44
RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David Proverbs University of Wolverhampton A decision support tool for the valuation of variations on civil engineering projects

A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

RICSResearch

RICS Research paper series

Volume 5, Number 7

May 2005

Monty Sutrisna, Kevan Buckley,

Keith Potts and David Proverbs

University of Wolverhampton

A decision support tool for the valuation ofvariations on civil engineering projects

Page 2: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

2 � RICS Research

MMoonnttyy SSuuttrriissnnaa was a PhD student inthe Research Institute in AdvancedTechnologies, University ofWolverhampton. This paper, alongwith many other papers producedduring his studentship, aims todisseminate the findings of his PhDresearch into the valuation ofvariations in construction projects.His PhD research project involvedkey staff members of the Universityof Wolverhampton, including KeithPotts (School of Engineering and theBuilt Environment), Kevan Buckley(School of Computing andInformation Technology) and DavidProverbs (Research Institute inAdvanced Technologies.

Monty Sutrisna has recentlycompleted his PhD and is currentlyworking as a post-doctoral researcherin the Research Institute for the Builtand Human Environment at theUniversity of Salford. His researchinterests encompass generalconstruction procuremrent, thebriefing and design process,negotiation and decision-making inconstruction and the generalapplication of informationtechnology in construction.

Page 3: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

AApprriill 22000055

VVoolluummee 55,, NNuummbbeerr 77

A decision supporttool for the valuationof variations on civilengineering projects

Monty Sutrisna, Keith Potts, David Proverbs andKevan BuckleyUniversity of Wolverhampton

Page 4: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

© RICS

April 2005

ISSN 1464-648X

ISBN 184 2192 175

Published by:

RICS

12 Great George Street

London SW1P 3AD

United Kingdom

The views expressed by the

author(s) are not necessarily those

of the RICS nor any body con-

nected with it. Neither the

author(s), nor the RICS accept any

liability arising from the use of this

publication.

Copies of this report can be made

free of charge for teaching and

research purposes, provided that:

• the permission of the RICS is

sought in advance

• the copies are not subsequent-

ly resold

• the RICS is acknowledged

AAiimmss aanndd ssccooppee ooff tthheeRRIICCSS RReesseeaarrcchh PPaappeerrSSeerriieess

The aim of the RICS Research

Paper Series is to provide an outlet

for the results of research relevant

to the surveying profession.

Papers range from fundamental

research work through to innova-

tive practical applications of new

and interesting ideas. Papers com-

bine academic rigour with an

emphasis on the implications in

practice of the material presented.

The Series is presented in a read-

able and lucid style which stimu-

lates the interest of all the mem-

bers of the surveying profession.

FFoorr mmoorree iinnffoorrmmaattiioonn oonn tthhee

RRIICCSS RReesseeaarrcchh PPaappeerr SSeerriieess,,

pplleeaassee ccoonnttaacctt::

Stephen Brown

Head of Research

RICS

12 Great George Street

London SW1P 3AD

United Kingdom

[email protected]

Tel: +44 (0)20 7695 1568

Fax: +44 (0)20 7334 3722

TThhee RRIICCSS PPaappeerr SSeerriieess

EEddiittoorr

Professor Les RuddockSchool of Construction andProperty ManagementUniversity of SalfordSalfordLancs M7 1NUUnited Kimgdom

Tel: +44 (0) 161 295 4208Fax: +44 (0) 161 295 5011Email: [email protected]

PPaanneell ooff rreeffeerreeeess

Akintole AkintoyeGlasgow Caledonian UniversityScotland

Ghassan AouadUniversity of SalfordEngland

David BaldryUniversity of SalfordEngland

Malcolm BellLeeds Metropolitan UniversityEngland

Alistair BlythUniversity of WestminsterEngland

Thomas BohnUniversity of LeipzigGermany

Paul BowenUniversity of Cape Town South Africa

Terry BoydQueensland University ofTechnologyAustralia

David ChapmanUniversity College LondonEngland

Charles CowapHarper Adams University CollegeEngland

Hoffie CruywagenUniversity of Pretoria South Africa

Christopher FortuneHeriot-Watt UniversityScotland

Andy HamiltonUniversity of SalfordEngland

Barbara HawardUniversity of PortsmouthEngland

Michael HoxleyAnglia Polytechnic UniversityEngland

Will HughesUniversity of ReadingEngland

Eddie HuiHong Kong PolytechnicUniversityHong Kong

Norman HutchisonUniversity of Aberdeen Scotland

Ramin KeivaniOxford Brookes UniversityEngland

Richard LaingRobert Gordon’s UniversityScotland

S M LoCity University of Hong KongHong Kong

David LoweUniversity of ManchesterEngland

William McCluskeyUniversity of UlsterNorthern Ireland

John MansfieldNottingham Trent UniversityEngland

Jacob OpadeyiThe University of the West IndiesTrinidad and Tobago

Rob PickardNorthumbria UniversityEngland

David ProverbsWolverhampton UniversityEngland

Rainer SchulzUniversity of AberdeenScotland

Martin SextonUniversity of SalfordEngland

Low Sui PhengNational University of SingaporeSingapore

Thomas UherUniversity of New South WalesAustralia

Clive Warren University of QueenslandAustralia

Peter WyattUniversity of the West of EnglandEngland

Page 5: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

Contents

Introduction 7

Valuation of variations 8

Research methodology 13

Data analysis 19

Conclusion 24

References 26

Appendix 1: The hypothetical case presented in the questionnaire 30

Appendix 2: Decision results from all respondents 32

Page 6: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

A decision support tool for the valuation ofvariations on civil engineering projects

The valuation of variations has been recognised as a prime cause of conflict and dispute in constructionmanagement. Such disputes often concern the prices and/or rates to be applied to the varied works.Previous research has identified the subjectivity of the decision-maker in interpreting the valuation rules tobe the major problem, particularly with regard to defining the work conditions and/or characteristicsduring a variation event.

Findings of a survey, conducted to elicit the views and perceptions of experienced practitioners towardsinterpreting the valuation rules are presented. The development of a decision-making tool based on arobust framework for valuing variations in civil engineering projects is described. The tool was developedby analysing changes in various decision attributes. The result of the changes was then mapped to relevantsets developed using fuzzy-logic principles. Various operators were used to perform the fuzzy-aggregationoperation. The modelling technique was demonstrated to be reliable in replicating the decision-makingprocess performed by experienced practitioners. As such is considered a suitable aid for decision-makinginvolved in valuing variations on civil engineering works.

The results of the analysis reported here have suggested the fuzzy-logic as an appropriate tool to modelhuman decision-making, particularly in valuing variations on civil engineering works. This is consideredan essential progress of the current study in modelling human decision-making process, particularly sincethere are so many unknown aspects associated with such a process. The modelling technique successfullydeveloped here is then used as the main algorithm for decision making in the subsequently developedKnowledge Based System (KBS) which is intended to assist practitioers minimise conflict and diputearising from the valuation of vaiations.

Contact:

Monty SutrisnaResearch Institute in Advanced TechnologiesUniversity of WolverhamptonWolverhampton WV1 1SBUnited Kingdom.

e-mail: [email protected]

Acknowledgements:

The author wishes to acknowledge the contribution ofStephen Brown, head of research of the Royal Institutionof Chartered Surveyors, in finalising this paper.

IInn ccoonnjjuunnccttiioonn wwiitthh tthhee MMuurrpphhyy GGrroouupp,, tthhee aauutthhoorr hhaassddeevveellooppeedd aa pprroottoottyyppee vveerrssiioonn ooff tthhee KKBBSS tthhaatt iissddeessccrriibbeedd iinn tthhiiss ppaappeerr,, wwhhiicchh iiss aavvaaiillaabbllee oonn tthhee iinntteerrnneett..RReeaaddeerrss ooff tthhiiss ppaappeerr wwhhoo aarree iinntteerreesstteedd iinn aa ttrriiaall ooff tthheeKKBBSS aarree iinnvviitteedd ttoo ccoonnttaacctt tthhee aauutthhoorr aatt tthhee eemmaaiillaaddddrreessss pprroovviiddeedd ttoo ggaaiinn aacccceessss ttoo tthhiiss..

