View
216
Download
0
Embed Size (px)
Citation preview
8/11/2019 69945-microwind1
1/13
Micro wind generation
and traditional buildings
2010
8/11/2019 69945-microwind1
2/13
The information in this publication is based on current
knowledge.Whilst every effort has been made to ensure
the accuracy of the advice given, English Heritage does not
accept liability for loss or damage arising from the use of
this information.This publication is intended only as a guide.
It has no statutory authority, and should not be used as a
substitute for professional advice.The guidance provided
here deals only with the practical aspects of installing the
equipment.The acceptability of the installation will depend on
the historic significance of the building or site being adapted.
You are strongly advised to discuss your proposals informally
with historic environment staff from your local council.
The inclusion in this publication of any company,group or individual, or any product or service, should
not be regarded as either a recommendation or anendorsement by English Heritage or its agents.
PLANNING AND HISTORIC BUILDINGLEGISLATION
THE INSTALLATION OF A RENEWABLE TECHNOLOGY
IMPLIES IN MOST CASES THE FIXING OF EQUIPMENTTO THE HISTORIC FABRIC OF A BUILDING. ENGLISH
HERITAGE SEEKS TO ENSURE THAT ANY WORKS TOA HISTORIC BUILDING DO NOT UNNECESSARILY
DISTURB OR DESTROY HISTORIC FABRIC
In decisions on how best to incorporate a renewable technology,the principles of minimum intervention and reversibility should
be adopted whenever and wherever possible.
Installing a wind turbine will probably need planning permission.
The local planning authority can grant permission under
the Town and Country Planning Act 1990, and they will be
looking for any issues concerning visual impact and proximity
to land boundaries.
Installing a wind turbine on a listed building or a building in
a conservation area will also need permission from the local
planning authority, under the Planning (Listed Buildings andConservation Areas) Act 1990. Planning Policy Guidance
(PPG) 15, Planning and the Historic Environment, can help
you with this; see www.planningportal.gov.uk.A New
Planning Policy Statement (PPS) 15 will replace Planning
Policy Guidance 15: Planning and the Historic Environment
(PPG15) and Planning Policy Guidance 16: Archaeology and
Planning (PPG16) from 2010.Work of any kind to a Scheduled
Monument requires consent from English Heritage under the
Ancient Monuments and Archaeological Areas Act 1979.
Your application will need to show clearly what you intend todo, with detailed drawings and photographs. It is useful to draw
the turbine on a photo of the site or building in order to help
the planning officer visualise it in its proposed setting and
determine its visual impact.
http://www.planningportal.gov.uk/http://www.planningportal.gov.uk/http://www.planningportal.gov.uk/8/11/2019 69945-microwind1
3/13
CONTENTS
INTRODUCTION 1
PLANNING A WIND
TURBINE INSTALLATION
Wind speed and direction
Wildlife
2
2
2INSTALLATION OPTIONS
Fixed to a building
Remote from building
2
3
4
ELECTRICAL SYSTEM
Non-grid connection
Grid connection
5
5
6
MAINTENANCE
AND WORKING LIFE
6
GRANTS 6
USEFUL CONTACTS
Renewable energy and climate change
Wind turbines and wildlife
Wind power
Planning guidance
Renewable energy grants
7
7
7
7
7
7
ACKNOWLEDGEMENTS 7
Front cover image courtesy of Quiet Revolution Limited.
8/11/2019 69945-microwind1
4/13
2 MICRO WIND GENERATION AND TRADITIONAL BUILDINGS
INTRODUCTION
English Heritage is the UK government's adviser on the historic environment. Central to
our role is the advice we give to local planning authorities and government departments
on development proposals affecting listed and traditional buildings, conservation sites and
areas, terrestrial and underwater archaeological sites, designed landscapes and historical
aspects of the landscape as a whole. For our policy statements on climate change andwind energy, refer to English Heritage's Historic Environment, Local Management website,
www.helm.org.uk.
