29
A Comparative Analysis of the Claim & Dispute Resolution Provisions of FIDIC’s 1999 Major Forms of Contract Against its Earlier Forms 1 by Nael G. Bunni, BSc, MSc, PhD, CEng, FICE, FIEI, FIStructE, FCIArb, FIAE, MConsEI. Chartered Engineer, Conciliator & Registered Chartered Arbitrator Visiting Professor in Construction Law & Contract Administration at Trinity College Dublin. 1. Introduction 1.1 The construction contract is unique in that it seeks to provide for a specific remedy in the event of any breach of the terms and conditions within its framework and/or for a contractual entitlement in respect of specified events or perceived risks. 2 Comparatively viewed against other types of contract, the wording of a construction contract is therefore more extensive having to provide for and deal with detailed conditions in respect of the risks that might arise during the construction period and beyond. 1.2 Thus, as in other standard forms of construction contracts, the genesis and development of the various FIDIC Forms of Contract were, and remain to be, based on the need to redefine and reapportion the risk ascribed to the respective parties by the applicable law. By including a mechanism to give one party a certain remedy if a specified event arises, the risk of that event, which would otherwise remain with that party, is transferred to the other party. This process is in conformity with the established principle that the purpose of a contract is to identify and allocate the risks between the parties. It is also in accord with the legal concept that the purpose of a contract is to 1 FIDIC is the acronym for the International Federation of Consulting Engineers, established in 1913 in Ghent, Belgium, by three associations of consulting engineers from France, Switzerland and Belgium. At the present time, FIDIC represents 73 national member associations of independent consulting engineers from different countries around the World. 2 “The FIDIC Forms of Contract”, by Nael G. Bunni, Blackwell Publishing, Oxford, 3 rd Edition, 2005, see Chapter 7 for the inherent characteristics of the construction contract and Chapter 13 for some of the unique obligations contained in it. Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 1

A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

Embed Size (px)

Citation preview

Page 1: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

A Comparative Analysis of the Claim & Dispute Resolution Provisions of

FIDIC’s 1999 Major Forms of Contract Against its Earlier Forms1

by

Nael G. Bunni, BSc, MSc, PhD, CEng, FICE, FIEI, FIStructE, FCIArb, FIAE, MConsEI.

Chartered Engineer, Conciliator & Registered Chartered Arbitrator

Visiting Professor in Construction Law & Contract Administration at Trinity College Dublin.

1. Introduction

1.1 The construction contract is unique in that it seeks to provide for a specific remedy in

the event of any breach of the terms and conditions within its framework and/or for a

contractual entitlement in respect of specified events or perceived risks.2

Comparatively viewed against other types of contract, the wording of a construction

contract is therefore more extensive having to provide for and deal with detailed

conditions in respect of the risks that might arise during the construction period and

beyond.

1.2 Thus, as in other standard forms of construction contracts, the genesis and development

of the various FIDIC Forms of Contract were, and remain to be, based on the need to

redefine and reapportion the risk ascribed to the respective parties by the applicable

law. By including a mechanism to give one party a certain remedy if a specified event

arises, the risk of that event, which would otherwise remain with that party, is

transferred to the other party. This process is in conformity with the established

principle that the purpose of a contract is to identify and allocate the risks between the

parties. It is also in accord with the legal concept that the purpose of a contract is to

1 FIDIC is the acronym for the International Federation of Consulting Engineers, established in 1913 in Ghent,

Belgium, by three associations of consulting engineers from France, Switzerland and Belgium. At the present

time, FIDIC represents 73 national member associations of independent consulting engineers from different

countries around the World. 2 “The FIDIC Forms of Contract”, by Nael G. Bunni, Blackwell Publishing, Oxford, 3rd Edition, 2005, see

Chapter 7 for the inherent characteristics of the construction contract and Chapter 13 for some of the unique

obligations contained in it.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 1

Page 2: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

identify and apportion the rights and obligations of the parties; since these rights and

obligations stem from the allocation of the risks to which the contract is exposed, a

principle which is particularly true in construction contracts. However, whether the

remedy sought is in respect of a breach of the contract terms and conditions or for the

occurrence of a specified event, the FIDIC Forms of Contract, as indeed in most

construction contracts, place an obligation on the party who wishes to avail of that

remedy to follow a set procedure, which is referred to as “the claims procedure”.

2. Claims & Counterclaims

2.1 The first step of the claims procedure of any construction contract is the launch of a

claim. Whilst this might be considered a straightforward exercise, the following

matters need to be fully understood by those involved in such a process:

(a) The meaning and definition of “a claim”;

(b) The legal basis of claims, and for that matter counterclaims;

(c) The process by which claims & counterclaims should be formulated and

managed;

(d) The parties’ rights and obligations under the Contract or in relation thereto; and

(e) The manner in which these rights and obligations might be protected or exercised

under the Contract or in relation thereto.3

2.2 Although no express definition of “a claim” appears in any of the FIDIC Forms of

Contract, a claim in practice is generally taken to be an assertion for (additional)

payment due to a party or for extension of the Time for Completion. This

interpretation of “a claim” is borne out by the wording of the contractual provisions

relating to claims, as adopted in the earlier FIDIC Forms of Contract, either explicitly

or implicitly. For example, Clause 44 of the Fourth Edition of the 1987 Red Book4

provides for an entitlement to “an extension of the Time for Completion of the Works

or any Section or part thereof” (emphasis added), albeit that the word “claim” appears

3 As for footnote no.2, but see Chapter 16 for more detailed description of the claims & counterclaims that are

expected in such contracts. 4 Conditions of Contract for Works of Civil Engineering Construction (1987), better known as the Red Book.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 2

Page 3: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

nowhere in this clause. Similarly, Sub-Clause 53.1 includes the words “…… if the

Contractor intends to claim any additional payment …” (emphasis added), but here

the word “claim” appears as a verb and as a noun. However, nowhere in these Forms

is there a reference to an assertion for a declaration, although such a claim is frequently

made. So, for example, a party might assert that a clause in the specification gives a

different meaning to that contended by the other party, or that a provision of the

contract is not valid under certain circumstances. Such an assertion forms a type of a

claim within the legal basis set out in paragraph 3.1(b) below. The 1999 FIDIC Forms

of Contract for major works5 follow the same pattern by not defining “a claim”, but the

word “claim” does appear in Sub-Clauses 2.5 and 20.1 of these Forms, see the quoted

text in paragraphs 4.2 and 4.3 below, respectively. However, it should be noted that

these sub-clauses do not preclude the parties from exercising their rights under the

general concepts of the law by making claims based on the applicable law of the

contract, as explained in paragraph 3.1(c) below, by the inclusion of the word

“otherwise” in the first paragraph of each sub-clause. Accordingly, in the end analysis,

a claim may therefore be defined as “an assertion of a right or a remedy”.

