Upload
vankhanh
View
222
Download
3
Embed Size (px)
Citation preview
Region of Waterloo Rapid Transit Project
Environmental Project Report
March 2012 139
7.4 Maintenance and Storage Facility
A Maintenance and Storage Facility is required to support the LRT component of the RT system. These
facilities typically include provision for service, inspection, repair and shunting.
Some of the common support operations found at maintenance and storage facilities include:
Crew office;
Dispatch center;
Machine shop;
Administration office;
Stores;
Employee / visitor parking; and
Outside material storage for signals, track
and traction power supplies.
A Maintenance and Storage Facility site evaluation ranked several sites against a set of five (5) criteria:
Site description;
Costs;
Operations;
Environmental and socio-economic impacts;
and
Land use.
The site that best met the identified requirements is located in the Northfield industrial area (518 Dutton
Drive) between the Waterloo Spur rail line and Highway 85 (Figure 7-14). This is near the northern limits
of the RT corridor, north of Weber Street and east of the Waterloo Spur.
Based on the City of Waterloo’s zoning by-law, current zoning on the site is 1-6 (Industrial 6) and its
property code is 736 (clubs, private and fraternal). The current zoning is compatible with the proposed
use. Land uses in the surrounding area are predominantly industrial and commercial, with a residential
neighbourhood approximately 250 m south of the property, on the south side of Weber Street.
The site is approximately 68,000 m2 (16.86 ac) in size. It is the former manufacturing and warehousing
facility of Bauer Industries, a textile manufacturer that provided products for the automotive industry. A
large manufacturing/warehouse building with office space and truck loading bays exists on the property.
Due to its location and configuration, it is not likely that the building can be reused for the Maintenance
and Storage Facility. A small woodlot takes up approximately one quarter of the property. The proposed
layout demonstrates that the full conceptual Maintenance and Storage Facility can be built with little
impact to this woodlot (see Volume 2: Functional Design Drawings, Sheet 55). A high tension hydro
corridor also runs along the southeastern edge of the land.
Rail access to and from the RT corridor will be in the southwest corner of the site. The site is
approximately 10 km north of GRT’s bus yard (Strasburg Barn) on Strasburg Road.
HIG
HW
AY 85
PA
RK
SID
E D
R
WEBER ST N DU
TT
ON
DR
HIG
HW
AY 85
This drawing has been prepared for the use of AECOM's client
and may not be used, reproduced or relied upon by third parties,
except as agreed by AECOM and its client, as required by law
or for use by governmental reviewing agencies. AECOM accepts
no responsibility, and denies any liability whatsoever, to any party
that modifies this drawing without AECOM's express written consent.
Datum: NAD 83, Zone 17Source: OBM, GRCA, ROW
1:2,000
November 2011 Figure 7-14
Maintenance and Storage Facility
Location
0 0.06 0.120.03
Kilometers
h
Legend
Roads
Rail
WaterlooWaterloo
KitchenerKitchener
Watercourses
Proposed LRT
Maintenance and Storage Facility
Rapid Transit Project
Transit Project Assessment Process
Environmental Project Report
Region of Waterloo Rapid Transit Project
Environmental Project Report
March 2012 141
7.5 Park and Ride Facilities
The RT corridor will include three (3) park and ride locations to provide access for riders at the following
locations:
Northfield Drive, Waterloo – near the interchange with Highway 85;
Fairview Park Mall, Kitchener – near the interchange of Fairway Road and Highway 8; and
Sportsworld Drive, Kitchener – near the interchange with Highway 8.
Specific site details will be addressed during future design phases.
7.6 Related Structures
A replacement/expansion program and order of magnitude cost estimate for each existing or new
structure requiring modifications as a result of the RT project was prepared under previous phases of this
project. The recommendations for each structure as they impact the current functional design are listed
below in Table 7.3.
Table 7.3 Proposed Structure Recommendations
LRT System (Conestoga Mall to Fairview Park Mall)
Structure New or Existing Proposed Work
Northfield Drive over Highway 85 Existing Remove asphalt and cast concrete curbs.
Waterloo Spur under Weber
Street
Existing Embankment slope removal.
Waterloo Spur over Cedar Creek
(Old Albert Street)
Existing Culvert extension.
