CUADRO DE METRADOS OBRA : MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LAS 13 CALLES EN LOS COMITES 3 Y 4 DE AA.HH. VIVA EL PERU II ETAPA, DISTRITO DE SANTIAGO CUSCO - CUSCO UND. EJECUTORA : MUNICIPALIDAD DISTRITAL DE SANTIAGO CONSULTOR : CONSORCIO SAN JOSE UBICACIÓN : SANTIAGO - CUSCO - CUSCO ECHA MARZO DEL 2014 ITEM DESCRIPCION ELEMENTOS DESCUENTOS TOTAL UND. Cant. Long. Ancho Alt. Sub Total Cant. Clase Long. Ancho Alt. Sub Total 01: VIAS VEHICULARES 01 VIAS VEHICULARES 01.01 OBRAS PROVISIONALES Y OBRAS PRELIMINARES 01.01.01 CONSTRUCCIONES PROVISIONALES 01.01.01.01. CARTEL DE IDENTIFICACION DE OBRA 1.00 1.00 1.00 und 01.01.01.02. OFICINAS 2.00 3.00 3.00 18.00 18.00 m2 01.01.01.03. ALMACEN DE OBRA 1.00 5.00 10.00 50.00 50.00 m2 01.01.01.04. SEÑALES PREVENTIVAS DURANTE EL PROCESO DE EJECUCION 26.00 26.00 26.00 und 01.01.02. TRABAJOS PRELIMINARES 01.01.02.01 LIMPIEZA DEL TERRENO 6641.70 m2 Calle 01 1.00 67.1 5.60 375.76 Calle 02 1.00 67.5 5.60 378.00 Calle 03 1.00 67.1 5.60 375.76 Calle 04 1.00 145.4 5.60 814.24 Calle 05 1.00 140 3.60 504.00 1.00 65.6 2.80 183.68 Calle 06 1.00 192.6 5.60 1078.56 Calle 07 1.00 68 5.20 353.60 Calle 08 1.00 96.8 5.60 542.08 Calle 09 1.00 35.8 2.40 85.92 1.00 32.8 3.00 98.40 Calle 10 1.00 30 5.20 156.00 Calle 11 1.00 70.33 5.60 393.85 Calle 12 1.00 84.9 5.60 475.44 Calle 13 1.00 118.57 5.60 663.99 Otros 1.00 AREA 1: 80.07 80.07 1.00 AREA 2: 54.14 54.14 1.00 AREA 3: 28.21 28.21 01.01.03 DEMOLICION Y REMOCION 01.01.03.01 DEMOLICION DE VEREDAS EXISTENTES 99.49 m3 Calle 05 1.00 230.83 0.80 0.20 36.93 Calle 06 1.00 129.3 0.90 0.20 23.27

8.1. Metrados - Vias Vehiculares

Embed Size (px)

DESCRIPTION

metrado para

Citation preview

Metrado Vias Vehiculares

CUADRO DE METRADOS

OBRA:MEJORAMIENTO DE LA TRANSITABILIDAD VEHICULAR Y PEATONAL DE LAS 13 CALLES EN LOS COMITES 3 Y 4 DE AA.HH. VIVA EL PERU II ETAPA, DISTRITO DE SANTIAGO CUSCO - CUSCOUND. EJECUTORA:MUNICIPALIDAD DISTRITAL DE SANTIAGOCONSULTOR :CONSORCIO SAN JOSEUBICACIN:SANTIAGO - CUSCO - CUSCOFECHA :MARZO DEL 2014

ITEMDESCRIPCIONELEMENTOSDESCUENTOSTOTALUND.Cant.Long.AnchoAlt.Sub TotalCant.ClaseLong.AnchoAlt.Sub Total

