99TricksandTraps

for

Microsoft®Project

2013and2016TheCasualUser’s“SurvivalGuide”

By

PaulEHarris

of

EastwoodHarrisPtyLtd

Page 3: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

©Copyright2016byEastwoodHarrisPtyLtd.Nopartofthispublicationmaybereproducedorusedinanyformorbyanymethodwithoutthewrittenpermissionoftheauthor.

Windows,XP,Microsoft®Project2000,Microsoft®ProjectStandard2003,Microsoft®P33rojectProfessional2003,Microsoft®ProjectStandard2007,Microsoft®ProjectProfessional2007,Microsoft®ProjectStandard2010,Microsoft®ProjectProfessional2010,Microsoft®ProjectStandard2013,Microsoft®ProjectProfessional2013,Microsoft®ProjectStandard2016,Microsoft®ProjectProfessional2016,PowerPoint,Word,VisioandExcelareregisteredtrademarksofMicrosoftCorporation.

Adobe®andAcrobat®areregisteredtrademarksofAdobeSystemsIncorporated.

Allothercompanyorproductnamesmaybetrademarksoftheirrespectiveowners.

ScreencaptureswerereprintedwithauthorizationfromMicrosoftCorporation.

ThispublicationwascreatedbyEastwoodHarrisPtyLtdandisnotaproductofMicrosoftCorporation.

DISCLAIMER

Theinformationcontainedinthisbookistothebestoftheauthor’sknowledgetrueandcorrect.Theauthorhasmadeeveryefforttoensureaccuracyofthispublication,butcannotbeheldresponsibleforanylossordamagearisingfromanyinformationinthisbook.

AUTHORANDPUBLISHER

PaulEHarris

EastwoodHarrisPtyLtd

POBox4032

DoncasterHeights3109

Victoria

Australia

[email protected]

http://www.eh.com.au

Tel:+61(0)411187701

Pleasesendanycommentsonthispublicationtotheauthor.

IwouldliketothankJesicaPaulaYaboforherassistanceinupdatingthisbookfromMicrosoftProject2007andMartinVaughnforproofreadingandvaluablesuggestions.

ISBN:978-1-925185-33-1Paperback

ISBN:978-1-925185-34-8eBook

25February2016

Page 4: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

CURRENTBOOKSPUBLISHEDBYEASTWOODHARRIS

99TricksandTrapsforMicrosoftOfficeProject-IncludingMicrosoftProject2000to2007

PlanningUsingPrimaveraProjectPlannerP3Version3.1-Revised2006

PlanningUsingPrimaveraSureTrakProjectManagerVersion3.0-Revised2006

ProjectPlanningandSchedulingUsingPrimaveraContractorVersion6.1-IncludingVersions4.1,5.0and6.1

PlanningandSchedulingUsingMicrosoftOfficeProject2007-IncludingMicrosoftProject2000to2003-Revised2009

PlanningandControlUsingMicrosoftProjectandPMBOK®GuideFourthEdition

PlanningandControlUsingMicrosoftProject2010andPMBOK®GuideFourthEdition

ProjectPlanning&ControlUsingPrimaveraP6Version7-ForallindustriesincludingVersions4to7Updated2012

PlanningandSchedulingUsingMicrosoftProject2010-Updated2013IncludingRevisedWorkshops

PlanningandControlUsingMicrosoftProject2010&PMBOK®GuideFifthEdition

PlanningandControlUsingMicrosoftProject2013

PlanningandControlUsingMicrosoftProject2013&PMBOK®GuideFifthEdition

PlanningandControlUsingMicrosoftProject2013

PlanningandControlUsingMicrosoftProject2013or2016&PMBOK®GuideFifthEdition

PlanningandControlUsingOraclePrimaveraP6-Versions8.2&8.3EPPMWeb

99TricksandTrapsforMicrosoftProject2013and2016

OraclePrimaveraP6Version8and15EPPMWebAdministratorsGuide

PlanningandControlUsingOraclePrimaveraP6Versions8.1to15.2PPMProfessional

PlanificaciónyControlUsandoOraclePrimaveraP6Versiones8.1a15.1PPMProfesional

规划和控制OraclePrimaveraP6应用版本8.1-15.1PPM专业版

PlanningandControlUsingOraclePrimaveraP6-Versions8.2to15.1EPPMWeb

Page 5: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

SERVICESOFFEREDBYEASTWOODHARRISPTYLTD

EastwoodHarrisspecializesinsettingupandrunningprojectcontrolssystemswithafocusonPrimaveraSystemsandMicrosoftProjectsoftware;weofferthefollowingservices:

ProjectPlanningandSchedulingTrainingCoursesusingOraclePrimaveraP6andMicrosoftOfficeProject

EastwoodHarrisoffersone-to-onetrainingtogetyournewschedulersupandrunningquickly,withoutthedelayofwaitingforthenextcourseandatthesametimebuildingupyourownprojectschedule.

Wealsorunin-housetrainingcoursesonanyofthesesoftwarepackages.Thisisaverycostefficientmethodoftrainingyourpersonnel.

Weareabletoassistyouinsettingupaschedulingenvironment.Thisincludesdesigningcodingstructures,writingprocedures,trainingandotherimplementationprocesses.

EastwoodHarriscanwritespecializedtrainingmaterialthatwillincorporateyourorganization’smethodologyintotheEastwoodHarristrainingmanualsanddevelopstudentworkshopstailoredtoyourrequirements.Projectpersonnelwillbeabletousethesebooksasreferencebooksafterthecourse.

SelectionandImplementationofProjectManagementSystems

EastwoodHarriswillassistyoubyconductinganinternalreviewofyourrequirementsandmatchthisrequirementanalysisagainstthefunctionalityofpackagedsoftware.

Wearethenabletoassistyouintheimplementationofthesesystems,includingwritingpoliciesandproceduresandtrainingpersonnel,toensureasmoothtransitiontoyournewsystem.

DisputeResolution

EastwoodHarrisisabletoanalyzeyoursubcontractor’sschedulesintheeventofclaimsandprovideyouwithaclearpictureofthescheduleinrelationtotheclaim.

ScheduleConversion

EastwoodHarrisisabletoconvertyourschedulesfromonesoftwarepackagetoanother.Theconversionofschedulesisoftentimeconsuming,soletusdoitforyou.

Pleasecontacttheauthorformoreinformationontheseservices.

Page 6: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

TABLEOFCONTENTS

1 IMPORTANTTHINGS

1.1 The“Delete”Key

1.2 TypingaDateorDraggingaTaskSetsaConstraint!

1.3 IndicatorsColumn

1.4 WhyAreTasksScheduledbeforethePredecessors?

1.4.1 UnderstandingtheActualStartDate

1.4.2 TasksWillAlwaysHonorTheirConstraintDates

1.5 TheProjectWillNotOpen!

1.6 TheLogicKeepsChanging!

1.7 WhyDoNewTasksHaveanEarlyStartConstraint?

1.8 RecommendedScheduleOptions

1.9 ManuallyScheduledandAutoScheduledTasks

1.10 SortingouttheMenus

2 CALENDARSURVIVALGUIDE

2.1 RoleoftheProjectCalendar

2.2 GuidelinesforCreatingCalendars

2.3 DisplayofDurationinDays

2.4 HowtoAssignTaskCalendars

2.5 OtherThingsTaskCalendarsAffect

2.5.1 Float

2.5.2 Lags

2.6 ResourceCalendars

2.7 WhichCalendaristheTaskUsing?

2.8 DefaultStartandEndTime

2.9 FinishVarianceCalculation

3 TRICKYSTUFF

3.1 TaskNamingIssues

3.2 TaskSplitting

3.2.1 WhatisSplitting?

Page 7: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

3.2.2 SplittingaTaskManually

3.2.3 SplittingIn-progressTasks

3.2.4 RemovingaBarSplit

3.2.5 HidingaBarSplit

3.3 DeadlineDate

3.4 NegativeandFreeFloatBars

3.5 WhereistheGantChartWizard?

3.6 AsLateAsPossibleConstraint

4 INTERESTINGFEATURES

4.1 WildcardFiltersforTextSearching

4.2 InteractiveFilters

4.3 AutoFilters

4.4 SelectingDates

4.5 UnderstandingStartandFinishMilestones

4.6 ConvertingaFinishMilestoneintoaStartMilestone

4.7 CreatingaHammockoraLEOTask

4.8 ElapsedDurations,LeadsandLags

4.8.1 ElapsedDurations

4.8.2 FloatonTaskswithElapsedDurations

4.8.3 ElapsedLeadsandLags

4.9 EstablishingTwoRelationshipsbetweenTwoTasks

4.10 Ladderscheduling

4.11 %Lags

4.12 TracingLogic

4.12.1 TaskDriversandTaskInspector

4.12.2 TracingtheLogic

4.12.3 TaskPath

5 MAKINGITLOOKRIGHT

5.1 DateFormatDangers

5.2 PreventingtheDateFormatfromChangingonOtherComputers

5.3 TheSmartWaytoCreateViews

Page 8: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

5.4 BarFormatting

5.4.1 BarDateFormat

5.4.2 BarHeights

5.4.3 AlwaysRollUpGanttBars

5.4.4 RoundBarstoWholeDays

5.5 PuttingTextonBars

5.6 FormatColors

5.7 HowtoStopTextWrapping

5.8 DisplayTaskswithoutSuccessorsasCritical

5.9 PreventingDescriptionsfromIndenting

5.10 ReducingColumnWidths

5.11 HowtoDisplayaTaskIDthatWillNotChange

5.12 HidingTaskInformation

5.12.1 HidingBars

5.12.2 HidingText

5.12.3 MarkingTasksInactive

5.13 AnchoraVerticalLinetoaMilestone

5.14 ZoomSliderDangers

5.15 WhyistheNon-workingTimeDisplayedIncorrectly?

5.16 DisplayinganS-Curve

5.17 DisplayingCumulativeHistogram

5.18 DisplayingaProjectSummaryTask

6 GETTINGITOUT-PRINTING

6.1 PrintingtoOnePageWide

6.2 PrintingaDateRange

6.3 PrintingaGanttChartandResourceGraphorUsageTableonOnePage

6.4 PrintingtheCalendar

6.5 HidingUnwantedBarsintheLegend

6.6 WhathasHappenedtotheManualPageBreaks?

7 RESOURCEBASICS

Page 9: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

7.1 HowManyResourcesShouldIHave?

7.2 TheBalanceBetweentheNumberofActivitiesandResources

7.3 DurationsandAssignmentsChangeasResourcesareAssigned

7.3.1 TaskType–FixedDuration,FixedUnits,FixedWork

7.3.2 EffortdrivenorNonEffortdriven?

7.3.3 TaskTypeandEffortdrivenOptions

7.4 AssigningResourcestoTasks

7.5 ResourcesandSummaryTasks

8 UPDATINGESSENTIALS

8.1 BaselinesandUpdatingaProject

8.2 WhichBaselineShouldBeUsed?

8.3 PrinciplesofUpdatingaProgram

8.4 In-progressTaskFinishDateCalculation

8.5 CurrentDateandStatusDate

8.6 AutoUpdatingUsingUpdateProject

8.7 MovingIncompleteWorkintotheFuturebySplitting

8.8 WhereistheTrackingToolbar?

8.9 WhyDoCalculationOptions–MoveendofcompletedpartsNotWork?

8.10 ComparingProgresswithBaseline

8.11 ProgressLines

8.12 SimpleProcedureforUpdatingaSchedule–UsingAutoStatus

8.13 ProcedureforDetailedUpdating

8.14 PreparingtoUpdatewithResources

8.15 UpdatingResources

9 CREATINGNEWPROJECTS

9.1 StandardizingProjects

9.2 Global.mpt

9.3 MicrosoftProjectTemplateChanges

9.4 UnderstandingTemplates

9.5 EastwoodHarrisTemplate

9.6 CopyingViews,TablesandFilters

Page 10: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

10 OTHERTHINGSOFINTEREST

10.1 EditingToolBars

10.2 DynamicallyLinkingCells

10.3 HowDoesNegativeFloatCalculateforSummaryActivities?

10.4 FloatandConstraints

10.5 UsingCustomFields

10.6 CustomColumnsFormulasandDrop-DownList

10.7 CustomOutlineCodes

10.7.1 DefineaCustomOutlineCodeStructure

10.7.2 AssigningtheCustomCodes

10.7.3 GroupingwithCustomData

10.7.4 GroupingwithCustomDatawithAutoFilters

10.8 ExportingtoExcel

10.9 TurningOffGettingStartedandotherPOPups

10.10 ContingentTime

10.11 EarnedValue

10.12 DoIHaveAlltheScope?

10.12.1 StakeholderAnalysis

10.12.2 RiskAnalysis

10.13 PreparingforDisputeResolution

10.13.1 KeepingElectronicCopiesofEachUpdate

10.13.2 ClearlyRecordtheEffectofEachChange

11 INDEX

Page 11: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

1IMPORTANTTHINGSReadersofthisbookshouldbefamiliarwith:

❖ ThebasicfunctionsofMicrosoftProjectand

❖ ThetheoryofCriticalPathincludingEarlydates,LatedatesandFloatcalculations.MicrosoftProjectusesSlackfortermFloat.

MicrosoftProjecthasfunctionsthatcatchoutusers.Youshouldunderstandthesefunctionsandbeabletoidentifywhentheyhavebeenusedinadvertently.

1.1The“Delete”KeyStrikingthedeletekeywilldeletedatawithoutwarning.Sokeepyourfingersawayfromit.ItisrecommendedthatyouplacetheTasksIDinthedescriptionofthelasttasksoyouknowifyouhavedeletedataskinerror.

1.2TypingaDateorDraggingaTaskSetsaConstraint!Functionsthatsetaconstraintwithoutwarningare:

❖ TypingorselectingastartdateinaStartdatefieldwillsetaStartNoEarlierThanconstraint

❖ TypingorselectingafinishdateinaFinishdatefieldwillsetaFinishNoEarlierThanconstraint

❖ DraggingabarintheGanttChartViewwillsetaStartNoEarlierThanconstraint

Note:Youneedtobeverycarefulwhendraggingtasksortypingintodatefieldsasthiswillsetaconstraintandthetaskswillnotmoveforwardintimewhenpredecessorsareremovedorfinishedearlier.

1.3IndicatorsColumnTheIndicatorscolumnisaveryusefulfeaturethatidentifieswhenataskhasanattributethatisdifferentfromanormaltaskwhichhasbeencreatedbyinsertinganewtask.TheindicatorscolumnwilldisplayaConstrainticonwhenaconstrainthasbeenset:

❖ BeforeenteringadateinaStartorFinishfieldorDraggingaTask,theindicatorcolumnisblank:

❖ AfterenteringadateinaStartorFinishfieldorDraggingaTask,aconstraintisset.TherenowisaConstraintindicatorintheIndicatorcolumn:

Page 12: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ Anoteisdisplayedwhentheindicatorfieldhasthemousepointerplacedovertheindicatorcell:

❖ TheindicatorcolumnshowsadifferenticonwhentaskshaveNotes,TaskCalendaroraConstraintconflictcausingNegativeFloat(Slack):

Note:NoindicatorisdisplayedwithaDeadlineDate,unlessNegativeFloatiscreated.

1.4WhyAreTasksScheduledbeforethePredecessors?Thereareacoupleofreasonswhytaskswouldbedisplayedbeforeapredecessorrelationshipwouldallowthemtobescheduled:

❖ AnActualStartdatehasbeenset,or❖ Taskswillalwayshonortheirconstraintdatesissetandthetaskhasa

Lateconstraint.

1.4.1UnderstandingtheActualStartDate

AnActualStartissetbyenteringadateintheActualStartfieldorenteringa%Complete.

❖ OnceanActualStartdatehasbeensetapredecessorrelationshipdoesnotaffecttheActualStartdate.

❖ Apredecessorrelationshipmaycauseanin-progressTaskwithanActualStartdatetosplitwhentheFILE,Options,ScheduletabSplitinprogresstasksoptionhasbeenchecked.

1.4.2TasksWillAlwaysHonorTheirConstraintDates

ThereisanoptionintheFILE,Options,ScheduleformtitledTaskswillalwayshonortheirconstraintdates.ThisoptionforcesatasktobescheduledbeforethepredecessorswhenthesuccessorhasaFinishnolaterthanorStartno

Page 13: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

laterthanconstraint.Ineffect,thisoptionwillmakeallconstraintsoverriderelationships,moreonthisoverthepage.

Withthisoptionset,ataskwithaMustStartOnconstraintsetpriortoapredecessor’sFinishdatewilldisplayanEarlyStartontheconstraintdateandnotthescheduleddate.TheTotalSlackmaynotcalculateasthedifferencebetweenLateStartandEarlyStart.

Examinethefollowingtwoexampleswiththeoptionboxcheckedandunchecked:

❖ Taskswillalwayshonortheirconstraintdates:optionboxchecked:

Task3startsbeforethepredecessorfinishesandtheTotalSlackofthesecondtaskiscalculatedasminus2days,whichisnotthedifferencebetweentheEarlyFinishandtheLateFinishdates.ThisconstraintdoesnotadheretocommonlyacceptedTotalFloatcalculations.

