Upload
titus-dews
View
217
Download
1
Tags:
Embed Size (px)
Citation preview
75 Express Lanes Corridor-Wide Construction
From NW 170 Street to I-595
Presentation to FDOT Materials LabTuesday, August 19, 2014
Project Team
I-75 Express – Corridor-wide
• Paul Lampley, P.E. – FDOT Construction Program Manager
• Antonio Castro, P.E. – FDOT Construction Project Manager
• Robert Bostian, P.E. – FDOT Design Program Manager
• Vanita Saini, P.E. – FDOT Design Project Manager
• Raj Rangaswamy, P.E. – CEI Senior Project Engineer, Target Engineering Group
• Aurelio Matos, P.E. – CEI Senior Project Engineer, CH Perez & Associates
• Scott Gombar, P.E. – CEI Senior Project Engineer, Eisman Russo
• Jeremy Grady, P.E. – CEI Bridge Project Administrator, Corradino Group
• Amanda Carballo – Construction Public Information Officer
• Christopher Lewis, P.E. – Corridor-wide Geo-technical Engineer (FGE)
State Road (SR) 826 from W. Flagler Street to I-75 and I-75 from SR 826 to I-595 (Total 28 miles)
D4 Segment :
I-75 from NW 170 Street to I-595
(15 miles)
D6 Segment:
SR 826 from W Flagler Street to NW 154 Street and I-75 from SR 826 to NW 170
Street (13 miles)
Project Limits
Project Overview
Project Location• Segment E – North of Griffin Road to I-595 (4.7 miles)• Segment D - South of Sheridan Street to North of Griffin Road (3.7 miles)• Segment C - South of Miramar Parkway to South of Sheridan Street (3.6 miles)• Segments A & B – NW 170 Street to South of Miramar Parkway (3 miles)
I-75 Express – Corridor-wide
Scope of Work
• Constructing Express Lanes in the existing I-75 median
• Constructing ingress and egress points throughout the corridor
• Constructing direct connections to 595 Express, Palmetto Express and
Florida’s Turnpike (HEFT)
• Reconstructing the interchanges at Sheridan Street, Miramar Parkway, Miami
Gardens Drive and the HEFT
• Constructing sound barrier walls at various locations
• Installing additional traffic cameras, dynamic message signs and toll gantries
• Adding new signals, signage, lighting and landscaping
I-75 Express – Corridor-wide
Projected Express Lane OpeningsPartial Corridor Opening in Spring 2017Full Corridor Opening in Summer 2017Construction Completion in Late 2018ITS Integration Completion in Summer 2019
Construction Schedule
I-75 Express – Corridor-wide
75 Express Lanes Typical Section
• Express Lanes– Centered in existing I-75 median
• Separated from the General Purpose Lanes
– Two northbound and two southbound lanes • Separated by concrete barrier wall
– Full width paved shouldersI-75 Express – Corridor-wide
Express Lanes
Ingress & Egress Ramps
NOT TO SCALE
I-75 MainlineI-75 Mainline
Visit the Access Points page to view all of the Ingress and Egress ramps
I-75 Express – Corridor-wide
Segment E Overview
From North of Griffin Road to I-595Construction start date: March 2014
Estimated construction completion date: Summer 2017Construction cost: $75 million
CEI: Target Engineering Group, Inc.Design-Build Team: Dragados USA/Parsons Brinckerhoff
I-75 Express – Corridor-wide
I-75 Express – Corridor-wide
Major Work Elements
2 Bridges
2,300 Bridge Length
650,000 Cubic Yards of Embankment
29,000 Length of Drainage
31,000 Tons of Asphalt
Contractors Quality Control Firm: Terracon
Proposed Connection Bridge to 595 Express Lanes
• Direct connect from 75 Express Lanes to 595 Express Lanes • Temporary ramp closures and detours will be scheduled
I-75 Express – Corridor-wide
Segment D Overview
From of South of Sheridan Street to North of Griffin RoadConstruction start date: September 2014
Estimated construction completion date: Summer 2018Construction cost: $80 million
CEI: Target Engineering Group, Inc.Design-Build Team: Ranger Construction/Wantman Group
I-75 Express – Corridor-wide
I-75 Express – Corridor-wide
Major Work Elements
2 Bridges
540 Bridge Length
982,600 Cubic Yards of Embankment
25,000 Length of Drainage
55,400 Tons of Asphalt
Contractors Quality Control Firm: Tierra South Florida
Scope of Work:
• New Express Lane bridge
New Improvement Features
C-11 Canal Bridge
I-75 Express – Corridor-wide
Scope of Work:
• Constructing ponds at the interchange
• Widening the Sheridan Street bridge to the north and replacing the existing bridge deck
• Installing additional signalized turn lanes
• Installing new sidewalk on the bridge
• Upgrading signage, lighting, landscaping and signals
New Improvement Features
Sheridan Street Interchange
I-75 Express – Corridor-wide
Segment C Overview