2.3 The term “counterclaim” is also not defined in, and indeed does not appear in the text

of, any of the FIDIC Forms of Contract. Nevertheless, the generally accepted meaning

given to a counterclaim is “an assertion made by a party, which can conveniently be

examined and disposed of in an action originally initiated by the other party”. It is

not necessarily a defence, but a substantive claim against the claimant which could have

5 In September 1999, FIDIC published a new set of standard forms of contract alongside those that have been in

use at that time. The new set is made up of the following four contract forms:

The Green Book: The Short Form of Contract - Agreement, General Conditions, Rules for Adjudication and

Notes for Guidance;

The New Red Book: The Construction Contract, (Conditions of Contract for Building and Engineering

Works, Designed by the Employer) - General Conditions, Guidance for the Preparation of the Particular

Conditions, Forms of Tender, Contract Agreement, and Dispute Adjudication Agreement;

The New Yellow Book: The Plant and Design-Build Contract, (Conditions of Contract for Electrical and

Mechanical Plant, and for Building and Engineering Works, Designed by the Contractor) - General

Conditions, Guidance for the Preparation of the Particular Conditions, Forms of Tender, Contract Agreement

and Dispute Adjudication Agreement; and

The Silver Book: The EPC & Turnkey Contract, (Conditions of Contract for EPC

Turnkey Projects) - General Conditions, Guidance for the Preparation of the Particular

Conditions, Forms of Tender, Contract Agreement and Dispute Adjudication Agreement.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 3

Page 4: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

grounded an independent action. The reference to convenience in this definition

signifies that the background of the counterclaim must be similar to that of the claim

and resulting from the same set of facts and events. For instance, a good example of a

counterclaim is where a delay event causes the contractor to claim that he has been

wrongfully denied an extension of time by the engineer and the same delay event gives

rise to the employer’s counterclaim for liquidated damages, referred to as “delay

damages” in the 1999 FIDIC Contracts. 6 The important point to note is that in respect

of a counterclaim falling within the above definition, the procedural steps that apply to

a claim do not have to be followed by the counter claimant.

3. Types of Claim

3.1 Essentially, other than claims under statutory law, claims in construction contracts may

be based on any one of four legal and one non-legal concepts, as set out below, subject

to the effect of the applicable law:

(a) A claim under the contract: This category is based on the grounds that should a

certain event occur, then a claimant would be entitled to a remedy that is specified

under a particular provision of the contract. It is explicitly referred to in Sub-

Clauses 2.5 and 20.1 of the 1999 three Major Forms of Contract by the words “…

under any Clause of these Conditions …” in their first paragraph with particular

reference to the word “under”. The event described above may be one of two

types.

Firstly, it may be a specified event under the contract, which might or might

not occur, where in certain defined circumstances a party is entitled to claim a

designated remedy. For example, the contractor may be entitled to claim an

additional payment and an extension of time if testing is delayed by, or on

behalf of, the employer, under Sub-Clause 7.4 “Testing” of the 1999 Red

Book.7

6 The example is taken from a paper by Mr. Christopher R. Seppälä, “The Arbitration Clause in FIDIC

Contracts for Major Works”, ICLR Vol. 22, Part 1, January 2005. 7 The 1999 Red and Yellow Forms of Contract contain some thirty provisions specifying events that, when and

if they occur, would entitle the contractor to make a claim; and thirteen that would entitle the employer to make

a claim. The 1999 Silver Form of Contract contains a lesser number of twenty provisions for the contractor and

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 4

Page 5: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

Secondly, the specified event may be a breach of a particular provision in the

contract entitling a claimant to a designated remedy if the terms of such

provision are not, or only partially, complied with. If the claim is successful,

the particular provision in the contract would apply and the remedy could be

in the form of a payment of a sum of money, or an extension of time, or some

other benefit, or a combination of all three. For example, it is stipulated in the

1999 Red Book that failure by the contractor to complete the works on a

specified date would entitle the employer to seek delay damages at a specified

rate per day or week, as provided in Sub-Clause 8.7 “Delay Damages”. In

this connection, the provisions of the applicable law must be taken into

consideration, for instance whether such damages are in effect a penalty, and

if so, whether or not such a claim can be treated as a valid claim.

(b) A claim arising out of or in connection with the contract: The second category

relates to a claim arising, not under but, out of or in connection with the contract,

where the remedy is not designated in the contract and the claimant needs to

invoke a provision of the applicable law to obtain a remedy. Therefore, if the

claim is valid, the remedy lies under the provisions of the applicable law of the

contract, an example of this type of a claim is where one of the parties has

misrepresented certain important facts. In such a case, the other party may use this

as a basis for cancelling the contract or for claiming damages. Where the 1999

Major Forms of Contract are concerned, this category of claims is explicitly

referred to in Sub-Clauses 2.5 and 20.1 by the words “under any Clause of these

Conditions or otherwise in connection with the Contract”, appearing in the first

paragraph, with particular reference to the word “otherwise” therein.

(c) A claim under the principles of the applicable law: The third category relates

to a claim arising under the application of the principles of the applicable law,

either by the parties to the contract or against third parties. This could lead to a

claim under the law of tort, or delict, as it is referred to in some jurisdictions.

Once again the important explicit word reference in this connection, or indeed in

fourteen for the employer. A list of claims is contained in The FIDIC Contracts Guide, which was published

separately by FIDIC during 2001, but was copyrighted in 2000, see pages 90 to 93.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 5

Page 6: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

this connection with claim category (d) below, is “otherwise”, as referred to in

category (b) above.

(d) A claim arising out of the principle of quantum meruit: The fourth category

comprises claims where no contract exists between the parties; where a contract

existed, but is deemed to be void; or where a contract is in existence but the price

is not stipulated, instead the amount to be paid is to be based on a reasonable sum

or the price is to be agreed from time to time. The principle is that an individual

has the right to be paid a reasonable remuneration for work done, which is

referred to in some legal systems as quantum meruit or as much as one has

earned.

(e) A claim for ex gratia payment: Finally there is the claim for an ex gratia

payment (meaning out of kindness). Although claims for ex gratia payments are

not claims which arise by virtue of a contractual or legal entitlement, they are

sometimes tolerated on the basis that there may be some commercial sense or

benefit in reaching a settlement between the parties without the acceptance of

liability.

