Upload
arun-dutt
View
215
Download
0
Embed Size (px)
Citation preview
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 1/293
1
1. INTRODUCTION
The population explosion and advent of industrial revolution led to the exodus of
people from villages to urban areas. This urbanisation led to a new problem – less space for
housing, work and more people. Because of the demand of the land, the land costs got
skyrocketed. So, under the changed circumstances, the vertical growth of buildings i.e.
constructions of multi-storeyed buildings has become inevitable both for residential and as
well as office purposes.
For multi-storeyed buildings, the conventional load bearing structures become
uneconomical as they require larger sections to resist huge moments and loads. But in a
framed structure, the building frame consists of a network of beams and columns which are
built monolithically and rigidly with each other at their joints. Because of this rigidity at the
joints, there will be reduction in moments and also the structure tends to distribute the loads
more uniformly and eliminate the excessive effects of localised loads. Therefore in non-load
bearing framed structures, the moments and forces become less which in turn reduces the
sections of the members. As the walls don‟t take any load, they are also of thinner
dimensions. So, the lighter structural components and walls reduce the self weight of the
whole structure which necessitates a cheaper foundation. Also, the lighter walls which can
easily be shifted about provide flexibility in space utilisation. In addition to the above
mentioned advantages the framed structure is more effective in resisting wind loads and earth
quake loads.
Work done in this project:
A plot of 369.75 m2 has been selected for the construction of a multi-storeyed office
building. In the office building the functions will be different and it plays a major role
because of different loads acts on different slabs. The frame analysis requires the dimensions
of the members. For the analysis, 6 substitute frames taken in transverse direction and in
longitudinal direction the net moment acting is zero because of the same span and assumed as
a simply supported. For the maximum mid span moment obtained from the analysis, a T-
beam has been designed and for the support moment „doubly reinforced‟ section has been
provided. Stair case has also been designed. Isolated rectangular sloped footings have been
designed to transfer the load to the ground strata.
Analysis of structure:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 2/293
2
Kani‟s method and substitute frame method is generally used to analyse a multi -
storeyed frame. The substitute frame method requires less computations and easier to carry
out the analysis. Therefore, here substitute frame method has been employed to carry out the
frame analysis and method is discussed in the following paragraphs.
Theoretically, a load applied at any point of the structure cause reactions at all
sections of the frame, but a close study of this aspect has shown that the moments in any
beam or column are mainly due to the loads on spans very close to it. The effect of loads on
distant panels is small. To facilitate the determination of moments in any member of a frame,
it is usual to analyse only a small portion of the frame consisting of adjacent members only.
Such a small portions are termed „SUBSTITUTE FRAMES‟. Their form and the end
conditions of their members are so adopted that the reaction in question works out to be the
greatest.
The reactions worked out with the help of substitute frame may sometimes appear to
be lower by about 10% compared with the value obtained from exact analysis. But it may be
mentioned that for analysis all the panels are located at the same time. Such a combination of
loading is highly improbable in practice. Thus the substitute frames give results are safe for
all practical purposes.
Design concept:
There are three design philosophies to design a reinforced concrete structures. They
are:
1. Working stress method,
2. Ultimate load method and
3. Limit state method.
In the „working stress‟ method it is seen that the permissible stresses for concrete and
steel are not exceeded anywhere in the structure when it is subjected to the worst
combination of working loads. A linear variation stress form zero at the neutral axis to the
maximum stress at the extreme fibre is assumed.
Practically, the stress strain curve for concrete is not linear as it was assumed in
working stress method. So, in „ultimate load‟ design an idealised form of actual stress
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 3/293
3
strain diagram is used and the working loads are increased by multiplying them with the
load factors.
The basis for „limit state‟ method is a structure with appropriate degrees of reliability
should be able to withstand safely all loads that are liable to act on it throughout its life
and it should also satisfy the serviceability requirements such as limitations on deflection
and cracking.
Limit state method is the most rational method of the three methods. It considers the
actual behaviour of the materials at failure and also it takes serviceability also into
consideration. Therefore, limit state method has been employed in this work.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 4/293
4
2. DESIGN OF SLABS
Typically we divided the slabs into two types:
i.
Roof Slab andii. Floor Slab
In case of roof slab the live load obtained is less compared to the floor slab. Therefore we
first design the roof slab and then floor slabs.
We have two types of supports. They are:
1. Ultimate support and
2. Penultimate support
Ultimate support is the end support and the penultimate supports are the intermediate
supports.
Ultimate support tends to have a bending moment of Wu x L
2
10 and the penultimate supports
haveWu x L
2
12
Design of roof slab:
It is a continuous slab on the top of the building which is also known as terrace.
Generally terrace has less live load and it is empty in most of the time except some occasions
in case of any residential building. In case of office buildings it will be empty and live load
act is very less.
According to the end conditions and the dimensions, the slabs are divided into 4 types. They
are Roof S1, Roof S2, Roof S3 and Roof S4.
Slab Dimensions (M x M)
Roof S1 8.62 X 3.05
Roof S2 8.62 X 3.05
Roof S3 5.78 X 3.05
Roof S4 5.78 X 3.05
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 5/293
5
We can observe the slab panels in the above figure and all the slabs are designed as one way
slab for the easy arrangement of the reinforcement and ease of work.
Roof S1 and Roof S2 are the slabs with same dimensions but different in end conditions.
Roof S3 and Roof S4 are also the slabs with the same conditions as mentioned above.
But the point to be noted is that all the Slabs have same shorter span and in design of one way
slab shorter span is of more importance. Therefore we design any two slabs with different end
conditions and the remaining two slabs also follow same design.
Design of Roof Slab S1:
Calculation of Depth (D) by using modification factor:
Assume the percentage of the tension reinforcement (P t) provided is 0.4%
From IS456-2000, P38 Fig4, we get the modification factor (α) = 1.4
Required Depth (D) =
L
ra + d
1
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 6/293
6
Where,L
r a=
Span
allowableL
dratio
d1 = Centre of the reinforcement to the end fibre (= 20mm for slab)
From IS456-2000, P39, Clause 24 & Clause 23.2 for continuous span we have
Span
Effective depth=
L
d= 26
r a = 26 x 1.4 = 36.4
Therefore, D =3.05 x 103
36.4
+ 20 = 103.79mm say 110 mm
Effective depth (d) = D – d1 = 110 – 20 = 90mm
Loads:
Dead loads (From IS875 – Part 1):
Terrace water proofing = 2.5 KN/m2
Self weight of the slab = 1 x 1 x D x 25 = 1101000
x 25
= 2.75 KN/m2
Live loads (From IS875 – Part 2):
Roof = 1.5 KN/m2
Total load (W) = 2.5 +2.75 + 1.5 = 6.75 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 6.75
=10.125 KN/m2
Design moment: (for end panel)
Mu =Wu x L2
10=
10.125 x (3.05)2
10= 9.42 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 7/293
7
Calculation of area of steel:
From IS456-2000, P96, Clause G-1.1 (b) we have
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d )
Or
Ast = 0.5 xf ck
f y(1-(1-4.6
Mu
f ck x b x d)1/2
) b x d
9.42 x 106 = 0.87 x 415 x Ast x 90 x (1 -415 x Ast
20 x 1000 x 90)
Ast = 312.4 mm2
Spacing of 8mm φ bars =ast x 1000
Ast=
π4
x 82 x1000
312.4= 160.9mm
Therefore, Provide 8mm φ @ 150mm c/c.
Distribution steel:
Ast = 0.12% of Ag
=0.12
1000x 110 x 1000 = 132 mm2.
Spacing of 8mm φ bars =π4
x 82 x1000
132=380mm
Therefore, Provide 8mm φ @ 300mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 8/293
8
Design of Roof slab S2:
Depth D = 110mm
Total load (W) = 6.75 KN/m2
Limit state load (Wu) = 1.5 x 6.75 = 10.125 KN/m2
Design moment: (for intermediate panel)
Mu =Wu x L2
12=
10.125 x (3.05)2
12= 7.85 KN-m
Calculation of area of steel:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
7.85 x 106 = 0.87 x 415 x Ast x 90 x (1 -415 x Ast
20 x 1000 x 90)
Ast = 256.78 mm2
Spacing of 8mm φ bars =π
4x 82 x
1000
256.78= 195.75mm
Therefore, Provide 8mm φ @ 190mm c/c.
Distribution steel:
Ast = 0.12% of Ag
=0.12
1000x 110 x 1000 = 132 mm2.
Spacing of 8mm φ bars =π4
x 82 x1000
132=380mm
Therefore, Provide 8mm φ @ 300mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 9/293
9
Design of Roof Slab S3 is same as Roof Slab S1.
Design of Roof Slab S4 is same as Roof Slab S2.
Area of steel at support next to end support:
From IS 456-2000, moment = Wu x L2
10
Total Load acting on the support (Wu) = 10.125 KN/m
Therefore, Moment =10.125 x (3.05)2
10= 9.42 KN-m
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
9.42 x 106 = 0.87 x 415 x Ast x 90 x (1 -415 x Ast
20 x 1000 x 90)
Ast = 312.4 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S1 =1
2x 312.4 = 160.7 mm2
From Slab S2 =1
2x 256.78 = 128.39 mm2
Total Ast (available) = 160.7 + 128.39 = 284.59 mm2
Therefore, extra bars required for Ast = 312.4 – 284.59 = 27.81 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 10/293
10
Area of steel at any other interior support:
From IS 456-2000, moment =Wu x L2
12
Total Load acting on the support (Wu) = 10.125 KN/m
Therefore, Moment =10.125 x (3.05)2
12= 7.85 KN-m
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
7.85 x 106 = 0.87 x 415 x Ast x 90 x (1 -415 x Ast
20 x 1000 x 90)
Ast = 256.78 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S2 =1
2x 256.78 = 128.39 mm2
From Slab S2 =1
2x 256.78 = 128.39 mm2
Total Ast (available) = 128.39 + 128.39 = 284.59 mm2
Therefore Ast (available) = Ast (required)
No need of providing extra bars.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 11/293
11
Design of Floor Slab:
It is the slab in which live load is more when compared to the roof slab. In this projectthe slab is divided into 9 types according to the end condition and function of slab.
S1 - Toilet and WC‟s
S2 - Office
S3 - Office sup dept.
S4 - Assembly hall
S5 (a), S5 (b) - Office chamber and waiting chamber
S6 (a), S6 (b) - Office
S7 - Library
S8 - Secretary Room
S9 (a), S9 (b) - Officers chamber
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 12/293
12
Floor Slab Dimensions
S1 to S5 (b) 8.62 x 3.05
S6 (a) to S9 (b) 5.78 x 3.05
DESIGN OF FLOOR SLAB (S1):
Calculation of Depth (D) by using modification factor:
Assume the percentage of the tension reinforcement (P t) provided is 0.4%
From IS456-2000, P38 Fig4, we get the modification factor (α) = 1.4
Required Depth (D) = Lra
+ d1
Where,L
r a=
Span
allowableL
dratio
d1 = Centre of the reinforcement to the end fibre (= 20mm for slab)
From IS456-2000, P39, Clause 24 & Clause 23.2 for continuous span we have
Span
Effective depth=
L
d= 26
r a = 26 x 1.4 = 36.4
Therefore, D =3.05 x 103
36.4+ 20 = 103.79mm say 120 mm
Effective depth (d) = D – d1 = 120 – 20 = 100mm
Loads:
Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2
Sanitary Blocks including filling = 2.5 KN/m2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 13/293
13
Self weight of the slab = 1 x 1 x D x 25 =120
1000x 25
= 3 KN/m2
Live loads (From IS875 – Part 2):
Sanitary blocks public = 3 KN/m2
Corridor = 5 KN/m2
Maximum = 5 KN/m2
For Partition Wall = 1.5 KN/m2
Total load (W) = 1 + 2.5 +3 + 5 + 1.5 = 13 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 13
=19.5 KN/m2
Design moment: (for end panel)
Mu =
Wu x L2
10 =
19.5 x (3.05)2
10 = 18.14 KN-m
Calculation of area of steel:
From IS456-2000, P96, Clause G-1.1 (b) we have
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
Or
Ast = 0.5 xf ck
f y(1-(1-4.6
Mu
f ck x b x d)1/2
) b x d
18.14 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 569.79 mm2
Spacing of 10mm φ bars =a
stx 1000
Ast=
π4 x 102 x
1000
569.79 = 137.83mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 14/293
14
Therefore, Provide 10mm φ @ 130mm c/c.
Distribution steel:
Ast = 0.12% of Ag
=0.12
1000x 120 x 1000 = 144 mm2.
Spacing of 8mm φ bars =π4
x 82 x1000
144=349mm
Therefore, Provide 8mm φ @ 300mm c/c.
DESIGN OF FLOOR SLAB (S2):
D =3.05 x 103
36.4 + 20 = 103.79mm say 120 mm
Effective depth (d) = D – d1 = 120 – 20 = 100mm
Loads:
Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2
Self weight of the slab = 1 x 1 x D x 25 =120
1000x 25
= 3 KN/m2
Live loads (From IS875 – Part 2):
Office = 4 KN/m2
Corridor = 5KN/m2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 15/293
15
Therefore, Maximum load = 5 KN/m2
For Partition wall = 1.5 KN/m2
Total load (W) = 5 +3 + 1 + 1.5 = 10.5 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 10.5
=15.75 KN/m2
Design moment:
Mu =Wu x L2
12=
15.75 x (3.05)2
12= 12.21 KN-m
Calculation of area of steel:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
12.21 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 365.97 mm2
Spacing of 10mm φ bars = π4
x 102 x1000
365.97= 214.61mm
Therefore, Provide 10mm φ @ 210mm c/c.
Distribution steel:
Ast = 0.12% of Ag
= 0.121000 x 120 x 1000 = 144 mm2.
Spacing of 8mm φ bars =π4
x 82 x1000
144=349mm
Therefore, Provide 8mm φ @ 300mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 16/293
16
Area of steel at support next to end support (between S1 and S2):
From IS 456-2000, moment =Wu x L2
10
Total Load acting on the support (Wu) =
13
2 +
15.75
2 = 14.375 KN/m
Therefore, Moment =14.375 x (3.05)2
10= 13.372 KN-m
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
13.372 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 404.28 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S1 =1
2x 569.79 = 284.895 mm2
From Slab S2 =1
2x 365.97 = 182.985 mm2
Total Ast (available) = 284.895 + 182.985 = 467.88 mm2
Therefore, extra bars required for Ast = 312.4 – 284.59 = 27.81 mm2
DESIGN OF FLOOR SLAB (S3):
D = 3.05 x 103
36.4+ 20 = 103.79mm say 120 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 17/293
17
Effective depth (d) = D – d1 = 120 – 20 = 100mm
Loads:
Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2
Self weight of the slab = 1 x 1 x D x 25 =120
1000x 25
= 3 KN/m2
Live loads (From IS875 – Part 2):
Private = 2 KN/m2
Corridor = 5 KN/m2
Maximum load = 5 KN/m2
For Partition wall = 1.5 KN/m2
Total load (W) = 5 +3 + 1 + 1.5 = 10.5 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 10.5
=15.75 KN/m2
Design moment:
Mu =Wu x L2
12=
15.75 x (3.05)2
12= 12.21 KN-m
Calculation of area of steel:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
12.21 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 365.97 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 18/293
18
Spacing of 10mm φ bars =π4
x 102 x1000
365.97= 214.61mm
Therefore, Provide 10mm φ @ 210mm c/c.
Distribution steel:
Ast = 0.12% of Ag
=0.12
1000x 120 x 1000 = 144 mm2.
Spacing of 8mm φ bars =π4
x 82 x1000
144=349mm
Therefore, Provide 8mm φ @ 300mm c/c.
Area of steel at any other interior support: (Between S2 and S3)
From IS 456-2000, moment =Wu x L2
12
Total Load acting on the support (Wu) =15.75
2+
15.75
2= 15.75 KN/m
Therefore, Moment = 15.75 x (3.05)
2
12= 12.21 KN-m
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
12.21 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 365.97 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 19/293
19
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S2 =1
2x 365.97 = 182.985 mm2
From Slab S3 =1
2x 365.97 = 182.985 mm2
Total Ast (available) = 182.985 + 182.985 = 365.97 mm2
Therefore Ast (available) = Ast (required)
No need of providing extra bars.
DESIGN OF FLOOR SLAB (S4):
D =3.05 x 103
36.4+ 20 = 103.79mm say 120 mm
Effective depth (d) = D – d1 = 120 – 20 = 100mm
Loads:
Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2
Self weight of the slab = 1 x 1 x D x 25 =120
1000x 25
= 3 KN/m2
Live loads (From IS875 – Part 2):
Assembly = 5 KN/m2
Corridor = 5 KN/m2
Maximum load = 5 KN/m2
For Partition wall = 1.5 KN/m2
Total load (W) = 5 +3 + 1 + 1.5 = 10.5 KN/m2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 20/293
20
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 10.5
=15.75 KN/m2
Design moment:
Mu =Wu x L2
12=
15.75 x (3.05)2
12= 12.21 KN-m
Calculation of area of steel:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
12.21 x 106 = 0.87 x 415 x Ast x 100 x (1 - 415 x Ast20 x 1000 x 100 )
Ast = 365.97 mm2
Spacing of 10mm φ bars =π4
x 102 x1000
365.97= 214.61mm
Therefore, Provide 10mm φ @ 210mm c/c.
Distribution steel:
Ast = 0.12% of Ag
=0.12
1000x 120 x 1000 = 144 mm2.
Spacing of 8mm φ bars =π4
x 82 x1000
144=349mm
Therefore, Provide 8mm φ @ 300mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 21/293
21
Area of steel at any other interior support: (Between S3 and S4)
Same as between S2 and S3
DESIGN OF FLOOR SLAB (S5 (a)):
D =3.05 x 103
36.4+ 20 = 103.79mm say 120 mm
Effective depth (d) = D – d1 = 120 – 20 = 100mm
Loads:
Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2
Self weight of the slab = 1 x 1 x D x 25 =120
1000x 25
= 3 KN/m2
Live loads (From IS875 – Part 2):
Office chamber = 4 KN/m2
Private = 2 KN/m2
For Partition wall = 1.5 KN/m2
Total load (W) = 2 + 4 +3 + 1 + 1.5 = 11.5 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 11.5
=17.25 KN/m2
Design moment:
Mu =Wu x L2
12=
17.25 x (3.05)2
12= 13.372 KN-m
Calculation of area of steel:
Mu = 0.87 x f y x Ast x d x (1 - f y x Astf ck x b x d )
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 22/293
22
13.372 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 404.27 mm2
Spacing of 10mm φ bars =π4
x 102 x1000
347.05= 194.27mm
Therefore, Provide 10mm φ @ 190mm c/c.
Distribution steel:
Ast = 0.12% of Ag
= 0.121000 x 120 x 1000 = 144 mm2.
Spacing of 8mm φ bars =π4
x 82 x1000
144=349mm
Therefore, Provide 8mm φ @ 300mm c/c.
Area of steel at any other interior support: (Between S4 and S5 (a))
From IS 456-2000, moment =Wu x L2
12
Total Load acting on the support (Wu) =15.75
2+
17.25
2= 16.5 KN/m
Therefore, Moment =16.5 x (3.05)2
12= 12.79 KN-m
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -
f y x Ast
f ck x b x d )
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 23/293
23
12.79 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 385 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S4 =1
2x 365.97 = 182.985 mm2
From Slab S5 (a) =1
2x 404.27 = 202.135 mm2
Total Ast (available) = 182.985 + 202.135 = 385.12 mm2
Therefore Ast (available) = Ast (required)
No need of providing extra bars.
DESIGN OF FLOOR SLAB (S5 (b)):
D =3.05 x 103
36.4+ 20 = 103.79mm say 120 mm
Effective depth (d) = D – d1
= 120 – 20 = 100mm
Loads:
Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2
Self weight of the slab = 1 x 1 x D x 25 =120
1000x 25
= 3 KN/m2
Live loads (From IS875 – Part 2):
Office chamber = 4 KN/m2
Private = 2 KN/m2
For Partition wall = 1.5 KN/m2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 24/293
24
Total load (W) = 2 + 4 +3 + 1 + 1.5 = 11.5 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 11.5
=17.25 KN/m2
Design moment: (for end panel)
Mu =Wu x L2
10=
17.25 x (3.05)2
10= 16.047 KN-m
Calculation of area of steel:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d
)
16.047 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 495.37 mm2
Spacing of 10mm φ bars =π4
x 102 x1000
495.37= 158.55mm
Therefore, Provide 10mm φ @ 150mm c/c.
Distribution steel:
Ast = 0.12% of Ag
=0.12
1000x 120 x 1000 = 144 mm2.
Spacing of 8mm φ bars =
π4 x 8
2
x
1000
144 =349mm
Therefore, Provide 8mm φ @ 300mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 25/293
25
Area of steel at support next to end support (between S5 (a) and S5 (b)):
From IS 456-2000, moment =Wu x L2
10
Total Load acting on the support (Wu) =17.25
2+
17.25
2= 17.25 KN/m
Therefore, Moment =17.25 x (3.05)2
10= 16.05 KN-m
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d
)
16.05 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 495.47 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S5 (a) =1
2x 404.27 = 202.135 mm2
From Slab S5 (b) =1
2x 495.47 = 247.735 mm2
Total Ast (available) = 202.135 + 247.735 = 449.87 mm2
Therefore, extra bars required for Ast = 495.47 – 449.87 = 45.6 mm2
DESIGN OF FLOOR SLAB (S6 (a)):
D =3.05 x 103
36.4+ 20 = 103.79mm say 120 mm
Effective depth (d) = D – d1 = 120 – 20 = 100mm
Loads:
Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 26/293
26
Self weight of the slab = 1 x 1 x D x 25 =120
1000x 25
= 3 KN/m2
Live loads (From IS875 – Part 2):
Office = 4 KN/m2
Total load (W) = 4 +3 + 1 = 8 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 8
=12 KN/m2
Design moment: (for end panel)
Mu =Wu x L2
10=
12 x (3.05)2
10= 11.163 KN-m
Calculation of area of steel:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
11.163 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 332.06 mm2
Spacing of 10mm φ bars =π4
x 102 x1000
332.06= 236.53mm
Therefore, Provide 10mm φ @ 230mm c/c.
Distribution steel:
Ast = 0.12% of Ag
=0.12
1000x 120 x 1000 = 144 mm2.
Spacing of 8mm φ bars =π4
x 82 x1000
144=349mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 27/293
27
Therefore, Provide 8mm φ @ 300mm c/c.
DESIGN OF FLOOR SLAB (S6 (b)):
D =3.05 x 103
36.4+ 20 = 103.79mm say 120 mm
Effective depth (d) = D – d1 = 120 – 20 = 100mm
Loads:
Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2
Self weight of the slab = 1 x 1 x D x 25 = 1201000 x 25
= 3 KN/m2
Live loads (From IS875 – Part 2):
Office = 4 KN/m2
Total load (W) = 4 +3 + 1 = 8 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 8
=12 KN/m2
Design moment: (for end panel)
Mu =Wu x L2
12=
12 x (3.05)2
12= 9.3025 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 28/293
28
Calculation of area of steel:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
9.3025 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 273.13 mm2
Spacing of 10mm φ bars =π4
x 102 x1000
273.13= 287.55mm
Therefore, Provide 10mm φ @ 280mm c/c.
Distribution steel:
Ast = 0.12% of Ag
=0.12
1000x 120 x 1000 = 144 mm2.
Spacing of 8mm φ bars =π4
x 82 x1000
144=349mm
Therefore, Provide 8mm φ @ 300mm c/c.
Area of steel at support next to end support (between S6 (a) and S6 (b)):
From IS 456-2000, moment =Wu x L2
10
Total Load acting on the support (Wu) = 12 KN/m
Therefore, Moment =12 x (3.05)2
10= 11.163 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 29/293
29
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
11.163 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 332.06 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S6 (a) =1
2x 332.06 = 166.03 mm2
From Slab S6 (b) =1
2x 273.23 = 136.565 mm2
Total Ast (available) = 166.03 + 136.565 = 302.595 mm2
Therefore, extra bars required for Ast = 332.06 – 302.595 = 29.465 mm2
DESIGN OF FLOOR SLAB (S7):
D = 3.05 x 103
36.4+ 20 = 103.79mm say 120 mm
Effective depth (d) = D – d1 = 120 – 20 = 100mm
Loads:
Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2
Self weight of the slab = 1 x 1 x D x 25 =120
1000x 25
= 3 KN/m2
Live loads (From IS875 – Part 2):
Library = 10 KN/m2
Total load (W) = 10 +3 + 1 = 14 KN/m2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 30/293
30
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 14
=21 KN/m2
Design moment: (for end panel)
Mu =Wu x L2
10=
12 x (3.05)2
10= 19.54 KN-m
Calculation of area of steel:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
19.54 x 106 = 0.87 x 415 x Ast x 100 x (1 - 415 x Ast20 x 1000 x 100 )
Ast = 621.3 mm2
Spacing of 10mm φ bars =π4
x 102 x1000
621.3= 126.41mm
Therefore, Provide 10mm φ @ 120mm c/c.
Distribution steel:
Ast = 0.12% of Ag
=0.12
1000x 120 x 1000 = 144 mm2.
Spacing of 8mm φ bars =π4
x 82 x1000
144=349mm
Therefore, Provide 8mm φ @ 300mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 31/293
31
DESIGN OF FLOOR SLAB (S8):
D =3.05 x 103
36.4+ 20 = 103.79mm say 120 mm
Effective depth (d) = D – d1 = 120 – 20 = 100mm
Loads:
Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2
Self weight of the slab = 1 x 1 x D x 25 =120
1000
x 25
= 3 KN/m2
Live loads (From IS875 – Part 2):
Private = 2 KN/m2
Total load (W) = 2 +3 + 1 = 6 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 6
= 9 KN/m2
Design moment:
Mu =Wu x L2
12=
9 x (3.05)2
12= 6.97 KN-m
Calculation of area of steel:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
6.97 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 201.47 mm2
Spacing of 10mm φ bars =π4 x 102 x
1000
201.47 = 389.8mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 32/293
32
Therefore, Provide 10mm φ @ 300mm c/c.
