View
219
Download
0
Tags:
Embed Size (px)
Citation preview
5th February 2010 FP7 Prep WP9000Progress Meeting
1
UpdateUpdateTim Morris
Durham University
FP7 PrepWP 9340
5th February 2010 FP7 Prep WP9000Progress Meeting
2
Contents
• Brief CANARY overview– Relationship to EAGLE– CANARY Consortium
• CANARY Status• FP7 Prep Specifics
– Systems Engineering / Key Component Selection
• Status
– Deliverables and Schedule
5th February 2010 FP7 Prep WP9000Progress Meeting
3
CANARY overview
• EAGLE – Phase A instrument concept study for E-ELT– Multi-IFU with LGS/NGS MOAO
• CANARY complements SESAME– Lab demonstrator
• CANARY consortium: LESIA, Durham, ONERA, UKATC, LAM• Location: 4.2m WHT La Palma (Nasmyth platform enclosure)
is the on-sky demonstrator for
Phase On-sky Dates Configuration
A July 2010FDR Dec 08
3 NGS tomo., low-order 52-act DM, truth sensor, near-IR camera, Cn
2 mon.
B Q2 - Q3 2011
FDR Dec 09
Adds 4 Rayleigh LGS + WFS
C Q2 - Q3 2012 Adds High-order 1024-act DM
5th February 2010 FP7 Prep WP9000Progress Meeting
4
CANARY Overview• CANARY is funded by a
combination of French and UK funding, along with FP7 Prep and FP7 OPTICON JRA-1
• Additional funding from:– STFC– INSU– Observatoire de Paris– Durham University
• UK STFC funding for Phase C approved but frozen– Decision expected soon!
• FP7 Prep funding covers systems engineering support and key component selection
Layout of upgraded Nasymth platform at the WHT
5th February 2010 FP7 Prep WP9000Progress Meeting
5
CANARY Status
• Phase A on-sky dates awarded from 21st to 28th July (6 nights)– 2 months later than originally planned
• Principal optomechanical subsystems have been assembled and are undergoing testing
• CANARY instrument control system is being integrated with the hardware
• Full system integration in Durham begins next week
5th February 2010 FP7 Prep WP9000Progress Meeting
6
Key Components:Telescope Simulator
• Passed initial acceptance tests in December 2009
• Minor modifications required to phase screen motors and fibre source clamps
• Modifications completed and system being delivered to Durham next week
• Field lens/Fold mirror assembly also completed– Required for AIT tests with
the Telescope Simulator
Telescope simulator integration (UKATC)
5th February 2010 FP7 Prep WP9000Progress Meeting
7
Key Components:AO Path
• AO path has been aligned– Dummy DM flat mirror used– Avoids DM flattening routine– Allows alignment jig design
• WFE ~55nm RMS– Error budget allowance of
104nm RMS • Throughput
– 60% @ 633nm with DM flat– Expected 69% in V-band with
DM– ADONIS DM to be measured
AO Path aligned with dummy flat DM (Durham)
Flat mirror in place of DM
5th February 2010 FP7 Prep WP9000Progress Meeting
8
Key Components:Low-order DM
• ADONIS DM re-polished– Less than 50nm RMS error
after flattening• 4% open-loop error after
calibration• Tested using SESAME
– Closed-loop SR = 0.39– Open-loop SR = 0.35
• Currently integrated in Durham– DMC testing– Truth Sensor interfaces– NCPA removal
Closed-loop CANARY DM and Truth Sensor testbench (Durham)
5th February 2010 FP7 Prep WP9000Progress Meeting
9
Key Components:NGS WFSs
• 4 x Andor Ixon (E2V 128x128 EMCCD) selected
– 3 x open-loop tomography– 1 x closed-loop
• All cameras have been interfaced to the RTC
– 2 cameras in Paris– 2 cameras in Durham
• Cameras have been integrated with:
– SESAME for open-loop tomography tests (LESIA)
– DM testbench for closed-loop control and interface tests (Durham)
• NGS Pickoff optics aligned (LESIA)– Installed on 2 of 3 cameras
• Truth sensor being integrated with main AO path (Durham)
NGS pickoff and WFS optics before alignment (LESIA)
5th February 2010 FP7 Prep WP9000Progress Meeting
10
Key Components:NGS TAS
• Target Acquisition System assembled
• WFSs to be mounted after SESAME tests completed
• Motion control interface completed– Probe collision detection
software requires development
• Shipping to Durham for AIT mid-March
NGS TAS during assembly (LESIA)
5th February 2010 FP7 Prep WP9000Progress Meeting
11
Key components:WHT Nasmyth Upgrade
• Upgraded GHRIL platform work progressing
• New bench and kinematic mounts installed
• Repositioned walls installed and derotator flange sealed
• Air conditioning units to be installed early March
• Derotator assembly starts after Telescope Simulator delivery (UKATC)
• Provisional derotator installation date of March– Backup date in May
CANARY bench installation within GHRIL (ING)