❖ Taskswillalwayshonortheirconstraintdates:optionboxNOTcheckedandtheTotalFloatiscalculatedcorrectly:

Note:ItissuggestedthatthisoptionisNEVERswitchedon,astheschedulemayappeartobeachievablewhenitisnot.

1.5TheProjectWillNotOpen!AllMicrosoftProjectfileshavea*.mppfileextension,soitisdifficulttodeterminetheversionthataMicrosoftProjectfilewascreatedwith.

MicrosoftProject2016,2013and2010sharethesameformatandmaynotbeopenedbyearlierversionsofMicrosoftProject.MicrosoftProject2016,2013and2010maysaveto2007and2000-2003format.

TheFILE,Options,TrustCenter,TrustCenterSettings…,LegacyFormatoptionalsodeterminesifyouareabletoopenearlierformats,itisrecommendedthatyouselectthePromptwhenloadingfileswithlegacyornon-defaultfileformatsoyouwillknowwhenyouareopeninganearlierfileformat.

Whensavingtoearlierversionstheremayalossofdataanddifferentsoftwareversionscanresultindifferentcalculationsinsomecircumstances.Forexample

Page 14: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

MicrosoftProject2000-2003formatdoesnotsupporteitherCostResourcesorthenamingofCalendarNonWorkDays.

YoushouldusetheGanttChartWizardtoformatthebarswhenopeningaprojectfromMicrosoftProject2016,2013or2010thatwascreatedwithMicrosoftProject2007orearlierversion.IfyouusetheRibbonfunctionalities,thebaselinewillbehiddenbehindthecurrentbars.

Note:Oneofthewellknowmethodsofobtainingacorruptfileistoworkinolderversionsorchangingversionformatsonaregularbasisandboththesepracticesshouldbeavoided.

1.6TheLogicKeepsChanging!ThelogicwillchangeifataskisdraggedtoanotherpositionwhenFILE,Options,Scheduletab,Autolinkinsertedormovedtasksoptionchecked.

Thisoptionisintendedtobeusedtoautomaticallylinknewinsertedtaskswithapredecessortothetaskaboveandasuccessortothetaskbelow.

Thedownsideofthisfunctionisthatwhenthetaskismovedthisfunctionwillchangetheexistingpredecessorsandsuccessorsofthefollowing:

❖ Movedtask,

❖ Originaltasksthatwereaboveandbelowthemovedtask,and

❖ Newtasksthatarenowaboveandbelowthemovedtasks.

Thisfunctionwillpotentiallymakesubstantialchangestoyourprojectlogicandmayaffecttheoverallprojectduration.

Note:ItisstronglyrecommendedthatthisoptionisNEVERswitchedon,asdragginganactivitytoanewlocationmaycompletelychangethelogicofaschedulewithoutwarning.

Anexampleofthisprocessisshownbelow:

❖ OriginalLogic:

❖ TaskDdraggedwithAutolinkinsertedormovedtaskschecked.Notethelogichaschangedonmanytasks:

Page 15: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ TaskDdraggedwithAutolinkinsertedormovedtasksunchecked.Thelogichasnotchanged:

1.7WhyDoNewTasksHaveanEarlyStartConstraint?Unlikeotherschedulingsoftware,MicrosoftProjectnormallyignorestheStatusDatewhencalculatingaschedulewithprogress.ItschedulestaskswithoutanActualStartorpredecessorsorconstraintsontheProjectStartDate,orasclosetotheProjectStartDateascalendarspermit.ItdoesnotautomaticallyscheduletheincompleteportionsofTasksaftertheStatusDate.

TheFILE,Options,ScheduletabhasanAutoscheduledtasksscheduledon:optionthatmaybesettoeither:

❖ StartonCurrentDate,or❖ StartonProjectStartDate.

Page 16: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ WhensettostartonCurrentDate,newtasksarecreatedwithanEarlyStartConstraintsettotheCurrentDate,whichissettothecurrentdateofthecomputersoperatingsystem,e.g.today’sdate.

❖ WhensettostartonProjectStartDate,newtasksarecreatedwithoutaconstraintandallnewtaskswillscheduleontheProjectStartDate.Thisistherecommendedsettingandnewtaskswillnotbeassignedaconstraintwhencreated.

1.8RecommendedScheduleOptionsItisbesttokeepascheduleassimpleaspossible.ItisrecommendthatyouconsiderthefollowingFILE,Schedule,Optionsasagoodstartingpointifyouhavelimitedexperienceinschedulingsoftware.

IfyouensureALLPROJECTSARECLOSEDbeforeyoustartsettingyouroptionsthenallchangesthatyoumaketotheoptionswillbeappliedtonewprojectscreatedusingtheFILE,NewcommandwhichusesyourGlobal.mpttemplate:

Note:Mostoftheotheroptionsarecoveredinthisbookbuttheoptionsthatmustbeswitchedofftoensurethesoftwareoperatesinapredictablewayare:

❖ Autolinkinsertedormovedtasks,❖ Splitin-progresstasks,and❖ Taskswillalwayshonortheirconstraintdates.

Page 17: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

1.9ManuallyScheduledandAutoScheduledTasksTheFile,Options,Schedule,Newtaskscreated:allowstheselectionofManuallyScheduledorAutoScheduled.

❖ TheManuallyScheduledoption(newtoMicrosoftProject2010)overridestheschedulecalculationsfortasksmarkedasManuallyScheduled,allowingthesoftwaretobeusedlikeawhiteboardfortheselectedtasks.

❖ ItisnormallyconsideredgoodschedulingtoselectAutoScheduledsotaskswillacknowledgetherelationshipsandconstraints.

❖ ThereforetheFile,Options,Schedule,Newtaskscreated:shouldalwaysbesettoAutoScheduled.

Ifyourscheduleisbehavingstrangelyorthereisunfamiliarbarformatting,thiscouldbebecausesometaskshavebecomeManuallyScheduled.Tofixthisyoumayeither:

❖ DisplaytheTaskModecolumnandsearchforManuallyScheduledtasksandfixtheminthecolumn,or

❖ ClickontheSelectAllbuttonandthenclickonthe AutoSchedulebutton.

Note:SometimesMicrosoftProjectwillchangeaTaskfromManuallyScheduledtoAutoScheduledwithoutawarningandthentheschedulewillstartbehavingstrangely.SowhenascheduledoesnotreschedulecorrectlyortherearesomestrangelookingbarsyoushouldapplytheManuallyScheduledfilterandchangeanyManuallyScheduledtaskstoAutoScheduled.

1.10SortingouttheMenusThegroupingoftheRibboncommandsisbysoftwarefunctions;suchasProject,Tasketc.andnotbyschedulingfunctionssuchascreatingorupdating.ThereforeUserscontinuallyswapfromoneRibbonmenutoanotherwhileoperatingthesoftware.Therearesomeactionsyoushouldconsiderchangingonyourmenustomakethesoftwareeasiertouse:

❖ RightclickontheRibbontoolbartoopenamenu:

Page 18: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ TheQuickAccessToolbarshouldbemovedbelowtheRibbonToolbarbyclickingontheShowQuickAccessToolbarBelowtheRibbon.ThisoptionallowsmorebuttonstobedisplayedandthetoolbarisnottruncatedbytheProjectNameatthetopofthescreen.

❖ TheCollapsetheRibbon…commandhidestheRibbonToolbarandjustleavesthemenudisplayedatthetop,providingmorescreenspace.ThiswascalledMinimizetheRibboninMicrosoftProject2010.ClickingononeofthemenucommandswilldisplaytheRibbonToolbar.

❖ YoushouldbuildyourownQuickAccessToolbarbyusingtheCustomizeQuickAccessToolbar…optionwhichopenstheProjectOptionsformQuickAccessToolbartabwherebuttonsmaybeaddedtoorremovedfromorreorderedontheQuickAccessToolbar.

❖ TheAddtoQuickAccessToolbarcommandwilladdaselectedRibbonToolbarbuttontotheQuickAccessToolbar.BydefaulttheQuickAccessToolbarispositionedatthetopleft-handsideofthescreenandisalwaysdisplayed.

Note:TodothisallthesechangesinonehityoushouldconsiderdownloadingtheEastwoodHarrisQuickAccesstoolbarfromwww.eh.com.au,Software&DownloadspageandimportitfromtheFILE,Options,QuickAccesstoolbar,Import/Exportcommand.

UnfortunatelyMicrosoftProject2016hasplacedlargegapesbetweenthebuttonsontheQuickAccesstoolbarwhichmakethisfunctionlessusefulaslessbuttonsaredisplayedontheQuickAccessToolbar:

MicrosoftProject2016

Page 19: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

MicrosoftProject2013

Page 20: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

2CALENDARSURVIVALGUIDE2.1RoleoftheProjectCalendarTheprojectcalendarisassignedtoaprojectintheFILE,Info,ProjectInformationform:

❖ Newtasksarenotassignedacalendarbydefault.

❖ AlltasksthathavenotbeenassignedaTaskCalendarcalculatetheirEarlyFinishdatefromtheirEarlyStartdateplustheDurationcalculatedfromtheProjectCalendar.

❖ Therefore,afive-daydurationtaskwithafive-dayworkweekcalendar,startingWednesday,withSaturdayandSundayasnonworkdays,willfinishattheendoftheworkdayonthefollowingTuesday,seethepicturebelow:

Note:AchangetotheProjectCalendarmaymakesubstantialchangestotheelapseddurationofallactivitiesthathavenotbeenassignedaTaskCalendar.

2.2GuidelinesforCreatingCalendarsCalendarsarecreatedandeditedusingthePROJECT,Project,ChangeWorkingTimeform.

Anunlimitednumberofcalendarsmaybecreated:

❖ OnecalendarisassignedastheProjectCalendar.

❖ Eachtaskandresourcemaybeassignedauniquecalendar.

❖ Thecalendarassignedtoaresourcemaybefurthereditedtorepresenttheresource’suniqueavailability.

Therearesomeguidelinesthatshouldbeconsideredwhencontemplatingtheuseofmultiplecalendars.Thesearesummarizedbelow:

Page 21: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ Ifyouareabletoscheduleaprojectwithonlyonecalendarthendoso;keeptheschedulesimple.

❖ Theworkhoursperdayforallcalendarsonaprojectshouldbethesameforeachworkday,otherwisetheSummaryTaskDurationsindayswillnotallcalculatecorrectly.

❖ KeeptheStartandFinishtimesforallcalendarsthesame,otherwisetheDefaultStartandFinishTimewillbeincorrectforsometaskswhenConstraintsorActualDatesareassignedwithouttimesbeingdisplayed.

❖ WhenresourcesareassignedtoataskwithoutaTaskCalendarthentheResourceCalendartakespreferenceovertheProjectCalendar,unlessSchedulingignoresresourcecalendarsischeckedintheTaskInformationform.

2.3DisplayofDurationinDaysMicrosoftProjecteffectivelycalculatesinhours.ThevalueofthedurationindaysiscalculatedusingtheparameterenteredintheHoursperday:fieldintheFILE,Options,Schedule,Calendaroptionsforthisprojectsection.ItisVERYIMPORTANTtounderstandthatalldurationsindaysarecalculatedusingONLYthisparameterwithEVERYcalendarirrespectiveofthenumberofhoursperdayinanycalendar.

Forexample,whentheOptionsformHoursperday:valueissetto“8”thentasksassigned:

❖ An8-hoursperdaycalendarwillhavedurationsindaysdisplayedcorrectly,and

❖ A24-hoursperdaycalendarwillhavedurationsindaysdisplayedincorrectly,

Thepicturebelowshows:

❖ Task1hasthecorrectdurationof5days,but

❖ Task2alsoshowsa5-daydurationthatisclearlymisleading.

❖ Tasks4and5displaythedurationinhoursandthisisnotasmisleadingbecausethecalendarcolumnisalsodisplayed.

Page 22: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

ItisSTRONGLYRECOMMENDEDthatyouavoidassigningcalendarswithadifferentnumberofhoursperdaywhereverpossible.

Therearesomeworkableoptionstoensurethatthedurationsindaysarecalculatedand/ordisplayedcorrectly:

❖ Allthecalendarsusedonaprojectscheduleshouldhavethesamenumberofhoursperdayforeachday.ThisvalueisenteredintheHoursperday:fieldintheFILE,Options,Scheduletab.

❖ Whenthereisarequirementtouseadifferentnumberofhoursperday(ineitherthesamecalendarorindifferentcalendars)thenalldurationsshouldonlybedisplayedinhoursandtheTaskCalendarshouldalsodisplayedinacolumn.TheDurationisenteredin:fieldintheFILE,Options,Schedule,SchedulingoptionsforthisprojectsectionshouldbesettoHours.Thusalldurationswillbeenteredbydefaultinhours.

❖ ACustomizedFieldmaybeusedtocalculateanddisplaythecorrectdurationindaysusingaformula.TheformulabelowmaybeusedtocalculatethecorrectdurationinaDurationCustomizedFieldoftasksscheduledona24hoursperdaycalendarwhentheProjectCalendarisan8hourperdaycalendar:IIf([TaskCalendar]=“24hr/day”,[Duration]*0.33,[Duration])

2.4HowtoAssignTaskCalendarsAtaskmaybeassignedacalendarthatisdifferentfromtheProjectCalendarby:

❖ DisplayingtheTaskCalendarcolumnandeditingtheTaskCalendarfromthiscolumn,or

❖ Double-clickingonthetasktoopentheTaskInformationformandselectingtheAdvancedtab.

Afteracalendarhasbeenassigned,aniconwillappearintheIndicatorscolumnandthecalendarnamedisplayedintheTaskCalendarcolumn,asshowninthepicturebelowfortheInstallationRequirementstask:

Page 23: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ ThetaskFinishdate,TotalFloat,FreeFloatandVariancesfromaBaselinewillbecalculatedontheTaskCalendar.Thisoftenleadstoconfusionfornewusersastasksona24-hour/daycalendarwillhavedifferentFloatthantasksonan8-hour/daycalendar.

❖ WhenresourcesareassignedtoaTask,theFinishdateiscalculatedontheResourcecalendar;unlesstheTaskhasbeenassignedacalendarandtheboxintheTaskInformationformAdvancedtabSchedulingignoresresourcecalendarsischecked,thenthetaskdurationiscalculatedbasedontheassignedTaskCalendar.

2.5OtherThingsTaskCalendarsAffect2.5.1Float

Float(Slack)iscalculatedontheTaskCalendar.Bothtasksbelowhavebeenscheduledtofinishat17:00hoursbuthavedifferentFloatvalues:

2.5.2Lags

LagsarecalculatedontheSuccessorCalendar,andthereforeaffectthestartdateandtimeofsuccessors:

Note:MicrosoftProject2000usestheProjectCalendartocalculatelags,thereforefilesmaycalculatedifferentlyin2000fromlaterversions.TheexamplebelowisthefilefromthepictureaboveandopenedinMicrosoftProject2000:

2.6ResourceCalendarsEachresourceiscreatedwithitsveryowneditablecalendar.Herearesomeimportantpoints:

❖ EachnewresourceisassignedacopyofthecurrentProjectCalendarasitsBaseCalendar.

Page 24: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ ThisResourceBaseCalendarmaybechangedintheResourceSheetorChangeWorkingTimeformtoanotherBaseCalendar.

❖ AnychangetoaBaseCalendarwillbereflectedinanyResourceCalendar.

❖ TheResourceCalendarmaybeeditedtosuittheavailabilityoftheresource.Daysmaybemadenonworkdaystorepresentholidays,etc.

❖ NormallythedurationofaresourcedtaskiscalculatedfromtheResourceCalendar.

❖ AtaskwillfinishattheendofthelongestresourceassignmentwhentherearetwoormoreresourcesassignedtoataskthathavedifferentenddatesduetodifferentResourcecalendarsorassignmentdurations.

❖ WhenaTaskhasbeenassignedacalendarandthecheckboxintheTaskInformationform,Advancedtab,Schedulingignoresresourcecalendarsischecked,thenthetaskdurationisthencalculatedfromtheTaskcalendar.

❖ TheFinishdatemaybecalculateddifferentlyafterataskisassignedoneormoreresourceswhentheResourcesCalendarsarenotthesameastheTaskCalendar.

2.7WhichCalendaristheTaskUsing?TrythechecklistbelowwhenitisdifficulttounderstandwhichcalendarisbeingusedforcalculatingataskFinishdate:

❖ ChecktheProjectCalendarinthePROJECT,Project,ProjectInformation…form,

❖ ThenchecktheTaskCalendarintheTaskInformationformAdvancedtaboraTaskCalendarcolumn,

❖ Nextcheckifresourcesareassignedtothetask,

❖ FinallychecktheResourceCalendarforholidays.

Therulesareasfollows:

❖ WhenNOTaskCalendarandNOresourcesareassigned,thentheProjectCalendarisused.

❖ WhenaTaskCalendarisassignedandthereareNOresourcesassignedthentheTaskCalendarisbeingused.

❖ WhenResourcesareassignedandNOTaskCalendarthentheResourceCalendarisused.