Monty Sutrisna Keith PottsSchool of Engineering and the Built Environment School of Engineering and the Built EnvironmentUniversity of Wolverhampton University of Wolverhampton

David Proverbs Kevan BuckleySchool of Engineering and the Built Environment School of Computing and Information TechnologyUniversity of Wolverhampton University of Wolverhampton

Page 7: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

n construction project managementresearch, the subject of variations hasattracted considerable attention

(Hibberd, 1980; Hibberd, 1986; Dorter,1990; Akinsola, 1997). Variations havebecome an almost inevitable part of theconstruction process and in many cases, leadto conflict between the parties involved.Lack of effort in managing these conflictscan result in disputes (Fenn et al, 1997).When disputes are left unresolved, then thirdparty intervention, such as the services of anadjudicator, may be employed to help reachan agreement (Latham, 1994). Variationshave also been reported to significantlyreduce labour efficiency by up to 15%depending on which trades are concerned(Hanna et al, 1999a and 1999a).

One of the main causes of disputes is in thevaluation of the variations (Potts, 1995;Seeley and Murray, 2001). The problemswithin the valuation of variations have beenmuch attributed to the failure of thetraditional cost model, i.e. the bill ofquantities (Barnes, 1971). For example arecent survey on the use of contracts in thebuilding and construction projects revealedthat on lump sum contracts, bills ofquantities are still being used in up to 20% ofthe projects in the UK (RICS, 2003). Thecurrent traditional approach to valuingvariations, favoured by many clients, hasbeen claimed incapable of providing anadequate scheme of compensation tocontractors for any delay or disruptioninvolved due to the variation. A particularconstraint within the current valuation rulesis the dependency on personal opinion orjudgement (Hibberd, 1986). That is, there is a

high degree of subjectivity involved in thedecision-making process when valuingvariations. A robust mechanism is needed toeliminate or at least reduce the level ofsubjectivity involved when deriving whichvaluation method is to be implemented(Winter, 2002).

The development of conceptual frameworksfor valuing variations in excavation works(Sutrisna and Potts, 2003a) and in concreteworks (Sutrisna et al, 2003a) has beenpreviously reported. Similarly, the potentialfeasibility for developing a Knowledge BasedSystem (KBS) capable of controlling thesubjectivity involved, using heuristicknowledge of the decision-makers, has alsobeen reported (Sutrisna et al, 2003b).However, in attempting to develop this KBS,several difficulties in knowledge acquisition,knowledge representation and associating theknowledge in the inference mechanism werefound. Applying the basic principles of fuzzy-logic to model the decision-making processwas found to help overcome these difficulties(Sutrisna et al, 2003c).

This paper reports the findings of asubsequent questionnaire survey, conductedfor the dual purpose of gathering thedecision-makers’ knowledge and forevaluating current levels of subjectivity. Thedevelopment of fuzzy-set models to replicatethe decision-making process is describedfollowed by the tests undertaken to validatethe decision-making tool.

Introduction

RICS Research � 7www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

II

Page 8: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

The valuation of variations has long beenrecognised as one of the commonest sourcesof dispute in the construction industry(McGowan et al, 1992; Potts, 1995; Seeleyand Murray, 2001; Winter, 2002). There areseveral ways to value variations, and differentcircumstances will require different methodsof valuation. Problems normally occur whenthere are different perceptions between theparties involved regarding the circumstances

of the variations that require differentmethods of valuation. As argued by Hibberd(1986), the valuation in many cases dependsupon a high degree of personal opinion orjudgment.

Following the rules for variations provided inthe form of contracts, a contractor must bearin mind the possibilities of becominginvolved in a contract that permits a widerange of variations; and also that ratesquoted in the bills of quantities, when

considered appropriate, may be used for thevaluation of the variations. However, theserates and prices may not be an accuratefigure for individual work items. This leads tofrequent claims arising from the contractorwhen the measured quantities of permanentworks priced at billed rates do not representthe true value of the construction works(Seeley and Murray, 2001). From thecontractor’s point of view, the rates and

prices included in thetender may contain a lowprofit margin with a highdegree of risk that is takento maintain thecompetitiveness of thetender. Thus, if such a lowrate and/or price is appliedfor further extensiveamounts of similar works,the contractor may sufferreduced profit or evensignificant losses. From theemployer’s point of view,an authorised variation,which is closely relatedand necessary for thecompletion of the overall

works, should be valued similarly to theoriginal works. Thus, an increase to the rateand price would increase the liability of theemployer to the project and may causesignificant discrepancies to the initialinvestment benefit analysis. Hence, theemployer can suffer losses in the longer termresulting in the project becoming lessprofitable or unprofitable due to theextensive additional expenses for variations.

As a result, it has been acknowledged that

Valuation of variations

8 � RICS Research

...a contractor mustbear in mind the

possibilities ofbecoming involvedin a contract that

permits a widerange of variations

Page 9: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

the rules of valuation should not beimplemented in a loose way, simply becausethe rates to which they are applied may notbe appropriate (Hibberd, 1986). The ratesand prices applied in the event of valuationshould be the rate, which the contractorwould have inserted against that item, had itbeen included at the time of tender (Haswell,1963). Differences in evaluating theapplicability of rates and/or prices from billsof quantities for valuation of variations havebeen demonstrated in several legal cases withvarying results. In the legal case of DudleyCorporation v. Parsons & Morrin Ltd. (1959),the court decision to apply originalprices/rates from the bill of quantity hadresulted in a significant loss for thecontractor while in the legal case of HenryBoot Construction Ltd. v. Alstom CombinedCycles Ltd (2000), a similar decision to applyoriginal prices/rates from the bill of quantityhad resulted in a large profit for thecontractor.

In the earlier stages of this research, twoframeworks for valuing variations weredeveloped for excavation works and concreteworks, respectively. The FIDIC Conditions ofContract for Construction 1999 was selectedas the platform for the concrete worksframework whilst the excavation worksframework was based on the ICE Conditionsof Contract Measurement Version, 7thedition, 1999. The most significant problemsidentified during the development of bothframeworks concerned the subjectiveinterpretation of the classical three-tiervaluation scheme. While the extent ofchanges in the work characteristics and/orconditions determines whether the

rates/prices in the bill of quantity can beapplied directly [Clause 52(3)(a)], appliedwith adjustments [Clause 52(3)(b)] or a newrate/price is required [Clause 52(3)(b)]; thereremains a high degree of subjectivityinvolved in determining which of these isappropriate.

A subsequent phase of the research led tothe decision to focus on the framework forexcavation works as these are common tocivil engineering contracts in which thevaluation of variations have generally beenthe main cause of dispute (Seeley & Murray2001). Furthermore, the excavation workshave been found to be a main source ofvariations due to (e.q.) unforeseen groundconditions (Clayton 2001). Moreover,excavation works represent a basic workactivity, performed on most constructionprojects and therefore extend the potentialfor applying the findings of this research.

The framework identified factors to beconsidered during the valuation of variationsin excavation works and provided acomprehensive checklist of items to reducethe subjectivity involved (refer to Figure 1).In order to measure the extent of changesinvolved in a variation event, all changes inthe factors within the framework arerecorded under five criteria known as thedecision attributes. The five decisionattributes are the extent of changes occurredin the Construction Programme, HumanResources, Construction Equipment,Materials and Sundry Charges. Theframework for excavation work wascomposed from the checklist of the primaryfactors and secondary factors, presenting the

RICS Research � 9www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Page 10: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

relationship and the effects to the decisionattributes. Primary factors are defined as thebasic factors to be considered in valuingvariations (i.e. nature of the site, weatherconditions, and nature of the works) whilstsecondary factors (i.e. ground conditions,ground water control, and excavatedmaterials and its disposal) are other factorsderived from the primary factors andstrongly affected by the combination of theprimary factors. The extent of changes ineach attribute measures the degree ofsimilarity of work character and/or workconditions of the varied works compared tothe ones in the bill of quantities.

Fuzzy logic

Fuzzy-logic is a superset of Boolean Logicthat deals with the concept of partial truthand the uncertainties of vague boundary thatwas first introduced by Zadeh (1965). Fuzzy-set theory and fuzzy-logic were established inorder to deal with the vagueness andambiguity associated with human thinking,reasoning, cognition, and the perceptionprocess (Zadeh, 1965; 1973; Zimmermann,1987). As human decision-making processesusually have to deal with making decisions inthe presence of incomplete or impreciseinformation (Prodanovic, 2001), fuzzy-logicthat replaces Boolean logic with degrees oftruth or degrees of membership, is capable ofmodelling decision-making in such acondition (Boshoff, 2002). Fuzzy-logic hasbeen proved successful in solving manydecision-making problems mostly ofindustrial control (Hruschka, 1988).

