Upload
amjad-pervaz
View
217
Download
0
Embed Size (px)
Citation preview
8/13/2019 6 1 Fire Protection
1/34
Section 6.0Fire Protection
Structural steelwork
Product:Knauf FireboardFp01
Small cavity barriers
Product: Earthwool Cavity Barrier
Mezzanine floors
Product:Rocksilk FireTech Slab
Fp03
Fp04
Structural steelwork
Product:Rocksilk FireTech Slab
Fp02
Large cavity barriers
Product:Rocksilk Smoke and FireBarrier
Fp05
Refurbishment of timber
separating/internal floor
Product:Earthwool Flexible SlabFp06
Steel Duct Encasement
Product:Rocksilk Pyroduct Slab
Fp07
8/13/2019 6 1 Fire Protection
2/34
66
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Fire protection of structural steelFire protection design
Can be installed prior to the building being
sealed and made watertight, in all
temperature and humidity conditions thisis in contrast to paint and sprays which are
often restricted by normal UK winter
conditions, causing potential delay to
site programs
Are fast, clean, and dry to install, with
negligible dust levels, allowing other trades
to work in close proximity
Are quick and easy to check (by visual
inspection) that all relevant areas have
been protected
Are fully compatible with drylining systems
and allow easy integration with partitioning
schemes
Fire protectionAny steel section which is an element of
structure and is deemed by any of the following
regulations to require fire resistance can be
protected with a fire protection system of dense
rock mineral wool slabs or fibre reinforced
gypsum based boards.
1. The Building Regulations (England and
Wales) Approved Document B (Fire Safety)
Volumes 1 and 2 (2006)
2. The Building (Scotland) Regulations,
Technical Booklets, Section 2, 2011
3. The Building Regulations (Northern Ireland)
Technical Booklet E, 2005
4. The Building Regulations (Republic of Ireland)
Technical Guidance Document B (2006)
Structural steel requires fire protection because
it loses structural strength at temperatures that
can be rapidly reached in a building fire. Thiswill consequently have a negative impact on the
structural integrity of the building. Protecting the
structural steel from the heat of a fire will delay
the onset of this loss of strength and the possible
collapse of the building. This is essential
because it allows extra time for both the
occupants of the building to escape and fire
services to tackle the fire. It could also prevent
the actual collapse of the building minimising
insurance losses. Building Regulations covering
fire safety are concerned with the preservation
of life.
With the increasing use of structural steel inconstruction, designers need fire protection
solutions that provide a combination of fast
installation and cost-effectiveness whilst
achieving the desired finish.
Whatever the application Knauf Insulation has
a range of board products and systems to cater
for any project.
When used for the fire protection of structural
steelwork, board systems offer several
compelling advantages over site applied paint
and spray coating systems.
Board systems:
Are manufactured to factory tolerances this
enables the specifier to be certain that the
correct thickness of fire protection is being
applied, by simply checking the thickness of
materials supplied
5. Loss Prevention Council Code of Practice for
Construction of Buildings
Steel sections can include universal beams,
columns and joists (plain and castellated),
structural and rolled tees, angles, channels and
round, square or rectangular hollow sections.
BenefitsBoth rock mineral wool slabs and fibre
reinforced gypsum boards offer a number of
advantages for the fire protection of structural
steelwork that make them ideal for fast track
projects.
Rock mineral wool
Lightweight product at less than half the
weight of calcium silicate slabs rockmineral wool fire protection boards are easy
to handle and fit on site par ticularly for
overhead work
Ease of cutting and fixing: Rock mineral wool
slabs are easy to cut with either a saw or a
sharp knife, furthermore there are four fixing
methods, all involve square edge butt joints
between the boards which enables a fast and
simple system to be installed without delaying
other trades and activities
Fibre reinforced gypsum
Smooth surface only requires decorative
finishes for completion Robust and impact resistant ideal for
columns and all exposed surfaces
Easy to cut to size can be scored and
snapped to speed up cutting and reduce
dust levels
Knauf Insulation are members of
the Association for Specialist Fire
Protection, and our fire protection
products are listed in the Yellow
Book, which presents economical
methods for the fire protection of
structural steelwork to provide
compliance with Building
Regulations
8/13/2019 6 1 Fire Protection
3/34
267
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Fire protectionSolution optimiser and pathfinder
Fire protection
Period of fire resistance(mins)
Knauf Insulation solution
Mezzanine floorsProduct:Rocksilk FireTech Slab
See page: 280
0 mins 30 mins 60 mins 90 mins 120 mins 150 mins 180 mins 210 mins 240 mins
Fp03
Key
Find online. Visit knaufinsulation.co.uk and key in construction code to find the
most up to date information on your chosen solution.Pb01
Fp04
Large cavity barriersProduct:Rocksilk Smoke and Fire Barrier
See page: 286
Fp05
Refurbishment of timber separating/internal floorProduct:Earthwool Flexible Slab
See page: 292
Fp06
Steel Duct EncasementProduct:Rocksilk Pyroduct Slab
See page: 294
Fp07
Structural steelworkProduct:Rocksilk FireTech Slab
See page: 274
Structural steelworkProduct:Knauf Fireboard
See page: 268
Fp01
Fp02
8/13/2019 6 1 Fire Protection
4/34
68
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Fire protectionStructural steelwork
Knauf Fireboard
Typical constructionKnauf Fireboard is used in frameless
encasements. The product has been specially
developed to accept direct edge fixings.
Casings consist of Knauf Fireboard screwed or
stapled to itself at abutting corners.
For steelwork encased on all four sides, Knauf
Fireboard is fixed at each corner directly
through the material, independent of the columnor beam. For partial encasement, involving wall
or ceiling abutments, Knauf Fireboard is fixed to
light gauge steel angles.
Knauf Insulation recommend the use of Knauf
Drywall Screws, essential for fast construction,
solid fixing and tightly closed edge joints.
ProductsKnauf Fireboardis a gypsum based board
specially developed for high performance lining
and encasement, providing up to two hours of
fire protection.
Knauf Fireboard has a high quality white
smooth surface finish ideally suited as a self
finish. Its surface allows direct decoration with
most paint finishes or it can be plastered*.
Knauf Drywall Screwsare gold passivated
screws with spoon tips and hi-low threads.
Knauf Fireboard can also be installed using
proprietary staples.
*Consult plaster manufacturer prior to application of plasterfinish.
Fp01 Quick and easy to install
Dry fix system providing up to 2hours fire protection
Combined fire protection andaesthetic finish
Knauf Fireboard
Non-combustible with a Euroclass
A1 reaction to fire rating
Zero Ozone Depletion Potential (ODP)
Zero Global Warming Potential (GWP)
Edge fix the boards usingeither Knauf Drywall Screwsat maximum 150mm centresor proprietary staples at120mm centres.
Knauf Fireboard
Knauf Drywall Screws at maximum100mm centres into backing strips
Abutment angles: light gaugesteel angle provides support atsoffit and wall junctions. Fixed toadjoining soffit or section flange.
REFURBNEW BUILD
8/13/2019 6 1 Fire Protection
5/34
269
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Typical specificationKnauf Fireboard, ...mm thick, to be used to
provide fire protection to structural steelwork.
It is to be installed on beam*/column* as a
complete 4 sided*/3 sided*/2 sided*
encasement (*specifiers choice) to provide
......minutes fire protection as detailed in the
Installation section.
Alternatively, consult the NationalBuilding Specifications, Standard
version clause/clauses
K10/265
Knauf Insulation specification clauses can be
downloaded from knaufinsulation.co.uk/nbs
PerformanceFire performance
The system can provide up to 2 hours fire
protection. For precise calculation of fire
protection periods, please contact Knauf
Insulation Technical Advice and Support Centre.
