Upload
armandogo92
View
244
Download
1
Embed Size (px)
DESCRIPTION
Este artíciculo habla sobre economía y costos de oportunidad
Citation preview
ORIGINAL ARTICLE
A method to exchange the demand of productsfor cost improvement
Sanjay Sharma
Received: 18 October 2007 /Accepted: 3 February 2009 /Published online: 24 February 2009# Springer-Verlag London Limited 2009
Abstract In a multiproduct manufacturing environment, theactual demands of various products are either available, orthese are expected. There are situations when demand of aproduct can be substituted with that of another. In the contextof cyclic manufacture, all the items are produced in an optimalcycle time, and the production facility runs at certain costlevel. The total cost consists of the facility setup cost,inventory carrying costs, and the manufacturing time costfor the basic case. The total cost is optimized. For the purposeof total cost improvement, a method is presented in which thedemand of a product is exchanged with that of another item inthe group. The basic model without backorders is analyzedfirst. Then, it is extended for an inclusion of shortages that areeither completely backlogged or partially. In addition to thecost components discussed before, shortage costs are includedin the total cost for this case. Finally, after a discussion of idletime costs, these are also included briefly in the formulation ofthe total cost. The proposed methods are useful for imple-mentation in a variety of industrial or business situations in thecontext of internal benchmarking or gradual improvement.
Keywords Multi-item cyclic manufacture . Demand rate .
Production time . Idle time costs
1 Introduction
In the manufacturing firms, one or more products are madein certain cycle time. In order to become competitive, theprogressive firms are expected to run their production
facilities optimally. However, when most of the firmsachieve this level, there is loss of competitive edge, andfurther cost reduction becomes necessary. In such a scenario,an examination of significant parameters is essential.Demand management is critical nowadays, and therefore, amethod is explored in the present paper to exchange thedemand of products for cost improvement in certain cases.
In a continuous production, single standard product ismanufactured in large quantities. Even if the type ofproduct is similar, it can be produced in a wide variety ofsizes. For instance, in a tube or pipe manufacturingindustry, these are in different diameters/thicknesses. In ajob shop/batch production also, several items are processedin a cycle time. For example, if the cycle time is 3 monthsor 0.25 year, all items/product varieties are manufactured inthe cycle time. This is called as common cycle time. If theproduction rate of an item is, say 300 U per month, and thedemand rate is 100 U per month, the production time in acycle time of 3 months will be 1 month, i.e., 3×(100/300).Benefits can be achieved by synchronizing productionactivities sequentially in a cycle time [3]. A relevant costneeds to be estimated/modeled for the concerning produc-tion environment. For example, if shortages are notallowed, the shortage costs will not become a componentof the total relevant cost. After an optimization of the totalrelevant cost, a common cycle time is usually obtained inwhich all the items in a family are produced. A generalizedproduction cost is used [1] including shop floor index, thevalue of which lies in the range 0–1. The generalizedproduction cost is obtained as the multiplication of fixedproduction cost and a factor that is an exponential order ofthe ratio of production rate to demand rate of an item.
In the context of modeling process, the rate of manufac-ture and demand rate are among significant input parameters.Manufacturing rate is considered to be a decision variable
Int J Adv Manuf Technol (2009) 45:382–388DOI 10.1007/s00170-009-1959-1
S. Sharma (*)National Institute of Industrial Engineering (NITIE),Vihar Lake, Mumbai 400087, Indiae-mail: [email protected]
[8]. Shortages are included in the production system. Thesemay be backordered completely/partially. Various cases areanalyzed [5–7, 9] for single/multi-item scenario. Thedemand rate per year or an annual demand needs to beadjusted in order to incorporate partial or fractional back-ordering situation. For a single product case, the demandincrease is included in different context [2, 4] consideringdemand function with respect to time. As it will be discussedlater, a quite different approach is presented in this paper inthe context of multiproduct manufacturing environment.This is expected to be useful in certain situations of businesswhen more or less stable product demands exist.
