23
A. General observations on Incidents reported to PNGRB: 1. Air tightness test prior to gas charging, at suitable pressure, will remove chance of incidents to a large extent. 2. The N2 cylinder and its source to be thoroughly verified and checked for purity before using the same for purging activity. 3. Proper odourisation with periodic tests to be carried out at various defined locations on the network and at network extreme ends to ensure minimum acceptable level. There have been cases of fire which have resulted because of inadequate or very less odourization. 4. Develop and communicate a procedure of positive isolation, by closing the isolation valve upstream of regulator, opening of union downstream of regulator and plugging the regulator downstream. 5. Gas supply to be started by opening of DRS valves after ensuring that there is no leakage or trapped air/oxygen. 6. It needs to be ensured that there is no gas at the location and all electric supply is stopped before excavating. 7. In order to effectively handle fire incidents, the entities having bulk storages of inflammable hydrocarbons should ensure the following: 8. Periodic technical and safety audit of its facilities. o Periodic review and approval of Disaster Management Plan and its implementation including mock drills covering range of scenarios. o Effective and monitorable Work Permit System so that work can take place only with prior written permit allowing access only to persons, tools and equipments authorised under the work permit to designated work area. Work to be carried out only under authorised supervision. o Periodic fire and safety trainings of all concerned. o Entity to ensure adequate fire water reservoir/storage of its own with sufficient quantity of water at all times along with automated fire water

A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

 

A. General observations on Incidents reported to PNGRB: 

 

1. Air tightness test prior to gas charging, at suitable pressure, will remove chance 

of incidents to a large extent. 

2. The N2 cylinder and its source to be thoroughly verified and checked for purity 

before using the same for purging activity. 

3. Proper  odourisation with  periodic  tests  to  be  carried  out  at  various  defined 

locations on  the network  and  at network extreme ends  to ensure minimum 

acceptable level. There have been cases of fire which have resulted because of 

inadequate or very less odourization.  

4. Develop  and  communicate  a  procedure  of  positive  isolation,  by  closing  the 

isolation  valve  upstream  of  regulator,  opening  of  union  downstream  of 

regulator and plugging the regulator downstream. 

5. Gas supply to be started by opening of DRS valves after ensuring that there  is 

no leakage or trapped air/oxygen. 

6. It  needs  to  be  ensured  that  there  is  no  gas  at  the  location  and  all  electric 

supply is stopped before excavating. 

7. In order to effectively handle fire incidents, the entities having bulk storages of 

inflammable hydrocarbons should ensure the following: 

8. Periodic technical and safety audit of its facilities. 

o Periodic  review  and  approval  of  Disaster  Management  Plan  and  its 

implementation including mock drills covering range of scenarios. 

o Effective  and monitorable Work  Permit  System  so  that work  can  take 

place  only with  prior written  permit  allowing  access  only  to  persons, 

tools and equipments authorised under  the work permit  to designated 

work area. Work to be carried out only under authorised supervision. 

o Periodic fire and safety trainings of all concerned. 

o Entity  to ensure adequate  fire water  reservoir/storage of  its own with 

sufficient quantity of water at all times along with automated fire water 

Page 2: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

spray/  sprinkling  system/foam/CO2  flooding  system  so  that  such 

emergency situations can be handled promptly and effectively. 

o MOU with nearby industries including periodic joint mock drills involving 

district administration. 

9. There  shall be an Emergency Vehicle  fully equipped with all necessary  tools, 

tackles to handle fire and safety emergency with trained man power equipped 

with proper communication gadgets on round the clock basis. 

10. The periodic checks of “o‐rings” and other parts of CNG filling equipment and 

system should be carried out by entities resulting in making the system safe. 

11. Regular checking of electrical installation/facilities of CNG station. 

12. Regular  checking  at  CNG  stations  so  as  to  ensure  that  CNG  kit  has  been 

properly maintained/ CNG cylinder hydro tested as due.  

13. The safety disc should be replaced with a new one of appropriate quality after 

every hydro‐testing of CNG cylinder. 

14. The  CGD  entities may  organize  awareness  camps/  free  CNG  kit  checking  by 

trained technicians regularly on rotation basis at their CNG stations. 

15.  Safety  awareness  should  be  created  among  drivers  of  CNG  vehicles 

particularly auto drivers and commercial vehicle drivers. 

