3 18-Feb-2004PM Report, GSC meeting Code development: Successes Workflow JES: since Itn03 Templates: Itn04 BPEL subset: Itn02: to be revised Data centre Merlin, 6dF, INT WFS, USNO-B: ongoing MySQL, Sybase, SQL Server CDS VizieR, NVO Conesearch Incorporated IVOA ADQL standard **Trial only**: need archive take-up
Citation preview
A PPARC funded project
PM Report
Grid Steering CommitteeMRC, London18-Feb-2004
18-Feb-2004 PM Report, GSC meeting 2
Status since Jul-2003!Code developmentMilestones summaryProject managementRisk assessmentExternal interactionsAstroGrid-2
18-Feb-2004 PM Report, GSC meeting 3
Code development: SuccessesWorkflow JES: since Itn03 Templates: Itn04 BPEL subset: Itn02: to be revised
Data centre Merlin, 6dF, INT WFS, USNO-B: ongoing MySQL, Sybase, SQL Server CDS VizieR, NVO Conesearch Incorporated IVOA ADQL standard **Trial only**: need archive take-up
18-Feb-2004 PM Report, GSC meeting 4
Code development: SuccessesPortal Cocoon-based approach: Itn04.1
Registry XML-based, XQuery usage: Itn03: to be
improved Conforms to IVOA RM 1.0, schema 0.9: Itn04
Community Authorisation, permissions: Itn03/4
(easy upgrade to certificate based authorisation: Itn06+)
18-Feb-2004 PM Report, GSC meeting 5
Code development: SuccessesGDW Uses OGSA-DAI & AstroGrid Web Service:
Itn04Tools ACE: Sextractor: Itn02, updated Itn04.1 HyperZ: Itn04.1 XMatch: Itn04.1
Includes VOTable merge facility
18-Feb-2004 PM Report, GSC meeting 6
Code development: Problem areas
Portal Not user-friendly screens
Itn05/06: redesign all screens Itn07+: focus on usability
MySpace Difficult to integrate Reliance: needs to be optional
Itn05: design review, disentangle from components
Itn06: refactor
18-Feb-2004 PM Report, GSC meeting 7
Milestones summaryPortal All screens delayed
Delivered generalised templateWorkflow, JES On targetAstroPass Concept delivered;
Itn06: certificate-based schemeData Centre On targetRegistry Delivered IVOA standardsCommunity On targetTools In advance: several tools delivered
Generalised code enables many toolsVisualisation In advance: via client- & server-side
integration of TopCatMySpace Delayed
See http://wiki.astrogrid.org/bin/view/Astrogrid/IterationDeliverablesR02 for comment on original milestones.
18-Feb-2004 PM Report, GSC meeting 8
Project ManagementSuccesses Single team, multiple workgroups Dynamic assignment Iterative development
Problem areas all of above!
Key: continuous integration
18-Feb-2004 PM Report, GSC meeting 9
Risk Assessmentsee http://wiki.astrogrid.org/bin/view/Astrogrid/ProjectRisksR03
Key issues: AstroGrid-2 Grid Web Services Resource Framework
Uprated risks: Data centre uptake Loss of development personnel
Downgraded risks: Grid & OGSA-DAI impacts Loss of senior personnel
New risks: WSRF focus of GT4
18-Feb-2004 PM Report, GSC meeting 10
External interactionsAVO Demo
IVOA Registry ADQL Data Access Layer Data Model
18-Feb-2004 PM Report, GSC meeting 11
AstroGrid-2Aspects Extension
Infrastructure Grid (GT4+) integration Intelligent resource discovery (semantic grid)
Additional components Data exploration Agents: eStar integration Client-based access: VO Workbench
Design Study
18-Feb-2004 PM Report, GSC meeting 12
AstroGrid-2…Design study: Goals Add to infrastructure Integrate with existing/planned services D rather than R Minimise staff loss
Future maintenance AstroGrid Software Foundation?
cF http://www.apache.org/foundation/