72
METHOD OF CONSTRUCTION OF METHOD OF CONSTRUCTION OF SEGMENTAL CONCRETE BRIDGE SEGMENTAL CONCRETE BRIDGE By , P P AMBEDKAR

6151968 Method of Construction of Segmental Concrete Bridge

Embed Size (px)

Citation preview

Page 1: 6151968 Method of Construction of Segmental Concrete Bridge

METHOD OF CONSTRUCTION METHOD OF CONSTRUCTION OF SEGMENTAL CONCRETE OF SEGMENTAL CONCRETE

BRIDGEBRIDGE

By ,

P P AMBEDKAR

Page 2: 6151968 Method of Construction of Segmental Concrete Bridge

Objective Of Dissertation work

Construction of segmental bridge involves use of different machineries and requires huge amount of skilled manpower. Hence the intention of dissertation is to study the Methods & techniques used in Construction of Segmental Bridge by Under Slung Method which consist of following activities.

1. Construction of Sub-structure

2. Construction of super-structure

Page 3: 6151968 Method of Construction of Segmental Concrete Bridge

Development of precast segmental bridge construction

First segmental bridge

Second segmental bridge

Segmental bridges in India

Page 4: 6151968 Method of Construction of Segmental Concrete Bridge

What is segmental construction

Pier

PC segmentsPrestressing cables

Page 5: 6151968 Method of Construction of Segmental Concrete Bridge

Method of construction of segmental bridge

1.Cast-in-Place Segmental Construction (Balance Cantilever method)

Bridge across the Lahn River in Germany

Page 6: 6151968 Method of Construction of Segmental Concrete Bridge

2. Precast Segmental Construction

Flyover at Agriculture College Pune

Page 7: 6151968 Method of Construction of Segmental Concrete Bridge

General design consideration

Principal Dimension of Segment

W = Top Slab width

D = Construction depth

B = Bottom slab width

L = Segment length

Page 8: 6151968 Method of Construction of Segmental Concrete Bridge
Page 9: 6151968 Method of Construction of Segmental Concrete Bridge

Construction of substructure

Cast-in-situ Pile

Detailed breakdown of activities is mentioned below

1. Setting Out2. Removal of Overburden3. Driving Permanent Liner4. Boring / Chiseling5. Reinforcement Cage Lowering6. Concreting

Page 10: 6151968 Method of Construction of Segmental Concrete Bridge

1. Setting Out

Page 11: 6151968 Method of Construction of Segmental Concrete Bridge

2. Removal of overburden3. Driving permanent liner

Tripod

Driving cap

Driving monkey

Liner

Page 12: 6151968 Method of Construction of Segmental Concrete Bridge

4. Boring/ Chiseling

BAILER

CHISEL

Page 13: 6151968 Method of Construction of Segmental Concrete Bridge

BailerExcavated mud

Removing of excavated material with help of bailer

Page 14: 6151968 Method of Construction of Segmental Concrete Bridge

5. Reinforcement cage lowering 6.Concreting

Chute

Funnel

Tremie pipe

Page 15: 6151968 Method of Construction of Segmental Concrete Bridge

Major Equipment Required

1) F 35d/d winch - 4 no

2) Pile driving tools & accessories - 4 set

3) Tripod - 4 set

4) Generator 70 KVA - 2 no

5) Welding machine - 2 no

6) Concreting equipments - 2 set

7) Batching Plant - 1 no

Page 16: 6151968 Method of Construction of Segmental Concrete Bridge

TIME CYCLE

Sr.No. Activity Duration

1 Road breaking/removal of top overburden/ Identification of utility services.

2 days

2 Positioning tripod / winch 2 hours

3 Survey & setting out 2 hours

4 Permanent liner driving/ boring 20 hours

5 Chiseling(6m @ 0.1m/hour) 60 hours

6 Cage lowering 2 hours

7 Tremie Pipe lowering/flushing 2 hours

8 Concreting 3 hours

9 Removal of tripod/winch 2 hours

Total time for pilling 93 hours

There fore total time for one pile @ 20hours per day working

4.5 days

Page 17: 6151968 Method of Construction of Segmental Concrete Bridge

Construction Of Pile Cap

Detailed breakdown of activities is mentioned below

1. Clear area for excavation and marking

2. Exaction up to pile cap bottom level i. Excavation in soft soil ii. Chiseling in hard strata

3. Simultaneously chipping of pile

4. Preparation of bed with PCC

5. Cutting and bending and preparation of reinforcement

cage

6. Shuttering for pile cap

7. Concreting

Page 18: 6151968 Method of Construction of Segmental Concrete Bridge

1. Clear area for excavation and marking2. Exaction up to pile cap bottom level i. Excavation in soft soil ii. Chiseling in hard strata