01: VIAS VEHICULARES01VIAS VEHICULARES01.01OBRAS PROVISIONALES Y OBRAS PRELIMINARES01.01.01CONSTRUCCIONES PROVISIONALES01.01.01.01.CARTEL DE IDENTIFICACION DE OBRA1.001.001.00und01.01.01.02.OFICINAS2.003.003.0018.0018.00m201.01.01.03.ALMACEN DE OBRA1.005.0010.0050.0050.00m201.01.01.04.SEALES PREVENTIVAS DURANTE EL PROCESO DE EJECUCION26.0026.0026.00und

01.01.02.TRABAJOS PRELIMINARES01.01.02.01LIMPIEZA DEL TERRENO6641.70m2Calle 011.0067.15.60375.76Calle 021.0067.55.60378.00Calle 031.0067.15.60375.76Calle 041.00145.45.60814.24Calle 051.001403.60504.001.0065.62.80183.68Calle 061.00192.65.601078.56Calle 071.00685.20353.60Calle 081.0096.85.60542.08Calle 091.0035.82.4085.921.0032.83.0098.40Calle 101.00305.20156.00Calle 111.0070.335.60393.85Calle 121.0084.95.60475.44Calle 131.00118.575.60663.99Otros 1.00AREA 1:80.0780.071.00AREA 2:54.1454.141.00AREA 3:28.2128.21

01.01.03DEMOLICION Y REMOCION01.01.03.01DEMOLICION DE VEREDAS EXISTENTES99.49m3Calle 051.00230.830.800.2036.93Calle 061.00129.30.900.2023.27Calle 091.0036.91.000.207.38Calle 101.0061.20.900.2011.02Calle 111.0044.31.000.208.86Calle 121.0060.121.000.2012.02

01.01.03.02ELIMINACION MANUAL DE MATERIAL EXCEDENTE MANUAL D=40m1.5Volumen:99.49149.23149.23m3

01.01.03.03ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA D = 10 KM1.00Volumen:149.23149.23149.23m3

01.01.04TRAZO, NIVELES Y REPLANTEO01.04.01.TRAZOS, NIVELES Y REPLANTEO PRELIMINAR6641.70m2Calle 011.0067.15.60375.76Calle 021.0067.55.60378.00Calle 031.0067.15.60375.76Calle 041.00145.45.60814.24Calle 051.001403.60504.001.0065.62.80183.68Calle 061.00192.65.601078.56Calle 071.00685.20353.60Calle 081.0096.85.60542.08Calle 091.0035.82.4085.921.0032.83.0098.40Calle 101.00305.20156.00Calle 111.0070.335.60393.85Calle 121.0084.95.60475.44Calle 131.00118.575.60663.99Otros 1.00AREA 1:80.0780.071.00AREA 2:54.1454.141.00AREA 3:28.2128.21

01.02MOVIMIENTO DE TIERRAS01.02.01SUB RASANTE01.02.01.01TRAZOS Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO6641.70m2Calle 011.0067.15.60375.76Calle 021.0067.55.60378.00Calle 031.0067.15.60375.76Calle 041.00145.45.60814.24Calle 051.001403.60504.001.0065.62.80183.68Calle 061.00192.65.601078.56Calle 071.0068.005.20353.60Calle 081.0096.85.60542.08Calle 091.0035.82.4085.921.0032.83.0098.40Calle 101.00305.20156.00Calle 111.0070.335.60393.85Calle 121.0084.95.60475.44Calle 131.00118.575.60663.99Otros 1.00AREA 1:80.0780.071.00AREA 2:54.1454.141.00AREA 3:28.2128.21

01.02.01.02CORTE A NIVEL DE SUB-RASANTE6948.83m3Calle 01LONGITUDAREA0+00006.010.000+010105.1855.950+020106.5158.460+030106.1063.020+040106.0860.880+050108.7173.960+060106.8677.860+067.17.16.8848.78Sub-Total438.89

Calle 02LONGITUDAREA0+00006.350.000+010106.0161.810+020105.3156.610+030105.8455.760+040106.4361.370+050105.6960.600+060104.8552.690+067.57.55.3038.08Sub-Total386.91