In the traditional production/manufacturing setup, thedemand is analyzed solely as an input parameter. In thepresent paper, the demands are being viewed in an uncon-ventional manner. For instance, several production lines run inparallel in the pharmaceutical industries. Whether it ismultiple or single production line, a batch production isusually adopted. After certain development or value addition,the management wishes to promote the improved product(which may be patented in a different name) at the cost ofsimilar (more or less for medicinal purpose) matured product.However, the improved product is at least presently in lowerdemand because of either the availability of a familiar maturedproduct at higher demand level or lack of awareness. Thismayalso be due to purely psychological or emotional reasonsattached to a familiar product. As the aggregate demand ismore or less uniform for similar types of products, theproduction strategy may be based on a conscious anticipateddemand swapping. Further, there should be a strong justifica-tion if it yields into the total relevant cost reduction.
In oligopoly, few firms dominate the market. While inthe monopolistic competition, many firms are active insatisfying the market demands. Whether it is monopolisticcompetition or oligopoly, each progressive firm in theindustrial sector would run their production operations at acertain optimum level. There is continuous pressure toadopt a kind of internal benchmarking and improve theproduction/operational cost further. In a planning period, itis possible to substitute the demand of an item by anothersuitable item in the product family. The firm may haveinvested in product development activities. It would like toexchange the lower demand of new product with higherdemand of an old matured product, and the firm manage-ment is confident of getting it consumed as a substitute inthe market. In yet another situation, a factory may facequality problems related to the input item of a product, andit wants to exchange the demand of such a product withanother in the short-run. In many cases, contribution perunit is almost similar for the products in a family. It is aninteresting approach to explore the possibility concerningthe exchange of demand of items and examine the effectson total relevant cost.
With the purpose of an internal benchmarking/improve-ment activities, it seems reasonable to consider an appro-priate item whose demand is to be interchanged by anyother remaining item in the group. The present paper isdivided into nine sections. Assumptions and notations areprovided in the “Assumptions” section, followed bymethodology in the “Methodology” section. Mathematicalformulation for the basic problem is dealt with in the“Mathematical formulation” section followed by an illus-trative numerical example in the “Illustrative example”section. Shortages are included in the “Extension forshortages” section with the assumption that all the shortagequantities will be backordered completely. This assumptionis relaxed in the “Partial backlogging” section. An idle timecost is introduced in the “Incorporating an idle time cost”section for this approach, and finally, the concludingremarks are provided in the “Concluding remarks” section.
2 Assumptions
An industrial organization is engaged in the production ofmultiple items in a common cycle time. The manufacturingfacility is being run conventionally in an optimum manner. Itis often difficult to obtain information for benchmarkingpurpose particularly at the production facility level. With theaim of a gradual improvement, an intentional search is madeto exchange the demand of an item (strategically selected bythe management) with another appropriate item in the familyfor any potential cost reduction. A business environment ofstable demand exists in general. The proposed methodconsiders an exact interchange of the demand level of twoitems because it is in the interest of the organization tomaintain a similar aggregate demand for the whole family ofitems.
In addition to the above, the following assumptions arealso made:
1. The facility is set-up for a family of items, andtherefore, the facility setup cost is included in theformulation. As the individual item setup time is notrelevant in the present context, it is ignored.
2. All the items are manufactured in a common cycle time.3. Shortages may or may not be allowed.4. In case shortages are allowed, these may be backordered
completely/partially depending on the situation.5. An idle time exists usually in a common cycle time. If the
idle time costs are significant, these may be incorporatedin the modeling process depending on the case.
Based on these assumptions, a formulation is first madefor the basic production situation. Then the shortages areincorporated with complete backordering. This is extendedfor a fractional backordering case. The idle time cost is
Int J Adv Manuf Technol (2009) 45:382–388 383
further discussed briefly with its inclusion in the suggestedmethod.
2.1 Notation
∝ Shop floor index lying usually in the range (0≤∝<1).
Ai Setup cost for item i.bi A faction of shortage quantity which is not
backordered for product i.c Fixed production cost per year.c1 Idle time cost per year.Di Annual demand for item i.E Total relevant cost.E1 Total cost after exchange of the demand rate of two
items.Hi Inventory carrying cost for an item i per unit-year.j An item whose demand rate is desired to be
exchanged with another appropriate item.Ji Shortage quantities for a product i.k Selected another appropriate item whose demand rate
would be exchanged with that of item j.Ki Annual shortage cost per unit for a product i.n Number of items in the group.Pi Production rate per year for item i.T Common cycle time in year.