3. Chipping of pile

Bottom of Pile cap Pile chipping by jack

hammer

Page 19: 6151968 Method of Construction of Segmental Concrete Bridge

4. Preparation of bed with PCC

Bed preparation for pile cap by laying PCC

Page 20: 6151968 Method of Construction of Segmental Concrete Bridge

5. Cutting and bending and preparation of reinforcement cage

Pile reinforcement bar

Tying of reinforcement

Page 21: 6151968 Method of Construction of Segmental Concrete Bridge

6. Shuttering

7. Concreting of pile cap

Shuttering

Haizen cloth for curing

Page 22: 6151968 Method of Construction of Segmental Concrete Bridge

MAJOR EQUIPMENTS REQUIRED

1. JCB Excavator 1 No.

2. Dumper 1 No.

3. Breaker (Jack hammer) 2 Nos.

4. Bar bending and cutting machine 1 No.

5. Concrete batching plant 1 No.

6. Transit Mixer 2 Nos.

7. Needle vibrators (60 mm) 2 Nos.

Page 23: 6151968 Method of Construction of Segmental Concrete Bridge

TIME CYCLE Sr.No. Activity Duration

1 Waiting period for curing of pile 7 Days

2 Clearing area, survey and marking for excavation 2 Hours

3 Excavation in soft soil 12 Hours

4 Chiseling in hard rock 2 Days

5 Cutting and removing liner 4 Hours

6 Chipping piles up to pile cap bottom level PCB) 4 Days

7 Preparation of bed with PCC as leveling course 8 Hours

8 Reinforcement cutting, bending and fabricating cage 1 Day

9 Placing and fixing shuttering 3 Hours

10 Concreting 1 HourTotal time = 8.5 days

Page 24: 6151968 Method of Construction of Segmental Concrete Bridge

Construction of Pier

Job breakdown

1. Cutting, and bending of reinforcement

2. Preparation of reinforcement cage

3. Casting Pier starter

4. Erection of staging and simultaneously fixing

shutters

5. Concreting of pier

6. De-shuttering and dismantling staging

7. Curing

Page 25: 6151968 Method of Construction of Segmental Concrete Bridge

1. Cutting, and bending of reinforcement & preparation of reinforcement cage

2.Casting Pier starter

3. Erection of staging and simultaneously fixing shutters

Pier shutter

Staging for supporting pier shutter & providing working platform at top for concreting

Page 26: 6151968 Method of Construction of Segmental Concrete Bridge

4. Concreting of pier

5. Curing

MAJOR EQUIPMENTS REQUIRED

1. HM 101 Crane -1 No2. Bar bending and cutting machine-1 No.3. Concrete batching plant -1 No.4. Transit Mixer - 2 Nos.5. Concrete Pump -1 No.6. D.G. Set -1 No.7. Compressor - 2 Nos.8. Needle vibrators (60 mm) - 2 Nos.

Page 27: 6151968 Method of Construction of Segmental Concrete Bridge

TIME CYCLE

Sr. no. Activity Duration

1 Cutting and Bending Reinforcement 2 Days

2 Tying and Cage Preparation 1 Day

3 Casting Starter and Curing 2 Hrs.

4 Staging and Simultaneously Shuttering 1 Day

5 Concreting 3 Hrs.

6 Waiting till achieving strength for deshuttering 1 Day

7 Deshuttering 12 Hrs.

8 Curing 28 Days

Total time required excluding curing = 3 days

Page 28: 6151968 Method of Construction of Segmental Concrete Bridge

CONSTRUCTION OF APPROCHES

Construction of approach involve two major activity that

are as follows:

i) Construction of Abutment wall.

ii) Construction of Wing wall (Retaining wall)

Page 29: 6151968 Method of Construction of Segmental Concrete Bridge

Types of abutment:

Masonry abutments:

RCC abutments:

Page 30: 6151968 Method of Construction of Segmental Concrete Bridge

R.C.C Abutments

In this case abutment wall is directly rest over raft /pile

foundation. Whole abutment wall made of rich mix concrete. Abutment

wall construction involves following activity:

1. Cutting, and bending of reinforcement

2. Preparation of reinforcement cage

3. Casting abutment starter

4. Erection of staging and simultaneously fixing

shutters

5. Concreting of abutment.

6. De-shuttering and dismantling staging

7. Curing

Page 31: 6151968 Method of Construction of Segmental Concrete Bridge

Staging arrangement

Shuttering

RCC Abutment

Page 32: 6151968 Method of Construction of Segmental Concrete Bridge

The wings walls are of masonry or RCC masonry, now days wings wall are constructed

with new technique that is Geosynthetic Soil Retaining wall in which precast RCC

panel is used. The advantage of this construction system is given below.