Calle 03LONGITUDAREA0+00006.240.000+010105.6859.620+020104.8552.680+030106.2555.510+040108.0071.240+050106.5472.690+060105.9662.510+067.17.14.8838.47Sub-Total412.71

Calle 04LONGITUDAREA0+00006.000.000+010105.6258.120+020105.2954.540+030105.8555.660+040105.9959.170+050104.9054.420+060104.5647.300+070105.5050.320+080106.0857.900+090105.8759.750+100105.5156.910+110105.2153.610+120104.4648.360+130103.9642.110+140103.4336.970+145.45.43.6419.08Sub-Total754.19

Calle 05LONGITUDAREA0+00003.950.000+010103.9539.520+020103.9539.490+030104.0139.780+040104.2241.140+050104.2542.340+060104.3943.200+070104.6345.100+080104.6446.340+090102.2234.290+100101.8920.530+110102.6522.700+120104.4935.700+130104.5044.930+140104.5545.260+150104.3344.390+160103.2437.850+170103.1331.850+180102.8229.740+190102.9929.050+200103.0330.080+205.65.63.1717.35Sub-Total760.59

Calle 06LONGITUDAREA0+00003.220.000+010104.5738.930+020105.7551.610+030105.2655.070+040104.2547.580+050105.3147.820+060105.8755.920+070106.4761.720+080107.0267.460+090107.6073.100+100108.6281.070+110108.6286.190+120105.7972.040+130105.7857.830+140106.4861.290+150106.3263.990+160106.2862.980+170106.2562.650+180106.3462.990+190105.9961.660+192.62.65.6815.17Sub-Total1187.03

Calle 07LONGITUDAREA0+00006.850.000+010106.4866.610+020106.0662.670+030106.1060.800+040106.2661.810+050106.6464.510+060106.5766.070+06886.6152.75Sub-Total435.21

Calle 08LONGITUDAREA0+00005.900.000+010106.7863.430+020108.9478.600+030108.0284.780+040104.8664.420+050105.9053.810+060106.4161.550+070106.2063.070+080104.8555.240+090105.0649.520+096.86.85.9037.25Sub-Total611.64

Calle 09LONGITUDAREA0+00002.580.000+010102.5725.740+020102.5925.780+030102.6025.940+040102.5925.940+050102.8427.130+060103.0929.640+068.68.62.6724.73Sub-Total184.88

Calle 10LONGITUDAREA0+00005.330.000+010105.4253.760+020105.6955.550+030105.3255.05Sub-Total164.36

Calle 11LONGITUDAREA0+00005.040.000+010105.0350.360+020105.6153.230+030105.8557.300+040106.0059.230+050105.8459.210+060105.6157.280+070105.4255.170+070.330.335.121.74Sub-Total393.51

Calle 12LONGITUDAREA0+00006.940.000+010106.8568.950+020106.0964.710+030105.8559.710+040105.6057.220+050105.6156.040+060105.5555.820+070105.5855.670+080105.8757.270+084.94.96.0729.27Sub-Total504.63

Calle 13LONGITUDAREA0+00004.900.000+010104.5647.300+020105.5050.320+030105.0452.700+040104.8749.570+050104.9749.200+060104.5947.760+070104.7046.430+080104.0243.580+090104.6043.080+100104.7946.940+110104.6147.020+118.578.575.0141.24Sub-Total565.11OtrosArea 1 1.00Volumen:72.8672.86Area 21.00Volumen:50.3550.35Area 31.00Volumen:25.9525.95Sub-Total149.17

01.02.01.03ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA (D=10km)9033.47m31.3Volumen:6948.839033.47