From South of Miramar Parkway to South of Sheridan StreetConstruction start date: June 2014
Estimated construction completion date: Summer 2018Construction cost: $85 million
CEI: A&P Consulting Transportation EngineersDesign-Build Team: Ranger Construction/Wantman Group
I-75 Express – Corridor-wide
I-75 Express – Corridor-wide
Major Work Elements
2 Bridges
910 Bridge Length
858,900 Cubic Yards of Embankment
39,000 Length of Drainage
55,000 Tons of Asphalt
Contractors Quality Control Firm: Tierra South Florida
Scope of Work:
• Reconstructing a new bridge to accommodate the new I-75 Express Lanes (60 feet longer and 36 feet wider)
• Reconstructing the interchange ramps at Miramar Parkway
• Installing additional signalized turn lanes
• Installing new sidewalk on the south side of the bridge
• Signage, lighting and signal upgrades
Miramar Parkway Interchange
New Improvement Features
I-75 Express – Corridor-wide
Miramar Parkway Interchange
Existing Interchange Features
New Improvement Features
Extended left turn lanes for maximum capacityTriple-left turn lanes (WB to SB)Dual-left turn lanes (EB to NB)
New sidewalk on both sides
New signalized ramps
Dual-left turn lanes (WB to SB)Dual-left turn lanes (EB to NB)
Option for future triple-left turn lanes
Sidewalk on north side only
New sidewalk on both sides
Existing left turn lanes
I-75 Express – Corridor-wide
• Collaborative effort between Broward County & FDOT
– Broward County will construct bridge approaches
– FDOT will construct the bridge over I-75
• Broward County began bridge approaches – June 2014
• FDOT to start bridge construction – September 2014
• Broward County to complete overpass
– Final paving, signing, striping, and lighting
• Anticipated opening by Broward County – late 2016
Pembroke Road BridgeScope of Work & Schedule
I-75 Express – Corridor-wide
Pembroke Road Bridge
• Four-lane divided bridge with inside and outside shoulders• Bike lanes and sidewalks on both sides• Lighting on the south side of the bridge
Bridge Features
I-75 Express – Corridor-wide
Segments A & B Overview
From NW 170 Street (Miami-Dade County) to South of Miramar ParkwayEstimated construction start date: Late 2014
Estimated construction completion date: Spring 2019Construction cost: $234 million
CEI: The Corradino GroupDesign-Build Team: Community Asphalt/Wantman Group
I-75 Express – Corridor-wide
I-75 Express – Corridor-wide
Major Work Elements
14 Bridges
6,880 Bridge Length
2.0million Cubic Yards of Embankment
60,000 Tons of Asphalt
Contractors Quality Control Firm: Construction Testing Inspection (CTI)
Proposed I-75/HEFT Interchange
I-75 Express – Corridor-wide
Miami Gardens Drive
Ramp H-5
Ramp H-12
HEFT
Ramp H-10 and H-11
Ramp H-13
Ramp H-7
Proposed I-75/HEFT Interchange
I-75 Express – Corridor-wide
Snake Creek Road
Ramp H-4
Bass Creek Road
Scope of Work:
• Modifying the existing bridges to accommodate the new I-75 Express Lanes and the new ramps
• Reconstructing the interchange ramps
• Signage, lighting and signal upgrades
Miami Gardens Drive Interchange
New Improvement Features
I-75 Express – Corridor-wide
Sound Barrier Walls
• Ground Mounted Sound Barrier Walls
• To be completed within the first half of the Segment contract
• Direct coordination with affected communities
• Hours of operation
– Daytime work only
– No weekend work
I-75 Express – Corridor-wide
Sound Barrier Wall LocationSegment E
• Benefited communities• Highland Ranch Estates
• New River Estates
• Woodgate Condos
• Vista Filare
• Royal Palm
• Forest Oak
I-75 Express – Corridor-wide
Sound Barrier Wall LocationSegment D
• Benefited communities• Sheridan Glen
• The Crossbow
• Waverly Hundred
• Falcon’s Lea
• Waterford
• Hawkes Bluff
• Ivanhoe Estates
• Chelsea
I-75 Express – Corridor-wide
Sound Barrier Wall Location
• Benefited communities• Windsor at Miramar
• Villas at Nautica
• Cobblestone Townhomes
• Towngate
Segment C
I-75 Express – Corridor-wide
Sound Barrier Wall Location
• Benefited communities• Royal Landings
• West Lakes Estates
• Century Gardens
• Lakes on the Green
• Marbella Park West
• Riviera Isles
• Huntington
• Courtyards at Nautica
Segments A & B
I-75 Express – Corridor-wide
Stay Informed
Sign up for Construction Updates and Lane Closure Information:
Project Public Information Officer Amanda Carballo (954) 548-2754
For more information on lane closures and other project details, log onto the FDOT Construction
website at www.75-express.com I-75 Express – Corridor-wide