.5 years to complete. The construction of this facility will begirt in 2005 and willtake 5.5 years to complete. The facility is scheduled to open in 2010 after completion of construction andgranting of the license. The spent MOX fuel is scheduled to be delivered to the repository facility fromDecember 2024 to September 2034. The HLW Repository facility schedule summary is shown in Table 4.13and in the overall alternative schedule in Section 4.1.5.

Table 4.13 HLW repository facility schedule summary -..

Task DurationID

Task Name(months)

Start Finish

1. Licensing Process 102 312002 8/2010

2. Construction 66 3/2005 8/2010

3. Repository Opening Date 8/2010

4. Delivery of MOX to Repository 118 1212024 912034

5. Transportation of first MOX to Repository 1 12/2024 1212024

6. Transportation of last MOX 1 9/2034 912034

4.1.5 Existing LWR Alternative Base Case Schedule Summary

The existing LWR alternative base case schedule is a combination of the individual facility schedules discussedabove. This overall schedule is summarized in Table 4.14 and shown in Figure 4.5. The plutonium dispositionmission begins when the frost mission fuel is loaded into a reactor in May 2010 and is complete after the lastCORloarl which contains MOX fuel assemblies, has been irradiated for a single cycle in August 2021. Theoverall mission time is 11.3 years and starts 13.5 years after ROD. The critical path for this alternative is thelicensing, design and facility modifications for the MOX fuel fabrication facility.

38

Page 39: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.14 Existing LWR alternative schedule summary

TaskTask Name

DurationID (years) Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Process 3 12/1996 12/1999

3. PuP Facility 22.8 10/1995 7/2018

4. R&D 3 10/1995 9/1998

5. Oversight, Permitting & Siting 5 12/1996 12/2001

6. Design 5.1 12/1996 1/2002

7. Facility Modification & Preoperation 4.5 1/2002 7/2006

8. Operation 10 7/2006 7/2016

9. Decontamination & Decommissioning 2 8/2016 7/2018

10. MOX fuel fabrication facility 23 4/1996 4/2019

11. Fuel Qualification 5 4/1996 412001

12. Licensing, Permitting & Siting 5 12/1997 1212002

13. Design 5 12/1996 1 1/2001

14. Facility Modification & Preoperation 5 12/2001 12/2006

15. Fabrication of LUAS 0.5 12/2006 6/2007

16. Operation 9.8 6/2007 4/2017

17. Decontamination & Decommissioning 2 4/2017 4/2019

18. Reactor Facility 35.7 12/1998 912034

19. Utility Selection. .

1 12/1998 12/1999

20. Licensing 4.2 12/1999 212004

21. Reactor Modifications 4 12/1999 11/2003

22. Reactor “ready” to accept MOX 212004

23. Lead Use Assemblies 4.5 6/2007 12/2011

24. MOX Loading Duration 9.75 5/2010 2/2020

25. Single irradiation cycle of last MOX 1.5 3/2020 8/2021

26. Spent Fuel Pool Duration 19.75 12/2014 9/2034

27. HLW Repository Facility

28. Licensing 8.5 3/2002 8/2010

29. Construction 5.5 312005 8/2010

30. MOX Delivery Duration 9.75 12/2024 9/2034

39

Page 40: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

htzumnsalnpatps

heuunsSo!wxqIjMd6UWX3:PO!OJd

=m

XON

—UWN

@J!s

~

Xoi

)dlaIU.3*

16M— ——

lq6

WW

W@IIrqeOJqIJWEPatieqoqa~w06svIsellZ

e@auOIWIpwllqlhqs-sqlque*sV1s01Oz

Iuq]ema6u!p607sw6~un61

ucqema6uIpe01cpun81MIeln<

ucqema6u!pe01z~un.!1

Uqtema6uIpe071pun91well

h

mRQz .

mI

Uopmdo(q-)A!lpnjJOwBatJ91

uciIapeJJIvnl●1

~&II

I+““

‘o’’”&‘OiT’.’OTa” !SUO!WJIJ!PON 10KW%

1qe~rm/~“ I

[email protected]~1

●lO!wqJp+yJolmeuOL

Iemddvpeqa~s

6U!SU6=TI vnle

~w!pps@n1111 Iemwddv6u!punjlw0!sseJ6u0~

ilI,w!qos~Joplm

El :9CIcozZIE )ZazE!z Iloz —

Page 41: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

u.

..-.—

..—

—--------------

__.-_.-...

..

...-.___

..

..

...

..,-.-.-._-,-

-------------------,-------

e;..

●✎

✎�

✎�

✍✎

��✎�

✎�

✎✎

�✎

�✎

PF.-

.-—

--.5—.—

.5:.-

%E

.-EE

E0—

-

%

.5—

.

~

ga

0*

z

e.—

m_

._.:

5.2

.%z.-

J

——

..._,g—

-——

______E

——

.—

.--—

-----~._

.-—.

——

EE

23

‘-!?

zs:

2.g—

—D

.—

.:0

w—z

.——.—_

_____________

t

~‘,—

--.-.-.__________________

1 i–.._________;____

_.._.-___>

“’“[:-1-- E

——

~—_

::

—.-

.-.

__________________

-----------------[_._._-.

___...-_.._-...______j__j

_..__.

,=___

En-Y

~g

.g:

e.——

-Q

.:—

+—

------4.%

—;—

.s:

2:

“9

.-—

.E

—P

$_2

_y

8,g

s—

.S—

UI

c-’g

E’—

:.-&

*_~

~’

*C

n:f

—’G

_&

—.=

m:;

_~.-

$:[

g~

g

‘-~-

—-

r

—.F

z

?a

—.4

–i‘—

.g_g_g

~E

“:.:

“;

.s?c

~.=

—~_

.-.-.-.._-,

g“--%

”–.._.--.––_-..

-.-.–J-.+

+..-

--------..--.,:...

2--&

-----------------

.9.5

“i~

68

36

j

.n_?—

_._—P

—--u

____

__z%

8

~-

[f~:-------

~-i[

.--.—

~g

‘-

n-:

------+

—.

-------—

-.--.--.-—

a0~—

‘IL

-----

—.

+

~-

__._...__?.._

...._-_._

..-.—

___________

—>5—r.

—053:c—,—

——

Page 42: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

4.2 Existing LWR Alternative Private MOX Plant, 50SPL5

Thef~st variant case for the existing LWR alternative uses four separate facilities: a PuP facility to process theweapons-usable plutonium from the various feed materials to PU02, a privately-owned MOX fuel fabricationfacility to convert the PU02 into MOX fuel, five existing PWRS to imadiate the MOX fuel, and a HLWrepository for ultimate emplacement of the spent MOX fuel. These facilities are the same as discussed above inSection 4.1 except for the changein ownershipof the MOX fuel fabrication facility. Thus only the schedule forthe MOX fuel fabrication facility is presented below.

4.2.1 MOX Fuel Fabrication Facility, Private Ownership

For this option, the privately-owned MOX fuel fabrication facility is assumed to be a new facility located on anexisting federal site. The duration and path of the license and permit process for the privately-owned MOX fuelfabrication facility has been assumed to follow the same schedule as the federally+wned MOX fuel fabricationfacility discussed in Section 4.1.2.2. The duration of operations for the privately-owned MOX facility is thesame schedule as the federally-owned MOX facility discussed in Section 4.1.2.3.

4.2.1.1 MOX Fuel Fabrication Facility Design & Construction Schedule

The duration and path of the design and constmction tasks for the privately-owned MOX fuel fabrication facilityare based on the same schedule as tie fedemlly~wned MOX facility discussed in Section 4.1.2.1. The onlychange is the issuing of a Request for Proposal (RFP) to select the private developer for this facility rather thana selection process for a M&O contractor. The design and construction schedule is shown in Table 4.15.

Table 4.15 MOX fuel fabrication facility design and construction schedule

Task Duration-,

IDTask Name

(months)Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Approval 36 12/1996 12/1999

3. Fuel Qualification Demonstration 60 4/1996 4/2001

4. Site Selection 12 12/1997 12/1998

5. Issue RFP & Select Private Contractor 12 12/1998 12/1999

6. Desi~n Process 60 12/1996 1 1/2001

7. Facility Construction 36 12/2001 12/2004

4.2.1.2 Private MOX Fuel Fabrication Facility Schedule Summary

The overall private MOX fuel fabrication facility implementation schedule is summarized in Table 4.16 andshown in Figure 4.6.

4.2.2 Existing LWR Alternative Private MOX Facility Case Schedule Summary

The existing LWR alternative private MOX fuel fabrication facility case schedule is a combination of theindividual facility schedules discussed in above. The overall schedule is the same as for the existing LWR basecase discussed in Section 4.1.5.

42

Page 43: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.16 MOX fuel fabrication facility schedule summary

TaskTask Name

DurationID (months)

Start Finish

1. FMDP ROD 12/1996

2. Congressional Funding Approval 36 12/1996 12/1999

3. Fuel Qualification Demonstration 60 4/1996 4/2001

4. Site Selection 12 12/1997 12/1998

5. Issue RFP & Select Private Contractor 12 12/1998 12/1999

6. Licensing and Permitting 60 12/1997 12/2002

7. Design Process 60 12/1996 1 1/2001

8. Facility Construction 36 12/2001 12/2004

9. Preoperational Phase 24 1212004 12/2006

10. PuP Facility Lead Time Complete 9/2006

11. MOX Facility Ready for PuO, 12/2006

12. LUA Fabrication 6 1212006 6/2007

13. MOX Facility Operation Duration 118 6/2007 4/2017

14. Decontamination & Decommission 24 4/2017 4/2019

4.3 Existing LWR Alternative Quick Start with EuroMOX, 50QSL5

Thesecond variant case for the existing LWR alternative uses five separate facilities: a PuP facility to processthe weapts-usable plutonium from the various feed materials to PuOZ, European and domestic MOX fuel -.fabrication facilities to convert the PU02 into MOX fuel, five existing PWRS to irradate the MOX fuel, and aHLW repository for ultimate emplacement of the spent MOX fuel. An additiond storage facility may henecessary to store the PuOJ prior to shipment to Europe and then store the MOX fuel assemblies after shipmentfrom Europe and prior to shipment to the reactor facilities. The preopemtional schedules for these facilities arelargely the same as discussed above for the existing LWR base case in Section 4.1, however the operationalschedules are differerm Also, there is the addition of an existing European fuel fabrication facility to theschedule. Tbe schedule changes for each facility are presented below.

4.3.1 PuP Facility and Prototype

The preopmtional schedule for the PuP facility is the same as descrii above for the existing LWR base casein Section 4.1.1. The setup of the ARIES demonstration is scheduled to be completed in July 1996.

4.3.1.1 PuP Facility and Prototype Operations Schedule

The ARIES prototype is scheduled to begin its operation in January 1998 and will opemte for six years. Asufficient amount of PU02 will be available for shipment to the European MOX fuel fabrication facility in July1999. The facility is scheduled to operate for just over nine years with art annual plutonium throughput of 5MT. The f~st PuOZ will be available for shipment two months after the start of operation. The operationalschedule is shown in Table 4.17 and in the Pu activities in the summary figure in Section 4.3.1.2.

43

Page 44: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.17 PuP facility and prototype operational schedule

TaskTask Name

DurationID (months) Start Finish -

1. ARIES Demonstration and Prototype 78 10/1995 1/2004

2. Set up ARIES Demonstration 9 10/1995 7/1996

3. ARIES Demonstration 18 7/1996 1/19984. ARIES Proto~pe Operation 72 1/1998 1/20045. Sufficient PuOj for shipment 18 1/1998 7/1999

6. Operation 109 7/2006 7/2016

7. Approval to Commence Operation (KD-4) 7/2006

8. Pu Processing Duration 109 7/2006 9/20159. First PuO, Available 2 7/2006 9/2006

4.3.1.2 PuP Facility and Prototype Schedule Summay

The overall PuP facility and prototype implementation schedule is summarized in Table 4.18 and shown inFigure 4.7. This facility schedule is also shown in the discussion of the overall alternative schedule in Section4.3.4. This schedule dces not include any contingency for schedule slip due to site selection difficulties,redesign, construction delays, or a delay in the approval of line item funding.

The critical path through the development of this facility is shown in Figure 4.7. If the start of operations at thePuP facility slips more than three months, the start of operations at the MOX fuel fabrication facility will alsoslip because the PU02 will not be available to begin fuel fabrication at the domestic fuel fabrication facility.Similarly, if the ARIES prototype operation slips more than a year or its output is lower than expected, there ‘“may not be sufficient PuOZto ship to Europe to begin the early fuel fabrication.

Table 4.18 PuP facility and prototype schedule summary

TaskTask Name

DurationID (months) Start Finish

1. R&D Funding Available 10/19952. FMDP Record of Decision 12/19963. Congressional Funding Approval 36 12/1996 12/19994. ARIES Prototype Set Up & Operation 78 10/1995 1/20045. Site & Facility Selection 12 12/1996 12/19976. Oversight and Permitting 60 12/1996 12/20017. Design Process 61 12/1996 1/20028. Facility Modification 48 1/2002 1/20069. preoperational Phase 12 8/2005 7/2006

10. Operation 109 7/2006 9/201511. Decontamination & Decommission 24 9/2015 9/2017

44

Page 45: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

’05

.

z—

DI

ii m EfE

ractor

DOIE”

;

Uctlon

I

7enf Inst

m: Pre

~ Pd

d

~

F! G %—

!101

i—

)n [

‘W

Ice

Ial

;Igl

;Igr

%?

n

h

m

=

ID ITask Name 1’95

1 I FMDP Record of Oeclsion— — — — —

ro )P

=2 Congreasiorml Funding Approval

3 Initial Funding Prmeaa~: II

nlllai FurwhcJ Process

i-l~: Flrml Funding I~-I FhalFundhgApproval I&

!Nte Sele

+ Isal

5 lFualt2ualltbat[on DemoI ‘no

Icc

Ing

EP,

bn

>on

em

;qu

SS2

01

<

t

91 NRC LlcenahgI

10 I Environmental I NEPA I DOE I

&-esa:

PtdlDe

11 Permitting

12 Design Process

13 I Conceptual DesignI

17 I Conatrucfion I

18 Procwement

19 Equipment Installation

IIratlonal

Ihcllify Le

IFFF Re

km

?Faclllfy I

Ikatlon c

~

20 Praoperatbnal Phaae

21 PIIP Facility Lead lime Compkate co!,I

U0222 I MOX FFF Ready for PU02I

-t1Starf

for conl

t

23 OparaUOn

24 MOX Facility Oparatlon start

2s Fabrication of LUAa - for confirmatbn of naw fuel

24 MOX Fual Fabrballon Duration

2T D&Cl

f

Btk

Ss

=

DfI

Fa

D—— — — —

Project: MOX Fual Fabrbatbn Facility I Taak ~ Critical Taak ~ Mi!eatone + Summary ~ w——

Figure 4.6 Private MOX fuel fabrication facility schedule summary

Page 46: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

11

——

——

——

....—

..._...-.

—.

..--—

.....

...

—--

-----

--..—

.—,

...

....-

—...

.—.

-...-

-—--.

..

--—

——

....

—-.--

..-—

...-.

.

-1-

.-..+

-.3._

.q_-

$__.

._.

:-_;..

--.--

.&q.

.-$

—-—

-..

....-

-.-—

.—.

.—g—

.~’

—.-

.—

.-..—

...—

—-.

——

——

—~—

.

E—

—..—

._—

.——

.—

..—

ii

pa—

.&f

—_-

---e

:_=

g~

—g

——

—-—

g

%

3—

—.—

——

~_.

.._

._~_

._—

.——

-.__

—:_

:.__-

—..

-....

.—.-

..——

.=

o2

3=g

-u.

—:

-–:—

—..—

..——

—[c

o---

----

---

--–-

--—

-—q

.–...

.-—

.-.–

____

.._

.-...

c[c u

●�✍

✍❞✍

✎✎

✎ ‘1{

—.—

- ~$

$~y

&m

1:—

~—

-—3–

-.-

0

s.-

:_5

“=2

g—

~—-u

—g

——

-..—

.-.-

——

.-—

____

_

I:—

—~‘-

–—..—

-–--

——

—.-

--...

.—g

——

g-i?

....—

.—

——

..—

W.-

–:

-——

:—$

-–p_

._._

—--

.–__

-.._

.c

—--

--g

—a

—.

——

.—

—-.

—.-

—...

——

-.—

.—

—--

----

-

cm

3~

$._

:.—

—_—

2—:

—..-

...—

-..

...

.....

..

....

.....

....

..

....

...

...

...

....

...

.....

....

.....

...

....

...

–;

—~

—&

—-—

--—

.–—

.——

.——

----

----

----

-~--

----

----

f

IIm

—..

..

..–j-

--–.

.-_-

&-..

.....

.....

.......

....

....

.........

.....

......

.....

.....

..........

.........

.........

...=

----

-g-

–.-.

—:-—

–—.–

-—–-

––—

1;.............

......................................

............~

zi

..—...—

—.

.—o—

-—

.—-

~—

—.–

--—

-.—

——

—.—

——

.—....

.—-.

——

—–—

—.-

.—.-

.—.–

——

—-—

~G

.—--

----

---

——

~—i

—...

.—--

-.

.....

.....

..

..

...

....

..

...

....

.....

...

...

.....

.....

......

.....

.....

....

..

..

.....

