Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
DRO Deakin Research Online, Deakin University’s Research Repository Deakin University CRICOS Provider Code: 00113B
A decision-making formula for value engineering applications in the Sri Lankan construction industry
Citation of the final article: Karunasena, Gayani and Rajagalgoda Gamage, Kosala 2017, A decision-making formula for value engineering applications in the Sri Lankan construction industry, Journal of financial management of property and construction, vol. 22, no. 1, pp. 77-91.
DOI: http://www.dx.doi.org/10.1108/JFMPC-01-2016-0001
This is the peer reviewed accepted manuscript.
© 2017, Emerald Group Publishing
Reproduced with permission.
Downloaded from DRO: http://hdl.handle.net/10536/DRO/DU:30100218
1
DECISION MAKING FORMULA FOR VALUE ENGINEERING APPLICATIONS
ABSTRACT
Purpose - Construction industry in many developing countries is reluctant to apply Value
Engineering (VE) due to uncertainty of outcomes. Thus, the purpose of this paper is to examine
existing practices of VE techniques and make recommendations to organisations and national
construction regulatory bodies to standardise VE practices to achieve value for money for all
stakeholders. Further, a decision making formula is introduced to determine profitability of VE
applications prior to implementation.
Methodology - A broad literature review consisting of six case studies with 39 semi structured
interviews and six experienced professional’s interviews were conducted with construction
professionals having extensive knowledge on VE techniques in Sri Lanka, to gather data.
Building projects which applied VE were selected as case studies. Content analysis and cognitive
mapping were used to analyse data within case studies.
Findings - Findings revealed that application, knowledge and experience on VE techniques
among construction professionals is unsatisfactory. Recommendations include reducing
contractor’s design responsibility, introducing proper VE guidelines and statutory regulations.
Accordingly, a framework is introduced with recommendations to assist authorities to
standardise application of VE techniques. Finally, a decision making formula is suggested to
determine margins of contractor’s portion due to VE techniques and original profits gained.
Value - The formula can be used as a decision making tool by construction industry practitioners
to determine successfulness of proposed VE techniques and proposed framework can be used to
guide construction professional bodies to standardise VE practices to achieve value for money.
Keywords: Construction Industry; Decision making formula; Framework; Value; Value
Engineering.
1. INTRODUCTION
“The construction industry can be differentiated from other industries by its organisation and
products, stakeholders, projects, processes and operating environment,” (National Research
Council, 2009). The development of construction industry is based on government decisions,
2
procedures and regulations which has an obvious relationship with value for money
(Wijewardana et al., 2013).
Enhancing value of a project can create a worthy positive impact on the economy of a country (Rameezdeen and De Silva, 2002). Zhang et al (2009) said that VE is the most appropriate technique to regulate value in construction projects, as other techniques focus on time and quality than value. Many researchers contend that VE is a systematic method to elevate value of goods, products and services by undertaking an investigation of intention (Miles 1972; Parker 2001;Zar et al., 2011). Gudem et al (2013) stated that by implementing VE in projects cost can be reduced up to 26%, enhance operational performance by 40-50% and upgrade product quality by 30-50%. However, literature revealed that construction sector of most countries including Sri Lanka are reluctant to implement VE in projects due to lack of awareness among clients, uncertainty of outcomes, additional costs involved, lack of government support, more time consumed, lack of expertise, lack of regulations and policy applications (Kosala and Karunasena, 2015; Senarathne et al., 2014; Atmo and Duffield, 2014 ; Iran and Iyer, 1984; Mansour and Abueusef, 2015 ). In this context, this paper presents an overview of real practices of VE techniques in Sri Lankan
construction sector and provide recommendations to standardise VE practices to facilitate
achievement of value for money by all stakeholders. The research data was limited to building
projects which applied VE techniques in Sri Lanka and the paper consists of literature findings,
details on research methodology adopted and findings of real practices of VE applications,
recommendations to standardise and decision making formula.
2. LITERATURE SYNTHESIS: VALUE ENGINEERING AND CONSTRUCTION INDUSTRY
Value is a subjective term and is conspicuous in various ways such as desire, attitude, preference
need, criteria and belief (Leung and Liu, 2003). Thiry (2001) stated that value has several
definitions for various people, “best buy” for a customer, “the lowest cost” for a manufacturer
and “highest functionality” for a designer. “Without understanding the customer, the concept of
value is undefined, and without a tangible concept of value, waste is even more intangible”
(Bertelsen and Emmitt, 2005, p.74).
A fundamental issue for construction firms is to guarantee value in projects (Lozon and Jergeas,
2008). Kliniotou (2004) stated that various value measuring techniques can be found in industrial
sectors such as value management (VM), benchmarking, total quality management, financial
management techniques, cost-benefit analysis, supply chain management, project management,
whole life cycle costing and earned value management.