16. Periodic  fire  and  safety mock  drills,  regular  training  of  operational  staff  for 

proper operating procedure  and  keeping  records of mock drills  at  the  filling 

station.  

17. Wide circulation of incident investigation report together with lessons learnt to 

all concerned including PNGRB. 

18. Pipelines and other associated facilities to be installed in accordance to PNGRB 

regulations/guidelines. 

19. Educating  the  consumers  at  the  time  of  commissioning  and  awareness 

programmes at regular  intervals. Regular  leak checking and  integrity check of 

gas delivery system not only outside the premises/house but also pipe, meter, 

rubber pipes etc installed inside the house/flat.  

20. The entity  is advised to conduct periodic tests/ audits as per ASTM standards 

by engaging the services of a PNGRB approved third party 

Page 3: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

21. Approved on‐site/ offsite emergency plan should be available in office/control 

room along with updated phone nos./ email/ fax nos. / Mobiles/ addresses of 

relevant  local authorities, hospitals,  fire &  safety, police, emergency  services 

etc.  

22. Improvement  in  design  and  automation  so  that  relevant  monitoring 

parameters can be checked and critical parameters/ facilities/instruments etc. 

can be operated and controlled  remotely, wherever  feasible/necessary. Such 

automation  would  be  of  help  in  situations  like  rampage/blockage  by mob, 

wherein  it  becomes  difficult  to  reach  the  site  quickly  for  safe  isolation  of 

critical valves. 

23. All  the  isolation  points  need  to  be  easily  accessible,  periodically  checked, 

cleaned  and  maintained  so  that  same  can  operate  during  any  emergency 

scenario. 

24. Records of safety & technical briefings, before carrying out pre‐commissioning, 

commissioning, repairs and maintenance are to be maintained. A checklist and 

written procedures to be provided. 

25. Proper approved  format with all relevant check points to be  in place  for pre‐

commissioning, commissioning, operation and maintenance activities. 

26. Suitable online alarm facility will be provided in SCADA system when significant 

pressure change occurs at the valve station instrumentation.  

27. A  solar  lantern  to be provided  in  the  station  so  that  light  is  available  in  the 

night in case of failure of power from the grid.  

28. To ensure an orderly and timely decision‐making and response process in case 

of any natural calamity.  

29. Prepare  a  security  threat  plan  and  action  plan  to meet  the  eventualities  in 

reference to ERDMP regulations. 

Page 4: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

30. The identification of potential impact on downwind air quality or downstream 

water quality from an  incidental release and possible danger to human, Flora 

and  Fauna  and  animal  health  and  evaluate  the  consequences  of  such 

occurrences based on scenarios such as most probable and worst case events. 

31. The zones and maps shall be prepared highlighting the Incident prone areas of 

the  unit  so  that  in  case  of  an  emergency  it  serves  as  a  basis  for  taking  the 

action. This  indicates the size of the area within which human  life  is seriously 

endangered  by  the  consequences  of  incident.  This  should  also  indicate  the 

location  of  assembly  points  and  emergency  control  rooms.  The map  should 

also  have  marked  24  wind  directions  to  facilitate  easy  access  in  case  of 

emergencies. 

32. Wind  speed and direction  should be  recorded with  the help of anemometer 

and declaration of off‐site emergencies should be immediately communicated 

to DDMA. 

B. Recommendations by entities: 

a. General 

1. Warning mat with anti rodent properties to be used for 20 mm PE lines. 

2. Route selection for laying of the domestic 20 mm PE pipe shall be such that 

sewage system is not very near. 

3. Proper back filling and restoration (compaction) of the boring pit and ends 

shall be done. 

4. RCC guard proper fixing with sand padding shall be done. 

5. All AMC contractors are checking domestic connection for any gas  leakage 

with MMT and with soap solution at TF joint. 

6. Company approved guidelines for destructive testing of electro fusion joints 

is issued. 

7. Good quality Electro fusion weld joint shall be applied by certified welder. 

8. LPT of the network and walk through survey for gas leakage detection shall 

be carried out as per the planning. 

Page 5: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

9.  Hot work  permit must  be  issued  for  carrying  out  any work  on  charged 

network  and  the  work  is  to  be  carried  out  in  the  presence  of  skilled 

/authorized supervisor. 

10.  To hold tool box talk before starting of any activity on charged network. 

11. O & M  team/patroller  shall ensure  removal of  flammable waste near  the 

installation  and  back  filling  of  pits  if  any  on  commissioned  network  to 

prevent incidents. 