❖ WhenResourcesandaTaskCalendarareassigned,thenthecommonlyavailabletimefrombothcalendarsisusedtoschedulethetask.

❖ WhenResourcesandaTaskCalendarareassignedandtheSchedulingignoresresourcecalendarsischecked,theTaskCalendarisused.

Page 25: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Note:Acommonmistakeisassigningataskaneditedtaskcalendar,thenatalaterdateassigningresourceswithouteditingtheresourcecalendarstomatchthetaskcalendarsandnotrealizingthatthetaskdurationsnolongercalculatethesame.

2.8DefaultStartandEndTimeYoumaynoticetasksspanonedaylongerinthebarchartthantheirduration.ThisoftenoccurswhenthecalendarstartandfinishtimesareeditedbuttheDefaultstarttime:andDefaultendtime:arenotadjustedtomatchthetaskcalendars.

ThesoftwareassignsaDefaultstarttime:andDefaultendtime:whenadateisenteredinafieldbutatimeisnotentered.

ThesetimesMUSTbealignedtotheProjectCalendarwhen:

❖ Constraintsareassignedtotasks,and

❖ ActualStartorActualFinishdatesareassigned.

Whenthesetimesarenotalignedthentasksmaybedisplayedonedaylongerthantheirassignedduration.Thepicturebelowshowsa3-daytaskspanningfourdaysbecausetheCalendarstarttimeis8:00amandtheDefaultstarttimeis9:00am.

ThesetimesaresetintheProjectOptionsform,Scheduletabwhichmaybeaccessedby:

❖ Clickingthe buttoninthePROJECT,Propertiestab,Changeworkingtimeform,or

❖ SelectingtheFILE,Options,Scheduletab.

Toassistinreadingandinterpretationofaschedulethathascalendarswithdifferentstartorfinishtimesthen:

❖ TheTaskCalendarshouldbedisplayedincolumns,and

❖ ThetimeshouldbedisplayedwiththedateinstartandfinishcolumnsbyselectingFILE,Options,_Generaltab,ProjectViewsectionandselectinganappropriatedateformat.

2.9FinishVarianceCalculation❖ TheFinishVarianceisthedifferencebetweentheEarlyFinishandBaseline

Finish.

Page 26: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ VariancesarecalculatedontheTaskCalendar.

ThepicturebelowshowstwomilestonesthathavetheirBaselinessetandhavebeendelayedoneweek:

❖ Themilestoneona5-dayperweekcalendarhasa5-dayvariancewhichisnottheelapsedvariance,and

❖ Themilestoneona7-dayperweekcalendarhasa7-dayvariancewhichistheelapsedvariance.

Note:Whenyouneedtocalculateamilestonevarianceincalendardays,itisbesttoplacethemilestoneona7-dayperweekcalendarwithoutholidaystoensuretheVariancecalculatestheelapsedduration.

Page 27: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

3TRICKYSTUFF3.1TaskNamingIssuesItisoftenbestinMicrosoftProjecttomakeallTaskNamesunique,soforexamplewhenyouhaveabuildingwithmanyfloorsandtradeseachTaskNameshouldincludethetradeandfloor.

❖ Thismakesiteasiertounderstandtheschedulewhenafilterhasbeenappliedandtofindpredecessorsandsuccessorsinalargeschedule.

❖ InMicrosoftProject2010,2013and2016thisisevenmoreimportantbecausethetasksarelistedinthepredecessorandsuccessorlistsinalphabeticalorderandnottheorderintheschedule.Soifyouhave20Floorswithaconcreteactivitytitled“Concrete”,thentheseactivitieswillbelistedalltogetherinalistanditwillbedifficulttoknowwhichflooreachconcretetaskbelongstoo.

ThesedescriptionsmaybecreatedinaspreadsheetbyusingtheConcatenatefunction,thepicturebelowdemonstrateshow.Textmaybeaddedbyincludingitindoublequotationmarks:

Page 28: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Asyoucanseebelowthetasksarenowlistedin“Floor”orderinthepredecessorlist.

Note:WheninsertingtheTaskNamecolumnyouwillfinditistitledName.

3.2TaskSplitting3.2.1WhatisSplitting?

SplittingataskputsoneormorebreaksinaTask,leaving:

❖ TheDurationvalueunchangedwithaFixedUnitstaskbuttheelapsed

Page 29: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

durationisincreased,

❖ TheDurationvaluechangedwithaFixedDurationtasktoequaltheelapsedduration,and

❖ Resourcesassignedtoasplittaskarenotassignedworkduringthesplits:

InthepictureabloveyouwillseethatWorkisnotscheduledduringthesplit.

3.2.2SplittingaTaskManually

Tosplitataskmanually,

❖ Left-clickonthe SplitTaskbuttonlocatedontheTASKtoolbar,Schedulesection,

❖ TheSplitTask:boxwillappear,❖ ClickonthepointontheGanttChartbarwherethesplitistobemadeand

click.

❖ Thendragthetask:

Note:

Thefinishandstartdatesandtimesofeachsplitarenotavailablethroughtheuserinterface.

3.2.3SplittingIn-progressTasks

Page 30: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

WhentheSplitin-progresstasksoptionisenabledintheFILE,Options,Scheduleform,ataskwillSplitautomaticallywhenataskcommencesbeforeitspredecessorfinishes.

Note:ThisfunctionissimilartothePrimaveraRetainedLogicfunctionandoftenproducesunwantedNegativeSlack.

3.2.4RemovingaBarSplit

Asplitisremovedby:

❖ Amanuallycreatedsplitisremovedbydraggingthesplitpartbackwiththemouse.

❖ AnautomaticallycreatedsplitisremovedbyTurningoffSplitin-progresstasksintheFILE,Options,Scheduleform.

Notes:

❖ YouthereforeneedtopaycarefulattentiontoanywarningmessagesMicrosoftProjectpresents,ifyouhavenotswitchedthewarningmessagesoff.

❖ SometimesatailofdotsisleftafterthesplithasbeenremovedfromaFixedDurationtask.Thisistheresultofasplitattheendofatask,thistailhastobedraggedbacktothefinishofthetaskandthentheDurationresetforthetasktocalculatecorrectly:

AlsoyoumayreceiveasplitatthestartofataskwhentheFILE,Options,Schedule,Splitin-progressoptionisselectedandanActualStartDateissetearlierthanthepredecessorfinish.Topreventthiseither:

❖ TurnoffAutomaticschedulingbeforeupdatingthetask,thenpressF9torecalculatethescheduleor

❖ SettheActualDurationbeforeenteringtheActualStart.

Page 31: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

3.2.5HidingaBarSplit

Eventhoughthetaskhasbeensplit,barsplitsmaybehiddenby:

❖ SelectingFORMAT,Format,LayouttoopentheLayoutformand❖ UnchecktheShowbarsplits.

❖ The10-dayFixedUnitsactivitybelowhasasplitwithanelapseddurationof17days:

❖ The10-dayactivitybelowhasahiddensplitandanelapseddurationof17days,whichmaybemisleading:

Page 32: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

3.3DeadlineDateMicrosoftProjectdoesnotallowsettingtwotaskconstraints;exceptinthecaseofaDeadlineDate.

❖ ADeadlineDateissetintheTaskInformationformAdvancedtaborintheDeadlineDatecolumn.

❖ DeadlineDateallowsthesettingofadatebywhichataskshouldbecompleted.

❖ ADeadlineDateissimilartoplacingaFinishNoLaterThanconstraintandaffectsthecalculationoftheLateFinishdateandfloatoftheactivity.

❖ AconstraintsuchasanEarlyStartconstraintmayalsobeassignedtoataskwithaDeadlineDate.

❖ TheDeadlineDatemaybedisplayedasacolumnandappearsonthebarchartasadownarrow .

❖ AnIndicatoricon isplacedintheIndicatorcolumnwhentheDeadlineDatecreatesNegativeFloat(Slack).

❖ ThepicturebelowshowhowaDeadlineDateisdisplayed,thisallowsthedatetobechangedbydraggingtheiconintheGanttchart.

❖ ItalsodisplayshowNegativeFloatiscalculatedwhentheDeadlineDateissetbeforetheTaskEarlyFinish.

3.4NegativeandFreeFloatBarsTherearesomeissueswiththedefaultMicrosoftProject2016and2013barformatting:

❖ BydefaultMicrosoftprojectonlydisplaystheFreeFloatBarwiththeFORMAT,BarStylesgroup,SlackbuttonnottheTotalFloatBarthatwouldnormallybeexpected.

❖ AlsotheNegativeFloatBarisnotautomaticallydisplayedbyanyMicrosoftProjectfunction,norisitincludedinanystandardView.

Page 33: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Thesearetwoofthemostimportantbarstoshowwhenaprojectfinishdatehasbeensetusingaconstraintandthesebarsmustalwaysbemanuallycreated.

❖ NegativeFloatisgeneratedwhentheLatedateiscalculatedearlierthantheEarlydateandrepresentstheamountoftimethattheschedulemustcatchuporhowmuchearlieraprojectmuststarttofinishontime.SettingaLateconstraintorDeadlinedateearlierthanthecalculatedEarlyFinishdatenormallycausesNegativeFloat.

❖ FreeFloatistheamountoftimeataskmaybedelayedwithoutdelayingasuccessortask.

ThesetwobarswillhavetobeaddedmanuallyusingtheBarStyleformby:

❖ SelectingFORMAT,BarStyles,Formatdropdownbox,BarStylesordouble-clickanywhereintheGanttChartareaexceptonanexistingbar(thiswillopentheFormatBarformandnottheBarStylesform)toformatanindividualbar.

❖ Thenaddtheadditionalbarsasindicatedbelow:

Note:Unlikesomeothersoftware,theNegativeFloatisdrawnfromtheStartDateofataskandnottheFinishDate.ThereforeonebarisrequiredforNegativeFloatandoneforPositiveFloat.

Therearesomeoptionstopermanentlyresolvethislackofformattingfunctionality:

❖ YoumaywishtoconsiderrecordingamacrotocreatethebarsandthiscanberunwhenaTotalFloatandNegativeFloatbarisrequired.

❖ YoucouldcreateaViewwiththesebars,saveyourowntemplatewiththisviewandthenusethetemplatetocreateallnewprojects.

❖ TheauthorhasfoundthattheseadditionalbarsproduceabetterpresentationanddonotinterferewiththedrawingofrelationshipswhencreatedatthebottomofthelistintheBarStylesform.

❖ YoumayalsodownloadanEastwoodHarrisMicrosoftProject2016and2013templateprojectfromtheEastwoodHarriswebsiteatwww.eh.com.au,Software&Downloadspage.ThishasaninbuiltViewwhichdisplaysboththeTotalandNegativeFloatbars.AlsootherissueswithMicrosoftProject

Page 34: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

2016and2013havebeenresolvedandarecoveredinthetemplatedescriptiononthewebsite

3.5WhereistheGantChartWizard?TheGanttChartWizardwasthemainmethodofformattingthebarsinMicrosoftProject2007andearlier.

ItisstillavailableinMicrosoftProject2016,2013and2010andmaybeaccessedbyadding icontotheRibbonorQuickAccesstoolbar.

TheGanttChartWizardshouldonlybeusedtoformatprojectscreatedwithMicrosoftProject2007andearlier.IfitisusedtoformatprojectscreatedwithMicrosoftProject2016or2013or2010thensomestrangethingshappenliketheBaselinebarscoverupthecurrentscheduleSummarybars.

3.6AsLateAsPossibleConstraintThisconstraintmustbeusedwithcautionasitconsumesTotalFloat(Slack)andthereforedelaysallsuccessoractivities;itdoesnotjustdelaythetaskthattheconstraintisappliedto.

❖ AllTasksinthepicturebelowhaveTotalFloat:

❖ WhenTaskCismadeAsLateAsPossiblethenTaskBdevelopsFreeFloat:

❖ WhenTaskCismadeAsSoonAsPossibleandTaskAismadeAsLateAsPossiblethenTaskAconsumesallavailableTotalFloatanddelaysallthesuccessors:

Note:SomesoftwarepackagesofferaZeroTotalFloatfunction,whichallowsactivitiestobedelayedandconsumeFreeFloatwithoutdelayinganysuccessor

Page 35: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

activities.

AStarttoFinishrelationshipwilldragasuccessorinfrontofitandactlikeaZeroFloatconstraint,buttheuseofthisrelationshipisusuallyconsideredbadpractice.

ThePrimaveraAsLateAsPossibleconstraintiscalculatesasaZeroFreeandnotasaMicrosoftProjectAsLateAsPossibleconstraint.

Page 36: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

4INTERESTINGFEATURES4.1WildcardFiltersforTextSearchingTheWildcardfunctionsaresimilartotheDOSWildcardfunctionsandaremainlyusedforfilteringtext:

❖ Youmayreplaceasinglecharacterwitha“?”.Thus,afiltersearchingforawordcontaining“b?t”willdisplaywordslike“bat”,“bit”and“but.”

❖ Thefunctionisnotcasesensitive.

❖ Youmayreplaceagroupofcharacterswithan“*”.Thus,afiltersearchingforawordcontaining“b*t”willdisplay“blot”,“blight”and“but.”

Note:FortheWildcardfunctiontooperatethe“equals”Testmustbeused.Thisfunctiondoesnotworkwiththe“contains”andinthismode“equals”worksasa“contains”operand,seethepicturebelow.

❖ NAallowstheselectionofablankvalue.ThefilterbelowdisplaystaskswithouteitheraBaselineStartorBaselineFinishdate:

4.2InteractiveFiltersThesefiltersallowyoutoenterarangeofValuesafterapplyingthefilter.Thusfilteristailoredeachtimeitisappliedviaauser-prompt.Thefilterbelowwillaskyoutoenterarangeofdates.ThisfilterisveryusefultolookatatimesliceofactivitiesandwouldbeusedtocreateaLookAheadfilterwhenupdatingaschedule.

Forthisfunctiontooperateproperly,thetextintheValue(s)fieldmustcommencewithadoublequoteandendwithadoublequoteandquestionmark,e.g.theformatshouldbe“Question”?.Thetextisuserdefinedandmaybeanyrelevant

Page 37: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

text:

4.3AutoFiltersAutoFiltersareturnedonbyclickingonthe button.Theymaybeusedto:

❖ FilteringtasksbyeitherusingthecheckboxesinthelowersectionorselectingfromtheoptionsundertheFiltersoption

❖ Sortisusedtosortonaselecteddataitem,butthisalsojumblesuptheSummaryTasks,

❖ GroupisusedtoGrouptasksbytheselectdatafield.Thisonlyallowsasinglelevelofgrouping.UsetheGroupby:functionifthetasksaregroupedbymorethanonefield.

ThepicturebelowdisplayssomeoftheoptionsfoundwithAutoFiltersfunction:

Page 38: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Note:AutoFilterswillalwaysshowSummaryTasks.

4.4SelectingDatesTherewasaslickwayofselectingdatesindatefieldsin2000to2003byscrollingthroughdays,monthsandyearsbutthisfunctionwaseliminatedin2007andtherewerenoimprovementsinversions2010,2013or2016.

In2010,2013and2016acalendarformisdisplayedbyclickingonadatecellwiththemousepointer:

❖ Tochangetheday,clickontherequiredday.

❖ Toselecttoday’sdate,clickonthe button.

❖ Tochangethemonthand/oryear;scrollamonthatatimebyclickingonthearrowsonthetopleft-handortopright-handsideoftheform;

Page 39: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Note:Whenadateisselectedfromacolumn,MicrosoftProjectwillsetaconstraintwithoutinformingtheuser.Thismayresultinunintentionallysettingaconstraint.

4.5UnderstandingStartandFinishMilestonesAMilestoneiscreatedbyassigningataskazeroduration:

❖ AMilestoneisaStartMilestonewhenithasnopredecessors,seeTask1below.

❖ AStartMilestoneisattheStartofaTimePeriod,forexample,8:00am,seeTask1below.

❖ AMilestoneisaFinishMilestoneifithasoneormorepredecessors,seeTask3and5below.

❖ AFinishMilestoneisattheEndofaTimePeriod,forexample,5:00pm,seeTask3and5below.

❖ AtaskmayalsobemadetolooklikeaMilestonebycheckingtheMarkasamilestoneintheTaskInformationformAdvancedtab,seeTask2below.

❖ ThetaskmadetolooklikeaMilestonemaybesettodisplayattheStartorFinishoftheTasksbyeditingtheFromandTofieldsofMilestonesintheBarStylesform:

Note:Unlikesomeotherschedulingsoftwareitisnotpossiblefortheuserto

Page 40: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

assignaMilestoneaseitheraStartorFinishMilestoneinMicrosoftProject.AlsoensureyourMilestonedescriptionmatchesthepurposeoftheMilestone;forexampleaFinishMilestonewouldhave“Completed”inthedescription.

4.6ConvertingaFinishMilestoneintoaStartMilestoneSometimesitisimportanttohaveaStartMilestonethathasapredecessor.Forexample,Task5inthepicturebelowmayberequiredonFridaymorningnotThursdayafternoon:

Oneworkaroundtoachievethis:

❖ AssignashortdurationtotheStartMilestone.Thedurationisnotimportant,say1min.

