Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
KSCE Journal of Civil Engineering (0000) 00(0):000-000
DOI 10.1007/s12205-012-1588-3
− 1 −
www.springer.com/12205
Water Engineering
A Hyper-concentrated Sediment Yield Prediction Model Using
Sediment Delivery Ratio for Large Watersheds
Jang Hyuk Pak and Joo Heon Lee
Received May 23, 2011/Accepted September 23, 2011
···································································································································································································································
Abstract
This paper presents a sediment prediction model using sediment delivery ratio approach for prediction of sediment yields fromlarge watersheds (larger than 800 ha). The Sediment Delivery Ratio (SDR) approach is effective for predicting the sediment yield asit moves through the stream system to a concentration point (debris basin) in the watershed. A statistical model, the Multi-SequenceDebris Prediction Model (MSDPM), was developed for use in relatively small watersheds (50-800 ha) in the Los Angeles area. Inthis study, the MSDPM was extended to include a sediment delivery ratio for modeling of sediment transport through the streamnetwork in the large watershed. The sediment delivery ratio approach was implemented to express the percent of sediment yield thatis delivered through a stream system from the sub-watersheds to the debris basin. After adding the sediment delivery ratio to estimatethe sediment yields from large watersheds, the revised MSDPM (MSDPM-R) was calibrated and validated based on precipitation,sediment yield and fire data collected from the William Fire (September 2002) and Grand Prix Fire (October and November 2003)events in southern California. Results from MSDPM-R were compared with the available field data obtained from several debrisbasins within Los Angeles and San Bernardino Counties. The MSDPM-R yields remarkably consistent results when compared withthe measured field data.
Keywords: sediment, fire, sediment delivery ratio, debris, watersheds
···································································································································································································································
1. Introduction
Alluvial fans are rapidly being urbanized in southern California
because of their relatively mild terrain and aesthetic views. The
mountain areas upslope from the alluvial fans are susceptible to
fires which can significantly increase the amount of sediment
material transported downstream during subsequent major
storms. In this situation, the sediment material collected in debris
basins is generated through a spectrum of processes, including
surface runoff, flooding and debris flow. Development of these
fan areas must consider the possibility of increasing sediment
yield from mountain watersheds due to the frequent occurrence
of fire events (Pak et al., 2008).
Westerling et al. found that wildfire frequency is strongly asso-
ciated with regional spring and summer temperatures and earlier
spring snowmelts in forests based on 34 years of western U.S.
wildfire history together with hydroclimatic data, (Westerling et
al., 2006). Fires produce 2.1±0.8 petagrams of carbon emissions,
or 66±24% of the CO2 growth rate anomaly during the 1997 to
1998 El Niño (van der Werf et al., 2004). The main contributors
were Southeast Asia (60%), Central and South America (30%),
and boreal regions of Eurasia and North America (10%) (van der
Werf et al., 2004). If global warming and early spring is
increasing large wildfires, carbon emissions from wildfire will
increase greenhouse gas emissions and this effect will further
accelerate global warming (Westerling et al., 2006). Fires gener-
ally cause water repellency in soil to be temporarily hydrophobic,
which effect infiltration, runoff and erosion in burned watersheds
(DeBano, 2000). Several previous studies have shown that
wildfire has a significant influence on the erosion of mountain
watersheds in southern California (Cannon et al., 2003; Middleton
et al., 2004). Rowe et al. (1954) estimated that a 100% burned
watershed produces 35 times more sediment yield than in the
unburned state. As mentioned above, there are strong relationships
among the global warming, early snow melting, wildfire, flood,
sediment yield, and green house gas emissions.
An understanding of key surface erosion and watershed
geomorphic processes is essential to the application of sediment
yield prediction techniques. In particular, the variability of these
processes in space and time is important in establishing limitation
on the accuracy of estimates derived from sediment discharge
data and/or predictive models (USACE, 1995). Although typical
sediment yield processes are generally familiar, the interplay of
factors that influence sediment yield from a watershed is less
*Research Hydraulic Engineer, U.S. Army Corps of Engineers, Institute For Water Resources, Hydrologic Engineering Center, Davis, CA 95616-4687 (E-
mail: [email protected])
**Member, Professor, Joongbu University, Department of Civil Engineering, Kumsan 312-702, Korea (Corresponding Author, E-mail:[email protected])
Jang Hyuk Pak and Joo Heon Lee
− 2 − KSCE Journal of Civil Engineering
obvious and much more difficult to estimate quantitatively.
Vegetation plays an essential role in the sediment yield, but
knowledge of biological functions is poorly integrated into
procedures for prediction of sediment yields especially under
burn conditions. On the geological time scale, the surface of the
earth is transformed by sediment production in the upper part of
a watershed, transportation of sediments in a fluvial system, and
deposition in low-lying lakes, alluvial fans, deltas, and in the
oceans (USACE, 1995). The sediment production and transport
system is extremely complex, involving the interaction of many
hydrologic, geomorphic, and geological processes. Having a
better understanding of their influence on sediment yield should
make a more credible study by overcoming the corresponding
limitations on sediment yield prediction models.