The concept of a fuzzy-logic system was

described as a non-linear mapping of aninput data vector into a scalar output, wherethe vector output decomposes into acollection of independent multi-input/single-output systems (Mendel, 2001). In otherwords, the fuzzy-logic system contains therichness of an enormous number of mappingpossibilities that is not provided by the crispBoolean logic (i.e. dual value concept of trueor false). Fuzzy-logic system shifts theparadigm of a crisp value in classicmathematics into a fuzzy value (i.e. degreesof membership in the range of 0 to 1) todefine a class without a clear boundary.These fuzzy values represent the degree ofmembership. The closer the degree ofmembership value to 1, the closer the objectcan be associated or belong to theclass/group.

As a set is defined as any collection ofobjects, a fuzzy-set is defined as ageneralisation of the characteristic functionto represent an indistinct boundary of a set(Miyamoto, 2000). In other words, in thecase when the boundary of a set cannotreally be appropriately defined, the particularset can be appropriately defined as a fuzzy-set.

The intention of applying fuzzy-logic in thisproblem area is mainly to accommodate theuncertainties and ambiguities resulting fromthe experts subjective semantic interpretationin the valuation of variations rules providedby the ICE 7th Measurement Version, 1999;particularly in the interpretation of similarwork characteristics and/or similar workconditions.

10 � RICS Research

Page 11: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

RICS Research � 11www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Figure 1. Framew

orkfor

assessing work

similarities and/or

work

conditions orexcavation w

orks (Adapted from

Sutrisna & Potts 2003a)

Page 12: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

Prior to its application in the problem area,the fuzzy-logic principle is explored. Let Ube the universe of discourse. A fuzzy set F inU is characterised by a membership functionas follows:

µF: U ∏ [0,1]

Where µF (u) represents the grade ofmembership of u∈ U in the fuzzy set. Thedegree of membership ranges from 0 to 1,where 0 demonstrates no membership and 1demonstrates a full degree of membership.In the problem domain, the valuation ofvariations, the universe of discourse U is thecollection of all possible value changes in thefive decision attributes. Three fuzzy sets(LOW, MEDIUM, and HIGH), which aredirectly associated with the three alternativesfor the decision-making, were defined for thevaluation of variations.

12 � RICS Research

Page 13: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

In order to operationalise the framework forexcavation works and to gather knowledgeand insight from practitioners, aquestionnaire survey was conducted toidentify and evaluate current practice invaluing variations. The questionnaire wasdesigned to elicit the decision-makers’knowledge and was used to evaluate theircurrent levels of subjectivity. The surveyutilised a hypothetical variation eventdeveloped specifically for this purpose (referto Appendix 1). The survey encompassedquantity surveying professional working forthe main parties involved in the valuation ofvariations, namely contractors,engineers/consultants and employers. Adetailed description of the survey design andquestionnaire design now follows prior to thepresentation of the results, analysis andconclusions.

The Questionnaire Survey

In order to utilise and validate the developeddecision-making tool, empirical data fromthe actual decision-maker was acquired via asemi structured questionnaire surveyencompassing open-ended and closed-endedquestions.

In performing surveys, the major concernsare sample size, data collection procedures,analysis and measurement. Statisticalapproaches that are utilised in the analyticalsurvey approach necessitate the priormeasurement of all pertinent variablesthrough their inclusion in a questionnaireformat (Ahlgren and Walberg, 1979). Thequestionnaire technique is defined as ageneral term to include all techniques of data

collection in which each person is asked torespond to the same set of questions in apredetermined order (deVaus, 1996). A self-administered postal questionnaire with spacefor feed back at the end of each section wasemployed. Respondents were asked to relatetheir answers towards a hypothetical casestudy (refer to Appendix 1) in order to elicitcomparable data for robust analysis, as usedin previous construction studies (Proverbs,1998; Xiao, 2002). The hypothetical caseinvolved an underground water tank andpumping station structure and presented avariation in the excavation works. Thehypothetical case was designed todemonstrate the simultaneous impact of avariation event on the decision attributes.The changes were deliberately set withinvarious arbitrary ranges for decisions inorder to capture the subjectivity of thedecision-makers (i.e. the practitioners).

Respondents

A major role of quantity surveyors is toprepare bills of quantities, performvaluations, and act as the economists of theproject (Seeley, 1984; Willis et al, 1994; TheAqua Group, 1996). Hence, thesepractitioners were considered appropriate toperform the decision-making in determiningthe valuation methods to be applied in avariation event (Sutrisna and Potts, 2003b).The target respondents were all memberslisted in the Construction CommercialManagement Practises Committee of theInstitution of Civil Engineering Surveyors2003 Yearbook and Directory of Members,excluding student members, graduatemembers and probationer members. The

Research Methodology

RICS Research � 13www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Page 14: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

population validity of these sample groupswas demonstrated by their membershipstatus in the Institution of Civil EngineeringSurveyors (ICES) as the ConstructionCommercial Management PractisesCommittee of ICES embodied qualifiedsurveying practitioners.

1,420 questionnaires were distributed to thetargeted respondents. The complicatednature of the research problem and the lackof literature available in the problem areameant that many difficult questions had to beincluded in the questionnaire. As aconsequence, the expected rate of return wasrealistically set to below 10%. This required alarge number of questionnaires to bedistributed in order to acquire a sufficientnumber of completed questionnaires for dataanalysis purposes. 125 questionnaires werereturned, representing a response rate of

8.82%. However, following an initial nettingof these, only 73 questionnaires were used foranalysis purposes since the remaindercontained item non-response errors and wereconsidered unfit for use. Item non-responseerrors occur when only part of the returnedquestionnaire is completed. While theresponse rate was considered quite poor, 73questionnaires used in the analysis had anestimated margin of error equivalent to11.5% at the 95% confidence level, which wasconsidered acceptable for the intendedanalysis.

In order to apply inferential statistic analysis,a large sample from an infinite populationwas required. In practice, the threshold for alarge sample is normally set to be larger than30 (Holt 1998; Kvanli et al, 2000). However,larger samples are needed in performingcomplex human decision-making modelling

14 � RICS Research

Number of responses analysed : 73

Respondents background Contractor: 40Consultant/Engineer: 17Employer/Client: 8N/A: 8

Respondents experience(in years) Min: 5

Max: 50Median: 40Mean: 28

Number of respondents interested to contribute further Interested: 44

Not interested: 29

Table 1. Respondents’ characteristic

Page 15: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

using fuzzy logic. Umbers & King (1981)have demonstrated that the sample sizeacquired here was sufficient for such analysis.The characteristics of the respondents areprovided in table 1.

Decision-Making Modelling

The decision-making model was developedfor each respondent using the basicprinciples of fuzzy-logic as described inSutrisna et al (2003c). The intention ofapplying fuzzy-logic in this problem area isto accommodate the uncertainties resultingfrom the decision-makers subjectiveinterpretation in the valuation of variationsrules provided by the ICE 7th MeasurementVersion, 1999; particularly in theinterpretation of similar work characteristicsand/or similar work conditions. Theapplication of fuzzy-logic in this problemdomain requires minimum knowledgeacquisition from the decision-makers andavoids the potential combinatorial explosionof the rules. Further, the inferencemechanism developed from the fuzzy-logicsystem can be subsequently applied to theintended KBS.

All changes in the hypothetical case wereaccommodated and quantified into the fivedecision attributes (i.e. changes inProgramme, Human Resources, ConstructionEquipment, Materials, and Sundry Charges).Based on this, the respondents were asked todetermine the extent of the overall changesdescribed in the hypothetical case studybased on the three-tier valuation mechanism.If the decision was to apply the rate/price inthe bill of quantity, then it was labelled

LOW. Other decisions were labelledMEDIUM and HIGH respectively. Further,the respondents were asked to break downtheir decisions for each decision attribute.This was followed by requesting therespondents to generalise and identify theirsubjective thresholds to determine theshifting point between the LOW, MEDIUMand HIGH for every decision attribute. Thiswas followed by requesting the respondentsto generalise (i.e. to also provide theirdecision breakdown for a general conditionin typical excavation works) and identify theirown version of thresholds to determine tehshifting point in order to group the variationsinto LOW, MEDIUM or HIGH. Therespondents were then asked to do this foreach of the decision attributes (i.e. changesin Programme, Human resources.Construction Equipment, Materials andSundry Charges).