❖ ChecktheMarkasaMilestoneintheGeneraltaboftheTaskInformationform.

❖ EnsureallsuccessorsoftheStartMilestoneareStarttoStart,otherwiseallsuccessorswillspan1daylongerthantheirassignedduration:

WithoutaStarttoStartsuccessor:

WithaStarttoStartsuccessor:

4.7CreatingaHammockoraLEOTaskAHammockorLevelOfEffort(LOE)taskisdefinedasataskthatspansbetweentwotasksormilestonesandwillchangeindurationwheneitherofthe

Page 41: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

drivingdateschange.

ThisisnotaSummaryTaskcreatedbyOutliningandisnotaMicrosoftProjectfunctionbutonemaybecreatedby:

❖ AssigningaTaskTypethatmustnotbeFixedDurationotherwisethedurationwillnotchange,

❖ ArelationshipiscreatedbetweenStartdateofthedrivingStartmilestoneorTaskandHammockStartdateusingtheCopyCell…andPasteSpecial…,PasteLink…linkcommand,

❖ ThenarelationshipiscreatedbetweenFinishdateofthedrivingFinishMilestoneorTaskandHammockFinishdateusingtheCopyCell…andEdit,PasteSpecial…,PasteLink…command.

❖ AseitheroftheDrivingmilestonesortasksismovedtheHammockwillrecalculateitsduration.

❖ InthepictureabovetherehasbeenalinkcreatedbetweentheStartdatesofTask2andTask1andtheFinishdatesofTask3andTask1.

Note:Alinkedcellhastriangleinthebottomrighthandcorner:

4.8ElapsedDurations,LeadsandLags4.8.1ElapsedDurations

IfyouassignataskanElapsedduration,thetaskwillignoreallcalendarsandwillbescheduled24hoursadayand7daysperweek.Toenteranelapsedduration,typean“e”betweenthedurationandunits.

❖ Thisisusefulfortaskssuchascuringconcreteorcomputerprocessesrunning24hoursperday.

❖ TheTotalFloatwillcalculateapproximatelythreetimeslongerthanataskonan8-hourperdaycalendar(dependingonthelengthofthelunchbreak)andthismaybemisleading.

Theexamplebelowshowsthedifferencebetweena7-ElapsedDaytaskanda7-

Page 42: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

daytaskonaStandard(5-dayperweek)calendar.

4.8.2FloatonTaskswithElapsedDurations

TheFloatonElapsedDurationtasksiscalculatedona24-hourperdaycalendarandwillbedifferentthanataskonan8-hourperdaycalendar:

4.8.3ElapsedLeadsandLags

Anelapsedleadorlagmayalsobeassignedtorelationshipsandthesealsoignoreallcalendars:

4.9EstablishingTwoRelationshipsbetweenTwoTasksSometimesitisdesirabletoputtworelationshipsbetweentwoactivities,forexample,aStarttoStartandaFinishtoFinish.Thisisoftenreferredtoas“LadderScheduling”.ItisnotpossibletoputtworelationshipsbetweentwotasksinMicrosoftProjectunlessaMilestoneisinsertedintheloop:

Page 43: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Note:Task3intheupperpictureabovehasbeendraggedAsLateAsPossiblebytheFinishtoFinishrelationship.

4.10LadderschedulingLargenegativelagsarenormallyunacceptableandLadderSchedulingisusedtolinkasetoftasksthathavesubstantialoverlap,suchaspipelayingoperations.

Mostproductsallowmultiplerelationshipsbetweentwotasks,aspertheP6examplebelow,wherethetasksarelinkedusingtworelationships,aSS+3dandaFF+3d:

MicrosoftProjectdoesnotallowtworelationshipsbetweentasks.LadderSchedulingmaybeachievedby:

❖ CommencingachainwithaStartMilestone,

❖ ConnecttheStartMilestonetoeachtaskwithaStarttoStartplustheappropriatelagand

❖ ConnecteachtasktotheirsuccessorwithaFinishtoFinishrelationshipplustheappropriatelag:

Page 44: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

4.11%LagsAPercentageLag,orNegativeLag,increasestheLagdurationasthepredecessordurationincreases:

ThelagdurationiscalculatedontheSuccessorCalendar.Whenthesuccessortaskischangedfroman8-hourperdaycalendartoa24-hourperdaycalendar,theelapseddurationofthesuccessorisreduced,aswellastheelapseddurationofthelag.NowtheFloatiscalculatedona24-hourperdaybasis.Thingsgetabittrickyhere!

Note:MicrosoftProject2000calculatesthelagontheProjectCalendar.

4.12TracingLogicItsometimegetquitehardtotracelogicinacomplexprojectwithrelationships

Page 45: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

flyingupanddownaGanttChart.

Therearesometoolsyoumayconsiderusingtoresolvetheseissuesincluding:

❖ TaskDrivers❖ RelationshipDiagramand

❖ TaskPath4.12.1TaskDriversandTaskInspector

ADrivingRelationshipisthepredecessorthatdeterminestheEarlyStartofanon-criticaltaskthathastwopredecessorswhichhavedifferentfinishdates.

MicrosoftProject2000–2003doesnotidentifythedifferencebetweenDrivingandNon-drivingRelationships,whichoftenmakesanalyzingascheduledifficult.IntheseearlierversionsofMicrosoftProject,thesimplestwaytodeterminethedrivingrelationshipfortasksnotonthecriticalpathandwithmorethanonepredecessorwastodeletetherelationshipsuntilthetaskmoved.

MicrosoftProject2007introducedaTaskDriversformthatindicatesthedrivingpredecessorandwhethertheschedulehasbeenResourceLeveled.Italsodisplaystheeffectsofleveling.ThiswasrenamedTaskInspectorinMicrosoftProject2013.

InMicrosoftProject2013and2016,gotoTASK,TasksgroupandfromthedropdownmenucontainedinInspect,select toopentheTaskInspectorpane,whichdisplaysinformationasinthepicturebelow:

InordertoseetheDrivingPredecessorsand/orDrivingSuccessors,clickonthe TaskPathiconlocatedintheFormattoolbar:

Page 46: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

4.12.2TracingtheLogic

AnothermethodtotracethelogicistodisplaytheBarChartintheTopPaneandtheRelationshipDiagramintheBottomPane.ScrollupanddownintheGanttCharttoidentifythepredecessorsandsuccessors:

AnothermethodistodisplaytheRelationshipDiagramintheTopPaneandtheTaskFormintheBottomPane.ClickonthepredecessorsorsuccessorsintheRelationshipDiagramtofollowthelogic:

Page 47: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

4.12.3TaskPath

MicrosoftProject2013introducedafunctiontitledTaskPathfoundbyselectingFORMAT,BarStyles,TaskPathandselectingoneoftheoptions:

Thisfunctionwillhighlightthetasksthatmatchthecriteriainthecolorsindicatedinthemenu.

Page 48: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

5MAKINGITLOOKRIGHT5.1DateFormatDangersThereisoftenconfusiononinternationalprojectsbetweenthenumericalUSdatestyle(mmddyy)andthenumericalEuropeandatestyle(ddmmyy).Forexample,intheUnitedStates020719isreadas07Feb‘19,andinmanyothercountriesas02Jul‘19.Consideradoptingtheddmmmyystyle,06Jan’09ormmmddyystyle,Jan06’09toavoidexpensivelitigationwhendatesaremisunderstood.

SelectFILE,OptionstodisplaytheOptionsformandselecttheGeneraltabDateformat::

Thisoptionselectsthedisplaystyleofthedatesforallprojects.Thedateformatoptionsavailablewillbedependentonyoursystemdefaultsettings.YoumayadjustyoursystemdateformatundertheControlPanel,RegionalandLanguageOptions.

5.2PreventingtheDateFormatfromChangingonOtherComputers

ThedateformatselectedintheFILE,Options,_Generaltabappliestoallprojectsopenedononecomputer.Someprojectsmayberequiredtodisplaythedayandtimeformatandothersdayandmonth,soyouhavetokeepchangingtheformateachtimeyouopenadifferentproject.

Ifyouareinthissituation,youmayoverridethedateformatselectedintheFILE,

Page 49: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Options,GeneraltabbyadateformatselectedinaVIEW,Data,Tables,MoreTables…form:

Eachprojectcouldhaveitsownsetoftablesallwiththeirownproject-specificdateformat.

Whenyousendthisprojecttosomeoneelse,theywillhaveabetterchanceofseeingthesamedateformatasyouespeciallyiftheirControlPanel,RegionalandLanguageOptionsarethesameasyours.

5.3TheSmartWaytoCreateViewsASingleGanttChartViewismadefromaGanttScreenandincludesaTable,anoptionalGroupandanoptionalFilter.AViewalsoholdstheBarformattingandPrintsettings.

IfyourprojectrequiresmultiplebutsimilarViews,forexample,headersandfootersmayneedtocontainthesameprintsettingsandbarformattingconsistent,thenthefollowingprocessisrecommended:

❖ EachViewshouldhaveauniquename.ThisnameshouldbeusedfortheTable,GroupandFilternamesassociatedwiththeView,soeachviewhasitsownuniqueTable,FilterandGroupwiththesamename.

❖ CreatetheTables,FiltersandGroupsforeachView.

❖ CreatethefirstViewandmakesuretheBarformattingandthePrintsettingsarecorrect.

❖ TheuniquelynamedTables,GroupsandFiltersshouldnotbedisplayedinthemenustoavoidtheirinadvertentapplicationandcorruption.

Page 50: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ TheprintpreviewHeader,FooterandLegendshouldreadallthetextdatafromtheFILE,Info,ProjectInformation,AdvancedPropertiesform.ThusachangetotheheaderorfootertextcanbemadeinoneplaceforallViews,theFILE,Info,ProjectInformation,AdvancedPropertiesform.

❖ EnsurethatyouhavehiddenallthebarsthatyoudonotwantdisplayedintheLegend,byplacingan“*”infrontofthebarnameintheBarsform.SeePara6.5.

❖ CreatenewViewsbycopyingthefirstViewonlyafterithasbeenchecked,double-checked,andcheckedagain.

5.4BarFormattingSelectFORMAT,Format,LayouttoopentheLayoutform,whichhassomeinterestingfeatures:

5.4.1BarDateFormat

TheBarDateformatoptionsetstheformatfordatesdisplayedonbarsonly.

Theoptiontodisplaydateson:

❖ OneormoreselectedbarsismadeusingtheFORMAT,BarStyles,Format,Baror

❖ OnallbarswiththeFORMAT,BarStyles,Format,BarStylesform.

Page 51: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

5.4.2BarHeights

TheBarheight:optionsetstheheightofallthebars.

Individualbarsmaybeassigneddifferentheightsbyselectingabarshapeinthestylesform.

5.4.3AlwaysRollUpGanttBars

AlwaysrollupGanttbarsandHiderollupbarswhensummaryexpandedworksasfollows:

❖ Tasksbeforerollup:

❖ TaskswithAlwaysrollupGanttbarscheckedandHiderollupbarswhensummaryexpandedunchecked,resultsinbothSummaryandDetailedtasksdisplayedintheBarChartwhenrolledup:

❖ TaskswithbothAlwaysrollupGanttbarsandHiderollupbarswhensummaryexpandedchecked,resultsintheSummaryTaskbarbeinghiddenwhentheNonSummaryTasksarerolledup:

❖ AnindividualbarmayberolleduptoasummarytaskusingtheRollupoptionintheTaskInformationform,GeneraltabwhenAlwaysrollupGanttbarsoptionsareunchecked.

Page 52: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

5.4.4RoundBarstoWholeDays

TheRoundbarstowholedays:isusedtomakeiteasiertoseeshortdurationbarsonalongdurationschedule:

❖ Whenthisoptionisunchecked,thelengthofthetaskwillbeshowninproportiontothetotalnumberofhoursworkedperdayoverthe24-hourtimespan.Forexample,an8-hourworkingdurationbarisshownbelow:

❖ Whenthisoptionischecked,thetaskbarisoftendisplayedandspannedoverthewholedayirrespectiveofcalendarworkingtime:

5.5PuttingTextonBarsTextmaybeplacedonallbarsusingtheFORMAT,BarStyles,Format,BarformorselectedbarsusingtheFORMAT,BarStyles,Format,BarStylesformandtheFontSizeisspecifiedintheTextStylesform.

Note:ThelengthoftheBarChartmaybereducedbyplacingthetextontopofthebarinsteadoftheend:

5.6FormatColorsColorsareformattedinanumberofforms:

Page 53: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ NonworkingtimecolorsintheGanttChartareformattedintheTimescaleform;double-clickonthetimescale.

❖ TextcolorsareformattedintheFORMAT,Format,TextStylesandFontforms.

❖ GridlinecolorsareformattedintheFORMAT,Format,Gridlinesform.❖ HyperlinkcolorsareformattedunderFILE,Options,Advancedtab.❖ TimescaleandColumnHeadercolorsareformattedwiththesystemcolor

schemeselectedfromtheFILE,Options,General,OfficeTheme.❖ TheLogicLines,alsoknownasDependencies,Relationships,orLinks,

inherittheircolorfromthepredecessor’sbarcolorintheGanttChartviewandmaybeformattedintheNetworkDiagramviewbyselectingFORMAT,Format,Layoutform.

5.7HowtoStopTextWrappingManypeoplegetfrustratedwiththewayMicrosoftProjectseemstowraptextwithoutwarningwhencolumnsareadjustedinwidthandclickingontheWrapText buttondoesnotsolvetheproblem.

ThefieldthatcontrolsthewrappingoftextistheTextWrappingfieldfoundintheVIEW,Data,Tables,MoreTablesformandselectingaTabletoedit:

TostopALLTextWrappingyoueither:

❖ OpentheTablesformandsetallcolumnstoNointheTextWrappingfield,or❖ IfyouwishtousetheWrapText buttonthenyoumustselectthecolumn

first,thenclickontheWrapText buttonandthereadjusttherowheightsbyselectingtheSelectAllbuttonandadjustingonerow.

Page 54: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

5.8DisplayTaskswithoutSuccessorsasCriticalNormallyataskthatdoesnothavesuccessorswilldisplayFloat,aspertask4below:

❖ SelecttheFILE,Options,Advancedtab,Calculationoptionsforthisproject:section,

❖ ChecktheCalculatemultiplecriticalpathsboxandthentasks:WithoutsuccessorswillhavetheirLatedatessettoequaltheirEarlydatesandwillbecalculatedwithzeroTotalFloat(Slack),

Displayedascriticalinthebarchartand

AreindicatedcriticalintheCriticalcolumn.

Youmightconsiderusingthisfunctionwhen:

❖ YouwouldliketodisplayMultipleCriticalPaths.Thishappensinaschedulewithseveralareasofseparablepartsandyouwishtodisplaythecriticalpathforeacharea.

❖ Youhavefewornorelationshipsinthescheduleandyouwanttofoolpeopleintothinkingthatyouhavecreatedaschedulewherealltasksareonthecriticalpath.Inthissituation,don’tforgettohidetheIndicators,PredecessorandSuccessorcolumns!

5.9PreventingDescriptionsfromIndentingWhenaprojecthasanumberofSummaryTasklevelsandthetaskdescriptionsarelongthentheTaskNamecolumnmayhavetobewidenedtodisplaythefulldescription:

Page 55: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

TopreventtheTaskNamefromindentingselecttheFILE,Options,QuickAccessToolbartab,Choosecommandsfrom:Allcommands,selecttheIndentNameoptionandpressAdd.GotothequickaccesstoolbarandunchecktheboxforIndentname:

Note:SmallindentsmaybecreatedbytypingspacesatthestartoftheTaskNames.

5.10ReducingColumnWidthsItisusefultoreducethewidthofcolumnssomoredatamaybedisplayedonscreenandinprintouts.Thereareseveralwaystoreducecolumnwidths:

❖ TopreventtheTaskNamefromindenting,gototheQuickAccessToolbarandunchecktheIndentnameoption.Refertopara5.9forinstructionsonhowtoaddthiscommand.

❖ ToreducethewidthoftheDurationcolumn,selecttheFILE,Options,AdvancedtabandunderDisplayoptionsforthisproject:

Minutes:,Hours:,Days:,Weeks:,Months:,Years:–Fromthedrop-downboxes,selectyourpreferreddesignatorsfortheseunits.Change“days”to“d”and“hr”to“h”tomakethedurationcolumnsnarrower.

Addspacebeforelabel–Placesaspacebetweenthevalueandthelabel;uncheckthistomakedurationcolumnsnarrower.

ChangethecolumntitlefromDurationtoDur:

❖ ChangethedateformattoashorterformatintheFILE,Options,Generaltab.

Page 56: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

5.11HowtoDisplayaTaskIDthatWillNotChangeOnefrustratingpartofusingMicrosoftProjectisthattheTaskIDisnotuniqueandasnewtasksareinsertedthentheIDchanges.TheTaskIDisthereforeaLineNumber.TheUniqueIDfieldhelpsresolvethisissue,whichisoftenveryimportantindisputeresolution.EachtaskisassignedaUniqueIDwhenitiscreated.Thisnumberisnotusedagainintheschedule,evenifthetaskisdeleted.