3 Methodology
From a family of n items, an item j is selected by themanagement whose demand rate is to be exchanged by thatof another appropriate item k among the remaining items.Figure 1 represents the process of exchange of demand rates.
The production time is TPni¼1
Di=Pið Þ in a cycle time T, and
in order to have a feasible schedule, the production timeshould be less than T, i.e.,
Pni¼1
Di=Pið Þ < 1. In the iterative
process of exchange (Fig. 2), Dj is exchanged by Dk suchthat the constraint on total production time is satisfied.
All the remaining items can be considered one at a time.However, the conditions are developed next in order tohave a small subset of items to make the search procedureconvenient.
4 Mathematical formulation
A generalized production cost is c Pi=Dið Þa per year, and asthe manufacturing time for an item i is (Di/Pi), the annualmanufacturing time cost for an item i is c Di=Pið Þ1�a. Withthe inclusion of this cost component, a total relevant costfor the basic model without shortages,
E ¼ cXni¼1
Di=Pið Þ1�a þ 1
T
Xni¼1
Ai þ T
2
Xni¼1
DiHi 1� Di=Pið Þ
ð1ÞThe optimal cycle time can be obtained by differentiatingEq. 1 with respect to T and equating to 0. The optimalvalues (T* and subsequently E*) can easily be obtained as,
T* ¼
ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi2Pni¼1
Ai
Pni¼1
DiHi 1� Di=Pið Þ
vuuuuut ð2Þ
and E* ¼ cXni¼1
Di=Pið Þ1�a
þffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi2
Xni¼1
Ai
" # Xni¼1
DiHi 1� Di=Pið Þ" #vuut
ð3Þ
Di, i≠j
D1
D2
.
.
.
Dk
.
.
.
Dn
Dj
Fig. 1 Exchanging the demandrate
No
∑(Di/Pi)< 1
Yes
Compute the existing cost, E
Select Dk from the set Di , i≠j
Exchange Dj with Dk
Compute the revised cost
Retain the minimum cost along with corresponding exchange and implement
Fig. 2 An iterative process of demand exchange
384 Int J Adv Manuf Technol (2009) 45:382–388
With reference to Eq. 3, the components concerning itemj and item k are separated from the remaining items. Afterexchanging Dj and Dk, the total optimal cost,
E�1 ¼ c
Xni 6¼ji 6¼k
Di=Pið Þ1�a þ Dk
�Pj
� �1�a þ Dj
�Pk
� �1�a
2664
3775
þ
ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi2
Xni¼1
Ai
" # Xni 6¼ji 6¼k
DiHi 1� Di=Pið Þf g þ DkHj 1� Dk
�Pj
� �þ DjHk 1� Dj
�Pk
� �2664
3775
vuuuuut
ð4Þ
Subtracting Eqs. (4) from (3), any potential cost improvement,
E� � E�1 ¼ c Dj
�Pj
� �1�a þ Dk=Pkð Þ1�a � Dk
�Pj
� �1�a � Dj
�Pk
� �1�ah i
þffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi2Xni¼1
Ai
sffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiPni¼1
DiHi 1� Di=Pið Þf gs
�ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiPni6¼ji 6¼k
DiHi 1� Di=Pið Þf g þ DkHj 1� Dk
�Pj
� �þ DjHk 1� Dj
�Pk
� �vuut
2666664
3777775
ð5Þ
Equation (5) has two components, the first component iscertain to be positive if,
Dj
�Pj
� �1�aþ Dk=Pkð Þ1�a> Dk
�Pj
� �1�aþ Dj
�Pk
� �1�a ð6Þ
The second component is certain to be positive if,
DjHj 1� Dj
�Pj
� �þ DkHk 1� Dk=Pkð Þ > DkHj 1� Dk
�Pj
� �þ DjHk 1� Dj
�Pk
� �or Dj � Dk
� �Hj � Hk
� �þ HkPk
� Hj
Pj
� �Dj þ Dk
� �h i> 0
ð7Þ
There is a guaranteed cost improvement if the conditions 6and 7 are satisfied. The entire feasible remaining itemdemand rate can be exchanged if it is difficult to draw anyconclusion with the use of conditions 6 and 7.