4. Claim Procedures

4.1 Under In the earlier FIDIC Forms of Contract, the claim procedures were tolerant of

lack of notice provisions in an attempt to ensure that payment is made where

contemporary records are kept and a discipline evolved in a procedure set out Clause 53

of the 1987 Red Book, which required the contractor when submitting a claim to follow

the procedural steps outlined below:

give a notice of intention to claim within 28 days of the event giving rise to the

claim (note it is not after the consequences of the event). The notice is required

whether the claim is pursuant to a clause of the Red Book or otherwise. It does not

have to include any details of the claim itself;

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 6

Page 7: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

keep contemporary records (by the contractor);8

inspect the records (by the engineer);

provide authority to instruct the contractor to keep further contemporary records (by

the engineer);

within 28 days of the notice or an agreed period, submit particulars of the claim in

respect of amount and grounds upon which it is based (by the contractor);

interim and accumulated accounts to be submitted for continuing effects (by the

contractor);

final accounts to be submitted at end (by the contractor);

a copy of accounts to be sent to the employer, by the contractor, if so required by

the engineer .

4.2 Under the 1999 FIDIC contracts for major works, the procedure for initiating a claim

under the contract by an employer differs from that for initiating a contractor’s claim.

The two procedures are explained in two different Sub-Clauses: Sub-Clause 2.5,

“Employer’s Claims”; and Sub-Clause 20.1, “Contractor’s Claims”, respectively.

4.3 Sub-Clauses 2.5 and 20.1 of the 1999 FIDIC contracts for major works provide as

follows:

“Employer’s Claims

2.5 If the Employer considers himself to be entitled to any payment under any

Clause of these Conditions or otherwise in connection with the Contract, and/or

to any extension of the Defects Notification Period, the Employer or the

Engineer shall give notice and particulars to the Contractor. However, notice is

not required for payments due under Sub-Clause 4.19 [Electricity, Water and

Gas], under Sub-Clause 4.20 [Employer's Equipment and Free-Issue Material],

or for other services requested by the Contractor.

The notice shall be given as soon as practicable after the Employer became

aware of the event or circumstances giving rise to the claim. A notice relating

to any extension of the Defects Notification Period shall be given before the

expiry of such period.

8 A list of the Records expected to be provided is given in Section 16.5.2 of the Authors book quoted in

Footnote 2 above.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 7

Page 8: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

The particulars shall specify the Clause or other basis of the claim, and shall

include substantiation of the amount and/or extension to which the Employer

considers himself to be entitled in connection with the Contract. The Engineer

shall then proceed in accordance with Sub-Clause 3.5 [Determinations] to agree

or determine (i) the amount (if any) which the Employer is entitled to be paid by

the Contractor, and/or (ii) the extension (if any) of the Defects Notification

Period in accordance with Sub-Clause 11.3 [Extension of Defects Notification

Period].

This amount may be included as a deduction in the Contract Price and Payment

Certificates. The Employer shall only be entitled to set off against or make any

deduction from an amount certified in a Payment Certificate, or to otherwise

claim against the Contractor, in accordance with this Sub-Clause.”

“Contractor’s Claims

20.1 If the Contractor considers himself to be entitled to any extension of the Time

for Completion and/or any additional payment, under any Clause of these

Conditions or otherwise in connection with the Contract, the Contractor shall

give notice to the Engineer describing the event or circumstance giving rise to

the claim. This notice shall be given as soon as practicable, and not later than

28 days after the Contractor became aware, or should have become aware, of

the event or circumstance.

If the Contractor fails to give notice of a claim within such period of 28 days,

the Time for Completion shall not be extended, the Contractor shall not be

entitled to additional payment, and the employer shall be discharged from all

liability in connection with the claim. Otherwise, the following provisions of

this Sub-Clause shall apply.

The Contractor shall also submit any other notices which are required by the

Contract, and supporting particulars for the claim, all as relevant to such event

or circumstance.

The Contractor shall keep such contemporary records as may be necessary to

substantiate any claim, either on the Site or at another location acceptable to the

Engineer. Without admitting the Employer's liability, the Engineer may, after

receiving any notice under this Sub-Clause, monitor the record-keeping and/or

instruct the Contractor to keep further contemporary records. The Contractor

shall permit the Engineer to inspect all these records, and shall (if instructed)

submit copies to the Engineer.

Within 42 days after the Contractor became aware (or should have become

aware) of the event or circumstance giving rise to the claim, or within such

other period as may be proposed by the Contractor and approved by the

Engineer, the Contractor shall send to the Engineer a fully detailed claim which

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 8

Page 9: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

includes full supporting particulars of the basis of the claim and of the extension

of time and/or additional payment claimed. If the event or circumstance giving

rise to the claim has a continuing effect:

(a) this fully detailed claim shall be considered as interim;

(b) the Contractor shall send further interim claims at monthly intervals,

giving the accumulated delay and/or amount claimed, and such further

particulars as the Engineer may reasonably require; and

(c) the Contractor shall send a final claim within 28 days after the end of the

effects resulting from the event or circumstance, or within such other

period as may be proposed by the Contractor and approved by the

Engineer.

Within 42 days after receiving a claim or any further particulars supporting a

previous claim, or within such other period as may be proposed by the Engineer

and approved by the Contractor, the Engineer shall respond with approval or

disapproval and detailed comments. He may also request any necessary further

particulars, but shall nevertheless give his response on the principles of the claim

within such time.

Each Payment Certificate shall include such amounts for any claim as have been

reasonably substantiated as due under the relevant provision of the Contract.

Unless and until the particulars supplied are sufficient to substantiate the whole of

the claim, the Contractor shall only be entitled to payment for such part of the

claim as he has been able to substantiate.

The Engineer shall proceed in accordance with Sub-Clause 3.5

[Determinations] to agree or determine (i) the extension (if any) of the Time for

Completion (before or after its expiry) in accordance with Sub-Clause 8.4

[Extension of Time for Completion], and/or (ii) the additional payment (if any)

to which the Contractor is entitled under the Contract.

The requirements of this Sub-Clause are in addition to those of any other Sub-

Clause which may apply to a claim. If the Contractor fails to comply with this

or another Sub-Clause in relation to any claim, any extension of time and/or

additional payment shall take account of the extent (if any) to which the failure

has prevented or prejudiced proper investigation of the claim, unless the claim is

excluded under the second paragraph of this Sub-Clause.”

4.4 As can be seen from the above provisions, although both claim procedures start with an

event or circumstance entitling the party to make a claim under one of the sub-clauses

of the contract and end with the provisions of Sub-Clause 3.5, quoted below, the

intermediate steps are different. Sub-Clauses 2.5, 3.5 and 20.1 are essentially the same

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 9

Page 10: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

for the 1999 Red and Yellow Forms, but they differ slightly in the Silver Form in that

the “Engineer” is replaced by the “Employer”.9

“Determinations

3.5 Whenever these Conditions provide that the Engineer shall proceed in

accordance with this Sub-Clause 3.5 to agree or determine any matter, the

Engineer shall consult with each Party in an endeavour to reach agreement. If

agreement is not achieved, the Engineer shall make a fair determination in

accordance with the Contract, taking due regard of all relevant circumstances.