01.02.01.04ACONDICIONAMIENTO DE MATERIAL EXCEDENTE EN BOTADEROS9033.47m31.00Volumen:9033.479033.47

01.02.01.05PERFILADO, RIEGO Y COMPACTADO DE SUB-RASANTE6641.70m2Calle 011.0067.15.60375.76Calle 021.0067.55.60378.00Calle 031.0067.15.60375.76Calle 041.00145.45.60814.24Calle 051.001403.60504.001.0065.62.80183.68Calle 061.00192.65.601078.56Calle 071.00685.20353.60Calle 081.0096.85.60542.08Calle 091.0035.82.4085.921.0032.83.0098.40Calle 101.00305.20156.00Calle 111.0070.335.60393.85Calle 121.0084.95.60475.44Calle 131.00118.575.60663.99OtrosArea 1 1.00Area:80.0780.07Area 21.00Area:54.1454.14Area 31.00Area:28.2128.21

01.02.02MEJORAMIENTO DE SUB RASANTE01.02.02.01EXTRACCION Y APILAMIENTO DE MATERIAL DE CANTERA3320.85m3Calle 011.0067.15.600.50187.88Calle 021.0067.55.600.50189.00Calle 031.0067.15.600.50187.88Calle 041.00145.45.600.50407.12Calle 051.001403.600.50252.001.0065.62.800.5091.84Calle 061.00192.65.600.50539.28Calle 071.00685.200.50176.80Calle 081.0096.85.600.50271.04Calle 091.0035.82.400.5042.961.0032.83.000.5049.20Calle 101.00305.200.5078.00Calle 111.0070.335.600.50196.92Calle 121.0084.95.600.50237.72Calle 131.00118.575.600.50332.00OtrosArea 1 1.00Area:80.070.5040.04Area 21.00Area:54.140.5027.07Area 31.00Area:28.210.5014.11

01.02.02.02ARMADO DE ZARANDA METALICA3.00und3.003.00

01.02.02.03ZARANDEO DE MATERIAL DE CANTERA3320.85m3Calle 011.0067.15.600.50187.88Calle 021.0067.55.600.50189.00Calle 031.0067.15.600.50187.88Calle 041.00145.45.600.50407.12Calle 051.001403.600.50252.001.0065.62.800.5091.84Calle 061.00192.65.600.50539.28Calle 071.00685.200.50176.80Calle 081.0096.85.600.50271.04Calle 091.0035.82.400.5042.961.0032.83.000.5049.20Calle 101.00305.200.5078.00Calle 111.0070.335.600.50196.92Calle 121.0084.95.600.50237.72Calle 131.00118.575.600.50332.00

Otros Area 1 1.00Area:80.070.5040.04Area 21.00Area:54.140.5027.07Area 31.00Area:28.210.5014.11

01.02.02.04CARGUIO DE MATERIAL DE CANTERA3320.85m31.00Volumen:3320.853320.85

01.02.02.05TRANSPORTE DE MATERIAL DE CANTERA3320.85m31.00Volumen:3320.853320.85

01.02.02.06EXTENDIDO, RIEGO Y COMPACTADO6641.70m2Calle 011.0067.15.60375.76Calle 021.0067.55.60378.00Calle 031.0067.15.60375.76Calle 041.00145.45.60814.24Calle 051.001403.60504.001.0065.62.80183.68Calle 061.00192.65.601078.56Calle 071.00685.20353.60Calle 081.0096.85.60542.08Calle 091.0035.82.4085.921.0032.83.0098.40Calle 101.00305.20156.00Calle 111.0070.335.60393.85Calle 121.0084.95.60475.44Calle 131.00118.575.60663.99OtrosArea 1 1.00Area:80.0780.07Area 21.00Area:54.1454.14Area 31.00Area:28.2128.21