Distribution steel:
Ast = 0.12% of Ag
=0.12
1000x 120 x 1000 = 144 mm2.
Spacing of 8mm φ bars =π4
x 82 x1000
144=349mm
Therefore, Provide 8mm φ @ 300mm c/c.
Area of steel at support next to end support (between S7and S8):
From IS 456-2000, moment =Wu x L2
10
Total Load acting on the support (Wu) =21
2+
9
2= 15 KN/m
Therefore, Moment =15 x (3.05)2
10= 13.95 KN-m
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
13.95 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 423.61 mm2
Area of steel available by bending up the alternate bars of mid span steel:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 33/293
33
From Slab S7 =1
2x 621.3 = 310.65 mm2
From Slab S8 =1
2x 201.47 = 100.735 mm2
Total Ast (available) = 310.65 + 100.735 = 411.385 mm2
Therefore, extra bars required for Ast = 423.61 – 411.385 = 12.225 mm2
DESIGN OF FLOOR SLAB (S9 (a)):
D =3.05 x 103
36.4+ 20 = 103.79mm say 120 mm
Effective depth (d) = D – d1 = 120 – 20 = 100mm
Loads:
Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2
Self weight of the slab = 1 x 1 x D x 25 =120
1000x 25
= 3 KN/m2
Live loads (From IS875 – Part 2):
Office chamber = 3 KN/m2
Total load (W) = 3 +3 + 1 = 7 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 7
= 10.5 KN/m2
Design moment:
Mu =Wu x L2
12=
10.5 x (3.05)2
12= 8.14 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 34/293
34
Calculation of area of steel:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
8.14 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 237.12 mm2
Spacing of 10mm φ bars =π4
x 102 x1000
237.12= 331.23mm
Therefore, Provide 10mm φ @ 300mm c/c.
Distribution steel:
Ast = 0.12% of Ag
=0.12
1000x 120 x 1000 = 144 mm2.
Spacing of 8mm φ bars =π4
x 82 x1000
144=349mm
Therefore, Provide 8mm φ @ 300mm c/c.
Area of steel at any other interior support: (Between S8 and S9 (a))
From IS 456-2000, moment =Wu x L2
12
Total Load acting on the support (Wu) =9
2+
10.5
2= 9.75 KN/m
Therefore, Moment = 9.75 x (3.05)2
12= 7.56 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 35/293
35
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
7.56 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 219.38 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S8 =1
2x 201.47 = 100.735 mm2
From Slab S9 (a) =1
2x 237.12 = 118.56 mm2
Total Ast (available) = 100.735 + 118.56 = 219.3 mm2
Therefore Ast (available) = Ast (required)
No need of providing extra bars.
DESIGN OF FLOOR SLAB (S9 (b)):
D =3.05 x 103
36.4+ 20 = 103.79mm say 120 mm
Effective depth (d) = D – d1 = 120 – 20 = 100mm
Loads:
Dead loads (From IS875 – Part 1):
Floor finish = 1 KN/m2
Self weight of the slab = 1 x 1 x D x 25 =120
1000x 25
= 3 KN/m2
Live loads (From IS875 – Part 2):
Office chamber = 3 KN/m2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 36/293
36
Total load (W) = 3 +3 + 1 = 7 KN/m2
Ultimate load or limit state load or design load (Wu) = 1.5 x W = 1.5 x 7
= 10.5 KN/m2
Design moment: (for end panel)
Mu =Wu x L2
10=
10.5 x (3.05)2
10= 9.77 KN-m
Calculation of area of steel:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d
)
9.77 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 287.79 mm2
Spacing of 10mm φ bars =π4
x 102 x1000
287.79= 272.91mm
Therefore, Provide 10mm φ @ 270mm c/c.
Distribution steel:
Ast = 0.12% of Ag
=0.12
1000x 120 x 1000 = 144 mm2.
Spacing of 8mm φ bars =
π4 x 8
2
x
1000
144 =349mm
Therefore, Provide 8mm φ @ 300mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 37/293
37
Area of steel at support next to end support (between S9 (a) and S9 (b)):
From IS 456-2000, moment =Wu x L2
10
Total Load acting on the support (Wu) = 10.5 KN/m
Therefore, Moment =10.5 x (3.05)2
10= 9.77 KN-m
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
9.77 x 106 = 0.87 x 415 x Ast x 100 x (1 -415 x Ast
20 x 1000 x 100)
Ast = 287.79 mm2
Area of steel available by bending up the alternate bars of mid span steel:
From Slab S9 (a) =1
2x 237.12 = 118.56 mm2
From Slab S9 (b) =1
2x 287.79 = 143.895 mm2
Total Ast (available) = 118.56 + 143.895 = 262.455 mm2
Therefore, extra bars required for Ast = 287.79 – 262.455 = 25.335 mm2
Detail of reinforcement provided in slabs:
Slab Function Main steel Distribution steel End shears
Long
span
(Wu x L
2)
KN/m
Short
span
(Wu x L
6)
KN/m
Roof S1 and
Roof S3
Terrace 8mmφ bars @
150mm c/c
8mmφ bars @
300mm c/c 15.441 5.1467
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 38/293
38
Roof S2 and
Roof S4
Terrace 8mmφ bars @
190mm c/c
8mmφ bars @
300mm c/c 15.441 5.1467
Floor S1 Toilet 10mmφ bars @
130mm c/c
8mmφ bars @
300mm c/c
29.738 9.913
Floor S2 Office 10mmφ bars @
210mm c/c
8mmφ bars @
300mm c/c
24.019 8
Floor S3 Office SupDt. 10mmφ bars @
210mm c/c
8mmφ bars @
300mm c/c
24.019 8
Floor S4 Assembly Hall 10mmφ bars @
210mm c/c
8mmφ bars @
300mm c/c
24.019 8
Floor S5 (a) Office chamber
and Waiting space
10mmφ bars @
190mm c/c
8mmφ bars @
300mm c/c 26.306 8.77
Floor S5 (b) Office chamber
and Waiting space
10mmφ bars @
150mm c/c
8mmφ bars @
300mm c/c 26.306 8.77
Floor S6 (a) Office 10mmφ bars @
230mm c/c
8mmφ bars @
300mm c/c
18.3 6.1
Floor S6 (b) Office 10mmφ bars @
280mm c/c
8mmφ bars @
300mm c/c
18.3 6.1
Floor S7 Library 10mmφ bars @
120mm c/c
8mmφ bars @
300mm c/c
32.025 10.675
Floor S8 Secretary room 10mmφ bars @
300mm c/c
8mmφ bars @
300mm c/c
13.725 4.575
Floor S9 (a) Office chamber 10mmφ bars @
300mm c/c
8mmφ bars @
300mm c/c
16.01 5.3375
Floor S9 (b) Office chamber 10mmφ bars @
270mm c/c
8mmφ bars @
300mm c/c
16.01 5.3375
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 39/293
39
3. Analysis of frames
We have many number frames from the plan and the need to be analysed. We have two
different types of frames:
1. Longitudinal direction frame
2. Transverse direction frame
Transverse frame:
The frames are chosen in such a way that the loads vary from one frame to the other and we
have 6 transverse frames.
i. Frame 19-10-01
ii. Frame 20-11-02
iii. Frame 24-15-06
iv. Frame 25-16-07
v. Frame 26-17-08
vi. Frame 27-18-09
In every frame we need to analyse the three types of loading cases and each frame consists of
roof and floor analysis.
Here we assumed the cross sections of beams and columns in advance and with the help of
the assumed dimensions, we calculate the stiffness of the members and there by the
distribution factors for the members especially at the joints.
To analyse the frame we use the substitute frame method and there by applying the moment
distribution method to know the moments carried by the member at the joints.
We take each floor span and we assume the top and bottom storeys are fixed by the substitute
frame principle.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 40/293
40
Typical building frame:
We have G+5frame with all the details shown in the above figure.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 41/293
41
Type of
member
b(mm) x
D(mm)
Length
(mm)
M.O.I
(mm4) =
b x D3
12
Multiplying
factor for
flanged
section
Final
M.O.I
(mm4)
K =
final M.O.I
LENGTH
(mm3)
Beam 230 x
300
6000 517.5 x
106
2 1035 x 10 172.5 x 10
230 x
300
8410 517.5 x
106
2 1035 x 10 123.07 x 10
Beam 230 x
450
6000 1746.56 x
106
2 3493.125
x 106
582.18 x 10
230 x
450
8410 1746.56 x
106
2 3493.125
x 106
415.35 x 10
Beam 230 x
600
6000 4140 x
106
2 8280 x 10 1.38 x 10
230 x
600
8410 4140 x
106
2 8280 x 10 0.985 x 10
Column 230 x
600
3350 4140 x
106
- 4140 x 106 1235.82 x
103
Frame 19-10-01:
Calculation of loads:
Roof:
Slab: 110mm
Dead load = self weight + F.F
= (0.11 x 25) + 2.5 = 5.25 KN/m2
Live load = 1.5 KN/m2
Beam (19-10) (230mm X 300mm)
Dead load:
Self weight = 0.23 x 25 x (0.3-0.11) = 1.1 KN/m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 42/293
42
Due to Slab =W x L
2=
5.25 x 3.05
2= 8 KN/m
250mm thick wall of 1m height = 0.25 x 1 x 20 = 5 KN/m
Live load:
Due to Slab =W x L
2=
1.5 x 3.05
2= 2.29KN/m
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5 x (1.1 + 8 + 2.29 + 5)
= 24.6 KN/m
Minimum load = 0.9 x D.L = 0.9 x (1.1 + 8 + 5) = 13 KN/m
Beam (10-01) (230mm X 300mm)
Dead load:
Self weight = 0.23 x 25 x (0.3-0.11) = 1.1 KN/m
Due to Slab =W x L
2=
5.25 x 3.05
2= 8 KN/m
250mm thick wall of 1m height = 0.25 x 1 x 20 = 5 KN/m
Live load:
Due to Slab =W x L
2=
1.5 x 3.05
2= 2.29KN/m
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5 x (1.1 + 8 + 2.29 + 5)
= 24.6 KN/m
Minimum load = 0.9 x D.L = 0.9 x (1.1 + 8 + 5) = 13 KN/m
Case 1:
Maximum load on beam 19-10 and minimum load beam 10-01
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 43/293
43
Calculation of distribution factors:
Joint Member K ΣK D.F
1 Column 1235.82 x 10 1.41 x 10 0.88
Beam 172.5 x 10 0.12
2 Beam 172.5 x 10 1.53 x 10 0.11
Column 1235.82 x 10 0.81
Beam 123.07 x 103 0.08
3 Beam 123.07 x 103 1.35 x 106 0.09
column 1235.82 x 10 0.91
Calculation of moments:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 44/293
44
Calculation of support reactions:
From beam 1-2, ΣM1=0
64.85 + V2 x 6 = 24.6 x 6 x6
2+ 78.52
V2 = 76.07 KN
V1 + V2 = 24.6 x 6 = 147.6 KN
V1 = 71.54 KN
Maximum Span moment,
X=71.54
24.6= 2.91m from the left support
Therefore, maximum moment =71.54 x 2.91
2- 64.85 = 39.24 KN-m
From beam 2-3, ΣM2=0
79.93 + V3 x 8.41 = 69.78 + 13 x 8.41 x8.41
2
V3 = 53.46 KN
V2 + V3 = 13 x 8.41 =109.33 KN
V2 = 55.87 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 45/293
45
Maximum Span moment,
X=53.46
13= 4.12m from the right support
Therefore, maximum moment =53.46 x 4.12
2- 69.78 = 40.35 KN-m
Case 2:
Minimum load on beam 19-10 and maximum load on 10-01
Distribution factors are same as calculate in case 1.
Calculation of moments:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 46/293
46
Calculation of support reactions:
From beam 1-2, ΣM1=0
28.96 + V2 x 6 = 13 x 6 x
6
2 + 53.16
V2 = 42.87 KN
V1 + V2 = 13 x 6 = 78 KN
V1 = 35.13 KN
Maximum Span moment,
X=35.13
13= 2.7m from the left support
Therefore, maximum moment =35.13 x 2.7
2- 28.16 = 19.27 KN-m
From beam 2-3, ΣM2=0
142.85 + V3 x 8.41 = 136.01 + 24.6 x 8.41 x8.41
2
V3 = 102.63 KN
V2 + V3 = 24.6 x 8.41 = 206.89 KN
V2 = 104.26 KN
Maximum Span moment,
X= 102.6324.6
= 4.17m from the right support
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 47/293
47
Therefore, maximum moment =102.63 x 4.17
2- 136.01 = 77.97 KN-m
Case 3:
Max load on beam 19-10 and beam 10-01
Distribution factors are same as calculated in case 1.
Calculations of moments:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 48/293
48
Calculation of support reactions:
From beam 1-2, ΣM1=0
61.38 + V2 x 6 = 24.6 x 6 x6
2 + 86.09
V2 = 77.92 KN
V1 + V2 = 24.6 x 6 = 147.6 KN
V1 = 69.68 KN
Maximum Span moment,
X=69.68
24.6= 2.83m from the left support
Therefore, maximum moment =69.68 x 2.83
2- 61.38 = 37.22 KN-m
From beam 2-3, ΣM2=0
145.76 + V3 x 8.41 = 134.65 + 24.6 x 8.41 x8.41
2
V3 = 102.05 KN
V2 + V3 = 24.6 x 8.41 = 206.89 KN
V2 = 104.84 KN
Maximum Span moment,
X=102.05
24.6= 4.15m from the right support
Therefore, maximum moment =102.05 x 4.15
2- 134.65 = 77.1 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 49/293
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 50/293
50
Due to Slab =W x L
2=
4 x 3.05
2= 6.1 KN/m
250mm thick wall = 0.25 x 20 x (3.35-0.3) = 15.25 KN/m
Live load:
Due to Slab =W x L
2=
4 x 3.05
2= 6.1KN/m
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5 x (1.9+6.1+15.25+6.1)
= 44.025 KN/m
Minimum load = 0.9 x D.L = 0.9 x (1.9+6.1+15.25) = 21 KN/m
Beam (10-01) (230mm X 450mm)
Dead load:
Self weight = 0.23 x 25 x (0.45-0.12) = 1.9 KN/m
Due to Slab =W x L
2=
4 x 3.05
2= 6.1 KN/m
250mm thick wall = 0.25 x 20 x (3.35-0.3) = 15.25 KN/m
Live load:
Due to Slab =W x L
2=
5 x 3.05
2= 7.625KN/m
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5 x (1.9+6.1+15.25+7.625)
= 46.5 KN/m
Minimum load = 0.9 x D.L = 0.9 x (1.9+6.1+15.25) = 21KN/m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 51/293
51
Case 1:
Maximum load on beam 19-10 and minimum load on beam 10-01
Calculation of distribution factors:
Joint Member K ΣK D.F
4 Column 1235.82 x 10 3.05 x 10 0.4
Beam 582.18 x 10 0.2
Column 1235.82 x 10 0.4
5 Beam 582.18 x 10 3.47 x 10 0.17
Column 1235.82 x 103 0.36
Beam 415.35 x 103 0.11
Column 1235.82 x 10 0.36
6 Beam 415.35 x 10 2.89 x 10 0.14
Column 1235.82 x 10 0.43
Column 1235.82 x 10 0.43
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 52/293
52
Calculation of moments:
Calculation of support reactions:
From beam 4-5, ΣM4=0
106.54 + V5 x 6 = 44.025 x 6 x 62
+ 143.19
V5 = 138.18 KN
V4 + V5 = 44.025 x 6 = 264.15 KN
V4 = 125.97 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 53/293
53
Maximum Span moment,
X=125.97
44.025= 2.86m from the left support
Therefore, maximum moment =125.96 x 2.86
2- 106.54 = 73.58 KN-m
From beam 4-5, ΣM5=0
133.85 + V6 x 8.41 = 105.76 + 21 x 8.41 x8.41
2
V6 = 84.96 KN
V5 + V6 = 21 x 8.41 = 176.61 KN
V5 = 91.65 KN
Maximum Span moment,
X=84.96
21= 4.05m from the right support
Therefore, maximum moment = 84.96 x 4.052
- 105.76 = 66.28 KN-m
Case 2:
Minimum load on beam 19-10 and maximum load on beam 10-01
Distribution factors are same as calculated in case-1.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 54/293
54
Calculation of moments:
Calculation of support reactions:
From beam 4-5, ΣM4=0
34.99 + V5 x 6 = 21 x 6 x 62 + 105.91
V5 = 74.81 KN
V4 + V5 = 21 x 6 = 126 KN
V4 = 51.19 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 55/293
55
Maximum Span moment,
X=51.19
21= 2.45m from the left support
Therefore, maximum moment =51.19 x 2.45
2- 34.99 = 27.72 KN-m
From beam 4-5, ΣM5=0
269.10 + V6 x 8.41 = 246.62 + 46.5 x 8.41 x8.41
2
V6 = 192.86 KN
V5 + V6 = 46.5 x 8.41 = 391.07 KN
V5 = 198.21 KN
Maximum Span moment,
X=192.86
46.5= 4.15m from the right support
Therefore, maximum moment = 192.86 x 4.152
- 246.62= 153.57 KN-m
Case 3:
Maximum load on both beams
Distribution factors are same as calculated in case 1.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 56/293
56
Calculation of moments:
Calculation of support reactions:
From beam 4-5, ΣM4=0
96.02 + V5
x 6 = 44.025 x 6 x6
2+ 169.53
V5 = 144.33 KN
V4 + V5 = 44.025 x 6 = 264.15 KN
V4 = 119.82 KN
Maximum Span moment,
X=119.82
44.025= 2.72m from the left support
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 57/293
57
Therefore, maximum moment =119.82 x 2.72
2- 96.02 = 66.94 KN-m
From beam 4-5, ΣM5=0
277.32 + V6 x 8.41 = 242.87 + 46.5 x 8.41 x8.41
2
V6 = 191.43 KN
V5 + V6 = 46.5 x 8.41 = 391.07 KN
V5 = 199.64 KN
Maximum Span moment,
X=191.43
46.5= 4.12m from the right support
Therefore, maximum moment =191.43 x 4.12
2- 242.87= 151.48 KN-m
Beam and column bending moments (KN-m):
Joint 4 Joint 5 Joint 6
Case Column Beam Max
span
moment
Beam Column Beam Max
span
moment
Beam Column
1 53.27 106.54 73.58 143.19 4.67 133.84 65.86 105.75 53.13
2 17.5 34.99 27.2 105.91 81.6 269.1 153.57 246.62 122.6
3 48.01 96.02 66.94 169.53 53.9 277.32 151.48 242.87 121.11
Max 53.27 106.54 73.58 169.53 81.6 277.32 153.57 246.62 122.6
Shear or support reaction (KN):
Case no. Joint 4 Joint 5 Joint 6
1 125.6 138.18 91.65 84.96
2 51.19 74.81 198.21 192.85
3 119.82 144.33 199.64 191.43
Maximum shear 125.6 144.33 199.64 192.85
Maximum column load 125.6 343.97 192.85
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 58/293
58
Frame 20-11-02:
Calculation of loads:
Roof:
Slab: 110mm
Dead load = self weight + F.F
= (0.11 x 25) + 2.5 = 5.25 KN/m2
Live load = 1.5 KN/m2
Beam (20-11) (230mm X 450mm)
Dead load:
Self weight = 0.23 x 25 x (0.45-0.11) = 1.2 KN/m
Due to Slab = W x L= 5.25 x 3.05= 16.0125 KN/m
Live load:
Due to Slab = W x L= 1.5 x 3.05= 4.6 KN/m
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5 x (1.2+16.0125+4.6)
= 33 KN/m
Minimum load = 0.9 x D.L = 0.9 x (1.2+16.0125) = 15.49 KN/m
Beam (11-02) (230mm X 450mm)
Dead load:
Self weight = 0.23 x 25 x (0.45-0.11) = 1.2 KN/m
Due to Slab = W x L= 5.25 x 3.05= 16.0125 KN/m
Live load:
Due to Slab = W x L= 1.5 x 3.05= 4.6 KN/m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 59/293
59
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5 x (1.2+16.0125+4.6)
= 33 KN/m
Minimum load = 0.9 x D.L = 0.9 x (1.2+16.0125) = 15.49 KN/m
Case 1:
Maximum load on beam 20-11 and minimum load beam 11-02
Calculation of distribution factors:
Joint Member K ΣK D.F
1 Column 1235.82 x 10 1.818 x 10 0.68
Beam 582.18 x 10 0.32
2 Beam 582.18 x 10 2.234 x 10 0.26
Column 1235.82 x 10 0.55
Beam 415.35 x 10 0.19
3 Beam 415.35 x 10 1.651 x 10 0.25
column 1235.82 x 103 0.75
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 60/293
60
Calculation of moments:
Calculation of support reactions:
From beam 1-2, ΣM1=0
68.42 + V2 x 6 = 33 x 6 x6
2+ 111.87
V2 = 106.24 KN
V1 + V2 = 33 x 6 = 198 KN
V1 = 91.76 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 61/293
61
Maximum Span moment,
X=91.76
33= 2.78m from the left support
Therefore, maximum moment =91.76 x 2.78
2- 68.42 = 59.13 KN-m
From beam 2-3, ΣM2=0
105.03 + V3 x 8.41 = 67.38 + 15.49 x 8.41 x8.41
2
V3 = 60.66 KN
V2 + V3 = 15.49 x 8.41 =130.27 KN
V2 = 69.61 KN
Maximum Span moment,
X=60.66
15.49= 3.92m from the right support
Therefore, maximum moment = 60.66 x 3.922
- 67.38 = 51.51 KN-m
Case 2:
Minimum load on beam 20-11 and maximum load on 11-02
Distribution factors are same as calculate in case 1.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 62/293
62
Calculation of moments:
Calculation of support reactions:
From beam 1-2, ΣM1=0
16.56 + V2 x 6 = 15.49 x 6 x 62
+ 94.59
V2 = 59.48 KN
V1 + V2 = 15.49 x 6 = 92.94 KN
V1 = 33.46 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 63/293
63
Maximum Span moment,
X=33.46
15.49= 2.16m from the left support
Therefore, maximum moment =33.46 x 2.16
2- 16.56 = 19.58 KN-m
From beam 2-3, ΣM2=0
188.13 + V3 x 8.41 = 158.87 + 33 x 8.41 x8.41
2
V3 = 135.28 KN
V2 + V3 = 33 x 8.41 = 277.53 KN
V2 = 142.25 KN
Maximum Span moment,
X=135.28
33= 4.1m from the right support
Therefore, maximum moment = 135.28 x 4.12
- 158.81 = 118.52 KN-m
Case 3:
Max load on beam 20-11 and beam 11-02
Distribution factors are same as calculated in case 1.