Knauf Fireboard is non-combustible
to BS 476: Part 4: 1970 (1984) and Class 1
surface spread of flame to BS 476: Part 7:1997. Knauf Fireboard complies with the Class
0 requirements of the Building Regulations
when tested to BS 476: Part 6: 1989 and Part
7: 1997 and with the limited combustibility
described in the Building Regulations.
Humidity
Constant humidity over 95% or subjection to
continuous water will reduce the serviceability
of the boards.
Operating temperatures
Continuous long term exposure to temperatures
over 50C can induce a change of state which
would reduce the physical performance and
serviceability of the boards.
Health and safety
Knauf Fireboard must be installed with care.
Ensure adequate ventilation during installation,particularly when cutting boards. Avoid harsh
body contact with sharp cut edges of metal
components. Refer to Knauf Insulation Material
Safety Data Sheets and to the Health and Safety
Executive publications.
For Hp/A tables please visit
knaufinsulation.co.uk
Knauf Fireboard casing
Stagger joints by 300mm minimum
Direct edge-fixing with Knauf DrywallScrews at 200mm centres orproprietary staples at 120mm centres
8/13/2019 6 1 Fire Protection
6/34
70
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
1 2 Hold in place thefirst 2 boards
with clamps.
3 After measuring the
size of the remaining
2 sides, cut another
two to the depth of
the column plus
twice the thickness
of the board.
4 Apply the remaining
boards, adjusting
the length of
adjoining boards to
ensure that board
joints are staggered
by at least 300mm.
5Edge-fix the boardsusing either selfdrilling Knauf
Fireboard Gripper
Screws at 200mm
centres or proprietary
staples at 120mm
centres. KnaufFireboard Gripper
Screws should
penetrate into the
casing by at least
30mm
Installation sequence
Fire protectionInstallation of column system
Partial column encasement
Assuming a typical three-sided encasement
where one of the column flanges straddles a
wall, follow the same procedure as outlined
for four-sided encasement with the following
differences:
Fix 25 x 25mm light gauge steel angles,
in continuous lengths, to either the abutting
wall face or the inner flange of the column.
Use appropriate proprietary fixings at
600mm centres
Double layer application
Install the first layer as described for either full
or partial encasement. Secure the second layer
to the first with fixings spaced as for the first
layer but avoid coincident fixing positions.
It is good practice that board joints are
staggered as with the first layer between
adjoining boards and also between the twolayers. In the case of structural steelwork,
double layer encasement will obviate the need
for joint backing strips.
Installation
Steelwork encasements must be installed in full
accordance with Knauf Insulations
recommendations and in compliance with
BS 8212: 1995 and BS 8000: Part 8: 1994.
The installation procedures outlined here relate
to normal single layer applications.
Knauf Drywall Screws
Knauf Drywall Screws should penetrate into the
casing by at least 30mm.
Four-sided column encasement
Cut two boards to the width of the column
flange. Cut another two to the depth of the
column plus twice the thickness of the board
Adjust the length of adjoining boards to
ensure that board joints are staggered by at
least 300mm
Edge-fix the boards using either Knauf
Drywall Screws at 200mm centres or
proprietary staples at 120mm centres
Cut two boards to
the width of the
column flange.
8/13/2019 6 1 Fire Protection
7/34
271
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Fire protectionInstallation of beam system
Beam encasement
Assuming a typical three-sided encasement,
where a beam is exposed directly below a level
soffit, fix light gauge steel angles to either the
adjoining soffit or the top flange of the beam.
Install continuous lengths of 25 x 25mm angle
using appropriate proprietary fixings at 600mm
centres.
Fix further lengths of 25 x 25mm angle at any
end abutment
Cut two boards to the depth of the section
plus twice the thickness of the board plus
l0mm. Screw-fix these to the angles at
150mm centres with 35mm Knauf Drywall
Screws
Cut a soffit board to the width of the steel
flange. The length of this board must differ
from the side boards to ensure adjacent
board joints are staggered by at least
300mm. Edge-fix this horizontal board to thetwo vertical boards using either self-drilling
Knauf Drywall Screws at 150mm centres or
staples at 120mm centres
Cut board off-cuts 100mm wide as joint
backing strips. Fit these, half-lapped, behind
all butt joints at the sides and soffit of the
beam fixed with Knauf Drywall Screws at
maximum 100mm centres
Double layer application
Install the first layer as described for either full
or partial encasement. Secure the second layer
to the first with fixings spaced as for the first
layer but avoid coinciding fixing positions.
It is good practice that board joints are
staggered as with the first layer between
adjoining boards and also between the two
layers. In the case of structural steelwork,
double layer encasement will obviate the need
for joint backing strips.
The second layer of boards across the webs are
fixed to the angle attached to the upper flange
using 55mm long Knauf Drywall Screws at
150mm centres and the second layer across the
bottom flange using Knauf Drywall Screws at
Installation sequence
1 Install continuous lengths of
25 x 25mm angle using
appropriate proprietary
fixings at 600mm centres, fix
further lengths of 25 x 25mm
angle at any end abutment.
2 Cut two boards to the depthof the section plus twice theboard thickness plus l0mm.
Screw-fix these to the anglesat 150mm centres with35mm Knauf Drywall
Screws.
3 Cut a soffit board to the
width of the steel flange.
The length of this board must
differ from the side boards to
ensure adjacent board joints
are staggered by at least
300mm.
Edge-fix horizontal board to
the two vertical boards using
either Knauf Fireboard
Gripper Screws at 150mm
centres or proprietary staples
at 120mm centres.
4 Cut board off-cuts 100mm
wide as joint backing strips.
Fit these, half lapped, behind
all butt joints at the sides
and soffit of the beam.
Fix with Knauf FireboardGripper Screws at maximum100mm centres.
6.
1
nominal 150mm centres, screw lengths should
be equal to the thickness of the second layer,
plus 30mm. Where two different thicknesses of
Fireboard are applied, the thicker layer is
installed first.
8/13/2019 6 1 Fire Protection
8/34
72
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Fire protectionApplication details for beams
25 x 25mm angle secured to top flangeof beam, or alternatively to soffit
Beam with partition abutment
Beam with wall abutment
25 x 25mm angle secured to top flange ofbeam, or alternatively to soffit
Knauf Drywall Screws at maximum100mm centres
Fireboard casing
Backing strip
10mm gap
Direct edge fixing with Knauf DrywallScrews at maximum 150mm centres orstaples at 120mm centres
C-Stud partition with standardU-Channel head track
Knauf Drywall Screws at maximum100mm centres
Fireboard casing
Direct edge fixing with KnaufFireboard Gripper Screws atmaximum 150mm centres orstaples at 120mm centres
Continuous 25 x 25mm KnaufFireboard Angle secured to substrateusing appropriate fixings
Masonry wall
8/13/2019 6 1 Fire Protection
9/34
273
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Column with partition abutment
Knauf C-Stud toggle-fixed to KnaufFireboard casing
Knauf Wallboard not fixed to this C-Stud
Direct edge fixing with Knauf DrywallScrews at maximum 200mm centres orstaples at 120mm centres
Continuous 25 x 25mm KnaufFireboard angle at each corner
Knauf Wallboard not fixed to this C-Stud
Direct edge fixing with Knauf DrywallScrews at maximum 200mm centres orstaples at 120mm centres
Column with wall lining abutment
8/13/2019 6 1 Fire Protection
10/34
74
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Fire protectionStructural steelwork
Rocksilk FireTech Slab
Noggin of Rocksilk FireTech Slabor Rocksilk FireTech Dry Fix NogginSlab
Rocksilk FireTech Slab
InstallationRocksilk FireTech Slab can be used with four
types of fixing methods for the fire protection of
structural steelwork and each system has its own
performance characteristics.