Debris basins have been constructed in many areas to capture
debris flows. The amount of solid materials (including boulders,
gravel, sand, silt, clay, trees, etc.) accumulated in debris basins is
called sediment, hyper-concentrated sediment, or debris yields.
The yield often excludes fine sand, silts, and clays which pass
through the debris basin in suspension during the storm event.
Sediment yield prediction is necessary for debris basin design
and can also help determine maintenance needs for debris basin
management.
During the 2003 debris disaster, a proper debris yield method
was not in existence to estimate debris yields from large water-
sheds (USACE, 2005). The objective of the present study is to
develop an accurate model to predict the sequential sediment
yields for large watersheds caused by wildfire and subsequent
storm events. The MSDPM is a statistical model, named the Multi-
Sequence Debris Prediction Model (MSDPM). The MSDPM is
based on a multiple regression analysis of measured sediment
yield data collected from small watersheds between 1938 and
1983. This equation included variables of precipitation, drainage
area, relief ratio, and a non-dimensional fire factor as well as
threshold precipitation factors for rainfall-intensity and total
rainfall. The MSDPM was calibrated and validated only for the
small watersheds (smaller than 800 ha) (Pak, 2005; Pak et al.,
2008, 2009).
For this study, the MSDPM was modified to develop a
sediment prediction model for large watersheds (larger than 800
ha) by adding the sediment delivery ratio. The most of current
other methods including MSDPM were originally developed for
use in relatively small watersheds (50-800 ha), and, therefore
there is no an adequate method for large watersheds. In many
cases, a large number of non-point source sediment and water
quality models, like the universal soil loss equation (USLE)
(Wischmeier and Smith, 1978) or the revised version of USLE
(RUSLE) (Renard et al., 1997), use the sediment delivery ratio to
model erosion on hillslopes. The sediment delivery ratio is an
approach used to predict the spatial variations of a sediment yield
as it moves through a stream network from the sub-watersheds to
the outlet of a watershed. The MSDPM is now referred to as the
MSDPM-R after adding the sediment delivery ratio option. After
including the sediment delivery ratio, the MSDPM-R was cali-
brated and validated using measured sediment yields, wildfire
data, and rainfall data collected from the 2002 and 2003 fire
events in southern California.
2. Model Development
The watersheds used in the analysis are located in the San
Gabriel Mountains and San Bernardino Mountains within Los
Angeles and San Bernardino Counties, as shown in Fig. 1. Debris
cleanout data from 2002 to 2003 were obtained for debris basins
owned by the Los Angeles County and San Bernardino County.
Debris cleanout data were obtained based on the truck count or
survey after excavating all material (clay, silt, sand, gravel,
boulders, and organic materials) deposited in the debris basin.
2.1 MSDPM
Pak et al. briefly described the background of MSDPM as
shown below (Pak et al., 2009) The MSDPM was developed for
sediment prediction of relatively small watersheds (25-800 ha).
Development of a multiple regression equation was the first step
to provide the fundamental statistical equation of MSDPM. The
relief ratio (S), drainage area (A), maximum 1-hr rainfall
intensity (Im) of each storm event, and fire factor (F) were finally
selected as independent variables among other meteorologic and
physiographic parameters through the stepwise multiple linear
regression analysis. In the selected stepwise regression routine,
independent variables are progressively added by the program in
order of decreasing significance. Variables determined to be sig-
nificant in earlier stages of the computations may be deleted upon
introduction of more significant variables at a later stage. This
process allows for determination of the effect of an independent
variable on the dependent variable as well as the change in the
relative value of this variable upon the inclusion of additional
variables (Gatwood et al., 2000).
The MSDPM allows the users to determine the sediment yield
based on several parameters. These include rainfall amount, max-
imum 1-hr rainfall intensity, Threshold for Maximum 1-hr Rainfall
Fig. 1. Locations of Debris Basin Watersheds for Study
A Hyper-concentrated Sediment Yield Prediction Model Using Sediment Delivery Ratio for Large Watersheds
Vol. 00, No. 0 / 000 0000 − 3 −
Intensity (TMRI), Total Minimum Rainfall Amount (TMRA),
relief ratio (S), drainage area (A), antecedent precipitation events,
and fire condition. The fire condition is defined on the percen-
tage of the basin area burned, the time since the last fire and the
number of antecedent effective precipitation events. These effective
events include the number of previous events that generated
sediment yield and have precipitation values exceeding the
Threshold Maximum 1-hr Rainfall Intensity (TMRI) and Total
Minimum Rainfall Amount (TMRA). The MSDPM does not
consider the spatial variation of effective rainfall within the
watershed. Thus, the MSDPM is applicable primarily for small
watersheds and the accuracy will decrease as the watershed area
increases.
Regression analysis on the variables above resulted in the
MSDPM equation, Eq. (1).