Calculations of moments:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 64/293
64
Calculation of support reactions:
From beam 1-2, ΣM1=0
57.83 + V2 x 6 = 33 x 6 x6
2+ 140.51
V2 = 112.78 KN
V1 + V2 = 33 x 6 = 198 KN
V1 = 85.22 KN
Maximum Span moment,
X= 85.2233
= 2.58m from the left support
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 65/293
65
Therefore, maximum moment =85.22 x 2.58
2- 57.83 = 52.1 KN-m
From beam 2-3, ΣM2=0
199.52 + V3 x 8.41 = 153.93 + 33 x 8.41 x8.41
2
V3 = 133.34 KN
V2 + V3 = 33 x 8.41 = 277.53 KN
V2 = 144.19 KN
Maximum Span moment,
X=133.34
33= 4.04m from the right support
Therefore, maximum moment =133.34 x 4.04
2- 153.93 = 115.42 KN-m
Beam and column bending moments (KN-m):
Joint 1 Joint 2 Joint 3
Case Column Beam Max
span
moment
Beam Column Beam Max
span
moment
Beam Column
1 68.42 68.42 59.13 111.87 6.84 105.0 51.51 67.38 68.22
2 16.58 16.58 19.58 94.59 93.54 188.13 118.52 158.81 155.58
3 57.85 57.83 52.1 140.51 59 199.51 115.42 153.93 152.3
Max 68.42 68.42 59.13 140.51 93.54 199.51 118.52 158.81 155.58
Shear or support reaction (KN):
Case no. Joint 4 Joint 5 Joint 6
1 91.76 106.24 69.61 60.66
2 33.46 59.48 142.25 135.28
3 85.22 112.78 144.11 133.34
Maximum shear 91.76 112.78 144.11 135.28
Maximum column load 91.76 256.89 135.28
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 66/293
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 67/293
67
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5x(2.76+12.2+14.5+15.25)
= 67.1 KN/m
Minimum load = 0.9 x D.L = 0.9x(2.76+12.2+14.5) = 26.5 KN/m
Case 1:
Maximum load on beam 20-11 and minimum load on beam 11-02
Calculation of distribution factors:
Joint Member K ΣK D.F
4 Column 1235.82 x 10
3.85 x 106
0.32
Beam 1.38 x 10 0.36
Column 1235.82 x 10 0.32
5 Beam 1.38 x 10
4.84 x 106
0.29
Column 1235.82 x 10 0.26
Beam 0.985 x 106 0.19
Column 1235.82 x 103 0.26
6 Beam 0.985 x 10
3.46 x 106
0.28
Column 1235.82 x 10 0.36
Column 1235.82 x 10 0.36
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 68/293
68
Calculation of moments:
Calculation of support reactions:
From beam 4-5, ΣM4=0
75.53 + V5 x 6 = 41 x 6 x6
2+ 154.22
V5 = 136.12 KN
V4 + V5 = 41 x 6 = 246 KN
V4 = 109.88 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 69/293
69
Maximum Span moment,
X=109.88
41= 2.68m from the left support
Therefore, maximum moment =109.88 x 2.68
2- 75.53 = 71.71 KN-m
From beam 4-5, ΣM5=0
172.08 + V6 x 8.41 = 114.85 + 26.5 x 8.41 x8.41
2
V6 = 104.63 KN
V5 + V6 = 26.5 x 8.41 = 222.87 KN
V5 = 118.24 KN
Maximum Span moment,
X=104.63
26.5= 3.95m from the right support
Therefore, maximum moment = 104.63 x 3.952
- 114.85 = 91.8 KN-m
Case 2:
Minimum load on beam 20-11 and maximum load on beam 11-02
Distribution factors are same as calculated in case-1.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 70/293
70
Calculation of moments:
Calculation of support reactions:
From beam 4-5, ΣM4=0
16.29 + V5 x 6 = 13.5 x 6 x6
2+ 158.17
V5 = 64.15 KN
V4 + V5 = 13.5 x 6 = 81 KN
V4 = 16.85 KN
Maximum Span moment,
X= 16.8513.5
= 1.25m from the left support
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 71/293
71
Therefore, maximum moment =16.85 x 1.25
2- 12.92 = -2.39 KN-m
From beam 4-5, ΣM5=0
375.67 + V6 x 8.41 = 315.93 + 67.1 x 8.41 x8.41
2
V6 = 275.05 KN
V5 + V6 = 67.1 x 8.41 = 564.31 KN
V5 = 289.26 KN
Maximum Span moment,
X=275.05
67.1= 4.1m from the right support
Therefore, maximum moment =275.05 x 4.1
2- 315.93= 247.92 KN-m
Case 3:
Maximum load on both beams
Distribution factors are same as calculated in case 1.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 72/293
72
Calculation of moments:
Calculation of support reactions:
From beam 4-5, ΣM4=0
49.25 + V5 x 6 = 41 x 6 x6
2 + 228.89
V5 = 152.94 KN
V4 + V5 = 41 x 6 = 246 KN
V4 = 93.06 KN
Maximum Span moment,
X= 93.0641
= 2.27m from the left support
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 73/293
73
Therefore, maximum moment =93.06 x 2.27
2- 49.25 = 56.37 KN-m
From beam 4-5, ΣM5=0
393.9 + V6 x 8.41 = 308.24 + 67.1 x 8.41 x8.41
2
V6 = 271.97 KN
V5 + V6 = 67.1 x 8.41 = 564.31 KN
V5 = 292.34 KN
Maximum Span moment,
X=271.97
67.1= 4.05m from the right support
Therefore, maximum moment =271.97 x 4.05
2- 308.24= 242.5 KN-m
Beam and column bending moments (KN-m):
Joint 4 Joint 5 Joint 6
Case Column Beam Max
span
moment
Beam Column Beam Max
span
moment
Beam Column
1 37.77 75.53 71.71 154.21 8.9 172.08 91.8 114.85 57.45
2 6.42 12.92 3.092 158.17 108.74 375.67 247.92 315.93 153.37
3 24.66 49.25 56.37 228.89 82.5 393.9 242.5 308.24 150.94
Max 37.77 75.53 71.71 228.89 108.74 393.9 247.92 315.93 153.37
Shear or support reaction (KN):
Case no. Joint 4 Joint 5 Joint 6
1 109.8 136.12 118.24 104.63
2 16.85 64.15 289.26 275.05
3 93.06 152.94 292.34 271.97
Maximum shear 109.8 152.94 292.34 275.05
Maximum column load 109.8 445.28 275.05
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 74/293
74
Frame 24-15-06
Roof:
Same as frame 20-11-02
Floor:
Slab = 120mm
Dead load = self weight + F.F
= (0.12 x 25) + 1 = 4 KN/m2
Live load = 10 KN/m2
for Beam 24-15
= 2 KN/m2 for Beam 24-15
= 5 KN/m2 for Beam 15-06
Beam (24-15) (230mm X 600mm)
Dead load:
Self weight = 0.23 x 25 x (0.6-0.12) = 2.76 KN/m
Due to Slab = W x L= 4 x 3.05= 12.2 KN/m
150mm wall of 2.2m height = 0.15 x 20 x 2.2 = 6.6 KN/m
Live load:
Due to Slab =5 x 3.05
2+
2 x 3.05
2= 10.675 KN/m
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5x(2.76+12.2+6.6+10.675)
= 48.5 KN/m
Minimum load = 0.9 x D.L = 0.9 x (2.76+12.2+6.6) = 19.5 KN/m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 75/293
75
Beam (15-06) (230mm X 600mm)
Dead load:
Self weight = 0.23 x 25 x (0.6-0.12) = 2.76 KN/m
Due to Slab = W x L= 4 x 3.05= 12.2 KN/m
Live load:
Due to Slab = W x L= 5 x 3.05= 15.25KN/m
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5 x (2.76+12.2+15.25)
= 45.5 KN/m
Minimum load = 0.9 x D.L = 0.9 x (2.76+12.2) = 22.5 KN/m
Case 1:
Maximum load on beam 24-15 and minimum load on beam 15-06
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 76/293
76
Calculation of distribution factors:
Joint Member K ΣK D.F
4 Column 1235.82 x 103
3.85 x 106
0.32
Beam 1.38 x 10 0.36
Column 1235.82 x 10 0.32
5 Beam 1.38 x 10
4.84 x 106
0.29
Column 1235.82 x 10 0.26
Beam 0.985 x 10 0.19
Column 1235.82 x 10 0.26
6 Beam 0.985 x 106
3.46 x 106
0.28
Column 1235.82 x 10 0.36
Column 1235.82 x 10 0.36
Calculation of moments:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 77/293
77
Calculation of support reactions:
From beam 4-5, ΣM4=0
95.08 + V5 x 6 = 48.5 x 6 x62
+ 166.11
V5 = 157.34 KN
V4 + V5 = 48.5 x 6 = 291 KN
V4 = 133.66 KN
Maximum Span moment,
X=133.66
48.5= 2.76m from the left support
Therefore, maximum moment =133.66 x 2.76
2- 95.08 = 89.37 KN-m
From beam 4-5, ΣM5=0
155.12 + V6 x 8.41 = 93.64 + 22.5 x 8.41 x 8.412
V6 = 87.3 KN
V5 + V6 = 22.5 x 8.41 = 189.23 KN
V5 = 101.93 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 78/293
78
Maximum Span moment,
X=87.3
22.5= 3.88m from the right support
Therefore, maximum moment =87.3 x 3.88
2- 93.64 = 75.72 KN-m
Case 2:
Minimum load on beam 24-15 and maximum load on beam 15-06
Distribution factors are same as calculated in case-1.
Calculation of moments:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 79/293
79
Calculation of support reactions:
From beam 4-5, ΣM4=0
14.68 + V5 x 6 = 19.5 x 6 x6
2+ 133.86
V5 = 78.37 KN
V4 + V5 = 19.5 x 6 = 117 KN
V4 = 38.63 KN
Maximum Span moment,
X=38.63
19.5= 1.98m from the left support
Therefore, maximum moment =38.63 x 1.98
2- 14.68 = 23.56 KN-m
From beam 4-5, ΣM5=0
261.6 + V6 x 8.41 = 211.34 + 45.5 x 8.41 x 8.412
V6 = 185.35 KN
V5 + V6 = 45.5 x 8.41 = 382.66 KN
V5 = 197.31 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 80/293
80
Maximum Span moment,
X=185.35
45.5= 4.07m from the right support
Therefore, maximum moment =185.35 x 4.07
2- 211.34= 165.85 KN-m
Case 3:
Maximum load on both beams
Distribution factors are same as calculated in case 1.
Calculation of moments:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 81/293
81
Calculation of support reactions:
From beam 4-5, ΣM4=0
80.19 + V5 x 6 = 44.5 x 6 x 62
+ 208.43
V5 = 166.87 KN
V4 + V5 = 48.5 x 6 = 291 KN
V4 = 124.13 KN
Maximum Span moment,
X=124.13
48.5= 2.56m from the left support
Therefore, maximum moment =124.13 x 2.56
2- 80.19 = 78.7 KN-m
From beam 4-5, ΣM5=0
280.82 + V6 x 8.41 = 203.22 + 45.5 x 8.41 x 8.412
V6 = 182.1 KN
V5 + V6 = 67.1 x 8.41 = 382.66 KN
V5 = 200.56 KN
Maximum Span moment,
X=182.145.5
= 4m from the right support
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 82/293
82
Therefore, maximum moment =182.1 x 4
2- 203.22= 160.98 KN-m
Beam and column bending moments (KN-m):
Joint 4 Joint 5 Joint 6
Case Column Beam Max
span
moment
Beam Column Beam Max
span
moment
Beam Column
1 47.54 95.08 89.37 166.11 5.5 155.12 75.72 93.64 47.54
2 7.34 14.63 23.56 133.86 63.86 261.6 166.85 211.34 103.08
3 40.11 80.19 78.7 208.43 36.19 280.82 160.98 203.22 100.52
Max 47.54 95.08 89.37 208.43 63.86 280.82 166.85 211.34 103.08
Shear or support reaction (KN):
Case no. Joint 4 Joint 5 Joint 6
1 133.66 157.34 101.93 87.3
2 38.63 78.37 197.31 185.35
3 124.13 166.87 200.56 182.1
Maximum shear 133.66 166.87 200.56 185.35
Maximum column load 133.66 367.43 185.35
Frame 25-16-07
Roof:
Same as frame 20-11-02
Floor:
Slab = 120mm
Dead load = self weight + F.F
= (0.12 x 25) + 1 = 4 KN/m2
Live load = 2 KN/m2 for Beam 25-16
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 83/293
83
= 4 KN/m2 for Beam 25-16
= 6 KN/m2 for Beam 16-07
= 5 KN/m2 for Beam 16-07
Beam (25-16) (230mm X 600mm)
Dead load:
Self weight = 0.23 x 25 x (0.6-0.12) = 2.76 KN/m
Due to Slab = W x L= 4 x 3.05= 12.2 KN/m
150mm wall of 2.2m height = 0.15 x 20 x 2.2 = 6.6 KN/m
Live load:
Due to Slab =2 x 3.05
2+
3 x 3.05
2= 7.625 KN/m
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5x(2.76+12.2+6.6+7.625)
= 44 KN/m
Minimum load = 0.9 x D.L = 0.9 x (2.76+12.2+6.6) = 19.5 KN/m
Beam (16-07) (230mm X 600mm)
Dead load:
Self weight = 0.23 x 25 x (0.6-0.12) = 2.76 KN/m
Due to Slab = W x L= 4 x 3.05= 12.2 KN/m
150mm wall of 2.2m height = 0.15 x 20 x 2.2 = 6.6 KN/m
Live load:
Due to Slab =5 x 3.05
2+
6 x 3.05
2= 16.775 KN/m
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5x(2.76+12.2+6.6+16.775)
= 57.51 KN/m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 84/293
84
Minimum load = 0.9 x D.L = 0.9 x (2.76+12.2+6.6) = 21.3 KN/m
Case 1:
Maximum load on beam 25-16 and minimum load on beam 16-07
Calculation of distribution factors:
Joint Member K ΣK D.F
4 Column 1235.82 x 10
3.85 x 106
0.32
Beam 1.38 x 10 0.36
Column 1235.82 x 10 0.32
5 Beam 1.38 x 10
4.84 x 106
0.29
Column 1235.82 x 10 0.26
Beam 0.985 x 10 0.19
Column 1235.82 x 103 0.26
6 Beam 0.985 x 106
3.46 x 106
0.28
Column 1235.82 x 10 0.36
Column 1235.82 x 10 0.36
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 85/293
85
Calculation of moments:
Calculation of support reactions:
From beam 4-5, ΣM4=0
85.69 + V5 x 6 = 44 x 6 x6
2+ 152.33
V5 = 143.11 KN
V4 + V5 = 44 x 6 = 264 KN
V4 = 120.89 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 86/293
86
Maximum Span moment,
X=120.89
44= 2.75m from the left support
Therefore, maximum moment =120.89 x 2.75
2- 85.69 = 80.45 KN-m
From beam 4-5, ΣM5=0
145.58 + V6 x 8.41 = 89.17 + 21.3 x 8.41 x8.41
2
V6 = 82.86 KN
V5 + V6 = 21.3 x 8.41 = 179.13 KN
V5 = 96.27 KN
Maximum Span moment,
X=82.86
21.3= 3.89m from the right support
Therefore, maximum moment = 82.86 x 3.892
- 89.17 = 72 KN-m
Case 2:
Minimum load on beam 25-16 and maximum load on beam 16-07
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 87/293
87
Distribution factors are same as calculated in case-1.
Calculation of moments:
Calculation of support reactions:
From beam 4-5, ΣM4=0
6.85 + V5 x 6 = 19.5 x 6 x6
2+ 155.96
V5 = 83.35 KN
V4 + V5 = 19.5 x 6 = 117 KN
V4 = 33.65 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 88/293
88
Maximum Span moment,
X=33.65
19.5= 1.73m from the left support
Therefore, maximum moment =33.65 x 1.73
2- 6.85 = 22.26 KN-m
From beam 4-5, ΣM5=0
327.23 + V6 x 8.41 = 268.6 + 57.51 x 8.41 x8.41
2
V6 = 234.86 KN
V5 + V6 = 57.51 x 8.41 = 483.66 KN
V5 = 248.8 KN
Maximum Span moment,
X=234.86
57.51= 4.08m from the right support
Therefore, maximum moment = 234.86 x 4.082
- 268.6= 210.5 KN-m
Case 3:
Maximum load on both beams
Distribution factors are same as calculated in case 1.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 89/293
89
Calculation of moments:
Calculation of support reactions:
From beam 4-5, ΣM4=0
62.24 + V5 x 6 = 44 x 6 x6
2+ 218.95
V5 = 158.11 KN
V4 + V5 = 48.5 x 6 = 264 KN
V4 = 105.89 K
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 90/293
90
Maximum Span moment,
X=105.89
44= 2.41m from the left support
Therefore, maximum moment =105.89 x 2.41
2- 62.24 = 65.36 KN-m
From beam 4-5, ΣM5=0
343.47 + V6 x 8.41 = 257.17 + 57.51 x 8.41 x8.41
2
V6 = 231.56 KN
V5 + V6 = 67.1 x 8.41 = 483.66 KN
V5 = 252.1 KN
Maximum Span moment,
X=231.56
57.51= 4.03m from the right support
Therefore, maximum moment = 231.56 x 4.032
- 257.17= 209.42 KN-m
Beam and column bending moments (KN-m):
Joint 4 Joint 5 Joint 6
Case Column Beam Max
span
moment
Beam Column Beam Max
span
moment
Beam Column
1 42.84 85.69 80.45 152.33 3.38 145.56 72 89.17 45.17
2 3.46 6.85 22.26 155.96 85.63 327.23 210.5 268.55 130.75
3 31.15 62.24 65.36 218.95 62.25 343.47 209.42 261.7 128.6
Max 42.84 85.69 80.45 218.95 85.63 343.47 210.5 268.55 130.75
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 91/293
91
Shear or support reaction (KN):
Case no. Joint 4 Joint 5 Joint 6
1 120.89 143.11 96.27 82.86
2 33.65 83.35 248.8 234.86
3 105.89 158.11 251.1 231.56
Maximum shear 120.89 158.11 251.1 234.86
Maximum column load 120.89 409.21 234.86
Frame 26-17-08
Roof:
Same as frame 20-11-02
Floor:
Slab = 120mm
Dead load = self weight + F.F
= (0.12 x 25) + 1 = 4 KN/m2
Live load = 3 KN/m2 for Beam 26-17
= 6 KN/m2 for Beam 17-08
Beam (26-17) (230mm X 600mm)
Dead load:
Self weight = 0.23 x 25 x (0.6-0.12) = 2.76 KN/m
Due to Slab = W x L= 4 x 3.05= 12.2 KN/m
Live load:
Due to Slab = 3 x 3.05= 9.15 KN/m
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5x (2.76+12.2+9.15)
= 36.2 KN/m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 92/293
92
Minimum load = 0.9 x D.L = 0.9 x (2.76+12.2) = 13.5 KN/m
Beam (17-08) (230mm X 600mm)
Dead load:
Self weight = 0.23 x 25 x (0.6-0.12) = 2.76 KN/m
Due to Slab = W x L= 4 x 3.05= 12.2 KN/m
Live load:
Due to Slab = 6 x 3.05= 18.3 KN/m
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5x (2.76+12.2+18.3)
= 50 KN/m
Minimum load = 0.9 x D.L = 0.9 x (2.76+12.2) = 13.5 KN/m
Case 1:
Maximum load on beam 26-17 and minimum load on beam 17-08
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 93/293
93
Calculation of distribution factors:
Joint Member K ΣK D.F
4 Column 1235.82 x 10
3.85 x 106
0.32
Beam 1.38 x 10 0.36
Column 1235.82 x 10 0.32
5 Beam 1.38 x 106
4.84 x 106
0.29
Column 1235.82 x 103 0.26
Beam 0.985 x 10 0.19
Column 1235.82 x 10 0.26
6 Beam 0.985 x 10
3.46 x 106
0.28
Column 1235.82 x 10 0.36
Column 1235.82 x 10 0.36
Calculation of moments:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 94/293
94
Calculation of support reactions:
From beam 4-5, ΣM4=0
73.1+ V5 x 6 = 36.2 x 6 x6
2+ 117.93
V5 = 116.07 KN
V4 + V5 = 46.2 x 6 = 217.2 KN
V4 = 101.13 KN
Maximum Span moment,
X=101.13
36.2= 2.8m from the left support
Therefore, maximum moment =101.13 x 2.8
2- 73.1 = 68.48 KN-m
From beam 4-5, ΣM5=0
97.78 + V6 x 8.41 = 54.2 + 13.5 x 8.41 x
8.41
2
V6 = 51.59KN
V5 + V6 = 13.5 x 8.41 = 113.54 KN
V5 = 61.95 KN
Maximum Span moment,
X= 51.5913.5
= 3.82m from the right support
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 95/293
95
Therefore, maximum moment =51.59 x 3.82
2- 54.2 = 44.34 KN-m
Case 2:
Minimum load on beam 26-17 and maximum load on beam 17-08
Distribution factors are same as calculated in case-1.
Calculation of moments:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 96/293
96
Calculation of support reactions:
From beam 4-5, ΣM4=0
1.84 + V5 x 6 = 13.5 x 6 x62
+ 126.71
V5 = 61.31 KN
V4 + V5 = 13.5 x 6 = 81 KN
V4 = 19.69 KN
Maximum Span moment,
X=19.69
13.5= 1.46m from the left support
Therefore, maximum moment =19.69 x 1.46
2- 1.84 = 12.54 KN-m
From beam 4-5, ΣM5=0
282.21 + V6
x 8.41 = 234.45 + 50 x 8.41 x8.41
2
V6 = 204.57 KN
V5 + V6 = 50 x 8.41 = 420.5 KN
V5 = 215.93 KN
Maximum Span moment,
X=204.57
50= 4.09m from the right support
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 97/293
97
Therefore, maximum moment =204.57 x 4.09
2- 234.45= 183.9 KN-m
Case 3:
Maximum load on both beams
Distribution factors are same as calculated in case 1.
Calculation of moments:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 98/293
98
Calculation of support reactions:
From beam 4-5, ΣM4=0
49.5 + V5 x 6 = 36.2 x 6 x6
2+ 185.08
V5 = 131.2 KN
V4 + V5 = 36.2 x 6 = 217.2 KN
V4 = 86 KN
Maximum Span moment,
X=86
36.2= 2.38m from the left support
Therefore, maximum moment =86 x 2.38
2- 49.5 = 52.84 KN-m
From beam 4-5, ΣM5=0
297.26 + V6 x 8.41 = 228.1 + 50 x 8.41 x
8.41
2
V6 = 202.03 KN
V5 + V6 = 50 x 8.41 = 420.5 KN
V5 = 218.47 KN
Maximum Span moment,
X= 202.0350
= 4.04m from the right support
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 99/293
99
Therefore, maximum moment =202.03 x 4.04
2- 228.1= 180 KN-m
Beam and column bending moments (KN-m):
Joint 4 Joint 5 Joint 6
Case Column Beam Max
span
moment
Beam Column Beam Max
span
moment
Beam Column
1 36.55 73.1 68.48 117.93 10.07 97.78 44.34 54.2 27.9
2 0.9 1.85 12.54 126.71 77.74 282.21 183.9 234.45 113.98
3 24.76 49.5 52.84 185.08 56.08 297.26 180 228.1 111.97
Max 36.55 73.1 68.48 185.08 77.74 297.26 183.9 234.45 113.98
Shear or support reaction (KN):
Case no. Joint 4 Joint 5 Joint 6
1 101.13 116.07 61.95 51.59
2 19.69 61.31 215.93 204.57
3 86 131.2 218.47 202.03
Maximum shear 101.13 131.2 218.47 204.57
Maximum column load 101.13 349.67 204.57
Frame 27-18-09
Roof:
Same as of roof frame 19-10-01
Floor:
Slab: 120mm
Dead load = self weight + F.F
= (0.12 x 25) + 1 = 4 KN/m2
Live load = 3 KN/m2 for Beam 27-18
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 100/293
100
= 6 KN/m2 for Beam 18-09
Beam (27-18) (230mm X 450mm)
Dead load:
Self weight = 0.23 x 25 x (0.45-0.12) = 1.9 KN/m
Due to Slab =W x L
2=
4 x 3.05
2= 6.1 KN/m
250mm thick wall = 0.25 x 20 x (3.35-0.3) = 15.25 KN/m
Live load:
Due to Slab =W x L
2=
3 x 3.05
2= 4.6KN/m
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5 x (1.9+6.1+15.25+4.6)
= 42 KN/m
Minimum load = 0.9 x D.L = 0.9 x (1.9+6.1+15.25) = 21 KN/m
Beam (18-09) (230mm X 450mm)
Dead load:
Self weight = 0.23 x 25 x (0.45-0.12) = 1.9 KN/m
Due to Slab =W x L
2=
4 x 3.05
2= 6.1 KN/m
250mm thick wall = 0.25 x 20 x (3.35-0.3) = 15.25 KN/m
Live load:
Due to Slab =W x L
2=
6 x 3.05
2= 9.15KN/m
Therefore, Maximum load = 1.5 x (D.L + L.L) = 1.5 x (1.9+6.1+15.25+9.15)
= 48.6 KN/m
Minimum load = 0.9 x D.L = 0.9 x (1.9+6.1+15.25) = 21KN/m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 101/293
101
Case 1:
Maximum load on beam 27-18 and minimum load on beam 18-09
Calculation of distribution factors:
Joint Member K ΣK D.F
4 Column 1235.82 x 10 3.05 x 10 0.4
Beam 582.18 x 10 0.2
Column 1235.82 x 103 0.4
5 Beam 582.18 x 10 3.47 x 10 0.17
Column 1235.82 x 10 0.36
Beam 415.35 x 10 0.11
Column 1235.82 x 10 0.36
6 Beam 415.35 x 10 2.89 x 10 0.14
Column 1235.82 x 10 0.43
Column 1235.82 x 10 0.43
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 102/293
102
Calculation of moments:
Calculation of support reactions:
From beam 4-5, ΣM4=0
101.22 + V5 x 6 = 42 x 6 x6
2+ 137.6
V5 = 132.06 KN
V4 + V5 = 42 x 6 = 252 KN
V4 = 119.94 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 103/293
103
Maximum Span moment,
X=119.94
42= 2.86m from the left support
Therefore, maximum moment =119.94 x 2.86
2- 101.22 = 70.3 KN-m
From beam 4-5, ΣM5=0
133.13 + V6 x 8.41 = 106.52 + 21 x 8.41 x8.41
2
V6 = 85.14 KN
V5 + V6 = 21 x 8.41 = 176.61 KN
V5 = 91.47 KN
Maximum Span moment,
X=85.14
21= 4.05m from the right support
Therefore, maximum moment = 85.14 x 4.052
- 106.52 = 65.89 KN-m
Case 2:
Minimum load on beam 27-18 and maximum load on beam 18-09
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 104/293
104
Distribution factors are same as calculated in case-1.
Calculation of moments:
Calculation of support reactions:
From beam 4-5, ΣM4=0
34.07 + V5 x 6 = 21 x 6 x6
2+ 108.08
V5 = 75.34 KN
V4 + V5 = 21 x 6 = 126 KN
V4 = 50.66 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 105/293
105
Maximum Span moment,
X=50.66
21= 2.41m from the left support
Therefore, maximum moment =50.66 x 2.41
2- 34.07 = 26.98 KN-m
From beam 4-5, ΣM5=0
280.96 + V6 x 8.41 = 257.96 + 48.6 x 8.41 x8.41
2
V6 = 201.63 KN
V5 + V6 = 48.6 x 8.41 = 408.73 KN
V5 = 207.1 KN
Maximum Span moment,
X=201.63
48.6= 4.15m from the right support
Therefore, maximum moment = 201.63 x 4.152
- 257.96= 160.42 KN-m
Case 3:
Maximum load on both beams
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 106/293
106
Distribution factors are same as calculated in case 1.