The earth's climate is changing at a rate that has not been seen before in human
history.The changes have been linked to rising concentrations of carbon dioxide in
our atmosphere. Carbon dioxide is a by-product of the burning of fossil fuels to supply
energy, and emissions have spiralled upwards as our demand for energy has increased.
The UK government, wishing to reduce the country's dependence on fossil-fuel storesand to cut carbon dioxide emissions, has made a commitment to find 10% of our energy
from renewable sources by 2010, rising to 20% by 2025. Renewable energy may come
from sources such as wood that are self-regenerating, or those such as the sun and the
wind that are effectively infinite.The technologies associated with these sources are
sometimes referred to as 'low-carbon', in that they emit much lower levels of carbon
dioxide and related compounds into the atmosphere than do fossil-fuel technologies.
For more information on the UK government's position on climate change, contact the
UK Climate Impacts Programme (see Useful contacts).This guide is one of a series onsmall-scale renewable energy options. Separate guides look at wind generation, solar
energy, bio-fuels, heat pumps and combined heat and power, explaining how each system
works and what you need to consider if you wish to install it in or on a historic building.
All the guides look at small-scale or 'Microgeneration' as it is known. Microgeneration is
defined by Government as, The production of heat and/or electricity on a small-scale
from a low carbon source.
Cutting demand for energy is as important as finding alternative means of generating it. Before decidingwhether to install a renewable energy technology in a building, all available energy-saving measures, includinglow-energy light bulbs, heating controls and improved insulation, should already have been taken.An EnglishHeritage guidance document, Energy Conservation in Traditional Buildings, looks at methods of improvinginsulation and introduces other methods for saving energy.
http://www.helm.org.uk/http://www.helm.org.uk/http://www.helm.org.uk/8/11/2019 69945-microwind1
5/13
3MICRO WIND GENERATION AND TRADITIONAL BUILDINGS
PLANNING A WIND
TURBINE INSTALLATION
AN IMPORTANT QUESTION TO CONSIDER BEFORE
INSTALLING A WIND TURBINE IS WHETHER THIS IS
THE MOST SUITABLE RENEWABLE TECHNOLOGY
FOR YOUR BUILDING.
Would another approach to generating renewable
energy be better?
WIND SPEED AND DIRECTION
Most wind turbines will only work at wind speeds
above about 4m/sec.The Energy Saving Trust (see
Useful
contacts) notes that a turbine may not be viable where
typical wind speed is below 4.5m/sec, since the amount
of energy generated would not justify the capital cost.
In order to generate the optimum annual electricity
yield, a wind turbine should face in the direction of the
prevailing wind.This is normally southwest, but can vary
from place to place.
There is a document called the Microgeneration
Installation Standard Document MIS 3003.
Microgeneration Installation Standard 3003 specifies
the requirements set out by Building Enterprise and
Regulatory Reform (BERR) for contractors supplying,
designing, installing micro and small wind turbines. In order
to work out what your turbine is likely to generate the
Standard sets out how you can estimate your annual
energy performance.Their recommendations are:-
1. Obtain the mean wind speed from the NOABL
(numerical objective analysis of boundary layer)
database for where you live.The wind speed
database is maintained by BERR which is accessible
via the British Wind Energy Association website
(www.bwea.com/noabl).The NOABL database,
presents annual mean wind speeds throughout the UK.
The data is keyed to Ordnance Survey grid reference,and takes no account of local terrain or local winds,
such as sea or valley breezes or the effects of others
structures or trees.
In built up areas the database has been found to
overestimate the wind speeds so the Building Research
Establishment (BRE) advises that where it is not possible
to use long term metrological data for the site the wind
speed data from the NOABL database should be
corrected so a more accurate estimation of the wind
power can be made.
2. Using the mean wind speed data from the NOABL
database it can be corrected to take into account
the local terrain where you live.
The Microgeneration Installation Standard Document
MIS 3003 gives scaling factors to apply fro dense urban,
low rise urban/suburban and rural. It can be seen that
where turbines are fixed onto buildings or areas withbuildings close to the turbine the scaling factor reduces.
