30
5 th February 2010 FP7 Prep WP9000 Progress Meeting 1 Update Update Tim Morris Durham University FP7 Prep WP 9340

5 th February 2010 FP7 Prep WP9000 Progress Meeting 1 Update Tim Morris Durham University FP7 Prep WP 9340

  • View
    219

  • Download
    0

Embed Size (px)

Citation preview

5th February 2010 FP7 Prep WP9000Progress Meeting

1

UpdateUpdateTim Morris

Durham University

FP7 PrepWP 9340

5th February 2010 FP7 Prep WP9000Progress Meeting

2

Contents

• Brief CANARY overview– Relationship to EAGLE– CANARY Consortium

• CANARY Status• FP7 Prep Specifics

– Systems Engineering / Key Component Selection

• Status

– Deliverables and Schedule

5th February 2010 FP7 Prep WP9000Progress Meeting

3

CANARY overview

• EAGLE – Phase A instrument concept study for E-ELT– Multi-IFU with LGS/NGS MOAO

• CANARY complements SESAME– Lab demonstrator

• CANARY consortium: LESIA, Durham, ONERA, UKATC, LAM• Location: 4.2m WHT La Palma (Nasmyth platform enclosure)

is the on-sky demonstrator for

Phase On-sky Dates Configuration

A July 2010FDR Dec 08

3 NGS tomo., low-order 52-act DM, truth sensor, near-IR camera, Cn

2 mon.

B Q2 - Q3 2011

FDR Dec 09

Adds 4 Rayleigh LGS + WFS

C Q2 - Q3 2012 Adds High-order 1024-act DM

5th February 2010 FP7 Prep WP9000Progress Meeting

4

CANARY Overview• CANARY is funded by a

combination of French and UK funding, along with FP7 Prep and FP7 OPTICON JRA-1

• Additional funding from:– STFC– INSU– Observatoire de Paris– Durham University

• UK STFC funding for Phase C approved but frozen– Decision expected soon!

• FP7 Prep funding covers systems engineering support and key component selection

Layout of upgraded Nasymth platform at the WHT

5th February 2010 FP7 Prep WP9000Progress Meeting

5

CANARY Status

• Phase A on-sky dates awarded from 21st to 28th July (6 nights)– 2 months later than originally planned

• Principal optomechanical subsystems have been assembled and are undergoing testing

• CANARY instrument control system is being integrated with the hardware

• Full system integration in Durham begins next week

5th February 2010 FP7 Prep WP9000Progress Meeting

6

Key Components:Telescope Simulator

• Passed initial acceptance tests in December 2009

• Minor modifications required to phase screen motors and fibre source clamps

• Modifications completed and system being delivered to Durham next week

• Field lens/Fold mirror assembly also completed– Required for AIT tests with

the Telescope Simulator

Telescope simulator integration (UKATC)

5th February 2010 FP7 Prep WP9000Progress Meeting

7

Key Components:AO Path

• AO path has been aligned– Dummy DM flat mirror used– Avoids DM flattening routine– Allows alignment jig design

• WFE ~55nm RMS– Error budget allowance of

104nm RMS • Throughput

– 60% @ 633nm with DM flat– Expected 69% in V-band with

DM– ADONIS DM to be measured

AO Path aligned with dummy flat DM (Durham)

Flat mirror in place of DM

5th February 2010 FP7 Prep WP9000Progress Meeting

8

Key Components:Low-order DM

• ADONIS DM re-polished– Less than 50nm RMS error

after flattening• 4% open-loop error after

calibration• Tested using SESAME

– Closed-loop SR = 0.39– Open-loop SR = 0.35

• Currently integrated in Durham– DMC testing– Truth Sensor interfaces– NCPA removal

Closed-loop CANARY DM and Truth Sensor testbench (Durham)