Fixing methods:
Dry Fix Noggin System
Adhesive Noggin Fixing System Combination Fixing System
Welded Pin Fixing System
Typical constructionThe exposed surfaces of any steel section are
fully enclosed in Rocksilk FireTech Slab, using
any of the fixing systems shown on the following
pages.
Rocksilk FireTech Slab can be used to provide
up to 4 hours fire protection to structural steel
and cast iron columns, beams and trusses. Steel
sections may include universal beams, columns
and joists (plain and castellated), structural and
rolled tees, angles, channels and round, square
or rectangular hollow sections.
ProductRocksilk FireTech Slabis a dense rock mineral
wool slab. It is available unfaced or faced with
a bright Class 0 reinforced aluminium foil, for
applications above clean rooms, within air
plenums, or for aesthetic purposes.
Plaster manufacturers advice and guidance
should be followed regarding pre-treatment of
Rocksilk FireTech Slabs before application ofplaster finishes
Rocksilk FireTech Dry Fix Noggin Slabis an ultra
high density rock mineral wool slab used for the
noggin in the Rocksilk FireTech Dry Fix Noggin
System.
Fp02 Flexible system with four installation
methods
Maintenance free, passive system
Clean installation process withnegligible dust generation
Rocksilk FireTech Slab
Non-combustible with a Euroclass A1
reaction to fire rating Zero Ozone Depletion Potential (ODP)
Zero Global Warming Potential (GWP)
Pig tail screws
REFURB
8/13/2019 6 1 Fire Protection
11/34
275
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Technical specificationRocksilk FireTech Slab, ...mm thick, to be
used to provide fire protection to structural
steelwork.
It is to be installed using the dry fix noggin
system*/adhesive noggin fixing system*/
combination fixing system*/welded pin
fixing system* (*specifiers choice) as
detailed in the Installation section.
Alternatively, consult the National
Building Specifications, Standard
version clause/clauses
K11/885
Knauf Insulation specification clauses can be
downloaded from knaufinsulation.co.uk/nbs
PerformanceFire performance
Rocksilk FireTech Slab is classified as
non-combustible to BS 476: Part 4:
1970(1984), Class 1 surface spread of flame
to BS 476: Part 7: 1997, and Class 0 to the
Building Regulations. Rocksilk FireTech Slab is
designed to provide up to 4 hours fire
protection to structural steelwork, thereby
satisfying the Building Regulations and
insurance demands for periods of fire
resistance.
Durability
Rocksilk FireTech Slab is rot proof, does not
sustain vermin and will not encourage the
growth of fungi, mould or bacteria.
Rocksilk FireTech Slab is odourless and
non-hygroscopic.
Rocksilk FireTech Slab is non-wicking when
tested to BS 2972: 1989: Section 12.When exposed to 90% relative humidity and
20C, Rocksilk FireTech Slab absorbs less than
0.004% of moisture.
For Hp/A tables please visit
knaufinsulation.co.uk
Noggin of Rocksilk FireTech Slab orRocksilk FireTech Dry Fix NogginSlab
Pig Tail Screws
Rocksilk FireTech Slab
8/13/2019 6 1 Fire Protection
12/34
76
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Fire protectionInstallation of Rocksilk FireTech Slab
Adhesive Noggin Fixing SystemUp to 2 hours fire protection
Attach web pieces to nogginswith pig tail screws at100mm centres.
Dry Fix Noggin SystemUp to 2 hours fire protection
Welded Pin Fixing SystemUp to 4 hours fire protection
Combination Fixing SystemUp to 3 hours fire protection
Attach web pieces tonoggins with pig tailscrews at 100mm centres.
The use of a dense rock mineral wool slab
requires no special vee cuts, drilling or
sub-frames, making it fast and easy to install.
Rock mineral wool slabs can be easily cut using
hand or power tools.
Note: Rocksilk FireTech Dry Fix Noggin Slab has a densityof 200 kg/m3.
The Combination Fixing System
Can be used to provide up to 2 hours fire
protection to all sizes of structural steelwork,
and up to 3 hours fire protection to steelwork
with section factors (Hp/A) of up to 133m-1for
columns and 143m-1for beams.
The Welded Pin Fixing System
Can be used to provide up to 3 hours fire
protection to all sizes of structural steelwork,
and up to 4 hours fire protection to steelwork
with section factors (Hp/A) of up to 172m-1for
columns and 184m-1for beams.
If section factors are above 260m -1contact our
Technical Advice and Support Centre.
Alternative installation methodsThe Dry Fix Noggin System
Is a fast and efficient friction fit noggin system
that does not require adhesive. It can give up to
2 hours fire protection to BS 476: Part 21.
When installing 20, 25 and 30mm Rocksilk
FireTech Slab, noggins should be cut from a
30mm Rocksilk FireTech Dry Fix Noggin Slab.
When greater thicknesses of Rocksilk FireTech
Slab are used, the noggins are cut from a
corresponding thickness of Rocksilk FireTech Dry
Fix Noggin Slab.
The Adhesive Noggin Fixing System
Can be used to provide up to 2 hours fire
protection to all sizes of structural steelwork.
100mm wide noggins ofRocksilk FireTech Dry FixNoggin Slab friction fittedbetween the flanges.
Attach flange pieces to webpieces using pig tail screwspositioned 25mm in fromeach end and at 150mmcentres.
Attach flange pieces toweb pieces using pig tailscrews positioned 25mmin from each end and at150mm centres.
100mm wide noggin ofRocksilk FireTech Slabglued into place usingsuitable adhesive
Attach the Rocksilk FireTechSlab web pieces by impalingover the welded pins andsecuring in place with 38mmspring steel washers.
Attach flange pieces to webpieces using pig tail screwsat 150mm centres.
Adhesive should be used atthe joint between subsequentweb pieces.
Attach the Rocksilk FireTechSlab web and flange piecesby impaling over the 3mmdiameter welded mild steelpins and securing in placewith 38mm spring steelwashers.
Adhesive should be used atthe joint between subsequentweb pieces.
8/13/2019 6 1 Fire Protection
13/34
277
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Adhesive noggin fixing systemNoggins are cut 100mm wide from 20mm thick
Rocksilk FireTech Slab. They should be cut to a
suitable length relative to the web size to give
a tight compression fit.
Noggins are glued top and bottom using a
typical adhesive thickness of 0.5mm and friction
fitted between the flanges at 600mm centres.
The noggins should be installed in such a way
that they are slightly 'proud' of the flange (by
about 2mm) and such that they coincide with
joints between the boards.
It is preferable to leave the noggins in position
for 4 hours to allow the adhesive to cure.
However, where this is impractical Rocksilk
FireTech Slab can still be fitted before the
adhesive cures since the noggins are essentially
friction fitted.
For web depths greater than 500mm, T-shaped
or solid noggins should be used, formed from
Rocksilk FireTech Slab, and screwed together
using pig tail screws.
Attach web pieces to noggins using pig tail
screws at 100mm centres
Solid noggin formed from one or more pieces
of Rocksilk FireTech Slab
Greaterthan
500mmFull
depth
100mm
T-shaped noggin formed from two pieces of
Rocksilk FireTech Slab joined at right angles
using pig tail screws
Insert noggins as described at 600mm
centres and if practicable leave for 4 hours
for adhesive to cure.