12. Better coordination with Utilities for any excavation work near the pipeline. 

13.  Safety  clinics  should  be  organized  in  residential  areas/society  to  make 

people aware of Do’s and Don’ts w.r.t. gas installations and network. 

         b.  In case of fire on PE line: 

1. Proper cordoning shall be done near the incident area. 

2. Close the respective PE network isolation valves. 

3. Ask general public to remain away at safe distance. 

4. Divert traffic of the nearby road if required with the help of traffic police. 

5. If required take help of fire brigade for controlling the fire. 

6. In case of fire  incident on network/installation; information shall reach to 

HSE  dept‐HO  and  signed  copy  of  the  preliminary  incident  report  shall 

reach to HSE dept within 24 hrs. 

7.  Display location hazard with safety guideline. 

8. Ensure to replace rupture disc during hydrotesting of CNG cylinders. 

 

 

Page 6: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

ANALYSIS OF INCIDENTS

S. NO. CAUSES OF INCIDENTS NO. OF

INCIDENTS

1. NATURAL CALAMITY 49

2. SAFETY MANAGEMENT AND AWARENESS ISSUES 1588

3. THIRD PARTY DAMAGE 2116

4. EQUIPMENT FAILURE 1058

5. GAS LEAKAGE (OTHER THAN THIRD PARTY) 480

TOTAL 5291

Page 7: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

 

Page 8: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

 Incidents reported under Level-2/Level-3 (Apr 1, 2012 to March 31, 2013)

 

 

Sr. No. 

Entity  Location  Date and time 

Type of Incident  Causes 

1.  IGL  Mayur Vihar III  02.09.2012 (21.00 hrs) 

LEVEL 3 / MAJOR (Fatal Incident) 

Sabotage and Arsoning

NH‐24 CNG Station  20.10.2012 (19.45 hrs) 

LEVEL 2 / MAJOR (Explosion) 

Explosion in CNG fitted vehicle 

2.  GSPC GAS  Arihant Petroleum and CNG Station, Navsari 

06.09.2012 (23.43 hrs) 

LEVEL 2 / MINOR   Equipment Failure (Fire Incident) 

Vapi  22.08.2012 (12.50 hrs) 

LEVEL 2 / MINOR  Third Party Damage (Gas Leakage) 

Kandari CNG Station 

03.07.2012 (22.40 hrs) 

LEVEL 2 / MINOR  Natural Calamity/Heavy wind 

Navsari  01.07.2012 (13.20 hrs) 

LEVEL 2 / MINOR  Third Party Damage 

3.  CUGL  Panchakki Chouraha, Kanpur 

04.08.2012 (04.30 hrs) 

LEVEL 3 / MAJOR (Fatal Incident) 

DRS Design fault by vendor

Shastri Nagar, Kanpur 

20.03.2013 (09.15 hrs) 

LEVEL 3 / MAJOR (Direct loss 20‐25 lacs) 

Pilferage/Sabotage (Gas Leakage and Fire) 

4.  GAIL  Vijaipur  29.08.2012 (19.25 hrs) 

LEVEL 3 / MAJOR (Fatal Incident) 

Safety management and awareness issues at construction site 

5.  MGL  Goregaon (E)  16.11.2012 (07.30 hrs) 

LEVEL 3 / MAJOR (Fatal Incident) 

Explosion in externally corroded CNG cylinder 

6.  GUJARAT GAS 

Rampura, Surat  29.12.2012 (10.15 hrs) 

LEVEL 2 / MAJOR (Fire about 30 minutes) 

Suspected Damage to Gas network by Third party Utility company 

7.  IOCL  Dabsar  04.12.2012 (10.15 hrs) 

LEVEL 3 / MAJOR (Fire about 30 minutes and Fatal Incident) 

Equipment Failure (Fire Incident) 

Hazira  05.01.2013 (10.15 hrs) 

LEVEL 3 / MAJOR (Fire and Fatal Incident) 

Under investigation 

 

Page 9: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

1. Incident at Kanpur (CUGL)  

Date of incident:                  04.08.2012 

Time:                                    04.30 PM 

Entity:                                  CUGL 

Location:                             Panchakki Chouraha, near Mall road, Kanpur.  

Description:  

A fatal accident took place on 4th August 2012 at CUGL Kanpur, and a project officer died on the spot  in the accident. The accident took place at underground DRS at paanchakki chouraha when downstream MDPE commissioning was undertaken on 4th August 2012 at 430 PM. 