Among these, VM is a unique application designed through the process of project value
measuring technique (Stenstrom et al, 2013). VM has great accuracy over other techniques
because all factors which affect value of a product are considered (Kelly et al, 2004). VM
ensures that construction value wanted by the client along with many processes such as public
3
relations, timeline and good neighbourship (Salvatierra-Garrido and Pasquire, 2011). According
to Potts (2008) and Male et al. (1998), systematic operation of VM can be simply separated into
three prime techniques, specifically Value Planning, VE and Value Analysis to certify that value
is conveyed to the project in an adequate manner.
VE is a disciplined and creative method which intends to submit a client with a trustworthy
opportunity for cost savings without detriment to quality or performance (Miles, 1972).
According to Othman (2008) and Fan and Shen (2011), VE investigates, analyses, compares and
selects amidst various alternatives to generate the desired function and encounter or surpasses
customer goals and expectations. Abidin and Pasquire (2007) said that VE is acknowledged as a
paramount contrivance in the management of construction projects all over the world.
VE has been progressively implemented in UK construction industry since 1980 and in
Malaysian since 1986, expanding and adjusting direction of its objectives over the years (Kelly
et al., 2004). The application of VE in USA became famous in 1993 with the introduction of two
bills that made the process mandatory for all government programmes (Fong and Shen, 2000). In
1996 President Clinton signed into law an act accommodating all executive agencies to establish
VE procedures and estimated savings were forecasted at $2.19 billion for 1996 (Thiry, 2001),
according to Shen and Liu (2004) when VE was introduced to Chinese construction industry in
1978.
Chen et al. (2010) has observed that, VE studies frequently result in a 10% to 30% diminution in
total cost of a project and often have an intense outcome on ultimate design. Vorakulpipat et al.
(2010) concurs noting that, when VE is carried out during the early phase of design, it can see a
10% to 30% reduction in total costs. For an example, taxpayers were released in the order of $ 1
billion alone in US Highways and Transportation Departments due to the application of VE
techniques (Jaapar et al., 2012). Dell’Isola (1997) yields typical VE savings as follows:
In construction programmes to a value of €10 million, savings typically range from 3 to
10 times the VE effort.
In programmes from €10-75 million, savings range from 5 to 15 times the effort.
In programmes over €75 million, savings range from 10 to 20 times the effort.
Bone and Law (2002) indicated that there are number of merits which a project can attain by
implementing VE during its project life. Bowman and Ambrosini (2010) have also introduced
several benefits of VE for construction projects such as, parties can get an opportunity to engage
in advancement of a project, elevated competitiveness and profitability, can get a full authorised
review of the total project, can generate a continuous improvements in quality and performance,
4
quantum increases in productivity of a project, diagnose and accommodate with project
betterments and crystalizes an organiser’s brief or project predominance. According to Hamilton
(2002), improved identification of merits of VE has caused for the affluence of market level in
worldwide.
Lack of flexibility, support, knowledge and awareness of VE in some regions are basis for its
minimal implementation (Cheah & Ting, 2005). Zhang et al (2009) stated that, participants can
get a negative and sometimes argumentative impression of VE with engineers searching to avoid
the obligation of design modifications by contractors and non-engineers, assuming the
expenditure and time of developing. The effect is that, they only suppose developing suggestions
with a particularly high cost reduction capability thereby reasoning the high cumulative impact
of minor savings to be lost (Vorakulpipat et al., 2010).
When price becomes the differentiator, all contractors want to be the lowest in bid, regardless of
the original scope of work (Kashiwagi, 2011). A transparent, fair and open procurement system
can attract contractors that can provide optimum arrangement of quality and whole life cost
(Phillips et al., 2007). Kashiwagi et al. (2009) stated that, if a contractor is forced and pressured
to submit the lowest possible price proposal, which will not raise the level of performance with
lowest labour, material and tighter inspection. For better VE proposals authorities should have
clear procedures, procurement strategies and policies (Phillips et al., 2007). Further, client and
consultant should provide freedom by bearing risk (Ratnasabapathy and Rameezdeen, 2007). In
general, clients and consultants minimise risk by using price based environment and value based
environment (Kashiwagi and Kashiwagi, 2011). Value based environment include involvement
of less parties and more efficiency, transparency, maximum accountability, minimisation of
project cost and time deviation where price based environment take the opposite.
According to Luu et al. (2003) VE applications is influenced by client requirements, client
characteristics, project characteristics and external environment. Client requirements can be
considered as the major criteria, where it will certainly help a client to make a project successful
by satisfying client needs and priorities (Ratnasabapathy and Rameezdeen, 2007). Chan et al.