TherearetwoothercolumnsthatmaybeusedtoeditanddisplayrelationshipsusingtheUniqueID:

❖ TheUniqueIDPredecessor,and❖ TheUniqueIDSuccessor.

TheTaskUniqueIDallowsuserstoidentifyeasilywhichactivitieshavebeenaddedordeletedorwhenarevisedschedulehasbeensubmitted.

Ontheotherhand,ifonewantstoresettheUniqueID,orhidetheadditionordeletionoftasks,thencreateanewschedule,transferthecalendars,etc.withOrganizer,andcopyandpasteallthetasksintothenewscheduleafterexportingtheResourcesandCalendars.

Notes:

CutandPastingTaskwillalsochangetheirUniqueIDs.

ThereisalsoauniqueResourceIDandaResourceAssignmentUniqueID.

5.12HidingTaskInformationSometimesitisdesirabletohidesomeinformationinabarorcellaboutaspecifictask.

5.12.1HidingBars

Tohideabar:

❖ OpenTaskInformationfromtheGeneraltab,and

Page 57: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ ChecktheHidebaroption.5.12.2HidingText

Tohidetextinoneormorecells:

❖ Selectthecells,

❖ RightClickandusetheTextStylesfunctiontomaketheTextcolorthesamecolorastheBackground,usuallywhite.

5.12.3MarkingTasksInactive

ToinactivefunctionfoundontheTaskInformationform,GeneraltabinProfessionalversionsonlymakesataskinactive:

❖ Thisallowsyoutoeffectivelyremoveataskfromtheschedulecalculations,

❖ ThepicturesbelowshowthebeforeandaftermakingataskInactive:

Note:ThisisusefultoshowscopebeingremovedfromaprojectbutmaintainavisiblehistoryandonlyavailableintheProfessionalVersionsandnotStandardVersions.

5.13AnchoraVerticalLinetoaMilestoneItisoftenusefultohaveaverticallineontheBarCharttoshowtheendofaPhaseorStagethatwillmoveastheprojectisrescheduled.

❖ InsertaverticallineontheBarChartusingtheFORMAT,Drawings,Drawingfunction.

❖ SelecttheLineoptionanddrawitonthescreen.

ToattachtheverticallinetoaTasksoitmoveswhenthetaskmoves:

❖ Double-clickontheverticallinetoopentheFormatDrawingform,❖ SelecttheSize&PositiontabandselecttheTaskIDtoattachthelineand

therelativepositiontothebar:

Page 58: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

5.14ZoomSliderDangersTheZoomSliderwasintroducedwithMicrosoftProject2010andreplacedtheView,Zoom…function.Thismaybefoundatthebottomright-handsideofthescreenandprovidesasimplewayofscalingthetimescaleintheGanttChartandallothertimescaledviewssuchastheCalendar,UsageandNetworkDiagramView.

Thisfunctionworksdifferentlytootherschedulingsoftwareinthatitchangesthescaleandthedisplayedtimeunitsatthesametimeandmayresultinsomeundesirabletimeunitsbeingdisplayed,suchas3and11daytimeintervals.

Page 59: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Oncethisfunctionisused,youroriginaltimescaledateformattingwillbelostandmayonlyberecoveredwithundoasthisfunctionappliesitsownformattingsuchasdateformats.

Theauthorhasfoundthatmorepredictableresultsareachievedbyusingthetraditional ZoomInandZoomOutfunctionswhichmaybeaddedtotheQuickAccessToolbar.

Note:YoumaywishtoremovetheZoomSliderfromtheStatusbaratthebottomonthescreen.

5.15WhyistheNon-workingTimeDisplayedIncorrectly?TheTimescaleformprovidesanumberofoptionsfortimescaledisplayincludingtheshadingofNonworkingtime.

ToopentheTimescaleformDouble-clickonthetimescale.TheNonworkingtimetaballowsyoutoformathowthenonworkingtimeisdisplayed.Youmayselectonlyonecalendar.Thenonworkingtimemaybepresentedasshadingbehindthebars,infrontofthebarsorhidden.

Notes:

BydefaultthisissettotheStandardCalendarforeachviewanddoesnotchangewhentheProjectDefaultCalendarischanged.

Page 60: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

ThereforeifyouchangetheProjectBasecalendarintheProjectInformationandyouwishtoseethisnewcalendarinallviews,thenyouwillhavetoeditalltheviews.

5.16DisplayinganS-CurveAsingleS-CurvemaybecreatedgraphicallyanddisplayedbyMicrosoftProjectby:

❖ DisplayingtheResourceSheetinthetoppaneandselectingalltheresources,

❖ TheResourceGraphinthebottompane,❖ Right-clickinganddisplayingtheCumulativeCosts,and❖ Right-clicking,openingtheBarStyles…formandformattingasshownbelow:

WhenmorethanoneS-CurveisrequiredthenitissuggestedthatthedatashouldbeexportedtoExcelwiththeREPORTtoolbar,VisualReportsbutton andgraphedoryoucouldconsiderusingaproductlikeDecisionEdge.

5.17DisplayingCumulativeHistogramThismaybeachievedinasimilarwayasanS-Curveby:

Page 61: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ SelectingCumulativeWorkand❖ SelectingtheBaroptionintheBarStyles…formunderTotalallocatedwork

forSelectedresources.

5.18DisplayingaProjectSummaryTaskAProjectSummaryTaskmaybedisplayedbycheckingtheShowprojectsummarytaskboxfromtheFILE,Options,Advancedtab,Displayoptionsforthisproject:section.

❖ Thistaskspansfromthefirsttothelasttaskintheprojectandis,ineffect,abuilt-inLevel0OutlineLevelTask.

❖ TheProjectSummaryTaskdescriptionislinkedtotheProjectTitleintheFILE,ProjectInformation,AdvancedPropertiesform.

❖ AProjectSummaryTaskisavirtualtaskandmaynotbeassignedresources,relationshipsorconstraints.

Note:UnfortunatelyinlaterversionstheProjectTitleinPropertiesformislinkedtothefilenametheprojectissavedwithandthislinkmaynotbebroken,sotheProjectSummarytaskisalwaysthesameastheFileName.

Page 62: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

6GETTINGITOUT-PRINTING6.1PrintingtoOnePageWidePrintinginMicrosoftProjecthasalwaysbeenalittleproblematicandrequiresalittlepatiencetogetright,butthefollowingsuggestionsmayassist:

❖ CreateViewsthatarejustusedforprintingandoncetheyworkdonoteditthemorusethemforday-to-daymaintenanceoftheschedule.

❖ Ifyouwishtofitascheduletoonepagewideitisusuallybesttomakesurethatmostoftheschedulefitsontothescreen,oratleastthatthecolumnsandbarseachdonotoccupymorethan2/3ofatypicalalaptopscreen.

❖ TryprintingtoapdfwriterwithanA3or11”x17”papersizeandthenreducethepapersizewhenprintingtoanA4orLetterpapersize.

Toreducethewidthofcolumns,asdiscussedearlier:

❖ Selectanarrowdateformat,

❖ SelecttheFILE,Options,Edittabandselectanarrowformatforthedurations;forexample,use“d”andnot“days”.

❖ SelecttheFILE,Options,AdvancedtabandunchecktheAddspacebeforelabeloption.Thiswillremovethespacebetweenthedurationvalueandunits.

❖ ConsiderincreasingtherowheightsotheTaskNamecolumnwidthmaybereducedandtextdisplayedontwoormorelines.

6.2PrintingaDateRangeAdaterangemaybeselectedfromthePrintform.InearlierversionsofMicrosoftProject,thishadtobeselectedfromtheFilemenu,butinlaterversionsthesedatesmaybeeditedbyselectingPrintfromthePrintPreviewform.

ThesedatesaresavedwiththeViewsoyoumaywishtoconsidercreatingaviewforeachdaterange.

Inaddition,afiltermaybecreatedtoremovetasksthatarenotinthedaterangetobeprinted.

Page 63: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

6.3PrintingaGanttChartandResourceGraphorUsageTableonOnePage

MicrosoftProjectallowsthedisplayofaGanttChartintheTopPaneandaResourceGraphorUsageTableinthebottompanebutdoesnotprintthetwopanesinoneprintout.

❖ Oneoptionistoprintbothreportstoapdfwriterandthenusethepdfsoftwaretocreateonefilewithbothpages.TheGanttChartandTableorHistogramwillnotbeonthesamepagebutwillbeonereport.ProgramslikeAdobeAcrobatenablethis.

❖ AnotheroptionistouseascreencaptureprogramlikeSnagItandcopyboththetopandbottompanetoExcelorWordtocreateacombinedreport.

6.4PrintingtheCalendarItisalwaysusefultobeabletoprintoutthecalendarforpeopletoreviewtheworkinghoursandnon-workperiods.

MicrosofthasremovedtheoldReportsfrom2013andthereforetheabilitytoprint

Page 64: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

textWorkingDaysreport,whichlistedtheNonWorkdayshasbeenlost.Theoptionstoprintonlythecalendarare:

❖ Saveyourproject,deletealltasks,displayandprinttheCalendarview,or❖ Downloadathirdpartysoftwarethatwillprintthecalendars,suchasAsta

Powerproject,or

❖ UsingaScreenCaptureprogramlikeSnagitandScreenCapturepicturesoftheCalendar,monthatatime.

6.5HidingUnwantedBarsintheLegendYouwillfindalargenumberofbarsaredisplayedintheLegendwhenprintingandtheseareoftenundesirableinreportsastheyconsumealotofspaceatthebottomofthepage.

TheseshouldnotbedeletedfromtheBarStylesformascertainfunctionssuchasRecurringTasksrelyontheseformatstodisplaythesespecialtaskbarsintheGanttChart.

Tohideabar,typeintheLegendan“*”infrontoftheNameintheBarStylesform.ThesebarswillstillbedisplayedintheGanttChartbutwillnotbedisplayedintheLegendinPrintPreview:

6.6WhathasHappenedtotheManualPageBreaks?TheManualpagebreakscheckbox,whichallowedprintingandignoringmanualpagebreaks,inthePrintformhasbeenremovedfromMicrosoftProject2013and2016.

YouwillneedtoaddtheInsertPageBreak ButtonontheQuickAccessToolbartoaddmanually-insertedbreaksPageBreaks.

Page 65: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

7RESOURCEBASICS7.1HowManyResourcesShouldIHave?Aresourcedschedulemaybecreatedforthefollowingpurposes:

❖ Estimating.Thistypeofscheduleisusedforestimatingthecostanddurationofaprojectorpartofaproject,suchasarepeatableprocess.Manyresourcesmaybeassignedtoeachtaskinanestimatingschedulebecauseitisnotintendedtostatustheschedule.

❖ Control.Thistypeofscheduleisusedtomonitorandcontroltheprogressofaproject.Inthissituationthenumberofresourcesshouldbeminimizedasfaraspossible.Thisisbecauseeachresourceassignmentshouldbereviewedandpossiblyupdatedwhenthescheduleisupdated.Updatingalargeschedule,withmanytasksandmanyresourcesassignedtoeachtaskbecomesaverytimeconsumingoperation.Inthissituationtheschedulermaylosesightoftheirprimaryaimofforecastingtheprojectenddate,resourcerequirementandpossiblytheFinalForecastCost.Thescheduleisnowindangerofbecominganexpensivetimerecordingsystemandthusunabletoprovideessentialforecastinformation.Thusthenumberofresourcesinacontrolscheduleshouldbelimitedtothemaximumnumberrequiredtosatisfycontrolandreportingrequirements.

7.2TheBalanceBetweentheNumberofActivitiesandResourcesOnlargeorcomplexschedules,youneedtomaintainabalancebetweenthenumberofactivitiesandthenumberofresourcesthataretobeplannedandtracked.Asageneralrule,themoreactivitiesaschedulehas,thefewerresourcesshouldbecreatedandassignedtotasks.

Whenaschedulehasalargenumberoftasksandalargenumberofresourcesassignedtoeachtask,theschedulermayendupinasituationwhereprojectteammembersareunabletounderstandthescheduleandtheschedulerisunabletomaintaintheschedule.

Youmayconsiderinthissituationusingresourcesthatrepresentskillsortradesinsteadofindividualpeople,andonverylargeprojectsusingcrewsorteams.

Updatingaprojectwithresourcesissubstantiallyharderthanwithoutresources.Thesoftwareishardenoughtousewithoutaddingthecomplexityoflotsofresourcesthatmaynotaddvaluetotheschedule.

Itiscriticaltoentertheminimumnumberofresourcesintoaschedulebecausetheyconsumeasubstantialamountoftimetoupdate.

7.3DurationsandAssignmentsChangeasResourcesareAssigned

Page 66: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

MicrosoftProjecthassomecomplexuserdefinablerelationshipsthatdeterminewhichparameterschangewhenresourcesareaddedtotasks.Forexampletheserelationshipsmayresultindurationsorhoursperresourcereducingasresourcesareaddedtotasks.

Thissectionwillexplainhowresourceassignmentscalculateandmakesomesuggestionsonhowtosetupthesoftwaresothetaskscalculatethewayyouexpect.

7.3.1TaskType–FixedDuration,FixedUnits,FixedWork

Usersmustunderstandtherelationshipbetweenthefollowingparameters:

❖ ThetaskDuration,❖ TheWork(thenumberofhoursrequiredtocompleteatask),and❖ TheUnitsperTimePeriod(therateofdoingtheworkornumberofpeople

workingonthetask).

Therelationshipis:

DurationxUnitsperTimePeriod=Work

Forexample,a2-daytaskat8hoursperdayhasaDurationof2x8=16hours.If2peopleareassignedtothetasktheUnitsperTimePeriodis2.00or200%andtheworkis16x2=32hours.

TherearethreeDefaulttasktype:optionsandthedefaultisassignedintheFILE,Options,Scheduletab.EachnewtaskissetwiththisTaskType.ItmaybechangedatanytimeforeachtaskintheTaskTypefieldwhichmaybeaccessedinanumberofplacessuchastheTaskTypecolumnintheTaskform,TaskDetailsformandtheTaskInformationform.

TheDefaulttasktypedecideshowthisrelationshipoperateswhenoneparameterchanges.Theyare:

FixedDurationTheDurationstaysconstantwheneithertheUnitsperTimePeriodorWorkarechanged.

AchangetotheDurationchangestheWork.

FixedUnits

TheUnitsperTimePeriodstayconstantwheneithertheDurationorWorkischanged.

AchangetotheUnitsperTimePeriodchangestheDuration.

Note:Thisistheauthorspreferreddefault.

Page 67: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

FixedWork

TheWorkstaysconstantifeitherDurationorUnitsperTimePeriodarechanged.

AchangetotheWorkchangestheDuration.

ThereforeyourestimatewillnotchangewhenyouchangeDurationorUnitsperTimePeriod.

7.3.2EffortdrivenorNonEffortdriven?

TheTaskEffortisthesumoftheWork(hours)ofallWorkTyperesourcesassignedtoatask.TheEffortdrivenoptiondetermineshowtheeffortiscalculatedasresourcesareaddedorremovedfromaFixedUnitsorFixedDurationtask.Therearetwooptions:

Effortdriven

Whenaresourceisaddedorremovedfromatask,theTaskEffortassignedtoataskremainsconstant.ThereforetheWorkofexistingResourcesisreducedwhenanewresourceisassigned.Addingorremovingresourcesfromataskwillleavethetotaleffortassignedtoataskconstant,unlessallresourcesareremovedorachangeismadetotheworkofexistingresourceassignments.

NonEffortdriven

Whenaresourceisaddedtoorremovedfromatask,theResourceEffortorWorkofotherresourcesremainsconstant.Addingordeletingresourcesincreasesordecreasesthetotaltaskeffortandwillnotchangetheeffortofassignedrecourses.

Note:Thisistheauthorspreferreddefault.

Insummary,asyouassignresources:

❖ IfyouwantthetotalnumberofhoursassignedtostayconstantthenmakethetaskEffortdriven.

❖ IfyouwishtoassigneachresourcewithitsownhoursorunitspertimeperiodthenmakethetaskNonEffortdriven.

Note:AFixedWorktaskisautomaticallyEffortdriven.

7.3.3TaskTypeandEffortdrivenOptions

IfyouarenotsurewhichoptiontousethenitisrecommendNonEffortdrivenasadefault.ThisoptionpreventschangestoTaskDurationsand/orexistingResourceassignmentsasResourcesareaddedorremovedfromatask.

Page 68: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ SelectFixedUnitsforactivitieswhentheUnitspertimeperiodmuststayconstantaseithertheDurationorWorkischanged.Forexample,acrewof1Excavatorand3TrucksmuststayconstantastheDurationorWorkischanged.

❖ SelectFixedDurationforactivitieswhenthedurationmustnotchangeaseitherresourceUnitspertimeperiodorWorkischanged.