 

The  underground  DRS  is  provided  by  the  vendor was  single  stream  of  capacity  5000 SCMH. The lid of the underground DRS cartridge blew away due to pressurization inside and hit the engineer on his face standing above ground on the side of the pit leading to the casualty. 

It  is  learnt  from  the  investigation  that  quarter  inch  outlet  vent  present  inside  the cartridge  remained  open  prior  to  the  charging  and  hence when  inlet  DRS  valve was opened,  gas  after  reduction  of  pressure  from  19  to  4  kg/cm2  got  released  inside  the upper half of the cartridge (which was not designed to handle any pressure) and due to the pressure of released gas the lid of cartridge busted into the pieces and blew away. It was collective failure of the, 

Design of DRS, 

• which did not have  inherent  fail  safe mechanism  to  release  such  vented  gases from the cartridge of DRS. 

• which could not hold the released gas inside the cartridge. Same could have been designed to handle max pressure in the system. 

Vendor’s commissioning team, 

Page 10: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

• who  did  not  mention  of  any  such  requirement  on  the  signed  commissioning format provided by them. 

CUGL commissioning team, 

• who  did  not  adhere  to  commissioning  procedure  including  venting  of  the assembly before Gas charging. 

Cause:  

• DRS Design fault by Vendor: Not a FAILSAFE design. 

• Deviation from adopted procedure. 

• Unidentified hazardous operation & compromise towards safety by CUGL team. The safety engineer was not called before start of commissioning. 

Recommendations:  • To be  taken up  strongly with Vendor  for  faulty DRS design  and  to own  them  the 

responsibility. 

• DRS  to  be  preferably  relocated  and  replaced  by  twin  stream  above  ground installation. 

• System to be in place to ensure checklist points on commissioning format itself and its compliance. 

• System to be in place to ensure use of PPEs • Role clarity and accountability should be fixed to avoid recurrence in future. • Provision of vent line to safer location should be a part of DRS inherent design. • DRS cartridge should be designed to hold max. Pressure in the system. • Necessary statuary approval/standards should be pre‐requisite before installation of 

these systems. • Pressure gauges provided inside the cartridge should be with isolation valves. • All  the  PGs  should  be  visible  for  noting  daily  readings  without  the  opening  of 

cartridge lid. • Quarter  inch vents provided  inside cartridge should be with double  isolation valves 

(block and bleed). • Installation should be with properly designed foundations and pedestals. 

 

 

 

 

 

Page 11: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

 

2. Incident at Mayor Vihar III (IGL)  

Date of incident:                  02.09.2012 

Time:                                    2100 hrs 

Entity:                                  IGL 

Location:                             MAYUR VIHAR III  

      Description:   

At 18:45 Hrs. media flashed news that a person died due to negligence of local police who have setup  a  barricade/  check  post  during  a  routine  exercise  on  road  going  from  Kalayanpuri  to Mayur  vihar‐1  via  Chilla  Village.  At  19:00  Hrs.  local mob  from  Chilla  village  attacked  police personnel  deployed  at  the  police  check  post.  At  19:30  Hrs.  station  staff was  updated  by  a customer who  came  for  refueling at  IFC‐2 CNG  station  regarding civic disruption. The  station was shut down as precautionary measures and information was given to Mktg & Control room. Due  to  heavy  barricading,  IGL  staff was  not  able  to  reach  the  site,  thus  telephonic  updates started between the station staff and IGL control room staff. 

At 20:30 Hrs. mob  from Khoda Village went on  rampage,  taking advantage of  the  incident & started looting the nearby market. At around 20:30 Hrs. on understanding the criticality of the situation,  Station  technician  isolated  all  the  manually  operated  gas  valves.  Meanwhile  the station manager collected the cash  from all DSMs and secured  it  in the safe. This activity was completed by 20:45 Hrs. At 21:00 Hrs, Delhi Police personnel asked the station staff to leave the station premises  as  the  crowd  started moving  closer.  Station  staff  left  the  IFC‐II  station  and gathered at  IFC‐I CNG station, which  is approx. 800 meters away. Few of them remained near the barricades to assess the situation and continuously informed about the sequence of events till the IGL teams reached IFC‐I. 