5th February 2010 FP7 Prep WP9000Progress Meeting

9

Key Components:NGS WFSs

• 4 x Andor Ixon (E2V 128x128 EMCCD) selected

– 3 x open-loop tomography– 1 x closed-loop

• All cameras have been interfaced to the RTC

– 2 cameras in Paris– 2 cameras in Durham

• Cameras have been integrated with:

– SESAME for open-loop tomography tests (LESIA)

– DM testbench for closed-loop control and interface tests (Durham)

• NGS Pickoff optics aligned (LESIA)– Installed on 2 of 3 cameras

• Truth sensor being integrated with main AO path (Durham)

NGS pickoff and WFS optics before alignment (LESIA)

5th February 2010 FP7 Prep WP9000Progress Meeting

10

Key Components:NGS TAS

• Target Acquisition System assembled

• WFSs to be mounted after SESAME tests completed

• Motion control interface completed– Probe collision detection

software requires development

• Shipping to Durham for AIT mid-March

NGS TAS during assembly (LESIA)

5th February 2010 FP7 Prep WP9000Progress Meeting

11

Key components:WHT Nasmyth Upgrade

• Upgraded GHRIL platform work progressing

• New bench and kinematic mounts installed

• Repositioned walls installed and derotator flange sealed

• Air conditioning units to be installed early March

• Derotator assembly starts after Telescope Simulator delivery (UKATC)

• Provisional derotator installation date of March– Backup date in May

CANARY bench installation within GHRIL (ING)

5th February 2010 FP7 Prep WP9000Progress Meeting

12

AIT Progress: Optomechanics

WHTNasmyth

Telescope Simulator

NGS Pickoffs

3 x NGS WFS

NGS FSM

Low-order DM

Science Verification

Truth Sensor

Figure Sensor

GHRIL Derotator

NGS TAS

AOPath

Focal Plane Calibration

Field Lens Fold Mirror

Science Relay

Acquisition Camera

External Turbulence

Profiler

Green bars show subsystem progress towards final CANARY configuration

~80% complete

5th February 2010 FP7 Prep WP9000Progress Meeting

13

Instrument Control System

5th February 2010 FP7 Prep WP9000Progress Meeting

14

Instrument Control System

5th February 2010 FP7 Prep WP9000Progress Meeting

15

Instrument Control System

5th February 2010 FP7 Prep WP9000Progress Meeting

16

Instrument Control System

5th February 2010 FP7 Prep WP9000Progress Meeting

17

Instrument Control System

5th February 2010 FP7 Prep WP9000Progress Meeting

18

Instrument Control System

5th February 2010 FP7 Prep WP9000Progress Meeting

19

Instrument Control System

5th February 2010 FP7 Prep WP9000Progress Meeting

20

RTCS Progress

4 main components

5th February 2010 FP7 Prep WP9000Progress Meeting

21

RTCS Progress

RECONSTRUCTORSTATUS:Shaktiware has delivered two reconstructor boxesUndergoing final acceptance

5th February 2010 FP7 Prep WP9000Progress Meeting

22

RTCS Progress

WAVEFRONT PROCESSING

UNITS

STATUS:WPUs interfaced to camerasWPUs interfaced to RTCSBeing used on testbenches

5th February 2010 FP7 Prep WP9000Progress Meeting

23

RTCS Progress

DEFORMABLE MIRRORCONTROLLER

STATUS:DMC interfaced to DM and RTCSSoftware interfaces being finalised

5th February 2010 FP7 Prep WP9000Progress Meeting

24

RTCS ProgressCLUSTER AND

CONTROLWORKSTATION(S)

STATUS:Low-level interfaces defined, tested and workingAO operations scripts and GUI under development

5th February 2010 FP7 Prep WP9000Progress Meeting

25

ICS/RTCS Progress: Summary• RTCS interfaced to subsystems at Paris and

Durham• Low-level functionality has been implemented

and is being tested• Scripting interface implemented

– Durham/Paris each have a list of scripts to implement and test

• GUI framework developed– Command set and functionalities identified– GUI running on workstation