5 Illustrative example
Table 1 shows the input parameters concerning two items.As it is a simple numerical example for illustration purpose,Pni 6¼ji6¼k
DiHi 1� Di=Pið Þ ¼ 0 andPni 6¼ji 6¼k
Di=Pið Þ1�a¼ 0.
Using the relevant parameters for the basic case, i.e.,without shortages,
Pni¼1
Di=Pið Þ ¼ 0:955 < 1, and the feasibledata are ensured.
Table 1 Input parameters
Item
1 2
Annual demand Di 400 300
Annual production rate Pi 720 750
Setup cost, Ai ($) 100 150
Annual carrying cost Hi ($ per unit) 13 5
Annual shortage cost Ki ($ per unit) 120 80
Fraction bi 0.2 0.3
c=$9,000 per year; α=0.2
Int J Adv Manuf Technol (2009) 45:382–388 385
From Eq. 3, the total relevant cost, E*=$11,214.88.Now, let j=1 and k=2. After exchanging Dj with Dk,Pn
i¼1Di=Pið Þ ¼ 0:95, and the feasibility is ensured.From condition 6, 1.105>1.101.From condition 7, 2.78>0.As the both conditions are satisfied, there is a guaranteed
cost improvement with the implementation of the proposedmethod.
With the use of Eq. 4, a reduced total relevant cost afterdemand exchange, E1
*=$11,177.19.
6 Extension for shortages
Quite often, the shortages are included in a manufacturingsystem. These are assumed to be completely backordered atpresent. Figure 3 shows this kind of environment.
Since the shortages exist for a period Ji= Pi � Dið ÞþJi=Dið Þ, the annual shortage cost for an item i,
¼ Ji2
JiPi�Dið Þ þ Ji
Di
h iKiT
and the total annual shortage cost ¼ 12T
Pni¼1
KiJ 2iDi 1�Di=Pið Þ
ð8ÞNow, the maximum inventory level, Vi ¼ Pi � Dið ÞTDi=Pi � Ji
and the annual carrying cost ¼ Vi2 T � Ji
Pi�Dið Þ � JiDi
h iHiT Substitut-
ing Vi, the total annual carrying cost,
¼ T
2
Xni¼1
DiHi 1� Di=Pið Þ �Xni¼1
HiJi þ 1
2T
Xni¼1
HiJ 2iDi 1� Di=Pið Þ
ð9ÞAdding the Eqs. 8, 9, and the remaining cost components,
E ¼ cXni¼1
Di=Pið Þ1�a þ 1
T
Xni¼1
Ai þ 1
2T
Xni¼1
Hi þ Kið ÞJ 2iDi 1� Di=Pið Þ
þ T
2
Xni¼1
DiHi 1� Di=Pið Þ �Xni¼1
HiJi
ð10Þ
Substituting optimal Ji ¼ TDiHi 1� Di=Pið ÞHi þ Kið Þ ð11Þ
E ¼ cXni¼1
Di=Pið Þ1�a þ 1
T
Xni¼1
Ai þ T
2
Xni�1
DiHiKi 1� Di=Pið ÞHi þ Kið Þ
ð12ÞThe optimal values can be obtained as,
T* ¼
ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi2Pni¼1
Ai
Pni¼1
DiHiKi 1� Di=Pið Þ= Hi þ Kið Þ½ �
vuuuuut ð13Þ
and E* ¼ cPni¼1
Di=Pið Þ1�a
þffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi2
Pni¼1
Ai
� � Pni¼1
DiHiKi 1� Di=Pið Þ= Hi þ Kið Þ� �s
ð14Þ
With the swapping of Dj and Dk,
E*1 ¼ cXni6¼ji 6¼k
Di=Pið Þ1�a þ Dk
�Pj
� �1�a þ Dj
�Pk
� �1�a
2664
3775
þ
ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi2
Xni¼1
Ai
" # Xni 6¼ji 6¼k
DiHiKi 1� Di=Pið Þ= Hi þ Kið Þf g þ DkHjKj 1� Dk
�Pj
� ��Hj þ Kj
� �þ DjHkKk 1� Dj
�Pk
� ��Hk þ Kkð Þ
2664
3775
vuuuuutð15Þ
Vi
Productioninventory
Pi – Di Di
0 Time
Ji
T
Fig. 3 The production cycle with shortages
386 Int J Adv Manuf Technol (2009) 45:382–388
Following the procedure discussed in the “Mathematicalformulation” section, the relevant conditions can be
obtained. The first condition is similar to 6. The secondcondition is obtained as,
Dj � Dk
� � HjKj
Hj þ Kj
� � � HkKk
Hk þ Kkð Þ þ Dj þ Dk
� � HkKk
Pk Hk þ Kkð Þ �HjKj
Pj Hj þ Kj
� �( )" #
> 0 ð16Þ
With the input parameters of Table 1, the condition 6 isalready satisfied.