1. It requires very limited construction space compared to the conventional wall

systems.

2. The completed structure occupies less space compared to the conventional wall

systems.

3. By using a facing of high rigidity, the stability of the wall system is increased while the

deformation is minimized.

4. The geosynthetic layers are closely spaced so that a wide range of backfill can be

used without affecting performance.

Wing wall

Page 33: 6151968 Method of Construction of Segmental Concrete Bridge

Component of part of GSR Wall

1.Concrete leveling Pad:

2.Precast concrete facing panels

3.Joint material

4.Geogrids

5.Backfill

Page 34: 6151968 Method of Construction of Segmental Concrete Bridge

Construction of Superstructure

Construction of Superstructure of segmental bridge involves two major activities that are as follows:

1) Segment Casting

2) Segment Erection

Different method of segment casting:

1)Long line casting

2)Short line casting

Page 35: 6151968 Method of Construction of Segmental Concrete Bridge

Long line casting

Page 36: 6151968 Method of Construction of Segmental Concrete Bridge

Short line casting

Page 37: 6151968 Method of Construction of Segmental Concrete Bridge

Segment casting involves following activities

1) Base mould preparation

2) Surveying and marking

3)Reinforcement cage leveling

4)Lowering and positioning stopend

5)Placing and fixing inner formwork

6)Concreting and finishing

7)Deshuttering of inner formwork and stopends

8)The segment used for match casting is then placed in the stacking yard and the newly

casted segment is used for next match casting.

Page 38: 6151968 Method of Construction of Segmental Concrete Bridge

1) Pre-cast Bed Survey and Setting out of moulds as per the co-ordinates.

Page 39: 6151968 Method of Construction of Segmental Concrete Bridge

2) Changing/re-fixing of liner material where required and cleaning of beds.

RUBBER LINER

3) Surveying and marking

4) Reinforcement cage lowering:

LIFTING FRAME

REINFORCEMENT CAGE

EOT CRANE

Page 40: 6151968 Method of Construction of Segmental Concrete Bridge

5) Lowering and positioning stopend:

Turn buckels

False work

StopendREINFORCEMENT CAGE

Page 41: 6151968 Method of Construction of Segmental Concrete Bridge

6. Placing and fixing inner-formwork:

Inner formwork

7. Concreting and finishing:

Page 42: 6151968 Method of Construction of Segmental Concrete Bridge

8. Deshuttering INF& Stopend:

9. Lifting and stacking of segments:

MAJOR EQUIPMENTS REQUIRED FOR SEGMENT CASTING

1) EOT 120T Capacity - 1 No.

2) Welding Machine - 2 No.

3) Gas-cutting Equipment - 2 No.

3) Concreting Equipments - 2 Sets

4) Batching Plant - 1 No.

5) Transit Mixer - 2 No.

Page 43: 6151968 Method of Construction of Segmental Concrete Bridge

TIME CYCLE Sr. No. Activity Description Time

Required in Hrs.

1 Base mold cleaning, rectification of rubber liner and applying POP

6

2 Survey and marking 1

3 Lowering reinforcement cage 1/2

4 Lowering and aligning stopend with jacks and knuckle bolts 1

5 Placing and fixing inner-formwork 8

6 Concerting and finishing 3

7 Curing till deshuttering stopend 24

8 Deshuttring stopend 2

9 Curing till deshuttering inner-formwork 46

10 Lifting and stacking segment 1Total time= 92 ½ Hrs

Page 44: 6151968 Method of Construction of Segmental Concrete Bridge

Segment Erection

Probably the most significant classification of segmental bridges

is by method of construction. Although construction methods may be

varied as ingenuity of the designers and the contractor they fall into two

basic categories:

1) Cast-in-Place segmental construction. (Balance Cantilever method)

2) Precast segmental construction.