These shifting points were then incorporatedwith the decision breakdown into each fuzzy-set to construct the model for each decisionattribute and denoted as C1, C2, C3 and C4(refer to Figure 2). For instance, the areabetween C1 and C2 in a fuzzy-set forHumanResouces repesents the ‘grey area’ for thisparticular expert/decision-maker. Thisparticular expert/decision maker was not surewhether any changes of Human Resourcesoccured in between C1 and C2 (denoted atU) should be classified as LOW orMEDIUM and so on. The intention of thiswas to define the shifting point for eachrespondent. These shifting points are thenused to develop the fuzzy-sets for everydecision attribute from each respondent.

RICS Research � 15www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Page 16: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

The extent of changes recorded in the fivedecision attributes were then mapped intorelated fuzzy-sets. The value of the changesunder each decision attributes were thenmapped into the corresponding fuzzy-sets todetermine their degree of membership inLOW, MEDIUM and HIGH. This groupingof LOW, MEDIUM and HIGH is related tothe three-tier decision-making alternativefrom the ICE 7th edition. LOW is associatedwith a certain degree of change in thedecision attributes that allows the originalrate/price from the bill of quantity to be

applied. MEDIUM is associated with acertain degree of change in the decisionattributes that requires adjustments to beapplied to the original rate/price from thebill of quantity. HIGH refers to a certaindegree of change in the decision attributesthat necessitates a new rate/price to bederived from a fair valuation.

An empirical symmetric membershipfunction consisting of the three fuzzy-setsused in the analysis is graphically illustratedin Figure 2.

16 � RICS Research

Page 17: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

The memberhip funciton of th ethree fuzzysets can also be represented:

Five membership functions were developedfor five decision attributes with three fuzzysets on each. As the inference mechanism,the membership values were then aggregatedusing appropriate fuzzy intersectionoperators (I) to represent aggregation"AND". Several fuzzy intersection operatorswere considered appropriate to represent theaggregation "AND". The selection of anappropriate operator is based on the natureof the problem (Zadeh ,1965; 1973; Duboisand Prade, 1980; Zimmerman, 1987; Yager,2000). In order to improve the accuracy ofthe results; three operators were used toaggregate the membership values, namely theminimum operator (this has been consideredthe most commn operator for intersection),arithmetic-sum operator (to accommodate a fullcompensation between “AND” and “OR”aggregation operation) and algebraic-product

operator (to accommodate furthercontribution of all membership values thatmay not be covered in the minimum operator).The majority outcome is considered as afinal result of these aggregation operations. Afailure to have a majority results in aninconclusive operation.

The fuzzy-intersection operators are definedas follows:

Minimum operator: µLowTotal(u) = min{ µLOW(u1), µLOW(u2), µLOW(u3), µLOW(u4),µLOW(u5)}

Arithmetic-sum operator: µLowTotal(u) ={µLOW(u1)+ µLOW(u2)+ µLOW(u3)+ µLOW(u4)+µLOW(u5)}

Algebraic-product operator: µLowTotal(u) ={µLOW(u1)o µLOW(u2)o µLOW(u3)o µLOW(u4)oµLOW(u5)}

Where u1,…,u5 are the degrees ofmembership in the LOW of all of thedecision attributes. The values ofµMediumTotal(u) and µHighTotal(u) can becomputed respectively. The mapping of thesevalues to the output of the inferencemechanism is performed by OR operator, i.e.fuzzy union operation (U). The operator usedis maximum operator to represent theselection process of the most influentialintersection-aggregation-result into a decisionand defined as:

Decision = LOW OORR MEDIUM OORR HIGH = µLow Total(u) U µMedium Total(u) U µHigh Total(u)= max {µLowTotal(u), µMediumTotal(u), µHighTotal(u)}

RICS Research � 17www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Page 18: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

For maximum operator, the highest value willbe selected as the decision. There is no needfor defuzzification of the result into a crispvalue as the objective of the operation hasbeen achieved, i.e. the resulting decision(Sutrisna et al, 2003c). An example of adetailed calculation is provided in appendix 2.

The decision-making modelling wasvalidated based on its capability to correctlypredict a majority of the actual decisions. Asthe success rate (non-error rate) is anarbitrary issue, a threshold value from anearlier study aimed at predicting humandecision-making using fuzzy-logic wasconsidered appropriate (Umbers and King,1981). Hence the model was consideredacceptable when capable of achieving a non-error rate above 60% at 90% significancelevel.

18 � RICS Research

Page 19: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

The discussion of the data analysis is focusedon two sets of analyses. The first involved acomparative analysis of the outcome of thefuzzy-sets with different aggregationoperators to the actual decision of thedecision-makers. As the main objective of themodelling was to replicate the decision-making process, validation is achieved whenthe model is competent in deriving a similardecision to the actual decision made by thedecision-maker. This part also reviews theapplicability and superiority of the fuzzy-intersection operators relatively from eachother for decision-making in the valuation ofvariations, particularly in excavation works.The second part of the analysis was on thedecision itself and set to investigate theinfluence of the background of the decision-makers on the decisions. That is, anevaluation of the objectivity found in thesedecisions is also described.

The Decision-Making Tool

The decisions resulted from the models werecompared to the actual decisions. Asummary of the comparison of actual andpredicted decisions is presented in Table 2.The results demonstrate the degree ofagreement betwen the decision makingcalculated by each aggregation operator andthe actual decisions of respondents.Appendix 2 provides full details of thisanalysis.

In modelling human decision-making usingfuzzy-logic, the developed model reliesentirely on the decision-makers’ explanationand therefore assumes that the statement wasa complete and correct explanation of thedecision-making process. Consequently, thedegree of agreement between the decisionsresulted by the developed model using fuzzy-logic and the actual decisions wererealistically expected to be above 60% for

Data Analysis

RICS Research � 19www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Table 2. Summary of the result

Min-max Arithmetic sum- Algebraic product- Combination ofoperator max operator max operator three operators

In agreement : 52 35 50 56

Not in agreementOverestimate : 2 2 2 1

Underestimate: 17 36 19 13Inconclusive : 2 0 2 3

Total : 73 73 73 73

Page 20: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

most cases. The degree of agreement in thisresearch is presented below.The hypotheses test are: H0: p <0.6

H1: p > 0.6Significant level used is α = 0.1 since theerror type II was considered more significantthan error type I. Error type II relates to theacceptance of an incorrect operator. The null hypothesis is rejected if Z>Zα. The Z is calculated as follows:

p = estimated probability = (total numberin agreement/total number ofsampling).

p0 = expected probability.n = number of sampling.The results of the hypotheses test arepresented in Table 3.

As demonstrated by the hypotheses testresult, the minimum-maximum operator andthe algebraic-product-maximum operatorprovide relatively higher probability toachieve a non-error rate above 60%. Onlythe arithmetic-sum operator provides asignificant probability to achieve a non-errorrate below 60%. Based on this, it can beconcluded that the arithmetic-sum operator isnot an appropriate stand-alone-operator forthe decision-making modelling purpose forvaluing variations.

However, the initial inclusion of thearithmetic-sum was to accommodate thecompensation that may be required whenmodelling the "linguistic AND" into a"logical AND", the use of the arithmetic-sumin a collective manner with the other twooperators has increased the overall non-errorrate. Using the normal/Gaussianapproximation to the binomial distribution,the level of agreement resulted from a

20 � RICS Research

Table 3.Hypotheses test result

Min-max Arithmetic sum Algebraic product- Combination of operator -max operator max operator three operators

0.712 0.479 0.685 0.767Z 1.955 -2.11 1.48 2.91Z0.1 1.28 1.28 1.28 1.28Result Reject Ho Accept Ho Reject Ho Reject Ho

Page 21: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

collective use of the three aggregationoperators with a non-error rate of 76.7% hasa probability of p<<0.001 which issignificantly better than by chance.Therefore, it was decided to include thethree operators to generate an optimal resultfrom the modelling. Based on an analysisexplained in Sutrisna and Potts (2004), theuse of multiple experts/decision-makers canbe performed by applying a simple majorityrule. Thus, the majority of the decisions

resulted from the modelling process can berecommended to support decision-making inthe valuation of variations.