This means that the output is greatly reduced compared
to a rural location.
1
3. To estimate what the annual energy performance
would be you can use the value given in step 2
and apply it to the manufacturers annual energy
performance curve, see below.
2
http://www.bwea.com/noablhttp://www.bwea.com/noabl8/11/2019 69945-microwind1
6/13
4 MICRO WIND GENERATION AND TRADITIONAL BUILDINGS
The Carbon Trust have a 'Wind Yield Estimator Tool'
that can be used to estimate the local annual mean
wind speed for a chosen location and the annual yield.
(www.carbontrust.co.uk/windpowerestimator/). The tool
allows the user to enter their postcode, the location
i.e rural, urban etc. and the type of turbine.
WILDLIFEThere is some concern about the potential negative
effects of wind turbines on wild animals birds and bats
in particular that make historic buildings their homes.
Roosting and nesting sites, access points and flight paths
all need to be considered in any assessment of the impact
a wind turbine, its installation and subsequent maintenance
might have on their activities.
The Royal Society for the Protection of Birds (RSPB) has
information on wind farm installations and on the problem
of birds colliding with large turbines.The Bat Conservation
Trust notes that bats have been found dead under large
wind farm installations. All bats and many birds are legally
protected. Natural England should be consulted at an
early stage in the planning of a wind turbine installation
of any size, especially on or near buildings known to be
frequented by wildlife or in areas used by protected
wildlife. For contact details see Useful contacts.
INSTALLATION OPTIONS
When planning the installation it isimportant tothink about the reversibility and the physicalimpact an installation can have on a building.This is to say that wind turbines and theirassociated equipment can have a life of up to 20years, so a building could have many installationsover its life. By carefully planning the installationand how it can be removed at the end of its usefullife damage can be limited to the building fabric.
Wind turbines work by converting the winds kinetic
energy into electrical energy. Most modern systems
use horizontal-axis wind turbines, with three or five
blades rotating around a central hub (Fig 3).Vertical-axis
wind turbines (Fig 4) are less common.
Wind turbines are more commonly located away
from the building they provide energy to but can be
fixed onto the building.The performance of the turbine
will be reduced when fixed to a building or in a densely
populated area.
3 4
Horizontal-axis wind turbine. (Photograph courtesy of Renewable DevicesSwift Turbines Limited) & Vertical-axis wind turbine. (Photograph courtesyof Quiet Revolution Limited)
FIXED TO A BUILDINGThe turbine is mounted on a pole which is fastened
with brackets to an external wall, high enough to project
above the building (Fig 5). In general the higher the
turbine above the roof the greater the power output will
be as it will be affected less by turbulence, See Fig 1
5
A house with a wall-mounted wind turbine, Camberwell, London.(Photographs courtesy of Eclectic Energy Limited)
When fixing a turbine to the building their will be an
additional structural load that would need to be assessed.
A structural survey by a specialist in the conservation of
historic buildings is necessary to ensure that the building iscapable of supporting the turbine. Domestic-sized turbines
weigh from 15kg to 30kg, and wall brackets must be fixed
strongly enough not only to support the turbine itself, but
to withstand the force exerted on it by a 50m/sec gust
over a 10-minute period.
Where a building is framed, for the best support the fixing
must be to the frame, not to infill panels. If the frame is
not exposed, it is generally possible to fix into the frame
through the external finish.
http://www.carbontrust.co.uk/windpowerestimatorhttp://www.carbontrust.co.uk/windpowerestimator8/11/2019 69945-microwind1
7/13
MICRO WIND GENERATION AND TRADITIONAL BUILDINGS 5
On a building with a pitched roof, the turbine is
fitted to the gable end (unless this conflicts with any
windows) so that the pole can be as short as possible
(Fig 6). If there is no gable end, a very tall pole may be
needed, making the turbine difficult to support (Fig 7).
High-hipped roofs can be even more problematic.