Calculation of moments:
Calculation of support reactions:
From beam 4-5, ΣM4=0
89.24 + V5 x 6 = 42 x 6 x6
2+ 166.05
V5 = 138.8 KN
V4 + V5 = 42 x 6 = 252 KN
V4 = 113.2 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 107/293
107
Maximum Span moment,
X=113.2
42= 2.7m from the left support
Therefore, maximum moment =113.2 x 2.7
2- 89.24 = 63.58 KN-m
From beam 4-5, ΣM5=0
288.45 + V6 x 8.41 = 254.55 + 48.6 x 8.41 x8.41
2
V6 = 200.33 KN
V5 + V6 = 48.6 x 8.41 = 408.73 KN
V5 = 208.4 KN
Maximum Span moment,
X=200.33
48.6= 4.12m from the right support
Therefore, maximum moment = 200.33 x 4.122
- 254.55= 158.33 KN-m
Beam and column bending moments (KN-m):
Joint 4 Joint 5 Joint 6
Case Column Beam Max
span
moment
Beam Column Beam Max
span
moment
Beam Column
1 50.61 101.22 70.3 137.6 2.24 133.12 65.89 106.09 53.26
2 17.04 34.07 26.98 108.08 86.44 280.96 160.42 257.96 128.22
3 44.62 89.24 63.58 166.06 61.2 288.45 158.33 254.55 126.86
Max 50.61 101.22 70.3 166.06 86.44 288.45 160.42 257.96 128.22
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 108/293
108
Shear or support reaction (KN):
Case no. Joint 4 Joint 5 Joint 6
1 119.94 132.06 91.47 85.14
2 50.66 75.34 207.28 201.63
3 113.2 138.8 208.4 200.33
Maximum shear 119.94 138.8 208.4 200.33
Maximum column load 119.94 347.2 200.33
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 109/293
109
4. DESIGN OF BEAMS
Bending moment diagram for entire building:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 110/293
110
1. Longitudinal beams
a. Beam 23-24
Roof :
Section: 230mm x 300mm (b x D)
Cover: 25mm
Effective depth (d‟) = 300 – 25 = 275mm
Concrete: M20 Steel: Fe415
Loads:
Slab: 110mm thick
Dead load = self weight + floor finish
= 0.11 x 25 +2.5 = 5.25 KN/m2
Live load = 1.5 KN/m2
Acting on beam:
Dead load:
Self weight = 0.23 x 25 x (0.3 – 0.11) = 1.1 KN/m
Slab =5.25 x 3.05
6= 2.67 KN/m
Parapet wall (250mm wall including plastering of 1m height)
= 20 x 0.25 x 1 = 5 KN/m
Live load:
Slab =1.5 x 3.05
6= 0.76 KN/m
Therefore, Total load (W) = 5 + 2.67 + 1.1 + 0.76 = 9.53 KN/m
Factored load (Wu) = 1.5 x 9.53 = 14.3 KN/m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 111/293
111
Maximum load on column removing the triangular load = 1.5 (1.1 +5)
= 9.15 KN/m
Shear on column =column load x l
2
=9.15 x 3.05
2
= 13.96 KN (from each side)
Design moment:
Mu =14.3 x (3.05)2
12= 11.09 x 106 N-mm = 11.09 KN-m
Calculation of Ast:
From IS456-2000, P96a, clause G-1.1 (b), we have
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
11.09 x 106 = 0.87 x 415 x Ast x 275 x (1-415 x Ast
20 x 230 x 275)
Ast = 116.12 mm2
No. of 10mm diameter bars =
4 x 116.12
π x 102 = 1.5 say 2 bars
Therefore, provided Ast = 2 xπ4
x 102 = 157.08 mm2
Design of shear reinforcement:
Vu =Wu x Lx
2=
14.3 x 3.05
2= 21.81KN
Nominal shear stress, v =Vu
b x d=
21.81 x 103
230 x 275= 0.35 N/mm2
Ast = 157.08 mm2
Consider Pt =100 xAst
b x d=
100 x 157.08
230 x 275= 0.25
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 112/293
112
From IS 456-2000, Table 19:
Pt c
0.25 0.36
Therefore, c = 0.36 N/mm2
v approximately equals to c
Therefore, provide minimum shear reinforcement.
Assuming 8mmφ- 2legged stirrups
Asv = 2 x π x 82
4= 100.53mm2
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 300
0.87 x 415= 76.44mm2 <100.5mm2 (safe)
Provide 8mm dia stirrups @ 300mm c/c.
Floor:
Section: 230mm x 450mm (b x D)
Cover: 25mm
Effective depth (d‟) = 450 – 25 = 425mm
Concrete: M20 Steel: Fe415
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 113/293
113
Loads:
Slab: 120mm thick
Dead load = self weight + floor finish
= 0.12 x 25 +1 = 4 KN/m2
Live load = 10 KN/m2
Acting on beam:
Dead load:
Self weight = 0.23 x 25 x (0.45 – 0.12) = 1.9 KN/m
Slab =4 x 3.05
6= 2.03 KN/m
Parapet wall (250mm wall including plastering of 2.2m height)
= 20 x 0.25 x (3.35-0.3) = 15.25 KN/m
Live load:
Slab =10 x 3.05
6= 5.08 KN/m
Therefore, Total load (W) = 1.9 + 2.03 + 15.25 + 5.08 = 24.26 KN/m
Factored load (Wu) = 1.5 x 24.26 = 36.39 KN/m
Maximum load on column removing the triangular load = 1.5 (1.9 +5.08)
= 25.725 KN/m
Shear on column =column load x l
2=
25.725 x 3.05
2
= 39.23 KN (from each side)
Design moment:
Mu =36.39 x (3.05)2
12= 28.21 x 106 N-mm = 28.21 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 114/293
114
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
28.21 x 106 = 0.87 x 415 x Ast x 425 x (1-415 x Ast
20 x 230 x 425)
Ast = 191.64 mm2
No. of 10mm diameter bars =4 x 191.64
π x 102 = 2.33 say 3 bars
Therefore, provided Ast = 3 xπ
4
x 102 = 235.62 mm2
Design of shear reinforcement:
Vu =Wu x Lx
2=
36.39 x 3.05
2= 55.5KN
Nominal shear stress, v =Vu
b x d=
55.5 x 103
230 x 425= 0.57 N/mm2
Ast = 235.62 mm2
Consider Pt =100 xAst
b x d=
100 x 235.62
230 x 425= 0.24
From IS 456-2000, Table 19:
Pt c
0.15 0.28
0.24 ?
0.25 0.36
Therefore, c = 0.28 +0.36-0.28
0.25-0.15x (0.24-0.15) = 0.352 N/mm2
Therefore, v > c,
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 115/293
115
From IS456-2000(Clause 40.4, P72)
When v exceeds c, shear reinforcement shall be provided
Shear reinforcement shall be provided to carry a shear equal to Vu - c bd. The strength of
shear reinforcement Vus shall be calculated as follows:
Vus =0.87 x f y x Asv x d
sv
Stirrups are designed for shear Vus = Vu - c bd
= (55.5 x 103) – (0.32 x 230 x 425)
= 24220N
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
Therefore,
Spacing of stirrups, sv =
0.87 x f y x Asv x d
Vus =
0.87 x 415 x 100.53 x 425
24220
=636.9mm
From IS456-2000, (clause 26.5.1.5, P47)
The maximum spacing of shear reinforcement measured along the axis of the member shall
not be exceed 0.75d for vertical stirrups where d is the effective depth of the section under
consideration. In no case shall the spacing exceed 300mm.
Provide spacing = 300mm
Therefore, Vus =0.87 x f y x Asv x d
sv=
0.87 x 415 x 100.53 x 425
300= 51419.83N
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv
≥0.4
0.87 x f y
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 116/293
116
Asv =0.4 x 230 x 300
0.87 x 415= 76.44mm2 <100.5mm2 (safe)
Provide 8mm dia stirrups @ 300mm c/c.
b. Beam 14-15
Roof :
Section: 230mm x 300mm (b x D)
Cover: 25mm
Effective depth (d‟) = 300 – 25 = 275mm
Concrete: M20 Steel: Fe415
Loads:
Slab: 110mm thick
Dead load = self weight + floor finish
= 0.11 x 25 +2.5 = 5.25 KN/m2
Live load = 1.5 KN/m2
Acting on beam:
Dead load:
Self weight = 0.23 x 25 x (0.3 – 0.11) = 1.1 KN/m
Slab = 2 x
5.25 x 3.05
6 = 5.34 KN/m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 117/293
117
Live load:
Slab = 2 x1.5 x 3.05
6= 1.53 KN/m
Therefore, Total load (W) = 1.1 + 5.34 + 1.53 = 7.97 KN/m
Factored load (Wu) = 1.5 x 7.97 = 11.96 KN/m
Maximum load on column removing the triangular load = 1.5 (1.1)
= 1.65 KN/m
Shear on column =column load x l
2=
1.65 x 3.05
2= 2.52 KN (from each side)
Design moment:
Mu =11.96 x (3.05)2
12= 9.27 x 106 N-mm = 9.27 KN-m
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
9.27 x 106 = 0.87 x 415 x Ast x 275 x (1-415 x Ast
20 x 230 x 275)
Ast = 96.41 mm2
No. of 8mm diameter bars =4 x 96.41
π x 82 = 1.91 say 2 bars
Therefore, provided Ast = 2 xπ4 x 82 = 100.53 mm2
Design of shear reinforcement:
Vu =Wu x Lx
2=
11.96 x 3.05
2= 18.239KN
Nominal shear stress, v =Vu
b x d=
18.239 x 103
230 x 275= 0.29 N/mm2
Ast = 100.53 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 118/293
118
Consider Pt =100 xAst
b x d=
100 x 100.53
230 x 275= 0.15
From IS 456-2000, Table 19:
Pt c
0.15 0.28
Therefore, c = 0.28 N/mm2
v approximately equals to c
Therefore, provide minimum shear reinforcement.
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
Provide spacing = 300mm
Therefore, Vus =0.87 x f y x Asv x d
sv=
0.87 x 415 x 100.53 x 275
300= 33371.66KN
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 300
0.87 x 415= 76.44mm2 <100.5mm2 (safe)
Provide 8mm dia stirrups @ 300mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 119/293
119
Floor:
Section: 230mm x 450mm (b x D)
Cover: 25mm
Effective depth (d‟) = 450 – 25 = 425mm
Concrete: M20 Steel: Fe415
Loads:
Slab: 120mm thick
Dead load = self weight + floor finish + wall
= 0.12 x 25 +1 + 1.5 = 5.5 KN/m2
Live load = 10 KN/m2 + 5 KN/m2
Acting on beam:
Dead load:
Self weight = 0.23 x 25 x (0.45 – 0.12) = 1.9 KN/m
Slab =5.5 x 3.05
6+
4 x 3.05
6= 4.83 KN/m
Internal wall (150mm wall including plastering of 2.2m height)
= 20 x 0.15 x 2.2 = 6.6 KN/m
Live load:
Slab =15 x 3.05
6= 7.625 KN/m
Therefore, Total load (W) = 1.9 + 4.83 + 6.6 + 7.625 = 20.955 KN/m
Factored load (Wu) = 1.5 x 20.955 = 31.4325 KN/m
Maximum load on column removing the triangular load = 1.5 (1.9 +6.6)
= 12.75 KN/m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 120/293
120
Shear on column =column load x l
2=
12.75 x 3.05
2
= 19.44 KN (from each side)
Design moment:
Mu =31.4325 x (3.05)2
12= 24.37 x 106 N-mm = 24.37 KN-m
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
24.37 x 106 = 0.87 x 415 x Ast x 425 x (1-415 x Ast
20 x 230 x 425)
Ast = 164.5 mm2
No. of 10mm diameter bars =4 x 164.5
π x 102 = 2.1 say 3 bars
Therefore, provided Ast = 3 xπ
4x 102 = 235.62 mm2
Design of shear reinforcement:
Vu =Wu x Lx
2=
20.955 x 3.05
2= 31.96KN
Nominal shear stress, v =Vu
b x d=
31.96 x 103
230 x 425= 0.33 N/mm2
Ast = 235.62 mm2
Consider Pt =100 xAst
b x d=
100 x 235.62
230 x 425= 0.24
From IS 456-2000, Table 19:
Pt c
0.15 0.28
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 121/293
121
0.24 ?
0.25 0.36
Therefore, c = 0.28 +0.36-0.28
0.25-0.15 x (0.24-0.15) = 0.352 N/mm2
Therefore, v approximately equals to c,
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 300
0.87 x 415= 76.44mm2 <100.5mm2 (safe)
Provide 8mm dia stirrups @ 300mm c/c.
c. Beam 7-8
Roof :
Section: 230mm x 300mm (b x D)
Cover: 25mm
Effective depth (d‟) = 300 – 25 = 275mm
Concrete: M20 Steel: Fe415
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 122/293
122
Loads:
Slab: 110mm thick
Dead load = self weight + floor finish
= 0.11 x 25 +2.5 = 5.25 KN/m2
Live load = 1.5 KN/m2
Acting on beam:
Dead load:
Self weight = 0.23 x 25 x (0.3 – 0.11) = 1.1 KN/m
Slab =5.25 x 3.05
6= 2.67 KN/m
Parapet wall (250mm wall including plastering of 1m height)
= 20 x 0.25 x 1 = 5 KN/m
Live load:
Slab =1.5 x 3.05
6= 0.76 KN/m
Therefore, Total load (W) = 5 + 2.67 + 1.1 + 0.76 = 9.53 KN/m
Factored load (Wu) = 1.5 x 9.53 = 14.3 KN/m
Maximum load on column removing the triangular load = 1.5 (1.1 +5)
= 9.15 KN/m
Shear on column =column load x l
2=
9.15 x 3.05
2= 13.96 KN (from each side)
Design moment:
Mu =14.3 x (3.05)2
12= 11.09 x 106 N-mm = 11.09 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 123/293
123
Calculation of Ast:
From IS456-2000, P96a, clause G-1.1 (b), we have
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d )
11.09 x 106 = 0.87 x 415 x Ast x 275 x (1-415 x Ast
20 x 230 x 275)
Ast = 116.12 mm2
No. of 10mm diameter bars =4 x 116.12
π x 102 = 1.5 say 2 bars
Therefore, provided Ast = 2 xπ4
x 102 = 157.08 mm2
Design of shear reinforcement:
Vu =Wu x Lx
2=
14.3 x 3.05
2= 21.81KN
Nominal shear stress, v =Vu
b x d=
21.81 x 103
230 x 275= 0.35 N/mm2
Ast = 157.08 mm2
Consider Pt =100 xAst
b x d=
100 x 157.08
230 x 275= 0.25
From IS 456-2000, Table 19:
Pt c
0.25 0.36
Therefore, c = 0.36 N/mm2
v approximately equals to c
Therefore, provide minimum shear reinforcement.
Assuming 8mmφ- 2legged stirrups
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 124/293
124
Asv =2 x π x 82
4= 100.53mm2
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 300
0.87 x 415= 76.44mm2 <100.5mm2 (safe)
Provide 8mm dia stirrups @ 300mm c/c.
Floor:
Section: 230mm x 450mm (b x D)
Cover: 25mm
Effective depth (d‟) = 450 – 25 = 425mm
Concrete: M20 Steel: Fe415
Loads:
Slab: 120mm thick
Dead load = self weight + floor finish + wall
= 0.12 x 25 +1 + 1.5 = 5.5 KN/m2
Live load = 6 KN/m2
Acting on beam:
Dead load:
Self weight = 0.23 x 25 x (0.45 – 0.12) = 1.9 KN/m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 125/293
125
Slab =5.5 x 3.05
6= 2.8 KN/m
External wall (250mm wall including plastering)
= 20 x 0.25 x (3.35 – 0.3) = 15.25 KN/m
Live load:
Slab =6 x 3.05
6= 3.05 KN/m
Therefore, Total load (W) = 1.9 + 2.8 + 15.25 + 3.05 = 23 KN/m
Factored load (Wu) = 1.5 x 23 = 34.5 KN/m
Maximum load on column removing the triangular load = 1.5 (1.9 +15.25)
= 25.73 KN/m
Shear on column =column load x l
2=
25.73 x 3.05
2
= 39.24 KN (from each side)
Design moment:
Mu =34.5 x (3.05)2
12= 26.75 x 106 N-mm = 26.75 KN-m
Calculation of Ast:
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
26.75 x 106 = 0.87 x 415 x Ast x 425 x (1-415 x Ast
20 x 230 x 425)
Ast = 181.3 mm2
No. of 10mm diameter bars =4 x 181.3
π x 102 = 2.31 say 3 bars
Therefore, provided Ast = 3 xπ
4
x 102 = 235.62 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 126/293
126
Design of shear reinforcement:
Vu =Wu x Lx
2=
34.5 x 3.05
2= 52.61KN
Nominal shear stress, v =Vu
b x d=
52.61 x 103
230 x 425= 0.54 N/mm2
Ast = 235.62 mm2
Consider Pt =100 xAst
b x d=
100 x 235.62
230 x 425= 0.24
From IS 456-2000, Table 19:
Pt c
0.15 0.28
0.24 ?
0.25 0.36
Therefore, c = 0.28 +0.36-0.28
0.25-0.15x (0.24-0.15) = 0.352 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (52.61 x 103) – (0.35 x 230 x 425)
= 18397.5N
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 425
18397.5
= 838.48mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 127/293
127
Provide spacing = 300mm
Therefore, Vus =0.87 x f y x Asv x d
sv=
0.87 x 415 x 100.53 x 425
300= 51419.83N
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 300
0.87 x 415= 76.44mm2 <100.5mm2 (safe)
Provide 8mm dia stirrups @ 300mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 128/293
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 129/293
129
ROOF: (section 230mm x 300mm, d' = 25mm)
From analysis of frames the moments acting on the supports are:
At left support (Ast1):
Moment due to external load (Mu) = 64.65 KN-m
From IS456-2000, P96, clause G-1.1 (c), moment of resistance of the section is given by
Mu‟Limit = 0.36 xxumax
dx (1- 0.42 x
xumax
d) x b x d2 x f ck
For Fe 415,xumax
d= 0.48
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (275)2 = 48 x 106 N-mm = 48 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
25
275= 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(64.65 - 48) x 106
353 x (275 - 25)=188.67 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 - f y x Ast1
f ck x b x d)
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 130/293
130
48 x 106 = 0.87 x 415 x Ast1 x 275 x (1 -415 x Ast1
20 x 230 x 275)
Ast1 = 602.55 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
353 x 188.67
0.87 x 415=184.46 mm2
Ast = Ast1 + Ast2 = 602.55 + 184.46 = 787.01 mm2
Between the support:
Span moment = 39.24 KN-m
For T-beam, from IS456-2000, P37, clause 23.1.2 (a)
Effective width of flange (bf ) =l0
6+ (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 6000 = 4200 mm
Therefore, bf =4200
6+ (6 x 110) + 230
= 1590 mm
Therefore Mu‟limit = 0.36 x f ck x bf x Df x(d – 0.42Df )
= 0.36 x 20 x 1590 x 110 x (275 – 0.42 x 110)
= 288.12 KN-m
Mu < < Mu‟limit
Ast:
39.24 x 106 = 0.87 x 415 x Ast2 x 275 x (1-415 x Ast2
20 x 230 x 275)
Ast2 = 466.65 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 131/293
131
At right support (Ast3):
Moment due to external load (Mu) = 86.09 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (275)2 = 48 x 106 N-mm = 48 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
25
275= 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(86.09 - 48) x 106
353 x (275 - 25)=431.62 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
48 x 106 = 0.87 x 415 x Ast1 x 275 x (1 -415 x Ast1
20 x 230 x 275)
Ast1 = 602.55 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
353 x 431.62
0.87 x 415=422 mm2
Ast3 = Ast1 + Ast2 = 602.55 + 422 = 1024.55 mm2
At support (Ast4):
Moment due to external load (Mu) = 145.76 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (275)2 = 48 x 106 N-mm = 48 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 132/293
132
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
25
275= 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(145.76 - 48) x 106
353 x (275 - 25)=1107.76 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 - f y x Ast1f ck x b x d )
48 x 106 = 0.87 x 415 x Ast1 x 275 x (1 -415 x Ast1
20 x 230 x 275)
Ast1 = 602.55 mm2
To find Ast2:
Ast2 = f sc x Asc
0.87 x f y= 353 x 1107.76
0.87 x 415=1083.06 mm2
Ast4 = Ast1 + Ast2 = 602.55 + 1083 = 1685.61 mm2
Between the support (Ast5):
Span moment = 77.97 KN-m
Effective width of flange (bf ) =
l0
6 + (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 8410 = 5887 mm
Therefore, bf =5887
6+ (6 x 110) + 230
= 1871.16 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 133/293
133
Therefore Mu‟limit = 0.36 x f ck x bf x Df x(d – 0.42Df )
= 0.36 x 20 x 1871.16 x 110 x (275 – 0.42 x 110)
= 339.07 KN-m
Mu < Mu‟limit
Ast:
77.97 x 106 = 0.87 x 415 x Ast5 x 275 x (1-415 x Ast5
20 x 230 x 275)
Ast5 = 1411.66 mm2
At right end (Ast6):
Moment due to external load (Mu) = 136.01 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (275)2 = 48 x 106 N-mm = 48 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
25
275= 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(136.01 - 48) x 106
353 x (275 - 25)=997.28 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
48 x 106 = 0.87 x 415 x Ast1 x 275 x (1 -415 x Ast1
20 x 230 x 275)
Ast1
= 602.55 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 134/293
134
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
353 x 997.28
0.87 x 415=975.05 mm2
Ast6 = Ast1 + Ast2 = 602.55 + 975.05 = 1577.6 mm2
Design of shear reinforcement:
At left support:
End shear = (Vu) = 71.54 KN
Nominal shear stress, v =Vu
b x d=
71.54 x 103
230 x 275= 1.13 N/mm2
Ast = 787.01 mm2
Consider Pt =100 xAst
b x d=
100 x 787.01
230 x 275= 1.25
From IS 456-2000, Table 19:
Pt c
1.25 0.67
Therefore, c = 0.67 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (71.54 x 103) – (0.67 x 230 x 275)
= 29162.5N
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 135/293
135
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 275
29162.5
= 342.27mm
Provide spacing = 300mm
Therefore, Vus = 0.87 x f y x Asv x dsv= 0.87 x 415 x 100.53 x 275300 = 33261.73N
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 300
0.87 x 415= 76.44mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 300mm c/c.
At middle support:
End shear = (Vu) = 77.92 KN
Nominal shear stress, v =Vu
b x d=
77.92 x 103
230 x 275= 1.23 N/mm2
Ast = 1024.55 mm2
Consider Pt =100 xAst
b x d=
100 x 1024.55
230 x 275= 1.62
From IS 456-2000, Table 19:
Pt c
1.5 0.72
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 136/293
136
1.62 ?
1.75 0.75
Therefore, c = 0.72 +0.75-0.72
1.75-1.5 x (1.62-1.5) = 0.734 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (77.92 x 103) – (0.734 x 230 x 275)
= 31494.5N
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 275
31494.5
= 316.93mm
Provide spacing = 300mm
Therefore, Vus =0.87 x f y x Asv x d
sv=
0.87 x 415 x 100.53 x 275
300= 33261.73N
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 300
0.87 x 415= 76.44mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 300mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 137/293
137
At middle support:
End shear = (Vu) = 104.84 KN
Nominal shear stress, v =Vu
b x d =104.84 x 103
230 x 275 = 1.66 N/mm2
Ast = 1685.61 mm2
Consider Pt =100 xAst
b x d=
100 x 1685.61
230 x 275= 2.67
From IS 456-2000, Table 19:
Pt c
2.67 0.82
Therefore, c = 0.82 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (104.84 x 103) – (0.82 x 230 x 275)
= 52975N
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 275
52975
= 188.42mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 138/293
138
Asv =0.4 x 230 x 180
0.87 x 415= 45.87mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 180mm c/c.
At right support:
End shear = (Vu) = 102.63 KN
Nominal shear stress, v =Vu
b x d=
102.63 x 103
230 x 275= 1.63 N/mm2
Ast = 1577.6 mm2
Consider Pt = 100 xAst b x d = 100 x 1577.6230 x 275 = 2.5
From IS 456-2000, Table 19:
Pt c
2.5 0.82
Therefore, c = 0.82 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (102.63 x 103) – (0.82 x 230 x 275)
= 50765N
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 275
50765
= 196.62mm < 300mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 139/293
139
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 190
0.87 x 415= 48.41mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 190mm c/c.
Reinforcement for roof 19-10-01:
FLOOR : (section: 230mm x 450mm, d‟= 25mm)
The moments acting on the beam are:
At left support (Ast1):
Moment due to external load (Mu) = 106.54 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (425)2 = 114.66 x 106 N-mm = 114.66 KN-m
Mu < Mu‟limit , therefore design as singly reinforced beam.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 140/293
140
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
106.54 x 106 = 0.87 x 415 x Ast1 x 425 x (1 -415 x Ast1
20 x 230 x 425)
Ast1 = 546 mm2
Between the supports (Ast2):
Span moment = 73.58 KN-m
Effective width of flange (bf ) = l06 + (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 6000 = 4200 mm
Therefore, bf =4200
6+ (6 x 120) + 230
= 1650 mm
Therefore Mu‟limit = 0.36 x f ck x bf x Df x (d – 0.42Df )
= 0.36 x 20 x 1650 x 120 x (425 – 0.42 x 120)
= 534.03 KN-m
Mu < Mu‟limit
Ast:
73.58 x 106 = 0.87 x 415 x Ast2 x 425 x (1-415 x Ast2
20 x 230 x 425)
Ast2 = 852.07 mm2
At right support (Ast3):
Moment due to external load (Mu) = 169.53 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 141/293
141
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (425)2 = 114.66 x 106 N-mm = 114.66 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
25
425= 0.05
Therefore, f sc = 355 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')
=(169.53 - 114.66) x 106
353 x (425 - 25)
=386.84 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
114.66 x 106 = 0.87 x 415 x Ast1 x 425 x (1 -415 x Ast1
20 x 230 x 425)
Ast1 = 932 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
353 x 386.84
0.87 x 415= 380.36 mm2
Ast3 = Ast1 + Ast2 = 932 + 380.6 = 1312.36 mm2
At support (Ast4):
Moment due to external load (Mu) = 277.32 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (425)2 = 114.66 x 106 N-mm = 114.66 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d =25
425 = 0.05
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 142/293
142
Therefore, f sc = 355 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d') =(277.32 -11 4.66) x 106
353 x (425 - 25) =1145.5 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
114.66 x 106 = 0.87 x 415 x Ast1 x 425 x (1 -415 x Ast1
20 x 230 x 425)
Ast1 = 932 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
355 x 1145.5
0.87 x 415=1126.31 mm2
Ast4 = Ast1 + Ast2 = 923 + 1126.31 = 2058.31 mm2
Between the supports (Ast5):
Span moment = 153.57 KN-m
Effective width of flange (bf ) =l0
6+ (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 8410 = 5887 mm
Therefore, bf =
5887
6 + (6 x 120) + 230
= 1931.67 mm
Therefore Mu‟limit = 0.36 x f ck x bf x Df x (d – 0.42Df )
= 0.36 x 20 x 1871.16 x 120 x (425 – 0.42 x 120)
= 625.2 KN-m
Mu < Mu‟limit
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 143/293
143
Ast:
153.57 x 106 = 0.87 x 415 x Ast5 x 425 x (1-415 x Ast5
20 x 230 x 425)
Ast5 = 1442.53 mm2
At right end (Ast6):
Moment due to external load (Mu) = 246.62 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (425)2 = 114.66 x 106 N-mm = 114.66 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
25
425= 0.05
Therefore, f sc = 355 N/mm2
Area of steel in compression (Asc):
Asc = Mu - Mu‟limitf sc x (d - d')
= (246.62 - 114.66) x 106
355 x (425 - 25)=929.29 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
114.66 x 106 = 0.87 x 415 x Ast1 x 425 x (1 -415 x Ast1
20 x 230 x 425)
Ast1 = 932 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
355 x 929.29
0.87 x 415=913.72 mm2
Ast6 = Ast1 + Ast2 = 932 + 913.72 = 1845.72 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 144/293
144
Design of shear reinforcement:
At left support:
End shear = (Vu) = 125.6 KN
Nominal shear stress, v =Vu
b x d=
125.6 x 103
230 x 425= 1.29 N/mm2
Ast = 546 mm2
Consider Pt =100 xAst
b x d=
100 x 546
230 x 425= 0.56
From IS 456-2000, Table 19:
Pt c
0.5 0.48
0.56 ?