Furthermore, the analysis also has shownthat the majority of the errors in the resultsfrom the minimum-maximum operator, thearithmetic-sum-maximum operator and thealgebraic-product-maximum operator areunderestimation errors. An underestimationerror means that the model result is LOWwhen the actual decision isMEDIUM/HIGH and/or the result isMEDIUM when the actual decision isHIGH. This discrepancy may be attributableto the "personal biases effect", where inperforming their judgment, the decision-makers do not base their judgments on thelogical form of arguments but rather on whatthey believe should be the results (Revlin andLeirer, 1978). A full-scale exploration on this"personal biases effect", in order to minimisethe effect, covers the logic-field of decision-making area which has been extensivelyresearched within the psychology domain(Slovic, 1969; Johnson, 1972 ; Revlin andLeirer, 1978; Wyer and Podeschi, 1978).However, the "personal biases effect" canonly be explained and there has been noevidence of a satisfactory attempt to modelthe effect. Another explanation for thisdiscrepancy can be sought from the personalaggregation process of the decision attributesknown as the "interaction effects" thatdemonstrates the occurrence of a substantialconfigural processing of the information onthe separate dimension by a human decision-maker (Slovic, 1969; Johnson, 1972). Asimilar effect was also reported by Wyer andPodeschi (1978) who described that the

RICS Research � 21

A decision support tool for the valuation of variations on civil engineering projects

www.rics.org

..decision-makers do not base theirjudgments on the logical form of

arguments but rather on what theybelieve should be the results.

Page 22: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

decision-maker who gives subjectivereactions on a particular matter, in somecases, showed inconsistencies to thecomposite of their reactions to individualattributes of the matter. Therefore,discrepancies in the decisions resulting fromthis research are likely to be caused by thedecision-makers’ biases and/orinconsistencies in sharing their knowledge.

The Resultant Decision

The actual decisions from the decision-makers representing the various projectstakeholders are presented in Figure 3.

A majority of the contractors may haveunderstandably selected high changes, as thisrequires the development of a new rate/priceby fair valuation (i.e. with due profit for thecontractor). However, a majority of theemployers and the engineers/consultants alsoselected high changes. This demonstrated acertain level of convergence on behalf of thevarious decision-makers. Notwithstandingthis, approximately 40% of the decision-makers did not select high changes. Thisdemonstrates the subjectivity involved andthat the changes presented in thehypothetical case study do not implicitlyguide the respondents to choose one of the

decisions whilst demonstrating that otherdecision options were adequately populated.

In order to test whether the decisions weresignificantly influenced by the backgroundsof respondents, i.e. contractors,engineers/consultants or employers, anobjectivity test was performed, namely thenon-parametric chi-square ((X2) test for kindependent samples to measure thedistribution of respondents with differentbackground in answering the questions. Thenon-parametric X2 test for k independentsamples is a straightforward extension of the

non-parametric X2 test for two independentsamples. The results of the decision-makingmodelling are assumed as ordinal data sinceeach question presented a choice of decision-options. Since the frequencies in discretecategories (nominal/ordinal) constitute thedata of research, the X2 test can be used todetermine the significance of the differencesamong k independent groups (Siegel, 1956).As not all of the respondents disclosed theirbackgrounds, 65 responses were used for thepurpose of this objectivity test.

22 � RICS Research

Page 23: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

The hypotheses tests are:

H0: the respondents from each backgroundare not randomly selecting the answers H1: the respondents from each backgroundare randomly selecting the answers Significant level used is α = 0.05 since theerror type I and error type II wereperceived equally significant. The nullhypothesis is rejected if:

X2 < X2a,df

When the X2 is relatively small, the observedfrequencies are in close agreement with theexpected frequencies which means that theproportion of respondents are closer to beingequally distributed for all background andtherefore H0 is rejected. Following the rulesin the non-parametric X2 test for kindependent samples, responses choosingLOW and MEDIUM were combined inorder to achieve sufficient group members.Results of the test are presented in Table 4.

The results demonstrate that respondentsfrom each background were randomlychoosing HIGH and other options(MEDIUM or LOW) and none of theoptions can be typically associated to anyparticular stakeholder.

The nature of changes in the variation eventin the hypothetical case study wereconsidered HIGH, by a majority of thedecision-makers. Therefore, in accordancewith the simple majority rule applied in thisdecision-making tool, new rates/prices forthis particular excavation works based on afair valuation can be recommended as anappropriate outcome in view of thesecircumstances, i.e. favouring Clause 53(3)(b)from the ICE Conditions of ContractMeasurement Version, 7th edition, 1999.

RICS Research � 23www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Category N df X2 X2 a, df Description

LOW/MEDIUM/ 65 2 0.47 5.99 Respondents from HIGH each background

are randomlychoosing betweenHIGH and otheroptions (MEDIUMor LOW).

Table 4. Results of non-parametricX2 test for k independent samples

Page 24: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

subsequent data analysis have beenpresented. The subjectivity of the decision-makers has been analysed. It has beendemonstrated that the background of thedecision-makers (i.e. contractors,consultants/engineers, or employers) did notsignificantly affect their decisions, as none ofthe decisions can be typically associated withany of the decision-makers groups.

An exploration of performance of eachproposed fuzzy-aggregation operators and thedecision-making tool has been described.Based on the results, the use of all threefuzzy-aggregation operators (i.e. minimum-maximum, arithmetic-sum, and algebraic-productoperators) were concluded appropriate andcan be recommended to represent the"semantic AND" in the valuation ofvariations.

The level of agreement resulted from acollective use of the three aggregationoperators proposed here is significantly

The valuation of variations has beenacknowledged as one of the commonestcauses of conflict and disputes. Referring tothe rules of valuing variations provided bythe ICE Conditions of ContractMeasurement Version, 7th edition, 1999, apotential problem is the subjectiveinterpretation of the human decision-makerin interpreting the changes in the workcondition and/or work characteristicsoccurring as a result of a variation event.

Frameworks for valuing variations inexcavation works and in concrete works havebeen previously reported, as has a feasibilitystudy of using a KBS for the valuation ofvariations. In tackling further difficulties inknowledge acquisition and representation,the conceptualisation of applying fuzzy-logicas an inference mechanism in order to modelthe decision-making in valuing variations hasalso been performed.

The results of the questionnaire survey and

Conclusion

24 � RICS Research

...the system is capable of providing a consistent and objectiverecommendation of the most appropriate decision.

Page 25: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

better than by chance and way above thethreshold set for acceptance. Therefore, it canbe concluded that the decision-makingsupport tool developed is capable ofreplicating human decision-making processin the valuation of variations. Therefore, theapplication of fuzzy-logic principles wasfound to be appropriate for this problemarea and is to be used in a subsequentdevelopment of this research as a platformfor developing a KBS for the valuation ofvariations.

The decision-making modelling reported inthis paper has provided a robust algorithmfor the subsequent development of a KBSaimed to reduce conflicts and disputes in thevaluationof variations, particularly on civilengineering works. Thus, by including themodels of the decision-making process of theexperts/decision-makers in the KBS, thesystem is capable of providing a consistentand objective recommendation of the mostappropriate decision (i.e. LOW, MEDIUM,or HIGH) for various project conditionsinputted by the user of the system. Thedevelopment of the KBS intends to provideassistance and support to the projectstakeholders (i.e. contractors, consultants andemployers) in deciding the appropriatenessof the rate/price in the bill of quantity to beapplied to value a particular variation. At themoment of preparing this paper, a prototypeversion of the KBS has been developed. Thisprototype has been demonstrated topractitioners in the UK construction industry.The responses from practitioners are

generally supportive and various inputs andfeedbacks for further development of theKBS have been obtained and will bereported in subsequent publications.

RICS Research � 25www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Page 26: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

Fenn, P., Lowe, D. & Speck, C. (1997).Conflict and dispute in construction.Construction Management and Economics15: 513-518.Hanna, A. S., Russell, J. S. & Vandenberg, P.J. (1999a). The impact of change orders onmechanical construction labour efficiency.Construction Management and Economics17: 721-730.