A turbine may be fixed directly to a flat roof (Fig 8),
but care should be taken that brackets do notcompromise the weatherproofing.
It is rarely advisable to fit the turbine to a chimney
stack: chimneys are not constructed to take this type
of structural loading, and the strength of those on
historic buildings may have been further reduced by
the effects of years of flue gases on their mortar. If a
chimney stack is no longer used, it could perhaps be
reinforced to take such a loading.
Most manufacturers recommend installing pads with
the brackets to dampen the vibration of the working
turbine. Noise is not generally an issue with small
modern wind turbines.
To minimise damage over the long term, the bracket
arrangement should use the minimum number of fixing
holes. Generally we advise that fixings should be installed
into mortor joints to minimise damage to fabric.
REMOTE FROM BUILDINGA wind turbine can be mounted away from a building
on a pole or latticework tower (Fig 10).The pole and
location must be high enough to avoid the effects of
turbulence.The optimal height will depend on the
surroundings: if trees or other buildings obstruct air
flow, the turbine will need to be raised, or moved
to a better location.
The pole or tower requires proper foundations; typically
a 70kg turbine on a 5m pole would require at least 1m3
of foundations, depending on soil conditions.
From the turbine a cable must run back to the buildings
electrical fuse board (Fig 11).The cable size is determined
by the load it must carry, as well as its length: the further
the turbine from the building, the larger (and more
expensive) the required cable. It is usually necessary to
bury it, to a depth of no less than 0.5m to avoid damage
from general gardening.
6Turbine fixed to a building
7
Wind turbine wall brackets. (Photograph A courtesy of RenewableDevices Swift Turbines Limited; photographs B and C courtesy ofEclectic Energy Limited)
Turbine mounted on flat roof8
8/11/2019 69945-microwind1
8/13
6 MICRO WIND GENERATION AND TRADITIONAL BUILDINGS
9Turbines mounted on a flat roof
Before excavating, both for foundations and for cabling,
it is important to assess the possibility of buried
archaeology on the site. If the building or grounds are
listed or scheduled, the statutory description may cover
this aspect of the site.Where the archaeology prevents
a cable being buried at a reasonable depth, an alternative
route should be found where it can be buried more
deeply.Where this is not possible, the cable duct should
be encased in concrete.
The access point of the cable into the building should
be properly sealed to prevent water ingress, maintain
fire protection and keep pests out.
A house with a pole-mounted turbine. (Photograph courtesy ofProven Energy Ltd)
10
ELECTRICAL SYSTEM
THE DESIGN OF THE TURBINES ELECTRICALSYSTEM WILL DEPEND TO A GREAT EXTENTON THE BUILDINGS PRESENT SYSTEM.
Is there a mains supply or is it independent of the
national grid? It will also depend on how the generatedpower is to be used.Will it be fed back into the national
grid, or cater for a specific load? Will energy be stored
for use at other times? It is wise to look at the buildings
present electrical load, and estimate how much of it
might be catered for by the wind turbine.
The electricity generated by a wind turbine is direct
current (dc).An inverter is needed to convert this to
alternating current (ac) so that it can be used for electrical
appliances or fed back into the grid. Other essential
elements of the system are a wind-turbine controller, tostop the turbine if the wind becomes strong enough to
damage it, and an isolation switch, allowing the turbine to
be disconnected for safe maintenance or repair (Fig 12).
Equipment should be located to permit easy access for
maintenance and repair. All parts of the installation should
be indicated on a working drawing.Where equipment is
to be fixed to building walls, the number of fixing points
should minimised by the use of a wooden pattress or
frame system (Fig 13).
There are three options for connecting a turbineto the electrical system: direct, off-grid and grid.
11Buried cable for a remotely-mounted turbine
8/11/2019 69945-microwind1
9/13
MICRO WIND GENERATION AND TRADITIONAL BUILDINGS 7
12
Electrical installations, showing inverters. (Photographs courtesy ofWind and Sun Limited)
NON-GRID CONNECTIONWhere no mains electricity is available, a wind turbine
can be used to replace or supplement the existing local
electricity supply (a diesel generator, for example).The
turbine is connected via the controller and inverter to
the fuse board or dedicated load (Fig 14).