5th February 2010 FP7 Prep WP9000Progress Meeting

26

Schedule(1 of 2)

5th February 2010 FP7 Prep WP9000Progress Meeting

27

5th February 2010 FP7 Prep WP9000Progress Meeting

28

Schedule Progress• Some delayed subsystems:

– RTCS reconstructor box– Telescope simulator– NGS TAS– WPU

• Delays identified early and have not impacted overall schedule– RTCS/ICS testing continued with hardware in test configurations

• SESAME bench• DM testbench in Durham

– Software development continued with dummy systems• Awarded an on-sky date 2 months after initial plan + 1.5 month

allowance for schedule slip– Still have ~ 2 week buffer for hardware (more for software)

5th February 2010 FP7 Prep WP9000Progress Meeting

29

GLOBAL Milestones (And EU funding deliverable due dates) ScheduledPhase A preliminary design, B&C concept design review DONE Jun 2008

Phase A final design review DONE→ FP7 Prep WP9-D15 Conceptual Design Report T0+12 ISSUED

Dec 2008Jan 2009

Phase A purchase and assemble Jun 2009

Phase A AIT prep review (tomographic WFS test bench Paris, closed loop RTC test bench Durham, Simulator UKATC )→ FP7 Prep WP9-D16 Phase A AIT Readiness Review Report T0+24

Sep 2009Jan 2010

Phase A Full system AIT Durham Jan 2010

Phase A - 3 NGS low order system on sky→ FP7 Prep WP9-D16 CANARY Phase A on-sky report

Jul and Sep 2010Jan 2011

Upgrade (Phase B) preliminary design review (+ OPTICON WP2.1 M1)→ FP7 OPTICON WP2.1 CANARY UPGRADE D1 Preliminary Design Report T0+18

Dec 2009June 2010

Upgrade (Phase B) purchase and assemble May 2010

Upgrade (Phase B) integrate with RTC at Durham Oct 2010

Upgrade (Phase B) AIT Durham Jan 2011

Upgrade (Phase B) final design report inc AIT results (+ OPTICON WP2.1 M2)→ FP7 OPTICON WP2.1 CANARY UPGRADE D2 Final Design Report T0+30

Jan 2011June 2011

Upgrade (Phase B) – 4 LGS & 3 NGS low order system on sky (+ OPTICON WP2.1 M3) May & Sep 2011

Upgrade (Phase B) On-Sky Report (+ OPTICON WP2.1 M4)→ FP7 OPTICON WP2.1 CANARY UPGRADE D3 On-sky Report T0+42

Jan 2012June 2012

Phase C preliminary design review Dec 2010

Phase C purchase and assemble Jun 2011

Phase C woofer tweeter integrate with RTC Durham Oct 2011

Phase C AIT Durham Jan 2012

Phase C final design review inc AIT results Jan 2012

Phase C - 4 LGS & 3 NGS high order system on sky May 2012

5th February 2010 FP7 Prep WP9000Progress Meeting

30

30

GLOBAL Milestones (And EU funding deliverable due dates) Scheduled

Phase A preliminary design, B&C concept design review DONE Jun 2008

Phase A final design review DONE→ FP7 Prep WP9-D15 Conceptual Design Report T0+12 ISSUED

Dec 2008Jan 2009

Phase A Purchase and assemble ONGOING Jun 2009

Phase A AIT Prep review: DONE Tomographic WFS test bench - Paris Closed loop RTC test bench - Durham Telescope simulator - UKATC→ FP7 Prep WP9-D16 Phase A AIT Readiness Review Report T0+24

ISSUED

Sep 2009Jan 2010

Phase A Full system AIT Durham ONGOING Jan 2010

Phase A - 3 NGS low order system on sky→ FP7 Prep WP9-D16 CANARY Phase A on-sky report

Jul & Sep 2010

Jan 2011

FP7 Prep Deliverables