01.02.03BASE (e1 = 0.20m y e2=0.30m)01.02.03.01TRAZOS Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO6641.70m2Calle 011.0067.15.60375.76Calle 021.0067.55.60378.00Calle 031.0067.15.60375.76Calle 041.00145.45.60814.24Calle 051.001403.60504.001.0065.62.80183.68Calle 061.00192.65.601078.56Calle 071.00685.20353.60Calle 081.0096.85.60542.08Calle 091.0035.82.4085.921.0032.83.0098.40Calle 101.00305.20156.00Calle 111.0070.335.60393.85Calle 121.0084.95.60475.44Calle 131.00118.575.60663.99

OtrosArea 1 1.00Area:80.0780.07Area 21.00Area:54.1454.14Area 31.00Area:28.2128.21

01.02.03.02MATERIAL DE CANTERA BASE1937.55m3Calle 011.0067.105.600.30112.73Calle 021.0067.505.600.2075.60Calle 031.0067.105.600.30112.73Calle 041.00145.405.600.20162.85Calle 051.00140.003.600.20100.801.0065.602.800.2036.74Calle 061.00192.605.600.20215.71Calle 071.0068.005.200.2070.72Calle 081.0096.805.600.20108.42Calle 091.0035.802.400.2017.181.0032.803.000.2019.68Calle 101.0030.005.200.2031.20Calle 111.0070.335.600.30118.15Calle 121.0084.905.600.30142.63Calle 131.00118.575.600.20132.80

OtrosArea 1 1.00Area:80.070.2016.01Area 21.00Area:54.140.2010.83Area 31.00Area:28.210.205.64Sub Total1490.42Coef. Esponjamiento1.30TOTAL1937.55

01.02.03.03EXTENDIDO, BATIDO Y PERFILADO DE MATERIAL DE BASE e=0.20m5018.65m2Calle 031.0067.15.60375.76Calle 041.00145.45.60814.24Calle 051.001403.60504.001.0065.62.80183.68Calle 061.00192.65.601078.56Calle 071.00685.20353.60Calle 081.0096.85.60542.08Calle 091.0035.82.4085.921.0032.83.0098.40Calle 101.00305.20156.00Calle 131.00118.575.60663.99

OtrosArea 1 1.00Area:80.0780.07Area 21.00Area:54.1454.14Area 31.00Area:28.2128.21

01.02.03.04EXTENDIDO, BATIDO Y PERFILADO DE MATERIAL DE BASE e=0.30m1623.05m2Calle 011.0067.15.60375.76Calle 021.0067.55.60378.00Calle 111.0070.335.60393.85Calle 121.0084.95.60475.44

01.02.03.05RIEGO Y COMPACTADO DE BASE e = 0.20 m5018.65m2Calle 031.0067.105.60375.76Calle 041.00145.405.60814.24Calle 051.00140.003.60504.001.0065.602.80183.68Calle 061.00192.605.601078.56Calle 071.0068.005.20353.60Calle 081.0096.805.60542.08Calle 091.0035.802.4085.921.0032.803.0098.40Calle 101.0030.005.20156.00Calle 131.00118.575.60663.99

OtrosArea 1 1.00Area:80.0780.07Area 21.00Area:54.1454.14Area 31.00Area:28.2128.21

01.02.03.06RIEGO Y COMPACTADO DE BASE e = 0.30 m1623.05m2Calle 011.0067.105.60375.76Calle 021.0067.505.60378.00Calle 111.0070.335.60393.85Calle 121.0084.905.60475.44

01.03SUPERFICIE DE RODADURA: PAVIMENTO RIGIDO01.03.01TRAZOS Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO6641.70m2Calle 011.0067.15.60375.76Calle 021.0067.55.60378.00Calle 031.0067.15.60375.76Calle 041.00145.45.60814.24Calle 051.001403.60504.001.0065.62.80183.68Calle 061.00192.65.601078.56Calle 071.00685.20353.60Calle 081.0096.85.60542.08Calle 091.0035.82.4085.921.0032.83.0098.40Calle 101.00305.20156.00Calle 111.0070.335.60393.85Calle 121.0084.95.60475.44Calle 131.00118.575.60663.99