(1)
where and
Dy: Sediment Yield per Event, (m3)
Im: Maximum 1-hr Rainfall Intensity per Event, (mm/
hr)
Ic: Threshold Maximum 1-hr Rainfall Intensity (TMRI),
(mm/hr)
P: Total Rainfall Amount per Event, (mm)
Pc: Total Minimum Rainfall Amount (TMRA), (mm)
| |: Absolute value
S: Relief Ratio, (m/km) (h2− h1)/L
h2: Highest Elevation in the watershed, (m)
h1: Lowest Elevation in the watershed, (m)
L: Maximum stream length (km), measured through
Geographic Information System (GIS) processing
based on the digital elevation model (DEM)
A: Size of Drainage Area, (ha)
F: Fire Factor, 3.0 ≤ F ≤ 6.5 (dimensionless):
(2)
where Bp: % of Burn/100, (0 ≤ Bp ≤ 1)
By: Number of Years since Burn, (1 ≤ By ≤ 10 yr)
Ap: Number of Antecedent Effective Precipitation Events
that have enough energy to generate sediment yield
The rainfall events were screened to select the effective rainfall
that can provide the required energy through Eq. (1). The
threshold maximum 1-hr rainfall intensity for entrainment of
sediment particles was determined as the TMRI (Ic) based on the
relationship between the TMRI and relief ratio shown in Fig.
2(a). The threshold minimum rainfall amount for the transport
capacity to move sediment to the concentration point was
determined as TMRA (Pc) based on the relationship between the
TMRA and TMRI shown in Fig 2(b) for each debris basin through
calibration processes, which defined the critical conditions used
in MSDPM (Detail discussion of Ic and Pc were given in Pak and
Lee (2008)).
The Fire Factor equation, Eq. (2), was developed based on the
fire factor curve for watersheds in the range of 26 to 777 ha (0.1
to 3.0 mi2) of Los Angeles District Debris Method (Gatwood et
al., 2000) by adding effects of antecedent precipitation events.
Tatum (1963) developed the fire factor curve of Los Angeles
District Debris Method using a relationship established by Rowe
et al. (1954), to correlate measured sediment yields and com-
puted sediment yields by means of a single fire curve.
The Fire Factor (F) was generated using the percentage of the
watershed burned, the number of years since the fire, and the
number of antecedent precipitation events above a certain threshold
value that occurred after the fire (Pak and Lee, 2008). The impacts
of fire are gradually reduced by re-vegetation, subsequent storms,
and watershed management. Robichaud (2000) stated that hy-
drophobicity in soils is broken up or is washed away within one
to two years after fire. The key to understanding soil recovery
after fire is how quickly the bare soil can be covered again by
vegetation or litter (Pierson et al., 2001).
The final Fire Factor equation, Eq. (2), was calibrated in a
manner that minimizes the differences between the measured
sediment yields and estimated sediment yields within the main
sediment yield equation, Eq. (1).
2.2 Sediment Delivery Ratio for Large Watersheds
The determination of the sediment delivery ratio is of primary
importance to provide realistic estimates of total sediment yield
at the concentration point based on estimated sub-watershed
Dy( )ii 1=
N
∑ 0.25 1Im( )i Ic–
Im( )i Ic–( )-----------------------+⎝ ⎠
⎛ ⎞i 1=
N
∑ 1P( )i Pc–
P( )i Pc–( )------------------------+⎝ ⎠
⎛ ⎞=
Im( )i0.541S0.134A1.023e0.290F
P Pc≠ Im Ic≠
F 6.5 Bp By0.29– 1 Bp–( ) 20 By–( )
0.29–
×+×( )× 2 eAp200⁄( )
–( )×=
Fig. 2. Regression Equations of TMRI and TMRA for Sediment
Prediction Using MSDPM (a) Relationship between TMRI
and Relief Ratio (b) Relationship between TMRA and TMRI
Jang Hyuk Pak and Joo Heon Lee
− 4 − KSCE Journal of Civil Engineering
sediment yields. The sediment delivery ratio is a simple process
used to predict the spatial variations of a debris flow as it moves
through the stream network. The short-term storage of sediment
throughout a stream system plays an important role in the
sediment transport. For rain occurring during the storm season,
sediment yields from sub-watersheds can be estimated at the
sub-watershed outlets by MSDPM. Then sediment yields are
delivered through the stream system based on the delivery ratio
to account for the storage effects on the stream system. The
sediment delivery ratio is developed based on the simple linear
reservoir routing model concept traditionally used in the lag-and-
route method. The sediment delivery ratio, Eq. (4), represents the
effect of the short-term storage concept (Ponce, 1989). The
sediment outflow from the stream is obtained by Eq. (3).
(3)
where Osed: Sediment Outflow from the Stream (m3)
Ised: Sediment Inflow to the Stream (m3)
SDR: Sediment Delivery Ratio
(4)
K: SDR Constant
3. Calibration and Validation
In practice, historically sediment yield data from large water-
sheds are very limited and may not be sufficient for calibration
and validation purposes. In this study, however, the SDR Con-
stant (K) for the large watershed analysis was calibrated and
validated based on currently available data generated from two
fire events that occurred between 2002 and 2003.