Cut Rocksilk FireTech Slab to size as follows:
Beams: flange pieces to dimension X, web
pieces to dimension Y + t (t = thickness of
board)
Columns: flange pieces to dimension X,web pieces to dimension Y + 2t
100mm
Greater
than
500mm
Y
X
Attach flange pieces to web pieces using pig
tail screws positioned 25mm in from each
end at 150mm centres.
Note: For flanges greater than 400mm use welded pinand spring steel washers to provide extra retention ofthe flange piece of insulation. The welded pins shouldbe located along the centre line of the flange at 300mmcentres.
8/13/2019 6 1 Fire Protection
14/34
78
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Fire protectionApplication details for beams
Partition abutment using a noggin fixing system
Wall abutment using a noggin fixing system
Pig tail screws at maximum100mm centres
Direct edge fixing with pig tail screws atmaximum 150mm centres
Attach flange piece to web piece byimpaling over welded pins and securingthe board to board joint with pig tailscrews at 150mm centres. Spring steelwashers are used over the welded pins toretain the insulation, any excess pinlength being trimmed off
Rocksilk FireTech Slab
C-Stud partition with standard U-Channel
head track
Pigtail screws at maximum 100mm centres
Attach flange piece to web piece by impalingover welded pins and securing the board toboard joint with pig tail screws at 150mmcentres. Spring steel washers are used overthe welded pins to retain the insulation, anyexcess pin length being trimmed off
Direct edge fixing with pig tail screws atmaximum 150mm centres
Rocksilk FireTech Slab
Masonry wall
Rocksilk FireTech noggin
8/13/2019 6 1 Fire Protection
15/34
279
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Column with wall lining abutment
Column with partition abutment
Adhesive detail
The adhesive used for gluing Rocksilk FireTech
Slabs should be a thixotropic paste type based
on soluble solids of silicate and potassium
mixed with clay or refractory mineral filler to an
approximate ratio of 70:30 by weight.
Steelwork should ideally be dry but the
presence of condensation will merely prolong
the cure time, not weaken the bond strength.
Since only the top and bottom sur face of each
noggin is glued with a typical adhesive
thickness of 0.5mm, excellent rates of usage are
achievable.Note: Steelwork should be clean and free from grease priorto the application of adhesive.
* For further details contact our Technical Advice andSupport Centre.
Rocksilk FireTech Slab
Masonry wall
Knauf Wallboard not fixed to this C-Stud
Direct edge fixing with pig tail screws atmaximum 150mm centres
Direct edge fixing with pig tail screws atmaximum 150mm centres
Rocksilk FireTech Slab
Knauf Wallboard not fixed to this C-Stud
Pig tail screws
The spirally wound or pig tail screws are
made from 16 gauge galvanised wire and
are available from stockists. A specification
is available on request from our Technical
Advice and Support Centre.
The screws should be installed flush at 150mm
centres on board to board joints and 100mm
centres over noggins, using either power or
hand tools. There is no need to countersink thescrew heads.
8/13/2019 6 1 Fire Protection
16/34
80
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Fire protectionMezzanine floors
Rocksilk FireTech Slab
Simple, clean and quick to install Provides up to 3 hours fire resistance System covers section factors up to
310 Hp/A - (A/V)
Rocksilk FireTech Slab
Non-combustible with a Euroclass A1reaction to fire rating
Zero Ozone Depletion Potential (ODP)
Zero Global Warming Potential (GWP)
PerformanceFire performance
Rocksilk FireTech Slab is classified as
non-combustible to BS 476: Part 4: 1970
(1984). Class 1 Surface Spread of Flame to BS
476: Part 7:1977, and Class O to the
Building Regulations. Rocksilk FireTech Slab is
designed to provide up to 3 hours fire
protection to the mezzanine floor column
support system, thereby satisfying the current
Building Regulations and insurance industry fire
resistance performance standards.
Performance
Rocksilk FireTech Slab is rot proof, does notsustain vermin, will not encourage the growth of
fungi, mould or bacteria and is odourless and
non-hygroscopic.
ProductRocksilk FireTech Slab is a dense rock mineral
wool slab specifically designed for the fire
protection of structural steelwork.
Typical construction
The exposed surface of a steel section is fully
enclosed in Rocksilk FireTech Slab, using a
metal clip, snap-lock system.
Installation
The column case is pre-fabricated to suit the
specific beam or column. It is lined with Rocksilk
Firetech Slab which is pre-bonded to the steel
skin. Note that no adhesive is applied to the
joints between individual slabs. The columncase is made of galvanized or PVC coated steel
minimum 0.7mm thick. For columns, the casing
is normally supplied in two pieces with the
closing face fixed with snap-lock joints.
Three-sided encasements are secured at 300mm
centres to continuous galvanized steel angles,
or the flange of the steel section, or to the wall
or floor at 500mm nominal centres.
Alternatively the casing may be secured using
an integral lip on the casing.
Fp03
Rocksilk FireTech Slab
REFURB
8/13/2019 6 1 Fire Protection
17/34
281
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Technical specificationRocksilk FireTech Slab.mm thick, to be
used to provide fire protection to structural
steelwork in a mezzanine floor system.
Alternatively, consult the National
Building Specifications, Standard
version clause/clauses
K11/885
Knauf Insulation specification clauses can bedownloaded from knaufinsulation.co.uk/nbs
Table 1 - Mezzanine floors
Time - mins Board Thickness (mm) Hp/A
60 20 224
25 260
30 310
35 310
40 310
45 310
90 20 91
25 115
30 139
35 165
40 190
45 217
50 244
55 260
60 270
65 310
120 20 57
25 72
30 87
35 102
40 117
45 133
50 149
55 165
60 181
65 198
180 30 49
35 58
40 66
45 75
50 84
55 92
60 101
65 110
8/13/2019 6 1 Fire Protection
18/34
82
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Cavity barriersCavity barrier design
Design considerationsEvery building must be designed and
constructed in such a way that in the event of
an outbreak of fire within the building, the
unseen spread of fire and smoke within
concealed cavities in its structure and fabric is
inhibited. The Building Regulations require
cavity barriers to sub-divide voids if they extend
beyond certain dimensions.
In addition cavity barriers are also required tobe placed above fire resisting partitions. Both
glass and rock mineral wool products are ideal
to act as cavity barriers due to their inherent
non-combustibility.
In the case of fire stopping minor imperfections
of fit between construction elements or
components, it is acceptable to seal small gaps
with unfaced glass or rock mineral wool
products. However, for specific periods of fire
resistance in small and large voids (as required
by the Building Regulations) it is necessary to
use specific products that have been tested and
assessed to offer the required performancewhen installed in a specific way, if necessary,
using specific fixing components.
Concealed cavitiesFire and smoke spread in concealed spaces is
particularly hazardous because fire can spread
quickly throughout a building and remain
undetected by the occupants of the building.
Cavity barriers are used to sub divide
cavities and so prevent smoke and flame from
by-passing fire-resisting walls and partitions.
The maximum distance between barriers must
be appropriate to the location of each cavity.Also, due consideration must be given to the
class of surface exposed within the cavity.
Cavity barriers should achieve at least 30
minutes fire resistance, providing a minimum of
30 minutes integrity and 15 minutes insulation.
Detailed requirements are complex. For full
details about the position and spacing of cavity
fire barriers refer to the relevant sections of the
appropriate Building Regulations.
Small cavity barriersSmall voids include the cavities in external walls
and voids beneath raised access floors. Largervoids include the spaces between suspended
ceilings and soffits or roofs.