(2001) argued that since client is the ultimate owner of a project, not only client’s requirements
but also characteristics should be considered. In addition, due to unique characteristics of each
construction project, most researchers have emphasised that project characteristic should also be
considered (Alhazmi and McCaffer, 2000). The rationale is different projects will have varying
degrees of complexity (Chan et al., 2001). Similarly, projects operate in different external
5
environments (Ratnasabapathy and Rameezdeen, 2007) and selection of a VE technique is
directly influenced by external environment factors (Luu et al., 2003).
With overview of VE applications in construction, next paragraphs will present detailed
procedure adopted for data collection and analysis.
3. RESEARCH METHODOLOGY
This study adopted qualitative research approach as it describes a situation as it exists without
formal hypotheses, focusing on social processes intensely. Under qualitative phenomenon, case
study was selected as it facilitates in-depth investigation. Further, it facilitates constituting
attitudes, emerged thinking and perceptions of body of engineering consultants and contractors
on VE concepts and subjectively examine and evaluate the need for, and potential benefits of,
VE services. The unit of analysis or case in this study is construction projects which applied VE
technique. 39 interviews were conducted within six selected case studies to gather information
on VE applications in Sri Lanka.
The cases were selected from building projects due to abundance of such projects and also to
avoid complexities which may occur when evaluating building and civil projects simultaneously.
Cases vary from super luxury residential to low cost housing projects and shopping complexes
procured under Design and Build and Lump Sum methods. Details of six case studies are
illustrated at Table 1.
Table 1: Case Study Description
Case Type
Contract
Sum (US$
million)
Duration
(Months)
Procurement
Method
Public/
Private
Sector
A Super luxury residential
project
35 26 D&B/ LS Private
B Low cost housing project 7-23 24 D&B/ LS Public
C Super luxury office complex 695 48 D&B/ LS Public
D Low cost housing project 8 24 D&B/ LS Public
E Super luxury office complex 60 36 D&B/ LS Public
6
F Hostel building 1.5 12 D&B/ LS Public
39 semi structured interviews were conducted face to face, as illustrated at Table 2. The
interviewees represent three significant groups of each project team: client’s representative,
consultant’s representative and contractor’s representative. The interviews were tape-recorded
(with permission of interviewees) to ensure a faultless reporting of conversations and avert loss
of data. Interview guideline was prepared to gather data on impacts of VE applications on
projects as well as stakeholders, benefits and suggestions for regulatory bodies. Ultimately,
interview transcripts were developed to form a sensible adaptation of interview data.
Table 2: Interview profile – case studies
Case Organisation
Designation Experience(Y)
A
Client/Consultant-
Mix Organisation
Contractor
General Manager
Project QS
Senior QS
QS
Project Architect
Engineer
Engineer
Engineer
Engineer
General Manager
Chief QS
Engineer
Engineer
Senior Site QS
35
14
22
07
14
12
08
06
25
37
08
14
22
10
B
Contractor I
Contractor II
QS
QS
Site Project Engineer
Site QS
Site Technical Officer
Site Technical Officer
Site Technical Officer
03
09
13
05
07
06
09
7
Contractor III
Contractor IV
Project QS
Site Engineer
Site QS
Site Technical Officer
Site QS
Site Manager
05
11
08
06
09
14
C Consultant Senior QS
Site Senior QS
QS
QS
21
08
06
05
D Contractor Site Senior QS 14
Contractor General Manager 08
E Contractor Site Engineer
Site QS
13
05
F Contractor Chief QS
Project QS
08
14
Institute Director of Development
Assistant Director
21
16
In addition, 06 interviews were conducted as confirmatory interviews to clarify and validate
research outcomes gathered through case studies, specifically on suggestions made to standardise
VE applications. Semi structured interviews were conducted with representative professionals
from client, consultant, contractor organisations and academia, each possessing more than 20
years of experience (Refer Table 3).
Table 3: Interview profile – Experienced professional’s opinions
Organisation Type Designation Experience (Y)
Client/Consultant General Manager 35
Consultant Director 22
Consultant Project Manager 22
Contractor Senior QS 37
Contractor Senior QS 42
8
University Senior Lecturer 22
Perry (1998) said that these findings should be justified by using ‘cross-case analysis’ to identify
interrelationships and differences between each case and afterwards, conclusions shall be made.
Content analysis, a technique to gather data, involves codifying qualitative information into pre-
defined categories (codes) to derive patterns in presentation and reporting (Guthrie et al., 2004).