On September 22, 2002, the William Fire in the Azusa to
Claremont area burned over 15,054 ha including the watershed
of Little Dalton Wash. Due to high temperatures, Santa Ana winds,
steep topography, and intense fire, control of the fire’s perimeter
was severely hampered. The fire destroyed over 60 residences
burning at high to moderate intensity (LACDPW, 2003). The Big
Dalton Dam precipitation gage (223C) was chosen for the data
analysis because the location is closest in proximity to the Little
Dalton Watershed and its data appeared to be the most consistent
with measured sediment yield data (debris basin cleanout record)
for the Little Dalton Debris Basin. The watershed of Little Dalton
Debris Basin was burned 89% by the William Fire as shown on
Fig. 3.
On October and November, 2003, the Padua Fire, Grand Prix
Fire, and Old Fire in the San Gabriel Mountains and San
Bernardino Mountains burned nearly 36,826 ha including the
watersheds of Cucamonga Creek Debris Basin, Deer Creek
Debris Basin, and Day Creek Debris Basin. Precipitation data
were collected from three precipitation gages [Demens Creek
Debris Basin (DCDB), Mt. Baldy (MTBY), and San Antonia
Dam (SNTO)], located in the vicinity of the Grand Prix Fire area.
After analyzing data from three precipitation gages, the Mt.
Baldy (MTBY) precipitation gage was selected for the data
analysis because its data were the most reliable and its elevation
is closer to the average elevation of watersheds. The watersheds
of three debris basins (Cucamonga Creek Debris Basin, Deer
Creek Debris Basin, and Day Creek Debris Basin) burned from
89% to 100% by the Grand Prix Fire as shown in Fig. 3.
Three Debris Basins (Little Dalton Debris Basin, Cucamonga
Creek Debris Basin, and Deer Creek Debris Basin) were selected
to determine the SDR Constant (K) via the model calibration that
minimized the residuals between the measured and estimated
sediment yields. The characteristics of the three debris basins
used for calibration are shown in Table 1.
For using MSDPM with the sediment delivery ratio, the water-
shed of debris basin was divided into several sub-watersheds
based on tributary junctions, slope, and drainage area (less than
800 ha). The MSDPM was applied to calculate the sediment
yields generated by each effective storm event from all sub-
watersheds using watershed characteristics. The sediment delivery
ratio was used to calculate the total sediment yield generated
through the stream network from all sub-watersheds to the
concentration point (debris basin) for each effective storm event.
Through the calibration process, the SDR constant (K) was
determined for each debris basin. The Threshold Maximum 1-hr
Rainfall Intensity and the Total Minimum Rainfall Amount for
all sub-watersheds were determined for MSDPM, Eq. (1),
through the equation y=175.05X-0.5491 of Fig 2(a) and the equation
y = 5.9752X0.6465 of Fig. 2(b), respectively.
3.1 Little Dalton Debris Basin
The watershed of Little Dalton Debris Basin was divided based
Osed SDR Ised×=
SDR1 K⁄
2 1 K⁄( )+----------------------=
Fig. 3. Fire Maps of William Fire and Grand Prix Fire
Table 1. Characteristics of Debris Basins used for Calibration
Debris BasinDrainage Area
(ha)Burn(%)
Relief Ratio(m/km)
Little Dalton 853 89 98
Cucamonga Creek 2,998 89 157
Deer Creek 966 100 244
A Hyper-concentrated Sediment Yield Prediction Model Using Sediment Delivery Ratio for Large Watersheds
Vol. 00, No. 0 / 000 0000 − 5 −
on tributary junctions, slope, and drainage area as shown on Fig.
4. MSDPM was applied to calculate the sediment yields gener-
ated by each effective storm event from all sub-watersheds based
on watershed characteristics of each sub-watershed indicated in
Table 2. Sediment yields estimated for storm events which
occurred between September 28, 2002 and December 29, 2002
from 9 sub-watersheds are summarized in Table 3.
The sediment delivery ratio was used to calculate the total
sediment yield generated at the concentration point through the
stream network as depicted in Fig. 4. The measured sediment yield
generated was 48,932 m3 (LACDPW, 2003) while the estimated
sediment yield calculated by the MSDPM-R with precipitation
data obtained from the Big Dalton Dam precipitation gage was
48,984 m3. The difference of the two values was 52 m3, (0.1%).
The final SDR Constant (K) was determined as 0.105 for the
Little Dalton Debris Basin via the calibration process.
3.2 Cucamonga Creek Debris Basin
The watershed of Cucamonga Creek Debris Basin was divided
based on tributary junctions, slope, and drainage area as shown
on Fig. 5. MSDPM was applied to calculate the sediment yields
generated by each effective storm event from sub-watersheds
based on watershed characteristics as contained in Table 4.
Sediment yields estimated for the storm events which occurred
between November 1, 2003 and January 2, 2004 are summarized
in Table 5. The sediment delivery ratio was used to calculate the
total sediment yield generated at the concentration point through
the stream network as depicted in Fig. 5. The measured sediment
yield was 175,848 m3 (USACE, 2005) while the estimated sedi-
ment yield by the MSDPM-R was 176,091 m3 with the precipitation
data obtained from the Mt. Baldy (MTBY) precipitation gage.