In cavities in external walls the resilient
properties of glass mineral wool mean that it
can be compression fitted, between the outer
leaf and the inner leaf or frame. The non-
combustible nature of glass mineral wool allows
it to resist the effects of fire, enabling it to
remain in place during the fire and effectively
block the transfer of fire through the cavity.
Large cavity barriersIn England, Wales and Northern Ireland, all
cavity barriers should be constructed to provide
at least 30 minutes fire resistance and 15
minutes insulation. In Scotland large cavity
barriers, which are defined as being greater
than 1m x 1m in size, must provide the same.
Fixing systemsAny product used for fire protection can only be
considered to be offering a specific period of
fire protection when it is installed in the manner
specified in the appropriate fire test report. This
includes the specification of all associated
fixings and supporting frame work.
8/13/2019 6 1 Fire Protection
19/34
283
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
DefinitionsThe following definitions are taken from
Approved Document B (Fire safety) - Volume
2: Buildings other than dwellinghouses
(2006)
Cavity barrier
A construction, other than smoke curtain,provided to close a concealed space against
penetration of smoke or flame, or provided to
restrict the movement of smoke or flame
within such a space.
Fire stop
Seal provided to close an imperfection of
fit or design tolerance between elements or
components, to restrict the passage of fire
or smoke. Any unfaced glass or rock mineral
product can be used as a fire stop.
50mm RocksilkSmoke and FireBarrier 50mm Rocksilk
Smoke andFire Barrier
50mm cavity
Suspended ceilingof 12.5mm plasterboard
30 minutes fire resistance 1 hour fire resistance
Photograph courtesy of Henley Building Systems
Small cavity barriers - to be deleted
Large cavity barriersProduct:Rocksilk Smoke and Fire BarrierSee page: 286
Fp04
Fp05
Period of fire resistance(mins)
Knauf Insulation solution 0 mins 30 mins 60 mins 90 mins 120 mins 150 mins 180 mins 210 mins 240 mins
8/13/2019 6 1 Fire Protection
20/34
84
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Meets Building Regulationrequirements for fire, acoustics andparty wall bypass applications
Simple, clean and quick to install
Colour coded for easy identification
Earthwool Cavity Barrier
Non-combustible with a Euroclass A1
reaction to fire rating A+ Generic BRE Green Guide rating
Zero Ozone Depletion Potential (ODP)
Zero Global Warming Potential (GWP)
Fire protectionSmall cavity barriers
Earthwool Cavity Barrier
InstallationIn vertical applications, both flanges of the
Earthwool Cavity Barrier should be fixed to the
inner leaf.
In horizontal applications, the top flange of
the polythene sleeve should be fixed to the
inner leaf.
All joints and intersections of Earthwool Cavity
Barriers should be closely butted.
Typical constructionEarthwool Cavity Barriers are engineered to
prevent the spread of smoke and fire through
walls, floors and cavities in timber frame, metal
frame and masonry buildings.
They are also suitable for reducing flanking
noise transmission in these concealed cavities.
The use of the correct size of Ear thwool Cavity
Barrier is essential. Earthwool Cavity Barriersare designed to compress to a tight fit in
cavities and in the event of fire breaking into
the cavity, Earthwool Cavity Barriers do not rely
on the polythene flanges to hold them in place,
but on their compression between the inner and
outer leaf.
It is, therefore, essential to specify the Earthwool
Cavity Barrier by reference to the actual
constructed cavity width.
ProductEarthwool Cavity Barrieris manufactured from
a continuous length of non-combustible glass
mineral wool which is compressed within a
resilient polythene sleeve incorporating two
flanges designed for ease of fixing.
The polythene sleeve is colour coded to suit a
variety of cavity widths from 50mm to 100mm
and eliminates the need for weather protectionduring installation.
The barriers are 1200mm long and can be
used in both vertical and horizontal
applications, and are available in two standard
widths (100mm and 300mm). 100mm barriers
are used for normal fire stopping and noise
reduction applications. 300mm barriers are
used where higher performance levels are
specified and at party wall/external wall cavity
junctions.
Fp04
Earthwool Cavity Barrier stapled through top flange tosheathing to fully fill the cavity
Brick outer leaf
NEW BUILD
8/13/2019 6 1 Fire Protection
21/34
285
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Technical specificationTimber frame construction
Earthwool Cavity Barrier 100mm*/300mm*
wide, coloured yellow*/ blue*/white* to be
friction fitted in the positions shown on the
drawings. Earthwool Cavity Barrier to fully fill
the depth of the cavity.
Polythene flanges to be stapled to the
timber*/sheathing board* to hold the cavity
barrier in place.
All joints and intersections of Earthwool
Cavity Barriers should be closely butted
together.
Alternatively, consult the National
Building Specifications, Standard
version clause/clauses
P10/420
Knauf Insulation specification clauses can be
downloaded from knaufinsulation.co.uk/nbs
Masonry construction
Earthwool Cavity Barrier 100mm*/ 300mm*wide, coloured yellow*/ blue*/white* to be
friction fitted in the positions shown on
the drawings.
Earthwool Cavity Barrier to fully fill the depth
of the cavity.
All joints and intersections of Earthwool
Cavity Barriers should be closely butted
together.
Alternatively, consult the National
Building Specifications, Standard
version clause/clauses
P10/420
Knauf Insulation specification clauses can be
downloaded from knaufinsulation.co.uk/nbs
PerformanceFire performance
Earthwool Cavity Barriers are manufactured
from glass mineral wool which has a Euroclass
A1 rating when classified in accordance with
BS EN 13501-1.
Earthwool Cavity Barriers have been tested for
fire resistance in accordance with BS 476: Par t
8: 1972 and will provide 60 minutes stability,
integrity and insulation.
Acoustic performance
Building Regulations require the use of a cavity
closer to reduce flanking noise transmission
along party wall cavities and external wall
cavities in masonry and timber frame
constructions.
Earthwool Cavity Barriers meet the generic
description for cavity closers and will therefore
ensure compliance with Part E and Robust
Details in timber frame and masonry wall
constructions.
Table 2 - Colour coding
Cavity width (mm) Colour
50-65 yellow
66-80 blue
81-100 white
Typical junction with party wall
300mm wide EarthwoolCavity Barrier - stapled tosheathing board eitherside of party wall
Earthwool Timber FrameParty Wall Slab
Earthwool FrameTherm
8/13/2019 6 1 Fire Protection
22/34
86
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Fire protectionLarge cavity barrier
Rocksilk Smoke and Fire Barrier
Simple, clean and quick to install
Provides both fire and acousticperformance
Versatile, flexible and adaptablesystem
Rocksilk Smoke and Fire Barrier
Non-combustible with a Euroclass
A1 reaction to fire rating Zero Ozone Depletion Potential (ODP)
Zero Global Warming Potential (GWP)
For one hour fire resistance
Two layers of 50mm Rocksilk Smoke and Fire
Barrier, separated by a 50mm air space,
applied as a hanging curtain with wire meshto the outside, supported continuously from
above and both sides, using the fixings listed in
Table 3. At the base it is either lapped freely on
to the back of a suspended ceiling, or fixed to a
partition head.
Use foil faced Rocksilk Smoke and Fire Barrier
when the ceiling void is used as an air plenum.
Installation
See page 288 - 291 for installation details.
See Table 3 for specification of fixings and
supporting metalwork.
Typical constructionFor half an hour fire resistance
A single layer of 50mm Rocksilk Smoke and
Fire Barrier, applied as a hanging curtain,
supported continuously from above and bothsides, using the fixings listed in the Table 3.
At the base Rocksilk Smoke and Fire Barrieris
either lapped freely on to the back of a
suspended ceiling or fixed to a partition head.