❖ SelectFixedWorkifyouwishtheWorktostayconstantasthedurationischanged.TheTaskwillbemadeEffortdrivenautomaticallywiththeEffortdrivenoptiongrayedout.Forexample,aprogrammerassignedfulltimeforaweekwillhave40hours’work.Whenthedurationisdoubledtoaweek,theprogrammerwillwork50%ofthetimeover2weeksbutstillwork40hours.IfyouassignanotherpersontohelpthenthetotalWorkwillremainat40hoursandtheDurationnotchange.

ThedefaultfornewTasksissetintheFILE,Options,Scheduletab,Schedulingoptionsforthisproject:,select fromthedropdownboxandallnewprojectswillhavetheseastheirdefaultoptions.

7.4AssigningResourcestoTasksTherearemanymethodstoassignresourcestotasks.Insummary,theyare:

❖ Highlightoneormoretasksthatyouwanttoassignresources.ClicktheAssignResourcesicon ontheResourcestoolbartodisplaytheAssignResourcesform.

❖ OpenthebottomwindowanddisplaytheTaskDetailsFormorTaskFormorTaskNameForm,thenselecttheResourceWorkorResourceCostoptionfromtheFormat,Detailsoptionorbyright-clickingintheform.

❖ Double-clickonaTasknameorclickontheTaskInformationicon toopentheTaskInformationformandselecttheResourcestab,

❖ DisplaytheResourceNamescolumnandtypeintheresourceassignment.

7.5ResourcesandSummaryTasks❖ SummarytasksmaybeassignedFixedCostsandResources.❖ AsummarytaskissettoFixedDurationandNonEffort-Driven.Thissetting

maynotbechanged.AnincreaseindurationwillincreaseWorkandtheResourceUnitswillstayconstant.

❖ ItisrecommendedthatunlessaSummarytaskWorkresourceassignmentandcostsarerequiredtovaryinproportiontotheSummarytaskduration,thenWorkresourcesshouldnotbeassignedtoaSummarytask.YoushouldconsiderusingFixedCosts,CostresourceoraMaterialresourceifappropriate.

Page 69: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

8UPDATINGESSENTIALS8.1BaselinesandUpdatingaProjectAfteraschedulehasbeenreviewedandapproved,itshouldbebaselinedbeforeitisupdatedforthefirsttime.SettingtheBaselinecopiestheEarlyStartandEarlyFinish,theOriginalDurationandeachresource’sCostsandWorkintoBaselinefields.

AMicrosoftProjectBaselineisnotacompletebaselinebecauseitdoesnotrecordConstraints,Relationships,FloatortheCriticalPath.

OncetheBaselineissetyouwillbeabletoupdateyourplanandcomparetheprogresswiththeoriginalplanandbeabletosee:

❖ Iftheplannedprogresshasbeenachieved,

❖ Iftheprojectisaheadorbehindschedule,and

❖ Byhowmuchintimeandcost.

ABaselineissetbyselectingPROJECT,Schedulegroup,SetBaseline.

ThereareanumberofoptionsandformsavailabletoupdateprojecttasksaftersettingtheBaseline.

Irrespectiveofwhichformsareused,therearetwomainmethodstoupdateaproject:

❖ AutoStatustheschedulebyallowingthesoftwaretoautomaticallyupdatethetasks,asiftheprojectprogressedexactlyaccordingtoschedule.Then,ifrequired,adjusttaskstoreflectactualeventsandrevisions,or

❖ Updateeachtaskonebyone.

8.2WhichBaselineShouldBeUsed?AfteraprojecthasprogresseditmaybenecessarytosetanewBaseline.

Thismayoccurwhenthescopeofaprojecthaschangedandanewbaselineisrequiredtomeasureprogressagainst,butatthesametimeyoumayalsowanttokeepacopyoftheoriginalbaseline.

AnewBaselinemaybeusedtodisplaytheeffectofscopechangesonaplanbysettingaBaseline,addingthescopechangeandcomparingtherevisedschedulewiththeBaseline.

TheBaselinedatamaybereviewedinsomeViewssuchastheTaskDetailsForm,incolumnsandontheBarChart.YouwillbeabletodisplaytheBaseline1to10andInterimPlandatesanddurationsincolumnsandasbarsontheGanttChartbutnotintheforms.Baseline1to10alsodonothavevariancecolumns.

Page 70: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Therefore,itisrecommendedthatthecurrentbaselinebesavedastheBaselinesincethedataismoreaccessiblefromtheBaselinethanBaseline1to10.PreviousbaselinesshouldbecopiedtoBaselines1to10andpreservedasarecord.

AnotherbenefitofusingBaselineisthatithasVarianceStart,VarianceFinishandVarianceDurationcolumnsthatarenotavailablewithotherBaselines,butmaybecalculatedusingaCalculatedField.

Note:ThedownsideofusingoneoftheBaselines1to10isthatitisnotpossibletoeasilyidentifywhattheBaselinewassetforasthereisnotinbuiltwayofnamingthesebaselines.

8.3PrinciplesofUpdatingaProgramIdeally,schedulingsoftwarehasonecurrentDataDateandthefunctionofitisto:

❖ Separatethecompletedpartsoftasksfromincompletepartsoftasks,

❖ CalculateorrecordallcostsandhourstodatebeforetheDataDate,andtoforecastcostsandhourstogoaftertheDataDate,

❖ CalculatetheFinishDateofanin-progresstaskfromtheDataDateplustheRemainingDurationovertheTaskCalendar.

ThereforeaproperlyupdatedMicrosoftProjectprogramtheStatusDateshouldbeusedastheDataDate:

❖ CompletedTaskswouldhaveActualStartandActualFinishDatesinthepast.

❖ InprogresstaskswouldhavetheActualStartandActualDurationinthepast,andtheEarlyFinishandRemainingDurationintheFuture.

❖ Unstartedtasksshouldbeinthefuture.

InMicrosoftProjectisrelativelysimpletobeinasituationwhereyouhavecompleteorin-progresstaskswithstartdateslaterthantheStatusDate,and/orincompleteorunstartedtaskswithafinishdateearlierthantheStatusDate.Thisisanunrealisticsituation,whichismoredifficulttoachieveinotherschedulingsoftwarepackages.Careshouldbetakentoavoidthissituationandchecksmadeaftertheschedulehasbeenupdated.

Note:TheEastwoodHarristemplatefoundatthewww.eh.com.auwebsiteSoftware&DownloadspagehasaTrackingTablewithanadditionalcolumnshowingwhatisrequiredtodotoensurethetasksarecorrectlyupdated.

8.4In-progressTaskFinishDateCalculationManyplanningandschedulingpackagescalculateataskFinishDatefromtheDataDateplustheRemainingDurationovertheTaskorResourceCalendar,

Page 71: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

whicheverisapplicable.

Unlikemostplanningandschedulingsoftwarepackages,MicrosoftProjectignorestheCurrentDateandStatusDatewhencalculatinganin-progresstask.ItcalculatesataskFinishDatefromtheActualStartDateplustheDurationandeffectivelyignorestheRemainingDurationfornormalprogresscalculation.

Thereisanin-builtproportionallinkbetweenDuration,%Complete,ActualDurationandRemainingDuration.Itisnotpossibletounlinkthesefields(asinotherschedulingsoftware)andthereforenotpossibletoentertheRemainingDurationindependentlyofthe%Complete.

Thus%Completefieldisthe%Durationofatask.

8.5CurrentDateandStatusDateMicrosoftProjecthastwoprojectdatadatefieldsthatmaybedisplayedasverticallinesontheschedule.ThesedatesmaybeeditedfromthePROJECT,Properties,ProjectInformationform:

❖ CurrentDate–Thisdateissettothecomputer’sdateeachtimeaprojectfileisopened.ItisusedforcalculatingEarnedValuedatawhenaStatusDatehasnotbeenset.ThetimeoftheCurrentDateissetbydefaulttothestarttimeofaday,seethepicturebelow.

❖ StatusDate–ThisfieldisblankbydefaultwithavalueofNA.TheStatusDatewillnotchangewhentheprojectissavedandreopenedatalaterdate.ItoverridestheCurrentDateforcalculatingEarnedValuedataandissetbydefaulttothefinishtimeofaday,seethepicturebelow.

Page 72: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Note:ItisrecommendthattheStatusDateissetanddisplayedasaverticallineonaprogressedscheduleandtheCurrentDatenotdisplayed,becausetheCurrentDaterepresentsthedatetodayanddoesnotnormallyrepresentanyschedulingsignificance.

8.6AutoUpdatingUsingUpdateProjectTheMicrosoftProjectfacilitytitledUpdateProgressisusedforupdatingaprojectasifithadprogressedaccordingtoplan.ThisfunctionsetsActualStartandActualFinishdates,%CompleteandRemainingDurationsinproportiontoauser-assigneddate,andalsosetstheStatusDate.

SelectPROJECT,UpdateProjectlocatedintheStatusgrouptoopentheUpdateProjectform:

TherearetwooptionsunderUpdateworkascompletethrough:whichapplytoin-progresstasksonly.

❖ Set0%–100%completeandthisistherecommendedoptionwhichsetstheprogressinlinewiththeStatusDate,or

❖ Set0%or100%completeonly.Thisoptionleavesthe%Completeatzero

Page 73: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

untilthetaskis100%complete.Thisoptionsupportstheprogressmeasurementphilosophyofnotawardingprogressuntilthetaskiscomplete,buttasksoftenlookbehindscheduleandtheActualandRemainingDurationsarecalculatedincorrectly.

8.7MovingIncompleteWorkintotheFuturebySplittingThereisafeaturewhichwillscheduletheIncompleteWorkofanIn-Progresstasktostartonaspecificdateinthefuture:

❖ Ifyouwanttoapplythisoperationtosometasks,thenthesetasksshouldbeselectedfirst.

❖ SelecttheFILE,Options,ScheduletabandensuretheSplitin-progresstasksoptionischeckedotherwisethisfunctionwillnotoperate.

❖ SelectPROJECT,UpdateProjectlocatedintheStatusgrouptoopentheUpdateProjectform:

❖ ClickontheRescheduleuncompletedworktostartafter:radiobutton.❖ Specifythedateafterwhichincompleteworkshouldcommenceinthedrop-

downboxtotherightandclickonthe button.

Note:ThisfunctiondoesnotsettheStatusDateandmaybedifferenttotheStatusDate.ItisthereforeeffectivelyanotherDataDate.

8.8WhereistheTrackingToolbar?MicrosoftProject2010,2013and2016donothaveadedicatedTrackingtoolbarasinearlierversionandsometrackingcommandscanbefoundintheTASK,SchedulegroupandPROJECT,Statustab.

TocreateacompleteTrackingtoolbar;gotoFILE,Options,CustomizeRibbon,clickon ,clickon andnameboththetabandthegroupTracking.NowselectandaddthecommandslistedontheleftsideofthepanetothenewlycreatedTrackingtoolbar.

Alternativelyyoumayaddthemissingbuttonstotheexistingtoolbars.

Page 74: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

YoumayfindthefollowingcommandsveryusefulandshouldbeaddedtoyourQuickAccessToolbar:

❖ MarkonTrackupdatestheselectedtaskasifithasproceededexactlyasitwasscheduled.Anin-progressorcompletedtaskcouldbedraggedtowhereitactuallyhappenedandthenthebuttonclickedtoprogressthetask.

❖ RescheduleWorkwillsplitataskthatisbehindscheduleandplacetheincompleteportionaftertheStatusDate.ForthisfunctiontoworkthechecktheSplitinProgresstaskboxintheFILE,Options,Scheduletab,Splitin-progresstasksmustbechecked.

Thefollowingcommandsyoumayalsofinduseful:

❖ ProgressLinewilladdaprogresslinethatshowsiftasksareaheadorbehindschedule.RightclickontheGanttCharttoopenthemenuandselectProgressLinestoopentheProgressLinesformwherethelinesareformatted.ABaselineshouldbesettoprovideacomparisontotheoriginalplan.MultipleProgresslinesmayberecorded.

❖ PercentCompletebuttonssetthepercentcompleteasindicatedbythebuttonandmaybeusedinconjunctionwiththeRescheduleWorkbutton.

❖ UpdateTasksopenstheUpdateTasksformwhereyoumayupdateindividualtasks.

❖ UpdateProjectopenstheUpdateProjectformwhereyoumayupdateacompleteprojecttoanewStatusDateasifitwentaccordingtoplan.

❖ DisplaystheProjectStatisticsform.

8.9WhyDoCalculationOptions–MoveendofcompletedpartsNotWork?

ThesenewfunctionswereintroducedinMicrosoftProject2002intendedtoassistschedulerstoplacethenewtasksastheyareaddedtothescheduleinalogicalpositionwithrespecttotheStatusDate.ThisfunctionisdifficulttouseandsomepracticeisrequiredtomakeitworkproperlyandyoushouldconsiderNOTusingit.

Herearesometipsifyouareunabletogetittowork:

❖ TheseoptionsareactivatedfromtheFILE,Options,Scheduletab,undertheSchedulingoptionsforthisproject:‘ProjectName’:

❖ IftheStatusDatehasnotbeensetthentheCurrentDateisused,andthisisoftenanirrelevantdate,soensureyousettheStatusDate.

Foralltheseoptionstooperateallfourofthefollowingparametersmustbemet:

Page 75: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ TheSplitin-progresstasksoptionintheScheduletabmustbechecked,and

❖ TherequiredoptionontheScheduletabmustbecheckedbeforethetaskisaddedoredited,and

❖ TheUpdatingtaskstatusupdatesresourcestatusoptionontheCalculationoptionsforthisproject:sectionmustbechecked,and

❖ TheTaskMUSTNOTBEassignedTaskDurationTypeofFixedDuration.❖ TheseoptionsmayNOTbeturnedonandofftorecalculatealltasks.The

optionsonlyworkonnewtaskswhentheyareaddedtoascheduleorwhenataskisupdatedbychangingthe%Complete.

❖ ThisfunctionwillignoreconstraintsevenwhentheScheduleOptionTaskswillalwayshonortheirconstraintdateshasbeenset.

❖ Thisfunctionmaynotbeappliedtoexistingschedules,butonlytonewtasksiftheoptionsaresetbeforethetasksareaddedorwhenatask%Completeisupdated.

Thisfunctionhassomerestrictions:

❖ Existingschedulesmaynotbeopenedandthefunctionapplied.

❖ WhentheMovestartofremainingpartsbeforestatusdateforwardtostatusdateisused,itwillchangeanyActualStartdatethatyouhaveenteredpriortoenteringa%Complete.ChanginganActualDateisnotadesirableevent.

Notes:

Thisoptionshouldbeusedwithcautionandusersshouldensuretheyfullyunderstandhowthisfunctionoperatesbyupdatingasimplepracticeschedulemultipletimes.

ItisrecommendthatthisfunctionshouldnotbeusedandtasksupdatedmanuallyasitisverydifficulttoperfecttheuseofthesefunctionsanditissimpletomakeundesirablechangestoActualData.

8.10ComparingProgresswithBaselineTherewillnormallybechangestothescheduledatesandmoreoftenthannotthesearedelays.ThefullextentofthechangesmaynotbeapparentwithoutaBaselinebartocomparewiththeupdatedschedule.

TodisplaytheBaselineBarintheBarCharteitheruse:

❖ TheFORMAT,BarStylesfunction,or❖ ManuallycreateaBaselineBar,or

Page 76: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ CreateaViewwiththeBaselinebardisplayed.

❖ YoumayusetheGanttChartWizard,butthisshouldonlybeusedwithprojectscreatedwithschedulescreatedwithMicrosoftProject2007andearlierduetotheincompatibilityoftheformattingoptionsbetween2007andearlierversionsand2010andlaterversions;resultinginsomebarsbeinghidden.

❖ YouwillneedtoaddtheaddGanttChartWizardbuttontotheQuickAccessToolbartouseit.

8.11ProgressLinesSomeusersliketodisplayProgressLines,whichareusuallyshownaszigzaglinesontheGanttChartshowinghowfaraheadorbehindtheprojecttasksare.

SelectFORMAT,Gridlines,andselectProgressLinesfromthedropdowntoopentheProgresslineformwheretheprogresslinesmaybeformatted:

8.12SimpleProcedureforUpdatingaSchedule–UsingAutoStatus

Thefollowingprocessshouldbeconsideredforpeoplewhorequireonesimplemethodofupdatingaschedule.Thismaynotsuitallsituationsespeciallywhenaprojectiswayoffplan:

❖ SettheBaselinebyselectingPROJECT,Schedule,SetBaseline.❖ DisplaytheBaselinebarsbyselectingFORMAT,BarStylesfunctionand

selectthenewlycreatedbaseline.

❖ DisplaytheStatusDategridline,selectFORMAT,Format,Gridlines,selectStatusDate.

❖ SelectPROJECT,Status,UpdateProjecttoopentheUpdateProjectformandselectSet0%–100%Complete,setthedateintheformtothenewStatusDate,

❖ TheprojectwillbeupdatedasifithasprogressedexactlyasplannedandtheStatusDateshouldnowbedisplayedinthebarchart.