In other words it attempts to find similar cognitions under a same concept or about its meaning
rather than actual content of segment. After developing interview transcripts, key themes (codes)
emerging from findings were identified in each case. Study selected the software program NVivo
(NUD*IST Vivo Version 10.0.281.0) produced by QSR (Qualitative Solutions and Research
Ltd.) for coding function. Coding structure consists of the codes to presents the real VE
applications in the construction industry as illustrated at figure 1. Accordingly, process, factors
affecting, benefits, drawbacks and impacts of VE applications to stakeholders are analysed in
details.
Figure 1: Coding structure used in analysing empirical data
This presents an overview of VE applications in Sri Lankan construction industry,
recommendations for standardised VE applications and decision making formula derived
through empirical data analysis.
4. RESEARCH FINDINGS
4.1 OVERVIEW OF VE APPLICATIONS IN SRI LANKAN CONSTRUCTION INDUSTRY
Almost all respondents mentioned that there is no predefined way to apply VE techniques in
construction industry. It is revealed that most stakeholders do not consider life cycle cost of a
9
project before application of VE techniques. Further, construction stakeholders understand and
apply VE techniques in projects as compatible with their knowledge and experience.
Accordingly, stakeholders of construction industry prefer different stages of VE application
based on their expertise. However, it was revealed that key objective of VE applications is to
reduce cost while time and quality is considered less. Consultants and contractors preferred cost
and time reductions while maintaining quality of a project. Most stakeholders believe client as
the most significant person affected by VE proposals than contractors.
Most respondents said that intangible benefits which are hard to achieve in normal construction
processes can be achieved through VE techniques which makes the end product more compatible
with surroundings and occupants achieving better value for money invested by client. When
there is a need for VE proposals for a project, contractors use experience and latest technology
available to suggest better VE proposals compatible with project requirements. Ultimately, client
gets a project with latest technology while contractor gains cost and time benefits. Contractors
can also use his subsidiary products in a project with prior approval of consultant.
Some respondents mentioned about the management system is impacting the performance. As
noted more management, control, rules and regulations will not increase the efficiency, quality
and production. To increase efficiency, quality and production, the entire system has to be
changed. It is the responsibility of the client and consultants to change the system because they
are the determiners of current system. Clients and consultants are reluctant to change the system,
due to fear of losing control over contractors and.
Risk is another key factor influencing VE. When a contractor makes a VE proposal that
contractor has to bear the risk. Non-transparency, more bureaucratic, lack of accountability,
more documentation and number of decision makers on client's side cause inefficiency. In this
context, government, clients and consultants have to;
Minimise client’s decision making, management, direction and control.
Identify the contractor as the expert and not the client's representative.
Uses a contractor proposed contract as a risk management tool instead of a control
mechanism.
Increase transparency which in turn will increase accountability
Encourage quality assurance instead of quality control
Minimise deviations in project cost and project duration
Identify the client's intent, but allow the contractor to determine the final deliverable
Change ideas from reactive, price based to proactive and value based
10
Lower cost and increase value and quality, efficiently by minimising transactions and
alignment of resources
Utilises expertise instead of management, direction and control to minimise risk
Conversion of a ‘win lose’ environment to a ‘win-win’ environment
Experienced professionals stated that it is difficult to change the environment of construction
industry.
For an example, a client with a construction idea having strict restrictions on time, cost and
quality will assist design firm to translate his expectation into a constructed project. The design
firm realises that if they disagree with the client’s perception of initial conditions (cost, time and
expected construction quality) the firm will not be selected. Thus, the firm designs the project
without informing the client of any misalignment or over expectations. During the design
process, client makes alterations and design team is forced to make further decisions. After the
design is completed the firm advices the client to select a contractor through tendering. Finally,
the designer attempts to manage, control and direct the contractor to make client’s expectations a
reality. In this context, applying VE into that project is useless with clients and consultants who
try to dictate. Thus, most contractors attempt to use more technical personnel to increase
management and control. However, experienced professionals clearly stated that this will never
increase the contractor’s performance.
Experienced professionals with overseas exposure mentioned that most developing countries
(Eg. Sri Lanka, India, Bangladesh, Malaysia) are faced with the problem of contractors’ low
performances. Nihas et al (1992) highlighted a research conducted in India using Construction
Industry Structure Model (CISM) which move from inefficient price based environment to
efficient best value environment. In the Netherlands also a research team has conducted a similar
research using Performance Information Procurement System (PIPS) and achieved good results.
According to Kashiwagi and Kashiwagi (2011), PIPS can increase value and quality and
minimise delivery cost and time. Perera et al (2011) stated that Northern Ireland has made good
use of VM process but lack of formality in execution effects performance and efficiency of a
country.
Accordingly, findings revealed that VE proposals must be executed with broader understanding
of project requirements and viewpoints of client, consultant and contractor. VE proposals have to
fit with the needs of the project and its’ stakeholders. Further, it is influenced by external factors
such as political, government rules and regulations, economical and environmental. According to
11
respondents, stakeholders are required to accept, avoid, share or transfer details of factors to have
better outputs through VE applications.