5th February 2010 FP7 Prep WP9000Progress Meeting
12
AIT Progress: Optomechanics
WHTNasmyth
Telescope Simulator
NGS Pickoffs
3 x NGS WFS
NGS FSM
Low-order DM
Science Verification
Truth Sensor
Figure Sensor
GHRIL Derotator
NGS TAS
AOPath
Focal Plane Calibration
Field Lens Fold Mirror
Science Relay
Acquisition Camera
External Turbulence
Profiler
Green bars show subsystem progress towards final CANARY configuration
~80% complete
5th February 2010 FP7 Prep WP9000Progress Meeting
21
RTCS Progress
RECONSTRUCTORSTATUS:Shaktiware has delivered two reconstructor boxesUndergoing final acceptance
5th February 2010 FP7 Prep WP9000Progress Meeting
22
RTCS Progress
WAVEFRONT PROCESSING
UNITS
STATUS:WPUs interfaced to camerasWPUs interfaced to RTCSBeing used on testbenches
5th February 2010 FP7 Prep WP9000Progress Meeting
23
RTCS Progress
DEFORMABLE MIRRORCONTROLLER
STATUS:DMC interfaced to DM and RTCSSoftware interfaces being finalised
5th February 2010 FP7 Prep WP9000Progress Meeting
24
RTCS ProgressCLUSTER AND
CONTROLWORKSTATION(S)
STATUS:Low-level interfaces defined, tested and workingAO operations scripts and GUI under development
5th February 2010 FP7 Prep WP9000Progress Meeting
25
ICS/RTCS Progress: Summary• RTCS interfaced to subsystems at Paris and
Durham• Low-level functionality has been implemented
and is being tested• Scripting interface implemented
– Durham/Paris each have a list of scripts to implement and test
• GUI framework developed– Command set and functionalities identified– GUI running on workstation
5th February 2010 FP7 Prep WP9000Progress Meeting
28
Schedule Progress• Some delayed subsystems:
– RTCS reconstructor box– Telescope simulator– NGS TAS– WPU
• Delays identified early and have not impacted overall schedule– RTCS/ICS testing continued with hardware in test configurations
• SESAME bench• DM testbench in Durham
– Software development continued with dummy systems• Awarded an on-sky date 2 months after initial plan + 1.5 month
allowance for schedule slip– Still have ~ 2 week buffer for hardware (more for software)
5th February 2010 FP7 Prep WP9000Progress Meeting
29
GLOBAL Milestones (And EU funding deliverable due dates) ScheduledPhase A preliminary design, B&C concept design review DONE Jun 2008
Phase A final design review DONE→ FP7 Prep WP9-D15 Conceptual Design Report T0+12 ISSUED
Dec 2008Jan 2009
Phase A purchase and assemble Jun 2009
Phase A AIT prep review (tomographic WFS test bench Paris, closed loop RTC test bench Durham, Simulator UKATC )→ FP7 Prep WP9-D16 Phase A AIT Readiness Review Report T0+24
Sep 2009Jan 2010
Phase A Full system AIT Durham Jan 2010
Phase A - 3 NGS low order system on sky→ FP7 Prep WP9-D16 CANARY Phase A on-sky report
Jul and Sep 2010Jan 2011
Upgrade (Phase B) preliminary design review (+ OPTICON WP2.1 M1)→ FP7 OPTICON WP2.1 CANARY UPGRADE D1 Preliminary Design Report T0+18
Dec 2009June 2010
Upgrade (Phase B) purchase and assemble May 2010
Upgrade (Phase B) integrate with RTC at Durham Oct 2010
Upgrade (Phase B) AIT Durham Jan 2011
Upgrade (Phase B) final design report inc AIT results (+ OPTICON WP2.1 M2)→ FP7 OPTICON WP2.1 CANARY UPGRADE D2 Final Design Report T0+30
Jan 2011June 2011
Upgrade (Phase B) – 4 LGS & 3 NGS low order system on sky (+ OPTICON WP2.1 M3) May & Sep 2011
Upgrade (Phase B) On-Sky Report (+ OPTICON WP2.1 M4)→ FP7 OPTICON WP2.1 CANARY UPGRADE D3 On-sky Report T0+42
Jan 2012June 2012
Phase C preliminary design review Dec 2010
Phase C purchase and assemble Jun 2011
Phase C woofer tweeter integrate with RTC Durham Oct 2011
Phase C AIT Durham Jan 2012
Phase C final design review inc AIT results Jan 2012
Phase C - 4 LGS & 3 NGS high order system on sky May 2012
5th February 2010 FP7 Prep WP9000Progress Meeting
30
30
GLOBAL Milestones (And EU funding deliverable due dates) Scheduled
Phase A preliminary design, B&C concept design review DONE Jun 2008
Phase A final design review DONE→ FP7 Prep WP9-D15 Conceptual Design Report T0+12 ISSUED
Dec 2008Jan 2009
Phase A Purchase and assemble ONGOING Jun 2009
Phase A AIT Prep review: DONE Tomographic WFS test bench - Paris Closed loop RTC test bench - Durham Telescope simulator - UKATC→ FP7 Prep WP9-D16 Phase A AIT Readiness Review Report T0+24
ISSUED
Sep 2009Jan 2010
Phase A Full system AIT Durham ONGOING Jan 2010
Phase A - 3 NGS low order system on sky→ FP7 Prep WP9-D16 CANARY Phase A on-sky report
Jul & Sep 2010
Jan 2011
FP7 Prep Deliverables