The Engineer shall give notice to both Parties of each agreement or

determination, with supporting particulars. Each Party shall give effect to each

agreement or determination unless and until revised under Clause 20 [Claims,

Disputes and Arbitration].”10

4.5 The provisions of Sub-Clauses 2.5 and 20.1 can be arranged in the following sequential

steps, simplifying the complex wording in these two sub-clauses. For Sub-Clause 2.5:

1. Step 1: An event or circumstance occurs with the potential of a claim by the

Employer against the Contractor under any clause of the Contract Conditions or

otherwise in connection with the Contract.

2. Step 2: The Employer or the Engineer should give notice and particulars of the

claim to the Contractor. This notice should be given with the following in mind:

2.1 It should be given as soon as practicable after the Employer became aware

of the event or circumstance.

2.2 A notice relating to an extension of the Defects Notification Period should

be given before the expiry of such period.

9 Although the wording of the three Forms of Contract is very similar and each contains 20 Clauses, there are

very important differences between them. The reader is advised to establish whenever relevant these precise

differences in wording. Chapter 27 of the Author’s book referred to in footnote 2 above provides a comparative

analysis between the texts of three Major Forms: Red, Yellow and Silver. 10 Sub-Clause 3.5 of the three Major Forms of FIDIC is a very important clause from the point of view of

Claims and Dispute Resolution. It is referred to throughout the Conditions in 27 Sub-Clause: 1.9, Delayed

Drawings or Instructions; 2.1, Right to Access to the Site; 2.5, Employer’s Claims; 3.2, Delegation by the

Engineer; 4.7, Setting Out; 4.12, Unforeseeable Physical Conditions; 4.19, Electricity, Water and Gas ; 4.20,

Employer’s Equipment and Free-Issue Material; 4.24, Fossils; 7.4, Testing; 8.9, Consequences of Suspension;

9.4, Failure to Pass Tests on Completion; 10.2, Taking Over of Parts of the Works; 10.3, Interference with Tests

on Completion; 11.4, Failure to Remedy Defects; 11.8, Contractor to Search; 12.3, Evaluation; 12.4, Omissions;

13.2, Value Engineering; 13.7, Adjustments for Changes in Legislation; 14.4, Schedule of Payments; 15.3,

Valuation at Date of Termination; 16.1, Contractor’s Entitlement to Suspend Work; 17.4, Consequences of

Employer’s Risks; 19.4, Consequences of Force Majeure; 20.1, Contractor’s Claims.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 10

Page 11: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

2.3 Notice is not required for payments due under Sub-Clauses 4.19, 4.20, or

for other services requested by the Contractor.

2.4 Supporting substantiating particulars should also be submitted with the

notice specifying the basis of the claim.

3. Step 3: The Engineer should then proceed in accordance with Sub-Clause 3.5 to

agree or determine (i) the amount (if any) which the Employer is entitled to be

paid by the Contractor, and/or (ii) the extension (if any) of the DNP in accordance

with Sub-Clause 11.3.

4. Step 4: The Engineer should consult with each Party in an endeavour to reach

agreement, failing which he is required to make a fair determination in

accordance with the Contract.

5. Step 5: If agreement between the parties is achieved, the Engineer is required to

give a notice with supporting particulars. Otherwise, he is required to give a

notice of his determination with supporting particulars.

6. Step 6: The amount determined may be included as a deduction in the Contract

Price and Payment Certificates. The Employer shall only be entitled to set off

against or make any deduction from an amount certified in a Payment Certificate,

or to otherwise claim against the Contractor.

7. Step 7: If the Engineer’s determination is not acceptable to any of the Parties, the

dispute arising should be resolved in accordance with Sub-Clauses 20.2 to 20.8.

4.6 For Sub-Clause 20.1, the procedural steps may be presented as follows:

1. Step 1: An event or circumstance occurs with the potential of a claim under any

clause of the Contract Conditions or otherwise in connection with the Contract.

2. Step 2: The Contractor should give notice of the claim to the Engineer describing

the event or circumstance giving rise to the claim. This notice should be given

with the following in mind:

2.1 It should be given as soon as practicable; and not later than 28 days after

the Contractor became aware, or should have become aware, of the event

or circumstance. Failure to do so is fatal to the claim.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 11

Page 12: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

2.2 All supporting particulars for the claim, as relevant to such event or

circumstance, should also be submitted.

2.3 Any other notices required by the Contract should also be submitted.

3. Step 3: The Contractor should keep substantiating contemporary records, which

the Engineer may monitor and/or instruct the Contractor to keep further

contemporary records.

4. Step 4: Within 42 days of the event, the Contractor should submit a fully detailed

claim which includes full supporting particulars of the claim. The period may be

varied if approved by the Engineer. If the event or circumstance giving rise to the

claim has a continuing effect:

(a) this fully detailed claim shall be considered as interim;

(b) the Contractor should submit further interim claims and any further

particulars at monthly intervals, giving the accumulated effect; and

(c) the Contractor should submit a final claim within 28 days after the end of

the effects resulting from the event, or within such other period approved

by the Engineer.

5. Step 5: Within 42 days after receiving a claim or any further particulars

supporting a previous claim, the Engineer should respond with approval or

disapproval and detailed comments. He may also request any necessary further

particulars, but shall nevertheless give his response on the principles of the claim

within such time. This period may be varied if approved by the Contractor.

6. Step 6: Substantiated amounts for any claim should be included in each Payment

Certificate. It is to be noted that the requirements of Sub-Clause 20.1 are in

addition to those of any other Sub-Clause which may apply to the claim and

failure to comply preventing or prejudicing proper investigation should be taken

into account by the Engineer.

7. Step 7: The Engineer should then proceed in accordance with Sub-Clause 3.5 to

agree or determine (i) the extension of time (if any) and/or (ii) the additional

payment (if any) to which the Contractor is entitled under the Contract.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 12

Page 13: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

8. Step 8: The Engineer should consult with each Party in an endeavour to reach

agreement, failing which he is required to make a fair determination in

accordance with the Contract.

9. Step 9: If agreement between the parties is achieved, the Engineer is required to

give a notice with supporting particulars. Otherwise, he is required to give a

notice of his determination with supporting particulars.

10. Step 10: Each Payment Certificate shall include such amounts for any claim as

have been reasonably substantiated as due under the relevant provision of the

Contract.

11. Step 11: If the Engineer’s determination is not acceptable to any of the Parties, the

dispute arising should be resolved in accordance with Sub-Clauses 20.2 to 20.8.