4.2 FRAMEWORK FOR RECOMMENDATIONS TO STANDARDISE VE APPLICATIONS
Figure 2 presents recommendations to construction organisations and national construction
regulatory bodies to standardise VE practice in Sri Lankan construction industry.
Recommendations which are suitable for construction organisations and national level
construction regulatory bodies are presented in three main levels as project level, organisational
level and national level. The framework provides support for professionals to measure value of a
project and apply VE techniques in various forms to achieve value where ordinary procedures
cannot meet. Thus, it can lead to increased application of VE techniques in construction projects.
12
Figure 2: Framework for recommendations
13
Outdated standards and specifications, over and inaccurate designs (Eg. concrete and
reinforcement), inadequate information (mechanical and electrical), failures of VE proposals due
to concealing of real impacts, unavailability of skilled labour, plant and equipment were
identified as project level barriers. Economical status (Eg. high price fluctuation), social culture,
political influence and local standards were identified as barriers at national level.
Recommendations to construction organisations
Stakeholders look for profit through projects and they will not perform if there are no incentives.
There must be some incentive system to encourage consultants and contractors to propose VE
techniques in projects. Most respondents stated that consultants and contractors are bound by
contract to the client and due to such there are many cost, time, quality and responsibility
constraints in projects. Reduction of those constraints will comfort consultants and contractors to
propose more flexible VE proposals.
Providing more opportunities to site staff to share their ideas through meetings, workshops and
discussions will lead to development of better VE applications and reducing contactor’s
responsibility for design will encourage doing more VE proposals at project level.
Establishment of proper procedures with adequate power and encouraging alternative proposals
at pre-construction stage will be more competitive and beneficial to a client at organisational
level. Ultimately this will increase competitive VE proposals reducing defective proposals and
contractors also will get a fair chance and more competitive advantage among other contractors.
Media is a powerful source which can create awareness through programmes and discussions
(Eg: television, newspaper and radio) about VE techniques and its benefits and further through
dissemination of real data on benefits gained by stakeholders. In addition, promote green
building certificates to gain for projects which apply VE techniques which eventually reduce
energy consumption, wastage and increase ease of maintenance. Along with that introduction of
point system or award system to select the best VE proposals which eventually push construction
companies to do more and more VE in their projects.
According to research findings minimum involvement of client and his representatives will allow
more efficiency and performance in the project. Using minimum standards, using quality
assurance instead of quality control, minimise transactions (direction, meetings, management,
negotiations, inspection and direction) can reduce the pressure of contractor resulting more
performance. According to Kashiwagi et al (2009), when the value environment process was
separated from construction industry and run on $1.5B of services at Arizona State University
14
and the research team saved over $100M as efficiency. It is 6.67% saving to the construction
industry and to the country.
Recommendations to national construction regulatory bodies
National construction regulatory bodies are the governing party in Sri Lanka who have authority
to regulate VE techniques by law. Respondents gave contradictory suggestions about regulating
VE technique. Most respondents stated that it is better to have such kind of law; otherwise
stakeholders will not use VE techniques in projects, specially by government. However, most
experts stated that it will not be possible to regulate VE directly in construction, but regulatory
bodies can regulate other things such as energy efficiency, wastage reduction and green building
concept which need VE techniques to meet those goals.
Government projects need to be more transparent than private sector as it involves public money.
However, government projects are influenced by factors such as rigid rules and regulations, audit
queries and political influences. Thus, procedures need to reduce rigidity and have more
flexibility to practice VE applications. In parallel, government must regulate VE techniques by
law to succeed in procedures. As an example, request for submission of a VE report to get
permission for design prior to actual construction for selected projects. Along with that,
awareness and knowledge on VE techniques is necessary for regulatory bodies to be successful
in said endeavour.
Thus, regulatory bodies are required to take necessary actions to satisfy stakeholder interest in
VE techniques through incorporation of relevant clauses in Standard Conditions of Contracts to
eventually reduce country’s burden and ensure protection of national interests.
According to Kashiwagi and Kashiwagi (2011), Netherland government is politically involved to
increase value in the construction projects by issuing a political Action Agenda in November
2003, based on five main objectives as follows;
Restoring trust between the government and the sector
Developing effective markets and a properly functioning sector
Enhancing professionalism in procurement
Instilling high standards in the supply chain
Less, but more effective, regulation
These objectives minimised the unnecessary involvement of clients and client’s representatives
and thereafter Netherland gradually achieved high efficiency and high performance. This
scenario is possible in any country with the willingness of the government of that country. Perera
15
et al (2011) stated that there is a skill gap in VE, resulting limited usage of VE in projects.