.....

g

!i

.—-.-. ~...

........

...........

.............

...............

....................

............

..........

..c ;.

-.;

..

.....

......

...

....

..

..

...

...

....

.....

.....

...

...

...

...

.....

......

....

.....

.....

.....

....

...

....

......

.....

......

......

......

....

......

......

......

......

....

10 ,. * =.

I

Page 47: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

4.3.2 MOX Fuel Fabrication Facility and EuroMOX Fuel Fabrication

The MOX fuel fabrication facility preoperational schedule for this alter-native is the same as described above forthe existing LWR base case in Section 4.1.2.

The contract negotiations with the European fuel fabricator and the licensing and permitting requirements for

shipping Pu02 to Europe are estimated to require 16 months and will begin after the approval of the intermediateline item funding.

4.3.2.1 MOX Fuel Fabrication Facility Operations Schedule

Fabrication of the LUAS will begin in Europe as sea as the fwst PU02 arrives in June 2000; after which, theEuropean fuel fabrication facility will fabricate 85 assemblies a year for 4.4 years, which corresponds to anannual plutonium throughput rate of 1.5 MT and a mission total of 375 assemblies.

The preoperational checkout of the domestic MOX fuel fabrication facility starts as soon as the constmction iscomplete and will take two years. The LUAS are fabricated in the facility during the six-month start-up period.Then, this facility will operate for 8.5 years with an annual plutonium throughput rate of 5 MT, supplying fuelfor the 5 existing PWRS at the sp.xitled loading rate. This throughput assumes an annual output of 280assemblies for a mission total of 2381 assemblies.

The operational schedule is shown in Table 4.19 and in the MOX fuel fabrication activities schedule summaryfigure in Section 4.3.2.2.

Table 4.19 ‘MOX fuel fabrication facility operational schedule

TaskTask Name

DurationID

-.

(months) Start Finish

1 European Facility Interactions 80 12/1998 812005

2 Contract Negotiation & Approval 16 12/1998 412000

3 Initial PuO, Shipment to Europe 2 4/2000 6/2000

4 Fabrication of LUAS 9 6/2000 3/2001

5 LUA Shipment from Europe 2 3/2001 6/2001

6 Mission Fuel Fabrication 53 3/2001 8/2005

7 Initial Mission Fuel Shippe d from Europe 2 3/2001 6/2001

8. Domestic MOX Facility Operations 108 12/2006 12/2015

9. MOX Facility Operation Start 12/2006

10. LUA Fabrication 6 12/2006 6/2007

11, Operation 102 6/2007 12/2015

4.3.2.2 MOX Fuel Fabrication Facility Schedule Summary

The overall MOX fuel fabrication activities schedule is surnman.ZUI in Table 4.20 and shown in Figure 4.8.These activities are also shown in the discussion of the overall alternative schedule in Section 4.3.4. Thisschedule does not include any condngency for schedule slip due to site selection difficulties, redesign,construction delays, or a delay in the approval of line item funding.

The critical path through the development of the domestic MOX fuel fabricationconceptual design and the NRC licensing process. If either of these tasks slip in theirimplementation process will also be delayed. This critical path is shown in Figure 4.8.

F

facility is through theschedule, the rest of the

47

Page 48: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.20 MOX fuel fabrication activities schedule summary

TaskTask Name

DurationID (months)

Start Finish

1 FMDP Record of Decision 12/1996

2 Congressional Funding Approval 36 12/1996 12/1999

3 Fuel Qualification Demo 60 4/1996 4/2001

4 European Facility Interactions 80 12/1998 8/2005

5 Domestic MOX fuel fabrication facility 252 12/1996 12/2017

6 Site & Facility Selection 12 12/1997 12/1998

7 Select M&O Contractor 12 12/1998 12/1999

8 Licensing and Permitting 60 12/1997 12/2002

9 Design Process 60 12/1996 1 1/2001

10 Facility Modification 36 12/2001 1212004

11 Preoperational Phase 24 12/2004 12/2006

12 Operation 108 12/2006 12/2015

13 Decontamination & Decommission 24 12/2015 12/2017

4.3.3 Existing PWR Facility

The existing PWR facility design and construction schedule for this alternative is the same as described abovefor the existing LWR base case in Section 4.1.3.1

4.3.3.1 Existing PWR Facility Quick Start Licensing and Permitting Schedule

The existing LWR facility licensing and permitting schedule for this alternative is the same as de-scribedabovefor the existing LWR base case in Section 4.1.3.2. However, the fuel qualillcation process begins 4.5 yearsearlier than in the base case because the European fabricated LUAS are available much sooner than thedomestically fabricated LUAS. This change in the fuel qualification and reload permit schedule is shown in Table4.21 and in Figure 4.9.

Table 4.21 Existing PWR facility quick start license and permit schedule

TaskTask Name

DurationID (months)

Start Finish

1. NRC Interactions 51 12/1999 212004

2 Environmental / NEPA / NRC 24 12/1999 1 1/2001

3 LUA & Reload Licenses 72 12/1999 11/2005

4 LUA Licensing 36 12/1999 1 1/2002

5 Reload Approval 18 512004 11/2005

6 Fuel Qualification - LUAS 126 6/2001 12/2011

7 European LUAS Arrive 6/2001

8 European LUA Irradiation 54 1212002 6/2007

9 Domestic LUAS Arrive 6/2007

10 Domestic LUA Irradiation 54 6/2007 12/2011

...

48

Page 49: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

...—

....-—-—

——

...-—

.——

..—-

=n—5---.—

——

—-—

_____-.-—

___.=

——

-——

—.—

—~

_.Q

n

Iz~

——

——

-.——

——

,——

—-!

~“

p~f#.l-.!-

___..

_...

_...

_._

...._

......._.

w~

~—

~—P

‘“----””””--”--”--F

F0:-.L

IIu&LA

———

0.—

w

-,m-a’

Page 50: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

4.3.3.2 Existing PWR Facilify Operations Schedule

The LUAS are loaded into the fwst unit as soon as the LUA license is granted and during a normal refuelingperiod for the reactor. After the completion of the LUA review during the second irradiation cycle, the firstEuropean fabricated mission fuel is loaded at the next scheduled refueling period in November 2005. The MOXfuel loading schedule was discussed in Section 2.2.3.1. After three irradiation cycles, the spent fuel assemblieszue discharged from the reactors and stored in the spent fuel storage pool for a minimum of ten years keforebeing shipped to the HLW repository facility. The existing LWR facility operational schedule is shown in Table4.22 and in the PWR facility schedule summary figure in Section 4.3.3.3.

4.3.3.3 Em”stingPWR Facility Schedule Summary

The overall existing PWR facility implementation schedule is summarized in Table 4.23 and shown in Figure4.9. This facility schedule is also shown in the discussion of the overall alternative schedule in Section 4.3.4.The critical path for this facility is the intermediate line item funding approval, utility selection and completionof the LUA license. The critical path for this facility is shown in Figure 4.9.

Table 4.22 Existing PWR facility quick start operations schedule

TaskTask Name

DurationID (months)

Start Finish

1. Reactor “ready” to ac;ept MOX 212004

2 Reactor Facility Operation 211 11/2005 712023

3 unit 1

4 European MOX Loading Duration 54 11/2005 5I201O

5 American MOX Loading Duration 90 5/2010 11/2017

6 Unit 2

7 European MOX Loading Duration 54 4/2006 10/2010

8 American MOX Loading Duration 90 10/2010 4/2018

9 Unit 3

10 European MOX Loading Duration 54 8/2006 2/201 1

11 American MOX Loading Duration 90 2/2011 8/2018

12 Unit 4

13 European MOX Loading Duration 54 1/2007 7/201 1

14 American MOX Loading Duration 90 7/201 1 1/2019

15 Unit 5

16 European MOX Loading Duration 54 1/2007 7/201 1

17 American MOX Loading Duration 72 7/201 1 7/2017

18 Last Assemblies - single cycle 18 1/2019 7/2020

19 Last Assembly Discharged 54 1/2019 712023

20 Spent Fuel Storage 277 5/2010 7/2033

21 First MOX in Spent Fuel Pool 120 5/2010 512020

22. Last MOX 120 712023 712033

50

Page 51: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.23 Existing PWR facility quick start schedule summary

Task DurationID

Task Name(months) Start Finish

1 FMDP Record of Decision 12/1996

2 Congressional Funding Approval 36 12/1996 12/1999

3 Utility Selection 12 12/1998 12/1999

4 Licensing 51 12/1999 2/2004

5 Reactor Modifications 48 12/1999 11/2003

6 LUA & Reload Licenses 72 12/1999 11/2005

7 Fuel Qualification 126 6/2001 12/2011

8 Reactor Facility Operation 211 11/2005 712023

9 European MOX Loading Duration (Units 1-5) 54 11/2005 5/2010

10 American MOX Loading Duration (Units 1-5) 103 5/2010 1/2019

11 Last Assemblies - single irradiation cycle 18 1/2019 7/2020

12 Last assembly discharged after three cycles 54 1/2019 7/2023

13 Spent Fuel Storage 277 5/2010 712033

14 First MOX in Spent Fuel Pool 120 5/2010 5/2020

15 Last MOX 120 712023 7/2033

4.3.4 HLW Repository Facility

The HLW Repository facility schedule for this alternative is the same as descrked almve for the existing LWRbase case in Section 4.1.4 except for the spent MOX fuel delivery schedule. The first spent fuel will arrive at the -’HLW repository facility in June 2020 and the last delivery is scheduled in August 2033.

4.3.5 Existing LWR Alternative Quick Start with EuroMOX Schedule Summary

The existing LWR alternative quick start case schedule is a combination of the individual facility schedulesdiscussed above. This overall schedule is summarized in Table 4.24 and shown in Figure 4.10. The plutoniumdisposition mission begins when the fwst mission fuel is leaded into a reactor in Novemlxr 2005 and iscomplete after the last core loa& which contains MOX fuel assemblies, has been irmdiated for a single cycle inJuly 2020. The overall mission time is 14.6 years and starts 9 years after ROD.

The critical path for this alternative is the line item approval, utility selection, and LUA licensing for the LWRfacility. However, if there are any &lays in the ARIES prototype development or a reduction in the ARIESprototype throughput, there may be insufficient PuOZ to supply the European fuel fabrication activity at therequired rate.

51

Page 52: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.24 Existing LWR quick start alternative schedule summary

TaskTask Name

DurationID (years)

Start Finish

1 FMDP Record of Decision 12/1996

2 Congressional Funding Process 3 12/1996 12/1999

3 PuP Facility and Prototype 21.9 10/1995 9/2017

4 R&D and Facility Design 6.3 10/1995 1/2002

5 Prototype Operation 6 1/1998 1/2004

6 Licensing, Permitting & Siting 5 12/1996 12/2001

7 Facility Modification & Preoperation 4.5 1/2002 7/2006

8 Production Facility Operation 9.1 7/2006 9/2015

9 Decontamination & Decommissioning 2 9/2015 9/2017

10 European MOX fuel fabrication facility 6.8 12/1998 912005

11 Contract Negotiation 1.4 12/1998 4/2000

12 Fabricate and Ship LUAS 1.1 4/2000 612001

13 Mission Fuel Fabrication 4.5 3/2001 9/2005

14 Domestic MOX fuel fabrication facility 21.6 4/1996 12/2017

15 Fuel Qualification 5 4/1996 4/200 1

16 Licensing, Permitting & Siting 5 12/1997 12/2002

17 Facility Design, Modification & Preoperation 10 12/1996 12/2006

18 Fabrication of LUAS .5 12/2006 6/2007

19 Operation 8.5 6/2007 12/2015

20 Decontamination & Decommissioning 2 12/2015 12/2017

21 Reactors 34.6 12/1998 7/2033

22 Utility Selection 1 12/1998 12/1999

23 LUA Licensing 3 12/1999 11/2002

24 European Lead Use Assemblies 4.5 1212002 6t2007

25 American Lead Use Assemblies 4.5 6/2007 12/201 1

26 MOX Loading Duration 13.1 11/2005 1/2019

27 Spent Fuel Pool Duration 23.1 5/2010 7/2033

28 Repository

29 Licensing & Construction 8.5 3/2002 8/2010

30 MOX Delivery Duration 13.1 6/2020 812033

,.

52

Page 53: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

2m6

!III

a

bdifi

I

Ieloa

~21X16 2010

)8 09 10 1

1

I

\

mI

I

I>prwal

I

,

2030

III

bID Task Name w

1 FMDPRecord of Deckkm 1: T2M2 2004)2 a3 04 o!

ckion

14 I

@rev al

roval

mtion

- 1 Lb8r

- React

~

r~ LLJALicem

GIII

3ti0n

ves

,mern

—#lion

m M(

2014III

LUA

2016

m

2020

m

2022

ax

2024

@

g DUI

- sin

it Ass

2026

m

m (U1

irrad

bfy D

2026

Iiz

1.5)

n wc

2m4

Zlz

s

s! MC

2000

EEi

xd d

2 lCongressiomlFu”dl”gApproval I IFumI

3 IntermediateApproval nedia

q FindkwxdI ‘inal I

5 lUtMtySe)8cti0”I Jtilify

1

6 LicensingI

7 Reactor Mcdlflcatlons1

I8 LUA 6 Rekad Lkenses

I9 LUALicensing

10 I Rebad Approval II

11 Fuel (kudiflcellon—d au!

;urcp

5

12 I E.rope6.LUAArrivesI LUA

I

13 EuropeanLUA Irradiation Es

14 AmericanLUAArrkes

15 AmericanLUAIrradiatim

~ EuropeanMOXLoadiwgDuraticm(Unis 1-5) )urat (Unit

~A

m

m

5)

la AmericanMOXLo6ding Duration(Units 1-5)

19 Last Assetillca - single Irradktlon cycle

20 LastAssarrblyDischargedafter thrae full eye!.ss

21 Spent Fuel Storage

h n

Iurged after th

I— -

LFM )X in ,nt FLI &-b— — — .

Figure 4.9 Existing PWR facility quick start schedule summary

Page 54: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

——

.-..-

.

i 3

.-.-.

.

--—

—.

____

____

____

____

____

_-.

.——

.——.

_..._

-,T

---+–

3-–-

-”’.

F——

. .— .......

NI

-16

--.-..

-..-..

.-..--

---7-

J.*-

-__.

._._

__~-

.-I._

_~...

_j._

_.__

~_g_

.._.

—-

.—

i

-4

..-

1 — —....—— — -E

.--

-”--

--””

-’--

-”—

“““. :$ !8:

%2

—yk

—R

h

~i

_.-.

--.

__.

-._.

.__.

___-

._.

._..

-..

-..._

.._.

.._.._

-_..

_._.

__._

.._-_

._.

.._.,

_.._

..---

.--

._..

_.-_

..__

____

__

g:$

-—

—::

..—__

____

—-.

—--

—.

g%

>

i?~;

----

....

....

....

....

....

..

....

....

....

..

....

....

...

....

....

....

..

....

.....

....

......

....

..

....

....

...

...

....

..

....

....

.0 :

%2

_gg;

Page 55: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

4.4 Existing LWR Alternative 32.5 MT Hybrid, 33SFL3

The third variant case for the existing LWR alternative will dispose of 32.5 MT of the surplus weapons-usableplutonium. The other 17.5 MT of Pu will be disposed of using one of the immobilization-based dispositionalternatives, which are described in the Immobilization Alternatives Technical Summary Reports (4). Thereactcx-based part of this alternative uses four separate facilities: a PuP facility to process the weapons-usableplutonium from the various feed materials to PU02, a domestic fuel fabrication facility to convert the PuOZ intoMOX fuel, three existing PWRS to irradiate the MOX fuel, and a HLW repository for ultimate emplacement ofthe spent MOX fuel. The preoperational schedules for these facilities are the same as discussed above for theexisting LWR base case in Section 4.1, however, the operational schedules are dfiferent. The schedule changesfor each facility are presented below.

4.4.1 PuP Facility

The overall PuP facility implementation schedule for this alternative is the same as described above for theexisting LWR base case in Section 4.1.1. The annual PuP facility output is split between the MOX fuelfabrication facility and the immobilization disposition option with 3.25 MT/yr. going to the MOX facility ad1.75 MT/yr. going to the immobilization facility. The PuP facility schedule summary is shown in thealternative summary table and figure in Section 4.4.5.

4.4.2 MOX Fuel Fabrication Facility

The preoperational MOX fuel fabrication facility implementation schedule for this alternative is the same asdescribed above for the existing LWR base case in Section 4.1.2. The MOX fuel fabrication facility will beginoperations in December 2007. The LUAS are fabricated at the MOX fuel fabrication facility during the six-month start-up period. Then, this facility will operate for 10.7 years with an annual plutonium throughput mte

of 3.1 MT, supplying fuel for the 3 existing PWRS at the specitkd loading rate. This throughput assumes an “annual output of 170 assemblies for a mission total of 1819 assemblies. The MOX fuel fabrication facilityschedule summary is shown in the alternative summary table and figure in Section 4.4.5.

4.4.3 Existing PWR Facility

The preoperational existing PWR facility implementation schedule for this alternative is the same as describedabove for the existing LWR base case in Section 4.1.3. Only three reactor units axe used in this alternativebecause the annual PuOZoutput of the PuP facility will not support five reactors and the immobilization feedrequirement. The reactor loading and dkcharge schedule was dkcussed in Section 2.2.3.1. The f~st mission fuelwilt be loaded into a reactor in June 2007 and the last MOX fuel will be loaded in November 2020. The existingPWR facility schedule summary is shown in Table 4.25 and in the alternative summary figure in Section 4.4.5.