4.7 Due to the numerous steps in these procedures and the different consequences that

might follow, it is perhaps easier to explain and better to understand them by using flow

charts, as illustrated below. Figures No. 1(a) and 1(b) show the procedure for the

Employer’s claims and Figures No. 2(a), 2(b) and 2(c) show the procedure for the

Contractor’s claims, each with its own steps from the time that the event or

circumstance occurs until the claim is properly dealt with or a dispute arises. If a

dispute does arise, then irrespective of whether it is the result of an Employer’s claim or

a Contractor’s claim, it falls to be resolved under Sub-Clauses 20.2 to 20.8 of the 1999

FIDIC contracts for major works.

4.8 Besides the different claim procedures adopted in the 1999 FIDIC contracts for major

works to those in the 1987 Red Book, two important questions arise as a result of the

provisions of Sub-Clause 3.5. The first relates to the precise meaning of the word

“fair” in the phrase “the Engineer shall make a fair determination” in the first

paragraph of the sub-clause. This word embodies a broad and elastic concept that is

extremely hard to capture in a precise manner. Attempts have been made to grapple

with the meaning of that term in a number of court cases. In a case in the New Zealand

Court of Appeal, Cooke J, said referring to Hatrick v Nelson Carlton Construction

[1964] NZLR 72, ‘In Hatrick the term “fairness” was avoided in the judgments,

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 13

Page 14: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

Richmond J saying that he resisted it partly because of its vagueness and partly

because it might be regarded as equivalent to natural justice. ….. Fairness is a broad

and even elastic concept, but it is not altogether the worse for that. In relation to

persons bound to act judicially fairness requires compliance with the rules of natural

justice. In other cases this is not necessarily so.’11

In the subsequent Amec case in the

English Court of Appeal, referred to in paragraph 4.12 and footnote 14 below, Lord

Justice May said ‘I would not be coy about saying that the Engineer has to act “fairly”,

so long as what is regarded as fair is flexible and tempered to the particular facts and

occasion. … Fairness also entitles one or both of the parties to ask for a speedy

decision, if limitation is becoming a problem; and fairness obliges the Engineer, I

think, to give a speedy decision in such circumstances, provided that it is given honestly

and independently and that it is in truth a properly considered decision.’ So, it seems

that acting fairly has to be viewed in two different ways. When acting in a judicial

capacity, fairness requires “compliance with the rules of natural justice”, but in all

other situations, acting fairly is elastic and “flexible and tempered to the particular facts

and occasion”.

4.9 The second question that arises from Sub-Clause 3.5 of the 1999 FIDIC contracts for

major works relates to its final sentence: “Each Party shall give effect to each

agreement or determination unless and until revised under Clause 20”. The question

is: What happens if one or all the parties do not “give effect to each agreement or

determination”. Presumably, the matter becomes a dispute and has to be dealt with

under the remaining part of Clause 20? But then, what is the definition of a dispute and

how and when does it precisely arise?

4.10 The questions posed in the preceding paragraphs form some of the very contentious

issues that are usually met under the Conditions of Contract for construction project.

Litigation and arbitration in the construction field has frequently commenced with such

an issue posed from the beginning, which has usually to be resolved first as a

11 Quoted from Cooke J, in Canterbury Pipe Lines v The Christchurch Drainage Board (1979) 16 BLR 76,

at 98, sitting in the New Zealand Court of Appeal. He added that

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 14

Page 15: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

preliminary point before dealing with the merits of the case.12

It is therefore of great

general interest and importance, particularly as there is usually a great deal of money at

stake.

4.11 In a recent case in the English Technology and Construction Court, the judge had to

deal with this specific point under Clause 66 of the standard ICE (Institution of Civil

Engineers) Conditions of Contract, which has similar, but not precisely the same,

procedures. In that case, having reviewed the authorities, Jackson J. derived the

following propositions:13

“1. The word “dispute” which occurs in many arbitration clauses and also in

section 108 of the Housing Grants Act should be given its normal meaning. It does

not have some special or unusual meaning conferred upon it by lawyers.

2. Despite the simple meaning of the word “dispute”, there has been much

litigation over the years as to whether or not disputes existed in particular

situations. This litigation has not generated any hard-edged legal rules as to what

is or is not a dispute. However, the accumulating judicial decisions have produced

helpful guidance.

3. The mere fact that one party (whom I shall call “the claimant”) notifies the other

party (whom I shall call “the respondent”) of a claim does not automatically and

immediately give rise to a dispute. It is clear, both as a matter of language and from

judicial decisions, that a dispute does not arise unless and until it emerges that the

claim is not admitted.

4. The circumstances from which it may emerge that a claim is not admitted are

Protean. For example, there may be an express rejection of the claim. There may be

discussions between the parties from which objectively it is to be inferred that the

claim is not admitted. The respondent may prevaricate, thus giving rise to the

inference that he does not admit the claim. The respondent may simply remain

silent for a period of time, thus giving rise to the same inference.

5. The period of time for which a respondent may remain silent before a dispute is

to be inferred depends heavily upon the facts of the case and the contractual

structure. Where the gist of the claim is well known and it is obviously

controversial, a very short period of silence may suffice to give rise to this

inference. Where the claim is notified to some agent of the respondent who has a

legal duty to consider the claim independently and then give a considered response,

12 See Chapter 16 of the Author’s book quoted in footnote 2 above. 13 Amec Civil Engineering Ltd v Secretary of State for Transport, [2004] EWHC 2339 (TCC).

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 15

Page 16: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

a longer period of time may be required before it can be inferred that mere silence

gives rise to a dispute.

6. If the claimant imposes upon the respondent a deadline for responding to the

claim, that deadline does not have the automatic effect of curtailing what would

otherwise be a reasonable time for responding. On the other hand, a stated

deadline and the reasons for its imposition may be relevant factors when the court

comes to consider what is a reasonable time for responding.

7. If the claim as presented by the claimant is so nebulous and ill-defined that the

respondent cannot sensibly respond to it, neither silence by the respondent nor even

an express non-admission is likely to give rise to a dispute for the purposes of

arbitration or adjudication.”

4.12 In a subsequent case in England, Clarke LJ quoted Jackson J’s seven propositions and

accepted them:14

“63. For my part I would accept those propositions as broadly correct. I entirely

accept that all depends on the circumstances of the particular case. I would, in

particular, endorse the general approach that while the mere making of a claim

does not amount to a dispute, a dispute will be held to exist once it can reasonably

be inferred that a claim is not admitted. I note that Jackson J does not endorse the

suggestion in some of the cases, either that a dispute may not arise until negotiation

or discussion have been concluded, or that a dispute should not be likely inferred.

In my opinion he was right not to do so.

64. It appears to me that negotiation and discussion are likely to be more consistent

with the existence of a dispute, albeit an as yet unresolved dispute, than with an

absence of a dispute. It also appears to me that the court is likely to be willing

readily to infer that a claim is not admitted and that a dispute exists so that it can

be referred to arbitration or adjudication. I make these observations in the hope

that they may be of some assistance and not because I detect any disagreement

between them and the propositions advanced by Jackson J.”