If there is no generator or other electricity supply, batteriescan be used to store energy as it is generated by the
turbine, for use later when it is needed.The number and
size of the batteries depend on how long they would
be expected to continue supplying electricity without
the wind turbine; this is known as the autonomy or how
long the batteries need to operate.The batteries should
be of a deep-cycle type, which can be discharged deeply
without damage.The storage space must be well
ventilated as batteries give of a gas in their operation,
and preferably cool: warmer temperatures reduce
battery life (Fig 15).
13Electrical equipment mounted on a pattress
Non-grid connection14
15
Deep-cycle battery installation. (Photograph courtesy of Wind and Sun Limited)
8/11/2019 69945-microwind1
10/13
8 MICRO WIND GENERATION AND TRADITIONAL BUILDINGS
GRID CONNECTIONA wind turbine can also be used to supplement mains
electricity, offering the security of a continuous electrical
supply. In this case there are two inputs to the fuse board,
one from the turbine and one from the mains (Fig 16).
When the turbine is not generating enough energy, mains
electricity is used. If more electricity is generated by the
turbine than is needed, the excess can be exported tothe national grid.To do this a special meter must be
installed, with the agreement of the mains electricity
supplier. Electricity exported in this manner is generally
bought at a wholesale rate which is far lower than the
cost of having it supplied. In addition the electricity
supplier levies a charge for the metering facility.
16
MAINTENANCE ANDWORKING LIFE
ALL RENEWABLE INSTALLATIONS REQUIREMAINTENANCE TO ENSURE THEY REMAINRELIABLE AND EFFICIENT.When maintenance is carried out there is the potential
for damage to be caused to the fabric of the building.
When planning the installation it is important to talk to
the installer about how often equipment would need
routine maintenance and the equipment is accessed.
Regular inspection of cables and equipment conditions
will also be necessary.
As mentioned earlier it is important to remember that,
because the maximum working life of a wind turbine is
around 20 years and that of many of its electrical parts
far less, a building could have more than one installation.
Damage to the buildings fabric can be minimised with
careful planning not only of the installation but of the
turbines removal at the end of its useful life. Batteries
have a life of around 6-10 years, depending on the typeof battery and on environmental conditions.
GRANTS
FEED IN TARIFFS WERE INTRODUCED BY THEGOVERNMENT FROM THE 1ST APRIL 2010.THEY WERE INTRODUCED TO INCREASE THELEVEL OF RENEWABLE ENERGY IN THE UK TO
A TARGET OF 15% OF TOTAL ENERGY FROMRENEWABLES BY 2020.The scheme gives a fixed payment for all the electricity
produced by the wind turbine called the 'generation
tariff'.This tariff is paid whether it is used or exported to
the grid. If the turbine generates a surplus you can export
to the electricity grid where an additional bonus called an
'export tariff' is paid.
The amount paid from the 'generation tariff' is dependent
on the type of renewable and its size.The export tariff is
dependant on how much excess electricity is sent back to
the grid and is paid at a flat rate of 3p/kilowatt hour
regardless of what technology is used.The tariffs are paid
for 20 or 25 years - so will cover the life time of the
turbine.
Once the installation is complete your chosen energy
supplier will enter the installation on the Central FIT
Register.The energy supplier will then start paying you the
'generation tariff' and if you export the 'export tariff. It is
necessary to have an Ofgem approved Total Generation
Meter which should be installed with your system to
measure the energy generated. If you choose to exportan additional meter is required. It varies as to whether the
energy company will pay for this meter or not.
Grants are also available from some local Governments
for renewables and energy efficiency measures.