Marketing  officers  of  IGL managed  to  reach  IFC‐I  at  around  2145.  The mob  even  tried  to damage station safe box at IFC‐II, which was carrying a two days cash of around Rs. 11 Lacs, but could not succeed. At around 22:30 Hrs. control room team, fire & safety team could manage to reach to  IFC‐II CNG station to take the stock of situation. Simultaneously, Pipeline department managed to close isolation valves as a precautionary measure. At 01:00 Hrs on  3rd Sept’ 2012. after ensuring the complete  isolation of the station equipments, the whole team  left  IFC‐II on 

Page 12: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

instruction  of  Delhi  Police  team  as  the mob  was  again  approaching  the  station.  The  team gathered at IFC‐I CNG station and finally dispersed. 

Cause: 

• Pilferage/sabotage 

• Lack of job knowledge/ awareness.  

Recommendations:  • Awareness among employees and  contract workers by means of  case  study  to be 

taken  up  by  respective  control  rooms  for  handling  such  emergency  situations efficiently. 

• Frequency  of  training/Drills  on  emergency  handling  should  be  increased.  The information system should be improved so that response time can be minimized. 

• Since, approach to site  locations under such circumstances  is difficult, possibility of automation may be explored for remote operations from control rooms. 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 13: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

3. Incident at Vijaipur (GAIL (INDIA) LIMITED)  

Date of incident:                  29.08.2012 

Time:                                    19.25 Hrs 

Entity:                                  GAIL (INDIA) LIMITED 

Location:                             Vijaipur  

      Description:   

Construction  of  a  New  Raw  Water  Reservior  for  the  C2C3  Recovery  project  was  being undertaken. For the execution of the said  job, a batching plant was erected by the contractor for concrete works. 

On the particular day i.e. on 29th August 2012, the victim along with other 4 / 5 fellow workers was engaged  for  shifting  the  cement bags,  cut open  the bags  and pour  the  cement  into  the Batching plant. At around 19:25 Hrs. after  finishing his day’s work the victim came out of the cement go‐down and was trying to cross the road to join his fellow workers. While crossing the road he might have slipped,  lost his balance and came under the front wheel of the Concrete loaded Transit Mixer. 

Cause: 

• Due to heavy rain, the approach road and incident area was very muddy and slippery. 

• Victim was standing very close i.e. on the turning of the road.  

• The driver may not have been able to clearly see the victim, who on the left hand side of the vehicle.  

 Recommendations by the entity:  • More  Training  and Awareness  programmes  on  Safety  should  be  conducted which 

includes all categories of workers. 

Page 14: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

• Tool box talks should be conducted by each and every contractor with their workers before they proceed on to the work. 

• Supervision may be increased i.e. the no. of supervisors/ safety personnel may be increased considering the nature of the work at different areas. 

• Proper housekeeping at site should be maintained by the respective contractors. 

• Regular monitoring of area.  Illumination at site may be checked and  if required, additional lighting should be provided. 

• The speed of the vehicles should be observed and non‐compliances should be penalized.  

Recommendations by PNGRB: • Even  temporary  roads  at  construction  sites  should  be  properly  compacted &  blind/sharp turns need to be avoided. 

• Effort should be made to create separate movement paths/ pavements need to be created for workers at construction sites.  

• Proper barricading wherever required along with warning/ safety boards to be displayed at construction sites. 

 

 

4. Incident at Kanpur (CUGL)  

Date of incident:                  20.03.2013 

Time:                                    9.15 hrs 

Entity:                                  CUGL 

Location:                             Shastri Nagar, Kanpur. 

 

      Description:   

On 16th march 2013, a contractor started the digging work near to MDPE and Steel pipeline for water line laying. 

Page 15: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

Since  then  contractor was digging on  intermittent  timings  (i.e.,  stopping  and  starting) hence patrolling team gave  instructions to the contractor for  informing them and as well CUGL room prior to any digging activity near to gas line. 

20th March 2013 

• 09:00 am The said contractor again started the digging activity however this time he did not inform to the patrolling team as well to the CUGL’s control room. 

• 09:15 am Damage to 125 mm dia MDPE  line occurred during the digging activity with JCB (excavator) for water line laying. 

• Upon seeing the Gas Leakage Contactor called officer (O & M) about the incident. 

• They  rushed  to  the  spot  and on  the way  instructed  a plumber  to  close  the  Isolation valves at the  immediate upstream and downstream from the damaged point of MDPE pipeline. 