Suitable for drops up to 7 metres.
ProductRocksilk Smoke and Fire Barrieris made from
rock mineral wool and formed into a flexible
mattress faced on one side with galvanised
wire mesh stitched in position.Rocksilk Smoke and Fire Barrier is also
available foil faced on one or both sides.
Rocksilk Smoke and Fire Barrier must be
installed in accordance with the specifications
detailed below and on the following pages. If
these specifications are not strictly followed the
installation cannot be deemed to offer any
specific period of fire protection.
Fixing components:
Angle: Mild steel - 50mm x 50mm x 2mm or
60mm x 40mm x 2mm
Strip: Mild steel - 40mm x 2mm
See Table 3 for suitable method of fixing angles
and strips to substrate.
Fp05
Rocksilk Smoke andFire Barrier fixed to 50mmtimber spacer
Metal angle fixed to soffit
Rocksilk Smoke and Fire Barrier
50mm airgap
REFURB
8/13/2019 6 1 Fire Protection
23/34
287
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Metal anglesfixed to soffit
Rocksilk Smokeand Fire Barrier
Rocksilk Smoke and Fire Barrierfixed to timber spacer
Technical specificationHalf hour cavity barrier
A single layer of 50mm Rocksilk Smoke and
Fire Barrier (*foil faced) to be installed in the
positions marked on the drawings, and fixed
in accordance with the manufacturers
recommendations. All joints either tightly
butted, overlapped, or with edges returned,
and stitched in a continuous spiral loop with
1mm diameter galvanised lacing wire.(* delete as appropriate)
One hour cavity barrier
Two layers of 50mm Rocksilk Smoke and
Fire Barrier (*foil faced), separated by a
50mm air space to be installed in the
positions marked on the drawings, and
fixed in accordance with the manufacturers
recommendations. All joints either tightly
butted, overlapped, or with edges returned,
and stitched in a continuous spiral loop with
1mm diameter galvanised lacing wire.(* delete as appropriate)
Alternatively, consult the National
Building Specifications, Standard
version clause/clauses
K10/545
Knauf Insulation specification clauses can be
downloaded from knaufinsulation.co.uk/nbs
PerformanceFire performance
Rocksilk Smoke and Fire Barrier is made from
rock mineral wool and is classified as non-
combustible to BS 476: Part 4: 1970. RocksilkSmoke and Fire Barrier has a Class 1 Surface
Spread of Flame to BS 476: Part 7: 1997 and
is Class 0 to the Building Regulations.
When subjected to full scale fire resistance tests
to BS 476: Part 22: 1987, a system comprising
one layer of 50mm Rocksilk Smoke and Fire
Barrier, fixed by using the components and
methods detailed on the following pages
achieved 19 minutes insulation, and retained its
integrity for 35 minutes, after which time the test
was discontinued. 50mm Rocksilk Smoke and
Fire Barrier thereby satisfies the criteria laid
down in the Building Regulations for cavitybarriers, by exceeding the minimum
requirement of 15 minutes insulation and 30
minutes integrity .
When subjected to full scale fire resistance tests
to BS 476: Part 22: 1987, a system comprising
a double layer of 50mm Rocksilk Smoke andFire Barrier, fixed by using the components and
methods detailed on the following pages,
achieved 61 minutes insulation, and retained its
integrity for 66 minutes, after which time the test
was discontinued.
A double layer of 50mm Rocksilk Smoke and
Fire Barrier thereby satisfies the criteria laid
down in the Building Regulations for one hour
cavity barriers.
These tests incorporated vertical and horizontal
joints between barriers. Fire resistance is
effective from either side of the barrier. When
tested, the wire side was exposed to the furnaceas this is the side most vulnerable to fire.
8/13/2019 6 1 Fire Protection
24/34
88
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Fire protectionInstallation of half hour cavity barrier
80mm
minimum
1. Metal angle fixed to purlin 2. Fixed to purlin 3. Fixed to rib of coffered slab
4. F ixed across cof fered cei ling 5. Perimeter f ixing wi th s teel s tr ip 6. Junction with ceiling
At the ceiling junction, Rocksilk Smoke and Fire
Barrier is cut and draped on and between the
joists, and secured by fixing to steel angle,
which is itself fixed to the joists (Figure 6). For
suspended ceilings, see Figure 11.At partitions or wall heads, if a secure fixing is
available, as at soffits, Rocksilk Smoke and Fire
Barrier should be clamped with a steel strip
Two layers of 50mm Rocksilk Smoke and Fire
Barrier with a 50mm air space between them
are needed for one hour fire resistance. In
general two separate layers should be installed
back to back, each in a manner identical to that
shown for half hour fire resistance. The joints in
the two layers should be staggered and Rocksilk
Smoke and Fire Barrier returned outward at the
top and bottom. The wire reinforced sides
should be placed outward, see Figure 7.
Concrete decks
Rocksilk Smoke and Fire Barrier is clamped
between the deck and steel angle secured by
expanding bolts. If the deck is coffered it should
usually be possible to locate the cavity barrier
along one of the ribs (Figure 3). If fitted acrossthe coffering it should be clamped by steel strip,
to the steel angle which is secured to the ribs.
If the depth of coffering is less than 100mm,
Rocksilk Smoke and Fire Barrier should be
returned at the top by 300mm, to allow for
cutting at the ribs and pushed securely into the
coffering (Figure 4). If the depth of coffering is
greater than 100mm, Rocksilk Smoke and Fire
Barrier should be fixed around the coffering
using steel angle, as described above.
Alternatively, proprietary profile fillers may be
used.
The perimeter of the barrier should be securedwith steel strip (Figure 5).
InstallationThe following information and illustrations
outline typical details for the installation of large
cavity barriers. In case of uncertainty, refer to
Knauf Insulation.
Metal deck with overdeck insulation
If Rocksilk Smoke and Fire Barrier runs with the
slope of the roof, a supporting steel angle
should be fixed between purlins and the smoke
and fire barrier clamped to this with steel strip
(Figure 1). The insulation should project 80mm
beyond the strip to ensure a good seal.
If fitted across the sheeting profile, Rocksilk
Smoke and Fire Barrier should be bolted to the
purlins (Figure 2). It is returned at the top, to a
length equivalent to 3 times the profile depth, to
allow for cutting at troughs and pushing
securely into profiles. Alternatively, proprietary
profile fillers may be used.
8/13/2019 6 1 Fire Protection
25/34
289
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
7. Fixed to concrete slab 8. Fixing to wall head
10. Fixing at perimeter9. Fixing to timber spacer
Partitions and wall heads
If possible, Rocksilk Smoke and Fire Barrier
should be secured with steel strip to the par tition
or wall head so as to maintain the 50mm air
space (Figure 8). If this is not possible, it should
be draped with a return of at least 150mm, or
fixed to a timber spacer which is fixed to the
partition or wall head (Figures 6 and 9).
Perimeter fixing
Rocksilk Smoke and Fire Barrier should be
secured with steel strip to the sides of the
perimeter wall, so as to maintain the 50mm air
space (Figure 10).
Fire protectionInstallation of one hour cavity barrier
Steel strip fixings: To masonry and concrete Buildex Tapcon 4H masonry anchorsTo timber Buildex HT range of fixingsTo steel angle Steel bolts
Minimum return of Rocksilk Smoke and Fire Barrier - When clamped to flat surface (vertical or horizontal)
80mm. When loose laid over horizontal surface - 150mm.
