33
5 th November 2010 R2E Mitigation Project iew of UJ56 relocation opt . Perrot, EN/MEF & R2E Study Group Main contributions from EN/CV, EN/EL, EN/MEF, GS/ASE, GS/SEM & equipments owners

5 th November 2010

  • Upload
    patch

  • View
    63

  • Download
    0

Embed Size (px)

DESCRIPTION

R2E Mitigation Project Review of UJ56 relocation options. Main contributions from EN/CV, EN/EL, EN/MEF, GS/ASE, GS/SEM & equipments owners. A. L. Perrot, EN/MEF & R2E Study Group. 5 th November 2010. Mitigation options studied . Option A : full relocation in the by-pass - PowerPoint PPT Presentation

Citation preview

Page 1: 5 th  November 2010

5th November 2010

R2E Mitigation Project

Review of UJ56 relocation options

A. L. Perrot, EN/MEF & R2E Study Group

Main contributions from EN/CV, EN/EL, EN/MEF, GS/ASE, GS/SEM & equipments owners

Page 2: 5 th  November 2010

Option A: full relocation in the by-pass (A. L. Perrot)

Option B: partial relocation in the by-pass & the UJ561 (UJ561 being the CMS exit path) (A. L. Perrot)

Option C: partial relocation in the by-pass & the UJ561 finding another CMS exit path (M. Gastal)

Mitigation options studied

Page 3: 5 th  November 2010

UJ56 1rst floorEquipment to be moved : power converters + 17 racks

Power converters

Page 4: 5 th  November 2010

UJ56 ground floor - ‘safe room’Equipment to be moved : 5 racks + internal part of SYAFD01 (fire detection) rack

EYP01 (anti-panic lightning), EYC01/02/03 (electric network control), EYU01 (AUG)

Page 5: 5 th  November 2010

Option A: full relocation in the by-pass

N.B. request of the equipments owners: 6 racks in the USC55/machine area and 1 rack in the USC55/CMS area

- Technically feasible

- Constraints/consequences: • mini safe – room construction in the by-pass (likely) • interference with transport volume: Power Converter calibrations racks• remaining free space along the USC55 wall before the PAD =20m

Page 6: 5 th  November 2010

RQX.R5RTQX2.R5

RYCA01-02

RYMCB01-05

RYLB01RYLC01

ERD1/56

DYPG01 & 02

CYCIP01

GYPOS01 à 03

CYNET01 – RYSC01

EYU01 & 02 – EYP01 & 02EYC01 à 04 (h=1.8m)

EOD1/56 – EOD3/56

EBS1/56 – UPS machine

QYC01 à 04 (h=2.00m)

CYTIM01 – CYFRE01 (h=2.00m)

RYSA01 – 02 (h=2.00m)

mini- safe room

UJ561 by-pass

Oct. 2010- Ph. Orlandi, JC Guillaume EN/ELJP Corso, Y. Muttoni, EN/MEF

Page 7: 5 th  November 2010

TYCFL02

DYXF01

YYACS01RYSA01 - 02

CYCIB01

6 racks moved from UJ56 1rst floor to USC55 /machine area

SYAFD01 eqpt moved from UJ56 ‘safe room’ to USC55/ CMS racks room (S2A19)

USC55 machine area

Page 8: 5 th  November 2010

Option B partial relocation in the by-pass & the UJ561 (UJ561 being the CMS exit path)

N.B. request of the equipments owners: 6 racks in the USC55/machine area and 1 rack in the USC55/CMS area

- Option B1: install 1 raw of racks in the UJ561= technically feasible=> remaining free thickness for the CMS exit path is 1.2 m

- Option B2: install the mini safe-room in the UJ561 = technically feasible=> remaining free thickness for the CMS exit path is 1.1 m thick

Safety requirements concerning exit path (CERN/TIS-GS/2002-03) depends on the number of persons to evacuate and the number of exits foreseen => 0.9m thick for less than 100 persons

Page 9: 5 th  November 2010

RQX.R5

RTQX2.R5

RYCA01-02

RYMCB01-05RYLB01RYLC01ERD1/56

DYPG01 & 02

CYCIP01GYPOS01 à 03CYNET01 – RYSC01

EYU01 & 02 – EYP01 & 02EYC01 à 04 (h=1.8m)