• Isolation Valve Closing Sequence : 

♦ 9:30 Isolation Valve of 125 mm dia MDPE line in front of KMC (downstream) 

♦ 9:40 Isolation Valve of 125 mm dia MDPE line in front of Kakadeo (upstream) 

♦ 9:45 Being  the only  industrial  customer M/S Quality  laminator was  instructed not to use the gas till further instruction. 

♦ 01:30 PM Damaged section repaired 

♦ By  the  time  repair work was over  gas was  totally  consumed by  the domestic customers from the entire 15 Km network in isolated section. 

♦ 01:35  PM  After  the  repairing  it was  decided  to  insert Nitrogen  from  Ranjeet Nagar area TF point at 2 kg to check the  leakage of  joints done to repair work and 125 mm dia valve located in front of KMC hospital was opened to allow the Nitrogen to fill in the empty network. 

♦ After  ensuring  no  leakage  it was  decided  to  push/purge  the  nitrogen/air  out from  various  points  preferably  from  the  risers  of  the  domestic  connection  at following strategic points: 

Lajpat Nagar Area:  Hayderabadi Biryani (Commercial Connection).  Farthest domestic connections (Domestic Connection).  Ram Misthan Bhandar (Commercial Connection) 

Ranjeet Nagar:  From the TF joint where nitrogen was inserted. 

Shastri Nagar:  Farthest TF point of Gulmohar Apartment II.  Sindhi Colony (Domestic Connections).  Quality Laminator (Industrial Connections) 

To start the purging 125 mm dia valve was opened in front of Kakadeo Thana to start the gas flow. 

Teams deployed were  instructed to carry out Venting/purging activity at each point after removing the regulator and for atleast 5‐10 mnts. 

After verifying the connections, CUGL team went to check the venting, the incident took place. 

Page 16: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

Cause: 

• Pilferage/sabotage. 

• Lack of job knowledge/ awareness.  

• Third Party Damage.  

• Auto‐ignition  

Recommendations:  • Needs to be explored by visiting various CGD’s for developing SOP for breakdown of 

MDPE pipeline. Hence firth the main line shall be fitted with end cap and Valve and this end cap of the main line shall be cut off to ensure proper purging. 

• Possibility of having a earthing  system at  the end  caps and Couplers and  Isolation valves to be explored. At the same time this can be checked up with fitting supplier as well as with other CGD’s. 

• System of  lock out and  tag out needs  to be developed  for averting any  tempering during any maintenance or breakdown activity. 

• Separate Line walkers (patrolmen) for MDPE network shall be hired to keep a check on unauthorized digging/tempering from third party.  

 

5. Incident at Goregaon (E) (MAHANAGAR GAS LIMITED)  

Date of incident:                  16.11.2012 

Time:                                    07.30 Hrs 

Entity:                                  MAHANAGAR GAS LIMITED 

Location:                             Goregaon (E)  

Page 17: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

      Description:   

A CNG cylinder of a Water tanker vehicle while filling gas at Bharat Coal tar pump, Goregaon (E) busted. During this explosion,  it caused minor  injuries to 2 pedestrians, who were discharged after giving first aid and 1pedestrian received severe injuries and later on died in hospital. 

Cause: 

• Externally corroded CNG cylinder. 

• Under investigation.  

 

6. Incident at Dabsar (IOCL)  

Date of incident:                  04.12.2012 

Time:                                    1700 hrs 

Entity:                                  IOCL 

Location:                             Loopline terminal near Dabsar.  

Description:  

Around  17:30  hrs,  the  Chief  Operations Manager  informed  that  the Main  pumps  at Viramgam station has  tripped on High discharge pressure  in  the Mainline and  the shift operation personal are restarting the pumps. 

Such  trippings  are  inbuilt  protection  systems  which  are  incorporated  in  the  Pipeline Operation  Logics whereby  any  effect which  is  in deviation  from  the normal operation parameters  of  either  the  pipeline,  or  of  equipments  or  the  effect  of  proceeding  or succeeding pipeline installation, is captured and pipeline operation are tripped.  

Page 18: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

Undersigned contacted Viramgam control room for updates. As telephone of control room was continuously engaged, undersigned immediately contacted Sidhpur control room for operation parameters. Sidhpur control room informed that the suction pressure (upstream pressure)at the station has drastically come down to Zero kg/cm2. Now, Viramgam Control room rang and told that the pumps were started and stopped immediately as discharge pressuire was not increasing beyond 12 kg/cm2 

The Central Dispatch, the body that controls day‐to‐ day operation of all the pumping installation on round the clock basis, took the decision immediately to take shutdown of the entire section of the pipeline and closed Motor Operated Mainline Block valves, remotely through SCADA command. 