0.75 0.56
Therefore, c = 0.48 +0.56-0.48
0.75-0.5x (0.56-0.5) = 0.5 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (125.6 x 103) – (0.5 x 230 x 425)
= 76725N
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 145/293
145
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 425
76725
= 184.87mm <300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asvb x Sv
≥ 0.40.87 x f y
Asv =0.4 x 230 x 180
0.87 x 415= 45.86mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 180mm c/c.
At middle support:
End shear = (Vu) = 144.35 KN
Nominal shear stress, v =Vu
b x d=
144.35 x 103
230 x 425= 1.48 N/mm2
Ast = 1312.16 mm2
Consider Pt =100 xAst
b x d=
100 x 1312.16
230 x 425= 1.34
From IS 456-2000, Table 19:
Pt c
1.25 0.67
1.34 ?
1.5 0.72
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 146/293
146
Therefore, c = 0.67 +0.72-0.67
1.5-1.25x (1.34-1.25) = 0.69 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (144.32 x 103) – (0.69 x 230 x 425)
= 78827.5N
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4
= 100.53mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 425
78827.5
= 195.7mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 190
0.87 x 415= 48.41mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 190mm c/c.
At middle support:
End shear = (Vu) = 199.64 KN
Nominal shear stress, v =Vu
b x d=
199.64 x 103
230 x 425= 2.04 N/mm2
Ast = 2058.31 mm2
Consider Pt =100 xAst
b x d=
100 x 2058.31
230 x 425= 2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 147/293
147
From IS 456-2000, Table 19:
Pt c
2.00 0.79
Therefore, c = 0.79 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (199.64 x 103) – (0.79 x 230 x 425)
= 122417.5N
Assuming 10mmφ- 2legged stirrups
Asv =2 x π x 102
4= 157.07mm2
Therefore,
Spacing of stirrups, sv =
0.87 x f y x Asv x d
Vus =
0.87 x 415 x 157.07 x 425
122417.5
= 196.9mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =
0.4 x 230 x 190
0.87 x 415 = 48.41mm2
<157.07mm2
(safe)
Therefore, provide 10mm dia stirrups @ 190mm c/c.
At right support:
End shear = (Vu) = 192.85 KN
Nominal shear stress, v =Vu
b x d=
192.85 x 103
230 x 425= 1.97 N/mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 148/293
148
Ast = 1845.72 mm2
Consider Pt =100 xAst
b x d=
100 x1845.72
230 x 425= 1.89
From IS 456-2000, Table 19:
Pt c
1.75 0.75
1.89 ?
2 0.79
Therefore, c = 0.75 +0.79-0.75
2-1.75x (1.89-1.75) = 0.77 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (192.85 x 103) – (0.77 x 230 x 425)
= 117582.5N
Assuming 10mmφ- 2legged stirrups
Asv =2 x π x 102
4= 157.07mm2
Therefore,
Spacing of stirrups, sv =
0.87 x f y x Asv x d
Vus =
0.87 x 415 x 157.07 x 425
117582.5
= 204.98mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 200
0.87 x 415 = 50.96mm2 <157.07mm2 (safe)
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 149/293
149
Therefore, provide 10mm dia stirrups @ 200mm c/c.
Reinforcement for floor 19-10-01:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 150/293
150
b. Beam 20-11 and Beam 11-02
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 151/293
151
ROOF (section: 230mm x 450mm, d‟ = 25mm)
The moments acting on the beam are:
At left support (Ast1):
Moment due to external load (Mu) = 68.42 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (425)2 = 114.66 x 106 N-mm = 114.66 KN-m
Mu < Mu‟limit , therefore design as singly reinforced beam.
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
68.42 x 106 = 0.87 x 415 x Ast1 x 425 x (1 -415 x Ast1
20 x 230 x 425)
Ast1 = 498.67 mm2
Between the supports (Ast2):
Span moment = 59.13 KN-m
Effective width of flange (bf ) =l0
6+ (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 6000 = 4200 mm
Therefore, bf =4200
6+ (6 x 110) + 230 = 1590 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 152/293
152
Therefore Mu‟limit = 0.36 x f ck x bf x Df x (d – 0.42Df )
= 0.36 x 20 x 1590 x 110 x (425 – 0.42 x 110)
= 477.02 KN-m
Mu < Mu‟limit
Ast:
59.13 x 106 = 0.87 x 415 x Ast2 x 425 x (1-415 x Ast2
20 x 230 x 425)
Ast2 = 423.4 mm2
At right support (Ast3):
Moment due to external load (Mu) = 140.51 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (425)2 = 114.66 x 106 N-mm = 114.66 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
25
425= 0.05
Therefore, f sc = 355 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(140.51 - 114.66) x 106
353 x (425 - 25)=181.97 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
114.66 x 106 = 0.87 x 415 x Ast1 x 425 x (1 -415 x Ast1
20 x 230 x 425)
Ast1 = 932 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 153/293
153
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
355 x 181.97
0.87 x 415= 178.92 mm2
Ast3 = Ast1 + Ast2 = 932 + 178.92 = 1110.4 mm2
At support (Ast4):
Moment due to external load (Mu) = 199.51 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (425)2 = 114.66 x 106 N-mm = 114.66 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
25
425= 0.05
Therefore, f sc = 355 N/mm2
Area of steel in compression (Asc):
Asc = Mu - Mu‟limitf sc x (d - d')
= (199.51 -11 4.66) x 106
353 x (425 - 25)=597.46 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
114.66 x 106 = 0.87 x 415 x Ast1 x 425 x (1 -415 x Ast1
20 x 230 x 425)
Ast1 = 932 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
355 x 597.46
0.87 x 415=587.45 mm2
Ast4 = Ast1 + Ast2 = 923 + 587.45 = 1518.93 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 154/293
154
Between the supports (Ast5):
Span moment = 118.5 KN-m
Effective width of flange (bf ) =l0
6 + (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 8410 = 5887 mm
Therefore, bf =5887
6+ (6 x 110) + 230
= 1871.17 mm
Therefore Mu‟limit = 0.36 x f ck x bf x Df x (d – 0.42Df )
= 0.36 x 20 x 1871.16 x 110 x (425 – 0.42 x 110)
= 561.37 KN-m
Mu < Mu‟limit
Ast:
118.5 x 106 = 0.87 x 415 x Ast5 x 425 x (1- 415 x Ast5
20 x 230 x 425)
Ast5 = 973.38 mm2
At right end (Ast6):
Moment due to external load (Mu) = 158.81 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (425)2 = 114.66 x 106 N-mm = 114.66 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
25
425= 0.05
Therefore, f sc = 355 N/mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 155/293
155
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(158.81 - 114.66) x 106
355 x (425 - 25)=310.85 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
114.66 x 106 = 0.87 x 415 x Ast1 x 425 x (1 -415 x Ast1
20 x 230 x 425)
Ast1 = 932 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
355 x 310.85
0.87 x 415=305.64 mm2
Ast6 = Ast1 + Ast2 = 932 + 305.64 = 1237.12 mm2
Design of shear reinforcement:
At left support:
End shear = (Vu) = 91.76 KN
Nominal shear stress, v =Vu
b x d=
91.76 x 103
230 x 425= 0.94 N/mm2
Ast = 498.67 mm2
Consider Pt =100 xAst
b x d=
100 x 498.67
230 x 425= 0.51
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 156/293
156
From IS 456-2000, Table 19:
Pt c
0.5 0.48
0.51 ?
0.75 0.56
Therefore, c = 0.48 +0.56-0.48
0.75-0.5x (0.51-0.5) = 0.483 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (91.76 x 103) – (0.483 x 230 x 425)
= 44546.75N
Assuming 8mmφ- 2legged stirrups
Asv =
2 x π x 82
4 = 100.53mm
2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 425
44546.75
= 346.29mm >300mm
Provide spacing = 300mm
Vus =0.87 x f y x Asv x d
sv=
0.87 x 415 x 100.53 x 425
300= 51419.84N
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 300
0.87 x 415 = 76.44mm2 <100.5mm2 (safe)
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 157/293
157
Therefore, provide 8mm dia stirrups @ 300mm c/c.
At middle support:
End shear = (Vu) = 112.78 KN
Nominal shear stress, v =Vu
b x d=
112.78 x 103
230 x 425= 1.15 N/mm2
Ast = 1110.4 mm2
Consider Pt =100 xAst
b x d=
100 x 1110.4
230 x 425= 1.14
From IS 456-2000, Table 19:
Pt c
1.00 0.62
1.15 ?
1.25 0.67
Therefore, c = 0.62 + 0.67-0.621.25-1
x (1.15-1.00) = 0.65 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (112.78 x 103) – (0.65 x 230 x 425)
= 49242.5N
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 158/293
158
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 425
49242.5
= 313.26mm < 300mm
Provide spacing = 300mm
Vus =0.87 x f y x Asv x d
sv=
0.87 x 415 x 100.53 x 425
300= 51419.84N
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asvb x Sv
≥ 0.40.87 x f y
Asv =0.4 x 230 x 300
0.87 x 415= 76.44mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 300mm c/c.
At middle support:
End shear = (Vu) = 144.11 KN
Nominal shear stress, v =Vu
b x d=
144.11 x 103
230 x 425= 1.47 N/mm2
Ast = 1598.13 mm2
Consider Pt =100 xAst
b x d=
100 x 1598.13
230 x 425= 1.64
From IS 456-2000, Table 19:
Pt c
1.50 0.72
1.64 ?
1.75 0.75
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 159/293
159
Therefore, c = 0.72 +0.75-0.72
1.75-1.5x (1.64 – 1.5) = 0.74 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (144.11 x 103) – (0.74 x 230 x 425)
= 71775N
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4
= 100.53mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 425
71775
= 214.92mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 210
0.87 x 415= 53.51mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 210mm c/c.
At right support:
End shear = (Vu) = 135.28 KN
Nominal shear stress, v =Vu
b x d=
135.28 x 103
230 x 425= 1.38 N/mm2
Ast = 1237.12 mm2
Consider Pt =100 xAst
b x d=
100 x1237.12
230 x 425= 1.27
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 160/293
160
From IS 456-2000, Table 19:
Pt c
1.25 0.67
1.27 ?
1.5 0.72
Therefore, c = 0.67 +0.72-0.67
1.5-1.25x (1.27-1.25) = 0.674 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (135.28 x 103) – (0.674 x 230 x 425)
= 69396.5N
Assuming 8mmφ- 2legged stirrups
Asv =
2 x π x 82
4 = 100.53mm
2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 425
69396.5
= 222.28mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 220
0.87 x 415= 56.06mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 220mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 161/293
161
Reinforcement for roof 20-11-02:
FLOOR (Section: 230mm x 600mm, d‟ = 50mm)
The moments acting on the beam are:
At left support (Ast1):
Moment due to external load (Mu) = 75.53 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu < Mu‟limit , therefore design as singly reinforced beam.
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
75.53 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 407.61 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 162/293
162
Between the supports (Ast2):
Span moment = 71.71 KN-m
Effective width of flange (bf ) =l0
6 + (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 6000 = 4200 mm
Therefore, bf =4200
6+ (6 x 120) + 230
= 1650 mm
Therefore Mu‟limit = 0.36 x f ck x bf x Df x (d – 0.42Df )
= 0.36 x 20 x 1590 x 120 x (550 – 0.42 x 120)
= 712.23 KN-m
Mu < Mu‟limit
Ast:
71.71 x 106 = 0.87 x 415 x Ast2 x 550 x (1- 415 x Ast2
20 x 230 x 550)
Ast2 = 385.5 mm2
At right support (Ast3):
Moment due to external load (Mu) = 228.89 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
50
550= 0.1
Therefore, f sc = 353 N/mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 163/293
163
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(228.89 - 192.027) x 106
353 x (550 - 50)=208.86 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
192.027 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 1205.32 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
353 x 208.86
0.87 x 415= 201.21 mm2
Ast3 = Ast1 + Ast2 = 1205.32 + 204.21 = 1409.53 mm2
At support (Ast4):
Moment due to external load (Mu) = 393.9 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'd = 50550 = 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(393.9 - 192.027) x 106
353 x (550 - 50)=1143.76 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 164/293
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 165/293
165
At right end (Ast6):
Moment due to external load (Mu) = 315.93 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
50
550= 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(315.93 - 192.027) x 106
353 x (550 - 50)=701.76 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -
f y x Ast1
f ck x b x d )
192.027 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 1205.32 mm2
To find Ast2:
Ast2 = f sc x Asc0.87 x f y = 353 x 701.760.87 x 415 = 686.11 mm2
Ast6 = Ast1 + Ast2 = 1205.32 + 686.11 = 1891.43 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 166/293
166
Design of shear reinforcement:
At left support:
End shear = (Vu) = 109.8 KN
Nominal shear stress, v =Vu
b x d=
109.8 x 103
230 x 550= 0.87 N/mm2
Ast = 407.61 mm2
Consider Pt =100 xAst
b x d=
100 x 407.61
230 x 550= 0.32
From IS 456-2000, Table 19:
Pt c
0.25 0.36
0.32 ?
0.5 0.48
Therefore, c = 0.36 +0.48-0.360.5-0.25
x (0.32-0.25) = 0.4 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (109.8 x 103) – (0.4 x 230 x 550)
= 59200N
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 167/293
167
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 550
59200
= 337.21mm >300mm
Provide spacing = 300mm
Vus = 0.87 x f y x Asv x dsv= 0.87 x 415 x 100.53 x 550300 = 66543.32N
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 300
0.87 x 415= 76.44mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 300mm c/c.
At middle support:
End shear = (Vu) = 152.94 KN
Nominal shear stress, v =Vu
b x d=
152.94 x 103
230 x 550= 1.21 N/mm2
Ast = 1409.33 mm2
Consider Pt =100 xAst
b x d=
100 x 1409.33
230 x 550= 1.12
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 168/293
168
From IS 456-2000, Table 19:
Pt c
1.00 0.62
1.12 ?
1.25 0.67
Therefore, c = 0.62 +0.67-0.62
1.25-1x (1.12-1) = 0.65 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (152.94 x 103) – (0.65 x 230 x 550)
= 70715N
Assuming 8mmφ- 2legged stirrups
Asv =
2 x π x 82
4 = 100.53mm
2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 550
70715
= 282.3mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 280
0.87 x 415= 71.35mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 280mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 169/293
169
At middle support:
End shear = (Vu) = 292.34 KN
Nominal shear stress, v =Vu
b x d =292.34 x 103
230 x 550 = 2.31 N/mm2
Ast = 2323.58 mm2
Consider Pt =100 xAst
b x d=
100 x 2323.58
230 x 550= 1.84
From IS 456-2000, Table 19:
Pt c
1.75 0.75
1.84 ?
2.00 0.79
Therefore, c = 0.75 +0.79-0.75
2-1.75x (1.84-1.75) = 0.77 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (292.34 x 103) – (0.77 x 230 x 550)
= 194935N
Assuming 10mmφ- 2legged stirrups
Asv =2 x π x 102
4= 157.07mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 157.07 x 550
194935
= 160mm < 300mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 170/293
170
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 160
0.87 x 415= 40.77mm2 <157.07mm2 (safe)
Therefore, provide 10mm dia stirrups @ 160mm c/c.
At right support:
End shear = (Vu) = 275.05 KN
Nominal shear stress, v = Vub x d = 275.05 x 10
3
230 x 550 = 2.18 N/mm2
Ast = 1891.43 mm2
Consider Pt =100 xAst
b x d=
100 x 1891.43
230 x 550= 1.5
From IS 456-2000, Table 19:
Pt c
1.5 0.72
Therefore, c = 0.72 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (275.05 x 103) – (0.72 x 230 x 550)
= 183970N
Assuming 10mmφ- 2legged stirrups
Asv =2 x π x 102
4= 157.07mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 171/293
171
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 157.07 x 550
183970
= 169.54mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 160
0.87 x 415= 40.77mm2 <157.07mm2 (safe)
Therefore, provide 10mm dia stirrups @ 160mm c/c.
Reinforcement for roof 20-11-02:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 172/293
172
c. Beam 24-15 and Beam 15-06
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 173/293
173
ROOF – Same as in case of roof 20-11-12
FLOOR :
The moments acting on the beam are:
At left support (Ast1):
Moment due to external load (Mu) = 95.08 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu < Mu‟limit , therefore design as singly reinforced beam.
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
95.08 x 106
= 0.87 x 415 x Ast1 x 550 x (1 -
415 x Ast1
20 x 230 x 550 )
Ast1 = 523.81 mm2
Between the supports (Ast2):
Span moment = 89.37 KN-m
Effective width of flange (bf ) =l0
6+ (6 x Df ) + bw
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 174/293
174
l0 = 0.7 x l = 0.7 x 6000 = 4200 mm
Therefore, bf =4200
6+ (6 x 120) + 230
= 1650 mm
Therefore Mu‟limit = 0.36 x f ck x bf x Df x (d – 0.42Df )
= 0.36 x 20 x 1590 x 120 x (550 – 0.42 x 120)
= 712.23 KN-m
Mu < Mu‟limit
Ast:
89.37 x 106 = 0.87 x 415 x Ast2 x 550 x (1-415 x Ast2
20 x 230 x 550)
Ast2 = 489.33 mm2
At right support (Ast3):
Moment due to external load (Mu) = 208.43 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'd = 50550 = 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(208.43 - 192.027) x 106
353 x (550 - 50)=92.94 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 175/293
175
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
192.027 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 1205.32 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
353 x 92.94
0.87 x 415= 90.87 mm2
Ast3 = Ast1 + Ast2 = 1205.32 + 90.87 = 1296.19 mm2
At support (Ast4):
Moment due to external load (Mu) = 280.82 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
50
550= 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(280.82 - 192.027) x 106
353 x (550 - 50)=503.08 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
192.027 x 106 = 0.87 x 415 x Ast1 x 550 x (1 - 415 x Ast1
20 x 230 x 550)
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 176/293
176
Ast1 = 1205.32 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y =353 x 503.08
0.87 x 415 = 491.86 mm2
Ast4 = Ast1 + Ast2 = 1205.32 + 491.86 = 1697.18 mm2
Between the supports (Ast5):
Span moment = 166.85 KN-m
Effective width of flange (bf ) =l0
6
+ (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 8410 = 5887 mm
Therefore, bf =5887
6+ (6 x 120) + 230
= 1931.17 mm
Therefore Mu‟limit = 0.36 x f ck x bf x Df x (d – 0.42Df )
= 0.36 x 20 x 1931.7 x 120 x (550 – 0.42 x 120)
= 833.83 KN-m
Mu < Mu‟limit
Ast:
166.85 x 106
= 0.87 x 415 x Ast2 x 550 x (1-
415 x Ast2
20 x 230 x 550 )
Ast5 = 1006.35 mm2
At right end (Ast6):
Moment due to external load (Mu) = 211.34 KN-m
Mu‟limit = 0.138 x f ck x b x d2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 177/293
177
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
50
550= 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(211.34 - 192.027) x 106
353 x (550 - 50)=109.42 mm
2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
192.027 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 1205.32 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
353 x 109.42
0.87 x 415= 106.98 mm2
Ast6 = Ast1 + Ast2 = 1205.32 + 106.98 = 1312.3 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 178/293
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 179/293
179
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 250
0.87 x 415= 63.7mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 250mm c/c.
At middle support:
End shear = (Vu) = 166.87 KN
Nominal shear stress, v = Vub x d = 166.87 x 10
3
230 x 550 = 1.32 N/mm2
Ast = 1296.19 mm2
Consider Pt =100 xAst
b x d=
100 x 1296.19
230 x 550= 1.03
From IS 456-2000, Table 19:
Pt c
1.00 0.62
1.03 ?
1.25 0.67
Therefore, c = 0.62 +0.67-0.62
1.25-1x (1.03-1) = 0.63 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (166.87 x 103) – (0.63 x 230 x 550)
= 87175N
Assuming 8mmφ- 2legged stirrups
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 180/293
180
Asv =2 x π x 82
4= 100.53mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 550
87175
= 229mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 220
0.87 x 415= 56.05mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 220mm c/c.
At middle support:
End shear = (Vu) = 200.56 KN
Nominal shear stress, v = Vu
b x d= 200.56 x 10
3
230 x 550= 1.59 N/mm2
Ast = 1697.18 mm2
Consider Pt =100 xAst
b x d=
100 x 1697.18
230 x 550= 1.34
From IS 456-2000, Table 19:
Pt c
1.25 0.67
1.34 ?
1.50 0.72
Therefore, c = 0.67 +0.72-0.67
1.5-1.25x (1.34-1.25) = 0.69 N/mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 181/293
181
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (200.56 x 103) – (0.69 x 230 x 550)
= 113275N
Assuming 10mmφ- 2legged stirrups
Asv =2 x π x 102
4= 157.07mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 157.07 x 550
113275
= 275.35mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 270
0.87 x 415= 68.8mm2 <157.07mm2 (safe)
Therefore, provide 10mm dia stirrups @ 270mm c/c.
At right support:
End shear = (Vu) = 185.35 KN
Nominal shear stress, v =Vu
b x d=
185.35 x 103
230 x 550= 1.47 N/mm2
Ast = 1312.3 mm2
Consider Pt =100 xAst
b x d=
100 x 1312.3
230 x 550= 1
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 182/293
182
From IS 456-2000, Table 19:
Pt c
1 0.62
Therefore, c = 0.62 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (185.35 x 103) – (0.62 x 230 x 550)
= 106920N
Assuming 10mmφ- 2legged stirrups
Asv =2 x π x 102
4= 157.07mm2
Therefore,
Spacing of stirrups, sv =
0.87 x f y x Asv x d
Vus =
0.87 x 415 x 157.07 x 550
106920
= 291mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =
0.4 x 230 x 290
0.87 x 415 = 73.9mm2
<157.07mm2
(safe)
Therefore, provide 10mm dia stirrups @ 290mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 183/293
183
Reinforcement for roof 24-15-06:
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 184/293
184
d. Beam 25-16 and Beam 16-07
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 185/293
185
ROOF – Same as 20-11-02
FLOOR :
The moments acting on the beam are:
At left support (Ast1):
Moment due to external load (Mu) = 85.69 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu < Mu‟limit , therefore design as singly reinforced beam.
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
85.69 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 467.34 mm2
Between the supports (Ast2):
Span moment = 80.45 KN-m
Effective width of flange (bf ) =l0
6+ (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 6000 = 4200 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 186/293
186
Therefore, bf =4200
6+ (6 x 120) + 230
= 1650 mm
Therefore Mu‟limit = 0.36 x f ck x bf x Df x(d – 0.42Df )
= 0.36 x 20 x 1590 x 120 x (550 – 0.42 x 120)
= 712.23 KN-m
Mu < Mu‟limit
Ast:
80.45 x 106 = 0.87 x 415 x Ast2 x 550 x (1-415 x Ast2
20 x 230 x 550)
Ast2 = 436.37 mm2
At right support (Ast3):
Moment due to external load (Mu) = 218.95 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
50
550= 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(218.95 - 192.027) x 106
353 x (550 - 50)=152.54 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 - f y x Ast1
f ck x b x d)
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 187/293
187
192.027 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 1205.32 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
353 x 152.54
0.87 x 415= 149.14 mm2
Ast3 = Ast1 + Ast2 = 1205.32 + 149.14 = 1354.46 mm2
At support (Ast4):
Moment due to external load (Mu) = 343.47 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider
d'
d =
50
550 = 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(343.47 - 192.027) x 106
353 x (550 - 50)=858.03 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
192.027 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 1205.32 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 188/293
188
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
353 x 858.03
0.87 x 415= 838.9 mm2
Ast4 = Ast1 + Ast2 = 1205.32 + 838.9 = 2044.22 mm2
Between the supports (Ast5):
Span moment = 210.5 KN-m
Effective width of flange (bf ) =l0
6+ (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 8410 = 5887 mm
Therefore, bf =5887
6+ (6 x 120) + 230
= 1931.17 mm
Therefore Mu‟limit = 0.36 x f ck x bf x Df x(d – 0.42Df )
= 0.36 x 20 x 1931.7 x 120 x (550 – 0.42 x 120)
= 833.83 KN-m
Mu < Mu‟limit
Ast:
210.5 x 106 = 0.87 x 415 x Ast2 x 550 x (1-415 x Ast2
20 x 230 x 550)
Ast5 = 1366.21 mm2
At right end (Ast6):
Moment due to external load (Mu) = 268.55 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 189/293
189
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
50
550= 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(268.55 - 192.027) x 106
353 x (550 - 50)=433.56 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 - f y x Ast1f ck x b x d )
192.027 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 1205.32 mm2
To find Ast2:
Ast2 = f sc x Asc
0.87 x f y= 353 x 433.56
0.87 x 415= 423.9 mm2
Ast6 = Ast1 + Ast2 = 1205.32 + 423.9 = 1629.22 mm2
Design of shear reinforcement:
At left support:
End shear = (Vu) = 120.89 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 190/293
190
Nominal shear stress, v =Vu
b x d=
120.89 x 103
230 x 550= 0.96 N/mm2
Ast = 467.34 mm2
Consider Pt =100 xAst
b x d=
100 x 467.34
230 x 550= 0.37
From IS 456-2000, Table 19:
Pt c
0.25 0.36
0.37 ?