Waterloo Spur over Silver
Lake/Laurel Creek
New Remove existing railway structure.
New structure for two (2) LRT tracks.
Pedestrian bridge to remain.
King Street under CN Guelph
Subdivision near Victoria Street
New New fully-grade separated crossing with road and LRT under the CN rail line.
Grade separation will be integrated with the multi-modal terminal at this location.
Borden Avenue over Schneider
Creek
Existing Existing structure to remain.
New structure to be superimposed over top of existing one.
Ottawa Street over Schneider
Creek
Existing Existing structure to remain.
New structure to be superimposed over top of existing one.
CN Huron Park Spur under
Highway 7/8
Existing Complete structure replacement with new single-span bridge.
142
CN Huron Park Spur over
Schneider Creek
New New bridge of same or similar construction adjacent to existing bridge.
Courtland Avenue over
Montgomery Creek
Existing No structural work required.
aBRT System (Fairview Park Mall to Ainslie Street Terminal)
Structure New or Existing Proposed Work
Highway 8 over the Grand River Existing MTO is currently constructing the widening of Highway 8.
The future structure will be wide enough to accommodate the bus bypass shoulders.
Highway 8 over King Street Existing Highway widening will be part of the MTO’s Grand River bridge widening project.
Highway 8 over Sportsworld
Drive
Existing No structural work required.
Highway 8 Flyover to Highway
401
Existing No structural work required.
Highway 401 under Fountain
Street
Existing No structural work required.
Highway 401 over CPR Waterloo
Subdivision
Existing No structural work required.
Highway 401 under Speedsville
Road
Existing No structural work required.
Highway 401 over the Speed
River and Tributaries
Existing No structural work required.
Highway 401 over CN Fergus
Spur
Existing No structural work required.
Hespeler Road over CPR
Waterloo Subdivision
New The Region is constructing a new structure under a separate project.
The structure will be wide enough to accommodate an 8 m RT corridor.
No structural work required as part of this project.
7.7 Utilities
The following assumptions were made with respect to utilities:
Utilities that cross the RT corridor transversely will generally not be problematic and these utilities will
remain in place unless there is a compelling reason to remove or replace the utility. However, all
utility crossings should be reviewed to determine if the transverse crossing could potentially become
problematic;
The 8.0 m RT right-of-way width will not need to be isolated from utilities;
If the utility is less than 30 years old, the utility will likely remain in place;
Region of Waterloo Rapid Transit Project
Environmental Project Report
March 2012 143
If the utility is between 30 and 40 years old, the break history/maintenance records of the utility will be
reviewed. A Closed Circuit Television (CCTV) inspection could be used to determine structural
integrity;
If the utility is 40 years old or more, the utility should be replaced; and
If utilities are to be replaced, the first priority will be to try to move the utility outside of the RT corridor.
Co-ordination with Utilities
Upon review of existing construction drawings from previous Regional and municipal projects, staff
superimposed the alignment of the proposed transit corridor to assess the location of the alignment in
relation to existing utility infrastructure. In addition, an examination of possible road widening alignments
required to accommodate RT was undertaken.
A high level review of the resulting details was conducted through a series of meetings held individually
with representatives from Hydro One Networks and each of the tenant municipal and private utilities,
except Allstream. Allstream initially declined to meet at this functional design stage, but desires
involvement at subsequent stages. Discussions at the meetings varied considerably, but fell into the
following general topics:
Impact of transit corridor on parallel and perpendicular running utilities;
Stray current impacts and mitigation;
Cost sharing between parties;
Future proceedings for utilities to access plants for maintenance and upgrading;
Lane closures; and
Vertical conflicts with overhead utility lines that are under/over the transit corridor.
The Region is in the process of completing a detailed topographic survey of the proposed RT corridors in
Kitchener and Waterloo. Through cooperation with municipal and private utility representatives, field
locates of existing underground infrastructure will be done at the same time and tied into the topographic
survey. This will allow the generation of a comprehensive and accurate base plan for future design.
Going forward, the municipal and private utility representatives have agreed to work cooperatively with
the Region in its design and construction of the proposed RT project. Ongoing meetings will be
scheduled to ensure the design and implementation of any relocation is done in a timely fashion and
budgeted appropriately by the responsible parties.