Around 18:15 hrs, information was conveyed by the maintenance personal that one villager from Dabsar village has conveyed to our Mainline Maintenance personal who was staying at Mehsana that there was heavy spray and leakage of oil from the Loopline Terminal at Dabsar. And a person is rushing towards Dabsar from Mehsana. 

At the same time the same message was conveyed by mobile informing that one more person is also rushing towards the installation as he was only a few kilometers from that place. 

After about 10 minutes, got the information that a person could see heavy smoke emanating from Dabsar loop‐line terminal. 

IOCL team headed by COM Viramgam, CISF crew, foam tenders, Maint crew rushed towards Dabsar. 

The undersigned activated the DMP from the control room along with Dy. Manager and started informing to all the members/ Bodies as per DMP. 

Site personal informed that the Disaster Management Authority took supervision and Control of the incident and fire fighting activity started at Site with Fire fighting personal from Kadi, Ahmedabad, ONGC, IOCL. 

The fire was brought under control around 22:30 and doused by 23:00 hrs. 

District Authorities shifted 3 persons who were injured to the Hospital by Ambulance. 

  

 

 

Cause:  

• Under investigation. 

•  2 motorcycles on the village road in charred condition. 

•  Heap of dry grass as well as presence of unwanted dery agricultural waste/ babool tree etc at a distance. 

Page 19: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

 

7. Incident at Hazira Terminal (IOCL)  

Date of incident:                  05.01.2013 

Time:                                    12:30 hrs 

Entity:                                  IOCL 

Location:                             Hazira Terminal.  

Description:   

On 05.01.2013 around 12:30 PM there was a thud and the floating roof of MS tank No. 4 having approx. 5000 KL blown off. 

This was followed by fire on tank. 

Immediately Gujarat State Office, neighboring industries and the local administration was informed of the accident. 

The auto fire fighting system available at location was operated immediately and the sprinklers started on adjacent tank No. 3 & 5 for cooling. The monitor also operated on Tank No. 4 was on fire. 

There are total 9 vertical tank farm area with 5 tanks of MS (Petrol) in a row and 4 tanks containing two SKO and two HSD in another dyke. 

The tank No. 1 of MS was empty and no product stored in the tank. However, other tanks of MS have contained product. 

Immediately, the neighboring industries rendered help and they deputed their fire tenders with fire fighting teams. 

The local administration also reported by 14:00 Hrs. the Factory Inspectors arrived at site and requested all neighboring industries i.e., KRIBHCO, RIL, ONGC, GAIL, L&T, Essar, Adani, BPC, HPC, etc. to extend their help. 

The tank wagons placed on 05.01.2013 at siding were pulled by Railways/ONGC immediately and placed at Sachin station safely. 

Page 20: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

ONGC provided water connection for providing water at IOC Hazira Terminal. 

The District Collector has been taking the feedback on the situation and visited site at around 19:00 Hrs. 

The DIG of police and the Police Commissioner also visited the site and reviewed the situation. The necessary help was extended by Police Department to cordon off the area and to maintain law and order. 

Two Ambulances were positioned at the site. 

The tank roof has fallen immediately on the approach road from tank No. 4 towards tank No. 5 and made it difficult for the fire tenders to approach for the same. 

The Collector immediately suggested for the alternative ways to approach tank No. 5, the adjacent tank to affected tank No. 4. 

It was decided that the team of officials from M/s Reliance, M/s Essar and the team of IOCL’s Gujarat Refinery shall start for firefighting immediately and the other industries shall provide backup to them. 

After the continuous fire fighting, the replenishment of water started after 5 Hrs. 

Under the disaster management the water tankers from different Municipal Corporations of Surat, Vadodara, Ahmedabad, Navsari, Valsad and Daman etc. also arrived at the site. The fire tenders from the neighboring industries like ONGC, GAIL, KRIBHCO, Reliance, L&T, Adani, Essar, etc. had arrived and were participating in the fire fighting. 

Tank No. 5 got affected due to winds unfavorable direction. 

Around 2300 Hrs the wind started blowing towards the tank No. 3 which is adjacent to other side of affected tank. 