The difference of the two values was 243 m3, (0.1%). The final
SDR Constant (K) was determined as 0.062 for the Cucamonga
Creek Debris Basin via the calibration process.
Fig. 4. Sub-Watershed Delineation for Little Dalton Watershed
Table 2. Sub-Watershed Characteristics of Little Dalton Debris Basin
Sub-Watershed Ic (mm/hr) Pc (mm) S (m/km) A (ha)
WS1 11.216 28.515 149.015 229.712
WS2 7.722 22.400 294.112 56.295
WS3 8.244 23.369 261.053 82.773
WS4 8.251 23.382 260.624 82.216
WS5 6.876 20.782 363.290 24.967
WS6 6.039 19.110 460.101 16.221
WS7 6.863 20.756 364.562 14.074
WS8 8.135 23.168 267.459 62.418
WS9 11.802 29.469 135.817 284.497
Table 3. Sediment Yield Calculation for Little Dalton Debris Basin
Date Dy (m3)
Accumulated Dy (m
3)I (mm/hr) P (mm)
9/28/2002 0 0 1.9812 2.9718
9/29/2002 0 0 0.9906 0.9906
11/8/2002 8,088 8,088 8.9408 83.2612
11/9/2002 1,198 9,286 6.9596 65.5066
11/29/2002 0 9,286 4.953 4.953
11/30/2002 12,009 21,294 18.923 24.892
12/16/2002 27,690 48,984 11.9634 45.212
12/17/2002 0 48,984 0.9906 0.9906
12/20/2002 0 48,984 5.969 26.797
12/29/2002 0 48,984 1.9812 4.953
Total 48,984 m3
Fig. 5. Sub-Watershed Delineation for Cucamonga Creek Water-
shed
Jang Hyuk Pak and Joo Heon Lee
− 6 − KSCE Journal of Civil Engineering
3.3 Deer Creek Debris Basin
The watershed of Deer Creek Debris Basin was subdivided
based on tributary junctions, slope, and drainage area as shown
on Fig. 6. MSDPM was applied to estimate the sediment yields
based on each effective storm event which occurred between
November 1, 2003 and January 2, 2004 from sub-watersheds
based on watershed characteristics as contained in Table 6.
Sediment yields estimated for storm events summarized in
Table 7. The sediment delivery ratio was used to calculate the
total sediment yield generated at the concentration point through
the stream network as depicted in Fig. 6.
The measured sediment was 120,112 m3 (USACE, 2005) while
the estimated sediment yield by the MSDPM-R was 120,319 m3
with the precipitation data obtained from the Mt. Baldy (MTBY)
precipitation gage. The difference of the two values was 207 m3,
(0.2%). The final SDR Constance (K) was determined as 0.012
for the Deer Creek Debris Basin via the calibration process.
The SDR Constant (K) for the watersheds of Little Dalton,
Cucamonga Creek, and Deer Creek debris basins were plotted
with the Relief Ratio (S) of each watershed in Fig. 7. The
calibration process is described: (1) Assume an initial K value
and then calculate sediment yield at the concentration point. (2)
Compare the estimated total sediment yield from all sub-
watersheds to debris basin (concentration point) with measured
Table 4. Sub-Watershed Characteristics of Cucamonga Creek Debris
Basin
Sub-Watershed Ic (mm/hr) Pc (mm) S (m/km) A (ha)
WS1 5.331 17.630 577.378 76.005
WS2 6.125 19.285 448.427 93.897
WS3 6.120 19.275 449.078 121.988
WS4 5.872 18.765 484.301 88.754
WS5 5.850 18.721 487.531 72.392
WS6 6.079 19.191 454.679 74.223
WS7 7.108 21.233 341.972 53.528
WS8 5.795 18.608 495.966 148.847
WS9 5.015 16.946 645.445 43.972
WS10 6.310 19.659 424.792 98.991
WS11 6.085 19.203 453.840 171.48
WS12 7.529 22.037 307.976 82.549
WS13 6.649 20.337 386.132 122.538
WS14 5.687 18.382 513.332 92.246
WS15 6.091 19.216 453.003 84.561
WS16 7.676 22.315 297.292 131.535
WS17 8.914 24.580 226.405 119.756
WS18 9.502 25.616 201.547 191.888
WS19 9.502 25.616 398.664 230.426
WS20 8.032 22.978 273.746 117.605
WS21 5.835 18.689 489.912 122.068
WS22 9.625 25.830 196.880 244.536
WS23 9.954 26.397 185.213 185.613
WS24 9.077 24.870 219.059 98.221
WS25 17.444 37.939 66.667 130.023
Table 5. Sediment Yield Calculation for Cucamonga Creek Debris
Basin
Date Dy (m3)
Accumulated Dy (m
3)I (mm/hr) P (mm)
11/1/2003 0 0 4.826 26.162
11/12/2003 40,344 40,344 7.874 22.352
12/25/2003 135,747 176,091 24.13 151.13
1/2/2004 0 176,091 1.778 11.43
Total 176,091 m3
Fig. 6. Sub-Watershed Delineation for Deer Creek Watershed
Table 6. Sub-Watershed Characteristics of Deer Creek Debris
Basin
Sub-Watershed Ic (mm/hr) Pc (mm) S (m/km) A (ha)
WS1 5.541 18.076 538.149 115.223
WS2 6.859 20.748 364.962 179.919
WS3 6.480 20.000 404.705 95.939
WS4 7.358 21.713 321.075 82.159
WS5 8.021 22.959 417.036 89.504