Hanna, A. S., Russell, J. S., Nordheim, E. V.& Bruggink, M. J. (1999b). Impact of ChangeOrders on Labor Efficiency for ElectricalConstruction. Journal of ConstructionEngineering and Management 125(4): 224-232.

Haswell, C. K. (1963). Rate Fixing in CivilEngineering Contracts. In: Proceeding ofInstitution of Civil Engineering (February)24: 223-34.

Hibberd, P.R. (1980). Building Contract-Variations. Unpublished MSc thesis.Manchester: UMIST.

Hibberd, P. R. (1986) Variations inConstruction Contracts. London: Collins.

Hruschka, H. (1988). Use of fuzzy relationsin rule-based decision support system forbusiness planning problems. EuropeanJournal of Operational Research 34: 326-335.

Ahlgren, A. & Walberg, H. J. (1979).Generalised regression analysis. In: Bynner,J. & Stribley, K. M. (Editors). SocialResearch, Principles and Procedures.London: Longman.

Akinsola, A.O. (1997). An Intelligent Modelof Variations' Contingency on ConstructionsProjects. Unpublished PhD thesis.Wolverhampton: University ofWolverhampton.

Barnes, N. M. L. (1971). Civil engineeringbills of quantities. Report to CIRIA onResearch Project No. 98. Manchester:Department of Civil and StructuralEngineering, UMIST.

Boshoff, G. (2002). Fuzzy Logic.www.developers-resources.com/stories/02/05/03/4739250 viewed: 21/11/02.DeVaus, D. A. (1996). Surveys in SocialResearch (4th Edition). London: UCL Pressand Allen & Unwin.

Dorter, J. (1990). Variations. ConstructionLaw Journal 7(4): 281-302.

Dubois, D. & Prade, H. (1980). Fuzzy Setsand System: Theory and Applications. NewYork: Academic Press.

References

26 � RICS Research

Page 27: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

Johnson, D. M. (1972). A SystematicIntroduction to the Psychology of Thinking.New York: Harper & Row Publisher, Inc.Kvanli, A. H., Pavur, R. J., Guynes, S. (2000).Introduction to Business Statistic (5thEdition). Ohio: South-Western CollegePublishing.

Latham, M. (1994). Constructing The Team.London: HMSO.

McGowan, P. H., Malcolm, R., Horner, W.,Jones, D. & Thompson, P. A. (1992). Allocation and Evaluation of Risk inConstruction Contracts. CIOB OccasionalPaper No. 52. Ascot: The Chartered Instituteof Building.

Mendel, J. M. (2001). Uncertain Rule-BasedFuzzy Logic Systems: Introduction and NewDirections. Los Angeles: Prentice Hall.

Miyamoto, A. (2000). A Shot Course forFuzzy Set Theory. In: Liu, Z. Q. &Miyamoto, A. (Ed.). Soft Computing andHuman-Centered Machines. Tokyo:Springer-Verlag.

Potts, K. F. (1995). Major ConstructionWorks: Contractual and FinancialManagement. Essex: Longman Scientific &Technical.

Prodanovic, P. (2001). Fuzzy Set RankingMethods and Multiple Expert DecisionMaking. Unpublished report, London: TheUniversity of Western Ontario.

Proverbs, D. G. (1998). A Best PracticeModel for High-rise Insitu ConcreteConstruction Based on French, German andUK Contractor Performance Measures.Wolverhampton: Unpublished PhD thesis,University of Wolverhampton.

Revlin, R. & Leirer, V. O. (1978). The effectsof personal biases in syllogistic reasoning:rational decision from personalisedrepresentation. In: Revlin, R. & Mayer, R. E.(Editors). Human Reasoning. New York:John Wiley & Sons.

Royal Institution of Chartered Surveyors(2003). Contracts in use: a survey of buildingcontracts in use during 2001. London. RICS.

Seeley, I. H. & Murray, G. P. (2001). CivilEngineering Quantities (6th Edition). NewYork: Palgrave.

Siegel, S. (1956). Nonparametric Statistics forthe Behavioral Sciences (InternationalEdition). Tokyo: McGraw-Hill Kogakusha.

Slovic, P. (1969), Analysing the expert judge:A descriptive study of a stockbrocker’sdecision processes. Journal of appliedPsychology 53: 255-263.

Sutrisna, M & Potts, K. (2003a). ValuingVariations in Excavation Works: a ProposedFramework. In: 3rd InternationalPostgraduate Research Conference. Lisbon,3-4 April 2003. Aouad, G. & Ruddock, L.(Editors). Salford: University of Salford, pp.499-510.

RICS Research � 27www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Page 28: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

Sutrisna, M. & Potts, K. (2003b). A ProposedResearch Methodology for Developing aSystematic Approach on Valuing Variations.In: 1st Scottish Conference for PostgraduateResearchers in the Built & NaturalEnvironment. Glasgow, Egbu, C & Tong, M.(Editors). Glasgow: Glasgow CaledonianUniversity, pp. 467-478.

Sutrisna, M., Potts, K. & Proverbs, D.(2003a). Development of a framework forvaluing variations in concrete works. In: 2ndInternational Structural Engineering andConstruction Conference. Rome, 23-26September 2003. Bontempi, F. (Editor).Lisse: Swets & Zeitlinger, pp. 129-136.

Sutrisna, M., Potts, K. & Buckley, K. (2003b).An Expert System as a Potential Decision-making Tool in the Valuation of Variation.In: 2003 COBRA Conference.Wolverhampton, 1-2 September 2003.Proverbs, D. (Editor). London: RICSFoundation, pp. 314-326.

Sutrisna, M., Potts, K. & Proverbs, D.(2003c). A Novel Approach TowardsDecision-Making in the Valuation ofVariations. In: 2nd International Conferenceon Innovation in Architecture, Engineeringand Construction. Loughborough, 25-27 June2003. Anumba, C. (Editor). Rotterdam:Millpress, pp. 431-440.

Sutrisna, M. & Potts, K. (2004). Using

Multiple Decision-Makers for ValuingVariations in Civil Engineering Works. In:3rd Scientific Conference on ProjectManagement. Thessaloniki, 23-24 September2004 (Accepted).

The Aqua Group (1996). ContractAdministration for the Building Team (8thEdition). Oxford: Blackwell Science Ltd.The Institution of Civil Engineers, TheAssociation of Consulting Engineers & TheCivil Engineering Contractors Association(1999). ICE Conditions of Contract:Measurement Version (7th Edition). London:Thomas Telford.

Umbers, I. G. & King, P. J. (1981). Ananalysis of human decision-making incement kiln control and the implication forautomation. In: Mamdani, E. H. & Gaines,B. R. (Editors). Fuzzy Reasoning and itsApplications. London: Academic Press, pp.369-381.

Willis, C. J., Ashworth, A. & Willis, J. A.(1994). Practice and Procedure for theQuantity Surveyor (10th Edition). Oxford:Blackwell Science Ltd.

Winter, J. (2002). Valuations of variationsunder the ICE Conditions of Contracts-theThrills & Spills of tendering.www.bakerinfo.com/documents/ 837_tx.htm,viewed: 22/01/02.

Wyer, Jr., R. S. (1978). The acceptance ofgeneralization about persons, objects, andevents. In: Revlin, R. & Mayer, R. E.

28 � RICS Research

Page 29: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

(Editors), Human Reasoning. New York:John Wiley & Sons.

Xiao, H. (2002). A Comparative Study ofContractor Performance Based on Japanese,UK and US Construction Practice.Unpublished PhD thesis. Wolverhampton :University of Wolverhampton.

Yager, R. R. (2000). Aggregation Operationsfor Fusing Fuzzy Information. In: Liu, Z. Q.& Miyamoto, S. (Editors). Soft Computingand Human-Centered Machines. Tokyo:Springer-Verlag, pp. 163-184.

Zadeh, L. A. (1965). Fuzzy Sets. InformationControl 8: 338-353.

Zadeh, L. A. (1973). Outline of a newapproach to the analysis of complex systemsand decision processes. IEEE Transaction ofSystem, Man, and Cybernetics, SMC-3 (1):28-44.

Zimmermann, H. J. (1987). Fuzzy Sets,Decision-making & Expert System. Boston:Kluwer.