The fire was fought with great courage and all the efforts were made to ensure that the adjacent tanks are cooled. 

The water was also replenished in the fire water tanks and the water was used judiciously for cooling purpose. 

There were approx. 40 Nos. of fire tenders reported. Two truckloads of foam was also brought from other location as back up to douse the fire. 

The fire fighting operation continued for the whole night. 

On 06.01.2013 around 0700 Hrs the intensity of fire reduced in tank No. 4 and by the time the tank was melted and was reduced to the height of approx. 4 Meter with one side reduced to approx. 1.5 Meter height. 

The fire intensity was further reduced at about 0900 Hrs in tank No.4 reducing the risk of direct heat on tank No. 3 & 5 

Page 21: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

The visit was made on 06.01.2013 morning by the Hon. Petroleum Minister, Shri Veerappa Moily along with Chairman and Director (M) of IOCL with OISD dignitaries. 

The situation was ascertained as under control. 

The fire fighters approached to the tank No. 5 from the top and douse the fire around 1300 Hrs. 

On visibility and approachability during the round, 3 bodies have been recovered. 

The flare on tank No.3 & 5 doused completely. The fire is confined in tank No. 4 with smoke and the intermittent fire is on 06.01.2013. 

One mobile in broken condition was found at tank farm area which is handed over to police on 06.01.2013. 

The effort of Terminal In‐Charge and his team was appreciated by District Collector on making all efforts in averting catastrophic disaster. 

Cause:  

• Under investigation.                        

Page 22: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

8. Incident at Dwarka (IGL) 

Date of incident:                  22.06.2013 

Time:                                    13.00 Hrs 

Entity:                                  IGL 

Location:                             Nuovo Apartment, Sec‐10, Dwarka. 

Description:  • It was admitted by the Engineer In Charge (of G.I. Riser Maintenance) that the job was being 

done without any permission or prior  intimation to any person  in PNG Control Room, G.I. Riser maintenance incharge or his concerned TPI (Third Party Inspector).  He also stated that there was no riser maintenance job  lined up on dated 22.06.2013. Still the job was carried by the contractor team without intimation and any supervision. However he refused to give any statement in writing. 

• Based  on  the  discussion with  bystanders  at  the  incident  site,  it was  informed  that  the incident happened as the rope that was being used by workers broke and the person who was working fell down on the ground and got injured. 

• The injured was taken to hospital where he succumbed to injuries. 

• The  incharge of G.I. Riser maintenance stated  that  there were  four members  in  the  team (including  the  deceased) working  on  that  day  in Nuova  apartment  for  Riser  testing  and Painting Job.  

 Observation: 

• It was observed that the yellow paint was found spilled on the ground i.e. at the base of the riser and no paint work was found done on riser from top to bottom. This implies that the worker  fell down almost  from  the  top of  the building, which was 9  storeyed, which was confirmed by the security guard on duty.  

Cause: • Based on the available  information from site visit, the apparent cause  is Equipment (rope) 

failure. 

• Since  the  job  of  ‘painting  of  riser’  was  taken  up  by  the  Contractor  team  without  the knowledge/ permission of concerned C/R and TPI, hence the safety precautions, checking of safety equipments & PPE’s could not be done before starting the job, that resulted in use of unapproved/unhealthy safety gadget. 

Page 23: A. General observations on Incidents reported to PNGRB · 16.Periodic fire and safety mock drills, regular training of operational staff for proper operating procedure and keeping

Immediate Actions/Remedial Measures: • Meeting  of  all  contractors,  their  authorised  supervisors  was  called  and  all  were 

instructed to ensure compliance of safety systems at all levels, failure of the same shall lead  to strict action as per contractual terms. M/s Shanvi Construction  (the contractor who was carrying out work at the aforesaid incident site) was asked to explain for such serious lapse in executing the work and action they are taking to avoid such recurrence.   

• Checking of all the safety gadgets, tools & tackles in all areas is carried out. 

• Refresher trainings, briefings, case studies, discussions is taken up in Control Rooms, to educate and sensitise the staff. 

      Recommendations by entity: 

• For  critical  activities  like working  at  high  rise  building,  a  Three  Tier  safety Work  Permit  System  may  be  followed  involving  representatives  of  PNG Control Room/PMC/TPI, and Fire & Safety department. 

• Certified Practical Training programs for Working at Height may be arranged for all working staff of PNG.