Page 45: 6151968 Method of Construction of Segmental Concrete Bridge

Cast-in-Place segmental construction

Segment Casting Cycle

Page 46: 6151968 Method of Construction of Segmental Concrete Bridge

Precast segmental construction

1)Segment erection by Crane

2) Segment erection by Winch and Beam

Page 47: 6151968 Method of Construction of Segmental Concrete Bridge

3)Launching Gantry (Over head method)

4)Segment erection by Under-slung method

Page 48: 6151968 Method of Construction of Segmental Concrete Bridge

Segment erection by Under Slung Method Segment erection involves following activities

1. Survey and Barricading

2. Erection of EOT

3. Fabrication and erection of staging

4. Erect sliding trolley with jack arrangement

5. Launch precast segments

6. Temporary pre stressing of segments

7. Permanent pre stressing

Page 49: 6151968 Method of Construction of Segmental Concrete Bridge

1. Survey and Barricading

2. Erection of EOT

Rail track alignment

EOT crane of 125 tone capacity

Page 50: 6151968 Method of Construction of Segmental Concrete Bridge

3. Fabrication and Erection of Staging

Main girder

Seating girder

Concrete block

Cribs

Bracing

Page 51: 6151968 Method of Construction of Segmental Concrete Bridge

4. Erect Sliding Trolley with Jack Arrangement

Screw jacks arrangement with pot bearing

Main girder

Tie box

Page 52: 6151968 Method of Construction of Segmental Concrete Bridge

5. Transportation of precast segment

6. Launch Precast Segments

7. Temporary Prestressing of Segments

Mac-alloy barLifter

Hydraulic machine

Hydraulic pipe

Outside temporary prestressing

Page 53: 6151968 Method of Construction of Segmental Concrete Bridge

Inside temporary prestressing

Page 54: 6151968 Method of Construction of Segmental Concrete Bridge

8. Bearing Installation

Page 55: 6151968 Method of Construction of Segmental Concrete Bridge

8. Permanent Prestressing

Page 56: 6151968 Method of Construction of Segmental Concrete Bridge

TIME CYCLE

Sr. No. Activity Duration

1 Staging Arrangement 1 Day

2 Placing of segments 1.5 Days

3 Dry Matching 0.5 Days

4 Glue and temporary stressing 1.0 Day

5 Install Bearing/ grouting and waiting till attain strength

2.0 Days

6 Permanent pre stressing 0.5 Days

7 Dismantle staging 2 Days

Average Progress: 6 Days per span

Page 57: 6151968 Method of Construction of Segmental Concrete Bridge

Case StudyNAME OF PROJECT: PUNE FLYOVER AT UNIVERSITY CIRCLE & AGRICULTURE COLLAGE.SITE ADDRESS: GANESHKHIND ROAD, UNIVERSITY CIRCLE, PUNE – 411 007

NAME OF CONTRACTOR: AFCONS INFRASTRUCTURE LIMITED NAME EMPLOYER: MAHARASTRA STATE ROAD DEVELOPMENT CORPORATION

NAME CONSULTANT: DAR CONSULTANTS (U.K) LTD. in association with DAR CONSULTANTS (I) PVT. LTD

Page 58: 6151968 Method of Construction of Segmental Concrete Bridge
Page 59: 6151968 Method of Construction of Segmental Concrete Bridge

UNIVERSITY CIRCLE JUNCTION:

GENERAL FEATURES OF UNIVERSITY CIRCLE FLYOVER

1) Length = 700 M between abutments

2) Carriageway = Single three lane carriageway

3) Foundation = Bored cast-in situ piles resting on rock

4) Substructure = RCC Piers

5) Superstructure = Segmental, Deck width – 12 M

Page 60: 6151968 Method of Construction of Segmental Concrete Bridge

AGRICULTURE COLLEGE JUNCTION

GENERAL FEATURES OF AGRICULTURE COLLEGE FLYOVER

1) Length = 210 M between abutments

2) Carriageway = Dual two lane carriageway

3) Foundation = Bored cast-in situ piles resting on rock

4) Substructure = RCC Piers

5) Superstructure = Segmental, Deck width – 16.4 M

Page 61: 6151968 Method of Construction of Segmental Concrete Bridge

The pre-casting Yard includes the following:

Casting Bay : For casting deck segments.

Curing Yard : For curing deck segments.

Stacking Yard : For stacking deck segments.

Reinforcement Yard : For fabrication of reinforcement of all structural elements

like pile, pile cap, pier, precast segment, etc.

Casting, Curing & : For casting, curing & stacking of Parapet, Retaining

Stacking Bay wall & Kerbs.

Fabrication workshop: For fabrication of structural steel for shuttering,

supportive elements & temporary works.

Mechanical workshop : For fabrication of tie rod

Page 62: 6151968 Method of Construction of Segmental Concrete Bridge

CLASSIFICATION OF SEGMENTS

No TypeSegment

widthLocation & Function

1

End Diaphragm (ED) 1.45 ED rest on Abutment. It also has a downstand that enables it to sit on bearings. It has a wall ... It houses coupler cones for pre- stressing cables which are locked here.