4.4.4 HLW Repository Facility

The overall HLW Repository facility schedule for t.hk alternative is the same as described above for the existingLWR base case in Section 4.1.4 except for the spent MOX fuel delivery schedule. The fwst spent fuel isscheduled to be delivered in December 2024 and the last spent fuel will arrive in June 2035. This schedule isshown in the alternative summary table and figure in Section 4.4.5.

4.4.5 Existing LWR Alternative Hybrid Schedule Summary

The existing LWR alternative 32.5 MT case schedule is a combination of the individual facility schedutesdiscussed above. This overall schedule is summarized in Table 4.26 and shown in Figure 4.11. The plutoniumdisposition mission begins when the fust mission fuel is loaded into a reactor in May 2010 and is completeafter the last core load, which contains MOX fuel assemblies, has been irradiated for a single cycle in May 2022.The overall mission time is 12 years and starts 13.5 years after ROD. The critical path for this alternative is thelicensing, design and facility modifications for the MOX fuel fabrication facility.

55

Page 56: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.25 Existing PWR facility, three reactor schedule summary

TaskTask Name

DurationID (months)

Start Finish

1. Fuel Qualification - LUAS 54 6/2007 12/2011

2. Reactor Operations 180 5I201O 5/2025

3. Unit 1 Loading Duration 126 5/2010 1 1/2020

4. Unit 2 Loading Duration 108 11/2010 11/2019

5. Unit 3 Loading Duration 108 5/2011 5/2020

6. Last Assemblies - fwst irradiation cycle 18 1 1/2020 512022

7. Spent Fuel Storage 246 11/2014 6/2035

Table 4.26 Existing LWR hybrid alternative schedule summary

TaskTask Name

DurationID (years)

Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Process 3 12/1996 12/1999

3. PuP Facility 22.8 10/1995 7/2018

4. R&D 3 10/1995 9/1998

5. Oversight, Permitting & Siting 5 12/1996 12/2001

6. Design 5.1 12/1996 1/2002

7. Facility Modification & Preoperation 4.5 1/2002 7/2006

8. Operation 10 7/2006 7/2016

9. Decontamination & Decommissioning 2 8/2016 7/2018

10. MOX fuel fabrication facility 23.8 4/1996 212020

11. Fuel Qualification 5 4/1996 412001

12. Licensing, Permitting & Siting 5 12/1997 12/2002

13. Design 5 12/1996 1 1/2001

14. Facility Modification & Preoperation 5 12/2001 12/2006

15. Fabrication of LUAS 0.5 1212006 6/2007

16. Operation 10.7 6/2007 2/2018

17. Decontamination & Decommissioning 2 2/2018 212020

18. Reactor Facility 36.5 12/1998 6/2035

19. Utility Selection 1 12/1998 12/1999

20. Licensing 4.2 12/1999 2/2004

21. Reactor Modifications 4 12/1999 11/2003

22. Reactor “ready “ to accept MOX 2/2004

23. Lead Use Assemblies 4.5 6/2007 12/2011

24. MOX Loading Duration 10.5 5/2010 1 1/2020

25. Single irradiation cycle of last MOX 1.5 1 1/2020 512022

26. Spent Fuel Pool Duration 20.5 1212014 6/2035

27. HLW Repository Facility

28. Licensing 8.5 312002 8/2010

29. Construction 5.5 312005 8/2010

30. MOX Delivery Duration 10.5 12/2024 6/2035

-.

Page 57: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

n5———

—...__.-.__—

_-——

____—

—-—

’—

FT3 —-

——

—.—-..~

–kF

___...___._:g:g_

____—

—_-----.

-.-.—.-.--.-—

.—,-

.--—-

,5E

si

.:E

zn—

~—

j6

0

:P

06—

“:—

~—

.-5

5,=$2

:;–6

-——

-.-.—.---—

——

.=—

—--—

...-.-—

-.--

——

-——

.—

.-—-

~—

-.

1=u-)

ms.*-W)

.-F3

—38r—r—

——

R—

Page 58: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

4.5 Existing LWR Alternative Collocated PuP/MOX, 50COL4

The fourth variant for the existing LWR alternative uses three separate facilities: a collocated PuP and MOX fuelfabrication facility to process the weapons-usable plutonium from the various fetal materials into MOX fuel,four existing BWRS to irradiate the MOX fuel, and a HLW repository for ultimate emplacement of the spentMOX fuel. The implementation schedule for each of these facilities is discussed below, followed by a summaryschedule for the overall alternative.

4.5.1 Collocated PuP and MOX Fuel Fabrication Facility

The collocated PuP and MOX fuel fabrication facility is a combination of the two facilities discussed above forthe existing LWR base case in Sections 4.1.1 and 4.1.2.

4.5.1.1 Collocated PuP and MOX Facility Design& Construction Schedule

The dumtion and path of the design and construction tasks for the collocated PuP and MOX fuel fabricationfacility are a combination of the tasks discussed for the existing LWR base case in Sections 4.1.1.1 and 4.1.2.1.The combined design and construction schedule is shown in Table 4.27 and in the facility schedule summaryfigure in Section 4.5.1.5.

Table 4.27 Collocated PuP and MOX facility design and construction schedule

Task DurationID Task Name

(months)Start Finish

1. R&D Funding Available 10/1995

2. FMDP Record of Decision 12/1996 ...

3. Congressional Funding Approval 36 12/1996 12/1999

4. Fuel Quali~lcation Demo 60 4/1996 4/2001

5. Research & Development 36 10/1995 9/1998

6. Site Selection 12 12/1997 12/1998

7. Select M&O Contractor 12 12/1998 12/1999

8. Design Process 60 12/1996 11/2001

9. Conceptual Design 25 12/1996 1/1999

10. Title I 12 12/1999 12/2000

11. Title It 12 12/2000 1 1/2001

12. Facility Construction 53 1/2002 6/2006

13. Construction 53 1/2002 6/2006

14. Procurement 36 1/2002 12/2004

15. Equipment Installation 17 1/2005 6/2006

4..5.1.2 Collocated PuP and MOX Facility Licensing and Permitting Schedule

For this analysis, it has been assumed that the duration of the NRC licensing process will be five years and thatthe process will start one year before the conceptual design is complete. The NEPA process and the other site-specitlc permitting will require three years; each process will start after the site has been selected. The licensingschedule is shown in Table 4.28 and in the facility schedule summary figure in Section 4.5.1.5.

58

Page 59: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.28 Collocated PuP and MOX facility licensing and permitting schedule

TaskTask Name

Duration

ID (months)Start Finish

1. Licensing and Permitting 60 1/1998 1/2003

2. NRC Licensing 60 1/1998 1/2003

3. Environmental / NEPA / DOE 36 12/1998 1 1/2001

4. Permitting 36 12/1998 1 1/2001 ,

4.5.1.3 Collocated PuP and MOXFuel Fabrication Facility Operations Schedule

The preoperational checkout of the collocated PuP and MOX fuel fabrication facility will start one year beforethe equipment installation is complete and will take two years. The Pu processing section of the facility willoperate for ten years with an annuaI plutonium throughput of five MT. The LUAS are fabricated in the MOXfuel fabrication section of the facility during the six-month start-up period. Then, this section of the facility willoperate for 15.6 years with an annual plutonium throughput rate of 3.2 MT. This throughput assumes an annualoutput of 602 assemblies for a mission total of 9416 assemblies and will supply fuel for the four existingBWRS at the specitied loading rate. The operational schedule is shown in Table 4.29 and in the facility schedulesummary figure in Section 4.5.1.5.

Table 4.29 Collocated PuP and MOX fuel fabrication facility operational schedule

TaskTask Name

Duration

ID (months)Start Finish

1. Preoperational Phase 24 6/2005 6/2007

2. Operation 193 6/2007-..

712023

3. Facility Operation Start 6/2007

4. LUA Fabrication 6 6/2007 1212007

5. Pu Processing Operation 120 6/2007 6/2017

6. MOX Operation 187 12/2007 712023

4.5.1,4 Collocated PuP and MOXFacility Decontamination& Decommissioning Schedule

The duration for the decontamination and decommissioning of the facility has been estimated to be two years.

4.5.1.5 Collocated PuP and MOX Fuel Fabrication Facility Schedule Summary

The overall collocated PuP and MOX fuel fabrication facility implementation schedule is summarized in Table4.30 and shown in Figure 4.12. This facility schedule is also shown in the discussion of the overall alternativeschedule in Section 4.5.4. This schedule does not include any contingency for schedule slip due to site selectiondiftlculties, redesign, construction delays, or a delay in the approval of line item funding.

The critical path through the development of this facility is through the conceptual design and the NRClicensing process. If either of these tasks slip in their schedule, the rest of the implementation process will alsobe delayed. This critical path is shown in Figure 4.12.

59

Page 60: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

——

——

—J ( 1 ( , ,

.

r.—

. .--

----

-.——

...

...

....

m o .-:

—..—

/

t

<--

~_.

_-....

.–.-..

...__

.~ z

g.=

——

—6

~<

~~

~C

g.;

—-g

~ ——

—._

..__

.__

......

...

...

..

——

—-.

—-.—

——

—__

____

__—

—-—

..—

.—.

Page 61: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.30 Collocated PuP and MOX fuel fabrication facility schedule summary

TaskTask Name

Duration

ID (months)Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Approval 36 12/1996 12/1999

3. Fuel Qualification Demonskation 60 4/1996 4/2001

4. Site and Facility Selection 12 12/1997 12/1998

5. Select M&O Contractor 12 12/1998 12/1999

6. Licensing and Permitting 60 1/1998 1/2003

7. Design Process 60 12/1996 1 1/2001

8. Facility Construction 53 1/2002 6/2006

9. Preoperational Phase 24 6/2005 6/2007

10. LUA Fabrication 6 6/2007 12/2007

11. Pu Processing Operation 120 6/2007 6/2017

12. MOX Fuel Fabrication Operation Duration 187 12/2007 712023

13. Decontamination & Decommission 24 712023 712025

4.5.2 Existing BWR Facility

4.5.2.1 Existing BWR Facility Design & Construction Schedule

The design and construction fasks for the existing BWR facility have been assumed to be the same as the tasksdescribed above in Section 4.1.3.1 for the existing PWR facility.

..

4.5.2.2 Existing B WR Facility Licensing & Permitting Schedule, For this analysis, a schedule developed by Fluor Daniel (9) for modifying an existing LWR facility license to

permit the use of MOX fuel with integrat neutron absorbers was followed. The process to obtain a reload permitfor a new fuel fabricator is also included in the permit schedule. The license and permit schedule is shown inTable 4.31 and Figure 4.13.

The license amendment (LA) process for the use of MOX fuel with integral neutron absorbers is longer than theprocess used for the license amendment for the use of MOX fuel without integral neutron absorbers, discussedabove for the existing LWR base case in Section 4.1.3.2. The license and permit prccess for the BWR caseincludes the possibility of full discovery and a hearing process by an Atomic Safety Licensing Board (ASLB) aswell as a longer license preparation time.

After the utility or utilities have been selectexl the license amendment (LA) process is started with thepreparation of the safety analysis report, the LA application, and the environmental report. The NRC issues thesafety evaluation report and the environmental assessment after completing the review of the application. Theschedule includes a provision for a year-long full discovery period and an eighteen-month hearing and decisionprocess by an ASLB. The requirements for these processes are subject to petitions for a hearing on specificissues. After a decision is issued by the ASLB, the NRC issue the license amendment to the Operating License(OL).

In addition, a reload license prmess is followed because of the use of a new MOX fuel fabrication facility. Thisanalysis assumes a three year LUA license process is followed prior to inserting the LUAS into the reactor. After

the LUAS have been irradiated for one cycle, 1.2 years for the BWR, a review of the LUA ~rfonnance is

completed. The reload permit for use of MOX fuel is granted after this review.

61

Page 62: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 4.31 Existing BWR facility license and permit schedule(

TaskTask Name

DurationID (months)

Start Finish

1 NRC Interactions 63 12/1999 312005

2 Licensee Prepares SAR & License Amendment 18 12/1999 6/2001

3 Licensee Files Application 6/2001

4 Pubtic Notice of Application for LA 3 6/2001 9/2001

5 NRC Review 12 9/2001 912002

6 NRC Issues SER 912002

7 Full Discovery 12 6/2002 6/2003

8 Hearing by ASLB 9 6/2003 312004

9 Decision by ASLB 9 312004 12/2004

10 ASLB Issues Decision 1212004

11 NRC Issues License Amendment 3 12/2004 3/2005

12 Notice of Amendment to Operating License 3/2005

13 Environmental / NEPA / NRC 33 12/1999 9/2002

14 Licensee Develops & Prepares ER 12 12/1999 12/2000

15 Licensee Files Report with NRC 6/2001

16 NRC Prepares & Issues Draft EA 6 6/2001 12/2001

17 NRC Issues Final EA 3 6/2002 9/2002

18 LUA & Reload Licenses 124 12/1999 4/2010

19 LUA Licensing 36 12/1999 11/2002

20 Reload Approval 14 2/2009 4/2010

21 Fuel Qualification - LUAS 73 12/2007 12/2013

22 LUA Arrives 12/2007

23 LUA Irradiation 73 12/2007 12/2013

4.5.2.3 Existing B WR Facili~ Operations Schedule

The LUAS are loaded into the f~st unit as soon as they are available and during a normal refueling period for thexeactor. After the completion of the LUA review during the second irradiation cycle, the first mission fuel isloaded at the next scheduled refueling period in April 2010. After full irradiation of the MOX fuel, the spent fuelassemblies are discharged from the reactors and stored in the spent fuel storage pool for a minimum of ten yearsbefore being shipped to the HLW repository facility. The existing BWR facility operational schedule is shownin Table 4.32 and in the BWR facility schedule summary figure in Section 4.5.2.4.

...

62

Page 63: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

—. )0

EII

)R

I

I

)02 2003200420052006 2W

Wll

ma—

I

sis

?rm

ndrl

)0s—

,mf

It t(

)12.

prc

IS

z=

D1d—

LU

11!

ra

)1(

;io

ns;e Pre’pares’SAR’& LA/l!~;~

:ensaa Files Applieafion ~

i)::: ii ii

Ibiic Notice of ADO. for LA i

3 Licensee Files Application

4 Publk Notica of App. for LA

51 NRC Review I’31 NRC Issues SER I7 I Full Discovery

I /6??3

+u/i.

s Heari~ by ASLB

9 Deciskm by ASLB

10 I ASLB Iaauaa DecisionI

11 I NRC bauaaLicecsaAmemfrnenf I

12 I Notice of Amendment to OL I

13 Envk.ncnental I NEPA I NRC

14 Lbenaee Develops& Prepares ER;:; ;:!! :

iceflaea heveloos & PreDaresER

15 1 Licensee Filea Reporl with NRC I16 I NRC F’repa,es& bauesClraftEA I

17 I NRC Issues Final EAI

18 LUA & Reload Licenses

19 LUA Licensing

@ss

&, LUA Art

!

-

ml Rebad ApprovalI ...

21 lFkscforModflmfionsI

22 lFualOualiiication -LUA.I

23 LUA Arrives

24 LUA Irradiationr ,

Proiact: Reactor License & PermfiTask

,. -

I Critical Task ~ Summary ~

Figure 4.13 Existing BWR facility license and permit schedule

Table 4.32 Existing BWR facility operations schedule

Task DurationID

Task Name(months)

Start Finish

1. Reactor “ready” to accept MOX 3/2005

2. Fuel Qualification 73 6/2007 12/2013

3. Reactor Facility Operation 268 4/2010 812032

4. Unit 1 Loading Duration 199 4/2010 10/2026

5. Unit 2 Loading Duration 185 4/2011 8/2026

6. Unit 3 Loadin~ Duration 171 4/2012 6/2026

7. Unit 4 Loading Duration 157 4/2013 5/2026

8. Last Assemblies - single cycle 14 10/2026 1212027

9. Last Assembly Discharged 70 10I2026 8/203 2

10. Spent Fuel Storage 330 3/2015 8/2042

11. First MOX in Spent Fuel Pool 120 3/2015 2/2025

12. Last MOX 120 812032 812042

63

Page 64: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

4..S.2.4 Existing B WR Facility Schedule Summary

The overall existing BWR facility implementation schedule is summarized in Table 4.33 and shown in Figure4.14. This facility schedule is also shown in the discussion of the overall alternative schedule in Section 4.5.4.The critical path for this facility is the availability of the LUAS and is shown in Figure 4.14. The reactors areready to accept MOX LUAS almost three years before the LUAS are available.

Table 4.33 Existing BWR facility schedule summary

TaskTask Name

DurationID (months)

Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Approval 36 12/1996 12/1999

3. Utility Selection 12 12/1998 12/1999

4. Licensing and Permitting 63 12/1999 3/2005

5. LUA & Reload Licenses 124 12/1999 4/2010

6. Reactor Modifications 48 12/1999 12/2003

7. Reactor “ready” to accept MOX 3/2005

8. Fuel Qualification 73 12/2007 12/2013

9. Reactor Operation 268 412010 812032

10. Last Assemblies - single cycle 14 1012026 12/2027

11. Spent Fuel Storage 330 3/2015 812042

4.5.3 HLW Repository Facility

The HLW repository facility schedule is the same as described for the existing LWR base case in Section 4.1.4,..

except the spent MOX fuel is scheduled to be delivered to the repository facility from March 2025 to September2042.