Law cases cited:

1) Dudley Corporation v. Parsons & MorrinLtd (1959) Building Contract Casebook 41(1984), Building Industry News (17 Feb.1967)

2) Henry Boot Construction Ltd. v. AlstomCombined Cycles Ltd (2000) 16 Const.L.J. 6

RICS Research � 29www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Page 30: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

The hypothetical project is a pumping station as shown in Appendix A. The pumping station willsupply hydrant water for a newly built factory. A contractor has been selected.• Location of pumping station: southwest part of the factory premises. • The contract is based on the ICE 7th edition, Measurement version, 1999. CESMM 3 applies. • The total lump sump project value including the supply and installation of the pumps, electricaland all plumbing inside the pumping station is £ 245,000 • To be completed in 4 months, from July to October. • The excavation work, to be executed as the earliest activities, is quoted:

Just one month before the execution, the employer, through his Engineer, instructed the project to bevaried. The pumping station is now to be built in the northeast part of the factory and withadditional 1 m depth. Since the contractor has not yet mobilised his team, there are no standingcharges. However, several changes have occurred as the result of the variation order.

• The initial methodology for excavation is battered open-cut. However since the new location is tooclose to adjacent structures, two sides of the excavation now requires steeper sides to the excavation,therefore requiring wire mesh as slope support.• The intended new location is still occupied by another contractor; the new location will be readyby November. As previously mentioned, there are no standing charges. However, the contractor isnow excavating in the autumn-winter period. The rainfall is anticipated to be 75% higher than insummer time and necessitates steel platforms to be provided for the plant to work in the muddyconditions.• The excavation is now 1 m deeper and the ground water level in the new location is higher; it isrequired to have pumping to provide a dry condition for excavation.• The ground condition in the new location is not really similar to the initial location. From theinvestigation it was found that the swelling factor is now higher and causes significant additionaldisposal. The type of the soil has also changed from a softer type of clay to a stiffer type of clay thatnecessitates the contractor to up-grade the excavator plant type to maintain his rate of productivity.

Appendix 1. The hypothetical casepresented in the questionnaire

30 � RICS Research

Excavation for foundation, max depth 5 – 10 m @ £ 20.45 1076 m3 £ 22,004.20

The breakdown of the excavation work is as follows:

Programme 40 working daysLabour £ 7,500.00Plant £ 8,500.00Material £ 3,500.00Sundry Charges £ 2,504.20

Page 31: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

These changes has resulted in this following aaddddiittiioonnaall ccoosstt to the contractor: (Changes in Programme are in days and assumed to represent the additional overhead)

Changes in Programme

Changes in Labour

RICS Research � 31www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

EEvveennttss Programme Labour Plant Materials Sundry Charges

1.Wire mesh slope support 3 days £ 250 £ 275 £ 375 -

2.Reduced productivitydue to rain 4 days - - - -

3.Steel platform forplant due to rain - £ 150 £ 75 £ 115 -

4.Pumping - £ 75 £ 150 - -5.Additional soil

disposal - - - - £ 4006.Excavator up-grade - - £ 450 - -

TTOOTTAALL 77 ddaayyss ££ 447755 ££ 995500 ££ 449900 ££ 440000

Page 32: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

Appendix 2. Decision results from allrespondents

32 � RICS Research

Appendix 2. Decision result from all respondents

RReessppoonn-- MMiinn--mmaaxx AArriitthhmmeettiicc ssuumm-- AAllggeebbrraaiicc pprroodduucctt-- MMooddeell AAccttuuaall ddeennttss ooppeerraattoorr mmaaxx ooppeerraattoorr mmaaxx ooppeerraattoorr ddeecciissiioonn ddeecciissiioonn

1 HIGH MED HIGH HIGH HIGH2 LOW/MED MED LOW/MED MED MED3 HIGH MED LOW Inconclusive HIGH4 HIGH LOW LOW LOW HIGH5 MED MED MED MED MED6 HIGH HIGH HIGH HIGH HIGH7 MED MED MED MED MED8 MED HIGH MED MED MED9 MED LOW MED MED MED10 MED MED HIGH MED MED11 HIGH HIGH HIGH HIGH HIGH12 LOW LOW LOW LOW LOW13 MED/HIGH HIGH MED/HIGH HIGH HIGH14 MED MED MED MED MED15 LOW LOW LOW LOW HIGH16 HIGH MED HIGH HIGH HIGH17 LOW MED HIGH Inconclusive HIGH18 LOW/MED LOW LOW/MED LOW HIGH19 MED/HIGH HIGH MED/HIGH HIGH MED20 HIGH HIGH HIGH HIGH HIGH21 LOW LOW LOW LOW HIGH22 LOW LOW LOW LOW MED23 LOW LOW LOW LOW LOW24 MED MED MED MED MED25 LOW LOW LOW LOW LOW26 MED LOW MED MED MED27 LOW/MED LOW LOW/MED LOW HIGH28 HIGH MED HIGH HIGH HIGH29 Inconclusive MED Inconclusive MED HIGH30 HIGH HIGH LOW HIGH HIGH31 LOW LOW LOW LOW LOW32 LOW LOW LOW LOW LOW33 HIGH HIGH HIGH HIGH HIGH34 LOW/HIGH HIGH LOW/HIGH HIGH HIGH35 HIGH HIGH HIGH HIGH HIGH36 Inconclusive HIGH Inconclusive HIGH HIGH37 HIGH LOW HIGH HIGH HIGH38 HIGH MED HIGH HIGH HIGH39 MED MED MED MED MED40 HIGH LOW HIGH HIGH HIGH

Page 33: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

RICS Research � 33www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

RReessppoonn-- MMiinn--mmaaxx AArriitthhmmeettiicc ssuumm-- AAllggeebbrraaiicc pprroodduucctt-- MMooddeell AAccttuuaall ddeennttss ooppeerraattoorr mmaaxx ooppeerraattoorr mmaaxx ooppeerraattoorr ddeecciissiioonn ddeecciissiioonn

41 LOW LOW LOW LOW LOW42 HIGH LOW HIGH HIGH HIGH43 MED MED MED MED MED44 LOW LOW LOW LOW LOW45 MED MED MED MED MED46 LOW LOW LOW LOW HIGH47 HIGH HIGH HIGH HIGH HIGH48 HIGH HIGH HIGH HIGH HIGH49 HIGH MED HIGH HIGH HIGH50 HIGH MED HIGH HIGH HIGH51 LOW LOW LOW LOW MED52 HIGH HIGH HIGH HIGH HIGH53 HIGH MED HIGH HIGH HIGH54 MED MED LOW MED MED55 HIGH MED HIGH HIGH HIGH56 MED MED HIGH MED HIGH57 HIGH MED HIGH HIGH HIGH58 HIGH MED HIGH HIGH HIGH59 LOW LOW LOW LOW HIGH60 LOW LOW LOW LOW LOW61 HIGH MED HIGH HIGH HIGH62 LOW/HIGH HIGH HIGH HIGH HIGH63 HIGH MED HIGH HIGH HIGH64 LOW MED LOW LOW HIGH65 MED LOW MED MED MED66 HIGH MED MED MED MED67 MED MED MED MED MED68 HIGH MED LOW Inconclusive HIGH69 HIGH MED HIGH HIGH HIGH70 MED/HIGH HIGH MED/HIGH HIGH HIGH71 MED MED MED MED MED72 LOW LOW LOW LOW HIGH73 HIGH MED HIGH HIGH HIGH

Appendix 2. Decision result from all respondents......continued

Page 34: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

SSaammppllee ooff ccaallccuullaattiioonn uussiinngg tthhee fuzzy-sets

Respondent Number: 67

Position in the organisation: Quantity surveyor/project manager

Type of organisation: Contractor

Experience: 15 years

Further contribution : Yes

Changes in Programme

C2 = C3, C3<u<C4, therefore,Membership functions:

34 � RICS Research

Page 35: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

Changes in labour

C1 = 0, C1<u<C2, therefore,Membership functions:

RICS Research � 35www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Page 36: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

Changes in Plant

C1 = 0, C2<C3, therefore,Membership functions:

Changes in Material

36 � RICS Research

Page 37: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

C1 <u<C2, therefore,Membership functions:

Changes in Sundry Cost

C2 = C3, C1<u<C2, therefore,Membership functions:

RICS Research � 37www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Page 38: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

38 � RICS Research

Summary of the results

Minimum-Maximum operator:µLowTotal(u) = min {µLOW(u1), µLOW(u2), µLOW(u3), µLOW(u4), µLOW(u5)}