WS6 6.374 19.789 399.527 72.992
WS7 6.526 20.092 293.935 60.473
WS8 7.724 22.405 372.971 72.312
WS9 6.777 20.589 359.145 90.205
WS10 6.919 20.867 298.766 29.721
WS11 7.655 22.276 298.766 77.836
Table 7. Sediment Yield Calculation for Deer Creek Debris Basin
Date Dy (m3)
Accumulated Dy (m
3)I (mm/hr) P (mm)
11/1/2003 0 0 4.826 26.162
11/12/2003 37,918 37,918 7.874 22.352
12/25/2003 82,401 120,319 24.13 151.13
1/2/2004 0 120,319 1.778 11.43
Total 120,319 m3 °° °°
A Hyper-concentrated Sediment Yield Prediction Model Using Sediment Delivery Ratio for Large Watersheds
Vol. 00, No. 0 / 000 0000 − 7 −
sediment yield. (3) Make adjustments to K to obtain the best
overall fit between estimated and measured sediment yields.
The sediment delivery ratio is affected by physical character-
istics of a watershed. It varies with the drainage area, relief ratio,
land use, and soil properties. This study has found that the SDR
Constant (K) has a stronger relationship with the Relief Ratio (S)
than other physical characteristics of a watershed. The logarithmic
regression equation, K = -0.1019Ln(S) + 0.5741, was generated
based on the relationship between the SDR Constant (K) and Relief
Ratio (S) from the three watersheds with the high R-squared
value (R2 = 0.9962). In an ungaged situation, a value for SDR
Constant (K) can be estimated based on this relationship because
determination of the SDR Constant (K) value in ungaged areas
can be very difficult. The MSDPM-R was developed based on
the MSDPM because the SDR was incorporated into MSDPM
with the logarithmic regression equation, K = -0.1019Ln(S) +
0.5741, to predict sediment yields from large watersheds.
The SDR Constant (K) was determined based on this regres-
sion equation for the Day Creek watershed. The MSDPM-R was
directly applied to predict the sediment yields from the Day Creek
Debris Basin watershed caused by subsequent storm events after
Grand Prix fire and the results were then compared with the field
data. The characteristics of watersheds used for validation are
shown in Table 8.
3.4 Day Creek Debris Basin
The watershed of Day Creek Debris Basin was divided based
on tributary junctions, slope, and drainage area as shown on Fig
8. The SDR Constant value (K), 0.029, was determined based on
the regression equation, K = -0.1019Ln(S) + 0.5741, using a Relief
Ratio of 211 m/km for the Day Creek watershed. MSDPM-R
was applied to calculate the sediment yields generated by each
effective storm event from all sub-watersheds using watershed
characteristics as contained in Table 9.
Sediment yields generated by storm events which occurred
between November 1, 2003 and January 2, 2004 summarized in
Table 10. The sediment delivery ratio was used to calculate the
total routed sediment yield generated at the concentration point
through the stream network as depicted in Fig. 8.
Fig. 7. Relationship of SDR Constant (K) and Relief Ratio (S)
Table 8. Characteristics of Debris Basin used for Validation
Debris BasinDrainage Area
(ha)Burn (%)
Relief Ratio(m/km)
Day Creek 1262 98 211
Fig. 8. Sub-Watershed Delineation for Day Creek Watershed
Table 9. Sub-Watershed Characteristics of Day Creek Debris
Basin
Sub-Watershed Ic (mm/hr) Pc (mm) S (m/km) A (ha)
WS1 5.513 18.017 543.164 58.742
WS2 4.877 16.642 679.207 40.629
WS3 6.221 19.480 435.934 128.452
WS4 5.553 18.101 536.042 37.387
WS5 5.909 18.842 478.750 73.203
WS6 7.136 21.286 339.551 68.059
WS7 6.112 19.258 450.183 77.496
WS8 7.515 22.012 308.975 98.661
WS9 6.131 19.298 447.611 33.614
WS10 6.338 19.717 421.339 171.813
WS11 6.738 20.512 376.903 113.732
WS12 7.582 22.139 304.009 165.919
WS13 6.661 20.359 384.954 56.591
WS14 9.902 26.308 186.984 137.479
Table 10. Summary of Calculation for Day Creek Debris Basin
Date Dy (m3)
Accumulated Dy (m
3)I (mm/hr) P (mm)
11/1/2003 0 0 4.826 26.162
11/12/2003 45,623 45,623 7.874 22.352
12/25/2003 94,037 94,037 24.13 151.13
1/2/2004 0 0 1.778 11.43
Total 139,660 m3 °° °°
Jang Hyuk Pak and Joo Heon Lee
− 8 − KSCE Journal of Civil Engineering
The measured sediment yield was 146,871 m3 (USACE, 2005)
while the estimated sediment yield by the MSDPM-R was
139,660 m3 with the precipitation data obtained from the Mt.