64

Page 65: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

5012 20142 13 14 1!

t

I

I

,

?ii2II

iatk

L40

ID Task Name1 FMDPRecord d Deddon 2/1

~

‘ma 201C

BLWID1

Wa I

sing

PA I DOE

G

@

1024

m

!032

Zlz

r

atior

Nion

tion

Ibn

!$-!

la96 I 199a I 2000 I 2002 ] 2004 I 2006

61971981 WlM]O11021~lW [M1W107

!026

@

● FMDPbecord’ofDeJsiOn I

IllcongressionalFurdmg A+

,ihw~kd~n1

“2-/Cmgrmtlo”alFundl”gA~roval /I

3 Utility Selection

4 lLlcendng I

5 I NRCLicemi”gI

Ia Environmental/ NEPA/ DOE

1

7 I LUA 6 Raload Licenses i

6 LUA LkmsingI

9 ReloadA@prwal

MIX

Iea.a

I

134

10 Illsactorhdifi.diem I lea<I

11 Reactor “ready” to accept MOX urea,

?-J

L(J

s

12 lFualQuallflccMon I1

13 LUAArrives

14 I LUAlmadiatio”I[

15 Raactor FacllitY(-ies) OparatlcmI

16 Unit 1LoadingDuration 1L(

2 Lo

Lcx

Loa

rg[

-mJC

gD

aD[

I

17 Unit2 LoadingDuratimI

16 Unit3 LoadingDurationI

11s Unit4 LoadingDurati.m

I20 Last Assamblleo - single Irradlatlm cycle Iiaticmcych

I

+La

1

21 Las! Assentdj D=harged alter lull hadialion )IyOiiwharfII

22 Spent Fuel Stomga!

in * ent Fuel Pal

m

EsJ$w-L

1

23 FirstMOXin SpemFuel Pod

24 Last MOX

Propct: ExistingSWRFacilitia$ Task Summary

Figure 4.14 Existing BWR facility schedule summary

65 :

Page 66: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

4.5.4 Existing LWR Alternative Collocated PuP and MOX Facility Summary

The existing BWR alternative collocated PuP and MOX fuel fabrication facility schedule is a combination of theindividual facility schedules discussed above. This overall schedule is summarized in Table 4.34 and shown inFigure 4.15. The plutonium disposition mission begins when the f~st mission fuel is loaded into a reactor inApril 2010 and is complete after the last core load, which contains MOX fuel assemblies, has been irmdiated fora single cycle in December 2027. The overall mission time is 17.7 years and starts 13.3 years after ROD. Thecritical path for this alternative is the licensing, design and construction of the new collocated PuP and MOXfuel fabrication facility.

Table 4.34 Existing LWR alternative with collocated PuP and MOX facility summary

Task DurationID Task Name (years) Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Process 3 12/1996 12/1999

3. Collocated PuP & MOX Facility 29.8 10/1995 7/2025

4. Fuel Qualification Process 5 4/1996 4/200 1

5. R&D 3 10/1995 9/1998

6. Licensing, Permitting & Siting 5 1/1998 1/2003

7. Design 5.1 12/1996 1/2002

8. Facility Modification 4.4 1/2002 6/2006

9. Preoperation 2 6/2005 6/2007

10. Fabrication of LUAS 0.5 612007 11/2007

11. Operation 15.6 12/2007 712023

12. Decontamination & Decommissioning 2 712023 712025

13. Existing BWR Facility 43.7 12/1998 8/2042

14. Utility Selection 1 12/1998 12/1999

15. Licensing 5.2 12/1999 312005

16. Reactor Modifications 4 12/1999 12/2003

17. Reactor “read y“ to accept MOX 3/2005

18. Lead Use Assemblies 6.1 12/2007 12/2013

19. MOX Loading Duration 16.6 4/2010 10/2026

20. Single irradiation cycle of last MOX 1.2 10/2026 1212027

21. Spent Fuel Pool Duration 27.5 3/2015 8/2042

22. HLW Repository Facility

23. Licensing 8.5 312002 8/2010

24. Construction 5.5 3/2005 8I201O

25. MOX Delivery Duration 17.5 3/2025 912042

66

Page 67: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

.—.—

-..—

.-..,----

—..-

-—~

_—

-–—?

——

-.--

;--

..-——

:_.

—.—

~c~

taIn

--

-------’-----’’--F:=-l-

——

——

.----.—

...............................................................................................................................

,P

—---

“=—

_.Qj--

.=-––,:

●:4 —

—.—

— ‘1—

—_

s—

;P.-

.Z~

E~g

.$i–

—m

----1i

——

.-—

-.-——

—___——--------

I.-.–—

---”--”””---””-----[““---‘–

‘–‘----”----”-----”

.*—L%

-—.

3‘a:

.—-----—

..._.

—________________________

.-~—._

--——

----------.

..__5

._._,

_

5.=—

.——

_--—

..4—

——

.:—

03~

.......

-—._,-_..

z,5

—-------

:_

._-

—____________

CJ=

_-–-

-—-—

-&-~

----.

..%8i~

–---e-”;–-:—

.:—--–

--—-------------------

~-–-..–-.—.__j__j----

ii%

.-.-

.-=m

ma

m.

.

—~

0

e:

E!!

..–..--.<–....—....

......‘E...__f_~u

‘P

::e

-—-:

:r=-:-T

‘-—:3

—’-

——.sii~%5–&+ t’g

-’~

—._ —-—J-—

,~______

8:*

7! Q $bT

“I

II?—

:–!–:+—

}5

——

:–k–L–+—

L-’T-7

m....?

II

II

A—

I -—----..__.:

----;-g

..&_______

__

ib

.;.-

11“--1”---

a—

-——

-----l--L

––.-l.——

.—m

;-E~~-L

~---.---..-_L?

..-.—

——

t—

——

Page 68: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

4.6 Existing LWR Alternative Summary

The plutonium disposition schedules for the four 50 MT existing LWR alternative cases are summarized inTable 4.35 and shown in Figure 4.16.

The schedule risk for all of these alternatives is similar. The PuP facilities, MOX fuel fabrication facilities adHLW repositories for the different alternatives are the same except for the duration of operations. A similarschedule for utility selection and reactor facility modifications will be used for both PWRS and BWRS. Theprimary differences in the existing LWR schedules are the license modification process and the fuel loadingschedule. There is a higher schedule risk in the license modification process for the existing LWRS using MOXfuel with integral neutron absorbers than for the LWRS using MOX fuel without integral neutron absorbers.However, this risk has been addressed in the schedules by including a longer license modification prccedure forthe former case.

The critical path facility for all of the existing LWR alternatives, except the quick start case, is the MOX fuelfabrication facility. For the quick start case, the process to obtain a permit for placing the LUAS in the core isthe critical path.

Table 4.35 Existing LWR disposition alternatives schedule summary

Option

Base Case PrivateMOXCollocated PuP& MOX facility

Quick Start

PuP Facility

prototype NA NA NA 1/1998

start processing at production facility 7/2006 7/2006 6/2007 7/2006

MOX fuel fabrication facility

start LUA fabrication 12/2006 12/2006 7/2007 6/2000

mission fuel fabrication start 6/2007 6/2007 12/2007 3/2001

mission fuel finish 4/2017 4/2017 712023 12/2015

Reactor Facility

reactor type PWR Pm BWR Pm

reactor “ready” 3/2004 3/2004 3/2005 3/2004

start irradiating European LUA NA NA NA 12/2002

start irradiating American LUA 6/2007 6/2007 12/2007 6/2007

mission start 5/2010 5/2010 4/2010 11/2005

last assembly loaded 212020 2/2020 10/2026 1/2019

mission finish 8/2021 8/2021 12/2027 7/2020

Mission duration (yr.) 11.3 11.3 17.7 14.6

ROD to mission start (yr.) 13.5 13.5 13.3 9.0

68

Page 69: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

~..

‘~___

..————

......8....___:

...............––.._”

‘%,

.st

z‘8

..-.—-.-..—

.—

------~

z-

..-.-..-..-—..

-—.....

..

—-...

--—-----

——

-...--.—..

8zia

‘.-”!

““’”””””’”””““””””1

“’””””’”“’””””

~~‘------

-!---[-‘------

55

‘%‘k

i,+

?.=

z‘!

------------—z

................-..

..

zc)

.—

.-...

..—.-..-..

..-..—

.....—

-..—

5

u+

_.----.E............t.._

..............—

-+--

~—

..

..—.

.:

:.

.

.-.8z.—

.g------

—j

----–+

ic!

a

--—-.:

-,:

......nz

.s!

.*...

z.-

.-—~

..—$

L8!5

n..

z::

._n.

...-.-

..-...—:—

‘;’T~ .]gp!

‘j.x..,..:

i,=–n

P+

;]-

...—..~—

.3

>g~

~-’:5

!3:~~

““–”i

-:“-;-~

~ -$--$~g@

—.......:

....fi—......~.,

mckL

J4:8>

-.-z....-

F--+--

!5

::

~.

i--->

-...-------

tc:i

2+!

Page 70: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

5. CANDU Heavy Water Reactor AlternativesThe implementation schedules for the two CANDU HWR options shown inTable 2.2 is presented in this section. For complete descriptions of each of the facilities and for the cost andother analyses for the CANDU options, see the RASR, volume 2 (2).

5.1 CANDU HWR Alternative Base Case, 50 SFC2-4

The base case for the CANDU HWR alternative uses four separate facilities: a PuP facility, a MOX fuelfabrication facility, several of the CANDU reactor units at Bmce-A, and the Canadian geologic repository. Theimplementation schedules for each of these facilities is presented below.

5.1.1 PuP Facility

The PuP facility for the CANDU base case is the same as described for the existing LWR base case in Section4.1.1 above.

5.1.2 MOX Fuel Fabrication Facility

The preopemtional schedule for the MOX fuel fabrication facility is the same as described for the existing LWRbase case in Sections 4.1.2.1 and 4.1.2.2.

5.1.2.1 MOX Fuel Fabrication Facility Operations Schedule

To supply fuel for the two CANDU reactors with Reference MOX fuel bundles, the MOX fuel fabricationfacility will operate for five years with an annual plutonium throughput rate of 3 MT. This throughput assumesan annual output of 9050 bundles for a mission total of 45,250 bundles. Then the production lines will beconverted to fabricate CANFLEX fuel to supply four CANDU reactors with an annual plutonium throughput of4.9 MT for 7.2 years; this corresponds to an annuat output of 10,500 CANFLEX bundles, for a mission total of75,279 bundles. A sufficient number of Reference MOX bundles for the initial loads will be available sixmonths after the start of operation. The operational schedule is shown in Table 5.1 and in the MOX fuelfabrication facility schedule summary figure in Section 5.1.2.2.

Table 5.1 MOX fuel fabrication facility operational schedule

Task DurationID Task Name

(months)Start Finish

1, Operation 152 12/2006 2/2019

2. MOX Facility Operation Start 12/2006

3. Fabrication of Initial Loads 6 12/2006 6/2007

4. Reference MOX Fuel Fabrication 60 12/2006 12/2011

5. CANFLEX Fuel Fabrication 86 12/2011 2/2019

5. I. 2.2 MOX Fuel Fabrication Facility Schedule Summary

The overall MOX fuel fabrication facility implementation schedule is summarizti in Table 5.2 and shown inFigure 5.1. This facility schedule is also shown in the overall alternative schedule figure in Section 5.1.5. Thisschedule does not include any contingency for schedule slip due to site selection difficulties, tiesign,construction delays, or a delay in the approval of line item funding.

70

Page 71: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

.

ID Task Name ’95 ’96 ’97 ’98 ’99 ‘III ’01 ’02 ’03 ‘J4 ’05 ’06 ’07 ’08 ’06 ‘1O ’11 ’12 ’13 ’14 ’15 ’16 ’17 ’16 ’16 ’20 ’21 ’22 ’23 ’24 ’25 ’26 ’27 ’28

1 FMDP Record of Decision l~ls~F~DP~em~dof [+onll~llllllll~ ~’~~1~’[11~~1~

2 thl!JW@Ollal Funding ApfNOVIIii,, , i!i!i i! ii! iiiii li~i

II~k+d.wwl~ ; ; ~ ~ ; ~ \ j ~ ~ ; ~ ~ ~ ~ \ ~ f f \ ; !il~j!!;3 Initial Funding Process

~!~*~lniii~lFu}ding~Pr~ss~ \ / / / i \ \ f ~ \ i / I \ ~ [1 I ~ \ ~ ~ ~ I

1~1 !!! !!! !;! ~!!!4

]!~!! !Final Funding Approval

!ii\ WFindl Fu~ding~Appr~val\ ~ \ { \ ~ f ~ ~ \ ~ ~ ; \ ~ , [ \ ; ~ ~ ~ ~ ~

{!!1!![ !i!!;

!i!;!;; ii! l!~!! !!!!! !!!!

5 FuelOuaiiicetion Osmo~~!~! !!!!

6 Siie&FecilNySelectien

7

!!! ;!! ,

3=electM&OContractw!!

8 Llcens-htgandPermitt!mgi!!:: !,i,!,! !~,!l

9 NRC Licensingillllll~ !! l!!!

10 Environmental / NEPA / DOE!!!!!!!1

11 Permitting

12 Ossign Procaees

13i!!!

Conceptual Deegn

14 Tile I!!

15 Ttle II

16 Fecility ModiticaNon !!!!!!!!

17!!! ii

Constructioni!!!!

18 Procurement //l\llil~~\,~~~~l~i!:!

19 Equipment Installation!!! !!!!! !!!!! !~i

20 Preoperationel Phase

21 PuP Fecllii bed Tkne Corn@ete

22

11!! 11! 1//!

MOX FFF Reedy for Pu02

23 Oparetiert ii iii!~~i!1!

24 MOX FFF Operation Slarf !!!!

25 MOX FFF Lead Time

26 MOX Fuel Fabrication Duratbn

27 CANFLEX Fuel Fabricatkxt Duration

28 IkOnteminetien & Decemrnieeien

Project MOX Fuel Fabrication Facility Taak ~ Crfiicsl Task~ Milestone + Summery ~

Figure 5.1 MOX fuel fabrication facility schedule summary

71

Page 72: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 5.2 MOX fuel fabrication facility schedule summary

TaskTask Name

Duration

ZD (months)Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Approval 36 12/1996 12/1999

3. Fuel Qualification Demonstration 60 4/1996 4/2001

4. Site and Facility Selection 12 12/1997 12/1998

6. Licensing and Permitting 60 12/1997 12/2002

7. Design Process 60 12/1996 11/2001

8. Facility Modification 36 12/2001 12/2004

9. Preoperational Phase 24 12/2004 12/2006

10. PuP Facility Lead Time Complete 9/2006

11. MOX Facitity Ready for PuO, 12/2006

12. Reference MOX Operation 60 12/2006 12/2011

13. CANFLEX Operation 86 12/2011 2/2019

I 4. Decontamination & Decommission 24 2/2019 1/2021

5.1.3 CANDU HWR Facility

5.1.3.1 CANDU HWR Facility Design & Construction

The duration and path of the design and construction tasks are based on information from Atomic Energy ofCanada, Ltd. (AECL). After approval of intermediate line item funding, the project begins with completion ofthe required design and reactor facility modifications and construction of the new fuel storage building. Thedesign and construction schedule is listed in Table 5.3 and shown in the CANDU facility schedule summaryfigure in Section 5.1.3.4.

Table 5.3 CANDU facility design and construction schedule

Task DurationID

Task Name(months) Start Finish

1. FMDP Record of Decision 12/1996

2. Intermediate Funding Approval 24 12/1996 12/1998

3. Reactor & Design Modifications 48 12/1998 11/2002

4. Design Modifications 24 12/1998 12/2000

5. Reactor Modifications 24 12/2000 11/2002

5.1.3.2 CANDUHWR Facility Licensing and Permitting

There are two licensing and permitting tasks for the CANDU facility: the requhed interactions with the AECBand the environmental assessment for using MOX fuel in the reactors and for buildhtg the new fuel storagebuilding. These tasks are listed in Table 5.4 and shown in the CANDU facility schedule summary figure inSection 5.1.3.4.

72

Page 73: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 5.4 CANDU facility license and permit schedule

TaskTask Name

DurationID (months)

Start Finish

1. Licensing and Permitting 72 12/1996 11/2002

2. AECB Interactions 48 12/1998 11/2002

3. Environmental Assessment 24 12/1996 12/1998

5.1.3.3 CANDUHWR Facility Operations Schedule

After completion of the preoperational phase, the CANDU reactors are ready to accept Reference MOX fuel inFebruary 2002 however, the MOX fuel fabrication facility will not produce a sufficient supply of fuel bundlesto begin continuous operation until June 2007. At this time, two reactor units at Bruce-A start operating withReference MOX fuel and operate with this fuel for five years. At the end of the five year period, the first twounits and two addhionaJ units rue switched to irradiating CANFLEX fuel. These four units are loaded withCANFLEX fuel for 7.2 years. After a residence time of 450 days, the spent MOX and CANFLEX fuel bundlesare placed in the spent fuel pool for a minimum of ten years. As the Canadian geological repository facility isnot scheduled to open until 2025, the spent MOX and CANFLEX fuel may be moved to dry cask storage afterten years in the pools. The CANDU facility o~mtional schedule is shown in Table 5.5 and in the CANDUfacility schedule summary figure in Section 5.1.3.4.

