Upload
gregory-nick-toledo-veliz
View
52
Download
2
Embed Size (px)
Citation preview
A. Design of a Thickener
With the use of the batch sedimentation data collected from the column with slurry of
concentration 100g/L CaCO3, the continuous thickener parameters calculated were as follows:
Table 5. Continuous Thickener Design Parameters
Feed concentration (g CaCO3/L) 100
Feed rate (kg dry solids/hr) 30000
Underflow concentration (g CaCO3/L) 350
Thickener Cross-sectional Area 455.8957 m2
Diameter of Cylindrical Thickener (D) 24.10 m
Volume of Compression Zone 240.1858 m3
Height of Compression Zone 0.5268 m
Total Height of the Thickener (H) 2.2032 m
The unit area requirement for a certain concentration may be calculated using Equation
1 (Perry,2008).
⁄ ⁄
Equation 1
Where a is the unit area, is the concentration at the interfacial velocity and is the
concentration of the underflow. From the unit areas calculated, the largest value is used for the
calculation of the cross-sectional area of the thickener. Theory holds that for any specific
sedimentation set up, there exists a critical concentration which limits the settling rate of solids
in the fluid (Perry, 2008). Thus, in designing thickeners, the settling rates at different
concentration are considered to ensure that the area of the thickener is sufficient for satisfactory
clarification of the overflow and concentration of the underflow. A rate limiting layer is identified
and is used as the basis for the calculations. This layer corresponds to the layer in the
sedimentation set up that has the lowest capacity for the passage of the solid particles (Foust,
1980) and thus requires the largest area.
Table 6. Unit Area at Different Concentrations
Time, tl (min) Concentration of Slurry,
cl (g/cm3) Settling Velocity, vl
(cm/min) Unit Area, a (cm2 min/g)
10 0.1000 1.3000 5.4942
30 0.1057 1.0767 6.1348
40 0.1232 0.7625 6.9006
50 0.1542 0.4520 8.0227
60 0.1754 0.3250 8.7494
70 0.1935 0.2536 9.1179
90 0.2140 0.2011 9.0277
108 0.2329 0.1681 8.5443
120 0.2481 0.1479 7.9306
138 0.3756 0.0622 -3.1306
150 0.4505 0.0357 -17.8768
From the calculated values, the largest unit area is 9.1179 cm2 min/g. To solve for the final
thickener area, Equation 2 is used.
Equation 2
where is the mass feed rate of dry solids per unit time.
The volume required for the compression zone in the continuous thickener is given by
Equation 3 (Brown, 1950). This is equal to the sum of the volume occupied by the solids plus
the volume of the associated fluids.
( )
∫
Equation 3
where V = the volume of the compression zone = mass of solids per unit time = time in which the solids have reached the desired underflow concentration =time when all solids at critical concentration go to compression L =mass of liquid in compression zone S =mass of solid in compression zone
With the assumption that the concentration of the solids in the compression zone of a
continuous thickener at any time is the same as the average concentration of the compression
zone of the batch test at time equal to the retention time of the solids in the continuous
thickener, then the time required for the slurry in the batch test to pass from the critical
concentration to the desired underflow concentration is the retention time of the solids in the
continuous thickener (Brown, 1950). The plot of the height of the interface of the supernatant
liquid and the slurry versus time may be described by Equation 4.
( )
( ) Equation 4
Where z is the height of the interface at time t and is the height at infinite time.
If the batch sedimentation basis has an initial slurry concentration at its critical concentration,
that is when t0 corresponds to which is the height of the compression zone at critical
concentration cc, then plotting ( )
( ) versus time would give a straight line. Since the initial
concentration of the slurry in the experimental batch sedimentation was not at cc, then tc is
determined by extrapolating the compression curve from the critical point to zero time and then
locating the time when the upper interface is at a height halfway between the initial slurry height
z0 and the extrapolated zero-time compression zone height z0’ (Brown, 1950). The tc obtained
from the batch test was 9.4 min from Figure--.
The density of the slurry is constant at 1.0831 g/cm3 as well as the feed rate at 30000
kg/hr. To obtain the volume of the compression zone, the area under the curve in Figure 10 is
obtained and values were inputted to Equation 3.
The height was obtained by dividing the volume of the compression zone to the area.
Height allowances for the bottom pitch of the thickener, storage capacity and for the
submergence of feed were added to the initial computed height (Foust, 1980) to get the total
height of the thickener. Suggested allowances are given below:
For the pitch of the bottom 0.3048-0.6096 m
For the storage capacity to cover interruptions
or irregularities in discharge 0.3048-0.6096 m
For submergence of feed 0.3048-0.9144 m