❖ DisplayingtheTrackingTablemayassisthere.Note:TheEastwoodHarristemplatefoundatthewww.eh.com.auwebsiteSoftware&DownloadspagehasaTrackingTablewithanadditionalcolumnshowingwhatisrequiredto

Page 77: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

dotoensurethetasksarecorrectlyupdated.

❖ Nowadjustthetaskdatesbydraggingthebarsorenteringthedatesintheappropriatecolumn;theorderthattheactionstakeplaceisimportant:

CompletetasksshouldhavetheActualStartandthentheActualFinishdatesadjusted,inthisorder,tomatchthedatesthatthetaskactuallystartedandactuallyfinished.IfyouadjusttheFinishdatefirstthentheStartdate,youwillthenhavetoreadjusttheFinishdateagain.

CompletedMilestoneswillbechangedtoaTaskwhenanActualFinishdateisentered,soensureyouonlyenteranActualStartand100%ifaMilestoneiscomplete,DONOTENTERANACTUALFINISH,In-ProgresstasksshouldhavetheActualStartenteredfirst,thenthetaskbardraggedorDurationadjustedsothefinishdateiswhereitisexpectedtofinish,andfinallythe%Completeadjusted.The MarkonTrackisusefulhereasupdatestheselectedtaskasifithasproceededexactlyasitwasscheduled.

Unstartedtasksshouldhavetheirlogicanddurationsrevised.❖ Addanyscopechangestotheschedule.

❖ Savetheprojectwithanewfilenameandsaveforfuturereference.

8.13ProcedureforDetailedUpdatingThisprocedureissuitedtopeoplewhowishtoupdateascheduleproperlyandmakesuretheActualdatesandRemainingDurationsofeachTaskiscorrect.Ithassmallbutimportantdifferencestothepreviousprocess:

❖ Ensurethateveryoneontheprojectteamisawareofthereportingcycle,theupdatingprocedureandreviewprocess.

❖ Collectaccurateandcompletestatusinformation.

❖ SettheBaselinebyselectingPROJECT,Schedule,SetBaseline.❖ DisplaytheBaselinebarsbyselectingFORMAT,Format,Baselineandselect

thenewlycreatedbaseline.

❖ SelecttheGanttChartviewandyoumayfindtheTrackingTableusefultoapply.

❖ DisplaytheVariancecolumnsasrequired;theFinishVarianceisalwaysapopularcolumntodisplay.

❖ DisplaytheStatusDategridline,selectFORMAT,Format,Gridlines,andselectStatusDate.

❖ Nowenterthetaskstatusforeachtaskoneatatimebyenteringtheinformationintheappropriatecolumn.

Page 78: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ Theorderinwhichtheactionstakeplaceisimportant:

CompletetasksshouldhavetheActualStartandthentheActualFinishdatesadjusted,inthisorder,tothedatethatthetaskactuallystartedandactuallyfinished.IfyouadjusttheFinishdatefirst,thentheStartdate,youwillhavetoreadjusttheFinishdateagain.

CompletedMilestoneswillbechangedtoaTaskifanActualFinishdateisentered,soonlyenteranActualStartand100%whenaMilestoneiscomplete,DONOTENTERANACTUALFINISH,In-ProgresstasksshouldhavetheActualStartenteredfirst,thenthetaskbardraggedorDurationadjustedsotheFinishDateiswhereitisestimatedtofinishandfinallythe%CompletemaybeadjustedwiththeMarkonTrackbuttonasthisfunctionupdatestheselectedtaskasifithasproceededexactlyasitwasscheduled.

Tasksthatarebehindschedulemaybesplitwiththe RescheduleWorkiconontheTrackingtoolbar.MakesurethattheFILE,Options,Scheduletab,Splitin-progresstasksboxischecked:

Unstartedtasksshouldhavetheirlogicanddurationsrevised.❖ Addanyscopechangestotheschedule.

❖ Savetheprojectwithanewfilename.

8.14PreparingtoUpdatewithResourcesUpdatingMicrosoftProjectscheduleswithresources:

❖ Usesanumberoffeaturesthatareveryinteractiveanddifficulttocomprehend,

❖ Requiresexperienceinthesoftware,

❖ Needssignificanttimetocompletetheprocess,and

❖ Asaresultitisoftendifficulttoachievethedesiredresult.

Itissuggestedthatbeforeyouworkonaliveprojectthatyou:

❖ Createasimpleschedulewithacoupleoftasksandassigntwoorthreeresourcesagainsteachtask,

❖ SettheOptionstoreflectthewayyouwanttoentertheinformationandhowyouwantMicrosoftProjecttocalculate,and

❖ Gothroughtheupdatingprocesswithdummydataandthencheckthatthe

Page 79: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

resultsareasyouexpected.

Youwillneedtoconsiderhowthemeasureofprogressatthesummarytasklevelwillbedisplayed:

❖ The%Completeisthe%DurationCompleteandtheSummaryTask%CompleteisbasedontheproportionofalltheDetailsTasksActualDurationsdividedbythesumofalltheDetailsTasksDurations.Thesummary%Completemayoftenbeverymisleading.Thepicturebelowshowstheprojectis20%throughthedurationbutthe%Completeshows60%:

❖ The%WorkfieldiscalculatedfromtheproportionoftheActualWorktoWorkandissummarizedatsummarytaskcorrectly:

❖ The%Workand%CompletefieldsmaybeunlinkedwiththeFILE,Option,Calculationoptionsforthisproject:tabUpdatingtaskstatusupdatesresourcestatus:option.Ifunlinked,the%Workmaybedifferentfrom%Complete.Seethepictureabove.ThisallowstheeditingofResourceWorkwithoutthe%Completebeingchangedwithsomeoptions.

Otherpointstoconsiderare:

❖ DoyouwishMicrosoftProjecttocalculatetheresourceActualCostswiththeoptionFILE,Option,Calculationoptionsforthisproject:,ActualcostsarealwayscalculatedbyMicrosoftProjectchecked?

❖ DoyouwishyourincompletetaskstobesplitandscheduledtostartafteradateusingPROJECT,Statusgroup,UpdateProjectbutton ,andcheckRescheduleuncompletedtaskstostartafter:radiobuttoninconjunctionwiththeSplittaskoption?

Page 80: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

MicrosoftProject2013and2016calculatesdifferentlytoearlierversionswhentheoptionActualcostsarealwayscalculatedbyProjectareuncheckedwhentheactivityisat100%.

❖ InearlierversionstheActualCostwasunchanged,butcouldbemanuallychangedthatpointon,

❖ InMicrosoftProject2013and2016,thesoftwarechangestheActualCoststozerowhenunchecked,whichwouldnormallybelessdesirable,andtheActualCostsmustthenbemanuallyentered.

8.15UpdatingResourcesThereareanumberofplacesthatresourcesmaybeupdated:

❖ TheTaskDetailsform,TaskInformationform,Taskform,Resourceform,ResourceNameformmaybeusedtoenterthequantitiesandcoststodateandquantitiestocomplete.Usingthismethoditissimpletoendupwithactualworkandcostsinthefutureorremainingworkandcostinthepast,whichisillogicalandshouldbeavoided.

❖ TheTaskUsageViewandResourceUsageViewmaybeusedtoenterthedataperdayorweekdependingonthetimescale.ThismethodtakesmoreeffortbutwillensureActualsareinthepastandRemainingWorkandCostsareinthefuture.

Acoupleofotherpoints:

❖ FixedCostsupdatesautomaticallyinproportiontothe%Complete.CostResourcesdonothaveaQuantity,allowsalittlemoreflexibilitythanFixedCosts.

❖ WhenActualcostsarealwayscalculatedbyProjectisuncheckedActualCostsareNOTcalculatedandyouwillneedtoenteryourown.ThisoptionalsoappliestoFixedCostswhichmayresultintheFixedCostandTotalCosthavingadifferentvalue,whereaswithresourcestheCostalwaysequalstheActualCostplusRemainingCosts.

❖ CosttoCompleteareALWAYScalculatedbyMicrosoftProjectfromtheResourceRates.

❖ IfyouassignOvertimetoaresourcemakesureyouhaveanOvertimerate;otherwise,asyouassignOvertimetheForecastCostwillreduce.

Page 81: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

9CREATINGNEWPROJECTS9.1StandardizingProjectsItisoftenimportanttobeabletocreatenewschedulesthathavestandardcharacteristicssuchascalendarstailoredwithyourlocalororganization’sholidays,orlayoutsandfilterstopresentschedulesinastandardformat.Thereareseveralmethodsofstandardizingnewprojects:

❖ Global.mptwhichisusedtocreatenewprojectswhentheFILE,New,BlankProjectoptionisused,

❖ CreatingandsavingaTemplates,❖ Creatinga“StandardProject”andcopyingit.

9.2Global.mptTheGlobal.mptfunctionmaybeusedtostandardizeprojects,onlyifyouaretheonlypersoncreatingnewprojects.

❖ AnewblankprojectcopiesdefaultvaluessuchastheStandardCalendarfromtheGlobal.mptfile.

❖ TheGlobal.mptfilemaybeeditedusingtheFILE,Info,Organizeutility.ThesourceprojecthastobeopentocopydataintotheGlobal.mpt.

❖ TheGlobal.mptmaynotbeopenedwithMicrosoftProjectandispartoftheMicrosoftProjectInstallationoneachcomputer.

Note:TheauthorhasfoundanumberofissueswiththeGlobal,mptfileshippedwithastandardloadofMicrosoftProject2013and2016andrecommendsusinganeditedPersonalTemplate.

9.3MicrosoftProjectTemplateChangesMicrosoftProject2013and2016templatesoperatedifferentlytoearlierversionsofMicrosoftProjectandtherearesomeimportantchangesthatneedtobeunderstoodbyusersofearlierversionsofMicrosoftProject.

❖ TemplatesthataresavedonyourcomputerarenowtitledPersonalTemplatesinMicrosoftProject2013and2016,

❖ AdefaultlocationforyourpersonaltemplatesneedstobecreatedandyoursoftwaremappedtothislocationbeforethePersonalTemplatesfunctionwilloperate:

Page 82: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ SelectFILE,Options,SaveandsetyourDefaultpersonaltemplateslocation:here,

❖ AtthispointintimePersonalTemplatesmaynowbesavedandusedtocreateprojects.

Note:TousePersonalTemplatesyouMUSTsetyourPersonaldirectoryinFILE,Options,Save.

9.4UnderstandingTemplatesAtemplateisacompleteprojectthatissavedandthencopiedintheprocessofcreatinganewproject.

❖ *.mptfileformatisusedforsavingMicrosoftProjectPersonalTemplates.❖ ThedefaultlocationforPersonalTemplatesissetintheFILE,Options,

Savetab,Savetemplatessection.❖ SelectFILE,Newtoopenthestart-upTaskPane.Thereareseveraloptions

fortemplatelocations:

FEATURED,thisprovidesanumberofsampletemplatesandtheabilitytosearchforavailableonlinetemplates.

PERSONAL,thiswillallowyoutoopentemplatesonyourcomputer.Asmentionedearlier,aTemplatedirectorymustbespecifiedfirstforthisoptiontobecomeavailable.

❖ Organizationaltemplatesmaybeaccessedby:

Allowingpeopletocopytheorganizationaltemplatesfromacorporatelocation,orreceivethembyemail,andsavethemonthelocaldrive.Thisprocessissuitablewhentheusersdonotalwayshaveanetworkconnection.

MappingtheUsertemplatesdirectorytoalocationonacorporatenetworkdrive.

9.5EastwoodHarrisTemplateAMicrosoftProjecttemplatein*.mppformatmaybedownloadedfromtheEastwoodHarriswebsiteatfromthewww.eh.com.au,Software&DownloadspagethathasanumberoftheissueswithMicrosoftProjectdefaultsandothersettingresolved.ThechangestotheGlobal.mptdefaultsettingsarelistedonthewebsite.

Youmaywishtodownloadthisfile,openitandsaveitasaPersonalTemplateandusethisfileinsteadoftheBlankProjectoptionasithassomeformattingissuesresolved.

9.6CopyingViews,TablesandFilters

Page 83: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

AspartofcreatingaTemplateorworkingonaprojectyoumaywishtobringinViews,TablesorFiltersfromanexistingproject.

TheOrganizerfunctionisusedtocopyinformationbetweenprojectsortoupdatetheGlobal.mpt.

❖ SelectFILE,Info,OrganizertoopentheOrganizerform.❖ Theprojectsyouwanttocopysettingstoandfromwillhavetobeopenedin

ordertocopydatafromonescheduletoanother,exceptfortheGlobal.mptproject.

❖ TheOrganizerfunctionisusedforrenaminganddeletingmostitemssuchasTables,ViewsandCalendars.

❖ Thetwotabswithtitlesthatarenotself-explanatoryare:

Maps–Thesearepredefinedtablesforexportingdata,andModules–TheseareVisualBasicMacros.

Page 84: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

10OTHERTHINGSOFINTEREST10.1EditingToolBarsItisrecommendyoucustomizeyourmenusby:

❖ FirstlytoallowmorebuttonstobedisplayedontheQuickAccessToolbar,rightclickontheToolbarandselectShowQuickAccessToolbarBelowtheRibbontomovetheQuickAccessToolbarbelowtheRibbonToolbar.

❖ SecondlyitisrecommendthatyouhidetheRibbonToolbarbyRight-clickingontheRibbonToolbaranddisplaytheRibbonToolbarMenu.ThenclickonCollapsetheRibbontohidetheRibbonToolbar.WhenyouclickintheGanttChartareatheRibbonwillminimizeandmoreworkareawillbeavailableallowingyoutoseemoretasks.

❖ ThirdlyitisrecommendthatyoudownloadtheMicrosoftProjectQuickAccessToolbarfromthewww.eh.com.auwebsiteSoftware&Downloadspage,unzipitbydoubleclickingonthefileanddraggingittoyourDesktop.ThenimportthetoolbarusingFILE,Options,QuickAccessToolbar,Import/Export.ThishasallthecommonlyusedcommandsontheQuickAccessToolbar.

TodofurthereditingtotheToolbaricons:

❖ Right-Clickinthetoolbararea,❖ SelectCustomizetheRibbon…,

❖ SelecttheAllCommandsoption,❖ Dragiconsontotherequiredtoolbar,or

❖ Dragiconsoffthetoolbartoremovethem.

Note:UnfortunatelyMicrosoftProject2016haswidespacingbetweentheQuickAccessToolbarandthusdisplayslessbuttonsthanMicrosoftProject2016makingtheQuickAccessToolbarlessuseful.

10.2DynamicallyLinkingCellsItisalsopossibletodynamicallylinkdatatootherprogramssuchasanExcelspreadsheet:

❖ Copythedatafromthespreadsheet,

❖ SelectthecellpositioninthetablewherethedataistobepastedinMicrosoftProject,

❖ SelectPasteSpecialandthenselectthePasteLinkandTextDataoptions,❖ Thedatawillbepastedintothecell(s)andchangestolinkedcellsinthe

spreadsheetorotherprogramwillbereflectedinMicrosoftProject.

Page 85: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ Thelinkedcellwillhavealittletriangleinthebottomright-handside:

❖ Becarefulwhenlinkingdatefieldsasthismaysetanunwantedconstraint.

❖ Whenyoureopentheprojectscheduleatalaterdateyouwillbeaskedifyouwishtorefreshthedatafromtheotherapplication.

❖ Deleteorchangethecelldatatoremovealink.

❖ Double-clickonthelittletriangleinthebottomrighthandsideofthecelltoopenthelink.

❖ Itisalsopossibletolinkoneormorecellsinaschedulewithanothercellinthesameschedulesoachangeinonecellwillchangealltheotherlinkedcell(s).AgainusethePasteLinkoption.

10.3HowDoesNegativeFloatCalculateforSummaryActivities?ThelowestvalueoftheTotalFloatofincompletetasksisadoptedbythesummarytask,SubTask1inthepicturebelowandhasadopted3days:

Inthepicturebelow,TaskCisthelatesttaskunderSubTask1andhasFloat,butSubTask1hasadoptedzerofloatfromTaskDthelowestfloatvalue.

Nowtheprojecthasprogressedandthetaskwithzerofloatiscomplete.SubTask1has3days’Float:

Page 86: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

10.4FloatandConstraintsThefollowingprinciplesapplytoconstraints:

❖ EarlyconstraintsoperateonEarlydates,❖ LateconstraintsoperateonLatedates,❖ StartconstraintsoperateonStartdates,and❖ FinishconstraintsoperateonFinishdates.

ThepicturebelowdemonstrateshowconstraintsaffectTotalFloat(Slack)calculationsoftasks(withoutpredecessorsorsuccessors)againstthefirsttaskof10daysduration.

Tasks9and10haveaDeadlineDateassignedwhichallowsasecondconstrainttobeappliedtoataskandoperateslikeaFinishNoLaterThanconstraint.

TheLateconstraintsreducetheamountofTotalFloat(Slack)ataskhasandmaygenerateNegativeFloat.

TheMustconstraintsactlikeanEarlyandLateconstraintinone.

10.5UsingCustomFieldsSelectthePROJECT,Properties,CustomFieldstoopentheCustomFieldsform.ThisfunctionincludesanumberofpredefinedfieldsforbothTaskand

Page 87: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Resources.