= 0.1µMediumTotal(u) = min {µMEDIUM(u1), µMEDIUM(u2), µMEDIUM(u3), µMEDIUM(u4), µMEDIUM(u5)}

= 0.6µHighTotal(u) = min {µHIGH(u1), µHIGH(u2), µHIGH(u3), µHIGH(u4), µHIGH(u5)}

= 0.25

Membership functions [µ(u) ] LOW MEDIUM HIGH Respondent’s actual decision:

Changes in Programme - 0.75 0.25 MEDIUMChanges in Labour 0.37 0.63 - MEDIUMChanges in Plant - 1 - MEDIUMChanges in Material 0.1 0.9 - MEDIUMChanges in Sundry-Cost 0.4 0.6 - MEDIUM

Page 39: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

DDeecciissiioonn = LOW OORR MEDIUM OORR HIGH= max {µLowTotal(u), µMediumTotal(u), µHighTotal(u)}= 0.6= MEDIUM

Arithmetic-sum Maximum operator: µLowTotal(u) = {µLOW(u1)+ µLOW(u2)+ µLOW(u3)+ µLOW(u4)+ µLOW(u5)}

= 0.87µMediumTotal(u) = {µMEDIUM(u1)+ µMEDIUM(u2)+ µMEDIUM(u3)+ µMEDIUM(u4)+ µMEDIUM(u5)}

= 3.88µHighTotal(u) = {µHIGH(u1)+ µHIGH(u2)+ µHIGH(u3)+ µHIGH(u4)+ µHIGH(u5)}

= 0.25

DDeecciissiioonn = LOW OORR MEDIUM OORR HIGH= max {µLowTotal(u), µMediumTotal(u), µHighTotal(u)}= 3.88= MEDIUM

Algebraic-product Maximum operator:µLowTotal(u) = {µLOW(u1)� µLOW(u2)� µLOW(u3)� µLOW(u4)� µLOW(u5)}

= 0.0148µMediumTotal(u) = {µMEDIUM(u1)� µMEDIUM(u2)� µMEDIUM(u3)� µMEDIUM(u4)� µMEDIUM(u5)}

= 0.3402µHighTotal(u) = {µHIGH(u1)� µHIGH(u2)� µHIGH(u3)� µHIGH(u4)� µHIGH(u5)}

= 0.25

DDeecciissiioonn = LOW OORR MEDIUM OORR HIGH= max {µLowTotal(u), µMediumTotal(u), µHighTotal(u)}= 0.3402= MEDIUM

RICS Research � 39www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Page 40: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

Summary of decision results

40 � RICS Research

Respondent’s actual decision: MEDIUM

Minimum-Maximum operator: MEDIUMArithmetic-sum Maximum operator: MEDIUM Overall: MEDIUMAlgebraic-product Maximum operator: MEDIUM

Page 41: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

RICS Research � 41www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Page 42: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

Submission of papers

The RICS encourages academics and other

researchers to submit work that is relevant to the

discipline of surveying in all its fields. Authors

may submit either by post or by email. In the first

instance, submissions should be made to the

RICS. Postal submissions should be made in

triplicate to:

Stephen Brown

Head of Research

Royal Institution of Chartered Surveyors

12 Great George Street

London SW1P 3AD

UNITED KINGDOM

Email submissions of Word or PDF files should be

sent to [email protected]

Telephone number for enquiries:

+44 (0)20 7334 3725

The refereeing process is double blind and all

submitted papers will be referred to at least two

reviewers.

The manuscript

There is no fixed limit on the length of papers

and each paper is published as:

� A PDF on the RICS website, with no charge

made for download.

� A stand-alone published document

Papers are placed on the RICS website

immediately that they are completed and printed

copies available shortly thereafter.

While there is no word limit, it is anticipated that

papers would be no less than 5,000 words and

generally no more than 30,000 words.

The manuscript must be in English, typed in

double spacing on one side of A4 paper only, with

a 4 cm margin on the left-hand side. The pages

should be numbered consecutively. There should

be no loose addenda or notes or other

explanatory material.

Title page

The first page of the manuscript must contain the

full title: the name(s), affiliation(s), address(es) of

the author(s); a title of not more than 75

characters and spaces; and five key words for the

purpose of indexing. If there is more than one

author, the corresponding author should be

indicated.

The abstract

The second page should contain the title and an

abstract. It should not contain the name(s) of the

author(s). The abstract should not exceed 200

words and must be a clear summary of the

contents of the manuscript, indicating the

contribution that the paper makes to knowledge

and providing a clear statement of the key

findings and outcomes of the paper.

Illustrations

Any illustrations must accompany the manuscript

but should not be included in the text. Diagrams,

charts, photographs and maps, should be referred

to as 'Figure 1', 'Figure 2' and so on. They should

be numbered in the order in which they are

referred to in the text.

Illustrations can be colour or monochrome. When

providing electronic version of illustrations, please

ensure that these are of a sufficient resolution for

reproduction. A resolution of 300 dots per inch is

the minimum acceptable standard for images.

RICS research paper series

42 � RICS Research

Page 43: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

They will normally be reduced in size on

reproduction and authors should bear this in

mind, particularly when selecting font sizes.

Appropriate electronic submission is permissible.

Proofs

Proofs, in the form of a PDF file, will be sent to

the corresponding author for correction and

approval. The website is used to provide ongoing

comment and feedback on papers that are posted

on the website, and comments that are provided

will be passed through to the corresponding

author. Authors are provided with ten free copies

of their paper. Further copies can bought at a

price of £2.00 each.

Publicity

The aim of the RICS is to ensure that papers are

promoted and publicised to appropriate

academic, professional, policy and media

audiences. In pursuit of this, the RICS may seek

to develop and issue supporting material for

papers published, such as press releases and

summary documents. The RICS will liaise with

the corresponding author on the drafting of this

material and on the appropriate degree of

involvement of the author in this process.

References

The Harvard system should be used. References

in the text should be quoted in the following

manner: Jones (1999) or (Edge and Moody, 2001)

or, if there are more than two authors ... Thomas

et al. (2002). If there is a citation of a page

number or numbers, the format should, as

appropriate, be Smith (1999, 20), Smith (1999, 20-

5), (Smith, 1999,20) or (Smith, 1999, 20-5).

References should be collected at the end of the

paper in alphabetical order by the first author's

surname. If references to the same author have

the same year, they should be differentiated by

using 1998a, 1998b and so on. The style should

follow the examples below:

Chau, K.W., MacGregor, B.D. and Schwann, G.

(2001) Price discovery in the Hong Kong real

estate market, Journal of Property Research, 18(3),

187-216.

Brown, G.R. and Matysiak, G.A. (2000) Real

estate investment - a capital markets approach,

Financial Times Prentice Hall, Harlow.

If no person is named as the author the body

should be used, for example:

Royal Institution of Chartered Surveyors (1994)

Understanding the property cycle, London.

Copyright

Submission of an article to the RICS Paper Series

is taken to imply that it represents original,

unpublished work, not under consideration for

publication elsewhere. When submitting a

manuscript, authors will be asked to transfer the

copyright for their article to the Royal Institution

of Chartered Surveyors, if and when the article is

accepted for publication. The Royal Institution of

Chartered Surveyors will not refuse any

reasonable request by the author for permission to

reproduce any of his or her contributions to the

series in other forms.

Permission to publish illustrations must be

obtained by the author before submission and any

acknowledgements should be included in the

figure captions.

RICS Research � 43www.rics.org

A decision support tool for the valuation of variations on civil engineering projects

Page 44: A decision support tool for the valuation of variations on ...RICS Research RICS Research paper series Volume 5, Number 7 May 2005 Monty Sutrisna, Kevan Buckley, Keith Potts and David

The Royal Institution

of Chartered Surveyors

12 Great George Street

Parliament Square

London SW1P 3AD

United Kingdom

T +44 (0)870 333 1600

F +44 (0)20 7334 3811

[email protected]

www.rics.org

RICS (Royal Institution of Chartered Surveyors) is the largest professional

body for property, land, construction and related environmental issues

worldwide. We are the leading source of property related knowledge

promoting best practice and consumer protection, and providing

impartial advice to governments, business and the public.

Ma

y 2

00

5/R

esea

rch

/20

0/5

01

92

/J.M

cDo

na

gh

www.rics.org