8/11/2019 69945-microwind1
11/13
MICRO WIND GENERATION AND TRADITIONAL BUILDINGS 9
USEFUL CONTACTS
RENEWABLE ENERGYAND CLIMATE CHANGE
Historic Environment, Local
Management (HELM)English Heritage
1 Waterhouse Square
138-142 Holborn
London EC1N 2ST
Tel: 020 7973 3000
www.helm.org.uk
UK Climate ImpactsProgramme (UKCIP)Oxford University Centre
for the EnvironmentDyson Perrins BuildingSouth Parks Road
Oxford OX1 3QY
Tel: 01865 285717
www.ukcip.org.uk
ENERGY CONSERVATIONAND FEED IN TARIFFS
Carbon Trust6th Floor
5 New Street SquareLondon EC4A 3BF
Tel:0800 085 2005
www.carbontrust.co.uk
WIND TURBINES AND WILDLIFE
The Royal Societyfor the Protection of BirdsThe Lodge
Sandy
Bedfordshire SG19 2DL
Tel: 01767 680551
www.rspb.org.uk
Bat Conservation TrustUnit 2, 15 Cloisters House
8 Battersea Park Road
London SW8 4BG
Tel: 020 7627 2629
www.bats.org.uk
Natural EnglandNorthminster HousePeterborough PE1 1UA
Tel: 0845 600 3078
www.naturalengland.org.uk
WIND POWER
British Wind Energy AssociationRenewable Energy House
1 Aztec Row, Berners Road
London N1 0PW
Tel: 020 7689 1960
www.bwea.com
Centre for Alternative TechnologyMachynlleth
Powys SY20 9AZ
Tel: 01654 705950
www.cat.org.uk
BRE TrustGarston
Watford
Hertfordshire WD25 9XX
Tel: 01923 664598www.bretrust.org.uk
PLANNING GUIDANCE
Department for Communitiesand Local GovernmentEland House
Bressenden Place
London SW1E 5DU
Tel: 020 7944 4400
www.communities.gov.uk
English Heritage1 Waterhouse Square
138-142 Holborn
London EC1N 2ST
Tel: 020 7973 3000
www.english-heritage.org.uk
RENEWABLE ENERGY GRANTS
Department of Energyand Climate Changehttp://www.decc.gov.uk
ACKNOWLEDGEMENTS
English Heritage would like toacknowledge the help of thefollowing people in the productionof this guide:
Eva Marwick, Renewable DevicesSwift Turbines Limited
Alison Anderson,
Eclectic Energy Limited
Moneeb Siddiqui,
Proven Energy Limited
Sophie Duncan,
Wind and Sun Limited
Text by Caroline Cattini,English Heritage Building services
Engineering and Safety Team (BsEST)
All Illustrations by Judith Dobie,
Centre for Archaeology,
English Heritage
Edited by John King
Produced by Creative Services,
English Heritage
October 2010
Product Code: 51366
http://www.helm.org.uk/http://www.ukcip.org.uk/http://www.carbontrust.co.uk/http://www.rspb.org.uk/http://www.bats.org.uk/http://www.naturalengland.org.uk/http://www.bwea.com/http://www.cat.org.uk/http://www.bretrust.org.uk/http://www.communities.gov.uk/http://www.english-heritage.org.uk/http://www.decc.gov.uk/http://www.decc.gov.uk/http://www.english-heritage.org.uk/http://www.communities.gov.uk/http://www.bretrust.org.uk/http://www.cat.org.uk/http://www.bwea.com/http://www.naturalengland.org.uk/http://www.bats.org.uk/http://www.rspb.org.uk/http://www.carbontrust.co.uk/http://www.ukcip.org.uk/http://www.helm.org.uk/8/11/2019 69945-microwind1
12/13
(EVO03/08)VIT1000
Building servicesEngineering and Safety TeamEnglish Heritage1 Waterhouse Square138-142 HolbornLondon EC1N 2ST
8/11/2019 69945-microwind1
13/13
If you would like this document in a different format, please contactour Customer Services department:Telephone: 0870 333 1181Fax: 01793 414926Textphone: 01793 414878
E-mail: [email protected]
mailto:[email protected]:[email protected]