❖ TaskfieldsmaybeusedforrecordingadditionalinformationaboutTasks(suchasresponsibility,location,floor,system)andmaybedisplayedinTaskViewssuchastheGanttChart.

❖ Resourcefieldsmayrecordinformationsuchastelephonenumber,address,officeandskillsandmaybedisplayedinResourceViewssuchastheResourceSheet.

❖ Thefieldsmayberenamed.Forexample,theTaskText1fieldmayberenamed“Responsibility”andthenameofthepersonresponsibleforthetask(thismaynotbetheresourceassignedtothetask)placedintheResponsibility(Text1)column.

❖ ArenamedfieldisthenavailableintheTaskInformationorResourceInformationCustomFieldstab.

❖ Formulasmaybecreatedtopopulatethetaskfieldswithcalculateddata.

❖ TasksandResourcesmaybeGroupedusingCustomFields.

Thesepredefinedfieldsfallintothefollowingcategories:Cost,Date,Duration,Finish(date),Flag,Number,OutlineCode,Start(date)andText.

10.6CustomColumnsFormulasandDrop-DownListTheCustomAttributessectionoftheCustomFieldsformisusedtodefineLookuplistsandFormulas:

❖ TheoptionNoneallowsdatatobeentered,withoutanyrestrictions,fromeitheracolumnortheTaskorResourceInformationforms.

❖ openstheEditLookupTablewhereatableofvaluesanddescriptionsmaybeentered.TheValueisdisplayedincolumnsandDescriptioninbandswhenthetasksaregroupedbythisfield.Dataentryrestrictionsmaybesethere.

❖ allowstheassigningofformulasforthecalculationoffieldvaluesfromothertaskandprojectfields.

TheCalculationfortaskandgroupsummaryrowsspecifieshowSummaryTaskscalculatetheirvalues,suchasMaximum,Minimum,Sum,NoneandAverage:

❖ DatescouldbeMinimumorMaximum,and

❖ CostwoulduseSum.

CalculationforassignmentrowsdeterminesifthefieldvalueisdisplayedagainsttheresourceortheresourceandassignmentinTaskUsageandResourceUsagefields.

Page 88: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Valuetodisplayallowstheoptionsofdisplayingthevalueinthecellorgeneratinggraphicalindicatorssuchastrafficlights.

10.7CustomOutlineCodesTherearetenhierarchicalTaskCustomOutlineCodesandtenhierarchicalResourceCustomOutlineCodesthatmayberenamedtosuittheprojectrequirements.

❖ TaskCustomOutlineCodesmaybeusedforanyhierarchicalprojectbreakdownstructure,suchasaPRINCE2ProductBreakdownStructure,ContractBreakdownStructure,WorkBreakdownStructureand

❖ ResourceCustomOutlineCodesmaybeusedfororganizationalbreakdownstructuressuchasthehierarchyofauthority,locationsanddepartments.

Theprocesstousethisfunctionhasthefollowingsteps:

❖ DefinethenewOutlineCodestructure,

❖ Assignthecodestothetasksorresources,and

❖ CreateaGrouptoorganizethetasksunderthenewCustomOutlineCodestructure.

10.7.1DefineaCustomOutlineCodeStructure

SelectthePROJECT,Properties,CustomFields:

❖ AnOutlineCodemaybecreatedforeitherTaskorResourcedatabyclickingontheappropriateradiobuttonunderthetitleField.

❖ SelecttheOutlineCodethedrop-downboxintoprighthandside.

❖ The functionallowsyoutocopyacodestructurefromanotherprojectinamethodsimilartoOrganizer.

❖ The buttonopensaformtoeditthenameoftheOutlineCode.

❖ The buttoninMicrosoftProject2013and2016openstheEditLookUpTableformfortheselectedOutlineCodetocreatetheLookuptable.

❖ DefinetheMaskorcodestructurebyclickingonthe buttonatthetopright-handsidein2007-2016,beforeenteringthecodes.ThiswillopentheOutlineCodeDefinitionformwherethecodestructureisdefined:

EachLevelisassignedanumber.TheSequencedefinesthetypeoftextthatmaybeenteredforthecode:Numbers,UpperCase,LowerCaseorCharacters(text).

TheLengthspecifieshowmanycharacterstheCodeLevelmayhave:any,oranumberbetween1and10.

Page 89: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

TheSeparatordefinesthecharacterthatseparateseachlevelinthestructure.

❖ Thepicturedisplays4levelseachusingadifferentoptionfortheircode:

❖ Clickthe buttontoreturntotheEditLookupTableformwheretheCodeValuesandDescriptionsareentered.ThepictureshowstwolevelsforaPowerStationUnitandEquipment:

Page 90: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

10.7.2AssigningtheCustomCodes

Thecodesareassignedby:

❖ Displayingtheappropriatecolumn:

Page 91: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ OrbyopeningtheTaskInformationorResourceInformationform:

10.7.3GroupingwithCustomData

GroupingallowsgroupingoftasksunderdataitemssuchasCustomizedfields,Durations,Constraints,etc.Thisfunctionisusefultogrouprelatedtasksthatarespreadthroughoutaprojectschedule.

TheGroupingfunctionworksinasimilarwaytoFiltersandTables.ApredefinedGroupmaybeassignedby:

❖ SelectingVIEW,Data,Groupby:dropdowntoopenupasubmenu,❖ Theneither:

Selectingagroupfromthelist,or

SelectingMoreGroups…toopentheMoreGroupsform,clickingontheTaskorResourceradiobutton,andthenselectingonefromthelist,or

Page 92: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Note:FieldsaresortedalphabeticallywhendisplayedonthescreensoyoumayneedtobecarefulwithyourCodeValuesandconsiderprefixingthemwithanumbersotheysortintheorderyoudesire.

TocreateanewGroup:

❖ SelectVIEW,Data,Groupby:dropdown,NewGroupBy…toopentheGroupDefinitionform,

❖ Nowcreatea“Grouping”whichmaybereappliedatalaterdateorcopytoanotherprojectusingOrganizer.

❖ TheDefineGroupIntervalformisavailablewithadditionalGroupByoptionsforcertainfields,suchasStartorFinish.Thisallowsfurtherformattingby

Page 93: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

definingtheintervalsofthebanding.Forexampleallthetasksthatstartinaweekormonthmaybebandedtogether:

ThepicturebelowshowsaprojectGroupedbytwotextfieldsthathavebeenrenamedSystemsandBuilding.NotetheorderoftheTaskIDs:

10.7.4GroupingwithCustomDatawithAutoFilters

GroupingwithonebandmayalsobeachievedbyturningontheAutoFilterfunctionbyeither:

❖ SelectingVIEW,Data,Filter:andselectingDisplayAutoFilteratthebottomofthelist,oraddtheAutoFilterbutton totheQuickAssesstoolbarandclickingonit.

❖ Therewillnowbeadownarrow inthecolumnheader,

❖ Clickonthecolumnheadertoopenthemenu,

❖ ClickonGroupby,

Page 94: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ Dependingonthedatacontainedinthecolumnyouwillbeofferedlogicaldataoptionstogroupyourtasks,

❖ ThepicturebelowdisplaystheoptionswhenGroupingbyDuration:

10.8ExportingtoExcelTheAnalysistoolbarisdesignedtoexporttime-phaseddatatoExcelinearlierversionsofMicrosoftProjectisnolongeravailableinVersion2010andlater.

TheoptionstoexporttoExcelare:

❖ SelectthedatainMicrosoftProjectandCutandPasteandyouhavetheoptionofkeepingornotkeepingtheformattingwhenPasting.

❖ TimescaledatamaybecopiedandpastedfromtheResourceUsageandTaskUsageviewsbutthedateinformationmustbemanuallyaddedtotheExcelSpreadsheet,

❖ TheREPORT,Export,VisualReportsexporttoExcelinPivotTableformat,soyouwillneedtohoneuponyourPivotTableskillstousethisfunction.

❖ TheFILE,SaveAs,ExcelformatallowsthemappingofspecificfieldstoandfromanExcelSpreadsheet.MapsmadebesetupandusedtomapdatatoandfromMicrosoftProjectandExcel.

10.9TurningOffGettingStartedandotherPOPupsTheseguidesoftenslowdownexperiencedusersastheyhavetobecontinuallyclosed:

❖ TopreventthepanetitledGettingStartedfromappearingeverytimeMicrosoftProjectisopened,selectFILE,Options,GeneralandunchecktheShowthestartscreenwhenthisapplicationstartsbox.

TheHelpsuggestionsofferedbyMicrosoftprojectisoftenmisleading,theseshouldbeswitchedoffbyselectingFILE,Options,Scheduleandunchecking:

❖ ShowschedulingMessages,❖ Showtaskschedulewarningsand❖ Showtaskschedulesuggestions.

Page 95: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ TheselecttheAdvancedtabanduncheckAdvicefromPlanningWizard.

10.10ContingentTimeThistopicshouldbeconsideredandContingentTimemaybeincludedusinganumberoftechniques:

❖ Addingoneormoretasksthatmaybereducedindurationtokeeptheprojectenddateconstantastheprojectprogressesandincursdelays.

❖ Increasingalltaskdurationsbyafactor.

❖ Makingsomecalendarworkdaysnonwork.

10.11EarnedValueThemethodthatMicrosoftProjectusestocalculatetheEarnedValuedataisdocumentedintheHelpfileandshouldbereadcarefully,asdifferentversionsofMicrosoftcalculatethesefieldsdifferently.ShoulddifferentEarnedValuecalculationsberequiredthenCustomDataFieldsshouldbeconsideredasanalternative.

ThecolumncalculationsshouldbecheckedandyouwillseethewayMicrosoftProjectcalculatesthevaluesandyoumaydisagreewiththeirmethod.

YoumaywishtouseCustomFieldsorthirdpartysoftwaretocalculatetheseEVfields.

10.12DoIHaveAlltheScope?ManyschedulesareunrealisticordonotcalculatearealisticCriticalPathbecausethewholescopehasnotbeenenteredintoaschedule.Thereareacoupleoftechniquesthatmaybeemployedtoensurethewholescopehasbeenincluded:

❖ StakeholderAnalysis,and

Page 96: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

❖ RiskAnalysis.

10.12.1StakeholderAnalysis

ManyprojectmanagersconductaStakeholderAnalysisatthestartofaproject.Thisprocessidentifiesallthepeopleandorganizationswithaninterestintheprojectandtheirinterests.

❖ Youmayuseastakeholderanalysistoidentifyallthestakeholdersandtheirassociatedactivities.Theactivitiesmustbeincludedintheschedule.

❖ Keyprojectsuccessfactorsmaybeidentifiedfromtheinterestsofthemostinfluentialstakeholders.

❖ Thestakeholderanalysismaybeusedasthebasisofacommunicationsplan.

10.12.2RiskAnalysis

Theprocessofplanningaprojectmayidentifyrisksandaformalriskanalysisshouldbeconsidered.Ariskanalysismayidentifyriskmitigationactivitiesthatshouldbeaddedtotheschedulebeforeitissubmittedforapproval.

10.13PreparingforDisputeResolutionDisputeresolutionisbecomingmorefrequent.Therearesomestepsthatmaybetakentoprepareforthiseventualitywhichshouldreducethecostofthisprocess.

10.13.1KeepingElectronicCopiesofEachUpdate

Eachtimeyoureporttotheclientormanagement,itisrecommendedthatyousaveacopyofyourprojectandchangethefilename(perhapsbyappendingadatetothefilenameorusingarevisionorversionnumber)orcreateasubdirectoryforeachversionoftheproject.Thisallowsyoutoreproducethesereportsatanytimeinthefutureandanelectroniccopywillbeavailablefordisputeresolutionpurposes.

10.13.2ClearlyRecordtheEffectofEachChange

Eachchangeshouldbeclearlyrecorded.Considerifyoushould:

❖ Createacopyofthescheduleforeachscopechangeanalysis,

❖ SettheBaselinebeforeenteringscopechanges,

❖ Forclarityaddnewtask/sforthescopechangesanddonotextendexistingtasks,

❖ Showdelaysastasks,notaslagsorconstraints,

❖ EnsurewhentheelapseddurationofthedelayisrequiredcalculatethisbyplacingadelayMilestoneona7dayperweekcalendar.

Page 97: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

11INDEX%Lags44

ActualcostsarealwayscalculatedbyMicrosoftProject?96,97

AddProgressLine86

Addspacebeforelabel59,67

AddtoQuickAccessToolbar12

AlwaysrollupGanttbars53

Analysistoolbar65

AsLateAsPossibleConstraint32

AutoScheduled10

AutoFilters35

Autolinkinsertedormovedtasks5,9

Bars

Baseline89,90

FormatStyle30

Height53

NegativeFloat31

Styles70

Text55

Baseline79

Calculatemultiplecriticalpaths57

CalculatedFilters33

CalendarNonWorkDays5

CalendarTask17

ChangeWorkingTime14,19

Changeworkingtimeform21

CollapsetheRibbon11

ColorsFormat55

Concatenate24

ContingentTime116

CurrentDate82

CustomOutlineCodes108

CustomizeFieldsForm106

CustomizeQuickAccessToolbar12

CustomizetheRibbon102

Date

Format49,52

OnBars52

DeadlineDate29

Defaultendtime:21

Defaultstarttime:21

Page 98: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Defaulttasktype:74

DefineGroupIntervalform113

DeleteKey1

DisputeResolution119

DrivingRelationships45

Durationisenteredin:16

DynamicallyLinkingCells103

EarnedValue82,117

Effortdriven75

ElapsedDurations41

ElapsedLeadsandLags42

Excel115

Exporting115

FeaturedTemplates100

FilterCalculated33

FinishNoEarlierThanconstraint1

Fixed

DurationTaskType73

UnitsTaskType73

WorkTaskType73

Float18

FloatBars31

Form

CustomizeFields106

DefineGroupInterval113

FormatBar30

MoreGroups112

ProjectStatistics86

Timescale64

Format

BarStyle30

BaselineBar89,90,92

Date49

NonworkingTime64

FreeFloat30

GanttChartWizard32,89,90

Global.mpt98,101

GridlinesColors55

Hiderollupbarswhensummaryexpanded53

Hidetaskbar61

HidingText61

Hoursperday:15,16

Page 99: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

HyperlinkColors55

Import/Export12

IndentName58,59

Indicatorscolumn2,17

InteractiveFilters35

InterimPlan79

Ladderscheduling43

Lags18

LegacyFormat5

Legend70

Macros101

ManualPageBreaks70

ManuallyScheduled10

Maps101,115

Markasamilestone38

Milestones37

Modules101

Movestartofremainingpartsbeforestatusdateforwardtostatusdate88

mptFileType99

MultipleCriticalPaths57

NegativeFloat30

Newtaskscreated:10

NonEffortdriven75

Non-drivingRelationships45

NonworkingTime64

NonworkingTimeColors55

OrganizerOverview101

PageBreaks70

PasteLink103

PersonalTemplate99,100

PredecessorUniqueID60

ProgressLines86,89

ProjectInformationform13

ProjectStartDate8

Project,ProjectInformationform20

QuickAccessToolbar11

RelationshipDiagram47

RelationshipsDriving45

RemainingDuration81

Reports115

Rescheduleuncompletedtaskstostartafter:96

RescheduleWork85,93

Page 100: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

ResourceAssignmentUniqueID60

RetainedLogic26

RiskAnalysis118

RollupGanttbartosummary54

RoundBarstoWholeDays54

ScheduleOptions9

Schedulingignoresresourcecalendars14,17,19,20

S-Curve65

Showprojectsummarytask66

ShowQuickAccessToolbarBelowtheRibbon11

ShowschedulingMessages116

Showtaskschedulesuggestions116

Showtaskschedulewarnings116

Split

RemovingaBarSplit27

ShowBarSplits28

Task26

Splitin-progresstasks3,9,26,84,85,87

StakeholderAnalysis118

StartNoEarlierThanconstraint1

StartonCurrentDate8

StartonProjectStartDate8

StatusDate8,82

TaskCalendar17

TaskDrivers45

TaskInformation17

TaskInspector46

TaskPath46

TaskSplitting25

TaskType

FixedDuration73

FixedUnits73

FixedWork73

Taskswillalwayshonortheirconstraintdates3,4,9,88

Templates99

TextColors55

TextWrapping56

Timescale64

TimescaleFormatColors55

TrackingToolbar85

UniqueID60

Predecessor60

Page 101: 99 Tricks and Traps for Microsoft Office Project 2013 and 2016projanco.com/Library/99 Tricks and Traps for... · 99 Tricks and Traps for Microsoft Project 2013 and 2016 Oracle Primavera

Successor60

UniqueResourceAssignmentID60

UniqueResourceID60

Units59

UnitsperTimePeriod73,74

UpdateasScheduled85,91,93

UpdateProjectform83,90

UpdateTasks86

Updatingtaskstatusupdatesresourcestatus87,95

VisualBasicMacros101

VisualReports115

Wildcard34

WrapText56

ZoomSlider63