From condition 16, 1.209>0.As the both conditions (6) and (16) are satisfied, there is
certain cost improvement using the proposed approach.From Eq. 14, E*=$ 11,158.62.The reduced relevant cost from Eq. 15, E�
1 ¼ $11; 121:22.The corresponding costs are also lower than that
obtained in the previous section. This can be justified byobserving Eqs. 3 and 14. As Ki= Hi þ Kið Þ is less than 1, therelevant costs are lower with relaxation of the constraintthat the backorders would not be allowed.
7 Partial backlogging
In a real-world situation, a portion of the shortage quantitiesmay not be backordered. A particular customer may switchover to another competitive firm in the industry. However,with the advertising among other efforts, a new customercan replace the old one, at a later date. In case where theshortage costs are estimated to be a good representation of
advertising costs apportioned for unit product and loss ofprofit among other factors, an explicit computation forcontribution of the lost units of product is not necessary. Asuitable parameter for relevant cost is assumed for all theshortage quantities whether these are backlogged or not. Anannual demand needs to be adjusted in order to incorporatethe partial backordering.
From Eq. 8, the annual shortage quantity can be obtainedas,
¼Xni¼1
J 2i2TDi 1� Di=Pið Þ
A fraction bi of the shortage quantity is not backordered,and therefore, the annual manufacturing cost,
¼ cXni¼1
1
P1�ai
Di � biJ 2i2TDi 1� Di=Pið Þ
� �1�a
Equation 10 can now be adjusted as follows for thissituation,
E ¼ cXni¼1
1
P1�ai
Di � biJ 2i2TDi 1� Di=Pið Þ
� �1�a
þ 1
T
Xni¼1
Ai þ 1
2T
Xni¼1
Hi þ Kið ÞJ 2iDi 1� Di=Pið Þ þ
T
2
Xni¼1
DiHi 1� Di=Pið Þ �Xni¼1
HiJi ð17Þ
Mathematical/analytical procedure as discussed before,cannot be followed for the optimization of Eq. 17. However,conventional search process such as univariate method canbe implemented conveniently for any real data set.
7.1 Specific case
α=0 in a specific case, and the Eq. 17 can be written as,
E ¼ cXni¼1
Di=Pið Þ þ 1
T
Xni¼1
Ai þ 1
2T
Xni¼1
Hi þ Ki � cbi=Pið ÞJ 2iDi 1� Di=Pið Þ þ T
2
Xni¼1
DiHi 1� Di=Pið Þ �Xni¼1
HiJi ð18Þ
The optimal relevant cost can be obtained as,
E* ¼ cXni¼1
Di=Pið Þ þffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi2
Xni¼1
Ai
" # Xni¼1
DiHi 1� Di=Pið Þ Ki � cbi=Pið Þ= Hi þ Ki � cbi=Pið Þ" #vuut ð19Þ
Int J Adv Manuf Technol (2009) 45:382–388 387
As c/Pi is the unit production cost, and shortage costs aremuch greater than this in the real world, an optimality/feasibility condition, i.e., Ki>c/Pi, is satisfied easily.
In order to exchange the demand of products, Eq. 19 canbe used as a reference equation.