Table 5.5 CANDU facility operations schedule

TaskTask Name

DurationID (months)

Start Finish

I. MOX Facility Lead Time 6 12/2006 6/2007

2. Preoperational Phase 3 1212002 2/2003

3. Reactor Facility Operation 161 6/2007 10/2020

4. Units 1&2 Reference MOX Loading Duration 60 6/2007 6/2012

5. Units 1-4 CANFLEX Loading Duration 86 6/2012 8/2019

6. Irradiationof last CANFLEX Bundles 15 8/2019 10/2020

7. Spent Fuel Storage 274 10/2014 7/2037

8. First MOX in Spent Fuel Pool 120 8/2008 8/2018

9. Last CANFLEX 120 1 1/2020 11/2030

S. 1.3.4 CANDU HWR Facility Schedule Summary

The overall CANDU facility implementation schedule is summarized in Table 5.6 and shown in Figure 5.2.This facility schedule is also shown in the discussion of the overall alternative schedule in Section 5.1.5.

73

Page 74: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 5.6 CANDU HWR facility schedule summary

Task DurationID

Task Name(months) Start

1. FMDP Record of Decision

2. Congressional Funding Approval 36 12/1996

3. Fuel Design and Development 62 10/1996

4. MOX Facility Lead Tne 24 12/2006

5. Licensing and Permitting 72 12/1996

6. Reactor & Design Modifications 48 12/1998

7. Preoperational Phase 3 12/2002

8. Reactors “ready “ to accept MOX

9. Units I&2 Reference MOX Loading 60 6/2007

10. Units 1-4 CAN FLEX Loading Duration 86 6/2012

11. Full Irradiation of Last CANFLEX Bundles 15 8/2019

12. Spent Fuel Storage 266 8/2008

Finish I12/1996

12/1999

11/2001

11/2008

11/2002

11/2002

2/2003

2/2003

6/2012

8/2019

10/2020

11/2030

74

Page 75: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

...........-~....~

.z

..............................

A

..

..............-

‘1 .................__.~..........U

..

g($+.........

-----xoz~

.e

;.....t

—...-..

"""""""""-"""""""`"""""""`"'"`""`-"--"""-------------------.---..-.......--.-------------------.......-..........----.$-------:.....-------------

i?

II YL

5 B........-....................-..-+

....................................................................................x......

Q-----

.-......

...........v

gg

;t)

....................................l&............................................................................................

t..................................

L‘E?

E~

=?

H.........-.....................~-.... ..z

----...

m---

.....................

::E

a.g~k:

2II

.-..—

cm.....”.

2.-..--..............

–-~........S._...-:.-..;

....-..$.-...$................................

..".

..

..

..

..

..

..

..

.

7;g

g+’~

;:j.,=.......?........8..............................................~........~.......%.............. ..K.....................................................................................

w~

.-<

<#c>

cf::

U.s

“+..; .-...”~........~.

.............-g-

gE

1;’”-””””#

””-”””`"""""""""""""-"""""z"""""""`"`"""----"""""""""-"--``""""--"""""""-"--"""""""-"-""""""-""-

Pg~~

,.;......1111..................u!.....-”~...........................................................................................................

muu

......................................................................................................‘$-”””””-””

.........

..-..-...

...

T:i=ju.u.

kKoz——

—.

.—

0——

m

Page 76: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

5.1.4 Canadian Geological Repository Facility

5.1.4.1 Canadian Geological Repository Facility Design& Construction Schedule

The duration and path of the design and construction tasks are based on information from AECL. The designactivities have been estimated to require ten years and will begin in 2004. The siting and construction activitiesare estimated to take 27 years and will begin in 1998.

5.1.4.2 Canadian Geological Repository Facility Licensing and Permitting

The duration of the license and permitting activities tasks are estimated by AECL to begin in 2002 and take toten years to complete.

5.1.4.3 Canadian Geological Repository Facility Operations Schedule

The Canadian Geological Repository facility is scheduled to open in 2025. The Reference MOX and CANFLEXfuel delivery schedule is shown in Table 5.7 and in the alternative schedule summary figure in Section 5.1.5.

Table 5.7 Canadian geological repository facility operations schedule

Task Duration

IDTask Name

(months)Start Finish

1. Repository Opening Date 1/2025

2. Delivery of MOX & CANFLEX Fuel 71 1/2025 11/2030

3. Transportation of first MOX to Repository 1 1/2025 1/2025

4. First MOX bundle arrives 1/2025

5. Transportation of last CANFLEX 1 11/2030 11/2030

6. Last CANFLEX bundle arrives 11/2030

5.1.5 CANDU HWR Base Case Alternative Schedule Summary

The CANDU alternative schedule is a combination of the individual facility schedules discussed earlier above.The overall schedule is summarized in Table 5.8 and shown in Figure 5.3. The plutonhm disposition missionbegins when the first Reference MOX is loaded into the CANDU reactors in June 2007 and is complete after thelast CANFLEX bundles rue fully imadiated in October 2020. The overall mission time is 13.3 years and starts10.5 years after ROD.

The critical path for the alternative is the licensing, design, and construction of the MOX fuel fabricationfacility. The CANDU reactors are rtady to accept the Reference MOX fuel five years before the fuel is available.

The schedule risk for the PuP and MOX fuel fabrication facilities are the same as for the other reactor-basedalternatives. The schedule risk for modifying the existing CANDU reactor facility is the same as for modifyingexisting LWR facilities for MOX fuel.

76

Page 77: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

_..-.-.-...-.-.-._..-----------------------------------------------------------------------------------------------------------------------------------.-._.—

.-.-.--—5zg0

---.-.-.

-.-—.

-—P%.

-.-.-—-------

8xu! ‘g

,-.-.-.-__.-.-.-_,----------------------------

;%-.--.-.-....................--------------------------------------------

------------------.-.—.-,----

..-,-,-----=

\k;:,8F$

r%;*~—

G!

--—------------ z<s

--.-.....j-.-.2

i

I

---------—

..;

..-.--%.-..

-._._:f_.

.

.-.-.-.-.-.-.-.-.—

-.--—-—

-.-.-—

.?---.

%.-EE.

..

..

..

..

..

..

....

---------------.

.0

.~0

s--.--.

-.-.—.-

——

-—---

.-.-..E---------

c.

.-.:

;c

--------------------------------------t

..----.’:.z~

E~x

..

..

..

..

..

..

..

..

..

.~

..-.-.-.-..g

.:3------------

---------------------------,-

5.-S---.-.-.—

-—-------------------

>--

n2’~

-------------------------------------m

---5

—.-..

....

....

--.—

-——

-

-—-

--—-

-----

------

------

......-

—---

rz-1

T-.-.--.------.-.-.---..0

--------.-

---------

1’............:----

......-..,62

5------------

.-..=-:------------------

:;..-...-.-.-.-–.$--~~

-----.--,---------C

LO

a=

?.-5

...................I ....----

z~

P~.-

--%.---g

---_-.~

.-.-,-.-=

x;-

0....f

...........3-.-.......?.....-----:

[

z-;----

.----------.-.-.-.-.-.-.—

-.-ee

-i-------

---------------8

11 ---.--. ----------------.--------------------

-----.-...................

1......._....-....-...-

.....-g..-

-----[

-----------------------:-----------.-~._....

----------------------

a

-----.-.---.

-.-.--.;.

..

..

..

.-.Z..-.-.-,_,F-.-.-.-.-.g

------------i%~

-...-.-...~_-------

,su

E

[

--....-.k.

..

....-.--.-.--—

.

P._.-..._.”~

.-..?.-.

----------------

Jg

_’$-~

1 ..... ---...-.....—----------[-_~ A

[1--------------

~----------

..--.-x.-.$j$---------------

i?%:

.,..........F...Z....$

...................

*3

..-g.._;_&

:fm-.-—---.—

-.

.s?~-

:%?lj

-..-..~

..-.0--

m_..:

--------------~

c?>

[r~--u.

.*-----

----

----.

.----

--------------------------

/----------

-------------------------------------

.....-[I------------L

------

0_.#

..-.-----

..

..

..

...

..

..

T ..-----...

--&--------------

——

—.

.——

Page 78: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 5.8 CANDU HWR base case alternative schedule summary

Task DurationID Task Name

(years) Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Process 3 12/1996 12/1999

3. Pu Processing Activities 22.8 10/1995 7/2018

4. R&D 3 10/1995 9/1998

5. Licensing, Permitting & Siting 5 12/1996 12/2001

6. Design 5.1 12/1996 1/2002

7. Faciiity Modification & Preoperation 4.5 1/2002 7/2006

8. Operation 10 7/2006 7/2016

9. Decontamination & Decommissioning 2 8/2016 7/2018

10. MOX Fuei Fabrication Faciiity 24.1 4/1996 1/2021

11. Licensing, Permitting & Siting 5 12/1997 12/2002

12. Design 5 12/1996 1 1/2001

13. Facility Modification & Preoperation 5 12/2001 12/2006

14. MOX Faciiity Lead Time 0.5 12/2006 6/2007

15. MOX Operation 5 12/2006 12/2011

16. CANFLEX Operation 7.2 12/2011 2/2019

17. Decontamination & Decommissioning 2 2/2019 l1202i

18. Reactors 34.1 9/1996 11/2030

19. Licensing 6 12/1996 1 1/2002

20. Fuei Design & Development 5.2 9/1996 1 1/2001

21. Reactor Design & Modifications 3.6 12/1998 7/2002

22. Units 1 & 2 “ready” to accept MOX 712002

23. MOX Loading Duration - Units 1 & 2 5 6/2007 6/2012

24. CANFLEX Loading Duration - Units 1-4 7.2 6/2012 8/2019

25. Last CANFLEX bundies irradiated for 1.2 yr. 10/2020

26. Spent Fuel Pool Duration 22.2 8/2008 11/2030

27. Repository

28. Licensing 10 1/2002 1/2012

29. Design Activities 10 1/2004 1/2014

30. Siting Issues and Construction 27 1/1998 1/2025

31. MOX/CANFLEX Deiivery Duration 5.9 1/2025 11/2030

5.2 CANDU HWR Alternative Hybrid Case, 33SFC2

Thehybrid case for the CANDU HWR alternative is the same as the base CANDU HWR case, except only 32.5MT of weapons-usable plutonium wiil be converted to MOX fuel, and only two CANDU reactor units will kused. Also, there will be no shift to the new CANFLEX fuel type. The changes to the various facilhiesoperational schedules from the base CANDU case are discussed below.

5.2.1 PuP Facility

The overall PuP facility implementation schedule for this alternative is the same as was presented for theexisting LWR hybrid ease above in Section 4.4.1. This schedule is also summarized in the overall alternativeschedule summary table and figure in Section 5.2.5.

78

Page 79: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

5.2.2 MOX Fuel Fabrication Facility

The overall MOX fuel fabrication facility design, construction, licensing and permitting schedules are the sameas were presented above for the existing LWR base case in Sections 4.1.2.1 and 4.1.2.2. To supply fuel for thetwo CANDU reactors with Reference MOX fuel bundles, the MOX fuel fabrication facility will operate for 10.9years with an annual plutonium throughput rate of 3 MT. This throughput assumes an annual output of 9050bundles for a mission total of 98485 bundles. This schedule is summarized in the overatl alternative schedulesummary table and figure in Section 5.2.5.

5.2.3 CANDU HWR Facility

The overall CANDU HWR design, construction, licensing and permitting schedules for the 32.5 MT case ruethe same as were presented for the 50 MT case above in Sections 5.1.3.1 and 5.1.3.2. Only two CANDUreactors will be used for this alternative. Reference MOX fuel will be loaded into these two reacto~ for 10.9years. This schedule is summarized in the overall alternative schedule summary table and figure in Section5.2.5.

5.2.4 Canadian Geological Repository Facility

The overall Canadian Geological Repository design, construction, licensing and permitting schedules for the32.5 MT case are the same as were presented for the 50 MT case above in Section 5.1.4. Spent Reference MOXfuel is scheduled to be deliveml to the facility stinting in 2025 and continuing for 4.6 years. This schedule issummarized in the overall alternative schedule summary table and figure in Section 5.2.5.

5.2.5 CANDU HWR Hybrid Alternative Schedule Summary

The overall schedule for the CANDU HWR 32.5 MT alternative is summarized in Table 5.9 and shown inFigure 5.4. The plutonium disposition mission begins when the first Reference MOX is loaded into theCANDU reactors in June 2007 and is complete after the last Reference MOX fuel bundles are fully irradiated inJuly 2019. The overall mission time is 12.1 years and starts 10.5 years after ROD.

79

Page 80: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 5.9 CANDU HWR hybrid alternative schedule summary

TaskTask Name

DurationID (years)

Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Process 3 12/1996 12/1999

3. Pu Processing Activities 22.8 10/1995 7/2018

4. R&D 3 10/1995 9/1998

5. Licensing, Permitting & Siting 5 12/1996 12/2001

6. Design 5.1 12/1996 1/2002

7. Facility Modification & Preoperation 4.5 1/2002 7/2006

8. Operation 10 7/2006 7/2016

9. Decontamination & Decommissioning 2 8/2016 7/2018

10. MOX Fuel Fabrication Facility 24.1 4/1996 1/2021

11. Licensing, Permitting & Siting 5 12/1997 12/2002

12. Design 5 12/1996 1 1/2001

13. Facility Modification & Preoperation 5 12/2001 12/2006

14. Operation 10.9 12/2006 10/2017

15. MOX Facility Lead Time 0.5 1212006 6/2007

16. Decontamination & Decommissioning 2 10/2017 10/2019

17. Reactors 32.8 9/1996 7}2029

18. Licensing 6 12/1996 1 1/2002

19. Fuel Design & Development 5.2 9/1996 1 1/2001

20. Reactor Design & Modifications 3.6 12/1998 712002

21. Units 1 & 2 “ready” to accept MOX 712002

22. MOX Loading Duration 10.9 6/2007 4/2018

23. Last MOX bundles irradiated for 1.2 yr. 7/2019

24. Spent Fuel Pool Duration 20.9 812008 712029

25. Repository

26. Licensing 10 1/2002 1/2012

27. Design & Construction 27 1/1998 1/2025

28. MOX Delivery Duration 4.6 1/2025 812029

80

Page 81: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

.gWI

....

......

....

....

......

......

....

..

......

.....

......

..

..

..

....

.....

.....

.....

......

...

......

.....

...

......

....

......

........................_

5●

..-%

..=-..-

..

..

..

..

.....

..

.......

..

..

..

-.,..

.~

..------

;E

:..-....-

E8

.2....................

......................................._:

..................................................@n

..--..-..-..-..-..-..-..-.-..-..---.-...2

.......-

8d

05

;...................

...............................

..........-..--..-.-.

-__..-________g_...g

..-_.._.._._______..”~_..”~

----.._

.Q.-;

5z

0~

.-—----..........

................

.............._._._.~...............

......._....

........-----~

-..-..Z

’g

..-...—_-..-..-..-..-_

--_._.._,e

..-.,..-,

2g

~......................

..........

.........

........c

_.-,E-..

.-..-..-..-.._.__._..__~.––.._n___

-.._._......._._.--.--..-.-..~.....

._..:

n8

I

z

I

-----------------------------....-...a

.....----

------------------------------------------------.

........................................

...-.

-I

1.1-””-””-‘“”-””-””-””-””-’”-””-””-””-””-””-”’-”/

‘“-”

s....................._

.........5.-..

..

...-..-..-...............%

.$

z

------------------i..-..

-------..-..-..-..-..-..-...:

...........

.........

....................

.........

.....–..,

..-.Iid

6?

cc0

i=

----..-..-..---.-....g

—..

....

....

..-..-._

......_.-_...~

..—.-..-:

...

......

__._.._._____.__g

.-..-.,-.,

._

x

g“

~m

>

.....-..-..-...e

...-...

..-...j.-.

....

......-..-.

.-..$....

..-..-..5..-..

.–-;.

.......-

-..-..-...._...F

–.j-;.-.

....

._.

.-.

..-

,,.

..-..—

....-

..—.

-...

..-—.

.......-----

-.-...

..

........

..—.

..-..-

,..----

..-.—

mCa

=1Is

gl~l%E

~:L

.-..-..-...—_.

.=“1

E‘J-z

:n“- 4

1~

‘“1””-”-””-‘“”-””-

11-. —

..-.-----—

-.-E..........._.~

..

...-.

..

..

..

..

g...-.._.B

E._..:

.........~

..

..

..

..

.gc

G;

;%$;

--.—.—

..—.g..._.oQ----

.....................m

_._.+...-

~,___

..............

...........-._,.

-~.--.0

-_a

-_.=

a.al.6

38

5:

-:“-””-””-”–””—

’”‘-”

‘--

.........

~+..T

-------g..-...-..;.....................- ------

----------P---”:

-.4-.--.-.1---Z----t

..--4.-–.=—.-..-..-1-–

10

..

----~

[[1-~+

1-..-....._________

..........___.-nll

FllI

$.-............................-_-..-,

...........

711R

llII/

------..-..—......._..............

-..-.,---1

‘AK

LF

----

It

b-g.-..

----..

......................... ~...t__.t__

._.--_.,i_,i_....-..-

._+-.._j_______

...............~&

..-.t.