Baldy (MTBY) precipitation gage. The difference of the two
values was -7,211 m3, (-4.9%).
When the MSDPM-R was applied to predict the sediment yields
for the Day Creek Debris Basin, the result (-4.9% difference)
was in good agreement with the measured amount. It should be
noted that the measured amount was computed using survey data
from SBCDPW. Based on the predicted result compared with
field data, one could reasonably conclude that the MSDPM-R
can be used to predict the accumulated sediment yield using the
sediment delivery ratio for the coastal southern California water-
sheds in the range of 800-3,000 ha.
The difference between with and without the sediment delivery
ratio approach is shown in Table 11. The MSDPM was used to
estimate the sediment yield without the sediment delivery ratio
based on one large watershed model while the MSDPM-R was
used to estimate the sediment yield with the sediment delivery
ratio based on multi sub-watersheds. The results from the two
methods are very different because the MSDPM was developed
based on the data generated from small watershed (25-800 ha).
To extend the use of MSDPM for large watershed, the sediment
delivery ratio should be implemented using MSDPM-R.
4. Conclusions
The MSDPM-R was developed by adding a sediment delivery
ratio component to the MSDPM for the prediction of sediment
yields for large watersheds in the San Gabriel Mountains and San
Bernardino Mountains in southern California. The present research
advances sediment yield prediction from a different perspective
since most existing methods were developed for small water-
sheds. The MSDPM-R will provide a means to rapidly estimate
debris yield with maximum 1-hr rainfall intensity and total
rainfall amount of each storm event based on precipitation data
for large watersheds. The modeling results suggest the MSDPM-
R can be used to predict the accumulated sediment yield for
coastal southern California watersheds with an area in the range
of 800-3,000 ha. The MSDPM-R using sediment delivery ratio
was developed based on limited data, therefore it should be
modified when additional data available. The MSDPM-R was
developed based on data generated from watersheds in the San
Gabriel Mountains and San Bernardino Mountains within southern
California. Expanded use of the MSDPM-R to wide areas should
be confirmed with additional debris data in order to apply this
model with confidence for a wider range of conditions in engin-
eering applications. The MSDPM-R is a viable tool for the effective
management of existing large debris basins, to determine whether
they should be excavated immediately to regain storage capacity
based on the remaining debris basin capacity before subsequent
storms occur. This will enable operators to have more control in
scheduling cleanout operation for large debris basins. The
MSDPM-R can be used for responding to the emergency situations
to protect human lives and to lessen the risks of economic damage
by predicting more accurately the post-fire sediment yields based
on the remaining debris basin capacity and National Weather
Service forecast information.
In this research, although the MSDPM-R was developed for
rapid estimation of sediment yield based on limited field data,
there is a huge potential for useful application once the MSDPM-
R is calibrated based on future available field data. Expanded use
of the model to other areas should be verified with additional
sediment measurements from large watersheds in order that this
model may be applied with confidence for a wider range of
conditions.
Acknowledgments
The author is thankful to Matt Fleming and Dr. Michael Gee of
the Hydrologic Engineering Center, Institute for Water Resources,
Kerry Casey of the Los Angeles District, U.S. Army Corps of En-
gineers, and Dr. Jiin-Jen Lee of the University of Southern
California for their helpful comments, insights, and suggestions.
Dr. Iraj Nasseri, Loreto Soriano, and Ben Willardson of the Water
Resources Division at the Department of Public Works of the
Los Angeles County have provided useful data and helpful
comments.
References
Cannon, S. H., Gartner, J. E., Rupert, M. G., and Michael J. A. (2003).
“Emergency assessment of debris-flow hazards from basins burned
by the grand prix and old fires of 2003, Southern California.” U.S.
Table 11. Comparison of Sediment Yield with and without Sediment Delivery Ratio
Debris BasinWatershed
Area(ha)
BurnArea(%)
ReliefRatio
(m/Km)
MeasuredSedimentYield (m3)
MSDPMSediment
Yield3 (m3)
MSDPMSediment
Difference (%)
MSDPM-RSediment
Yield4 (m3)
MSDPM-RSediment
Difference (%)
Little Dalton1 835 89 98 48,932 0 -100 48,984 0.11
Cucamonga Creek1 2,998 89 157 175,848 232,197 32 176,091 0.14
Deer Creek1 966 100 244 120,112 87171 -27 120,319 0.17
Day Creek2 1,262 98 211 146,871 109,874 -25 139,660 -4.911Debris Basin for the calibration2Debris Basin for the validation3Sediment yield estimated based on the one watershed without the sediment delivery ratio4Sediment yield estimated based on multi sub-watersheds and stream network with the sediment delivery ratio
A Hyper-concentrated Sediment Yield Prediction Model Using Sediment Delivery Ratio for Large Watersheds
Vol. 00, No. 0 / 000 0000 − 9 −
Geological Survey Open File Report 03-475, pp. 1-10.