Academic institutions and professional bodies have to take action for greater awareness and
training to the construction industry authorities and stakeholders on VE process.
4.3 DECISION MAKING FORMULA FOR VE APPLICATION
Reduction of construction cost will affect the profit margin of a contractor. Both consultant and
contractor need to be aware on VE technique and its profitability. To ease this process, a formula
as given below was developed.
Original construction cost of the item = A
Actual overhead and profit percentage = b
Original profit of the Contractor = Ab
Revised construction cost of the item = C
Overhead and profit percentage given by the = d
consultant
Revised profit of the contractor = Cd
According to general practice in the industry, the formula should be;
Contractor’s portion due to VE technique = (A+Ab-C-Cd)+ Cd
2
= (A+Ab-C+Cd)
2
But for contractor to get a profit
contractor’s portion due to VE technique > Original profit of the contractor
(A+Ab-C+Cd) > Ab
2
A+Ab-C+Cd > 2Ab
C (d-1) > A (b-1)
C < A (1-b) (1-d)
16
Above formula validated by applying actual figures of case A is as follows.
Original construction cost of the item = $.396,825.40 (A)
Actual overhead and profit percentage = 34% (b)
Overhead and profit percentage given by the consultant = 10% (d)
Revised construction cost of the item = $.158,730.16 (C)
C < A (1-b)
(1-d)
C < 396,825.40 (1-34%)
(1-10%)
C < 396,825.40 (0.66)
(0.9)
C < 396,825.40 x .0.73
C < 289,682.54
To obtain a real profit to a stakeholder, revised construction cost of item should be lower than
the answer(C). In above calculation, C = $ 158, 730. 16, and it is lower than the answer
$.289,682.54. Therefore, this VE proposal is beneficial to stakeholders.
The formula will be useful to both contractors and consultants. This formula is to determine a
margin between contractor’s portion due to VE technique and original profit of the contractor.
As actual figures satisfy above formula, it is proposed to adopt such VE proposals. Professionals
can easily calculate and figure out the feasibility of a VE proposal, as per above.
5. CONCLUSIONS
The formula is based on research findings to facilitate professionals to understand real VE
practices in the construction industry. Further, the framework provides VE techniques to apply in
various forms in achieving value where ordinary procedures cannot meet. The formula is simply
17
trying to determine a margin between contractor’s portion due to VE techniques and original
profit of contractor. Professionals can easily calculate and figure out feasibility of a VE proposal.
Findings revealed that the main reason for less performance and inefficiency is unawareness of
VE techniques and processes. Other researchers also conveyed the same conclusion that VE
technology has to reach every professional in the construction industry. Government of a country
has a major role in establishing more favourable grounds for VE. Recommendations to construct
organisations and national level construction regulatory bodies suggest general requirements and
improvements to construction industry. This study can be further extended to civil construction
projects as well as possibilities of integrating VE to new trends in construction, such as Building
Information Modelling.
REFERENCES
Abidin, N.Z., and Pasquire, C.L., 2007. Revolutionize value management: A mode towards
sustainability. International Journal of Project Management, 25(3), 275-282.
doi:10.1016/j.ijproman.2006.10.005
Alhazmi, T., and McCaffer, R., 2000. Project procurement system selection model. Journal of
Construction Engineering and Management, 126(3), 176-184. doi:10.1061/(ASCE)0733-
9364(2000)126:3(176)
Bertelsen, S., and Emmitt, S., 2005. The client as a complex system. In: Proceedings of the 13th
International Group for Lean Construction Conference: Proceedings International Group on
Lean Construction. 73-83. Available from:
https://www.researchgate.net/profile/Sven_Bertelsen/publication/236841941_THE_CLIENT_A
S_A_COMPLEX_SYSTEM/links/00463519510067d805000000.pdf [Accessed 15 February
2016].
Bowman, C., and Ambrosini, V., 2010. How value is created, captured and destroyed. European
Business Review, 22(5), 479-495. doi:10.1108/09555341011068903
Chan, A.P.C., Yung, K.H.E., Lam, P.T.I., Tam, C.M., and Cheung, S.O., 2001. Application of
Delhi method in selection of procurement systems for construction projects. Construction
Management and Economics, 19(3), 699-718. doi:10.1080/01446190110066128
Cheah, C.Y., and Ting, S.K., 2005. Appraisal of value engineering in construction in Southeast
Asia. International Journal of Project Management, 23(2), 151-158.
doi:10.1016/j.ijproman.2004.07.008
18
Chen, W. T., Chang, P. Y., and Huang, Y. H., 2010. Assessing the overall performance of value
engineering workshops for construction projects. International Journal of Project
Management, 28(5), 514-527. doi:10.1016/j.ijproman.2009.08.005
Dell'Isola, A., 1997. Value engineering. 1st ed. Kingston, Mass: R.S. Means Co.