0.5 0.48
Therefore, c = 0.36 +0.48-0.36
0.5-0.25x (0.37-0.25) = 0.42 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (120.89 x 103) – (0.42 x 230 x 550)
= 67760N
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 550
67760
= 294mm <300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asvb x Sv
≥0.4
0.87 x f y
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 191/293
191
Asv =0.4 x 230 x 290
0.87 x 415= 73.9mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 290mm c/c.
At middle support:
End shear = (Vu) = 158.11 KN
Nominal shear stress, v =Vu
b x d=
158.11 x 103
230 x 550= 1.25 N/mm2
Ast = 1354.46 mm2
Consider Pt = 100 xAst b x d = 100 x 1354.46230 x 550 = 1.07
From IS 456-2000, Table 19:
Pt c
1.00 0.62
1.07 ?
1.25 0.67
Therefore, c = 0.62 +0.67-0.62
1.25-1x (1.07-1) = 0.634 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (158.11x 103) – (0.634 x 230 x 550)
= 77909N
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 192/293
192
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 550
77909
= 256.24mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 250
0.87 x 415= 63.7mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 250mm c/c.
At middle support:
End shear = (Vu) = 251.1 KN
Nominal shear stress, v =Vu
b x d=
251.1 x 103
230 x 550= 2 N/mm2
Ast = 2044.2 mm2
Consider Pt =100 xAst
b x d=
100 x 2044.2
230 x 550= 1.62
From IS 456-2000, Table 19:
Pt c
1.5 0.72
1.62 ?
1.75 0.75
Therefore, c = 0.72 +0.75-0.72
1.75-1.5x (1.62-1.5) = 0.73 N/mm2
Therefore, v > c,
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 193/293
193
Stirrups are designed for shear Vus = Vu - c bd
= (251.1 x 103) – (0.73 x 230 x 550)
= 158755N
Assuming 10mmφ- 2legged stirrups
Asv =2 x π x 102
4= 157.07mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus
=0.87 x 415 x 157.07 x 550
158755
= 196.5mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 190
0.87 x 415= 48.41mm2 <157.07mm2 (safe)
Therefore, provide 10mm dia stirrups @ 190mm c/c.
At right support:
End shear = (Vu) = 234.86 KN
Nominal shear stress, v =Vu
b x d=
234.86 x 103
230 x 550= 1.86 N/mm2
Ast = 1629.22 mm2
Consider Pt =100 xAst
b x d=
100 x 1629.22
230 x 550= 1.29
From IS 456-2000, Table 19:
Pt c
1.25 0.67
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 194/293
194
1.29 ?
1.5 0.72
Therefore, c = = 0.67 +0.72-0.67
1.5-1.25 x (1.29-1.25) = 0.68 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (234.86 x 103) – (0.68 x 230 x 550)
= 148840N
Assuming 10mmφ- 2legged stirrups
Asv =2 x π x 102
4= 157.07mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 157.07 x 550
148840
= 209.56mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 200
0.87 x 415= 50.96mm2 <157.07mm2 (safe)
Therefore, provide 10mm dia stirrups @ 200mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 195/293
195
Reinforcement for roof 25-16-07
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 196/293
196
e. Beam 26-17 and Beam 17-08
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 197/293
197
ROOF – Same as 20-11-02
FLOOR:
The moments acting on the beam are:
At left support (Ast1):
Moment due to external load (Mu) = 73.1 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu < Mu‟limit , therefore design as singly reinforced beam.
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
73.1 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 393.52 mm2
Between the supports (Ast2):
Span moment = 68.48 KN-m
Effective width of flange (bf ) =l0
6+ (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 6000 = 4200 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 198/293
198
Therefore, bf =4200
6+ (6 x 120) + 230
= 1650 mm
Therefore Mu‟limit = 0.36 x f ck x bf x Df x(d – 0.42Df )
= 0.36 x 20 x 1590 x 120 x (550 – 0.42 x 120)
= 712.23 KN-m
Mu < Mu‟limit
Ast:
68.48 x 106 = 0.87 x 415 x Ast2 x 550 x (1-415 x Ast2
20 x 230 x 550)
Ast2 = 366.94 mm2
At right support (Ast3):
Moment due to external load (Mu) = 185.08 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu < Mu‟limit , therefore design as singly reinforced beam.
To find Ast3:
Mu‟limit = 0.87 x f y x Ast3 x d x (1 - f y x Ast3f ck x b x d )
185.08 x 106 = 0.87 x 415 x Ast3 x 550 x (1 -415 x Ast3
20 x 230 x 550)
Ast3 = 1148.33 mm2
At support (Ast4):
Moment due to external load (Mu) = 297.26 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 199/293
199
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
50
550= 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc = Mu - Mu‟limit
f sc x (d - d')= (297.26 - 192.027) x 106
353 x (550 - 50)=596.22 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
192.027 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 1205.32 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
353 x 596.22
0.87 x 415= 582.93 mm2
Ast4 = Ast1 + Ast2 = 1205.32 + 582.93 = 1788.25 mm2
Between the supports (Ast5):
Span moment = 183.9 KN-m
Effective width of flange (bf ) =l0
6+ (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 8410 = 5887 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 200/293
200
Therefore, bf =5887
6+ (6 x 120) + 230
= 1931.17 mm
Therefore Mu‟limit = 0.36 x f ck x bf x Df x(d – 0.42Df )
= 0.36 x 20 x 1931.7 x 120 x (550 – 0.42 x 120)
= 833.83 KN-m
Mu < Mu‟limit
Ast:
183.9 x 106 = 0.87 x 415 x Ast2 x 550 x (1-415 x Ast2
20 x 230 x 550)
Ast5 = 1138.82 mm2
At right end (Ast6):
Moment due to external load (Mu) = 234.45 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
50
550= 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(234.45 - 192.027) x 106
353 x (550 - 50)=240.36 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 - f y x Ast1
f ck x b x d)
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 201/293
201
192.027 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 1205.32 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
353 x 240.36
0.87 x 415= 235 mm2
Ast6 = Ast1 + Ast2 = 1205.32 + 235 = 1440.32 mm2
Design of shear reinforcement:
At left support:
End shear = (Vu) = 101.13 KN
Nominal shear stress, v =Vu
b x d=
101.13 x 103
230 x 550= 0.8 N/mm2
Ast = 393.52 mm2
Consider Pt = 100 xAst b x d
= 100 x 393.52230 x 550
= 0.31
From IS 456-2000, Table 19:
Pt c
0.25 0.36
0.31 ?
0.5 0.48
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 202/293
202
Therefore, c = 0.36 +0.48-0.36
0.5-0.25x (0.31-0.25) = 0.39 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (101.13 x 103) – (0.39 x 230 x 550)
= 51795N
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4
= 100.53mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 550
51795
= 385.42mm >300mm
Provide spacing = 300mm
Vus =0.87 x f y x Asv x d
sv=
0.87 x 415 x 100.53 x 550
300= 66543.32N
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =
0.4 x 230 x 300
0.87 x 415 = 76.44 mm2
<100.5mm2
(safe)
Therefore, provide 8mm dia stirrups @ 300mm c/c.
At middle support:
End shear = (Vu) = 131.2 KN
Nominal shear stress, v =Vu
b x d=
131.2 x 103
230 x 550= 1.04 N/mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 203/293
203
Ast = 1148.33 mm2
Consider Pt =100 xAst
b x d=
100 x 1148.33
230 x 550= 0.91
From IS 456-2000, Table 19:
Pt c
0.75 0.56
0.91 ?
1.00 0.62
Therefore, c = 0.56 +0.62-0.56
1-0.75x (0.91-0.75) = 0.6 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (131.2x 103) – (0.6 x 230 x 550)
= 55300N
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
Therefore,
Spacing of stirrups, sv =
0.87 x f y x Asv x d
Vus =
0.87 x 415 x 100.53 x 550
55300
= 361mm > 300mm
Provide spacing = 300mm
Vus =0.87 x f y x Asv x d
sv=
0.87 x 415 x 100.53 x 550
300= 66543.32N
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 204/293
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 205/293
205
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 157.07 x 550
128655
= 242.5mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 240
0.87 x 415= 61.16mm2 <157.07mm2 (safe)
Therefore, provide 10mm dia stirrups @ 240mm c/c.
At right support:
End shear = (Vu) = 204.57 KN
Nominal shear stress, v =Vu
b x d=
204.57 x 103
230 x 550= 1.62 N/mm2
Ast = 1400.32 mm2
Consider Pt =100 xAst
b x d=
100 x 1400.32
230 x 550= 1.11
From IS 456-2000, Table 19:
Pt c
1.00 0.62
1.11 ?
1.25 0.67
Therefore, c = = 0.62 +0.67-0.62
1.25-1.00x (1.11-1.00) = 0.64 N/mm2
Therefore, v > c,
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 206/293
206
Stirrups are designed for shear Vus = Vu - c bd
= (204.57 x 103) – (0.64 x 230 x 550)
= 123610N
Assuming 10mmφ- 2legged stirrups
Asv =2 x π x 102
4= 157.07mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus
=0.87 x 415 x 157.07 x 550
123610
= 252.33mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 250
0.87 x 415= 63.7mm2 <157.07mm2 (safe)
Therefore, provide 10mm dia stirrups @ 200mm c/c.
Reinforcement for roof 26-17-08
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 207/293
207
f. Beam 27-18 and Beam 18-09
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 208/293
208
ROOF – Same as 19-10-01
FLOOR :
The moments acting on the beam are:
At left support (Ast1):
Moment due to external load (Mu) = 101.22 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu < Mu‟limit , therefore design as singly reinforced beam.
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
101.22 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 561.43 mm2
Between the supports (Ast2):
Span moment = 70.3 KN-m
Effective width of flange (bf ) =l0
6+ (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 6000 = 4200 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 209/293
209
Therefore, bf =4200
6+ (6 x 120) + 230
= 1650 mm
Therefore Mu‟limit = 0.36 x f ck x bf x Df x(d – 0.42Df )
= 0.36 x 20 x 1590 x 120 x (550 – 0.42 x 120)
= 712.23 KN-m
Mu < Mu‟limit
Ast:
70.3 x 106 = 0.87 x 415 x Ast2 x 550 x (1-415 x Ast2
20 x 230 x 550)
Ast2 = 377.38 mm2
At right support (Ast3):
Moment due to external load (Mu) = 166.06 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu < Mu‟limit , therefore design as singly reinforced beam.
To find Ast3:
Mu‟limit = 0.87 x f y x Ast3 x d x (1 - f y x Ast3f ck x b x d )
166.06 x 106 = 0.87 x 415 x Ast3 x 550 x (1 -415 x Ast3
20 x 230 x 550)
Ast3 = 1000.42 mm2
At support (Ast4):
Moment due to external load (Mu) = 288.45 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 210/293
210
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
50
550= 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc = Mu - Mu‟limit
f sc x (d - d')= (288.45 - 192.027) x 106
353 x (550 - 50)=546.31 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 -f y x Ast1
f ck x b x d)
192.027 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 1205.32 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
353 x 546.31
0.87 x 415= 534.13 mm2
Ast4 = Ast1 + Ast2 = 1205.32 + 534.13 = 1739.45 mm2
Between the supports (Ast5):
Span moment = 160.42 KN-m
Effective width of flange (bf ) =l0
6+ (6 x Df ) + bw
l0 = 0.7 x l = 0.7 x 8410 = 5887 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 211/293
211
Therefore, bf =5887
6+ (6 x 120) + 230
= 1931.17 mm
Therefore Mu‟limit = 0.36 x f ck x bf x Df x(d – 0.42Df )
= 0.36 x 20 x 1931.7 x 120 x (550 – 0.42 x 120)
= 833.83 KN-m
Mu < Mu‟limit
Ast:
160.42 x 106 = 0.87 x 415 x Ast2 x 550 x (1-415 x Ast2
20 x 230 x 550)
Ast5 = 958.56 mm2
At right end (Ast6):
Moment due to external load (Mu) = 257.96 KN-m
Mu‟limit = 0.138 x f ck x b x d2
= 0.138 x 20 x 230 x (550)2 = 192.027 x 106 N-mm
= 192.027 KN-m
Mu > Mu‟limit , therefore design as doubly reinforced beam.
Consider d'
d=
50
550= 0.1
Therefore, f sc = 353 N/mm2
Area of steel in compression (Asc):
Asc =Mu - Mu‟limit
f sc x (d - d')=
(257.96 - 192.027) x 106
353 x (550 - 50)=373.56 mm2
To find Ast1:
Mu‟limit = 0.87 x f y x Ast1 x d x (1 - f y x Ast1
f ck x b x d)
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 212/293
212
192.027 x 106 = 0.87 x 415 x Ast1 x 550 x (1 -415 x Ast1
20 x 230 x 550)
Ast1 = 1205.32 mm2
To find Ast2:
Ast2 =f sc x Asc
0.87 x f y=
353 x 373.56
0.87 x 415= 365.23 mm2
Ast6 = Ast1 + Ast2 = 1205.32 + 365.23 = 1570.55 mm2
Design of shear reinforcement:
At left support:
End shear = (Vu) = 119.94 KN
Nominal shear stress, v =Vu
b x d=
119.94 x 103
230 x 550= 0.95 N/mm2
Ast = 561.43 mm2
Consider Pt =100 xAst
b x d=
100 x 561.43
230 x 550= 0.44
From IS 456-2000, Table 19:
Pt c
0.25 0.36
0.44 ?
0.5 0.48
Therefore, c = 0.36 +0.48-0.36
0.5-0.25x (0.44-0.25) = 0.45 N/mm2
Therefore, v > c,
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 213/293
213
Stirrups are designed for shear Vus = Vu - c bd
= (119.94 x 103) – (0.45 x 230 x 550)
= 63015N
Assuming 8mmφ- 2legged stirrups
Asv =2 x π x 82
4= 100.53mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus
=0.87 x 415 x 100.53 x 550
63015
= 316.8mm >300mm
Provide spacing = 300mm
Vus =0.87 x f y x Asv x d
sv=
0.87 x 415 x 100.53 x 550
300= 66543.32N
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 300
0.87 x 415= 76.44 mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 300mm c/c.
At middle support:
End shear = (Vu) = 138.8 KN
Nominal shear stress, v =Vu
b x d=
138.8 x 103
230 x 550= 1.1 N/mm2
Ast = 1000.42 mm2
Consider Pt =100 xAst
b x d=
100 x 1000.42
230 x 550= 0.79
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 214/293
214
From IS 456-2000, Table 19:
Pt c
0.75 0.56
0.79 ?
1.00 0.62
Therefore, c = 0.56 +0.62-0.56
1-0.75x (0.79-0.75) = 0.57 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (138.8x 103) – (0.57 x 230 x 550)
= 66695N
Assuming 8mmφ- 2legged stirrups
Asv =
2 x π x 82
4 = 100.53mm
2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 100.53 x 550
66695
= 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 300
0.87 x 415= 76.44 mm2 <100.5mm2 (safe)
Therefore, provide 8mm dia stirrups @ 300mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 215/293
215
At middle support:
End shear = (Vu) = 208.4 KN
Nominal shear stress, v =Vu
b x d =208.4 x 103
230 x 550 = 1.65 N/mm2
Ast = 1739.5mm2
Consider Pt =100 xAst
b x d=
100 x 1739.5
230 x 550= 1.38
From IS 456-2000, Table 19:
Pt c
1.25 0.67
1.38 ?
1.5 0.72
Therefore, c = 0.67 +0.72-0.67
1.5-1.25x (1.38-1.25) = 0.7 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (208.4 x 103) – (0.7 x 230 x 550)
= 119850N
Assuming 10mmφ- 2legged stirrups
Asv =2 x π x 102
4= 157.07mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 157.07 x 550
119850
= 260.25mm < 300mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 216/293
216
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 260
0.87 x 415= 66.25mm2 <157.07mm2 (safe)
Therefore, provide 10mm dia stirrups @ 260mm c/c.
At right support:
End shear = (Vu) = 200.33 KN
Nominal shear stress, v = Vub x d = 200.33 x 10
3
230 x 550 = 1.58 N/mm2
Ast = 1570.5 mm2
Consider Pt =100 xAst
b x d=
100 x 1570.5
230 x 550= 1.24
From IS 456-2000, Table 19:
Pt c
1.00 0.62
1.24 ?
1.25 0.67
Therefore, c = = 0.62 +0.67-0.62
1.25-1.00x (1.24-1.00) = 0.67 N/mm2
Therefore, v > c,
Stirrups are designed for shear Vus = Vu - c bd
= (200.33 x 103) – (0.67 x 230 x 550)
= 115575N
Assuming 10mmφ- 2legged stirrups
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 217/293
217
Asv =2 x π x 102
4= 157.07mm2
Therefore,
Spacing of stirrups, sv =0.87 x f y x Asv x d
Vus=
0.87 x 415 x 157.07 x 550
115575
= 269.87mm < 300mm
Min shear reinforcement (IS456-2000, clause 26.5.1.6, P48)
Asv
b x Sv ≥
0.4
0.87 x f y
Asv =0.4 x 230 x 260
0.87 x 415= 66.25mm2 <157.07mm2 (safe)
Therefore, provide 10mm dia stirrups @ 260mm c/c.
Reinforcement for roof 27-18-09
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 218/293
218
5. DESIGN OF COLUMNS
Since the loads and moments in the three columns in a frame are different. Each of the
Column is required to be designed separately. However, when entire building is to be
designed, there will be a number of other columns along with each of the above columns to
form a group.
Since exact values of Pu and Mu are known for all storeys for all columns, the column
section will be designed using exact method using charts and tables. Charts are useful for any
which of column. It is advisable to have curves plotted of Pu-Mu for standard sections
normally used in building design to avoid calculations.
All the columns are subjected to axial loads and uni-axial bending. They will be
designed to resist Pu and Mu for bending @ x-axis which is the major axis.
For frame 19-10-01:
Columns are C19 at left end, C10 at middle and C01 at right end of the frame.
The moments and axial forces are calculated in analysis of frames and design of
beams. We have transverse frames and in these frames the plinth level transverse beams are
absent and longitudinal beams are present at the plinth level.
In each level the types of loads are:
1. Max shear from transverse beams
2. Shear from longitudinal beams
3. Self weight of columns.
But in plinth level shear from transverse beams is absent. We have only two values at the plinth level
Section: 230mm x 600mm
Cover (d‟) = 50mm
Minimum eccentricity (ex,min) =unsupported length
500+
lateral dimension
30or
= 20mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 219/293
219
Pu – Load acting on the column
Mux,min = ex,min x Pu
MuD = Maximum (Mu, Mux,min)
f ck x b x D = 20 x 230 x 600 = 2760000N = 2760 KN
f ck x b x D2 = 20 x 230 x (600)2 = 1676 x 106 N-mm = 1676 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 220/293
220
For Column 19:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 3050 26.1 102.83 64.85 2.68 64.85
5-4 2900 25.8 271.485 53.27 7 53.27
4-3 2900 25.8 440.14 53.27 11.36 53.27
3-2 2900 25.8 608.795 53.27 15.71 53.27
2-1 2900 25.8 777.45 53.27 20.06 53.27
1- Plinth 4900 29.8 946.11 53.27 28.19 53.27
Plinth –
Footing
- 29.8 982.185 0 29.27 29.27
By the help of SP16, chart no:32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.04 0.04 0.015 0.3
5-4 0.1 0.03 0.01 0.2
4-3 0.16 0.03 0.01 0.2
3-2 0.22 0.03
0.01
0.22-1 0.28 0.03 0.01 0.2
1- Plinth 0.34 0.03 0.01 0.2
Plinth – Footing 0.36 0.02 0.01 0.2
But from Is 456-2000, P48, Clause 26.5.3.1 (a)
The cross-sectional area of longitudinal reinforcement, shall be not less than
0.8% nor more than 6% of the gross cross-sectional area (b x D) of the column.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 221/293
221
Therefore, provide P = 0.8%
Ast =0.8
100x 230 x 600 = 1104 mm2
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4x diameter of max main steel bar =
1
4x 16 = 4mm
Maximum of two values =6mm.
But in the recent construction the usage of 6mm bars is outdated. Therefore consider
minimum 8mm dia bars.
Design of pitch:
1.
Least lateral dimension = 230mm2. 16 x diameter of main steel bar = 16 x 16 = 256
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1104 6 bars of 16mm φ
2-1 1104 6 bars of 16mm φ
1-Plinth 1104 6 bars of 16mm φ
Plinth – footing 1104 6 bars of 16mm φ
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 222/293
222
For Column 10:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 3050 26.1 202.61 89.7 5.29 89.70
5-4 2900 25.8 583.35 81.6 15.05 81.60
4-3 2900 25.8 964.09 81.6 24.87 81.60
3-2 2900 25.8 1344.83 81.6 34.70 81.60
2-1 2900 25.8 1725.57 81.6 44.52 81.60
1- Plinth 4900 29.8 2106.31 81.6 62.77 81.60
Plinth –
Footing - 29.8 2136.1 0 63.66 63.66
By the help of SP16, chart no:32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.07 0.05 0.02 0.4
5-4 0.21 0.05 0.02 0.4
4-3 0.35 0.05 0.02 0.4
3-2 0.49 0.05 0.04 0.82-1 0.63 0.05 0.08 1.6
1- Plinth 0.76 0.05 0.12 2.4
Plinth – Footing 0.77 0.04 0.12 2.4
But from Is 456-2000, P48, Clause 26.5.3.1 (a)
The cross-sectional area of longitudinal reinforcement, shall be not less than
0.8% nor more than 6% of the gross cross-sectional area (b x D) of the column.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 223/293
223
Therefore, provide P = 0.8%
Ast =0.8
100x 230 x 600 = 1104 mm2
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
For P = 1.6%
Ast =1.6
100x 230 x 600 = 2208 mm2
No. of bars of 20mmφ bars =4 x 2208
π x (20)2 = 7 bars
Therefore provide 8 bars of 20mmφ bars. (Each side 4bars)
For P = 2.4%
Ast =2.4
100x 230 x 600 = 3312 mm2
No. of bars of 25mmφ bars =4 x 3312
π x (25)2 = 6.75 bars say 8 bars
Therefore provide 8 bars of 25mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4 x diameter of max main steel bar =1
4 x 25 = 6.25mm say 8mm
Maximum of two values =8mm.
Design of pitch:
1. Least lateral dimension = 230mm
2. 16 x diameter of main steel bar = 16 x 16 = 256
3. 300mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 224/293
224
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm2) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1104 6 bars of 16mm φ
2-1 2208 8 bars of 20mm φ
1-Plinth 3312 8 bars of 25mm φ
Plinth – footing 3312 8 bars of 25mm φ
For Column 01:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 3050 26.1 133.97 136.67 3.50 136.67
5-4 2900 25.8 383.39 122.6 9.89 122.60
4-3 2900 25.8 632.81 122.6 16.33 122.60
3-2 2900 25.8 882.23 122.6 22.76 122.60
2-1 2900 25.8 1131.65 122.6 29.20 122.60
1- Plinth 4900 29.8 1381.07 122.6 41.16 122.60
Plinth –
Footing
-
29.8 1430.66 0 42.63 42.63
By the help of SP16, chart no:32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 225/293
225
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.05 0.08 0.02 0.4
5-4 0.14 0.07 0.02 0.4
4-3 0.23 0.07 0.02 0.4
3-2 0.32 0.07 0.04 0.8
2-1 0.41 0.07 0.04 0.8
1- Plinth 0.50 0.07 0.06 1.2
Plinth – Footing 0.52 0.03 0.06 1.2
Provide min P = 0.8%
Ast = 0.8100
x 230 x 600 = 1104 mm2
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
For P=1.2%
Ast =1.2
100x 230 x 600 = 1656 mm2
No. of bars of 20mmφ bars =4 x 1656
π x (20)2 = 5.27 say 6 bars
Therefore provide 6 bars of 20mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 14 x diameter of max main steel bar = 14 x 20 = 5mm
Maximum of two values =6mm.
But in the recent construction the usage of 6mm bars is outdated. Therefore consider
minimum 8mm dia bars.
Design of pitch:
1. Least lateral dimension = 230mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 226/293
226
2. 16 x diameter of main steel bar = 16 x 16 = 256
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1104 6 bars of 16mm φ
2-1 1104 6 bars of 16mm φ
1-Plinth 1656 6 bars of 20mm φ
Plinth – footing 1656 6 bars of 20mm φ
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 227/293
227
For frame 20-11-02:
Columns are C20 at left end, C12 at middle and C02 at right end of the frame.
Section: 230mm x 600mm
Cover (d‟) = 50mm
Minimum eccentricity (ex,min) =unsupported length
500+
lateral dimension
30or
= 20mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 228/293
228
f ck x b x D = 20 x 230 x 600 = 2760000N = 2760 KN
f ck x b x D2 = 20 x 230 x (600)2 = 1676 x 106 N-mm = 1676 KN-m
For Column 20:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 2900 25.8 137.01 68.42 3.53 68.42
5-4 2750 25.5 315.59 37.77 8.05 37.77
4-3 2750 25.5 494.17 37.77 12.60 37.77
3-2 2750 25.5 672.75 37.77 17.16 37.77
2-1 2750 25.5 851.33 37.77 21.71 37.77
1- Plinth 4750 29.5 1029.91 37.77 30.38 37.77
Plinth –
Footing
-
29.5 1091.71 0 32.21 32.21
By the help of SP16, chart no: 32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.05 0.04 0.01 0.2
5-4 0.11 0.02 0.01 0.2
4-3 0.18 0.02 0.01 0.2
3-2 0.24 0.02 0.01 0.2
2-1 0.31 0.02 0.01 0.2
1- Plinth 0.37 0.02 0.01 0.2
Plinth – Footing 0.40 0.02 0.01 0.2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 229/293
229
Therefore, provide P = 0.8%
Ast =0.8
100x 230 x 600 = 1104 mm2
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4x diameter of max main steel bar =
1
4x 16 = 4mm
Maximum of two values =6mm.