QYC01 à 04CYTIM01 – CYFRE01RYSA01 – 02

Option B: partial relocation in the by-pass & the UJ561 CMS exit path

Oct. 2010- Ph. Orlandi, JC Guillaume EN/ELJP Corso, Y. Muttoni, EN/MEF

Page 10: 5 th  November 2010

Option B: partial relocation in the by-pass & the UJ561 CMS exit path

Oct. 2010- Ph. Orlandi, JC Guillaume EN/ELJP Corso, Y. Muttoni, EN/MEF

Page 11: 5 th  November 2010

TYCFL02

DYXF01

YYACS01RYSA01 - 02

CYCIB01

6 racks moved from UJ56 1rst floor to USC55 /machine area

SYAFD01 eqpt moved from UJ56 ‘safe room’ to USC55/ CMS racks room (S2A19)

USC55 machine area

Page 12: 5 th  November 2010

Civil engineering – Ducts to be drilled

Page 13: 5 th  November 2010

5 new ductsØ mm – length 2m

‘mur tympan’ : 5 new ducts Ø 350mm – length 2m

Civil engineering – Ducts to be drilled

Page 14: 5 th  November 2010

Main work to be performed for both Options A & B

Civil engineering activities: - drill 4 ducts between UJ56 and by-pass for PC cables,- drill ducts in the wall between by-pass and UJ561 CMS exit path (cables & ventilation)- drill 5 ducts in the wall UJ56- machine- reinforce the by-pass vault structure (under study)

CV activities: UTAs and cooling system installation

EL activities: cables trays displacement/installation, cables installation

Access : sector door to be moved from by-pass to the UL56 (displt of 11 m)

Mini-‘safe room’ construction in the by-pass/UJ561 (under study),

BRAN pipes to be rerouted

Page 15: 5 th  November 2010

Draft time estimate – main activities

- EL activities: - 15 months (1 shift)- 11.5 months (2 shifts)

- CE activities: 4 ducts between UJ56/ by-pass - 3 months 5 between UJ56- machine - 1 month 4 ducts in the UJ561/by-pass wall: - 3 weeks

- CV activities: - 2.5 months (1 shift)

- AFD activities: - 5 weeks (detection interruption 5 days) ( 1 shift)

- Safe room : - 3 weeks ( 1 shift)

- Displacement sector door: GS/ASE: - 2 days mechanical work :- 1 week

The work load equivalent for options A/B => identical time estimate

for the options A/B/C

compatibility between EL, CE, and CV activities => Planning

negotiation needed with contractor

Page 16: 5 th  November 2010

Draft cost estimate – main activities- EL activities: opt A: 2.405 MCHF /opt B: 2.355 MCHF (1 shift)

opt A: 2.555 MCHF /opt B: 2.502 MCHF (2 shifts: 10% manpower)

- CE activities: 4 ducts between UJ56/ by-pass: 200 KCHF 5 between UJ56- machine: 25 KCHF 4 ducts in the UJ561/by-pass wall: 40 KCHF - CV activities: opt. A: 420 KCHF/ opt. B: 445 KCHF (1 shift)

- AFD activities: 96 KCHF (1 shift)

- Safe room : 57 KCHF

- Displacement sector door: GS/ASE: 30 KCHF mechanical work : t.b. estimated

EL 1 shift: opt. A: 3.233 MCHF / opt. B: 3.2 MCHFEL 2 shifts: opt. A: 3.383 MCHF / opt. B: 3.355 MCHF

Provisional budget~ 3.4 MCHF

for the options A/B/C

Page 17: 5 th  November 2010

Open issues

integration study (details) precise schedule (co-activities) and impact on other LHC activities negotiate the 2 shifts scenario with EL contractor final budget

To be done after the decision on the baseline for the mitigation option

Page 18: 5 th  November 2010

- Integration studies: - 1 month (completion and compatibility CV/EL/LHC drawings, documentation preparation, approval loop)

- Planning : - 1 month (sequence, co-activities)

- EL activities: - DC/CTR: 1 year (Market Survey for special cables?, supply)- power distrib. : 8 months (study, supply)

- CE activities: - 3 months (offers, contractor, work set-up)

- CV activities: - 6 months (Market Survey for special UTAs?, supply)

- AFD activities: - 3 months (supply, work set-up)

Time to get ready for installationonce baseline mitigation is chosen

1 year and 1 month process

Installation in Jan. 2012decision on the baseline end of Nov. 2011

Page 19: 5 th  November 2010

Summary

Option A: full relocation in the by-pass = technically feasible

Option B: partial relocation in the by-pass & the UJ561 (UJ561 being the CMS exit path) = technically feasible (CMS exit path 1.2m-1.1 m thick)

It looks reasonable to assume that the work could not be performed in less than 15 months for a budget of about 3.4 MCHF

Decision on the mitigation option is needed this month to be ready in January 2012.