4.13 The decision of Jackson J in the Amec case was appealed to the English Court of

Appeal where it came before Lord Justice May, Lord Justice Rix and Lord Justice

Hooper. The Court approved Jackson J’s decision and made further observations

regarding other important areas and issues that are frequently debated in construction

disputes. The logical analysis of the decision in the Court of Appeal is well worth

reading and considering in full by all construction professionals. These issues are

14 Collins (Contractors) Limited v Baltic Quay Management (1994) Limited [2004] EWCA Civ 1757.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 16

Page 17: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

outside the scope of this paper except those referred to above and perhaps one other,

which is dealt with in following paragraph. Of course, this decision is binding on all

lower courts and on arbitrators in England and Wales; and is persuasive in other

common law countries. However, it is suggested here that its logic ought to be

followed also in all international arbitrations where the same issues are dealt with.15

4.14 Although not of immediate relevance to the 1999 FIDIC contracts for major works, but

to the earlier FIDIC Forms of Contract, an interesting point was also decided in this

appeal. It is the difference between the words “difference” and “dispute”, which had

eluded lawyers for some time.16

In his judgment, Lord Justice May discussing Clause

66 of the ICE Contract stated that ‘Clause 66 refers, not only to a “dispute”, but also to

a “difference”. “Dispute or difference” seems to me to be less hard-edged than

“dispute” alone’. Lord Justice Rix added in this connection: “I agree that the word

“difference” probably goes wider than the concept of a “dispute”.

15 Amec Civil Engineering Ltd v Secretary of State for Transport, [2005] EWCA Civ 291. 16 In the Author’s book on the FIDIC Forms of Contract, which was first published in 1991, the author

suggested that the word “difference” is wider in concept than the word “dispute”, but some lawyers disagreed,

see page 150 of the third edition of the book.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 17

Page 18: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

An event or circumstance occurs, of which the Em* considers

himself to be entitled to payment and/or to any extension of the

Defects Notification Period, the Em or the E* shall give notice and

particulars to the C under any clause of the Conditions or

otherwise.

STEP 1

STEP 2.1 Does the Em or E give notice to the C* as

soon as practicable after the Employer

became aware of the event or

circumstances giving rise to the claim of

entitlement?

YesNo

No notice is required for payments under Sub-Clauses

4.19 and 4.20, or for services requested by the C.

Notice for extension of the DNP shall be given before to

the expiry of such period.

The Contract

Conditions are

silent on the

consequences in

that connection.

No

STEP 2.4

Does the Em or E give the C

the particulars required with

the notice?Yes

Proceed to Sub-Clause 3.5 of the Contract Conditions, as in Figure 1(b)

The particulars shall specify the Clause or other basis of the

claim, and shall include substantiation of the amount and/or

extension to which the Em considers himself to be entitled in

connection with the Contract.

STEP 3

STEPS

2.2 & 2.3

* In these Flow Charts, Figures 1 & 2 , Em = Employer; E = Engineer; and C = Contractor.

Figure No. 1(a). Claim Procedure under Sub-Clause 2.5 of the 1999 FIDIC

contracts for major works.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 18

Page 19: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

The E shall then proceed in accordance with Sub-Clause 3.5 to agree

or determine (i) the amount (if any) which the Em is entitled to be paid

by the C, and/or (ii) the extension (if any) of the DNP in accordance

with Sub-Clause 11.3. S-C 2.5

Sub-Clause 3.5 requires the E to consult with each Party in an endeavour

to reach agreement. If agreement is not achieved, the Engineer shall

make a fair determination in accordance with the Contract.

No

STEP 4

STEP 3

Continued from Figure 1(a) above

End

Yes

Yes

No

Does the Engineer proceed

in accordance with S-C 3.5

& consult with each party?

Is agreement between

the parties achieved &

notice with particulars

given by the E?

This amount may be included

as a deduction in the Contract

Price & Payment Certificate,

‘PC’. The Em shall only be

entitled to set off against or

make any deduction from an

amount certified in a PC, or to

otherwise claim against the C,

under this Sub-Clause.

A dispute results & the provisions of Sub-Clauses 20.3 to 20.8 apply

Does the E make a

fair determination &

give notice with

support particulars?

No

Yes

Is determination

acceptable to the P’s?

No

Yes

STEP 6

STEP 5 a STEP 5b

STEP 7

Figure No. 1(b). Claim Procedure under Sub-Clause 2.5 and continued as

required under Sub-Clause 3.5 of the 1999 FIDIC contracts for major works.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 19

Page 20: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

An event or circumstance occurs, of which the C became

aware or should have become aware, and for which he

considers himself to be entitled to EoT and/or additional

payment, under any clause of the Conditions or

otherwise.

STEP 1

STEPS

2 & 2.1 Does the C give notice to the E

within 28 days after the event

or circumstance giving rise to a

claim of entitlement?

Yes No

The C should also submit supporting particulars

and notices as required by the Contract.

No entitlement to EoT &

no additional payment,

and the employer is

discharged from all

liability in that connection.

No

STEPS 2.2 & 2.3

STEPS 4 a to c

End

Does the event or circumstance

giving rise to the claim have a

continuing effect?Yes

Proceed to Figure 2b below

(a) the fully detailed claim shall be considered as interim;

(b) the C to send further monthly interim claims, giving the

accumulated delay &/or amount claimed, and such further

particulars as the E may reasonably require; and

(c) the C to send a final claim within 28 days after the end of the

effects resulting from the event or circumstance.**

Within 42 days after the C became aware (or should have

become aware) of the event or circumstance,** the C should send to the E

fully detailed claim which includes full supporting particulars of the basis

of the claim and of the EoT and/or additional payment claimed.

STEP 3

STEP 4

The C is to keep & E to monitor contemporaneous records.

** or within such other period as may be proposed by the C and approved by the E.

Figure No. 2(a). Claim Procedure under Sub-Clause 20.1of the 1999 FIDIC

contracts for major works

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 20

Page 21: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

Any EoT and/or additional payment

shall take account of the extent (if

any) to which failure to comply has

prevented or prejudiced proper

investigation of the claim.

NoYes

No

STEP 6

STEP 5

Does the C comply with this

Sub-Clause & all others?

Continued from Figure 2(a) above

Within 42 days after receiving a claim or any further particulars supporting a

previous claim,** the E shall respond with approval or disapproval and detailed

comments. He may also request any necessary further particulars, but shall

nevertheless give his response on the principles of the claim within such time.

End

Yes

Yes

No

Does the Engineer

comply with this clause?

Are the Parties satisfied

with the E’s Response?

i i

The provisions of

Sub-Clause 3.5 apply

Each Payment Certificate shall include such amounts

for any claim as have been reasonably substantiated as

due under the relevant provision of the Contract.