Fan, S., and Shen, Q., 2011. The effect of using group decision support systems in value
management studies: An experimental study in Hong Kong. International Journal of Project
Management, 29(1), 13-25. doi:10.1016/j.ijproman.2010.01.008
Fong, P.S.W., and Shen, Q., 2000. Is the Hong Kong construction industry ready for value
management?. International Journal of Project Management, 18(5), 317-326. Available from:
http://ac.els-cdn.com/S0263786399000289/1-s2.0-S0263786399000289-
main.pdf?_tid=77300e04-e0b7-11e3-b292-
00000aab0f6b&acdnat=1400656613_e9947cf335a5f61c 5e549abee907331c [Accessed 31 July
2015].
Fong, P. S. W., Shen, Q., and Cheng, E. W., 2001. A framework for benchmarking the value
management process. Benchmarking: An International Journal, 8(4), 306-316.
doi:10.1108/14635770110403800
Gudem, M., Steinert, M., Welo, T., and Leifer, L., 2013. Redefining customer value in lean
product development design projects. Journal of Engineering, Design and Technology, 11(1),
71-89. doi:10.1108/17260531311309143
Hamilton, A., 2002. Considering value during early project development: A product case
study. International Journal of Project Management, 20(2), 131-136. doi:10.1016/S0263-
7863(00)00052-1
Jaapar, A., Maznan, N. A., and Zawawi, M., 2012. Implementation of value management in
public projects. Procedia-Social and Behavioral Sciences, 68, 77-86.
doi:10.1016/j.sbspro.2012.12.208
Kashiwagi, D. and Kashiwagi, J., 2011. Case study: performance information procurement
system (pips) in the Netherlands. Malaysian Construction Research Journal, 8(1). Available
from: http://pbsrg.com/app/wp-content/uploads/publications/papers-intro/Case-Study-
Performance-Information-Procurement-System-PIPS-in-the-Netherlands-02-2011.pdf [Accessed
10 February 2016].
Kashiwagi, D., 2011. Case study: Best value procurement/performance information procurement
system development. Journal for the Advancement of Performance Information & Value, 3(1).
Available from: http://pbsrg.com/app/wp-content/uploads/publications/papers-intro/Case-Study-
19
Best-Value-Procurement-Performance-Information-Procurement-System-Development.pdf
[Accessed 03 February 2016].
Kashiwagi, D., Kashiwagi, J. and Savicky, J., 2009. Industry structure: misunderstood by
industry and researchers. In 2nd Construction Industry Research Achievement International
Conference, Kuala Lumpur, Malaysia, CD-Day, 1(1), 3-5. Available from:
https://www.researchgate.net/profile/Dean_Kashiwagi/publication/267942951_Industry_Structur
e_Misunderstood_by_Industry_and_Researchers/links/55cb747a08aeca747d6c1a9e.pdf
[Accessed 15 February 2016].
Kelly, J., Male, S., and Graham, D., 2004. Value management of construction project. Oxford:
Blackwell Publishing.
Kliniotou, M., 2004. Identifying, measuring and monitoring value during project
development. European Journal of Engineering Education, 29(3), 367-376.
doi:10.1080/03043790310001658613
Kosala, R.G., and Karunasena, G., 2015. Value Engineering practices and its impact to
construction industry. In: Proceeding of The 4th World Construction Symposium 2015:
Sustainable Development in the Built Environment: Green Growth and Innovative Directions,
538-546. Available from: http://dl.lib.mrt.ac.lk/handle/123/11268 [Accessed 10 September 2015]
Leung, M.Y., and Liu, A.M., 2003. Analysis of value and project goal specificity in value
management. Construction Management and Economics, 21(1), 11-19.
doi:10.1080/0144619032000065081
Leung, M.Y., Ng, S.T., and Cheung, S.O., 2002. Improving satisfaction through conflict
stimulation and resolution in value management in construction projects. Journal of
Management in Engineering, 18(2), 68-75. doi:10.1061/(ASCE)0742-
597X(2002)18:2(68)
Lozon, J., and Jergeas, G., 2008. The use and impact of value improving practices and best
practices. Cost Engineering, 50(6), 26-32. Avalilable from:
http://cat.inist.fr/?aModele=afficheN&cpsidt=20476771 [Accessed 12 September 2015].
Luu, D.T., Ng, S.T., and Chen, S.E., 2003. Parameters governing the selection of procurement
system–an empirical survey. Engineering, Construction and Architectural Management, 10(3),
209-218. doi:10.1108/09699980310478458
Male, S., Kelly, J., Fernie, S., Gronqvist, M., and Bowles, G., 1998. The value management
benchmark: Research results of an international benchmarking study. London: Thomas Telford.