Consider the input data of Table 1.From Eq. 19, E*=$9,809.46After an exchange of the demands, the reduced relevant
cost is obtained as,
E�1 ¼ $ 9; 759:21
8 Incorporating an idle time cost
In the cyclic manufacture, a production activity usually takesplace for certain portion of the cycle time, and the remaining
portion is idle. With reference to Eq. 3,Pni¼1
Di=Pið Þ is the
annual manufacturing time. After an exchange of demand,this parameter will vary. For instance, an annual manufac-turing time has been reduced after the exchange of demandin the illustrative example of the “Illustrative example”section. This means that the idle time during the cycle hasincreased. In few cases, the problems are associated with anidle production facility such as the maintenance problems.Consistency in the quality of a product and skills of thehuman resources may also get affected up to some extent.With the occurrence of this type of problems, it seemsreasonable to introduce the idle time cost.
Consider an idle time cost per year ¼ c1 c1 < cð Þ
Idle time cost in a year ¼ c1 1�Xni¼1
Di=Pið Þ" #
Equation 3 can now be transformed as follows:
E* ¼ cXni¼1
Di=Pið Þ1�a þ c1 1�Xni¼1
Di=Pið Þ" #
þffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi2
Xni¼1
Ai
" # Xni¼1
DiHi 1� Di=Pið Þ" #vuut ð20Þ
The above equation can be used as a reference equation forthe exchange of demand.
Similarly an idle time cost can be added in Eq. 14 withthe inclusion of shortages in a manufacturing system.
9 Concluding remarks
Almost all competitive firms in an industrial/business sectorare expected to perform in an optimal manner within the
framework of organization along with several inputparameters. However, these are continuously striving forthe cost improvement. Internal benchmarking practices arealso adopted where the standards are bound to vary withtime. A method is proposed and analyzed in which thedemand of a strategically selected item is exchanged withanother suitable item in the group. Analysis is first made forthe basic case without shortages and conditions aredeveloped for convenience in the search of another suitableitem. The process is illustrated with the help of a numericalexample. Further extensions are concerning the inclusion ofshortages that may be backlogged completely or partially.The costs are obtained at a lower level with the allowablebackorders. However, an annual shortage cost needs to beestimated with care considering the all relevant factors.
In a production cycle time, a certain period is usually idle.This idle time frequently repeats itself in case where theassociated manufacturing schedule is implemented. Idle timecost is introduced for the proposedmethod.With the inclusionof this cost, the reference equations are obtained which can beuseful for an exchange of demand. In the presence of arelevant situation, these are suitable for a trade-off concerningthe production time and idle time among other factors.
The possibilities for demand exchange can be conve-niently explored, and depending on the business strategy, theproposed approach may be implemented in a short-run/long-run. In case of the various problems being faced by the firm,an alternate schedule is available on the basis of certainmethodology. This will help in incorporating flexibility inthe industrial system and also in the decision-making processin a variety of situations.
References
1. Chowdhury MR, Sarker BR (2001) Manufacturing batch size andordering policy for products with shelf lives. Int J Prod Res 39(7):1405–1426. doi:10.1080/00207540110052148
2. Giri BC, Jalan AK, Chaudhari KS (2005) An economic productionlot size model with increasing demand, shortages and partialbacklogging. Int Trans Oper Res 12:235–245
3. Hall RW (1988) Cyclic scheduling for improvement. Int J Prod Res26(3):457–472. doi:10.1080/00207548808947876
4. Hill RM (1995) Inventory models for increasing demand followedby level demand. J Opl Res Soc 46(10):1250–1259
5. Sharma S (2004) Optimal production policy with shelf lifeincluding shortages. J Opl Res Soc 55(8):902–909
6. Sharma S (2006) Incorporating fractional backordering in the multi-product manufacturing situation with shelf lives. Proc IMechE, PartB: Journal of Engineering Manufacture 220:1151–1156
7. Sharma S, Sadiwala CM (1997) Effects of lost sales on compositelot sizing. Computers Ind Engng 32(3):671–677
8. Silver EA (1990) Deliberately slowing down output in a familyproduction context. Int J Prod Res 28(1):17–27
9. Viswanathan S, Goyal SK (2000) Incorporating planned backordersin a family production context with shelf life considerations. Int JProd Res 38(4):829–836
388 Int J Adv Manuf Technol (2009) 45:382–388