OtrosArea 1 1.00Area:80.0780.07Area 21.00Area:54.1454.14Area 31.00Area:28.2128.21

01.03.02ENCOFRADO Y DESENCOFRADO EN PAVIMENTO RIGIDO1222.94m2Calle 013.0067.100.2040.2624.005.600.2026.88Calle 023.0067.500.2040.5024.005.600.2026.88Calle 033.0067.100.2040.2624.005.600.2026.88Calle 043.00145.400.2087.2450.005.600.2056.00Calle 053.00140.000.2084.0048.003.600.2034.563.0065.600.2039.3623.002.800.2012.88Calle 063.00192.600.20115.5666.005.600.2073.92Calle 073.0068.000.2040.8024.005.200.2024.96Calle 083.0096.800.2058.0834.005.600.2038.08Calle 093.0035.800.2021.4813.002.400.206.243.0032.800.2019.6812.003.000.207.20Calle 103.0030.000.2018.0011.005.200.2011.44Calle 113.0070.330.2042.2025.005.600.2028.00Calle 123.0084.900.2050.9430.005.600.2033.60Calle 133.00118.570.2071.1441.005.600.2045.92

01.03.03CONCRETO f'c= 245 kg/cm2, en PAVIMENTO RIGIDO1328.34m3Calle 011.0067.15.600.2075.15Calle 021.0067.55.600.2075.60Calle 031.0067.15.600.2075.15Calle 041.00145.45.600.20162.85Calle 051.001403.600.20100.801.0065.62.800.2036.74Calle 061.00192.65.600.20215.71Calle 071.00685.200.2070.72Calle 081.0096.85.600.20108.42Calle 091.0035.82.400.2017.181.0032.83.000.2019.68Calle 101.00305.200.2031.20Calle 111.0070.335.600.2078.77Calle 121.0084.95.600.2095.09Calle 131.00118.575.600.20132.80

OtrosArea 1 1.00Area:80.070.2016.01Area 21.00Area:54.140.2010.83Area 31.00Area:28.210.205.64

01.03.04JUNTA LONGITUDINAL DE ARTICULACION 5/8" ACERO CORRUGADOPeso Unit1254.57kgCalle 0190.000.601.5583.70Calle 0290.000.601.5583.70Calle 0390.000.601.5583.70Calle 04194.000.601.55180.42Calle 050.000.001.550.00Calle 06257.000.601.55239.01Calle 0791.000.601.5584.63Calle 08130.000.601.55120.90Calle 090.000.001.550.00Calle 1040.000.601.5537.20Calle 1194.000.601.5587.42Calle 12114.000.601.55106.02Calle 13159.000.601.55147.87

01.03.05JUNTA TRANSVERSAL DE CONTRACCION 3/4'' ACERO LISOLong.N PaosPeso Unit5163.20kgCalle 0112.000.5023.002.24309.12Calle 0212.000.5023.002.24309.12Calle 0312.000.5023.002.24309.12Calle 0412.000.5049.002.24658.56Calle 058.000.5069.002.24618.24Calle 0612.000.5022.002.24295.68Calle 0711.000.5065.002.24800.80Calle 0812.000.5023.002.24309.12Calle 097.000.5023.002.24180.32Calle 1011.000.5010.002.24123.20Calle 1112.000.5024.002.24322.56Calle 1212.000.5029.002.24389.76Calle 1312.000.5040.002.24537.60

01.03.06JUNTA DE DILATACION 1'' ACERO LISOLong N Juntas Peso Unit4030.34kgCalle 0124.000.604.003.97228.67Calle 0224.000.604.003.97228.67Calle 0324.000.604.003.97228.67Calle 0424.000.6010.003.97571.68Calle 0516.000.6013.003.97495.46Calle 0624.000.6013.003.97743.18Calle 0722.000.604.003.97209.62Calle 0824.000.606.003.97343.01Calle 0914.000.604.003.97133.39Calle 1022.000.602.003.97104.81Calle 1124.000.604.003.97228.67Calle 1224.000.603.003.97171.50Calle 1324.000.606.003.97343.01