..

.....

....

......

....~.

..-—

—~ii)—a.

—?J

g!j—a—Y

-

Page 82: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

6. Partially-Complete Light Water Reactor AlternativeThe implementation schedule for the partially-complete LWR option, 50SFP2, shown inTable 2.2 is presented in this section. This alternative uses four separate facilities: a PuP facility, a MOX fuelfabrication facility, a reactor facility with two partially-complete PWR units, and the HLW repository. TwoABB-CE System 80 reactors have been chosen as surrogate representatives for fuel throughput calculations forthis alternative. For complete descriptions of each of the facilities, and for the cost and other analyses for thepartially-complete LWR option, see the RAS~ volume 3 (2).

6.1 PuP Facility

ThePuP facility for the partially<omplete LWR case is the same as described for the existing LWR base case inSection 4.1.1 above.

6.2 MOX Fuel Fabrication Facility

Thepreoperationalschedule for the MOX fuel fabrication facility is the same as described for the existing LWR

base case in Sections 4.1.2.1 and 4.1.2.2.

6.2.1 MOX Fuel Fabrication Facility Operations Schedule

To supply fuel for two ABB-CE System 80 reactors at the specitled loading rate, the MOX fuel fabricationfacility will operate for 17.1 years with an annual plutonium throughput rate of 2.9 MT. This throughputassumes an annual output of 157 assemblies for a mission total of 2692 assemblies. The LUAS will be ready toload into a sister reactor six months after the start of operations at the MOX fuel fabrication facility. Asufficient number of MOX fuel assemblies for the initial core loads will be available thirty-one months after thestart of opemtions. The operational schedule is shown in Table 6.1 and in the MOX facility schedule summaryfigure in Section 6.2.2.

Table 6.1 MOX fuel fabrication facility operational schedule

Task DurationID

Task Name(months)

Start Finish

1. Operation 211 12/2006 712024

2. MOX Facility Operation Start 12/2006

3. LUA Fabrication 6 12/2006 6/2007

4. Fabrication of Initial Core Loads 25 6/2007 6/2009

5. Operation 205 6/2007 712024

6.2.2 MOX Fuel Fabrication Facility Schedule Summary

The overall MOX fuel fabrication facility implementation schedule is summarized in Table 6.2 and shown inFigure 6.1. This facility schedule is also shown in the discussion of the overall alternative schedule in Section6.5. This schedule does not include any contingency for schedule slip due to site selection difficulties, redesign,construction delays, or a delay in the approval of line item funding.

82

Page 83: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 6.2 MOX fuel fabrication facility schedule summary

Task Duration

IDTask Name

(months)Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Approval 36 12/1996 12/1999

3. Fuel Qualification Demonstration 60 411996 4/2001

4. Site and Facility Selection 12 12/1997 12/1998

5. Select M&O Contractor 12 12/1998 12/1999

6. Licensing and Permitting 60 12/1997 12/2002

7. Design Process 60 12/1996 11/2001

8. Facility Modification 36 1212001 12/2004

9. Preoperational Phase 24 1212004 12/2006

10. PuP Facility Lead Time Complete 9/2006

11. MOX Facility Ready for PuO, 12/2006

12. LUA Fabrication 6 12/2006 6/2007

13. MOX Facility Lead Tme 25 6/2007 6/2009

14. MOX Facility Operation Duration 205 6/2007 712024

15. Decontamination & Decommission 24 712024 7/2026

6.3 Partially-Complete PWR Facility

6.3.1 Partially-Complete PWR Facility Design & Construction

The duration and path of the design and constmction tasks are based information from Fluor Daniel andTennessee Valley Authority (TVA). After the intermediate approval of line item funding, the project beginsselection of the M&O contractor and project mobilization. The completion of the first unit has been set tocoincide with the availability of the initial core load of fuel assemblies from the MOX fuel fabrication facility inJune 2009. If construction on the f~st unit staled directly after the transfer of the construction permit to the newcontractor without waiting for the MOX fuel fabrication facility, the reactors would be complete three yearssooner. The second unit is scheduled to be completed one year later than the first unit. The design andconstruction schedule is listed in Table 6.3 and shown in the facility schedule summary figure in Section 6.3.4.

Table 6.3 Partially-complete PWR facility design and construction schedule

TaskTask Name

DurationID (months)

Start Finish

1. FMDP Record of Decision 12/1996

2. Intermediate Line Item Approval 24 12/1996 12/1998

3. Mobilization & Select M&O Contractor 27 12/1998 3/2001

4. Reactor Construction 66 1212004 6/2010

5. Complete Unit 1 54 1212004 6/2009

6. Complete Unit 2 51 3/2006 6/2010

83

Page 84: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

——

.....

...-

---

... s

-.-...

,

......

......

......

......

......

......

.....

......

.....

.....

......

......

.....

......

....

..=

-..... m

_-..

-.-

—--

----

----

----

-_.

—__

____

____

____

____

____

----

-&

~_J

--:

!3-1

----

----

----

----

----

----

----

----

----

----

----

----

---

{

–.—

-.-.

-a—

---z-

–.&

d

-.--

.—

.-—

-.--

.-.

-.-.

-.-.

—__

____

____

____

____

____

4..-

.—.—

-.--.

-_.-—

-.-._--.—

------

----

_.-._

__..

.......

.......

........

........

.....

......

..

~h

.-.

--$

_;_:

,--

----

----

----

----

----

----

----

----

-g-

~--

--g-

---

g--

g___

___

~-.

T=

,.

...s.

,.~-.

-..

.=!

1

I

Page 85: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

6.3.2 Partially-Complete PWR Facility Licensing and Permitting

For this analysis a licensing schedule developed by Fluor Daniel (9) for a partially-complete LWR facility wasfollowed. The licensing schedule is shown in Table 6.4 and Figure 6.2.

To begin the licensing process, the application for transferring the construction permit (CP) to the newcontractor is developed and filed with the NRC. The NRC reviews the application and approves the transfer ofthe CP. Once the CP is transfemed, construction may resume on the reactor facility. At the same time, work onthe application for the operating license (OL) and ER is started. After the application for the OL and the ER isfded with the NRC, the NRC conducts technical reviews of the OL application and develops the EIS and theSER. The schedule includes a provision for a year-long full discovery period and a one-year hearing and decisionprocess by an ASLB. The requirement for these prccesses are subject to petitions for a hearing on specificissues. After a decision is issued by the ASLB, the NRC grants the OL.

Table 6.4 Partially-complete PWR facility license and permit schedule

TaskTask Name

DurationID (months) Start Finish

1. NRC Licensing Process 65 3/2001 7/2006

2. Prepare and File Application for Transfer of CP 3 3/2001 6/2001

3. Public Notice of Application for Transfer of CP 1 6/2001 6/2001

4. NRC Review of CP Transfer 6 7/2001 12/2001

5. NRC Approves of CP Transfer 1 12/2001 1/2002

6. Licensee Prepares & Files OL Application 12 1/2002 1/2003

7. Public Notice of Application for License 1/2003

8, NRC Performs Tech. Reviews for OL Application 12 1/2003 1/2004

9. NRC Issues SER 1/2004

10. Pre Hearing Conference 6 1/2003 7/2003

11. Full Discovery 12 7/2003 7/2004

12. Hearing by ASLB 12 712004 7/2005

13. Decision Issued by ASLB 12 712005 7/2006

14. NRC Issues Operating License 7/2006

15. NRC Environ mental/NEPA Process 24 1/2002 1/2004

16. Licensee Prepares & Files OL ER 12 1/2002 112003

17. NRC EIS Process for OL Application 12 1/2003 1/2004

18. NRC Issues “EIS 1/2004

6.3.3 Partially-Complete PWR Facility Operations Schedule

After completion of the fiist unit in June 2009, which is when the MOX fuel fabrication facility lead time willbe complete, the reactor is loaded with the initial core load of MOX fuel and additional physics tests ateperformed before ascending to full power in September 2009. The second unit is loaded with fuel one year later.After two cycles of irradiation, 3.33 years, the spent MOX fuel assemblies am d~harged from the reactors andam stored in the spent fuel storage pool for ten years before being shipped to the HLW reposito~ facility. Thepartially-complete LWR facility operationat schedule is shown in Table 6.5 and in the facility schedulesummary figure in Section 6.3.4.

85

Page 86: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

ID Task Name 2001 I 2002 ] 2002 I 2004 I 2005 I 2006 I 2007 I 2008 I 2009 I 2010 I 2011

1 NRC Licmming Process,,. ;~

%Cfk4r@ Pm+a I i-l ~ ~ \ ‘

Prepare and File Application for Trarafer of CP ll!ll~.~~2 u Prepare and File Appficatkm for Tranater o(CP

;:

3 Public Notice of Application for Transfer of CP i! 11~,~~1Publk Notice of Application for Transfer of CP ~ :

4 NRC Review of CP Tranafer \ii ‘/:

‘: ‘RcYOicpTrlnafer ~ .115 NRC Approves of CP Transfer B NRC Approves of CP Tranafer ~ , ~

~dlili~ /;

6 Licemee Preparea & Files OL Application Lice~ee Prepares& Files OL Application ;~,

7 Public Notice of Application for Licerae ~l,,.$ 1 1 ~ji i ~ ~ !Public NotIce of A rcation for License ;

8 NRC Performs Technical Reviews for OL Application \l~llj~ Ii~- NRC #’erforms Techni~l Rav~ws for OL Application \

Q NRC Issues SER

?

ll!~:~:1/23 NRC Iaauaa SER

10 Pre Hearing Conference Ii ~~~~~~ Ple Haari;g Conf~rence ~::~!

11 Full Discovery:: {;

i;; ~ FuII Disco~ery ~ ] ~ j ~

12 Hearing by ASLB \:\i!jii~

~ ~ i ~ ‘~ringb;AsLB~ ~ ‘13 Decision Issued by ASLB

14 NRC Issues Operating Liceme 1 \ ~ \ ~ ymyedbYAsLB~ ~, ,,

7,21 ● NRC IssuesOperating License/;:

15!/

NRC EnvironmantaVNEPA Procaaai~i II

~NRC +viron~ ta+PAPr+eaa~\\ ,:;:: t , i

16j: ~~

Licensee Prepares & Files OL ER:- Lice~ee Pre~res & tiles OL~ER ~ \ [ \

17 NRC EIS Process for OL Application;! ll:i~~

;- NRC ~lS Process for OL Application ~ ~;:.

18 NRC Issues EISi)

\ ?/23

4!

NRJ ,JE,S ~ ~ ~ ~ ‘

:;, ~: ~{t

Task ~ WestorraProject Reactor License & Permit +

cri~cal Task ~ Summary ~

Figure 6.2 Partially-complete PWR facility license and permit schedule

Table 6.5 Partially-complete PWR facility operations schedule

TaskTask Name

DurationID (months) Start Finish

1. MOX Facility Lead Time 25 6/2007 6/2009

2. Reactor Facility Operation 225 6/2009 312028

3. Unit 1 Loading Duration 188 6/2009 212025

4. Unit 1 Full Power 9/2009

5. Unit 2 Loading Duration 169 6/2010 8/2024

6. Single cycle of Last Assemblies 18 212025 9/2026

7. Last MOX Fuel Discharged 37 212025 312028

8. Spent Fuel Storage 323 4/201 1 212038

9. First MOX in Spent Fuel Pool 120 4/2011 4/202 1

10. Last MOX in Spent Fuel Pool 120 312028 312038

Page 87: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

6.3.4 Partially-Complete PWR Facility Schedule Summary

The overall partially-complete PWR facility implementation schedule is summarized in Table 6.6 and shown inFigure 6.3. This facility schedule is also shown in the discussion of the overall alternative schedule in Section6.5. This schedule does not include any contingency for schedule slip due to redesign, construction delays, or adelay in the approval of line item funding.

The critical path for the partially-complete LWR facility deployment is shown in Figure 6.3. The start ofconstruction on the reactor facility is dependent on the expcted completion date of the MOX facility andsubsequent lead time requirements to ensure sufficient fuel is available. However, if this constraint is removedfrom the start of construction, the critical path for the facility is through the line item funding process, programmobilization, and the NRC licensing process before construction may restart.

Table 6.6 Partially-complete PWR facility schedule summary

TaskID Task Name

Duration(months)

Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Approval 36 12/1996 12/1999

3. MOX Facility Lead Time 25 6/2007 6/2009

4. Mobilization & Select M&O Contractor 27 12/1998 3/2001

5. Licensing and Permitting 65 3/2001 7/2006

6. Reactor Construction Completion 66 12/2004 6/2010

7. Reactor Facility Operation 225 6/2009 3/2028

8. Last Assemblies - fust cycle 18 212025 9/2026

9. Spent Fuel Storage 323 4/201 1 3/2038

6.4 HLW Repository Facility

The HLW repository facility schedule is the same as described for the existing LWR base case in Section 4.1.4,except the spent MOX fuel is scheduled to be delivered to the facility for 17 years, from May 2025 to April2038.

87

Page 88: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

——

——

—— In --

E ]. —

G Y i ij a

— ——

...

——

——

-—-—

.—

--—

--—

-.— ---

----

-

. ..---

C-L

“:1”

-”’”

-”.-

-...

-.—-.

....----

----

-.....-_~..........

.........................,,.-.,,_,___

_-_

--.,

-_.

-...--.,.-.,.._,.,,.-”,--------------

-g

‘:::;

2~m gg N

g-—

—-—

..-...

-.-

--.-

-—--

----

-_-

._.

.---

----

----

----

----

----

----

----

----

----

----

---

..

...

....

...

.,_-

--.-

-.,-

----.

_,--

---

- ~g m:

-——

—.-

—-_

____

.._-.-

...

....

.....

.....

...

......

.....

....

.....

.....

......

.....

......

.-..-

-....

--.,-

----

.w gg

f!Iic . z.

....

.....

....

crv

g..

.--.

..-.~..

......

...w

---L-

i__.

.._;..._

...-."....-_.

.___.

_..._.

..._....-_-_.

_._.

__...-_-.-..._..-__

....-..

__...

:~

gtj.;___,_:

Lu-

------

------

------

------

------

------

------

------

---&

+:

-—-.

..-—..-..—

—..

-...--

...-...-

—.-

.JI

;;

88 Ug

w---

--.:

.....

.....

..._.

..._.

._.

.?L

.._.

...

...

...

...

....

...

...

...

....

...

...

...

....

......

......

......

...-

p z .2

1

-n-

----

----~

-.—

-!L

ls

-—-”g---

~

---g

--- -n 1%

,-._

.-.—

-

$

——

...-,

._,

L 2

Page 89: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

6.5 Partially-Complete LWR Alternative Schedule Summary

The partially-complete LWR alternative schedule is a combination of the individual facility schedules dxussedabove. This overall schedule is summarized in Table 6.7 and shown in Figure 6.4. The plutonium dispositionmission begins when the first reactor attains full power in September 2009 and is complete after the last coreload, which contains MOX fuel assemblies, has been irrad~ted for a single cycle in September 2026. Theoverall mission time is 16.9 years and starts 12.8 years after ROD.

The critical path for the alternative is the licensing, design and facility modifications of the MOX fuelfabrication facility. The schedule risk for completing a partially-complete reactor facility is higher thanschedule risk for modifying existing reactors because of the uncertainties completing the reactor facility.

Table 6.7 Partially-complete LWR alternative schedule summary

TaskTask Name

DurationID (years)

Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Process 3 12/1996 12/1999

3. PuP Facility 22.8 10/1995 7/2018

4. R&D 3 10/1995 9/1998

5. Licensing, Permitting & Siting 5 12/1996 12/2001

6. Design 5.1 12/1996 1/2002

7. Facility Modification & Preoperation 4.5 1/2002 7/2006

8. Operation 10 7/2006 7/2016

9. Decontamination and Decommission 2 8/2016 7/2018

10. MOX Fuel Fabrication Facility 30.3 4/1996 7/2026

11. Fuel Qualification 5 4/1996 4/2001

12. Licensing, Permitting & Siting 5 12/1997 12/2002

13. Design 5 12/1996 1 1/2001

14. Facility Modification & Preoperation 5 12/2001 12/2006

15. LUA Fabrication for use in a Sister Reactor 0.5 12/2006 6/2007

16. MOX Fuel Fabrication Lead Time 2.1 6/2007 6/2009

17. Operation 17.1 6/2007 712024

18. Decontamination and Decommission 2 712024 7/2026

19. Reactors 39.3 12/1998 312038

20. Mobilization and M&O Contractor Selection 2.2 12/1998 312001

21. Licensing & Permitting 5.4 3/2001 7/2006

22. Reactor Design and Construction Completion 6.5 1212003 6/2010

23. LUA Irradiation in a Sister Reactor 3.1 6/2007 7/2010

24. MOX Loading Duration 15.7 6/2009 212025

25. Unit 1 Fult Power 912009

26. Last Assemblies – First Cycle 1.5 212025 9/2026

27. Last MOX Discharged to Spent Fuel Pool 312028

28. Spent Fuel Pool Duration 27 412011 312038

29. Repository

30. Licensing 8.5 3/2002 8/2010

31. Construction 5.5 312005 8/2010

32. MOX Delivery Duration 17 5/2021 4/2038

the

89

Page 90: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

—a

l

TT

_d_

T

T-i--

–-t-

+-i-

----

l-1

I0 .