20
Male, S., Kelly, J., Gronqvist, M., and Graham, D., 2007. Managing value as a management
style for projects. International Journal of Project Management, 25(2), 107-114.
doi:10.1016/j.ijproman.2006.09.001
Miles, L.D., 1972. Techniques of value analysis and engineering. New York: Mcgraw-Hill.
National Research Council, 2009. Advancing the competitiveness and efficiency of the U.S.
construction industry. Washington, DC: The National Academies Press. Available from:
http://modular.org/marketing/documents/NRC_USConstructionIndustry_Report.pdf [Accessed
21 July 2015].
Nihas, S., Barlish, K., Kashiwagi, J. and Kashiwagi, D., 2013. An analysis of the construction
industry structure in India. Journal for the Advancement of Performance Information & Value,
5(2). Available from: http://cibw117.com/journal/index.php/performance-info-and-
value/article/view/132 [Accessed 07 February 2016].
Norton, B.R., and McElligott, W.C., 1995. Value management in construction: A practical
guide. New York: McMillan.
Othman, A.A.E., 2008. Incorporating value and risk management concepts in developing low
cost housing projects. Emirates Journal for Engineering Research, 13(1), 45-52. Available from:
http://cpas-egypt.com/pdf/Ayman_Othman/R/002.pdf [Accessed 03 September 2015].
Parker, D.E., 2001. Determining building worth. Washington, D.C.: Donald E. Parker.
Perera, S., Hayles, C.S. and Kerlin, S., 2011. An analysis of value management in practice: the
case of Northern Ireland's construction industry. Journal of Financial Management of Property
and Construction, 16(2), 94-110. doi:10.1108/13664381111153097
Phillips, S., Martin, J., Dainty, A. and Price, A., 2007. Uncertainty in best value decision
making. Journal of Financial Management of Property and Construction, 12(2), 63-72.
doi:10.1108/13664380780001094
Potts, K., 2008. Construction cost management. 1st ed. London: Taylor & Francis.
Rameezdeen, R., and De Silva, S., 2002. Trends in construction procurement systems in Sri
Lanka. Built Environment Sri Lanka, 2(2). 2-9. Available from: http://dl.nsf.ac.lk/handle/1/8303
[Accessed 15 August 2015].
Ratnasabapathy, S., and Rameezdeen, R., 2007. A decision support system for the selection of
best procurement system in construction. Built Environment Sri Lanka, 7(2). 43-53.
doi:10.4038/besl.v7i2.1943
21
Salvatierra-Garrido, J. and Pasquire, C., 2011. Value theory in lean construction. Journal of
financial management of property and construction, 16(1), 8-18.
doi.10.1108/13664381111116043
SAVE International., 2006. Value methodology standards and body of knowledge. USA: The
Value Society.
Shen, Q., and Liu, G., 2004. Applications of value management in the construction industry in
China. Engineering, Construction and Architectural Management, 11(1), 9-19.
doi:10.1108/09699980410512629
Stenstrom, C., Parida, A., Kumar, U., and Galar, D., 2013. Performance indicators and
terminology for value driven maintenance. Quality in Maintenance Engineering, 19(3), 222-232.
doi:10.1108/JQME-05-2013-0024
Thiry, M., 1997. A framework for value management practice. USA: Project Management
Institute.
Thiry, M., 2001. Sensemaking in value management practice. International Journal of Project
Management, 19(2), 71-77. doi:10.1016/S0263-7863(00)00023-5
Vorakulpipat, C., Rezgui, Y., and Hopfe, C. J., 2010. Value creating construction virtual teams:
A case study in the construction sector. Automation in Construction, 19(2), 142-147.
doi:10.1016/j.autcon.2009.11.016
Wijewardana, C., Jayasena, H.S., and Ranadewa, K.A.T.O., 2013. Impact of government policies
and regulations when adopting alternative procurement methods. In: Proceeding of The Second
World Construction Symposium 2013: Socio-Economic Sustainability in Construction, 253-260.
Available from: http://www.suranga.net/publications/2013_gov_policy_proc.pdf [Accessed 17
July 2015].
Zar, F.I.M., Razaee, Z.S., and Karbasian, M., 2011. A fuzzy case based reasoning approach to
value engineering. Expert Systems with Applications, 38(8), 9334-9339.
doi:10.1016/j.eswa.2011.01.124
Zhang, X., Mao, X., and AbouRizk, S.M., 2009. Developing a knowledge management system
for improved value engineering practices in the construction industry. Automation in
Construction, 18(6), 777-789. doi:10.1016/j.autcon.2009.03.004