But in the recent construction the usage of 6mm bars is outdated. Therefore consider
minimum 8mm dia bars.
Design of pitch:
1.
Least lateral dimension = 230mm2. 16 x diameter of main steel bar = 16 x 16 = 256
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1104 6 bars of 16mm φ
2-1 1104 6 bars of 16mm φ
1-Plinth 1104 6 bars of 16mm φ
Plinth – footing 1104 6 bars of 16mm φ
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 230/293
230
For Column 11:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 2900 25.8 279.26 93.54 7.20 93.54
5-4 2750 25.5 806.49 108.74 20.57 108.74
4-3 2750 25.5 1307.98 108.74 33.35 108.74
3-2 2750 25.5 1809.47 108.74 46.14 108.74
2-1 2750 25.5 2310.96 108.74 58.93 108.74
1- Plinth 4750 29.5 2812.45 108.74 82.97 108.74
Plinth –
Footing - 29.5 2861.68 0 84.42 84.42
By the help of SP16, chart no: 32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.10 0.06 0.02 0.4
5-4 0.29 0.07 0.02 0.4
4-3 0.47 0.07 0.06 1.2
3-2 0.66 0.07 0.1 22-1 0.84 0.07 0.16 3.2
1- Plinth 1.02 0.07 0.2 4
Plinth – Footing 1.04 0.05 0.2 4
For P less than 0.8, Provide P = 0.8%
Ast =0.8
100 x 230 x 600 = 1104 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 231/293
231
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
For P = 1.2%
Ast =1.2
100x 230 x 600 = 1656 mm2
No. of bars of 20mmφ bars =4 x 1656
π x (20)2 = 5.27, say 6 bars
Therefore provide 6 bars of 20mmφ bars.
For P = 2%
Ast =2
100x 230 x 600 = 2760 mm2
No. of bars of 25mmφ bars =4 x 2760
π x (25)2 = 5.62 bars say 6 bars
Therefore provide 6 bars of 25mmφ bars.
For P = 3.2%
Ast =3.2
100x 230 x 600 = 4416 mm2
No. of bars of 25mmφ bars =4 x 4416
π x (25)2 = 9 bars
Therefore provide 10 bars of 25mmφ bars. (Each side 5bars)
For P = 4%
Ast =4
100x 230 x 600 = 5520 mm2
No. of bars of 25mmφ bars =4 x 5520
π x (25)2 = 11.24 say 12 bars
Therefore provide 12 bars of 25mmφ bars.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 232/293
232
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4
x diameter of max main steel bar =1
4
x 25 = 6.25mm say 8mm
Maximum of two values =8mm.
Design of pitch:
1. Least lateral dimension = 230mm
2. 16 x diameter of main steel bar = 16 x 25 = 400 mm
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ 4-3 1656 6 bars of 20mm φ
3-2 2760 6 bars of 25mm φ
2-1 4416 10 bars of 25mm φ
1-Plinth 5520 12 bars of 25mm φ
Plinth – footing 5520 12 bars of 25mm φ
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 233/293
233
For Column 02:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 2900 25.8 180.53 155.8 4.66 155.80
5-4 2750 25.5 551.39 153.37 14.06 153.37
4-3 2750 25.5 922.25 153.37 23.52 153.37
3-2 2750 25.5 1293.11 153.37 32.97 153.37
2-1 2750 25.5 1663.97 153.37 42.43 153.37
1- Plinth 4750 29.5 2034.83 153.37 60.03 153.37
Plinth –
Footing
-
29.5 2123.66 0 62.65 62.65
By the help of SP16, chart no:32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.07 0.09 0.04 0.8
5-4 0.20 0.09 0.04 0.8
4-3 0.33 0.09 0.06 1.2
3-2 0.47 0.09 0.08 1.6
2-1 0.60 0.09 0.1 2
1- Plinth 0.74 0.09 0.14 2.8
Plinth – Footing 0.77 0.04 0.16 3.2
For P = 0.8%
Ast =0.8
100x 230 x 600 = 1104 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 234/293
234
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
For P=1.2%
Ast =1.2
100x 230 x 600 = 1656 mm2
No. of bars of 20mmφ bars =4 x 1656
π x (20)2 = 5.27 say 6 bars
Therefore provide 6 bars of 20mmφ bars.
For P=1.6%
Ast =1.6
100x 230 x 600 = 2208 mm2
No. of bars of 25mmφ bars =4 x 2208
π x (25)2 = 4.5 say 6 bars
Therefore provide 6 bars of 25mmφ bars.
For P = 2%
Ast =2
100x 230 x 600 = 2760 mm2
No. of bars of 25mmφ bars =4 x 2760
π x (25)2 = 5.62 bars say 6 bars
Therefore provide 6 bars of 25mmφ bars.
For P = 2.8%
Ast =2.8
100x 230 x 600 = 3864 mm2
No. of bars of 25mmφ bars =4 x 3864
π x (25)2 = 7.87 bars say 8 bars
Therefore provide 8 bars of 25mmφ bars.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 235/293
235
For P = 3.2%
Ast =3.2
100x 230 x 600 = 4416 mm2
No. of bars of 25mmφ bars =4 x 4416
π x (25)2 = 9 bars
Therefore provide 10 bars of 25mmφ bars. (Each side 5bars)
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4x diameter of max main steel bar =
1
4x 25 = 6.25mm say 8mm
Maximum of two values =8mm.
Design of pitch:
1. Least lateral dimension = 230mm
2. 16 x diameter of main steel bar = 16 x 25 = 400mm
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1656 6 bars of 20mm φ
3-2 2208 6 bars of 25mm φ
2-1 2760 6 bars of 25mm φ
1-Plinth 3864 8 bars of 25mm φ
Plinth – footing 4416 10 bars of 25mm φ
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 236/293
236
For frame 24-15-06:
Columns are C24 at left end, C15 at middle and C06 at right end of the frame.
Section: 230mm x 600mm
Cover (d‟) = 50mm
Minimum eccentricity (ex,min) =unsupported length
500+
lateral dimension
30or
= 20mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 237/293
237
f ck x b x D = 20 x 230 x 600 = 2760000N = 2760 KN
f ck x b x D2 = 20 x 230 x (600)2 = 1676 x 106 N-mm = 1676 KN-m
For Column 24:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 2900 25.8 137.01 68.42 3.53 68.42
5-4 2750 25.5 339.45 47.54 8.66 47.54
4-3 2750 25.5 541.89 47.54 13.82 47.54
3-2 2750 25.5 744.33 47.54 18.98 47.54
2-1 2750 25.5 946.77 47.54 24.14 47.54
1- Plinth 4750 29.5 1149.21 47.54 33.90 47.54
Plinth –
Footing
-
29.5 1211.01 0 35.72 35.72
By the help of SP16, chart no: 32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.05 0.04 0.01 0.2
5-4 0.12 0.03 0.01 0.2
4-3 0.20 0.03 0.01 0.2
3-2 0.27 0.03 0.01 0.2
2-1 0.34 0.03 0.01 0.2
1- Plinth 0.42 0.03 0.01 0.2
Plinth – Footing 0.44 0.02 0.01 0.2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 238/293
238
Therefore, provide P = 0.8%
Ast =0.8
100x 230 x 600 = 1104 mm2
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4x diameter of max main steel bar =
1
4x 16 = 4mm
Maximum of two values =6mm.
But in the recent construction the usage of 6mm bars is outdated. Therefore consider
minimum 8mm dia bars.
Design of pitch:
1.
Least lateral dimension = 230mm2. 16 x diameter of main steel bar = 16 x 16 = 256
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1104 6 bars of 16mm φ
2-1 1104 6 bars of 16mm φ
1-Plinth 1104 6 bars of 16mm φ
Plinth – footing 1104 6 bars of 16mm φ
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 239/293
239
For Column 15:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 2900 25.8 279.26 93.54 7.20 93.54
5-4 2750 25.5 702.9 63.86 17.92 63.86
4-3 2750 25.5 1126.54 63.86 28.73 63.86
3-2 2750 25.5 1550.18 63.86 39.53 63.86
2-1 2750 25.5 1973.82 63.86 50.33 63.86
1- Plinth 4750 29.5 2397.46 63.86 70.73 70.73
Plinth –
Footing - 29.5 2446.69 0 72.18 72.18
By the help of SP16, chart no: 32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2 P
f ck From chart
P (%)
Roof – 5 0.10 0.06 0.01 0.2
5-4 0.25 0.04 0.01 0.2
4-3 0.41 0.04 0.02 0.4
3-2 0.56 0.04 0.06 1.22-1 0.72 0.04 0.1 2
1- Plinth 0.87 0.04 0.16 3.2
Plinth – Footing 0.89 0.04 0.16 3.2
For P less than 0.8, Provide P = 0.8%
Ast =0.8
100 x 230 x 600 = 1104 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 240/293
240
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
For P = 1.2%
Ast =1.2
100x 230 x 600 = 1656 mm2
No. of bars of 20mmφ bars =4 x 1656
π x (20)2 = 5.27, say 6 bars
Therefore provide 6 bars of 20mmφ bars.
For P = 2%
Ast =2
100x 230 x 600 = 2760 mm2
No. of bars of 25mmφ bars =4 x 2760
π x (25)2 = 5.62 bars say 6 bars
Therefore provide 6 bars of 25mmφ bars.
For P = 3.2%
Ast =3.2
100x 230 x 600 = 4416 mm2
No. of bars of 25mmφ bars =4 x 4416
π x (25)2 = 9 bars
Therefore provide 10 bars of 25mmφ bars. (Each side 5bars)
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4x diameter of max main steel bar =
1
4x 25 = 6.25mm say 8mm
Maximum of two values =8mm.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 241/293
241
Design of pitch:
1. Least lateral dimension = 230mm
2. 16 x diameter of main steel bar = 16 x 25 = 400 mm
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1656 6 bars of 20mm φ
2-1 2760 6 bars of 25mm φ
1-Plinth 4416 10 bars of 25mm φ
Plinth – footing 4416 10 bars of 25mm φ
For Column 06:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 2900 25.8 180.53 155.8 4.66 155.80
5-4 2750 25.5 461.69 103.08 11.77 103.08
4-3 2750 25.5 742.85 103.08 18.94 103.08
3-2 2750 25.5 1024.01 103.08 26.11 103.08
2-1 2750 25.5 1305.17 103.08 33.28 103.08
1- Plinth 4750 29.5 1586.33 103.08 46.80 103.08
Plinth –
Footing
-
29.5 1675.16 0 49.42 49.42
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 242/293
242
By the help of SP16, chart no:32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.07 0.09 0.04 0.8
5-4 0.17 0.06 0.02 0.4
4-3 0.27 0.06 0.02 0.4
3-2 0.37 0.06 0.02 0.4
2-1 0.47 0.06 0.04 0.8
1- Plinth 0.57 0.06 0.08 1.6
Plinth – Footing 0.61 0.03 0.08 1.6
For P = 0.8% and P <0.8%
Ast =0.8
100x 230 x 600 = 1104 mm2
No. of bars of 16mmφ bars = 4 x 1104 π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
For P=1.6%
Ast =1.6
100x 230 x 600 = 2208 mm2
No. of bars of 25mmφ bars =4 x 2208
π x (25)2 = 4.5 say 6 bars
Therefore provide 6 bars of 25mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4x diameter of max main steel bar =
1
4x 25 = 6.25mm say 8mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 243/293
243
Maximum of two values =8mm.
Design of pitch:
1. Least lateral dimension = 230mm
2. 16 x diameter of main steel bar = 16 x 25 = 400mm
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm2) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1104 6 bars of 16mm φ
2-1 1104 6 bars of 16mm φ
1-Plinth 2208 6 bars of 25mm φ
Plinth – footing 2208 6 bars of 25mm φ
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 244/293
244
For frame 25-16-07:
Columns are C25 at left end, C16 at middle and C07 at right end of the frame.
Section: 230mm x 600mm
Cover (d‟) = 50mm
Minimum eccentricity (ex,min) =unsupported length
500+
lateral dimension
30or
= 20mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 245/293
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 246/293
246
For P < 0.8%, Provide P = 0.8%
Ast =0.8
100x 230 x 600 = 1104 mm2
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4x diameter of max main steel bar =
1
4x 16 = 4mm
Maximum of two values =6mm.
But in the recent construction the usage of 6mm bars is outdated. Therefore consider
minimum 8mm dia bars.
Design of pitch:
1.
Least lateral dimension = 230mm2. 16 x diameter of main steel bar = 16 x 16 = 256
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1104 6 bars of 16mm φ
2-1 1104 6 bars of 16mm φ
1-Plinth 1104 6 bars of 16mm φ
Plinth – footing 1104 6 bars of 16mm φ
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 247/293
247
For Column 16:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 2900 25.8 279.26 68.42 7.20 68.42
5-4 2750 25.5 744.68 42.84 18.99 42.84
4-3 2750 25.5 1210.1 42.84 30.86 42.84
3-2 2750 25.5 1675.52 42.84 42.73 42.84
2-1 2750 25.5 2140.94 42.84 54.59 54.59
1- Plinth 4750 29.5 2606.36 42.84 76.89 76.89
Plinth –
Footing - 29.5 2655.59 0 78.34 78.34
By the help of SP16, chart no: 32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.10 0.04 0.01 0.2
5-4 0.27 0.03 0.01 0.2
4-3 0.44 0.03 0.02 0.4
3-2 0.61 0.03 0.08 1.62-1 0.78 0.03 0.12 2.4
1- Plinth 0.94 0.05 0.18 3.6
Plinth – Footing 0.96 0.05 0.18 3.6
For P less than 0.8, Provide P = 0.8%
Ast =0.8
100 x 230 x 600 = 1104 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 248/293
248
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
For P = 1.6%
Ast =1.6
100x 230 x 600 = 2208 mm2
No. of bars of 25mmφ bars =4 x 2208
π x (20)2 = 4.5 say 6 bars
Therefore provide 6 bars of 25mmφ bars.
For P = 2.4%
Ast =2.4
100x 230 x 600 = 3312 mm2
No. of bars of 25mmφ bars =4 x 3312
π x (25)2 = 6.77 bars say 8 bars
Therefore provide 8 bars of 25mmφ bars.
For P = 3.6%
Ast =3.6
100x 230 x 600 = 4968 mm2
No. of bars of 25mmφ bars =4 x 4968
π x (25)2 = 10.12, say 12 bars
Therefore provide 12 bars of 25mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4x diameter of max main steel bar =
1
4x 25 = 6.25mm say 8mm
Maximum of two values =8mm.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 249/293
249
Design of pitch:
1. Least lateral dimension = 230mm
2. 16 x diameter of main steel bar = 16 x 25 = 400 mm
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 2208 6 bars of 25mm φ
2-1 3312 8 bars of 25mm φ
1-Plinth 4968 12 bars of 25mm φ
Plinth – footing 4968 12 bars of 25mm φ
For Column 07:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 2900 25.8 180.53 155.8 4.66 155.80
5-4 2750 25.5 511.2 130.75 13.04 130.75
4-3 2750 25.5 841.87 130.75 21.47 130.75
3-2 2750 25.5 1172.54 130.75 29.90 130.75
2-1 2750 25.5 1503.21 130.75 38.33 130.75
1- Plinth 4750 29.5 1833.88 130.75 54.10 130.75
Plinth –
Footing
-
29.5 1922.71 0 56.72 56.72
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 250/293
250
By the help of SP16, chart no:32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.07 0.09 0.04 0.8
5-4 0.19 0.08 0.02 0.4
4-3 0.31 0.08 0.04 0.8
3-2 0.42 0.08 0.06 1.2
2-1 0.54 0.08 0.08 1.6
1- Plinth 0.66 0.08 0.12 2.4
Plinth – Footing 0.70 0.03 0.12 2.4
For P < 0.8%, Provide P = 0.8%
Ast =0.8
100x 230 x 600 = 1104 mm2
No. of bars of 16mmφ bars = 4 x 1104 π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
For P=1.2%
Ast =1.2
100x 230 x 600 = 1656 mm2
No. of bars of 20mmφ bars =4 x 1656
π x (20)2 = 5.27 say 6 bars
Therefore provide 6 bars of 20mmφ bars.
For P=1.6%
Ast =1.6
100x 230 x 600 = 2208 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 251/293
251
No. of bars of 25mmφ bars =4 x 2208
π x (25)2 = 4.5 say 6 bars
Therefore provide 6 bars of 25mmφ bars.
For P = 2.4%
Ast =2.4
100x 230 x 600 = 3312 mm2
No. of bars of 25mmφ bars =4 x 3312
π x (25)2 = 6.74 bars say 8 bars
Therefore provide 8 bars of 25mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4x diameter of max main steel bar =
1
4x 25 = 6.25mm say 8mm
Maximum of two values =8mm.
Design of pitch:
1. Least lateral dimension = 230mm
2. 16 x diameter of main steel bar = 16 x 25 = 400mm
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 252/293
252
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1656 6 bars of 20mm φ
2-1 2208 6 bars of 25mm φ
1-Plinth 3312 8 bars of 25mm φ
Plinth – footing 3312 8 bars of 25mm φ
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 253/293
253
For frame 26-17-08:
Columns are C26 at left end, C17 at middle and C08 at right end of the frame.
Section: 230mm x 600mm
Cover (d‟) = 50mm
Minimum eccentricity (ex,min) =unsupported length
500+
lateral dimension
30or
= 20mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 254/293
254
f ck x b x D = 20 x 230 x 600 = 2760000N = 2760 KN
f ck x b x D2 = 20 x 230 x (600)2 = 1676 x 106 N-mm = 1676 KN-m
For Column 26:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 2900 25.8 137.01 68.42 3.53 68.42
5-4 2750 25.5 306.92 36.55 7.83 36.55
4-3 2750 25.5 476.83 36.55 12.16 36.55
3-2 2750 25.5 646.74 36.55 16.49 36.55
2-1 2750 25.5 816.65 36.55 20.82 36.55
1- Plinth 4750 29.5 986.56 36.55 29.10 36.55
Plinth –
Footing
-
29.5 1048.36 0 30.93 30.93
By the help of SP16, chart no: 32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2 P
f ck From chart
P (%)
Roof – 5 0.05 0.04 0.01 0.2
5-4 0.11 0.02 0.01 0.2
4-3 0.17 0.02 0.01 0.2
3-2 0.23 0.02 0.01 0.2
2-1 0.30 0.02 0.01 0.2
1- Plinth 0.36 0.02 0.01 0.2
Plinth – Footing 0.38 0.02 0.01 0.2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 255/293
255
For P < 0.8%, provide P = 0.8%
Ast =0.8
100x 230 x 600 = 1104 mm2
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4x diameter of max main steel bar =
1
4x 16 = 4mm
Maximum of two values =6mm.
But in the recent construction the usage of 6mm bars is outdated. Therefore consider
minimum 8mm dia bars.
Design of pitch:
1.
Least lateral dimension = 230mm2. 16 x diameter of main steel bar = 16 x 16 = 256
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1104 6 bars of 16mm φ
2-1 1104 6 bars of 16mm φ
1-Plinth 1104 6 bars of 16mm φ
Plinth – footing 1104 6 bars of 16mm φ
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 256/293
256
For Column 17:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 2900 25.8 279.26 68.42 7.20 68.42
5-4 2750 25.5 685.14 36.55 17.47 36.55
4-3 2750 25.5 1091.02 36.55 27.82 36.55
3-2 2750 25.5 1496.9 36.55 38.17 38.17
2-1 2750 25.5 1902.78 36.55 48.52 48.52
1- Plinth 4750 29.5 2308.66 36.55 68.11 68.11
Plinth –
Footing - 29.5 2357.89 0 69.56 69.56
By the help of SP16, chart no: 32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2 P
f ck From chart
P (%)
Roof – 5 0.10 0.04 0.01 0.2
5-4 0.25 0.02 0.01 0.2
4-3 0.40 0.02 0.01 0.2
3-2 0.54 0.02 0.04 0.82-1 0.69 0.03 0.1 2
1- Plinth 0.84 0.04 0.14 2.8
Plinth – Footing 0.85 0.04 0.14 2.8
For P less than 0.8, Provide P = 0.8%
Ast =0.8
100 x 230 x 600 = 1104 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 257/293
257
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
For P = 2%
Ast =2
100x 230 x 600 = 2760 mm2
No. of bars of 25mmφ bars =4 x 2760
π x (25)2 = 5.62 bars say 6 bars
Therefore provide 6 bars of 25mmφ bars.
For P = 2.8%
Ast =2.8
100x 230 x 600 = 3864 mm2
No. of bars of 25mmφ bars =4 x 3864
π x (25)2 = 7.87, say 8 bars
Therefore provide 8 bars of 25mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4x diameter of max main steel bar =
1
4x 25 = 6.25mm say 8mm
Maximum of two values =8mm.
Design of pitch:
1. Least lateral dimension = 230mm
2. 16 x diameter of main steel bar = 16 x 25 = 400 mm
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 258/293
258
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1104 6 bars of 16mm φ
2-1 2760 6 bars of 25mm φ
1-Plinth 3864 8 bars of 25mm φ
Plinth – footing 3864 8 bars of 25mm φ
For Column 08:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 2900 25.8 180.53 155.8 4.66 155.80
5-4 2750 25.5 480.91 113.98 12.26 113.98
4-3 2750 25.5 781.29 113.98 19.92 113.98
3-2 2750 25.5 1081.67 113.98 27.58 113.98
2-1 2750 25.5 1382.05 113.98 35.24 113.98
1- Plinth 4750 29.5 1682.43 113.98 49.63 113.98
Plinth –
Footing
-
29.5 1771.26 0 52.25 52.25
By the help of SP16, chart no: 32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 259/293
259
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.07 0.09 0.04 0.8
5-4 0.17 0.07 0.02 0.4
4-3 0.28 0.07 0.02 0.4
3-2 0.39 0.07 0.04 0.8
2-1 0.50 0.07 0.06 1.2
1- Plinth 0.61 0.07 0.1 2
Plinth – Footing 0.64 0.03 0.1 2
For P = 0.8%
Ast = 0.8100
x 230 x 600 = 1104 mm2
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
For P=1.2%
Ast = 1.2100
x 230 x 600 = 1656 mm2
No. of bars of 20mmφ bars =4 x 1656
π x (20)2 = 5.27 say 6 bars
Therefore provide 6 bars of 20mmφ bars.
For P = 2%
Ast =2
100x 230 x 600 = 2760 mm2
No. of bars of 25mmφ bars =4 x 2760
π x (25)2 = 5.62 bars say 6 bars
Therefore provide 6 bars of 25mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 260/293
260
2. 1
4x diameter of max main steel bar =
1
4x 25 = 6.25mm say 8mm
Maximum of two values =8mm.
Design of pitch:
1. Least lateral dimension = 230mm
2. 16 x diameter of main steel bar = 16 x 25 = 400mm
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm2) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1104 6 bars of 16mm φ
2-1 1656 6 bars of 20mm φ
1-Plinth 2760 6 bars of 25mm φ
Plinth – footing 2760 6 bars of 25mm φ
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 261/293
261
For frame 27-18-09:
Columns are C27 at left end, C18 at middle and C09 at right end of the frame.
Section: 230mm x 600mm
Cover (d‟) = 50mm
Minimum eccentricity (ex,min) =unsupported length
500+
lateral dimension
30or
= 20mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 262/293
262
f ck x b x D = 20 x 230 x 600 = 2760000N = 2760 KN
f ck x b x D2 = 20 x 230 x (600)2 = 1676 x 106 N-mm = 1676 KN-m
For Column 27:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 3050 26.1 102.83 64.85 2.68 64.85
5-4 2900 25.8 265.825 50.61 6.86 50.61
4-3 2900 25.8 428.82 50.61 11.06 50.61
3-2 2900 25.8 591.815 50.61 15.27 50.61
2-1 2900 25.8 754.81 50.61 19.47 50.61
1- Plinth 4900 29.8 917.805 50.61 27.35 50.61
Plinth –
Footing
-
29.8 953.88 0 28.43 28.43
By the help of SP16, chart no: 32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.04 0.04 0.01 0.2
5-4 0.10 0.03 0.01 0.2
4-3 0.16 0.03 0.01 0.2
3-2 0.21 0.03 0.01 0.2
2-1 0.27 0.03 0.01 0.2
1- Plinth 0.33 0.03 0.01 0.2
Plinth – Footing 0.35 0.02 0.01 0.2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 263/293
263
For P < 0.8, provide P = 0.8%
Ast =0.8
100x 230 x 600 = 1104 mm2
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4x diameter of max main steel bar =
1
4x 16 = 4mm
Maximum of two values =6mm.
But in the recent construction the usage of 6mm bars is outdated. Therefore consider
minimum 8mm dia bars.
Design of pitch:
1.
Least lateral dimension = 230mm2. 16 x diameter of main steel bar = 16 x 16 = 256
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1104 6 bars of 16mm φ
2-1 1104 6 bars of 16mm φ
1-Plinth 1104 6 bars of 16mm φ
Plinth – footing 1104 6 bars of 16mm φ
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 264/293
264
For Column 18:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 3050 26.1 202.61 89.7 5.29 89.70
5-4 2900 25.8 586.58 86.44 15.13 86.44
4-3 2900 25.8 970.55 86.44 25.04 86.44
3-2 2900 25.8 1354.52 86.44 34.95 86.44
2-1 2900 25.8 1738.49 86.44 44.85 86.44
1- Plinth 4900 29.8 2122.46 86.44 63.25 86.44
Plinth –
Footing - 29.8 2152.25 0 64.14 64.14
By the help of SP16, chart no: 32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.07 0.05 0.01 0.2
5-4 0.21 0.05 0.01 0.2
4-3 0.35 0.05 0.02 0.4
3-2 0.49 0.05 0.04 0.82-1 0.63 0.05 0.08 1.6
1- Plinth 0.77 0.05 0.14 2.8
Plinth – Footing 0.78 0.04 0.14 2.8
Therefore, provide P = 0.8%
Ast =0.8
100 x 230 x 600 = 1104 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 265/293
265
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
Therefore provide 6 bars of 16mmφ bars.