‘Ft–

–rrr

r‘t

7i”r

T’”

-vT

——

..—-—

-——

-—-—

—.

_._~-.

_. ----

----

----

----

----

-.._

_.~_

..:,

.-._

._.

_..

----

-__

___

-#__

___

___~

IIl-

-g

—.

..

.--

----

- '::T--"t-[-i---"t-"--'i-"-`l-"-F-f-"-"--"-"l-"-"---"--t--"l-i----""!-"--

?--

l--i-l

---s

’---

--.—

---—

—-

.—~—=-._

.___

P--

—--

---

—--

----

-~

—--

----

3--

----

---

~—

..-.

-

Z g—

----

-w o ..

.-. —

-—-t

-- El— r[.—----

----

--.

..—-

.—

:

75

—.—

—-

*~

g

i.w

g

; 3~

8~

~g

——

____

-.-.

—--

-.—

.~,

----

----

----

----

----

----

----

----

----

----

----

----

----

----

----

----

----

----

----

----

----

----

----

---

—.

gg

i“~

u—

—.

---

q01

—g

g

c$f

g—

----

-m

wg

a—

—-—

—-—

3—

-g

g0 g

72

8:

..

.--

---

----

----

----

----

----

----

.-—

.-.

...

.---

----

----

----

----

----

----

---

..

...

..

..

...

..

...

..

...

----

----

----

----

..

...

..

....

....

----

----

-.

..

z~

g

o;

:..

.....

....

.-

u--

----

----

.--

.---

.-.

-.--

.-.

-.--

-.-.

--...

-.-.

-.-.

..-.

-.-.

--.-

.-.

-.--

.-.-

.-...

...-

_-.

...-

----

----

----

----

----

----

----

----

----

----

----

----

----

----

----

~ z—:

2G

~&

g:.

.a

.*

Page 91: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

7. Evolutionary Light Water Reactor AlternativeThe implementation schedule for the evolutionary LWR option, 50SFE2, shown inTable 2.2, is presented in this section. This alternative uses four separate facilities: a PuP facility, a MOX fuelfabrication facility, two ABB-CE System 80+ evolutionary PWR unirs, and the HLW repository. For completedescriptions of each of the facilities and for the cost and other analyses for the evolutionary LWR option see theRASR, volume 4 (2). As mentioned in Section 2.1, other evolutionary and advanced reactor designs could alsobe used for this alternative. If an evolutiomuy LWR option had been selected at ROD, further analysis would berequired to examine the trade-offs between the various designs.

7.1 PuP Facility

The PuP facility for the evolutionary LWR case is the same as described for the existing LWR base case inSection 4.1.1 above.

7.2 MOX Fuel Fabrication Facility

The preoperational schedule for the MOX fuel fabrication facility is the same as desaibed for the existing LWRbase case in Sections 4.1.2.1 and 4.1.2.2.

7.2.1 MOX Fuel Fabrication Facility Operations Schedule

To supply fuel for the two new ABB-CE System 80+ reactcm at the specified loading rate, the MOX fuelfabrication facility will operate for fourteen yeas with an annual plutonium throughput of 3.57 MT. Thisthroughput assumes an annual output of 129 assemblies for a mission total of 1807 assemblies. A sufficientnumber of MOX assemblies for the initial core loads will be available 22 months after the start of operation. -.The operational schedule is shown in Table 7.1 and in the MOX facility schedule summary figure in Section7.2.2. This operational schedule would be modified for a different reactor type and loading schedule.

Table 7.1 MOX fuel fabrication facility operational schedule

Task DurationID

Task Name(months)

Start Finish

1. Operation 168 12/2006 12/2020

2. MOX Facility Operation Start 12/2006

3. Fabrication of Initial Core Loads 23 12/2006 10/2008

4. MOX Fuel FabricationDuration 168 12/2006 1212020

7.2.2 MOX Fuel Fabrication Facility

The overall MOX fuel fabrication facility implementation schedule is summarized in Table 7.2 and shown inFigure 7.1. This facility schedule is ~o shown in the discussion of the overall alternative schedule in Section7.5. This schedule does not include any contingency for schedule slip due to site selection difficulties, redesign,construction delays, or a delay in the approval of line item funding.

The critical path through the development of this facility is through the conceptual design and the NRClicensing process. If either of these tasks slip in their schedule, the rest of the implementation process will alsobe delayed. This critical path is shown in Figure 7.1. If a combination of a delay in the start of operations at theMOX fuel fabrication facility and an earlier completion date of the reactors is longer than 17 months, the overallalternative schedule will begin to slip.

91

Page 92: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

——

——

——

——

——

c.)

w to ..

~x_

:_$

:3

x~o+

g--

$-.-a--

~--= g=

=?!

!-.

—-—

Qd

;—

='--

"-""

""--

"``-

"""-

""--

""-"

"---

-"-"

--""

----

----

---"

"-"-

-""-

--"-

-"-"

----

-`--

---$

—&

—; a

-s

&_w

=_

;__

ZF

-y—

-g

-g_;

2-.

—g

—._

__....

.....—

—.

-__-_

_-—__

____

____

____

____

__—

3==

—s—

—--

--_-

..___

____

____

___

____

___.___

_._

_.--

----

----

----

----

----

-

--—

.._-

%..—-—

.. _-.

.—..—

---

Tm

----

-‘!

Zz-g

~—

——

$–$

w--

$J

...

....

...

...

..

..

...

...

._

~—

——

_--

----

--..

...

....

...

..

....

...

....

....

....

...

..

....

...

...

...

...

...

...

...

...

....

...

....

..

....

....

..

...

....

..

...

....

...

2..-

.9—

—.

~. =—5

@g

o ~—z

—.-

—.-

.—__

____

——

—-.

-——_

____

____

____

____

8 3—

—-—

——

3__

____

____

——

-——

—--

--

~.

....

.....

....

.....

....

.....

....

.....

....

....

...

....

....

.....

....

.....

.....

.....

.....

....

......

.....

.....

...

....

.....

......

......

......

......

......

......

......

......

......

......

..

~.--

.—-

——

----

----

---

0-—

——

____

____

Page 93: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 7.2 MOX fuel fabrication facility schedule summary

Task DurationID Task Name

(months)Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Approval 36 12/1996 12/1999

3. Fuel Qualification Demonstration 60 4/1996 4/2001

4. Site and Facility Selection 12 12/1997 12/1998

5. Select M&O Contractor 12 12/1998 12/1999

6. Licensing and Permitting 60 12/1997 12/2002

7. Design Process 60 12/1996 1 1/2001

8. Facility Modification 36 12/2001 1212004

9. Preoperational Phase 24 12/2004 12/2006

10. PuP Facility Lead Time Complete 9/2006

11. MOX Facility Ready for PuO, 12/2006

12. Operation 168 12/2006 12/2020

13. Decontamination & Decommission 24 1212020 12/2022

7.3 Evolutionary PWR Facility

7.3.1 Evolutionary PWR Facility Design & Construction

The duration and path of the design and construction tasks are based on the construction of a new evolutionary ‘-reactor facility developd by Fluor Daxdel(9). Depending on the specific reactor design .selec@ this design adconstruction schedule might be shortened if an already certified design exists, or if modular constructiontechniques are used.

After the intermediate approval of line item funding, the project begins with the selection processes for theM&O contractor, reactor vendor, and the appropriate federal site. After completion of these tasks the reaetordesign work begins. Site preparation begins 16 months before the license process is complete. After thecombined license is granted, the fwst nuclear concrete is poured. The design and construction schedule is shownin Table 7.3 and Figure 7.2. Construction on the second reactor unit starts one year after construction starts onthe f~st unit and proceeds following the same schedule.

7.3.2 Evolutionary PWR Facility Licensing and Permitting

For this analysis a licensing schedule developed by Fluor Daniel (9) for a large evolutionary LWR was followed.The licensing schedule is shown in Table 7.4 and Figure 7.3.

To begin the licensing process, the site specific ER and combined license application are developed adsubmitted to the NRC. The NRC conducts technical reviews of the combmed license application and developsthe EIS and the SER. The schedule includes a provision for a year-long full discovery period and a two-yearhearing and decision process by an ASLB. The requirement for these processes are subject to petitions for ahearing on specitlc issues. After a decision is issued by the ASLB, the NRC grants the combined license and thesafety-related construction of the reactor facility may begin. The NRC will also conduct Inspections, Tests, andAnalyses of Acceptance Criteria (ITWC) during the construction process.

93

Page 94: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 7.3 Evolutionary PWR facility design and construction schedule

TaskID

&1.

2.

E3.

4.

5.

6.

7.

8.

9.

10.

11.

E12.

13.

14.

15.

16.

17.

Task NameDuration(months)

Start

FMDP Record of Decision

Intermediate Funding Approval 24 12/1996

Mobilization & Select M&O Contractor 33 12/1998

Site Selection 18 12/1998

Reactor Design 78 9/2001

Design to Procurement & License Support 30 9/2001

Post Procurement Design & License Support 48 312004

Construction, Procurement, Installation 81 3/2004

Procurement of Reactor System 48 312004

Unit 1 60 11/2004

Site Preparation 16 11/2004Construct from 1st Nuclear Concrete to 23 2/2006Equipment Delivery (ED)

Complete Construction 22 1/2008

Unit 2 60 10/2005

Site Preparation 16 10/2005

Construct from Ist Nuclear Concrete 23 2/2007

Complete Construction 22 1/2009

10 Task Name 951 FMDPRocotdof Dooition ,2,

2 Ccmgr@adondFunding Appmv.1

3 ProgmmMobifimtiom& WO COntrOetOrSOkOtion

4 Sits ?.dutbn

6 NRCLcensing

e Rmtior Duign

7 Maled 08sigl to Procurement & tical$e SLppOrl

8 Pest PrOcummeat 0.3sign h Lice-meS.~

e COn*trucdOn, PrOcumm*nt h Installatho

10 Pmummem d Reaztw Syst6m

11 Unill

12 SJtoPreparatk

13 Ccnstrucl km 1d Nuclear Gwete ta EO

14 Ccnstrud fran EO to [email protected]

Is Unfi 2

16 Site Prcparatica

17 Cm$trud fran 1m Nuclear wmb to EO

18 CrnsW km EO to CcmpWmn

,

wF’MOP Fk

~

z

E#l

T1c504070sm

>g *W.+

ji=ti~ ,~&om ~

J?Jl N Ctic8r8 1-q

Ill

tiM2ded 0.3siw 10 Prom

I I I

i

t

:

n

Finish I12/1996

12/1998

8/2001

6/2000

2/2008

2/2004

2/2008

11/2010

212008

11/2009

212006

1/2008

11/2009

11/2010

2/2007

112009

1 1/2010

T1 12 13 14 1s 16

d m

.4 Licalse slppml

1111nmt Ckign & fkanse SL

tdb b

{d Reactor systern

I 1st Nuclear Ccacmte to

11111IruclIran EO to Canpld,

I fmm 1s1Nuclear Ccmcru

:~strw!!fr~ E~,o~~~

ii

)01

)

to

*1—

8

I

TaskPrqect Reactoroasi~ & Cmstruclicm

~ MJestcoa +

criti~ Ta* EZZZZZ5 S...v ~

.

Figure 7.2 Evolutionary PWR facility design and construction schedule

94

Page 95: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

,,

Table 7.4 Evolutionary PWR facility license and permit schedule

Task DurationID Task Name

(months) Start Finish

1. NRC Licensing Process 54 9/2001 2/20062. DOE Prepares & Files Comb. License App. 12 9/2001 8120023. Public Notice of Application for License 8120024. NRC Performs Tech. Reviews for License 12 912002 8/2003

5. NRC Issues SER 8/2003

6. Pre Hearing Conference 6 9/2002 2/2003

7. Full Discovery 12 3/2003 212004

8. Hearing by ASLB 12 312004 2/20059. Decision Issued by ASLB 12 2/2005 212006

10. NRC Issues Combined License 2/2006

11. NRC Environmental / NEPA Process 24 9/2001 8/200312. DOE Prepares and Files ER 12 9/2001 8/200213. NRC EIS Process for Combined License 12 9/2002 8/200314. NRC Issues EIS 8/200315. Site Permits 24 9/2001 8/2003

10 Task Name I 2001

1 NRC Lkemaing Pr~eav

I

2 DOE Prepares and Files Combined Llcenae Application

3 Public Notice of Appliiafion for Lkertse

4 NRC Performs Technical Reviews for Combined Llcenst

I5 NRC Issues SER

,6 Pre Hearing Conference

7 Full Oiacovery

I

t8 Hearing by ASLB

I

12 DOE Prepares and Files ER

13 NRC EIS Process for Combinad LicenseI,

14 NRC Iaeues EIS

f

t1s Site Permits

e

200212W3120041200512006 2007 2008

cLjI=rPl=a@ I ~ ~

~ DOE Preparea and Fi!ea Combined Licerse Appfiialion

~ Pre H$ng C{nferenc;i

~1 ~~ Full pry I

!1:~ Hearirg by ASLB

I II~~ Decision Issued by AS1

,1 2/24& NR~laauas/lmtincI

“TT”r’-r--j\

_ DOE Prep:raa and ~bs ERi

:1N’RCEIS Process for Combiced Licenae

{z, ●lNRCISS~.EISII

~ S[e permi{s

t 1

200s

Lken

Licens

2010

TaskProject Reacfor License & Permit

~ ~lestofw +

Critical Task fZZZZZZ summary ~

Figure 7.3 Evolutionary PWR facility license and permit schedule

..

95

Page 96: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

7.3.3 Evolutionary PWR Facility Operations Schedule

After completion of the f~st unit, the preoperational checkout and start-up testing begins. The fuel is loaded intothe reactor vessel in June 2010 and additional physics tests are perforrqed prior to ascending to full power. Fuelis loaded into the second reactor unit two years later than the f~st unit. After the MOX fuel has been imdatedfor the full cycle of 3.75 years, the spent fuel assemblies are discharged from the reactors and stored in the spentfuel storage pool for a minimum of ten years before being shipped to the HLW repository facility. Theevolutionary PWR facility operational schedule is shown in Table 7.5 and in the facility schedule summaryfigure in Section 7.3.4. This operational schedule would be modiflxl for a different reactor type or loadingschedule.

Table 7.5 Evolutionary PWR facility operations schedule

Task DurationID Task Name

(months)Start Finish

1. MOX Facility Lead Time 24 12/2006 11/2008

2. Preoperational & Startup Testing 7 11/2009 6/2010

3. Reactor Facility Operation 205 6/2010 712027

4. Unit 1 Loadi~g Duration 142 6/2010 412022

5. Unit 1 Futl Power 1/2011

6. Unit 2 Loading Duration 136 6/2012 10/2023

7. Last Assemblies - f~st reshuffle 9 10/2023 712024

8. Last MOX Discharged after futt irradiation 45 10/2023 7/2027

9. Spent Fuel Storage 274 10/2014 7/2037

10. First MOX in Spent Fuel Pool 120 10/2014 10/2024

11. Last MOX 120 8/2027 712037

7.3.4 Evolutionary PWR Facility Schedule Summary

The overall evolutionary PWR facility implementation schedule is summarized in Table 7.6 and shown inFigure 7.4. This facility schedule is also shown in the discussion of the overall alternative schedule in Section7.5. This schedule does not include any contingency for schedule slip due to site selection difficulties, redesign,construction delays, or a delay in the approval of line item funding.

The critical path through the development of this facility is through the line item funding process, programmobilization, and the NRC licensing process. If any of these tasks slip in their schedule, the rest of theimplementation process also will be delayed. This critical pati is shown in Figure 7.4. If the programmobilization process proceeds more quickly, or the ASLB hearing process is redueed in scope, the reaetor wouldbe ready earlier than shown in this schedule. If the overall duration of the preoperationrd tasks for the nmctorfacility is redmxd by more than 17 months, the start of reaetor operations will be delayed by the MOX fuelfabrication facility operations.

..

7.4 HLW Repository Facility

The HLW repository facility schedule is the same as described for the existing LWR base case in Section 4.1.4,except the spent MOX fuel is scheduled to be delivered to the repository facility from November 2024 to August2037.

96

Page 97: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

——

..—.

...——

.——

____________x

——

______-

1 —.........-—–i..-...s__5x

.—.~--—

—-.

--—_____

—________________

~--

%

----------------------------------------------------------_________________

~i%

t ,.-..

clM

——

..----..--.-—____________________

__.!j_._._:_-._

z.d

?.

—-g

._.../j---

——

____________

~;

(%.-:x

:

.s{;

“i5

n%

n.

-.&

——

—m.

*.—

Page 98: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 7.6 Evolutionary PWR facility schedule summary

TaskTask Name

Duration

ID (months)Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Approval 36 12/1996 12/1999

3. MOXFacility Lead Tme 24 12/2006 11/2008

4. Mobilization & Select M&O Contractor 33 12/1998 8/2001

5. Site Selection 18 12/1998 6/2000

6. Licensing and Permitting 54 9/2001 2/2006

7. Preoperational Phase (unit 1) 7 11/2009 6/2010

8. Reactor Facility Operation 205 6/2010 712027

9. Last Assemblies - fmt reshuffle 9 10/2023 712024

10. Spent Fuel Storage 274 10/2014 7/2037

7.5 Evolutionary LWR Alternative Schedule Summary

Theevolutionary LWR alternative schedule is a combination of the individual facility schedules discussed above.‘his overall schedule is summarized in Table 7.7 and shown in Figure 7.5. The plutonium disposition missionbegins when the fust reactor attains full power in January 2011, and is complete after the last core loa& whichcontains MOX fuel assemblies, is reshuffled for the fwst time in July 2024. The overall mission time is 13.5years and starts 14 years after ROD.