Unless and until the particulars supplied are sufficient

to substantiate the whole of the claim, the Contractor

shall only be entitled to payment for such part of the

claim as he has been able to substantiate.

** or within such other period as may be proposed by the E and approved by the C,

Figure No. 2(b). Claim Procedure under Sub-Clause 20.1 of the 1999 FIDIC

contracts for major works, continued below.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 21

Page 22: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

The E shall proceed in accordance with Sub-Clause 3.5 to agree or

determine (i) the EoT (if any) for Completion (before or after its expiry) in

accordance with Sub-Clause 8.4, and/or (ii) the additional payment (if any)

to which the C is entitled under the Contract. S-C 20.1

Sub-Clause 3.5 requires the E to consult with each Party in an endeavour

to reach agreement. If agreement is not achieved, the Engineer shall make

a fair determination in accordance with the Contract.

No

STEP 9 b

STEP 7

Continued from Figure 2(b) above

End

Yes

Yes

No

Does the Engineer proceed

in accordance with S-C 3.5

& consult with each party?

Is agreement between

the parties achieved &

notice with particulars

given by the E?

Each Payment Certificate shall

include such amounts for any claim as

have been reasonably substantiated as

due under the relevant provision of

the Contract. Unless and until the

particulars supplied are sufficient to

substantiate the whole of the claim,

the Contractor shall only be entitled

to payment for such part of the claim

as he has been able to substantiate.

A dispute results & the provisions of Sub-Clauses 20.3 to 20.8 apply

Does the E make a

fair determination &

give notice with

support particulars?

No

Yes

Is determination

acceptable to the P’s?

Yes

No

STEP 9a

STEP 10

STEP 11

STEP 8

** or within such other period as may be proposed by the C and approved by the E.Figure No. 2(c). Claim Procedure under Sub-Clause 20.1 and continued as

required under Sub-Clause 3.5 of the 1999 FIDIC contracts for major works.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 22

Page 23: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

5. Dispute Resolution

5.1 In a comparative sense, the multi-tier dispute resolution procedure of Clause 67 of

FIDIC’s well established fourth edition of the Red Book (1987) has been retained in

the 1999 FIDIC contracts for major works, but the role of the Engineer as an

adjudicator of disputes has been relegated in favour of allocating the role of

adjudication to a board of in dependent professionals, usually three, referred to as

Dispute Adjudication Board, “DAB”. However, the role of the DAB has been made

wider to encompass dispute avoidance as well as dispute resolution. Dispute

avoidance can only be used if both parties wish it to take place whereas dispute

resolution can be initiated by one party alone once a dispute arises. 17

5.2 The dispute resolution procedure of the 1999 FIDIC contracts for major works is

contained in Sub-Clauses 20.2 to 20.8 of the Contract Conditions. As mentioned

above, it is also a multi-tier process. It starts with a dispute adjudication procedure

followed by an amicable dispute resolution mechanism and if both of these fail, then

arbitration. Once again, due to the fact that the procedure is a difficult and complex

one, it is easier explained and better understood by using flow charts. Figure No. 3

shows the procedure itself and Figure No. 4 illustrates the compliance requirements

contained in the fourth paragraph of Sub-Clause 20.4. As can be seen from Figure

No. 3, essentially, the procedure comprises only five steps that can be summarised as

follows:

1. Step 1: A dispute arises.

2. Step 2: The dispute is referred to the DAB in writing for its decision, under Sub-

Clause 20.4.

3. Step 3: The DAB gives notice of its decision within 84 days or it fails to give a

decision within that period.

17 As this topic is extremely wide and goes beyond the scope of this paper, interested readers could refer to

Chapter 26 of the Author’s book quoted in footnote 2 above; and also to a paper by the author on “Dispute

Boards & Dispute Resolution” presented at an ICC/FIDIC Conference held in Paris on 17th and 18th of October

2005.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 23

Page 24: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

4. Step 4: The Parties react to the decision of the DAB, which could be one of two

possibilities:

(a) Both Parties are satisfied with that decision, the dispute is resolved and

such decision becomes final and binding; or

(b) At least one of the Parties is dissatisfied with the decision of the DAB, or

with its lack of decision, and thus notifies the other Party of its

dissatisfaction within 28 days.18

In this case, the Parties are given 56 days

to attempt resolving their dispute by amicable settlement, under Sub-

Clause 20.5. If the attempt is successful, the dispute is resolved. If not,

step 5 applies.

5. Step 5: If the attempt to amicably resolve the dispute fails, such dispute is to be

finally settled by international arbitration, under Sub-Clause 20.6.

5.3 It is important to note that irrespective of whether the dispute is resolved through steps

4(a) or 4(b), the decision of the DAB becomes binding on the Parties pursuant to the

terms of Sub-Clause 20.4, which provides in its fourth paragraph the following

wording: “The decision shall be binding on both Parties, who shall promptly give

effect to it unless and until it shall be revised in an amicable settlement or an arbitral

award as described below. …”.

5.4 The effect of this provision on the decision of the DAB is known technically as a

“temporarily final & binding” effect. The decision must be complied with by both

parties, which is a characteristic feature of the FIDIC DAB procedure under the 1999

FIDIC contracts for major works distinguishing it from the DRB procedure under other

forms of contract. The decision becomes, in effect, a contractual obligation on both

Parties such that non-compliance with it by either of them is a breach of contract and

the Party in breach would be liable in damages. However, such liability for damages on

its own is:

18 If the notice of dissatisfaction is not given within the required 28 days, the decision of the DAB will

become final and binding and the provisions relating to Step 4(a) will apply.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 24

Page 25: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

** The decision shall be binding on both Parties, who shall promptly give effect to it unless and until it

shall be revised in an amicable settlement or an arbitral award, see 4th

paragraph of Sub-Clause 20.4.

A dispute arises under

Sub-Clause 20.1 or 2.5

The dispute is referred to the DAB for its

decision under Sub-Clause 20.4

DAB provides its decision within

84 days under Sub-Clause 20.4 **DAB fails to do so within 84

days under Sub-Clause 20.4

STEP 1

STEP 2

STEP 3

STEP 4

or

Is either Party dissatisfied with

the decision? No

Does that Party give its notice

of dissatisfaction under 20.4

in the time allowed (28 days)?

STEP 4b

No

Yes

The Parties have 56

days to resolve the

Dispute amicably, Sub-

Clause 20.5

Is the dispute

settled amicably? YesDispute

is

settled

Dispute shall be finally settled by International Arbitration, Sub-Clause 20.6

STEP 5

No

Dispute is settled and the

decision is final and

binding, Sub-Clause 20.4

STEP 4a

Yes

Figure No. 3. Dispute Resolution Procedure under Clause 20 of

the 1999 FIDIC contracts for major works.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 25

Page 26: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

** The decision shall be binding on both Parties, who shall promptly give effect to it unless and until it

shall be revised in an amicable settlement or an arbitral award, see 4th

paragraph of Sub-Clause 20.4.