Fixing system specifications
Table 3 - Specification of angles and strips
Angle: Mild steel - 50mm x 50mm x 2mm or 60mm x 40mm x 2mm
Strip: Mild steel - 40mm x 2mm
Angle fixings to concrete decks and steel sections: angles 50 x 50 x 2mm
Fire resistance Maximum spacing of fixings (m) for the following drop heights (m)period (mins) 3 3.5 4 4.5 5 5.5 6 6.5 7
30 2 2 2 2 2 2 2 2 2
60 2 2 1.75 1.5 1.5 1 1 0.75 0.75
Key: M8bolts
M6bolts
Angle fixings to timber beams and trusses: angles 50 x 50 x 2mm
Fire resistance Maximum spacing of fixings (m) for the following drop heights (m)
period (mins) 3 3.5 4 4.5 5 5.5 6 6.5 7
30 2 2 2 2 2 2 2 2 2
60 2 2 1.75 1.5 1.5 1 1 0 .75 0.75
Key: Buildex HT screws, minimum 25mm thread penetration into timber
Buildex HT screws, minimum 40mm thread penetration into timber
8/13/2019 6 1 Fire Protection
26/34
90
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Fire protectionJointing Rocksilk Smoke and Fire barrier
Suspended ceilings
With suspended ceilings where positive fixing
to wall heads or partition heads is not possible,
the weight of Rocksilk Smoke and Fire Barrier
and the stiffness of wire facing are such that it
will form an effective seal if it laps the
horizontal surface by a minimum of 150mm.
Lapped joints are only permissible where the
suspended ceiling has the same fire resistance
as the cavity barrier. Rocksilk Smoke and Fire
Barrier must be slit and fitted around any
crossing tees to eliminate gaps and ensure that
excessive loads are not transferred to the ceiling
(Figure 11).
Jointing
This section describes the approved methods for
joining adjacent pieces of Rocksilk Smoke and
Fire Barrier. The methods are applicable to both
half and one hour large cavity barriers.
12. Ver tical butt joint 13. Ver tical returned joint 14. Ver tical lap joint
500mmminimumoverlap
15. Perpendicular joint 16. Horizontal joint at a drop
Vertical and horizontal joints
Three methods of securing the joints between
adjacent pieces of Rocksilk Smoke and Fire
Barrier are approved.
Joints are tightly butted together and stitched in
a continuous spiral loop with 1mm diameter
galvanised lacing wire. The stitching should
pass through the reinforcement mesh and the
wool on each side of the butt joint at centres not
exceeding 100mm (Figure 12).
Alternatively the Rocksilk Smoke and Fire
Barrier edges are returned at least 80mm and
wired together (Figure 13), or they may be
lapped at least 100mm and wired together
(Figure 14).
Perpendicular jointsThe junction between two barriers should be
securely wired together (Figure 15) with a
return of at least 80mm.
Drops
All barriers can be used for drop heights up to
5m without additional support. For drops
between 5m and 7m it is necessary to introduce
additional supporting members in order to
support the weight of the fire barriers (Figure
16).
Services
Services which are permitted by Building
Regulations to penetrate barriers, should
be provided with collars of Rocksilk Smoke and
Fire Barrier at least 300mm long, sewn to the
main barrier and then strapped or wired so as
to avoid any possibility of gaps (Figure 17).
A half hour barrier requires a collar on
one side of the barrier. A one hour barrier
requires one collar on both sides of the barrier
system.
11. Junction with suspended ceiling
8/13/2019 6 1 Fire Protection
27/34
291
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Penetrating steelwork
This should be provided with a collar of Rocksilk
Smoke and Fire Barrier at least 300mm long(Figure 18). The collar is fixed to the concrete or
metal deck by clamping against these surfaces
behind steel angle. The voids in the steelwork
are filled with Rocksilk Smoke and Fire Barrier
(figure 18). A half hour barrier requires a collar
on one side of the barrier. A one hour barrier
requires one collar on both of the layers of the
barrier system.
Access
Where permanent access is needed through the
barrier, a fire door and frame, rated to the
appropriate fire resistance, must be used.
Rocksilk Smoke and Fire Barrier should be fixed
securely to the frame.
300mm
minimum
17. Penetrating pipe
19. Temporary framework to ease handling
18. Penetrating steelwork
Handling
Depending on the size of the barrier and the
working space available, it is sometimes difficultto hold the material in place while top fixings
are being secured. It will be found helpful to
make a temporary prop from, e.g. slotted
angle. This may comprise a crosspiece of length
appropriate to the width of the Rocksilk Smoke
and Fire Barrier, with studs on the top which will
hook into the wire mesh of the Rocksilk Smoke
and Fire Barrier. This may be swivelled on the
top of a handle, and secured horizontally or to
the angle of the roof by an adjustable brace. It
is used to hold the Rocksilk Smoke and Fire
Barrier up, 100mm or so behind the fixing
location, while fixing is being carried out.
When fixing to a sloping deck, the top of theRocksilk Smoke and Fire Barrier should be
trimmed to the correct angle to ensure that joints
are truly vertical (Figure 19).
Following trades
The integrity of barriers must be restored if
disturbed by following trades, either duringthe building process or after completion.
This instruction should be incorporated into
the building handbook.
Fire protectionPenetrating pipes and ducts
8/13/2019 6 1 Fire Protection
28/34
92
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Internal floorRefurbishment of timber separating/internal floor
Earthwool Flexible Slab
Minimum 18mm ChipboardEarthwool Flexible Slab
Support meshstapled to joists
Existing ceiling
Existing ceiling can beretained, avoiding disruptionto rooms below
Provides thermal and acousticinsulation as well as fireresistance
Meets the requirements ofApproved Document E for soundresistance of internal floors
Earthwool Flexible Slab
Non-combustible with a Euroclass A1reaction to fire rating
A+ Generic BRE Green Guide rating
Zero Ozone Depletion Potential (ODP)
Zero Global Warming Potential (GWP)
Installation
After removal of the floor deck, line the voids in
the floor with 25mm wire mesh, to form a
support tray for the insulation. Staple the wire
mesh to the sides of the joists, at least 40mm up
from ceiling level.
Cut 100mm Earthwool Flexible Slabs to size
and lay onto the wire mesh support, so that
there are no gaps between the insulation andthe joists. Butt joint the insulation slabs so there
are no gaps between them.
Fix a chipboard floor deck, at least 18mm thick,
over the entire floor area.
Typical construction
The use of Earthwool Flexible Slab in a
suspended timber floor achieves one hour fire
resistance, whilst allowing the existing ceiling to
be retained.
To achieve one hours fire resistance:
The floor deck should be at least 18mm thick
tongued and grooved chipboard or timber
boarding The joists must be at least 200mm deep and
37mm wide
The wire mesh should be stapled to the sides
of the joists at least 40mm above the ceiling
level
Any ceiling can be used
ProductsEarthwool Flexible Slabis a multi-purpose rock
mineral wool slab designed to be friction fitted
in a wide range of acoustic, thermal and fire
resistant applications.
Introduction
Where the loft space of a two storey house is
converted into habitable accommodation, the
floor to the new rooms must have 30 minutesfire resistance over any part of the escape route
directly below. This is often the case when, for
example, the floor of the new room extends
over a landing in the stairway enclosure below.
The solution on this page provides the required
period of fire protection without having to
upgrade the existing ceiling.
Fp06REFURB
8/13/2019 6 1 Fire Protection
29/34
293
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Typical specificationLay 100mm Earthwool Flexible Slab on
25mm chicken wire mesh, stapled to sides of
joists at least 40mm up from ceiling level and
at 600mm centres. The joists should be at
least 200 x 37mm and spaced at not more
than 600mm centres. The flooring board to
be at least 18mm thick.