(http://pubs.usgs.gov/of/2003/ofr-03-475/OFR03-475Text508.pdf)
DeBano, L. F. (2000). “The role of fire and soil heating on water repellency
in wildland environmental: a review.” Journal of Hydrology, Vol.
231-232, pp. 195-206.
Gatwood, E., Pedersen, J., and Casey, K. (2000). “Los Angeles district
method for prediction of debris yield.” U.S. Army Corps of
Engineers, Los Angeles District, Los Angeles, California, pp. 1-20.
(http://www.spl.usace.army.mil/resreg/htdocs/DebrisMethod.pdf)
LACDPW (Los Angeles County Department of Public Works) (2003).
“2002-2003 storm report Los Angeles County.” Los Angeles County,
Department of Public Works, Alhambra, California, pp. 11-36.
Middleton, J., Syhaphom, S., Grim, J., and Collins, W. (2004). “The
Emergency Watershed Protection program (EWP) - Greenwood
Ave, San Bernardino County.” CA. Natural Resources Conservation
Service, File Code 390-14.
Pak, J. H. (2005). “A Real-Time Debris Prediction Model (USCDPM)
Incorporating wildfire and subsequent storm events.” Ph.D. Thesis,
University of Southern California, Los Angeles, California.
Pak, J. H. and Lee, J. J. (2008). “A statistical sediment yield prediction
model incorporating the effect of fires and subsequent storm
events.” Journal of the American Water Resources Association, Vol.
44, No. 3, pp. 689-699.
Pak, J. H., Kou, Z., Kwon, H. J., and Lee, J. J. (2009). “Predicting debris
yield from burned watersheds: Comparison of statistical and arti-
ficial neural network models.” Journal of the American Water
Resources Association, Vol. 45, No. 1, pp. 210-223.
Pierson, F. B., Robichaud, P. R., and Spaeth, K. E. (2001). “Spatial and
temporal effects of wildfire on the Hydrology of a Steep Rangeland
Watershed.” Hydrological Processes, Vol. 15, Issues 15, pp. 2905-
2916.
Ponce, V. M. (1989). Engineering hydrology, principles, and practices,
Prentices Hall, pp. 256-259.
Renard, K. G., Foster, G. R., Weesies, G. A., McCool, D. K., and Yoder,
D. C. (1997). Predicting soil erosion by water: A guide to con-
servation planning with the Revised Universal Soil Loss Equation
(RUSLE), Agricultural Handbook No. 703. US Department of
Agriculture, Washington, DC.
Robichaud, P. R. (2000). “Fire effects on infiltration rates after pre-
scribed fire in northern rocky mountain forests, USA.” Journal of
Hydrology, Vol. 231-232, Issue 1-4, pp. 220-229.
Rowe, P. B., Countryman, C. M., and Storey, H. C. (1954). “Hydrologic
analysis used to determine effects of the fire on peak discharge and
erosion rates in Southern California watersheds.” U.S. Department
of Agriculture, Forest Service and Range Experimental Station, pp.
1-49.
Tatum, F. E. (1963). “A new method of estimating debris-Storage re-
quirements for debris basin.” Second National Conference on
Sedimentation of the Subcommittee on Sedimentation, Interagency
Committee on Water Resources, Jackson, Mississippi, pp. 1-6.
U.S. Army Corps of Engineers (USACE) (1995). Application of
methods and models for prediction of land surface erosion and yield,
TD-36, Hydrologic Engineering Center, Davis, California, pp. 1-20.
U.S. Army Corps of Engineers (2005). Analyses of the debris and
sedimentation impacts at selected debris basins associated with the
wildfires of 2003 and the December 25, 2003 storm: Hydrology and
Hydraulics Section, U.S. Army Corps of Engineers, Los Angeles
District, after action report DRAFT, p. 39.
Van der Werf, G. R., Randerson, J. T., Collatz, G. J., Giglio L.,
Kasibhatla, P. S., Arellano, A. F., Olsen, S. C., and Kasischke, E. S.
(2004). “Continental-scale partitioning of fire emissions during the
1997 to 2001 El Niño/La Niña period.” Science, Vol. 303, No. 00,
pp. 73-76.
Westerling, A. L., Hidalgo, H. G., Cayan, D. R, and Swetnam, T. W.
(2006). “Warming and earlier spring increase Western U. S. Forest
Wildfire Activity.” Science, Vol. 313, No. 00, pp. 940-943.
Wildfire Safety Panel (1994). Report to the Los Angeles County board
of supervisors, Fire Department, County of Los Angeles, California,
pp. 1-15.
Wischmeier, W. C. and Smith, D. D. (1978). Predicting rainfall erosion
losses – A guide to conservation planning, Agriculture Handbook
No. 537. US Department of Agriculture, Washington, DC.