01.03.07ACERO GRADO 60 1/4'' EN MALLA DE TEMPERATURALong.Peso Unit8135.75kgCalle 01167.005.200.25217.1014.0066.700.25233.45Calle 02168.005.200.25218.4014.0067.100.25234.85Calle 03167.005.200.25217.1014.0066.700.25233.45Calle 04363.005.200.25471.9014.00145.100.25507.85Calle 05514.002.800.25359.808.00205.200.25410.40Calle 06481.005.200.25625.3014.00192.200.25672.70Calle 07170.004.800.25204.00146600013.0067.600.25219.70727000Calle 08242.005.200.25314.605600014.0096.400.25337.402249000Calle 09171.002.700.25115.432698806.0068.200.25102.3070000Calle 1075.004.800.2590.003373513.0029.600.2596.2033735Calle 11175.005.200.25227.50265635014.0069.930.25244.76Calle 12212.005.200.25275.6014.0084.500.25295.75Calle 13296.005.200.25384.8014.00118.170.25413.60OtrosArea 1 24.0014.050.2584.3048.009.380.25112.56Area 254.003.30.2544.5519.006.410.2530.45Area 321.0013.560.2571.1976.003.620.2568.78

01.03.08CURADO DE CONCRETO EN SUPERFICIE DE RODADURA6641.70m2Calle 011.0067.15.60375.76Calle 021.0067.55.60378.00Calle 031.0067.15.60375.76Calle 041.00145.45.60814.24Calle 051.001403.60504.001.0065.62.80183.68Calle 061.00192.65.601078.56Calle 071.00685.20353.60Calle 081.0096.85.60542.08Calle 091.0035.82.4085.921.0032.83.0098.40Calle 101.00305.20156.00Calle 111.0070.335.60393.85Calle 121.0084.95.60475.44Calle 131.00118.575.60663.99

OtrosArea 1 1.00Area:80.0780.07Area 21.00Area:54.1454.14Area 31.00Area:28.2128.21

01.03.09SELLADO DE JUNTAS LONGITUDINALESLongitud 1048.91mCalle 011.0067.1067.10Calle 021.0067.5067.50Calle 031.0067.1067.10Calle 041.00145.40145.40Calle 050.00205.600.00Calle 061.00192.60192.60Calle 071.0068.0068.00Calle 081.0096.8096.80Calle 090.0068.600.00Calle 101.0030.0030.00Calle 111.0070.3370.33Calle 121.0084.9084.90Calle 131.00118.57118.57

OtrosArea 1 1.0020.0120.01Area 21.0013.5513.55Area 31.007.057.05

01.03.10SELLADO DE JUNTAS DE CONTRACCION2267.20mCalle 0124.005.60134.40Calle 0224.005.60134.40Calle 0324.005.60134.40Calle 0450.005.60280.00Calle 0548.003.60172.8023.002.8064.40Calle 0666.005.60369.60Calle 0724.005.20124.80Calle 0834.005.60190.40Calle 0913.002.4031.2012.003.0036.00Calle 1011.005.2057.20Calle 1125.005.60140.00Calle 1230.005.60168.00Calle 1341.005.60229.60

01.04PRUEBAS DE CONTROL DE CALIDAD01.04.01DISEO DE MEZCLAS DE CONCRETO3.00undPavimento Rigido2.002.00Veredas y Sardineles1.001.0001.04.02PRUEBAS DE RESISTENCIA DEL CONCRETO39.00und3.00N calles:13.0039.00