Alternatively, consult the National
Building Specifications, Standardversion clause/clauses
P10/250
Knauf Insulation specification clauses can be
downloaded from knaufinsulation.co.uk/nbs
Performance
Fire performance
Earthwool Flexible Slab is classified as
Euroclass A1 to BS EN 13501-1 and non-
combustible to BS 476: Part 4: 1970
(1984), Class 1 Surface Spread of Flame to BS
476: Part 7: 1997 and Class 0 to the Building
Regulations.
Acoustic
The acoustic performance of an internal floor
containing 100mm of Earthwool Flexible Slab
(and 12.50mm standard plasterboard ceiling)
will be at least 40dB and therefore, meet the
requirements of Approved Document E of the
Building Regulations.
Existing wall
Minimum 18mm chipboard
EarthwoolFlexible Slab
Wire mesh stapled to joists to providesupport for Earthwool Flexible Slab
Existing ceiling
Earthwool Flexible Slab cut and frictionfitted between last joist and wall
Typical wall floor junction
8/13/2019 6 1 Fire Protection
30/34
94
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Lightweight, mineral wool has
approximately one half to one third of
the weight of traditional silicate and
vermiculite boards
Fast and simple fixing system makes the
slabs quick and easy to install
Provides excellent acoustic and thermal
performance insulation
Rocksilk Pyroduct Slab
Non-combustible with a Euroclass A1
reaction to fire rating
Zero Ozone Depletion Potential (ODP)
Zero Global Warming Potential (GWP)
ProductRocksilk PyroDuct Slabis a 160 kg/m3density
rock mineral wool slab. The slabs are faced
with a bright Class O reinforced aluminium
foil, making it suitable for applications above
clean rooms, within air plenums or for aesthetic
purposes.
Typical construction
The exposed surfaces of steel ductwork are fullyenclosed in Rocksilk PyroDuct Slab using the
fixing system shown on the following pages.
Rocksilk PyroDuct Slab can be used to provide
up to 2 hours fire protection to steel ductwork.
InstallationRocksilk PyroDuct Slab is applied in a single
thickness, removing the need for multi layer
applications. This provides assurance of a
uniform thickness and therefore the integrity of
the system and allows for easy verification of
correct installation on site.
Individual slabs are 1200mm long and 600mm
wide making them easy to carry around site.Their lightweight nature also makes them easy
to use.The fixing system of welded pins and
square edge butt jointsgives a fast and simple
system which requires no special vee cuts,
drilling or sub-frames and also makes the slabs
fast and easy to install.
PerformanceFire
Rocksilk PyroDuct Slab is classified as
non-combustible to BS 476: Part 4: 1970
(1984), Class 1 surface spread of flame to BS
476: Part 7:1997 and Class O to the Building
Regulations.
Rocksilk PyroDuct Slab has been tested in
accordance with BS 476: 24:1987 and canprovide up to two hours fire resistance for steel
ductwork exposed to fire either inside or outside
of the duct.
Moisture resistance
Rocksilk PyroDuct Slab is non-wicking when
tested to BS 2972: 1989: Section 12. When
exposed to 90% relative humidity and 20C,
Rocksilk PyroDuct Slab absorbs less than
0.004% of moisture.
Fire protectionSteel Duct Encasement
Rocksilk Pyroduct SlabNEW BUILD REFURB
Fp07 Blockwork compartmentwall
RS33 Slab as packing
Steel angle rivetted at 150mm centres
Rocksilk Pyroduct fixed to duct
Rocksilk Pyroduct glued to wall and insulation
8/13/2019 6 1 Fire Protection
31/34
295
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Typical specificationRocksilk PyroDuct Slab...........mm thick to be
used to provide up to 2 hours fire protection
to steel ductwork as detailed in this schedule
(specifier to state which ducts require fire
protection).
It is to be installed using the fixing system as
detailed, and at a thickness with due regard
to the duct size, orientation and period of fire
protection required.
Table 4 - Required thickness of Rocksilk PyroDuct Slab
Thickness of insulation (mm)
Period of fireresistance (hours)
Vertical ducts Horizontal ducts Kitchen extractducts
0.5 - - 45
1.0 45 45 90
2.0 90 90 -
Table 5 -Weight of slabs
Thickness(mm)
Weight(kg/m2)
45 7.20
90 14.40
WeightTable 5 shows the weight per square metre of
Rocksilk PyroDuct Slab.
Fire protection
Any vertical or horizontal, rectangular or
square steel ductwork associated with
ventilation and/or air conditioning systems,
including ducted supply and extract systems
(whether through ducts or plenums),
mechanically assisted systems and those
relying on natural convection can be
protected with Rocksilk PyroDuct Slabs to
provide the required degree of fire protection.
Achieving the required fireperformance
The required thickness of Rocksilk PyroDuct
Slab depends upon the orientation of the duct
and the period of fire resistance required.
Table 4 displays the thicknesses required for
vertical and horizontal ducts and also for
kitchen extract ducts for the commonest
periods of fire resistance.
Foil facing omitted for clarity
8/13/2019 6 1 Fire Protection
32/34
96
Fire Protection6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
Fire protectionSteel Duct Encasement
350m
m
X
Y
Greater
than
1000mm
350m
m
50mm
500mm
max
350m
m50mm
500mm
max
1. Weld 3mm diameter steel pins at 350mm longitudinal centres
along the centre line of the vertical sides of the ductwork.
2. Where the dimension of the vertical sides exceed 1000mm,
the steel pins should be in rows starting 50mm in from the edge
and spaced apart at a maximum of 500mm centres.
3. Weld 3mm diameter steel pins at 350mm longitudinal centres
along the horizontal surfaces of the ductwork in rows starting
50mm in from the longitudinal edge and spaced apart at a
maximum of 500mm centres.
4. Cut Rocksilk PyroDuct Slab to size as follows:
horizontal surfaces to dimension X,
vertical surfaces to dimension Y + 2t,
where t = thickness of insulation.
5. Attach the insulation by impaling over the welded pins and
securing with 38mm spring steel washers.
6. Glue all board to board joints using a thixotropic silicate
based adhesive.7. Trim off pin lengths to about 30mm excess and bend this
excess to form a right angle with the insulation.
8. Although not essential, it is good practice to offset the joints
for each surface.
6
7
8
8/13/2019 6 1 Fire Protection
33/34
297
Fire Protection 6.1
Technical Advice and Support Centre 01744 766666 www.knaufinsulation.co.uk
6.
1
Fire protectionSteel Duct Encasement
Vertical ducts
The installation detail on the previous pages for horizontal ducts is
also relevant for vertical ductwork, though the horizontal and vertical
surfaces referred to for horizontal ductwork will be the longest and
shortest surfaces respectively in vertical ductwork.
Ductwork passing through compartment
walls or floors
In accordance with The Building Regulations, when ductwork passesthrough any element of construction which has a designated period
of fire resistance, the integrity of that compartment should be
maintained. In these situations, the ductwork in the immediate vicinity
of the penetration should be stiffened as follows:
a) When the flange is within 100mm of the penetration then a50 x 50 x 3mm steel angle should be rivetted to the top edge
of the duct using a single row of rivets with washers starting50mm from the edge and at 150mm centres.
Earthwool Building Slab RS33 should be used to pack any gapbetween the main insulation and the blockwork.
120 x 90mm sections of Rocksilk Pyroduct Slab is glued to thewall and main Pyroduct insulation.
b) When the flange is greater than 100mm from the penetration,two angles should be used, fixed as described in a) above, and45mm Rocksilk Pyroduct Slab installed perpendicular to the ductat the penetration.
8/13/2019 6 1 Fire Protection
34/34