DAB provides its decision within

84 days under Sub-Clause 20.4**

Is either Party dissatisfied?No Yes

NoDoes that Party give its notice of

dissatisfaction within 28 days?

STEP 3

STEP 4STEP 4a STEP 4b

Proceed under Sub-

Clauses 20.5 & 20.6.

Yes

Do the Parties comply

with DAB’s decision?

End

Yes

Proceed to Sub-

Clause 20.7 & refer

the failure itself to

arbitration

No Yes

Dispute will

be settled

through

arbitration

GAP

Non-compliant Party is in

breach of contract & subject to

damages

No

The Decision is

final & binding

Do the Parties comply

with the DAB’s decision?

Figure No. 4. Compliance with the Decision of the DAB under the 1999

FIDIC contracts for major works.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 26

Page 27: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

1. Insufficient to ensure that the decision of the DAB is complied with “promptly”,

since

(a) The dissatisfied party might feel so strongly against the decision that it might

ignore it and continue its work, or the position it had adopted, in breach of the

DAB’s decision, taking on board the risk that in the end, at some future date,

it might be vindicated and found not to be liable in damages;

(b) The dissatisfied party might simply keep silent and not respond;

2. Unlikely to be an appropriate remedy in the circumstances of a dispute, since the

dispute might require instantaneous attention such as the case where the DAB’s

decision is in connection with allegations of defective design, material or

workmanship under Sub-Clause 15.1;19

and

3. Not decisive enough to ensure the smooth running of a project or a contract to

proper completion, since additional investigation, instruction or drawing might be

quickly required.

5.5 Sub-Clause 20.7, in its present wording quoted below, resolves this problem in the

event that a DAB’s decision is not complied with, but unfortunately it only deals with

the situation when the decision of the DAB has become final and binding.

Accordingly, as can be seen from Figure No. 4 above, the compliance by the Parties

with the decision of the DAB where the decision has not become final and binding, i.e.

where one of the Parties is dissatisfied with the decision, remains without a prompt and

decisive mechanism to enforce it promptly. For completeness sake, the present

wording of Sub-Clause 20.7 is as follows:

“20.7 Failure to Comply with Dispute Adjudication Board’s Decision

In the event that:

(a) neither Party has given notice of dissatisfaction within the period stated in

Sub-Clause 20.4 [Obtaining Dispute Adjudication Board’s Decision],

(b) the DAB’s related decision (if any) has become final and binding, and

(c) a Party fails to comply with this decision,

19 Failure to comply with a Notice to Correct under Sub-Clause 15.1 entitles the Employer to terminate the

Contract under Sub-Clause 15.2 with all of its serious consequences.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 27

Page 28: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

then the other Party may, without prejudice to any other rights it may have, refer

the failure itself to arbitration under Sub-Clause 20.6 [Arbitration]. Sub-Clause

20.4 [Obtaining Dispute Adjudication Board’s Decision] and Sub-Clause 20.5

[Amicable Settlement] shall not apply to this reference.”

5.6 The provisions that describe the situation where one Party is dissatisfied with the

DAB’s decision are contained in the fifth and sixth paragraphs of Sub-Clause 20.4.

They provide that the dissatisfied Party must give a notice to this effect to the other

Party within 28 days of the DAB’s decision. These two paragraphs also provide that,

except as stated elsewhere (Sub-Clauses 20.7 and 20.8), neither Party shall be entitled

to proceed to arbitration of the dispute unless such notice of dissatisfaction has been

given.

5.7 There are three consequences to a properly given decision by the DAB under Sub-

Clause 20.4 of the 1999 FIDIC contracts for major works. These are as follows:

1. The decision of the DAB affects the Parties’ rights and obligations and as such it is

binding on the Parties who are required to “promptly give effect to it unless and

until it shall be revised in an amicable settlement or an arbitral award”, as

described in Sub-Clauses 20.5 and 20.6 of the contract conditions.

2. Sub-clause 20.4 also stipulates that “If the DAB has given its decision and no

notice of dissatisfaction has been given by either Party within 28 days after it

received the DAB’s decision, then the decision shall become final and binding

upon both Parties”. (emphasis added.)

3. However, if a notice of dissatisfaction is given by either Party within 28 days after

receiving the decision, setting out the matter in dispute and the reason(s) for

dissatisfaction, then both Parties are required to attempt to settle their dispute

amicably, as stipulated under Sub-Clause 20.5, before commencement of

arbitration. Furthermore, as set out in Sub-Clause 20.6, unless settled amicably, any

dispute in respect of which the DAB’s decision has not become final and binding

may be finally settled by international arbitration.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 28

Page 29: A Comparitive Analysis of the Claims & Dispute Resolution Provisions of FIDIC 1999 Major Forms of Contract

5.8 As a result of the first consequence, Sub-Clause 20.7 deals with the possibility of non-

compliance with the DAB’s decision. However, although the clear intention of Sub-

Clause 20.4 is that the DAB’s decision should be complied with promptly, unless and

until it is revised in a subsequent forum (amicable settlement or arbitration), and

irrespective of whether or not one of the Parties is dissatisfied with it, Sub-Clause 20.7

is worded in such a way that it only deals with the event where the Parties are satisfied

with the decision. The draftsmen did not deal with circumstances where the parties are

dissatisfied with the decision, leaving that situation without any prompt solution or

elucidation, hence creating a gap.

5.9 It is also worth noting in connection with the amicable dispute resolution requirement

in the 1987 Red Book and the 1999 FIDIC contracts for major works that it is

obligatory on the parties, and to correct the erroneous belief that some commentators

have that this is intended to be a “cooling off period”. There are two reasons for the

process being obligatory, the first is to remove any perceived idea that a proposal by

one party towards amicable settlement is a sign of weakness in its case and second

reason of making the process a mandatory step before reference to arbitration is the

avoidance of any possible blame being attached to the decision maker who pursues

amicable settlement of a dispute instead of the ultimate forum of arbitration.

5.10 Finally, it is worth mentioning that Sub-Clause 20.8 of the 1999 FIDIC contracts for

major works provides that where there is no DAB in place, any dispute arising should

proceed directly to arbitration without the benefit of the two intermediate steps of DAB

and Amicable Settlement. In this regard, it is in stark contrast with the provisions of

the 1987 Red Book, which required an Engineer’s decision before either party could

proceed to arbitration. That position presented a problem in circumstances where the

dispute arises after the works had been completed and the Engineer has departed from

the Site. This problem does not exist any longer in the 1999 FIDIC contracts for major

works.

Nael G. Bunni,

January 2006.

Comp’Analysis’FIDIC Contracts – © Nael G. Bunni 29