01.04.03PRUEBAS DE DENSIDAD DE CAMPO24.00undCalle 011.001.00Calle 021.001.00Calle 031.001.00Calle 043.003.00Calle 054.004.00Calle 064.004.00Calle 071.001.00Calle 082.002.00Calle 091.001.00Calle 101.001.00Calle 111.001.00Calle 122.002.00Calle 132.002.00

01.04.04ENSAYO DE PROCTOR MODIFICADO17.00undCalle 011.001.00Calle 021.001.00Calle 031.001.00Calle 041.001.00Calle 052.002.00Calle 062.002.00Calle 071.001.00Calle 082.002.00Calle 091.001.00Calle 101.001.00Calle 111.001.00Calle 122.002.00Calle 131.001.00

01.05SEALIZACION 01.05.01DEMARCACION PERMANENTE EN EL PAVIMENTO6641.70m2Calle 011.0067.105.60375.76Calle 021.0067.505.60378.00Calle 031.0067.105.60375.76Calle 041.00145.405.60814.24Calle 051.00140.003.60504.001.0065.602.80183.68Calle 061.00192.605.601078.56Calle 071.0068.005.20353.60Calle 081.0096.805.60542.08Calle 091.0035.802.4085.921.0032.803.0098.40Calle 101.0030.005.20156.00Calle 111.0070.335.60393.85Calle 121.0084.905.60475.44Calle 131.00118.575.60663.99

OtrosArea 1 1.00Area:80.0780.07Area 21.00Area:54.1454.14Area 31.00Area:28.2128.21

01.06SEGURIDAD Y SALUD 01.06.01Elaboracion, implementacion y Administracion del Plan de Seguridad1.001.001.00glb01.06.02Equipos de Proteccion Individual 1.001.001.00glb01.06.03Equipos de Proteccion Colectiva1.001.001.00glb01.06.04Capacitacion en Seguridad y Salud1.001.001.00glb

Hoja1LONGITUDANCHOALT CORTEAREAScalle 167.15.60.553.080.331.8480.442.4640.613.416

PROMEDIOVOL TOTAL10.8082.702181.3042LONGITUDANCHOALT CORTEAREAScalle 267.55.60.553.080.482.6880.532.9680.553.08

PROMEDIOVOL TOTAL11.8162.954199.395LONGITUDANCHOALT CORTEAREAScalle 367.15.60.462.5760.221.2320.744.1440.452.52

PROMEDIOVOL TOTAL10.4722.618175.6678LONGITUDANCHOALT CORTEAREAScalle 4145.45.60.42.240.522.9120.52.80.351.96

PROMEDIOVOL TOTAL9.9122.478360.3012LONGITUDANCHOALT CORTEAREAScalle 5205.63.20.611.9520.872.7840.712.2720.561.792

PROMEDIOVOL TOTAL8.82.2452.32LONGITUDANCHOALT CORTEAREAScalle 6192.65.60.673.7520.211.1760.683.8080.553.08

PROMEDIOVOL TOTAL11.8162.954568.9404LONGITUDANCHOALT CORTEAREAScalle 7685.20.351.820.341.7680.361.8720.361.872

PROMEDIOVOL TOTAL7.3321.833124.644LONGITUDANCHOALT CORTEAREAScalle 896.85.60.52.80.492.5480.261.3520.673.484

PROMEDIOVOL TOTAL10.1842.546246.4528LONGITUDANCHOALT CORTEAREAScalle 968.62.70.551.4850.572.9640.331.7160.52.6

PROMEDIOVOL TOTAL8.7652.19125150.31975LONGITUDANCHOALT CORTEAREAScalle 10305.20.452.340.442.2880.452.340.442.288

PROMEDIOVOL TOTAL9.2562.31469.421488011.09780149.2555034.53LONGITUDANCHOALT CORTEAREASCD2323194.87calle 1284.95.60.673.752EXP700000.52.6`SUO34847.923050.512.652LIQ34847.923050.432.2362462890.7161

PROMEDIOVOL TOTAL11.242.81238.569