The critical path for the alternative is the licensing, design and construction of the reactor facility. However, as-.

discussed above, delays in the constmction of the MOX fuel fabrication facility or PuP facility may move eitherof these facilities into the critical path.

The schedule risk for the PuP facility and MOX fuel fabtieation facility are the same as for ttte other reaetor-based alternatives. The schedule risk for building an evohstionafy reactor facility is higher than the schedule riskfor modifying existing reactors because of the uncertainties in siting and building new nuclear power reactors.

98

Page 99: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

Table 7.7 Evolutionary LWR alternative schedule summary

Task DurationID

Task Name(years) Start Finish

1. FMDP Record of Decision 12/1996

2. Congressional Funding Process 3 12/1996 12/1999

3. Pu Processing Activities 22.8 10/1995 712018

4. R&D 3 10/1995 9/1998

5. Licensing, Permitting & Siting 5 12/1996 12/2001

6. Design 5.1 12/1996 1/2002

7. Facility Modification & Pre-Operation 4.5 1/2002 7/2006

8, Operation 10 7/2006 7/2016

9. Decontamination & Decommissioning 2 8/2016 7/2018

10. MOX Fuel Fabrication Facility 26.6 4/1996 12/2022

11. Fuel Qualification 5 4/1996 4/2001

12. Licensing, Permitting & Siting 5 12/1997 1212002

13. Design 5 12/1996 11/2001

14. Facility Modification & Pre-Operation 5 12/2001 12/2006

15. MOX Fuel Fabrication Lead Tne 1.9 12/2006 10/2008

16. Operation 14 12/2006 12/2020

17. Decontamination & Decommissioning 2 1212020 12/2022

18. Reactors 38.6 12/1998 712037

19. Mobilization and M&O Contractor Selection 2.7 12/1998 8/2001

20. Licensing 4.5 9/2001 2/2006

21. Reactor Design and Construction 9.2 9/2001 11/2010

22. Unit 1 “ready” to accept MOX 6/2010

23. MOX Loading Duration 13.3 6/2010 10/2023

24. Unit 1 Full Power 1/2011

25. Last Assemblies – First Reshuffle 712024

26. Last MOX Discharged to Spent Fuel Pool 712027

27. Spent Fuel Pool Duration 22.8 10/2014 712037

28. Repository

29. Licensing 8.5 3/2002 8/2010

30. Construction 5.5 3/2005 8/2010

31. MOX Delivery Duration 12.8 11/2024 812037

99

Page 100: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

1 i- .

1:+iij

..—-n..2 ~g

.‘%

zj-{

-n

...—

088

2$

qj

.u—

~-.—

,j.

~$

?>

.—E

...z?

~~

g&

-.._

_~_.

-%.._

._..

j___

;{

1,;

;;

—--

-—

. ~---

-$--

---

-$--

+

__.

.__.

.;_.

._j._

j.._.

._..

.;._.

._.

F!

;:

~—

.—.

—..-

—.—

..—..—

.——

..6

.8.–

..–z

:.

;:

;?.

-..-

..—

..=.

..

.._.

..

i-””

Eg

;.

-..—

-—

..~.

..

..._

.._-,

Ik& .

-.-...

g-.

!._.....

_.._._.._

..:u

.;g .

.!&.ii-

;m-..-

..-..-..—

—.

—..

_.._.._.._-_.

.:8

s~g

-~,--

-–--

—-–

--–-

.–.....

=- ggg

w~--

-g-—-

--–-

.—.—..—

.-:.

..—.—.–.

.—..—

..—..

—.

—..

—.

—..

—..—

..L_

__F~8 ~g

~-..-..

_.._.._.._

.._.

.......

..__

3%

~–R ~m

..—._

.__

._.__

_._

.._.._..__

_ w--_.

._.._

_.,_

.._.

—-—

..—_,

—-~ z

~8~

E:—_

____

____

____

_—

——__

____

____

_g~ u:

“-”’

1—

.J—..

—..

—..—.._

..._

..__.

-..--—

..— -—

..—...IL i3

—.._.

_._.

..

—..—

lL.-

..—..—..—..—

..—

..—.

.—..—.._

...

....

....

....

....._

,,_,._. }-

1—

..—

-—

..—

..—

----

----

___

.._

1—

-—

-—

.—

..-..

..—

..—

..—..—

..—

..— -..-

L-.;

.-. 3

~l!.

8—

—..

-.—

..—

.-..

..-.

.-..

.=—

.~

-

I I“;2

---

-g-

–-–.

&----

-g

—..—

.. $_.

..._

=

O_

z-..—

...*.

..—.

–m ~

;—

—..

..–f.

..–.

–__.

_.._

:g w

—..—

..g

-..

..—~—

.._.._

.——

..-

---

i--

..-f.

..-.–

..–.-

.--

---

g

—..—

..—..—

..—..—

.—..—

..——

..—.—

T--

..—--

----

..—--

---

.—.

—..

—.-

..-—

.-.

.-—..-

.-..

.— 11A—

..—__

____

____

___

_..

.._-_ i’

—..—.—.—

.—

..—._._

.._..__.

._ --~.

._—

.—..—

.__

,_.,_

.._.__

---

_._.

_.._

._–-

_.__

.--

g_.:..

_-..-..-.._.G--..-+.-

-..5

-$_ ‘-l

(-l

z—

--—

.$—

...5-

...=_

.._.._

~.._

.:s

73

.Q

2--

—-—

.-.

p.-

..—

i-—

_._.

_.g_

s :’””

----

---

----

-— ;.

..~xi

?9

-..—

—..

-—..

--..—

-~

____

___

.

—.—

.——

..-

—.

_.._

.._.

.___

._..

_

-..~

-..-

.-

5—

g—.._..

_x..

._..

_.._

.._

.....

..–

.-.._

ii

-.i&

&–

____

____

____

_-

..f__

;___

____

.Z

_..

_.._

.._.-.._

..–.

–..–

..–.

-.–

—; 2

—~

----

-..-

---—

-—__

._._

._,

*

.--.—

--..—

..—

..—..—

..— :1[”

:.—

..—..

—I

—..

—..

—.._ &&

. P

4-.

—.—

—-

.......

_._-_

,_

I-–..—

-.o-

-–-.-

.-.--

-—-

% ~—

..--—

——

.$ --—

..-.—

..-..—

—-—

.—.—

..—..—

...—..—

.——

.—.-

,

..—-.

.—.—

..—..—

.—._

,

Hgg

~:

.-.

________________

1+~~

ol~

____

____

____

____

____

____

____

____

____

____

____

____

_. g

g Wg .~

____

____

___,

__

—-—

—._

._._

_-_,

,_,

,_._

.._

–.-.-

-—--

--—

-—

--—

--—

......

.......

......

......

......

......

......

..... ..

uz ~

—.—

..—~-

””-

f ~--–

..—..-

,~ i .-

.—..-

-—-,

5 ,

$HX

&-

=..

.....

..—..—

..—.._

..—..—

..

.._._

.._..—

..—..—

..—..—

..—..—

..—..—

..—..—

..—..—

..—.._

.._..—

..—..—

.—..—

.._._

.—..—

—..—

..—.—

.._.._

wg

.2 9

$ –2

-g---

------

"`----

""---

"---"-

"-----

"----"

"-"-"-

--""--

-'-""

-"----

-""-`"

-""-""

--"-`"

-"-"--

-""--"

'$;

o .~

g-J

_..-

---_

__._

-_..

_._

_..

_..

_.

_,.

_-_.

._

_._

._

,_,

__

__

__

__

__

__

__

__

__

__

__

__

__

__

__

__

__

__

__

__

__

_

g

Page 101: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

8. Schedule SummariesThe overall alternative schedules are based on combining the individual facility schedules. The individual facilityschedules wem developed using estimates of the time required for the design, engineering, and constructionphases based on previous experience. For the plutonium processing, MOX fuel fabrication, and collocatedfacilities, the NRC licensing process and DNFSB oversight process were assumed to take five years. For thevarious reactor facilities, the appropriate NRC reactor licensing process and schedule described in the FluorDaniel Report (9) was used. Also, a two-stage congressional line item approval constraint is included in eachfacility schedule. The first stage of the approval has been assumed to require two years. No Title I or detaileddesign work may start prior to this time for the processing facilities. For the reactor facilities, no utilityselection, site selection, or licensing processes are started before this date. The construction of any new facilitymay begin as soon as a year before a license is granted, however, no safety related construction may begin untilafter the license is granted.

The alternative with the shortest mission time is the existing LWR base case, 50SFL5. The earliest missionstart is the existing LWR quick start alternative, 50QSL5. A summary table of the nine options is shown inTable 8.1.

The critical path through the facilities for all of the alternatives, except for the evolutionary LWR, is throughthe MOX fuel fabrication facility. For the options which use only American fabricated fuel, the existing PWRSare ready to start-up six years before the LUA irradiation is complete, and the BWRS are ready to start-up fiveyears before. The CANDU reactors are ready to start-up five years before the fuel fabrication facility lead time is

Table 8.1 Reactor-based disposition alternatives schedule summary

I Option I

;::~5 50COL4 50QSL5 50SFP2 50SFE2 50 SFC2-4 33SFL3 33SFC2

Pu Processing Facility

prototype NA NA Jan-98 NA NA NA NA NA

start processing at 8/2006 612007 8/2006 8/2006 8/2006 8/2006 8/2006 8/2006production facility

MOX Fuel Fabrication Facility

start LUA fabrication 12/2006 7/2007 6/2000 12/2006 NA NA 12/2006 NA

mission fabrication start 6/2007 12/2007 3/2001 6/2007 12/2006 12/2006 6/2007 12/2006

mission fuel finish 4/2017 712023 12/2015 712024 12/2020 2/2019 2/2018 10/2017

Reactor FacilitySystem System

reactor type PWR BWR PWR80 80+ CANDU PWR CANDU

reactor “ready” to 3/2004 3/2005 3/2004 612009 6/2010 7/2002 2/2004 7/2002accept MOX

start irradiating NA NA 12/2002 NA NA NA NA NAEuropean LUA

start irradiating 6/2007 1212007 6/2007 6/2007 NA NA 6/2007 NAAmerican LUA

mission start 5/2010 4/2010 11/2005 9/2009 1/2011 6/2007 5/2010 6/2007

last assembly loaded 2/2020 10/2026 1/2019 2/2025 10/2023 8/2019 11/2020 4/2018

mission finish 8/2021 1212027 712020 912026 712024 10/2020 512022 7/2019

Mission duration

(Y r.) 11.3 17.7 14.6 16.9 13.5 13.3 12.0 12.1

ROD to mission start

(Y r.) 13.5 13.3 9.0 12.8 14.1 10.5 13.5 10.5

101

Page 102: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

complete. The first partially-complete LWR could be ready to start-up three years before a sufficient number offuel assemblies have been fabricated to supply the two teactors at the s~fied rate. For the evolution~ light

water reactor alternative, a sufficient supply of MOX fuel is ready eighteen months before the reactor

construction is complete.

Using European fabricated fuel to initiate the mission moves the start date 4.5 years earlier for the existingPWR base case. If European fabricated LUAS were used, without using European mission fuel, the mission startcould occur one irradiation cycle earlier because the reload license would be granted after one cycle of theAmerican LUA instead of two cycles. However, for the BWR option and the partially-complete LWR option,which use integral neutron absorbers, European fabricated LUAS are unlikely to be available. For the CANDUreactors, the time to start the mission would also be improved if the initial fuel could be fabricated in Europe.However, as the European fuel fabricators do not currently fabricate CANDU fuel, it is unlikely that this wouldoccur without a full fuel development program. For the evolutionary LWR option, an earlier start of themission would be achieved if the reactor licensing and construction could start sooner. Also, the missionduration could be shortened by building an additional reactor, however, this would have a substantial impact onthe cost of this option.

The schedule risk for the existing BWR option is slightly higher than the schedule risk for the existing PWRoptions because the MOX fuel design includes integral neutron absorbers. For the partially-complete LWRalternative, there are several schedule elements which involve a higher degnx of schedule risk than in theexisting LWR options. For example, completing the reactors involves some uncertainties such as whether ahearing by an ASLB is required. The fuel qualification process for the new fuel design containing integralneutron absorbers also involves some schedule risk. The schedule risk for the evolutionary LWR alternative ishigher than the partially-complete reactor because building a new ~actor has even more schedule uncertaintiesthan completing a partially-complete reactor. The CANDU options have about the same schedule risk as theexisting LWR options.

102

Page 103: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

9. References

12

3

4

5

6

7

8

9

Fissile Materials Disposition Program, Swnntaty Report of the Screening Process, DOE/MD-0002, 1995.Oak Ridge National Laboratory, FMDP Reactor Allerna(ive Summary Report, Vol. 1 – Existing L WRAlternative, ORNL/TM-1375/Vl, September 1996.Oak Ridge National Laboratory, FMDP Reactor Alternative Summaq Report, Vol. 2 – CANDU ReactorAlternative, ORNL/TM-1375/V2, September 1996.Oak Ridge National Laboratory, FMDP Reactor Alternative Summary Report, Vol. 3 – Partially-CompleteLWR Alternative, 0RNL/TM-1375/V3, September 1996.Oak Ridge Natioml Laboratory, FMDP Reactor Alternative Sumnwy Report, Vol. 4- Evolutional L WRAlternative, ORNL/TM-1375/V4, September 1996.Office of Fissile Materials Disposition, Department of Energy, Technical Summary Report Long-TermStorage of Weapons-Usable Fissile Materials, DOEiMD-0004, July 1996.Lawrence Livermore National Laboratory, Vi@ijication Greenjeld Alternative, UCRL-ID-122663, L20215-1, 1996.Lawrence Livermore National Laboratory, Vitrification Can-in-Canisler Ahernative, UCRL-ID-122659,L20216-1, 1996.Lawrence Livermore National Laboratory, Vilification Adjunct Melter to DWPF Alternative, UCRL-ID-122660, L20217-1, 1996.Lavmnce Livermore National Laboratory, Ceramic Greenjleki Alternative, UCRL-ID-122662, L20218-1,1996.Lawrence Livermore National Laborato~, Ceramic Can-in-Canisler Alternative, UCRL-ID-122661,L20219-1, 1996.Lawrence Livermore National Laboratory, Elec(rometallurgical Treatment Alternative, UCRL-ID-122664,L20220-1 , 1996.Lavmnce Livermore National Laboratory, Immobilized Disposition in Deep Boreholes, Version 3.0,UCRL-LR-121736, 1996.Lawrence Livermore National Laboratory, Direct Disposition in Deep Boreholes, Version 3.0, UCRL-LR-121737, 1996.Office of Fissile Materials Disposition, Department of Energy, Technical Summary Report for SurplusWeapons-Usable Plutonium Disposition, DOE/MD-0003 Rev. 1, October 1996.National Academy of Sciences, Managenwnf and Disposition of Excess Weapons Plutonium, Washington,D.C.: Nationat Academy Press, 1994.Department of Energy, Storage and Disposition of Weapons-Usable Fissile Materials Final EnvironmentalImpact Statement, DOJYEIS-0229, December 1996.Department of Energy, Record of Decision for the Storage and Disposition of Weapons-Usable FissileMaterials Final Environmental Impact Statement, DOE/ROD-???, January 14, 1997.Department of Energy, Press Release, “Energy Secretary Unveils Strategies to Reduce Global NuclearDangen Post-Cold War Plans for Plutonium Disposal, Weapons Dismantlement and Solar Energy at Nevada Test

Site Announced”, December 9, 1996.Fluor Daniel, Inc., Regulato~ Plans for NRC Licensing of Fissile Materials Disposition Alternatives,6/26/95.

103

Page 104: A Preliminary Analysis of the Reactor-Based Plutonium ......SAND97-8288 Unlimited Release Printed September 1997 Distribution Category UC-721 A Preliminary Analysis of the Reactor-Based

UNLIMITED RELEASE

INITIAL DISTRIBUTION:

4 ShernAIGreeneOak Ridge National LaboratoryPO Box 2009Bldg. 9104-1, Mail Stop 8057Oak Ridge, TN 37831-8057

1 Dan O’ConnorOak Ridge National LaboratoryPO Box 2009Bldg. 9104-1, Mail Stop 8057Oak Ridge, TN 37831-8057

1 MS 9001 T. O. Hunter, 8000Attn.: J. B. Wrigh~ 2200

L. A. West, 8200W. J. McLean, 8300R. C. Wayne, 8400P. N. Smith, 8500T. M. Dyer, 8700P. E. Brewer, 8800D. L. Crawfora 8900

1 MS 9005 W. G. Wilson, 22211 MS 9004 M. E. John, 8100

Attn.: L. D. Brand~ 81121 MS 9201 P. K. Falcone, 81141 MS 9202 R. L. Bierbaum, 811610 MS 9202 R. M. Zum (10), 8116

3 MS 9018 Central Technical F~les,8940-24 MS 0899 Technical Library, 49161 MS 9021 Technical Communications Department,

8815/Technical Library, MS 0899,49162 MS 9021 Technical Communications Department,

8815, for DOE/OSTl

104