2Adjacent to End Diaphragm

(EDA)2.095

It is located adjacent to ED segment.

3 Internal Diaphragm (ID)

2ID segment rest on all the piers except

expansion piers.

4Standard Segment(SS) 2.725 There are 3 nos. SS in the middle of

every span.

5Coupling segment stressing

end (CSS)2.917 CSS segment last segment of

intermediate span which has stressing

6Coupling segment coupling

end (CSC)2.917 CSC Segment is starting segment of

next span

Page 63: 6151968 Method of Construction of Segmental Concrete Bridge
Page 64: 6151968 Method of Construction of Segmental Concrete Bridge

SEGMENT ERECTION There are 3 types of spans to be erected i.e.:

• Type A-Beginning span of each bridge unit,

• Type B-Internal spans,

• Type C- End of each unit.

Type A has 13 segments to be erected with an End diaphragm at the start of

the span. And a CSS segment at the end of the span.

Type B Span start with CSC segment & end with CSS segment.

Type C Span start with CSC segment & end with ED segment.

Page 65: 6151968 Method of Construction of Segmental Concrete Bridge

PLAN SHOWING DIFFERENT TYPES OF SEGMENT WITH THERE LOCATION IN SPAN “A” TYPE.

Page 66: 6151968 Method of Construction of Segmental Concrete Bridge

For erection of 16.4 m wide segment involves following activities

1. Survey and Barricading

2. Erection of EOT

3. Fabrication and erection of staging

4. Erect sliding trolley with jack arrangement

5. Launch precast segments

6. Temporary pre stressing of segments

7. Permanent pre stressing

Page 67: 6151968 Method of Construction of Segmental Concrete Bridge

MAJOR EQUIPMENTS DEPLOYED

1) EOT 60T Capacity - 1 No.

2) EOT 120 T capacity - 1 No.

3) Service crane PH 320 - 2 No

4) JCB Excavator -

2 Nos.

5) Trailer of 40 T capacity - 3 No.

6) Trailer of 100 T capacity -1 No.

Labour required for segment erection including staging& gluing :

• Welder = 01• Grinder = 01• Gas cutter = 01• Skilled labour = 17• Unskilled labour = 10

TOTAL NO. = 30

Page 68: 6151968 Method of Construction of Segmental Concrete Bridge

Technical detailsCapacity of horizontal hydraulic jacks = 50TCapacity of screw jacks = 100TCapacity of one HT strands = 25T Stress induced in each strands = 25.26 Kg/cm2Total stress induced in nineteen strands = 480 Kg/cm2Total elongation of HT cables = 265mmDiameter of one stand = 15.7mm Diameter of one duct = 110mmGluing material used = Sikadur (Component A & B)Quantity of gluing material required per joint = 70 kgWastage of gluing material per joint = 7 kgLoad carrying capacity of Bearing plate = 800TGrouting pressure = 5 Kg/cm2

Properties of gluing material given below

Gluing details

Segment Gluing

Bearing Gluing

Setting time 45 Min. 1hr.

Strength 100 Mpa in 24hrs.

45 Mpa in 24hrs.

Mfg. by SIKA (Goa) Ltd. SIKA (Goa) Ltd.

Page 69: 6151968 Method of Construction of Segmental Concrete Bridge

Following were the main reasons to delay in the completion of project Land acquisition problem

Improper matching of segment

Delay in decision making

Labour strike

Delay in approval of drawings from consultant

Delay in diversion of utilities

Page 70: 6151968 Method of Construction of Segmental Concrete Bridge

CONCLUSION

After studying detail procedure segmental construction that segmental bridges posses following advantages

Rapid erection of superstructure.

High quality & high strength of concrete can be achieved.

Whenever we need to allow traffic underneath even during construction.

The structural geometry may be adopted to any horizontal or vertical curvature or any roadway super-elevation.

Concrete shrinkage & creep substantially reduced.

Segmental construction relatively insensitive to weather condition.

Enhanced durability of bridge.

Page 71: 6151968 Method of Construction of Segmental Concrete Bridge

Segmental bridge reveals following disadvantages

Need for higher level of technology in design

Necessity for a high degree of dimensional control.

The possible solution to the problems discussed in the case study can be enlisted as follows:

Perfect matching of segment at site can be achieved by considering vertical &

horizontal alignment of bridge profile at the time of segment casting.

Whenever the segments are not matched properly considerable time is lost in

chipping out the segment faces. Hence the segment casting should be done

accurately in accordance with drawings.

Page 72: 6151968 Method of Construction of Segmental Concrete Bridge

Thank You