Page 20: 5 th  November 2010

Many thanks to all the involved teams for their work during this last month

Especially to GS/SEM: John Osborne and Antoine KosmickiEN/EL: Jean-Claude Guillaume, Philippe Orlandi , Nuno dos SantosEN/CV: Piero Valente EN/MEF-INT: Yvon Muttoni, Jean Pierre Corso

Page 21: 5 th  November 2010

Back –up slides

Page 22: 5 th  November 2010

Interferences with loading volume:PC: 52 mm PC calibration racks: 338mm UTA: 40 mm

PC calibration racks

PCs

Page 23: 5 th  November 2010

Interferences with loading volume : UTA: 40 mm

On UJ561 wall side: dedicated racks with height of 1.8 m in the safe room and 2m elsewhere to stay below the cable trays of ‘forward detectors’(2.4m high).

Safe room 1rst door at 21 mm from loading volume -> ok

Page 24: 5 th  November 2010

20 m free between the last UTA control box and the PAD door

Page 25: 5 th  November 2010

Safe room:9 fire resisting doors (l. 1 m, h. 2.1 m) Structure in ‘siporex’ 15 cm thick (external dims. L. 16m, h. 2.4 m, d. 0.85 m)

Page 26: 5 th  November 2010

- Note by TIS/GS in October 2001 concerning the minimum requirements in terms of access / evacuation of an experimental area

- 79th SAFETY CO-ORDINATION MEETING FOR LHC EXPERIMENTS (19/10/2001) https://edms.cern.ch/document/327707/1

Safety requirement for evacuation exit path(documentation)

Page 27: 5 th  November 2010

Source: 79th safety coordination meeting for LHC experiments (19/10/2001)

Page 28: 5 th  November 2010

Source: 79th safety coordination meeting for LHC experiments (19/10/2001)

Page 29: 5 th  November 2010

Source: 79th safety coordination meeting for LHC experiments (19/10/2001)

Page 30: 5 th  November 2010

Source: 79th safety coordination meeting for LHC experiments (19/10/2001)

Page 31: 5 th  November 2010

Source: 79th safety coordination meeting for LHC experiments (19/10/2001)

Page 32: 5 th  November 2010

Cost /schedule estimate - breakdownSafe room (options A & B):- devis Ingo: 9 fire resisting doors (material + manpower)= 36 KCHF / max 9 days- external contractor: the full safe room (structure + doors)

- material: 27 KCHF- manpower: 30 KCHF- schedule: 2-3 weeks- delay for material delivery: 10 weeks

Civil engineering (options A & B)-Drilling 4 ducts between UJ56 and by-pass (diam. 350mm, l. 16.7m): ???- drilling apertures in the UJ561/by-pass wall (3 apertures h25cm, t. 60 cm or 1 aperture h.75cm, t. 60 cm): 30 KCHF /1-2 weeks

-EL activities:-Control and DC cables: 1.5 MCHF (option A); 1.45 MCHF (option B); shift work +10%-Puissance: 1.2 MCHF (options A & B), shift work +10%-Total: 2.7 MCHF (option A); 2.65 MCHF (option B) ; shift work +10% -Planning (see table): one shift: 17.5 months / 2 shifts: 12 months

-CV activities-Budget (material + manpower)= 380-420 KCHF-planning (see table): cooling: demi water: 3 weeks -3 persons/1 shift; iced water: idem

- ventil: 3 weeks -3 persons/1 shift; elec: 3 weeks -3 persons/1 shift- control: 1 week- 2 persons/1 shift

Page 33: 5 th  November 2010

EN/EL planning tentative 9th October 2010

J. –C. GuillaumeGiven for the 1 shift option: total= 15 monthsGain 2 months vs previous version (activities in the safe room in // control cable inst. In UL55

compatibility between CE, CV and EL activities ?=> planning