For P = 1.6%
Ast =1.6
100x 230 x 600 = 2208 mm2
No. of bars of 20mmφ bars =4 x 2208
π x (20)2 = 8 bars
Therefore provide 8 bars of 20mmφ bars.
For P = 2.8%
Ast =2.8
100x 230 x 600 = 3864 mm2
No. of bars of 25mmφ bars =4 x 3864
π x (25)2 = 7.87 bars say 8 bars
Therefore provide 8 bars of 25mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 1
4x diameter of max main steel bar =
1
4x 25 = 6.25mm say 8mm
Maximum of two values =8mm.
Design of pitch:
1. Least lateral dimension = 230mm
2. 16 x diameter of main steel bar = 16 x 16 = 256
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 266/293
266
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1104 6 bars of 16mm φ
2-1 2208 8 bars of 20mm φ
1-Plinth 3864 8 bars of 25mm φ
Plinth – footing 3864 8 bars of 25mm φ
For Column 09:
To find MuD:
Storey Length
(mm)
ex,min (mm) Pu (KN) Mux (KN-
m)
Mux,min
(KN-m)
MuD
Roof – 5 3050 26.1 133.97 136.67 3.50 136.67
5-4 2900 25.8 390.87 128.22 10.08 128.22
4-3 2900 25.8 647.77 128.22 16.71 128.22
3-2 2900 25.8 904.67 128.22 23.34 128.22
2-1 2900 25.8 1161.57 128.22 29.97 128.22
1- Plinth 4900 29.8 1418.47 128.22 42.27 128.22
Plinth –
Footing
-
29.8 1468.06 0 43.75 43.75
By the help of SP16, chart no: 32,
FromPu
f ck x b x Dand
MuD
f ck x b x D2 Plot theP
f ck
Where p is the percentage of steel reinforcement
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 267/293
267
Storey Pu
f ck x b x D
MuD
f ck x b x D2
P
f ck From chart
P (%)
Roof – 5 0.05 0.08 0.04 0.8
5-4 0.14 0.08 0.02 0.4
4-3 0.23 0.08 0.02 0.4
3-2 0.33 0.08 0.04 0.8
2-1 0.42 0.08 0.04 0.8
1- Plinth 0.51 0.08 0.06 1.2
Plinth – Footing 0.53 0.03 0.06 1.2
Provide min P = 0.8%
Ast = 0.8100
x 230 x 600 = 1104 mm2
No. of bars of 16mmφ bars =4 x 1104
π x (16)2 = 5.49 say 6 bars
For P=1.2%
Ast =1.2
100x 230 x 600 = 1656 mm2
No. of bars of 20mmφ bars =4 x 1656
π x (20)2 = 5.27 say 6 bars
Therefore provide 6 bars of 20mmφ bars.
Design of lateral ties:
1. Should not be less than 6mm
2. 14 x diameter of max main steel bar = 14 x 20 = 5mm
Maximum of two values =6mm.
But in the recent construction the usage of 6mm bars is outdated. Therefore consider
minimum 8mm dia bars.
Design of pitch:
1. Least lateral dimension = 230mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 268/293
268
2. 16 x diameter of main steel bar = 16 x 16 = 256
3. 300mm
Minimum of the above values is considered.
Therefore, provide 8mm φ bars @230mm c/c.
No. of bars:
Storey Ast (mm ) No.of bars:
Roof-5 1104 6 bars of 16mm φ
5-4 1104 6 bars of 16mm φ
4-3 1104 6 bars of 16mm φ
3-2 1104 6 bars of 16mm φ
2-1 1104 6 bars of 16mm φ
1-Plinth 1656 6 bars of 20mm φ
Plinth – footing 1656 6 bars of 20mm φ
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 269/293
269
6. DESIGN OF FOOTINGS
In this design of footing, the loads are known from the column analysis. The working load is
used for the footing design than the ultimate load. Footing is a member through which the
load of the superstructure is transferred to the sub soil. Therefore the safe bearing capacity is
the main factor in design of footings. From the information provided and conducting test on
sub soil, it is decided that the Safe Bearing Capacity (SBC) of the soil is 250 KN/m2.
Therefore the footing is isolated rectangular sloped footing. The slope is provided to decrease
the amount of concrete in the construction which results into an economic construction.
From the analysis of frames and columns, we considered 6 frames and each frame
consists of 3 footings so totally 18 footings are to be designed. But in this project we designthe most critical any 3 footings based on the load carried are selected and the design of
remaining footings follow the same.
Footing F19:
Steel : Fe415
Concrete : M20
Column : 230mm x 600mm (bmm x Dmm)
Load from column (Pu) : 982.185 KN
Working load (P) :982.185
1.5= 654.79 KN
Self weight of footing : 10% of Pu
SBC of soil : 250 KN/m2
Area of footing (Af ) :1.1 x P
SBC of soil=
1.1 x 654.79
250= 2.88 m2
Consider,D-b
2=
600 - 230
2= 185 mm
Length of footing (Lf ) = 185mm + (√(185)2 + 2.88 x 106 ) = 1892.11
say 1900mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 270/293
270
Breadth of footing (Bf ) =Af
Lf =
2.88 x 106
1900= 1515.79 say 1550 mm
Area of footing provided = Lf x Bf = 2000 x 1520 = 2.95 x 106 = 2.95 m2
Wu =Pu
Af =
982.185
2.95= 332.95 KN/m2
X1 =
Lf - D
2 =
1900 - 600
2 = 650 mm
Y1 =Bf - b
2=
1550 - 230
2= 660 mm
Depth of footing for 2-way bending:
Mux =Wu x Bf x X1
2
2=
332.94 x 1.550 x (0.65)2
2= 109.02 KN-m
Muy =Wu x Lf x Y1
2
2=
332.94 x 1.9 x (0.66)2
2= 137.78 KN-m
Therefore, max bending moment = Mu = 137.78 KN-m
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 271/293
271
b' = b + 2 x e = 230 + 2 x 50 = 330 mm
D' = D + 2 x e = 600 + 2 x 50 = 700 mm
Clear cover = 50mm
Assume 10mm bars
d'x = 50 +10
2= 55mm
d'y = 50 + (3 x102
)= 65mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 272/293
272
Depth of foundation:
(Df )x =
+ d'x = √109.02 x 106
0.138 x 20 x 330+ 55 = 400.97 mm
(Df )y =
+ d'y = √ 137.78 x 10
6
0.138 x 20 x 700 + 65 = 332.05 mm
Therefore, maximum (Df ) = 400.97 mm say 450mm
Therefore dx = 450 – 55 = 395mm
dy = 450 – 65 = 385mm
Provide Df,min = 150mm
df,min ( x-direction) = 150 - 55 = 95mm
df,min ( y-direction) = 150 - 65 = 85mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 273/293
273
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 274/293
274
Check for two way shear:
Consider a section „dy
2 ‟ from the face of the column.
L2 = D +dy
2+
dy
2= 600 + 385 = 985 mm
B2 = b +dy
2+
dy
2= 230 + 385 = 615 mm
d2 = Df – (Df – Df,min) x
(dy
2- 50)
(X1 - 50) – d'y
= 450 – (450 – 150) x
(385
2- 50)
(650 - 50) – 65 = 313.75 mm
Area of resisting shear (A2) = 2 x(L2 + B2) x d2
= 2 x (985 + 615) x 313.75
= 1004000 mm2
Shear strength of concrete for two way:
τuc2 = k s x τuc
where, τuc = 0.25 x √f ck = 0.25 x √20 = 1.12 N/mm2
k s = (0.5 + βc) < 1 else =1
βc =
b
D =
230
600 = 0.385
therefore, k s = (0.5 + βc) = 0.5 + 0.385 = 0.885 <1
k s = 0.885
τuc2 = k s x τuc = 0.885 x 1.12 = 0.99 N/mm2
Internal load carrying capacity (Vuc2) = 1004000 x 0.99 = 993960 N
= 993.96 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 275/293
275
External load (VuD2) = Wu x (Lf x Bf – L2 x B2)
= 332.94 x (1.900 x 1.550 – 0.985 x 0.615)
= 778.82 KN
Therefore, Vuc2 > VuD2 (SAFE)
Design of Steel mesh:
Mux = 0.87 x f y x Astx x dx x (1-f y x Astx
f ck x b' x dx)
109.02 x 106 = 0.87 x 415 x Astx x 395 x (1-415 x Astx
20 x 330 x 395
)
Astx = 890.72 mm2
No. of 10mmφ bars =4 x 890.74
π x 102 = 11.34 say 12 bars
Muy = 0.87 x f y x Asty x dy x (1-f y x Astx
f ck x D' x dy)
137.78 x 106 = 0.87 x 415 x Astx x 385 x (1- 415 x Astx
20 x 700 x 385)
Asty = 1081.2 mm2
No. of 10mmφ bars =4 x 1081.2
π x 102 = 13.77 say 14 bars
Check for one way shear:
Consider a section at distance„d‟ from the face of column
d1 = Df – (Df – Df,min) x(dy- 50)
(Y1 - 50) – d'y
= 450 – (450 – 150) x(385- 50)
(660 - 50) – 65 = 220.24 mm
L1 = D + 2 x dy = 600 + 2 x 385 = 1370 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 276/293
276
Area resisting shear (A1) = (Lf x Dy,min) + (d1 – Dy,min) x (Lf + L1
2)
= (1900 x 150) + (220.24 – 150) x (1900 + 1370
2)
= 399842.4 mm2
Asty = 14 bars of 10mm dia = 1099.56 mm2
Pt =100 x Asty
A1=
100 x 1099.56
399842.4= 0.28
From IS456-2000, P73, Table 19
P τc (N/mm2)
0.25 0.36
0.28 ?
0.50 0.48
τc = 0.36 +(0.48 - 0.36)
(0.5 - 0.25)x (0.28 – 0.25) = 0.38 N/mm2
Internal shear resisting capacity =0.38 x 399842.4
1000= 151.94 KN
External shear = Wu x Lf x (Y1 – dy)
= 332.94 x 1.900 x (0.660 – 385)
= 173.96 KN
Internal shear resisting capacity < External Shear (NOT SAFE)
Increase the depth.
Shear =load
area
0.38 =173.96 x 103
A1
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 277/293
277
A1 =457789.47 mm2
To calculate d1:
A1 = (Lf x Dy,min) + (d1 – Dy,min) x (Lf + L1
2 )
457789.47 = (1900 x 150) + (d1 – 150) x (1900 + 1370
2)
d1 = 255.68 mm
Footing F11:
Load from column (Pu) : 2861.68 KN
Working load (P) :2861.68
1.5= 1907.79 KN
Self weight of footing : 10% of Pu
SBC of soil : 250 KN/m2
Area of footing (Af ) :1.1 x P
SBC of soil=
1.1 x 1907.79
250= 8.4 m2
Consider,D-b
2=
600 - 230
2= 185 mm
Length of footing (Lf ) = 185mm + (√(185)2 + 8.4 x 106 ) = 3089.17
say 3100mm
Breadth of footing (Bf ) =Af
Lf =
8.4 x 106
3100= 2709.67 say 2725 mm
Area of footing provided = Lf x Bf = 3100 x 2725 = 8.45 x 106 = 8.45 m2
Wu =Pu
Af =
2861.68
8.45= 338.66 KN/m2
X1 =Lf - D
2=
3100 - 600
2= 1250 mm
Y1 = Bf - b2
= 2725 - 2302
= 1247.5 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 278/293
278
Depth of footing for 2-way bending:
Mux =Wu x Bf x X1
2
2=
338.66 x 2.725 x (1.25)2
2= 720.98 KN-m
Muy =Wu x Lf x Y1
2
2=
338.66 x 3.1 x (1.2475)2
2= 816.92 KN-m
Therefore, max bending moment = Mu = 816.92 KN-m
b' = b + 2 x e = 230 + 2 x 50 = 330 mm
D' = D + 2 x e = 600 + 2 x 50 = 700 mm
Clear cover = 50mm
Assume 16mm bars
d'x = 50 +16
2= 58 mm
d'y = 50 + (3 x16
2) = 74 mm
Depth of foundation:
(Df )x =
+ d'x = √720.98 x 106
0.138 x 20 x 330+ 58 = 947.71 mm
(Df )y =
+ d'y = √816.92 x 106
0.138 x 20 x 700+ 74 = 724.26 mm
Therefore, maximum (Df ) = 947.71 mm say 1000mm
Therefore dx = 1000 – 58 = 942 mm
dy = 1000 – 74 = 926 mm
Provide Df,min = 150mm
df,min ( x-direction) = 150 - 58 = 92 mm
df,min ( y-direction) = 150 - 74 = 76 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 279/293
279
Check for two way shear:
Consider a section „dy
2 ‟ from the face of the column.
L2 = D +dy
2+
dy
2= 600 + 926 = 1526 mm
B2 = b +dy
2+
dy
2= 230 + 926 = 1156 mm
d2 = Df – (Df – Df,min) x
(dy
2- 50)
(X1 - 50) – d'y
= 1000 – (1000 – 150) x
(926
2- 50)
(1250 - 50) – 74 = 633.45 mm
Area of resisting shear (A2) = 2 x(L2 + B2) x d2
= 2 x (1526 + 1156) x 633.45
= 3.4 x 106 mm2
Shear strength of concrete for two way:
τuc2 = k s x τuc
where, τuc = 0.25 x √f ck = 0.25 x √20 = 1.12 N/mm2
k s = (0.5 + βc) < 1 else =1
βc =
b
D =
230
600 = 0.385
Therefore, k s = (0.5 + βc) = 0.5 + 0.385 = 0.885 <1
k s = 0.885
τuc2 = k s x τuc = 0.885 x 1.12 = 0.99 N/mm2
Internal load carrying capacity (Vuc2) = 3.4 x 106 x 0.99 = 3.37 x 106 N
= 3370 KN
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 280/293
280
External load (VuD2) = Wu x (Lf x Bf – L2 x B2)
= 338.66 x (3.1 x 2.725 – 1.526 x 1.156)
= 2263.41 KN
Therefore, Vuc2 > VuD2 (SAFE)
Design of Steel mesh:
Mux = 0.87 x f y x Astx x dx x (1-f y x Astx
f ck x b' x dx)
720.98 x 106 = 0.87 x 415 x Astx x 942 x (1-415 x Astx
20 x 330 x 942
)
Astx = 2555.91 mm2
No. of 16mmφ bars =4 x 2555.91
π x 162 = 12.71 say 13 bars
Muy = 0.87 x f y x Asty x dy x (1-f y x Astx
f ck x D' x dy)
816.92 x 106 = 0.87 x 415 x Astx x 926 x (1- 415 x Astx
20 x 700 x 926)
Asty = 2671.98 mm2
No. of 16mmφ bars =4 x 2671.98
π x 162 = 13.29 say 14 bars
Check for one way shear:
Consider a section at distance„d‟ from the face of column
d1 = Df – (Df – Df,min) x(dy- 50)
(Y1 - 50) – d'y
= 1000 – (1000 – 150) x(926- 50)
(1247.5 - 50) – 74 = 304.21 mm
L1 = D + 2 x dy = 600 + 2 x 926 = 2452 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 281/293
281
Area resisting shear (A1) = (Lf x Dy,min) + (d1 – Dy,min) x (Lf + L1
2)
= (3100 x 150) + (304.21 – 150) x (3100 + 2452
2)
= 893086 mm2
Asty = 14 bars of 10mm dia = 2814.87 mm2
Pt =100 x Asty
A1=
100 x 2814.87
893086= 0.32
From IS456-2000, P73, Table 19
P τc (N/mm2)
0.25 0.36
0.32 ?
0.5 0.48
τc = 0.36 +(0.48 - 0.36)
(0.5 - 0.25)x (0.32 – 0.25) = 0.4 N/mm2
Internal shear resisting capacity =0.4 x 893086
1000= 357.23 KN
External shear = Wu x Lf x (Y1 – dy)
= 338.66 x 3.1 x (1.2475 – 0.926)
= 337.53 KN
Internal shear resisting capacity > External Shear (SAFE)
Footing F07:
Load from column (Pu) : 1922.71 KN
Working load (P) :1922.71
1.5= 1281.81 KN
Self weight of footing : 10% of Pu
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 282/293
282
SBC of soil : 250 KN/m2
Area of footing (Af ) :1.1 x P
SBC of soil=
1.1 x 1281.81
250= 5.64 m2
Consider,D-b
2=
600 - 230
2= 185 mm
Length of footing (Lf ) = 185mm + (√(185)2 + 5.64 x 106 ) = 2567.06
say 2575mm
Breadth of footing (Bf ) =Af
Lf =
5.64 x 106
2575= 2190.29 say 2200 mm
Area of footing provided = Lf x Bf = 2575 x 2200 = 5.665 x 106 = 5.665 m2
Wu =Pu
Af =
1922.71
5.665= 339.4 KN/m2
X1 =Lf - D
2=
2575 - 600
2= 987.5 mm
Y1 =Bf - b
2=
2200 - 230
2= 985 mm
Depth of footing for 2-way bending:
Mux =Wu x Bf x X1
2
2=
339.4 x 2.2 x (0.9875)2
2= 364.06 KN-m
Muy =Wu x Lf x Y1
2
2=
339.4 x 2.575 x (0.985)2
2= 423.97 KN-m
Therefore, max bending moment = Mu = 423.97 KN-m
b' = b + 2 x e = 230 + 2 x 50 = 330 mm
D' = D + 2 x e = 600 + 2 x 50 = 700 mm
Clear cover = 50mm
Assume 12mm bars
d'x = 50 + 122
= 56 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 283/293
283
d'y = 50 + (3 x12
2) = 68 mm
Depth of foundation:
(Df )x =
+ d'x = √364.06 x 106
0.138 x 20 x 330+ 56 = 688.23 mm
(Df )y =
+ d'y = √423.97 x 106
0.138 x 20 x 700+ 68 = 536.45 mm
Therefore, maximum (Df ) = 688.23 mm say 700mm
Therefore dx = 700 – 56 = 644 mm
dy = 700 – 68 = 632 mm
Provide Df,min = 150mm
df,min ( x-direction) = 150 - 56 = 94 mm
df,min ( y-direction) = 150 - 68 = 82 mm
Check for two way shear:
Consider a section „dy
2 ‟ from the face of the column.
L2 = D +dy
2+
dy
2= 600 + 632 = 1232 mm
B2 = b +dy
2+
dy
2= 230 + 632 = 862 mm
d2 = Df – (Df – Df,min) x
(dy
2- 50)
(X1 - 50) – d'y
= 700 – (700 – 150) x
(632
2- 50)
(987.5 - 50) – 68 = 475.95 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 284/293
284
Area of resisting shear (A2) = 2 x(L2 + B2) x d2
= 2 x (1232 + 862) x 475.95
= 1993278.6 mm2
Shear strength of concrete for two way:
τuc2 = k s x τuc
where, τuc = 0.25 x √f ck = 0.25 x √20 = 1.12 N/mm2
k s = (0.5 + βc) < 1 else =1
βc = bD
= 230600
= 0.385
therefore, k s = (0.5 + βc) = 0.5 + 0.385 = 0.885 <1
k s = 0.885
τuc2 = k s x τuc = 0.885 x 1.12 = 0.99 N/mm2
Internal load carrying capacity (Vuc2) = 1993278.6x 0.99 = 1973345.814N
= 1973.35 KN
External load (VuD2) = Wu x (Lf x Bf – L2 x B2)
= 339.4 x (2.575 x 2.2 – 1.232 x 0.862)
= 1562.27 KN
Therefore, Vuc2 > VuD2 (SAFE)
Design of Steel mesh:
Mux = 0.87 x f y x Astx x dx x (1-f y x Astx
f ck x b' x dx)
364.06 x 106 = 0.87 x 415 x Astx x 644 x (1-415 x Astx
20 x 330 x 644)
Astx = 1929.08 mm2
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 285/293
285
No. of 12mmφ bars =4 x 1929.08
π x 122 = 17.1 say 18 bars
Muy = 0.87 x f y x Asty x dy x (1-f y x Astx
f ck x D' x dy)
423.06 x 106 = 0.87 x 415 x Astx x 632 x (1-415 x Astx
20 x 700 x 632)
Asty = 2051.42 mm2
No. of 12mmφ bars =4 x 2051.42
π x 122 = 18.13 say 19 bars
Check for one way shear:
Consider a section at distance„d‟ from the face of column
d1 = Df – (Df – Df,min) x(dy- 50)
(Y1 - 50) – d'y
= 700 – (700 – 150) x(632- 50)
(985 - 50) – 68 = 289.65 mm
L1 = D + 2 x dy = 600 + 2 x 632 = 1864 mm
Area resisting shear (A1) = (Lf x Dy,min) + (d1 – Dy,min) x (Lf + L1
2)
= (2575 x 150) + (289.65 – 150) x (2575 + 1864
2)
= 696203.175 mm2
Asty = 19 bars of 12mm dia = 2148.84 mm2
Pt =100 x Asty
A1=
100 x 2148.84
696203.175= 0.31
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 286/293
286
From IS456-2000, P73, Table 19
P τc (N/mm2)
0.25 0.36
0.31 ?
0.5 0.48
τc = 0.36 +(0.48 - 0.36)
(0.5 - 0.25)x (0.31 – 0.25) = 0.39 N/mm2
Internal shear resisting capacity =0.39 x 696203.175
1000
= 271.52 KN
External shear = Wu x Lf x (Y1 – dy)
= 339.4 x 2.575 x (0.985 – 0.632)
= 308.51 KN
Internal shear resisting capacity < External Shear (NOT SAFE)
Increase the depth.
Shear =load
area
0.39 =308.51 x 103
A1
A1 =791051.28 mm2
To calculate d1:
A1 = (Lf x Dy,min) + (d1 – Dy,min) x (Lf + L1
2)
791051.28 = (2575 x 150) + (d1 – 150) x (2575 +1864
2)
d1 = 332.38 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 287/293
287
7. DESIGN OF STAIR CASE
Stairs consist of steps arranged in a series for purpose of giving access to different floors of a
building. Since a stair is often the only means of communication between the various floors
of a building, the location of the stair requires good and careful consideration. In a residential
house, the staircase may be provided near the main entrance. In a public building, the stairs
must be from the main entrance itself and located centrally, to provide quick accessibility to
the principal apartments. All staircases should be adequately lighted and properly ventilated.
Various types of Staircases
Straight stairs
Dog-legged stairsOpen newel stair
Geometrical stair
RCC design of a Dog-legged staircase
In this type of staircase, the succeeding flights rise in opposite directions. The two
flights in plan are not separated by a well. A landing is provided corresponding to the level at
which the direction of the flight changes.
Dimensions:
B x L x H = 2820mm x 6000mm x 3350mm
Assume, Rise = 150mm
Tread = 300mm
sec θ =√(150)2+(300)2
300= 1.12
No. of risers =3350
150 = 22.33 say 22
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 288/293
288
Provide 11 + 11.
For flight-1: 11 and for Flight-2: 11
Going = 11 x treads = 11 x 300 = 3300mm
Total width of landings = 6000 – 3300 = 2700 mm
Therefore, width of landing at each end = 1350 mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 289/293
289
Design of Flight -1:
Type: One way single span simply supported inclined slab
Span (L): 3300 + 1350 = 4650mm
Trail Depth:
From IS456-2000, P39, Clause 24 & Clause 23.2 for Simply supported span we have
Span
Effective depth=
L
d= 20
r a = 20 x 1.4 = 28
Therefore, D =4750
28+ 20 = 189.65mm say 200 mm
Effective depth (d) = D – d1
= 200 – 20 = 180mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 290/293
290
Loads:
Self weight of slab (inclined) = 25 x D x secθ
= 25 x 0.2 x 1.12
= 5.6 KN/m2
Weight of steps =25 x rise x secθ
2=
25 x 0.15 x 1.1
2
= 2.09 KN/m2
Live load = 5 KN/m2
Floor Finish = 1 KN/m2
Total Load (W) = 13.69 KN/m2
Ultimate load (Wu) = 1.5 x 13.69 = 20.54 KN/m2
Design moment (Mu) =Wu x L2
10=
20.54 x (4.65)2
10= 44.41 KN-m
Mu,limit = 0.138 x f ck x b x d2 = 0.138 x 20 x 1000 x (180)2
= 89.42 x 106 N-mm = 89.42 KN-m
Mu < Mu,limit
Main steel:
From IS456-2000, P96, Clause G-1.1 (b) we have
Mu = 0.87 x f y x Ast x d x (1 -f y x Ast
f ck x b x d)
44.7 x 106 = 0.87 x 415 x Ast x 180 x (1 -415 x Ast
20 x 1000 x 180)
Ast = 753.21 mm2
Spacing of 12mm φ bars =ast x 1000
Ast=
π4
x 122 x1000
753.21= 150.15mm
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 291/293
291
Therefore, Provide 12mm φ @ 150mm c/c.
Distribution steel:
Ast = 0.12% of Ag
=0.12
1000x 200 x 1000 = 240 mm2.
Spacing of 8mm φ bars =π4
x 82 x1000
240= 209.44mm
Therefore, Provide 8mm φ @ 200mm c/c.
Design of flight-2:
Same as design of flight-1.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 292/293
292
8. CONCLUSION
The complete details and the necessity of the Multi-Storeyed building have been
explained in the introduction part. Live loads and dead loads are taken into consideration and
analysis is done manually. Manual analysis comprises of load distribution of slabs on to
beams and calculation of bending moment and shear force by any approximate method.
Analysis of frames is done by the substitute frame method and is furnished in the
introduction part. With the help of moment distribution method the moments carried at each
joints are known.
The design method adopted is limit state method. The bending moments obtained from
chapter 4 are used in calculating the area of steel in each frame section. The percentage of
steel obtained by limit state method is minimum as mentioned in limit state method of IS
456-2000.
Design of columns and footings are done depending on the load acting on them.
This project explains the basic concept behind the software. With the help of any softwarewe can do this analysis within no time but the basic thing is to know the concept behind it.
The same result can be achieved using the software like “Staad-Pro”. The wind load and
seismic analysis can be included for the future extension of the project.
7/27/2019 9. Final Project Report
http://slidepdf.com/reader/full/9-final-project-report 293/293